Refine search Expand filter

Reports

Published

Actions for Driver vehicle system

Driver vehicle system

Transport
Finance
Cyber security
Information technology
Internal controls and governance
Project management
Service delivery

What this report is about

Transport for NSW (TfNSW) uses the Driver vehicle System (DRIVES) to support its regulatory functions. The system covers over 6.2 million driver licences and over seven million vehicle registrations.

DRIVES first went live in 1991 and has been significantly extended and updated since, though is still based around the same core system. The system is at end of life but has become an important service for Service NSW and the NSW Police Force.

DRIVES now includes some services to other parts of government and non-government entities which have little or no connection to transport. There are 141 users of DRIVES in total, including commercial insurers, national regulators, and individual citizens.

This audit assessed whether TfNSW is effectively managing DRIVES and planning to transition it to a modernised system.

Audit findings

TfNSW has not effectively planned the replacement of DRIVES.

It is now working on its third business case for a replacement system but has failed to learn lessons from its past attempts.

In the meantime, TfNSW has not taken a strategic approach to managing DRIVES’ growth.

TfNSW has been slow to reduce the risk of misuse of personal information held in DRIVES. With its delivery partner Service NSW, TfNSW has also been slow to develop and implement automatic monitoring of access.

TfNSW uses recognised processes for managing most aspects of DRIVES, but has not kept the system consistently available for users. TfNSW has lacked accurate service availability information since June 2022, when it changed its technology support provider.

TfNSW needs to significantly prioritise cyber security improvements to DRIVES. TfNSW is seeking to lift DRIVES’ cyber defences, but it will not achieve its stated target safeguard level until December 2025.

Even then, one of the target safeguards will not be achieved in full until DRIVES is modernised.

Audit recommendations

TfNSW should:

  • implement a service management framework including insight into the views of DRIVES users, and ensuring users can influence the service
  • ensure it can accurately and cost effectively calculate when DRIVES is unavailable due to unplanned downtime
  • ensure implementation of a capability to automatically detect anomalous patterns of access to DRIVES
  • ensure that DRIVES has appropriate cyber security and resilience safeguards in place as a matter of priority
  • develop a clear statement of the future role in whole of government service delivery for the system
  • resolve key issues currently faced by the DRIVES replacement program including by:
    • clearly setting out a strategy and design for the replacement
    • preparing a specific business case for replacement.

Read the PDF report

Parliamentary reference - Report number #388 - released 20 February 2024

Published

Actions for Regional road safety

Regional road safety

Transport
Health
Community Services
Internal controls and governance
Management and administration
Project management
Risk

What this report is about

Around one-third of the state’s population lives in regional NSW, but deaths on regional roads make up around two-thirds of the state’s road toll.

Transport for NSW (TfNSW) is responsible for managing road safety outcomes across the NSW road network. This audit assessed the effectiveness of TfNSW’s delivery of road safety strategies, plans and policies in regional areas.

The NSW Road Safety Action Plan 2022–2026 has the stated goal of ‘no death or serious injury occurring on the road transport network’ by 2050.

What we found

There is a disproportionate amount of trauma on regional roads, but there are no specific road safety plans or trauma reduction targets for regional NSW.

TfNSW advises that the setting of state-wide road safety targets is consistent with other jurisdictions and international best practice. However, the proportion of road fatalities and serious injuries in regional NSW is almost the same as ten years ago.

There is no regional implementation plan to assist TfNSW to target the Road Safety Action Plan 2026 to regional areas.

TfNSW considers that local road safety outcomes should be managed by councils, but only 52% of regional councils participated in its Local Government Road Safety Program (LGRSP) in 2022–23. This program has not been updated since 2014, despite commitments to do so in 2021 and 2022.

TfNSW has not undertaken a systematic and integrated analysis of the combined impact of its road safety strategies and plans in regional NSW since 2012.

TfNSW reports against the Community Road Safety Fund (CRSF) annually but there is no consolidated, public reporting on total road safety funding allocated to regional NSW. The Fund underspend increased from 12% in 2019–20 to 20% in 2022–23.

What we recommended

We recommended TfNSW:

  • develop a regional implementation plan to support the NSW Road Safety Action Plan, including a framework to annually measure, analyse and publicly report on progress
  • develop a plan to measure and mitigate risks causing underspend in the CRSF
  • expedite the review of the LGRSP including recommendations to increase involvement of regional councils.

Disclosure of confidential information

Under the Government Sector Audit Act 1983 (the Act), the Auditor-General may disclose confidential information if, in the Auditor-General’s opinion, the disclosure is in the public interest, and that disclosure is necessary for the exercise of the Auditor-General’s functions.

Confidential information in the Act means Cabinet information or information subject to legal privilege. This performance audit report contained confidential information.

The NSW Premier has certified that in his opinion the disclosure of the confidential information was not in the public interest.

The confidential information has been redacted from this report.

Under section 36A(2) of the Government Sector Audit Act 1983, the Auditor-General may authorise the disclosure of confidential information if, in the Auditor-General’s opinion, the disclosure is in the public interest and necessary for the exercise of the Auditor-General’s functions. Confidential information under the Government Sector Audit Act 1983 means Cabinet information, or information that could be subject to a claim of privilege by the State or a public official in a court of law. This performance audit report contained confidential information which, in the opinion of the Auditor-General, is in the public interest to disclose and that disclosure is necessary for the exercise of the Auditor-General’s functions.

On 26 October 2023, pursuant to section 36A(2)(b) of the Government Sector Audit Act 1983, the Auditor-General notified the NSW Premier of the intention to include this information in the published report, having formed the opinion that its disclosure is in the public interest and is necessary for the exercise of the Auditor-General’s functions.

