Refine search Expand filter

Reports

Published

Actions for Volume Eight 2012 focusing on Transport and Ports

Volume Eight 2012 focusing on Transport and Ports

Transport
Industry
Compliance
Financial reporting
Fraud
Information technology
Infrastructure
Management and administration
Procurement
Project management
Regulation
Risk
Workforce and capability

We issued unqualified audit opinions on the transport entities’ 30 June 2012 financial statements.

Some of the findings of the report include:

  • government funding to the public transport operators totalled $4.4 billion in 2011-12 ($3.7 billion in 2010-11)

  • passenger services revenue only covered 20 per cent of RailCorp's operating costs

  • Transport for NSW has formalised a protocol to mitigate the risk of potential conflicts of interests

  • At present, no sustainability framework exists for the transport agencies around environment and sustainability. Transport for NSW should complete its Environment and Sustainability Policy Framework by June 2013 and should publicly report its results annually

  • Transport patronage continued to grow with 510 million journeys on train, bus and ferry services

  • CityRail had two peak hour periods where only 36 per cent and 39 per cent of services were on time

  • On-time running performance for Sydney Ferries was above the NSW 2021 plan target of 98.5 per cent for most routes in 2011-12

  • Customer surveys by transport agencies no longer specifically address crowding on public transport. Transport for NSW should observe and report on crowding on all transport modes

  • Over 2,500 transport staff, or 8.3 per cent of the workforce, have excessive leave balances. All transport entities should do more to reduce excessive annual leave balances to ensure they will comply with new targets set by the Premier.

 

Published

Actions for Volume Three 2012 focusing on New South Wales State Finances

Volume Three 2012 focusing on New South Wales State Finances

Whole of Government
Asset valuation
Compliance
Financial reporting
Internal controls and governance
Management and administration
Project management

A qualified audit opinion was issued on the Total State Sector Accounts for the year ended 30 June 2012. Qualified opinions have been issued every year for the past decade. The key issue contributing to past qualifications has been partially resolved, but new issues have arisen that impact the ability to confirm property, plant and equipment balances in 2011-12.

Published

Actions for Liverpool to Parramatta Bus Transitway

Liverpool to Parramatta Bus Transitway

Transport
Treasury
Infrastructure
Management and administration
Project management
Service delivery

Several of my recent audits have identified a need to improve our public transport system – both for the benefit of travellers and to assist in achieving better air quality.

Bus Transitways can provide a good public transport solution for lower density population areas, potentially at a relatively low capital cost. This audit examines the transitway running between Liverpool and Parramatta, the first of several planned for Sydney. This audit should contribute to a better understanding of the lessons learnt from this first project, and so to future transitways providing better value for money.

But this audit also raises broader issues.

It highlights the importance of accurately projecting the total cost of major infrastructure projects before governments lock in their decisions. It also highlights the need for sound decision-making processes when government agencies compete with the private sector. The principles and recommendations flowing from these issues are ones I would draw to the attention of all agencies, and to the Government.

 

Parliamentary reference - Report number #146 - released 5 December 2005

Published

Actions for Managing Disruptions to Cityrail Passenger Services

Managing Disruptions to Cityrail Passenger Services

Transport
Management and administration
Service delivery
Workforce and capability

About one in every twelve Sydney people travels by train each weekday.

Unplanned disruptions to services are inevitable, even on the best-run railways.

Because of the complexities of Sydney’s rail network, a single event can disrupt many services.

From a passenger’s perspective, three issues are important –

  • how quickly the disruption is fixed (“When will my train arrive?”)
  • the accuracy of information provided about the disruption (“Should I change my travel/meeting/other arrangements?”)
  • how often the disruptions occur (“Should I give up on rail travel?”).

In this audit, we looked at how well RailCorp responds when there are routine disruptions to its CityRail passenger services. We focused on how RailCorp manages passenger journeys and informs passengers.

This report informs Parliament and the community about the limitations of the current system, and what more needs to be done in order to minimise the impact of disruptions on passengers.

It should also help passengers judge the extent to which they can rely on the information they receive, and to better understand some of the obstacles faced by staff.

 

Parliamentary reference - Report number #139 - released 22 June 2005

Published

Actions for Follow-up of Performance Audit: Bus Maintenance and Bus Contracts

Follow-up of Performance Audit: Bus Maintenance and Bus Contracts

Transport
Asset valuation
Compliance
Financial reporting
Infrastructure
Management and administration
Procurement
Project management
Service delivery
Workforce and capability

Periodically we review the extent to which agencies have implemented the recommendations they accepted from our earlier audits.

This gives Parliament and the public an update on the extent of progress made.

In this follow-up audit, we examine changes following our May 2002 report on how well the:

  • State Transit Authority maintained its buses
  • Ministry of Transport administered contracts for the provision of regular passenger bus services.

 

Parliamentary reference - Report number #138 - released 14 June 2005

Published

Actions for Outsourcing Information Technology

Outsourcing Information Technology

Whole of Government
Information technology
Management and administration
Procurement

Agencies have managed the planning of outsourcing in a competent way. All agencies satisfactorily managed the contractual aspects of outsourcing. The Audit Office is of the opinion, however, that there is no objective evidence to demonstrate that agencies have achieved their goals in outsourcing IT. Most agencies had identified the current and expected costs and risks of outsourcing. Agencies were not able to demonstrate that the actual costs of outsourcing matched the expected costs.

 

Parliamentary reference - Report number #103 - released 23 October 2002

Published

Actions for User-Friendliness of Websites

User-Friendliness of Websites

Whole of Government
Information technology
Service delivery

Of the sites examined, users would find that some offered a pleasant and productive experience. Using others would be onerous and frustrating. Some users would not be able in practice to access features on some sites. All sites, even the best, had aspects warranting better attention to users’ needs. The failure of some sites to provide important information about privacy, security and legal matters was of particular concern. For the sites evaluated there was little use of the web to foster two-way communication between the public and agencies on issues of concern or as part of the policy process. And it seems that consultation with users on site design is not always sufficiently undertaken. A website is more likely to be user-friendly if design is based on thorough consultation with users.

 

Parliamentary reference - Report number #99 - released 26 June 2002

Published

Actions for Bus Maintenance and Bus Contracts

Bus Maintenance and Bus Contracts

Transport
Management and administration
Procurement
Service delivery

State Transit has developed fleet management plans and maintenance standards that meet its regulatory and contractual obligations as a bus operator and are consistent with vehicle manufacturers’ standards and best practice. However, assumptions used in fleet management plans to forecast fleet growth may not result in the most efficient and effective outcome for State Transit. Forecasts fail to take account of opportunities to redesign or reduce services where they exceed contract requirements and are difficult to justify on a commercial basis. Of greater concern are the consequences arising from bus maintenance practices not meeting State Transit’s own standards.

 

Parliamentary reference - Report number #97 - released 29 May 2002

Published

Actions for Management of road passenger transport regulation

Management of road passenger transport regulation

Transport
Management and administration
Regulation
Service delivery
Shared services and collaboration

The Audit Office is of the opinion that the Department’s levels of regulatory activity in respect of road passenger transport regulation may have exceeded optimum levels. The Department’s current focus on processing activity limits the Department in achieving all of its desired outcomes. The Audit Office considers that a change in the approach to undertaking and managing road passenger transport regulatory activities would achieve better outcomes for the community and a better use of resources within the Department.

The Audit Office believes that while there is scope to make some improvements from procedural changes, such changes would not be sufficient to generate significant improvements.

 

Parliamentary reference - Report number #75 - released 6 September 2000