Reports
Actions for WestConnex: Assurance to the Government
WestConnex: Assurance to the Government
This audit assesses the assurance provided to the NSW Government for the initial stages of the WestConnex project.
The audit examined the WestConnex project from concept development to the pre-tender phase for Stage 1A – M4 (Parramatta to Homebush Bay). It did not examine the merit of the project or whether it represented value-for-money.
This audit found a number of shortcomings with the governance of the WestConnex project during its early stages and makes recommendations on how to better govern the remainder of the project to minimise the risk of failure.
Parliamentary reference - Report number #247 - released 18 December 2014
Actions for Volume Seven 2014 Focusing on Transport
Volume Seven 2014 Focusing on Transport
All agencies in transport cluster received unqualified audit opinions for the year ended 30 June 2014. The quality of financial reporting continues to improve with the number of misstatements identified during audits falling for the fifth year in a row.
Actions for Volume Four 2014 focusing on New South Wales State Finances
Volume Four 2014 focusing on New South Wales State Finances
For the second consecutive year, the General Government and Total State Sector Accounts received an unqualified auditor’s opinion following more than a decade of qualifications. The quality and timeliness of financial reporting across the NSW public sector has continued to improve. Compared to previous years, there were fewer errors in agencies’ 2013–14 financial statements submitted for audit and used for whole-of-government financial reporting.
Actions for Making the Most of Government Purchasing Power - Telecommunications
Making the Most of Government Purchasing Power - Telecommunications
The Auditor-General has found that agencies have consistently failed to negotiate the best price for their telecommunication contracts and are not getting value for money because of inadequate contract and expense management processes.
The audit examined six agencies to assess whether the government was getting value for money from its telecommunications contracts. It again raised problems with the way NSW government agencies manage contracts.
Parliamentary reference - Report number #244 - released 26 June 2014
Actions for Volume One 2014 - Areas of focus from 2013
Volume One 2014 - Areas of focus from 2013
Today the Auditor-General of New South Wales, Grant Hehir, released his Volume One Report to Parliament for 2014. The observations included in this report are designed to inform readers of common findings from the 2013 financial and performance audits so agencies and audit committees can use them to identify issues that may be relevant to their organisations.
Actions for Volume Nine 2010 focus on Transport, Planning and Industry
Volume Nine 2010 focus on Transport, Planning and Industry
The report includes comments on his financial audits of NSW Government transport, planning and industry agencies for 2009-10. A key recommendation from the report is that the New South Wales Government identify lessons learnt from the metro experience and ensure that future decision processes are developed to ensure the State never again expends such a large amount of scarce transport funding dollars and valuable time on a project that does not proceed.
Actions for Volume Three 2010 focus on Total State Sector
Volume Three 2010 focus on Total State Sector
The final Budget result for 2009-10 was a surplus of $994 million, originally budgeted to be a $990 million deficit. If the Commonwealth Government’s capital stimulus funding had been excluded, the result would have been a deficit of $861 million. Employee costs (excluding superannuation costs) increased by approximately 3.5 per cent compared to 7.5 per cent in the prior year.
“I have issued a qualified Independent Auditor’s Report as the State has not recognised the value of Crown Reserves and the infrastructure on those reserves that should be recorded as an asset,” Mr Achterstraat said.
Actions for Improving the Performance of Metropolitan Bus Services
Improving the Performance of Metropolitan Bus Services
The 2004 Review of Bus Services in NSW always envisaged that there would be a transition period as the new bus contracts were introduced. NSWTI has developed and implemented the new arrangements, and pursued a range of new initiatives including the network improvement program, strategic corridors and uniform bus fares and concessions. The new contracts provided for a performance management regime to hold operators accountable. But this is still being developed four years after the bus contracts came into effect and it remains unproven as a basis for ensuring value for money from the contracts - each of which guarantees monopoly rights to the operators.
Parliamentary reference - Report number #198 - released 10 March 2010
Actions for Condition of State Roads
Condition of State Roads
The Roads and Traffic Authority (RTA) has improved the overall surface condition of State Roads in the last decade. Country road surfaces are now generally much better. Ride quality has improved and cracking has been reduced. The RTA has also achieved a substantial reduction in the number of structurally deficient bridges over the same period.
Despite a significant increase in the State’s contribution to maintenance since 1999-2000, the RTA has deferred road rebuilding projects. The RTA is rebuilding at less than half its long term target, and has not met this target at any time this decade. The RTA has not identified how it will address deferred rebuilding, although it advises it is developing a new road network management plan which will address this.
Parliamentary reference - Report number #157 - released 16 August 2006
Actions for The Cross City Tunnel Project
The Cross City Tunnel Project
In our opinion the Government’s ‘no net cost to government’ requirement was a legitimate (but not the only possible) basis for the tunnel bid process. The Government was entitled to decide that tunnel users meet the tunnel costs. Structuring the bid process on the basis of an upfront reimbursement of costs incurred (or to be incurred) by the Roads and Traffic Authority (RTA) was therefore appropriate.
In our opinion, however, the Government, Treasury and the RTA did not sufficiently consider the implications of an upfront payment involving more than simple project cost reimbursement (i.e. the ‘Business Consideration Fee’ component). In addition, the RTA was wrong to change the toll escalation factor late in 2002 to compensate the tunnel operator, Cross City Motorway Pty Ltd, for additional costs.
Parliamentary reference - Report number #152 - released 31 May 2006