On 23 November 2023, pursuant to section 36A(2)(c) of the Government Sector Audit Act 1983, the NSW Premier certified that, in his opinion, the proposed disclosure of the confidential information contained in this report was not in the public interest. The Premier’s certificate follows. Section 36A(4) states that a certificate of the Premier that it is not in the public interest to disclose confidential information is conclusive evidence of that fact.

The issuance of the certificate by the NSW Premier prevents the publication of this information. The relevant sections of the report containing confidential information have been redacted.

One-third of the New South Wales population resides in regional areas, but two-thirds of the state’s road crash fatalities take place on regional roads.

Between 2017 and 2021, the average number of fatalities for every 100,000 of the population living in regional New South Wales was 8.33 — approximately four times higher than the equivalent measure for Greater Sydney. Similarly, the average number of serious injuries in regional New South Wales over the same period was 75.24 per 100,000 of the population, compared with 50.53 in Greater Sydney. Further, more than 70% of people who lose their lives in accidents on regional roads are residents of regional areas.

Residents of regional areas face particular transport challenges. They often need to travel longer distances for work, health care, or recreation purposes, yet their public transport options are more limited than metropolitan residents. Vehicle safety is also an issue. According to the NSW Road Safety Progress Report 2021, of the light vehicles registered in New South Wales that were manufactured in or after 2000, 48.4% of light vehicles in regional areas had a five-star Australasian New Car Assessment Program (ANCAP) rating, compared to 54.8% in metropolitan areas. Road conditions in regional areas can also be more challenging for drivers.

Regional New South Wales covers 98.5% of the total area of the state. The road network in New South Wales is vast — spanning approximately 200,000 kilometres.

The road network includes major highways, state roads and local roads. Speed limits range from 10 km/hr in high pedestrian shared zones, up to 110 km/hr on high volume and critical road corridors. Eighty per cent of the network has a 100 km/h speed limit, which is mostly applied as a default speed limit, regardless of the presence of safety features and treatments.

Speed is the primary causal factor in more crashes in New South Wales than any other factor, and car crashes in regional areas are more likely to be fatal because of the higher average speeds involved.

The responsibility for managing road safety outcomes across the entire New South Wales road network lies with Transport for NSW (TfNSW), pursuant to Schedule 1 of the Transport Administration Act 1988.

While its safety responsibilities are state-wide, TfNSW does not own or directly manage all of the road network in regional New South Wales, which spans approximately 200,000 kilometres. Approximately 80% of the roads are classified as Local Roads and are administered and managed by local councils. Local councils also maintain Regional Roads that run through their local government areas. TfNSW is responsible for managing State Roads (approximately 20% of roads), which are major arterial roads. It also provides funding for councils to manage over 18,000 km (approximately 10%) of state-significant Regional Roads.

According to TfNSW, between 2016 and 2020, there were 9,776 people killed or seriously injured on roads in regional New South Wales. Adding to the tragic loss of life, according to TfNSW, the estimated cost to the community between 2016 and 2020 resulting from regional road trauma and fatalities was around $13.7 billion.

TfNSW also noted that the ‘risk of road trauma is pervasive, and a combination of effective road safety measures is required to systematically reduce this risk’.

TfNSW released its first long-term road-safety strategy in December 2012, which introduced the goal of ‘Vision Zero’ — a long-term goal of zero deaths or serious injuries on NSW roads. The terminology was changed to ‘Towards Zero’ in the 2021 Road Safety Plan and has been retained in the NSW Road Safety Action Plan 2022–2026. Towards Zero has the stated goal of ‘no death or serious injury occurring on the road transport network’ by 2050.

The objective of this audit is to assess the effectiveness of TfNSW’s delivery of ‘Towards Zero’ in regional areas.

In making this assessment, the audit examined whether TfNSW:

  • is effectively reducing the number of fatalities and serious injuries on regional roads
  • has an effective framework, including governance arrangements, for designing and refreshing the NSW Road Safety Strategy 2012–2021 and the NSW Road Safety Action Plan 2022–2026
  • effectively makes use of whole-of-government and other relevant sources of data to support decision-making, and to evaluate progress and outcomes
  • effectively manages accountabilities, including roles and responsibilities, with respect to road safety outcomes and the use of data.

This audit focused on the policies and strategies used by TfNSW for managing road safety outcomes in regional areas. We did not evaluate individual road safety projects, programs and initiatives as part of this audit.

Whilst Regional Roads and Local Roads (as defined by the Road Network Classifications) are owned and maintained by local councils, we included these roads in this audit as TfNSW may advise and assist councils to promote and improve road safety, as well as manage grant programs that focus on improving road safety outcomes on these roads. Hereafter, unless otherwise stated, references to ‘regional roads’ refer to all classifications of roads in the state which are in regional New South Wales, irrespective of their ownership.

Local councils in regional areas are key stakeholders for the purposes of this audit, and we interviewed eight as part of the audit process (noting that this was not intended to be a representative sample). Road asset management by local councils is also out of scope for this audit as it is the focus of a subsequent performance audit by the Audit Office of New South Wales.b

The Audit Office of New South Wales has undertaken several performance audits relating to road safety since 2009 and these have been referenced while undertaking this audit. They include:

  • Condition of State Roads (August 2006)
  • Improving Road Safety: Heavy Vehicles (May 2009)
  • Improving Road Safety: School Zones (March 2010)
  • Improving Road Safety: Speed Cameras (July 2011)
  • Regional Assistance Programs (May 2018)
  • Mobile speed cameras (October 2018)
  • Rail freight and Greater Sydney (October 2021).

