Refine search Expand filter

Reports

Published

Actions for Volume Eight 2011 Focus on Transport and Ports

Volume Eight 2011 Focus on Transport and Ports

Transport
Industry
Asset valuation
Financial reporting
Fraud
Information technology
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Workforce and capability

The report includes comments on financial audits of government agencies in the Transport and Ports sectors. The audit of corporations’ financial statements for the year ended 30 June 2011 resulted in unmodified audit opinions within the Independent Auditor’s Reports. A key recommendation from the report is that Sydney Ports Corporation should continue working with other government authorities and industry stakeholders to improve the effectiveness of program initiatives for increasing container freight movements by rail. The Corporation should review the underlying causes hindering growth in the rail mode and develop and implement strategies to address the unfavourable trend.

Published

Actions for Volume Three 2011

Volume Three 2011

Whole of Government
Asset valuation
Compliance
Financial reporting
Internal controls and governance
Management and administration
Project management

On 31 October 2011, the Auditor-General, Mr Peter Achterstraat, released Volume Three Report to Parliament on the 2010-11 NSW Total State Sector Accounts. The audited budget surplus was $1,340 million. The Auditor-General issued a qualified independent auditor’s opinion as the State could not identify the full extent and value of its land and infrastructure holdings for the eighth year in a row. The government needs to address its processes for identifying, valuing and recording land and related assets it controls as a matter of priority so it can effectively manage the full extent of its land and infrastructure holdings.

Published

Actions for Government expenditure and transport planning in relation to implementing Barangaroo

Government expenditure and transport planning in relation to implementing Barangaroo

Industry
Treasury
Transport
Compliance
Internal controls and governance
Management and administration
Project management
Service delivery

Barangaroo is an ambitious and significant development on Government-owned Sydney Harbour foreshore. Construction on the 22 hectare CBD site is expected to take 12 years to 2023. Developer contributions to Government of $1 billion are to provide for public domain and other Government development costs, including a six hectare Headland Park. When completed the precinct is to service an anticipated 26,000 workers and residents and up to 33,000 visitors a day. The Auditor-General concluded that while there was extensive transport planning and extensive documentation supporting Government financial forecasts, considerable risks remain for the implementation of the Barangaroo project. 

 

Parliamentary reference - Report number #214 - released 15 June 2011

Published

Actions for Signal failures on the metropolitan rail network

Signal failures on the metropolitan rail network

Transport
Information technology
Infrastructure
Internal controls and governance
Project management
Risk
Service delivery

Between 2004 and 2006, the number of signalling failures, signalling downtime and the number of trains delayed as a result of signal failures all fell. RailCorp’s on-time running performance improved over the same period. The fall in failures is a clear indication of improved performance. Changes in the definition of on-time and to the timetable during 2005 and 2006 however make it difficult to determine whether improvements in response downtime and signalling delays are due to a true performance improvement. To build upon this strong base, RailCorp needs to determine with more confidence the number and duration of signalling failures the network can tolerate without impacting on service levels.

 

Parliamentary reference - Report number #170 - released 15 August 2007

Published

Actions for Connecting with public transport

Connecting with public transport

Transport
Information technology
Infrastructure
Internal controls and governance
Management and administration
Project management
Service delivery
Workforce and capability

We see considerable potential for the Ministry of Transport to plan and manage interchanges more effectively, so as to make better use of our public transport network. We believe that the Ministry now needs to focus more on multi-modal transport planning and interchange performance. It needs to assign responsibility for the coordination and oversight of inter-modal operations to an entity resourced for the purpose. Without this it will continue to be very difficult to identify and address unmet needs, seek and secure stakeholder funding, and monitor and evaluate system performance.

 

Parliamentary reference - Report number #168 - released 6 June 2007

Published

Actions for Fare evasion on public transport

Fare evasion on public transport

Transport
Management and administration
Regulation

The Audit Office is of the opinion that whilst agencies have taken steps to combat fare evasion, the current arrangements are not adequate and improvement is required. A significant number of passengers travel without paying the due fare, resulting in many millions of dollars in revenue foregone. Even when infringed, the majority does not pay the fine. To some extent it would appear to be due to the lack of a provision requiring evaders to produce valid identification.

There is a need for the State Rail Authority and the State Transit Authority to estimate more reliably the extent of fare evasion. Only with more accurate estimates can the most appropriate response to fare evasion be developed.

 

Parliamentary reference - Report number #78 - released 5 December 2000

Published

Actions for A guide to preparing performance information for annuals

A guide to preparing performance information for annuals

Whole of Government
Management and administration

The Audit Office has recently completed a performance audit of the information published in the annual reports of eight public sector agencies. Although there is much guidance material on preparing annual reports, the performance audit found that the quality of published performance information in annual reports often falls short of what is considered best practice.

The aim of this Guide is to assist agencies to prepare annual reports that provide performance information that demonstrates accountability for the expenditure of public monies.

 

Parliamentary reference - Report number #77 - released 29 November 2000

Published

Actions for Judging Performance from Annual Reports: Review of eight agencies' annual reports

Judging Performance from Annual Reports: Review of eight agencies' annual reports

Whole of Government
Management and administration

Agencies have made some notable attempts to nominate objectives and define measures of performance and report against them each year. However, the quality of the performance information varies and in most cases falls short of what is accepted as best practice. The result is diminished accountability, transparency and openness.

Agencies still have problems reporting outcomes and results and frequently regress to reporting activities and plans. Few annual reports discussed setbacks and failures (particularly in the same detail as successes) or compared performance to goals or targets. And none of the agencies benchmarked their achievements against the results of operators in other jurisdictions or the private sector.

 

Parliamentary reference - Report number #76 - released 29 November 2000

Published

Actions for Management of road passenger transport regulation

Management of road passenger transport regulation

Transport
Management and administration
Regulation
Service delivery
Shared services and collaboration

The Audit Office is of the opinion that the Department’s levels of regulatory activity in respect of road passenger transport regulation may have exceeded optimum levels. The Department’s current focus on processing activity limits the Department in achieving all of its desired outcomes. The Audit Office considers that a change in the approach to undertaking and managing road passenger transport regulatory activities would achieve better outcomes for the community and a better use of resources within the Department.

The Audit Office believes that while there is scope to make some improvements from procedural changes, such changes would not be sufficient to generate significant improvements.

 

Parliamentary reference - Report number #75 - released 6 September 2000