Reports
Actions for Volume Eight 2012 focusing on Transport and Ports
Volume Eight 2012 focusing on Transport and Ports
We issued unqualified audit opinions on the transport entities’ 30 June 2012 financial statements.
Some of the findings of the report include:
-
government funding to the public transport operators totalled $4.4 billion in 2011-12 ($3.7 billion in 2010-11)
-
passenger services revenue only covered 20 per cent of RailCorp's operating costs
-
Transport for NSW has formalised a protocol to mitigate the risk of potential conflicts of interests
-
At present, no sustainability framework exists for the transport agencies around environment and sustainability. Transport for NSW should complete its Environment and Sustainability Policy Framework by June 2013 and should publicly report its results annually
-
Transport patronage continued to grow with 510 million journeys on train, bus and ferry services
-
CityRail had two peak hour periods where only 36 per cent and 39 per cent of services were on time
-
On-time running performance for Sydney Ferries was above the NSW 2021 plan target of 98.5 per cent for most routes in 2011-12
-
Customer surveys by transport agencies no longer specifically address crowding on public transport. Transport for NSW should observe and report on crowding on all transport modes
-
Over 2,500 transport staff, or 8.3 per cent of the workforce, have excessive leave balances. All transport entities should do more to reduce excessive annual leave balances to ensure they will comply with new targets set by the Premier.
Actions for Volume Three 2012 focusing on New South Wales State Finances
Volume Three 2012 focusing on New South Wales State Finances
A qualified audit opinion was issued on the Total State Sector Accounts for the year ended 30 June 2012. Qualified opinions have been issued every year for the past decade. The key issue contributing to past qualifications has been partially resolved, but new issues have arisen that impact the ability to confirm property, plant and equipment balances in 2011-12.
Actions for Managing Overtime: RailCorp and Roads and Maritime Services
Managing Overtime: RailCorp and Roads and Maritime Services
Overtime is a significant cost for RailCorp and Roads and Maritime Services, adding about ten per cent to the cost of regular salaries. RailCorp’s overtime cost was $133.7 million in 2010–11, and at Roads and Maritime Services it cost $49.3 million.
Parliamentary reference - Report number #223 - released 20 June 2012
Actions for Handback of the M4 Tollway
Handback of the M4 Tollway
This audit focuses on the M4 handback. It looks at whether the road will be in good condition when the State gets it back, and whether it will cope with the extra traffic after the toll is removed. These are critical issues for taxpayers and motorists. Taxpayers don’t want to be responsible for a large repair bill and motorists don’t want to be stuck in traffic jams.
To ensure that future private sector partnerships (PPP) deal adequately with handback, we recommend that the Roads and Traffic Authority (RTA):
- ensure deeds spell out an appropriate inspection and testing program to determine repairs required to bring roads up to a satisfactory condition at handback (p.11)
- ensure deeds link condition standards and maintenance approaches to changing industry standards and approaches over the life of the PPP (p.11)
- consider including in deeds a requirement that operators provide a performance bond or similar security over the cost of handback repairs (p.11)
- review the lessons learnt from the M4 tollway handback and determine whether it should seek to negotiate changes to existing tollway deeds to better deal with handback, by June 2010 (p.11)
Parliamentary reference - Report number #193 - released 27 October 2009
Actions for Managing Disruptions to Cityrail Passenger Services
Managing Disruptions to Cityrail Passenger Services
About one in every twelve Sydney people travels by train each weekday.
Unplanned disruptions to services are inevitable, even on the best-run railways.
Because of the complexities of Sydney’s rail network, a single event can disrupt many services.
From a passenger’s perspective, three issues are important –
- how quickly the disruption is fixed (“When will my train arrive?”)
- the accuracy of information provided about the disruption (“Should I change my travel/meeting/other arrangements?”)
- how often the disruptions occur (“Should I give up on rail travel?”).
In this audit, we looked at how well RailCorp responds when there are routine disruptions to its CityRail passenger services. We focused on how RailCorp manages passenger journeys and informs passengers.
This report informs Parliament and the community about the limitations of the current system, and what more needs to be done in order to minimise the impact of disruptions on passengers.
It should also help passengers judge the extent to which they can rely on the information they receive, and to better understand some of the obstacles faced by staff.
Parliamentary reference - Report number #139 - released 22 June 2005
Actions for Follow-up of Performance Audit: Bus Maintenance and Bus Contracts
Follow-up of Performance Audit: Bus Maintenance and Bus Contracts
Periodically we review the extent to which agencies have implemented the recommendations they accepted from our earlier audits.
This gives Parliament and the public an update on the extent of progress made.
In this follow-up audit, we examine changes following our May 2002 report on how well the:
- State Transit Authority maintained its buses
- Ministry of Transport administered contracts for the provision of regular passenger bus services.
Parliamentary reference - Report number #138 - released 14 June 2005