Conclusion

TfNSW has acknowledged that there is a disproportionate amount of road trauma on regional roads in the NSW Road Safety Strategy 2012–2021, the NSW Road Safety Plan 2021, and the NSW Road Safety Action Plan 2022–2026. However, TfNSW has not articulated or evaluated a strategy for implementing road safety policy in regional New South Wales to assist in guiding targeted activities to address regional road trauma. There is also no transparency about the total amount of funding invested in improving road safety outcomes for regional New South Wales.

People living in regional New South Wales make up one-third of the state’s population, but deaths on regional roads make up around two-thirds of the state’s total road toll. This statistic is almost the same in 2023 as it was ten years ago when TfNSW released its first long-term road safety strategy.

More than 70% of people who died on roads between 2012 and 2022 in regional New South Wales were residents of regional areas. Speed is the greatest contributing factor to road fatalities and serious injuries across the entire state. However, it is responsible for more fatalities on regional roads (43%) than in Greater Sydney (34%).

TfNSW’s road safety strategies and plans acknowledge that most road fatalities occur in regional New South Wales but none of its existing strategies or plans show evidence of tailoring measures to suit particular regional settings or ‘hot spots’. There are infrastructure initiatives (such as Saving Lives on Country Roads) and behavioural programs targeting regional areas (such as Driver Reviver). However, these activities are not aligned to a regional-specific strategy or plan that addresses issues specific to regional areas.

TfNSW has state-wide responsibility for managing road safety outcomes. TfNSW advised the audit that a regional plan and regional trauma reduction targets are not needed as the state-wide plan and targets apply equally for all areas of New South Wales, and local road safety factors are best managed by local councils. TfNSW partners with local councils. However, only 52% of councils in regional New South Wales participate in TfNSW’s Local Government Road Safety Program, compared to 84% of councils in metropolitan areas. TfNSW has not undertaken any evaluations to determine whether projects completed under the Local Government Road Safety Program have reduced road trauma at the local level.

Notwithstanding the above points, TfNSW works with local councils (who are road authorities for local roads in their respective areas under the Roads Act 1993) and other key stakeholders such as the NSW Police Force to achieve the NSW Government’s road safety policy objectives.

TfNSW advised that ‘the setting of state-wide road safety targets is consistent with other jurisdictions and international best practice. Importantly, delivery of road safety countermeasures is tailored and applied with a focus on road user groups across all geographic locations to maximise trauma reductions’. There may be legitimate reasons for the existing approach, as articulated by TfNSW. However, the proportion of road fatalities in regional New South Wales roads has not reduced since 2012 – despite a long-term reduction in the overall number of deaths on the state’s roads between 2012–2021. The audit report has recommended that a regionally focused implementation plan could address this issue. TfNSW has accepted this report’s recommendation that such a plan be developed.

Specific road safety initiatives targeted to regional areas have not been implemented or expanded

Text removed pursuant to section 36A of the Government Sector Audit Act 1983 (NSW), in compliance with the issuance of a Premier’s certificate preventing the publication of this information.

TfNSW increased the use of other forms of automated enforcement (such as tripling enforcement hours in mobile speed cameras).
However, the use of automated enforcement has a strong metropolitan focus with most red light and fixed speed cameras being in metropolitan areas. Average speed cameras are the only camera type overwhelmingly located in regional areas but these apply only to heavy vehicles and are positioned on major freight routes. 

There is no consolidated, public reporting of what proportion of total road safety funding is directed to regional New South Wales each year. The main source of funding for road safety in New South Wales, the Community Road Safety Fund, has been underspent since 2019.

Fines from camera-detected speeding, red-light and mobile phone use offences are required to be used solely for road safety purposes through the Community Road Safety Fund (CRSF), as set out in the Transport Administration Amendment (Community Road Safety Fund) Act 2012.

The CRSF has been underspent every year since 2019–20. The underspend has increased from 12% in 2019–20 to 20% in 2022–23 where the full year underspend was forecasted to be $104 million. Of this underspend, $13.5 million was dedicated for regional road infrastructure projects. TfNSW advised the audit that much of the underspend is the result of delays to infrastructure projects due to COVID-19, bushfires, and floods, as well as skills shortages. However, TfNSW has not provided any evidence that it had a plan to mitigate these risks – meaning the level of underspend could continue to grow. TfNSW also advised ‘there is no reason to expect budget management and controls will not return to pre-COVID circumstances’.

In total, TfNSW received $700 million in funding for road safety in 2021–22 (including federal contributions and the Community Road Safety Fund). Of this, $411 million (or ~59%) was directed to regional New South Wales. This is the most recent comprehensive financial data that was provided by TfNSW to the audit team. The 2022–23 NSW Budget allocated $880 million for road safety in 2022–23, with a forecasted total allocation for road safety of $1.6 billion in recurrent expenses and $0.8 billion in capital expenditure over the period 2022–23 to 2025–26.

Appendix one – Response from Transport for NSW

Appendix two – The Safe Systems framework and NSW road safety strategies and plans

Appendix three – About the audit

Appendix four – Performance auditing

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #386 - released 30 November 2023

Published

Actions for Government's acquisition of private property: Sydney Metro project

Government's acquisition of private property: Sydney Metro project

Transport
Planning
Whole of Government
Compliance
Infrastructure
Internal controls and governance
Project management
Risk

What the report is about

Sydney Metro is Australia’s largest public transport project. It requires the acquisition of many private properties, including residential and business properties.

This audit assessed the effectiveness of the acquisition of private properties for the Sydney Metro project. The audited agencies were Sydney Metro, the Department of Planning and Environment (Valuer General NSW) and Transport for NSW (the Centre for Property Acquisition).

The audit assessed agencies against the framework for property acquisitions in New South Wales. It did not re-perform the valuations done for individual properties that were acquired by Sydney Metro.

What we found

Acquisitions of private property for the Sydney Metro project were mostly effective in the sample of acquisitions we assessed. We found Sydney Metro:

  • complied with legislative and policy requirements for compensation and communication with people subject to property acquisitions
  • kept accurate records of its acquisitions and applied probity controls consistently
  • did not complete detailed plans or negotiation strategies for the high-risk and high-value acquisitions we reviewed
  • did not comply with legislative timelines for most compulsory acquisitions because of delays in receiving the required information from the Valuer General in these cases.

The Centre for Property Acquisition has overseen the implementation of reforms to residential acquisition processes, but its assessment of the effectiveness of these reforms has not been comprehensive.

What we recommended

The audit made four recommendations to the audited agencies to improve:

  • plans and strategies for the acquisition of high-risk and high-value properties
  • timeliness of issuing compensation determinations for compulsory acquisitions
  • data quality on the experience of people subject to property acquisitions.

The NSW Government has the power to acquire land that is owned or leased by individuals or businesses, if it is needed for a public purpose. The power arises from the Land Acquisition (Just Terms Compensation) Act 1991 (the Just Terms Act). Government agencies that have the power to compulsorily acquire private property are referred to as ‘acquiring authorities’. People who are subject to acquisitions are referred to as ‘affected parties’ and include property owners (business or residential), businesses with a commercial lease on a property, or individuals with residential tenancy leases. In recent years, the vast majority of acquisitions by the NSW Government have been for public transport or road projects.

Sydney Metro is a NSW Government agency with responsibility for building the Sydney Metro railway project. Sydney Metro is Australia’s largest public transport project. The project requires the acquisition of a large number of private properties. Sydney Metro has been one of the largest acquirers of private property in recent years, completing over 500 acquisitions between 2020 and mid-2022, with a total acquisition value of over $2 billion. Other agencies and statutory officers involved in the acquisition of property for the Sydney Metro project include:

  • the Department of Planning and Environment (DPE), which supports the minister responsible for the Just Terms Act. DPE also provides staff to the Valuer General of NSW
  • the Valuer General of NSW, an independent statutory officer that determines compensation in cases where the acquiring authority and the affected party cannot agree on compensation for property that has been acquired
  • Transport for NSW, which includes the Centre for Property Acquisition (CPA). The CPA does not have a direct role in acquiring properties, but its responsibilities include developing guidance for acquiring agencies and monitoring and reporting on their activities.

About this audit

The objective of this audit was to assess the effectiveness of acquisitions of private properties for Sydney Metro projects. The audit assessed agencies against the legislative and policy requirements in place for government acquisitions of private property in New South Wales. In line with the Audit Office's legislative mandate, the audit does not comment on the merits of the policy objectives reflected in the Just Terms Act.

The audit examined a sample of 20 property acquisitions. This was not a statistically representative sample. While our report provides comments on Sydney Metro’s overall acquisition processes, it does not provide assurance regarding the acquisitions that were not examined for this audit.

The audit did not re-perform the valuations done for individual properties that were acquired by Sydney Metro. Affected parties who disagree with the valuation of their property have the right to seek independent assessment of this via the Valuer General and the Land and Environment Court.

Conclusion

Acquisitions of property for the Sydney Metro project were mostly effective in the sample of acquisitions we assessed. Sydney Metro followed requirements for communication with affected parties. Compensation processes were conducted in compliance with legislative requirements, but compensation determinations for compulsory acquisitions were not completed within legislated time frames due to delays in receiving these from the Valuer General. Governance and probity processes were followed consistently, with some relatively minor exceptions. 

Sydney Metro has detailed guidelines for acquisitions that are based on relevant legislation and government policy. In the 20 acquisitions we assessed for this audit, these procedures were followed consistently. This included adhering to minimum timelines for negotiation periods, engaging independent valuers and other experts when needed, and complying with governance and probity processes.

Sydney Metro staff followed requirements for communication and support for residential acquisitions by assigning ‘personal managers’ and providing additional support to affected parties when needed. The Centre for Property Acquisition (CPA) has overseen reforms to the residential property acquisition process in recent years. These reforms include the introduction of the NSW Property Acquisition Standards and the use of personal managers, in addition to the existing acquisition managers, for residential acquisitions. However, the CPA has not assessed the impact of these changes on the experiences on people affected by property acquisitions.

Sydney Metro did not comply with the legislative requirement to provide a formal compensation notice to the affected party within 45 days of a compulsory acquisition starting in any of the eight relevant acquisitions in our sample. This was because Sydney Metro must wait for the Valuer General to complete a compensation determination before Sydney Metro can send the compensation notice, and the Valuer General did not do this within 45 days. We acknowledge that Sydney Metro does not have full control over this process, and that it has taken steps to mitigate the impact of delays on affected parties. 

This chapter presents our findings on Sydney Metro's acquisition of industrial and commercial properties. Industrial properties include construction businesses and manufacturing facilities. Commercial properties were mostly properties such as shopping centres and office towers. Many of these acquisitions involve businesses and properties that are relatively complex and have high values. This means the valuation process can require multiple experts and can be lengthy and contested. Adherence to governance and probity requirements is important for these acquisitions in order to demonstrate that the acquiring authority has achieved value for money.

This chapter presents our findings on Sydney Metro's acquisition of residential properties, which include apartments and houses, and small business leases, which mostly affected businesses in small shopping centres or arcades. Most of these acquisitions were lower value compared to industrial and commercial property acquisitions and did not require as much expert advice on complex technical issues. However, residential property acquisitions can be personally distressing for the affected parties and require staff from the acquiring authority to provide support and show empathy while ensuring legislative compliance and value for money.

Appendix one – Responses from agencies

Appendix two – About the audit 

Appendix three – Performance auditing 

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #375 - released 9 February 2023

Published

Actions for Audit Insights 2018-2022

Audit Insights 2018-2022

Community Services
Education
Environment
Finance
Health
Industry
Justice
Local Government
Premier and Cabinet
Planning
Transport
Treasury
Universities
Whole of Government
Asset valuation
Cross-agency collaboration
Compliance
Cyber security
Financial reporting
Fraud
Information technology
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Regulation
Risk
Service delivery
Shared services and collaboration
Workforce and capability

What the report is about

In this report, we have analysed the key findings and recommendations from our audit reports over the past four years.

This analysis includes financial audits, performance audits, and compliance audits of state and local government entities that were tabled in NSW Parliament between July 2018 and February 2022.

The report is framed by recognition that the past four years have seen significant challenges and emergency events.

The scale of government responses to these events has been wide-ranging, involving emergency response coordination, service delivery, governance and policy.

The report is a resource to support public sector agencies and local government to improve future programs and activities.

What we found

Our analysis of findings and recommendations is structured around six key themes:

  • Integrity and transparency
  • Performance and monitoring
  • Governance and oversight
  • Cyber security and data
  • System planning for disruption
  • Resource management.

The report draws from this analysis to present recommendations for elements of good practice that government agencies should consider in relation to these themes. It also includes relevant examples from recent audit reports.

In this report we particularly call out threats to the integrity of government systems, processes and governance arrangements.

The report highlights the need for balanced advice to government on options and risks, for transparent documentation and reporting of directions and decisions, and for early and open sharing of information with integrity bodies and audit.

A number of the matters highlighted in this report are similar to those described in our previous Insights Report, (Performance Audit Insights: key findings from 2014–2018) specifically in relation to cyber and information security, to performance measurement, reporting and evaluation, and system and workforce planning and capability.

Fast facts

  • 72 audits included in the Audit Insights 2018–2022 analysis
  • 4 years of audits tabled by the Auditor-General for New South Wales
  • 6 key themes for Audit Insights 2018–2022.

picture of Margaret Crawford Auditor-General for New South Wales in black dress with city skyline as backgroundI am pleased to present the Audit Insights 2018–2022 report. This report describes key findings, trends and lessons learned from the last four years of audit. It seeks to inform the New South Wales Parliament of key risks identified and to provide insights and suggestions to the agencies we audit to improve performance across the public sector.

The report is framed by a very clear recognition that governments have been responding to significant events, in number, character and scale, over recent years. Further, it acknowledges that public servants at both state and council levels generally bring their best selves to work and diligently strive to deliver great outcomes for citizens and communities. The role of audit in this context is to provide necessary assurance over government spending, programs and services, and make suggestions for continuous improvement.

A number of the matters highlighted in this report are similar to those described in our previous Insights Report, (Performance Audit Insights: key findings from 2014–2018) specifically in relation to cyber and information security, to performance measurement, reporting and evaluation, and system and workforce planning and capability.

However, in this report we particularly call out threats to the integrity of government systems, processes and governance arrangements. We highlight the need for balanced advice to government on options and risks, for transparent documentation and reporting of directions and decisions, and for early and open sharing of information with integrity bodies and audit. Arguably, these considerations are never more important than in an increasingly complex environment and in the face of significant emergency events and they will be key areas of focus in our future audit program.

While we have acknowledged the challenges of the last few years have required rapid responses to address the short-term impacts of emergency events, there is much to be learned to improve future programs. I trust that the insights developed in this report provide a helpful resource to public sector agencies and local government across New South Wales. I would be pleased to receive any feedback you may wish to offer.

Margaret Crawford
Auditor-General for New South Wales

Integrity and transparency Performance and monitoring Governance and oversight Cyber security and data System planning Resource management
Insufficient documentation of decisions reduces the ability to identify, or rule out, misconduct or corruption. Failure to apply lessons learned risks mistakes being repeated and undermines future decisions on the use of public funds. The control environment should be risk-based and keep pace with changes in the quantum and diversity of agency work. Building effective cyber resilience requires leadership and committed executive management, along with dedicated resourcing to build improvements in cyber security and culture. Priorities to meet forecast demand should incorporate regular assessment of need and any emerging risks or trends. Absence of an overarching strategy to guide decision-making results in project-by-project decisions lacking coordination. Governments must weigh up the cost of reliance on consultants at the expense of internal capability, and actively manage contracts and conflicts of interest.
Government entities should report to the public at both system and project level for transparency and accountability. Government activities benefit from a clear statement of objectives and associated performance measures to support systematic monitoring and reporting on outcomes and impact. Management of risk should include mechanisms to escalate risks, and action plans to mitigate risks with effective controls. In implementing strategies to mitigate cyber risk, agencies must set target cyber maturity levels, and document their acceptance of cyber risks consistent with their risk appetite. Service planning should establish future service offerings and service levels relative to current capacity, address risks to avoid or mitigate disruption of business and service delivery, and coordinate across other relevant plans and stakeholders. Negotiations on outsourced services and major transactions must maintain focus on integrity and seeking value for public funds.
Entities must provide balanced advice to decision-makers on the benefits and risks of investments. Benefits realisation should identify responsibility for benefits management, set baselines and targets for benefits, review during delivery, and evaluate costs and benefits post-delivery. Active review of policies and procedures in line with current business activities supports more effective risk management. Governments hold repositories of valuable data and data capabilities that should be leveraged and shared across government and non-government entities to improve strategic planning and forecasting. Formal structures and systems to facilitate coordination between agencies is critical to more efficient allocation of resources and to facilitate a timely response to unexpected events. Transformation programs can be improved by resourcing a program management office.
Clear guidelines and transparency of decisions are critical in distributing grant funding. Quality assurance should underpin key inputs that support performance monitoring and accounting judgements. Governance arrangements can enable input into key decisions from both government and non-government partners, and those with direct experience of complex issues.     Workforce planning should consider service continuity and ensure that specialist and targeted roles can be resourced and allocated to meet community need.
Governments must ensure timely and complete provision of information to support governance, integrity and audit processes.          
Read more Read more Read more Read more Read more Read more

 

This report brings together a summary of key findings arising from NSW Audit Office reports tabled in the New South Wales Parliament between July 2018 and February 2022. This includes analysis of financial audits, performance audits, and compliance audits tabled over this period.

  • Financial audits provide an independent opinion on the financial statements of NSW Government entities, universities and councils and identify whether they comply with accounting standards, relevant laws, regulations, and government directions.
  • Performance audits determine whether government entities carry out their activities effectively, are doing so economically and efficiently, and in accordance with relevant laws. The activities examined by a performance audit may include a selected program or service, all or part of an entity, or more than one government entity. Performance audits can consider issues which affect the whole state and/or the local government sectors.
  • Compliance audits and other assurance reviews are audits that assess whether specific legislation, directions, and regulations have been adhered to.

This report follows our earlier edition titled 'Performance Audit Insights: key findings from 2014–2018'. That report sought to highlight issues and themes emerging from performance audit findings, and to share lessons common across government. In this report, we have analysed the key findings and recommendations from our reports over the past four years. The full list of reports is included in Appendix 1. The analysis included findings and recommendations from 58 performance audits, as well as selected financial and compliance reports tabled between July 2018 and February 2022. The number of recommendations and key findings made across different areas of activity and the top issues are summarised at Exhibit 1.

The past four years have seen unprecedented challenges and several emergency events, and the scale of government responses to these events has been wide-ranging involving emergency response coordination, service delivery, governance and policy. While these emergencies are having a significant impact today, they are also likely to continue to have an impact into the future. There is much to learn from the response to those events that will help the government sector to prepare for and respond to future disruption. The following chapters bring together our recommendations for core elements of good practice across a number of areas of government activity, along with relevant examples from recent audit reports.

This 'Audit Insights 2018–2022' report does not make comparative analysis of trends in public sector performance since our 2018 Insights report, but instead highlights areas where government continues to face challenges, as well as new issues that our audits have identified since our 2018 report. We will continue to use the findings of our Insights analysis to shape our future audit priorities, in line with our purpose to help Parliament hold government accountable for its use of public resources in New South Wales.

Appendix one – Included reports, 2018–2022

Appendix two – About this report

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Rail freight and Greater Sydney

Rail freight and Greater Sydney

Transport
Information technology
Infrastructure
Management and administration
Project management
Service delivery

What the report is about

The movement of freight contributes $66 billion annually to the NSW economy. Two thirds of all freight in NSW moves through Greater Sydney, and the volume of freight moving through Greater Sydney is expected to increase by 48 per cent by 2036.

This audit assessed the effectiveness of transport agencies in improving the use of rail freight capacity in Greater Sydney, and to meet current and future freight demand.

What we found

Transport agencies do not have strategies or targets in place to improve the efficiency or capacity of the metropolitan shared rail network for freight.

The transport agencies acknowledge that they do not have sufficient information to achieve the most efficient freight outcomes and they do not know how to use the shared rail network to maximise freight capacity without compromising passenger rail services.

The Freight and Ports Plan 2018-2023 contains one target for rail freight - to increase the use of rail at Port Botany to 28 per cent by 2021. However, Transport for NSW (TfNSW)'s data indicates this target will not be met.

Sydney Trains records data on train movements and collects some data on delays and incidents. TfNSW collects data for the construction of the Standard Working Timetable and third-party contracts.

However, a lack of clarity around what data is gathered and who has ownership of the data makes data sharing difficult and limits its analysis and reporting.

The Freight and Ports Plan 2018-2023 includes the goal of 'Reducing avoidable rail freight delays', but the transport agencies do not have any definition for an avoidable delay and, as a result, do not measure or report them.

TfNSW and Sydney Trains are appointed to manage and deliver the Transport Asset Holding Entity of New South Wales (TAHE)'s obligations to allow rail freight operators to use the shared rail network. There are no performance measures in rail freight operator contracts or inter-agency agreements. This limits transport agencies' ability to improve performance.

TfNSW’s Freight Branch is working on four freight-specific strategies; a review of the Plan, a freight rail strategy, a port efficiency strategy and a freight data strategy.

TfNSW has not yet determined the timeframes or intended outcomes of these strategies.

What we recommended

Transport agencies should:

  • commit, as part of the review of Future Transport 2056, to delivering the freight-specific strategies currently in development and develop whole-of-cluster accountability for this work including timeframes, specific targets and clear roles and responsibilities 
  • improve the collection and sharing of freight data
  • develop a plan to reduce avoidable freight delays
  • systematically collect data on the management of all delays involving and/or impacting rail-freight
  • develop and implement key performance indicators for the agreements between the transport agencies.

Fast facts    

  • 288 million tonnes of freight volume predicted to pass through Greater Sydney in 2036, up from 194 million in 2016 (an increase of 48%)

  • 54 trucks that can be replaced by one 600 m long port shuttle freight train    

  • 26,671 freight trains that passed through the metropolitan shared rail network between 1 July 2020 and 30 June 2021

The movement of freight contributes $66.0 billion annually to the New South Wales economy — or 13 per cent of the Gross State Product. Two thirds of all freight in New South Wales moves through Greater Sydney, and the volume of freight moving through Greater Sydney is expected to increase by 48 per cent by 2036. This increasing demand is driven by increasing population and economic growth.

The sequence of activities required to move goods from their point of origin to the eventual consumer (the supply chain) is what matters most to shippers and consumers. Road can provide a single-mode door-to-door service, whereas conveying goods by rail typically involves moving freight onto road at some point. In Greater Sydney, 80 per cent of all freight is moved on road. Freight often passes through intermodal terminals (IMTs) as it transitions from one mode of transport to the next.

In 2016, Transport for NSW (TfNSW) released Future Transport 2056 - the NSW Government's 40-year vision for transport in New South Wales, which is intended to guide investment over the longer term. In Future Transport 2056, TfNSW noted that New South Wales will struggle to meet increasing demand for freight movements unless rail plays a larger role in the movement of freight.

Sydney Trains manages the metropolitan shared rail network, which is made up of rail lines that are used by both passenger and freight trains. The Transport Administration Act 1988 requires that, for the purposes of network control and timetabling, NSW Government transport agencies give ‘reasonable priority’ to passenger trains on shared lines. As the Greater Sydney population and rail patronage continue to grow, so too will competition for access to the shared rail network. See Appendix two for details of the area encompassed by Greater Sydney.

Freight operators can also use dedicated rail freight lines operated by the Australian Rail Track Corporation (ARTC - an Australian Government statutory-owned corporation). As the metropolitan shared rail network connects with dedicated freight lines, freight operators often use both to complete a journey.

TfNSW, Sydney Trains and the Transport Asset Holding Entity (TAHE) work in conjunction with other rail infrastructure owners and private sector entities, including port operators, privately operated IMTs and freight-shipping companies. TfNSW and Sydney Trains are responsible for managing the movement of freight across the metropolitan shared rail network. TAHE is the owner of the rail infrastructure that makes up the metropolitan shared rail network. The NSW Government established TAHE, a NSW Government state-owned corporation, on 1 July 2020 to replace the former rail infrastructure owner - RailCorp. The Auditor-General for New South Wales has commenced a performance audit on TAHE which is expected to table in 2022.

On 1 July 2021, TAHE entered into new agreements with TfNSW and Sydney Trains to operate, manage and maintain the metropolitan shared rail network. Until 30 June 2021, and in accordance with TAHE's Implementation Deed, TAHE operated under the terms of RailCorp's existing arrangements and agreements.

This audit assessed the effectiveness of TfNSW, Sydney Trains and TAHE in improving the use of rail freight capacity in Greater Sydney, and to meet current and future freight demand.

The audit focused on:

  • the monitoring of access to shared rail lines
  • the management of avoidable delays of rail freight movements
  • steps to increase the use of rail freight capacity in Greater Sydney.

Conclusion

Transport agencies do not have clear strategies or targets in place to improve the freight efficiency or capacity of the metropolitan shared rail network. They also do not know how to make best use the rail network to achieve the efficient use of its rail freight capacity. These factors expose the risk that rail freight capacity will not meet anticipated increases in freight demand.

Future Transport 2056 notes that opportunities exist to shift more freight onto rail, and that making this change remains an important priority for the NSW Government. However, the transport agencies acknowledge that they do not have sufficient information to achieve the most efficient freight outcomes. In particular, transport agencies do not know how to use the shared rail network in a way that maximises freight capacity without compromising passenger rail services.

Neither Future Transport 2056 nor the Freight and Ports Plan 2018–2023 give any guidance on how transport agencies will improve the efficiency or capacity of the shared rail network. Other than a target for rail freight movements to and from Port Botany, which TfNSW's data indicates will not be met, there are no targets for improving rail freight capacity across the shared network. The lack of specific strategies, objectives and targets reduces accountability and makes it difficult for transport agencies to effectively improve the use of rail freight capacity in line with their commitment to do so.

Sydney Trains and Transport for NSW do not effectively use data to improve rail freight performance and capacity.

To drive performance improvement when planning for the future, transport agencies need good quality data on freight management and movements. Sydney Trains records data on train movements in real-time and collects some data on delays and incidents. TfNSW collects data for the construction of the Standard Working Timetable (SWTT) and third-party contracts. However, the different types of data gathered and the separation between the teams responsible mean that there is a lack of clarity around what data is gathered and who has ownership it. This lack of coordination prevents best use of the data to develop a single picture of how well the network is operating or how performance could be improved.

Sydney Trains' ability to evaluate the effectiveness of its incident and delay mitigation strategies is also limited by a lack of information on its management of rail-freight related delays or incidents. While Sydney Trains collects data on major incidents, it can only use this to conduct event-specific analysis on the causes of an incident, and to review the operational and management response. The use of complete and accurate incident data would assist to define, identify and reduce avoidable delays. Reducing avoidable delays is a goal of the Freight and Ports Plan 2018–2023. More complete data on all incidents would help TfNSW to have more effective performance discussions with rail freight operators to help improve performance.

TfNSW has started developing strategies to identify how it can use rail freight capacity to achieve efficient freight outcomes, but it has not committed to implementation timeframes for this work.

TfNSW’s Freight Branch has started work on four freight-specific strategies to improve freight efficiency: a review of the Plan, a freight rail strategy, a port efficiency strategy and a freight data strategy. However, none of these strategies will be fully developed before the end of 2022. TfNSW has not yet determined the implementation timeframes or intended outcomes of these strategies, although TfNSW reports that it is taking an iterative approach and some recommendations and initiatives will be developed during 2022. 

Appendix one - Response from agencies

Appendix two - The Greater Sydney region

Appendix three - TfNSW strategic projects 

Appendix four - Sydney Trains path priority principles 

Appendix five - Sydney Trains delay management

Appendix six - About the audit 

Appendix seven - Performance auditing
 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #357 - released (19 October 2021).

Published

Actions for WestConnex: changes since 2014

WestConnex: changes since 2014

Transport
Compliance
Infrastructure
Internal controls and governance
Management and administration
Project management
Risk

What the report is about

The report examined whether Transport for NSW (TfNSW) and Infrastructure NSW (INSW) effectively assessed and justified major scope changes to the WestConnex project since 2014.

What we found

NSW Government decisions to fund WestConnex-related projects outside WestConnex's $16.812 billion budget have reduced transparency and understate the full cost of WestConnex.

The NSW Government's decision to separate Sydney Gateway from WestConnex has reduced transparency over the cost of the road component of Sydney Gateway. $1.76 billion of the cost to complete Sydney Gateway is funded outside the WestConnex budget.

Network integration costs, currently estimated at $2.3 billion, are also funded outside the WestConnex budget. Many of these costs are directly attributable to WestConnex and ought to be included in the reported budget.

The Parramatta Road Urban Amenity Improvement Program, costing $198 million, should also be included as part of the WestConnex reported budget.

Decisions to exclude or remove these elements from WestConnex without justification have seen $4.26 billion of projects funded outside the $16.8 billion budget.

Positively, robust analysis was used to develop and incorporate design improvements into the 2015 WestConnex Updated Strategic Business Case.

The separate components of WestConnex underwent all required assurance reviews. However, the NSW Government's assurance framework does not require ongoing ‘whole-of-program’ assurance for large and complex projects like WestConnex. The absence of a holistic review of WestConnex allows for some costs and benefits to avoid scrutiny.

What we recommended

TfNSW should:

  • review the impact of scope changes on project objectives, costs and benefits for complex infrastructure projects
  • ensure that estimated costs and benefits of works which are reasonably required to meet consent conditions are included in business cases for complex large infrastructure projects
  • establish centralised and project specific record keeping for major infrastructure projects.

Infrastructure NSW should provide transparent whole of program assurance on total costs and benefits when complex projects are split into sub-projects.

Government should consider enhancing public transparency of existing infrastructure assurance processes by requiring that large complex infrastructure programs undergo periodic review at a whole-of-program level.

Fast facts

  • $16.812b 2015 WestConnex business case budget
  • $2.3b current estimated cost of network integration works to enable WestConnex, funded outside the WestConnex budget
  • $1.76b cost to complete Sydney Gateway to enable WestConnex and also funded outside the WestConnex budget
  • $198m Parramatta Road Urban Amenity Improvement Program, originally part of WestConnex but now funded outside the WestConnex budget

WestConnex

WestConnex is a 33 km motorway network that will link the western and south‑western suburbs with the Sydney CBD and the Airport and Port Botany precinct. It will also connect with proposed future motorway links to the north shore, northern beaches, and southern Sydney. The project is being delivered in three stages, with completion scheduled for 2023.

When first conceived by Infrastructure NSW (INSW) in 2012, WestConnex was described as a single integrated concept. In August 2013, government approved a business case for an integrated concept of WestConnex, with an estimated cost of $14.881 billion (in nominal outturn costs). Transport for NSW (TfNSW) is the government agency (sponsor agency) accountable for the delivery of WestConnex in accordance with the business case. In August 2014, the NSW Government established the Sydney Motorway Corporation to fund, deliver and operate WestConnex.

In November 2015, the NSW Government publicly released an updated WestConnex business case with greater detail and design enhancements, which increased the estimated cost to $16.812 billion.

Subsequent to this update, further changes were made to the design, including realignment of the M4 to M5 Link connection to the Western Harbour Tunnel project, an expanded interchange at Rozelle, the deletion of the Camperdown Intersection, and the addition of the Iron Cove Link. The reported budget for WestConnex was not changed as a result of these design updates.

To fund WestConnex, Sydney Motorway Corporation consolidated a concessional loan of $2 billion from the Australian Government, private sector debt and equity funding from the State. The Australian Government also provided a $1.5 billion contribution to the State to partially fund construction of WestConnex.

In August 2018, the NSW Government sold 51 per cent of its stake in Sydney Motorway Corporation for $9.26 billion. At the time of writing, the NSW Government is in the process of selling its remaining 49 per cent stake of Sydney Motorway Corporation.

About this audit

In the course of delivering a complex major infrastructure project, it is reasonable to expect changes to the original design and scope. Changes may occur as the design moves from a high‑level concept to a detailed design for project delivery, as new risks or issues are identified, as demands change, or as other interdependent projects are approved. Changes can also occur in response to potential cost or delivery overruns which arise as a result of planning deficiencies. Where design and scope changes significantly change the project costs and/or expected benefits, the justification for these changes should be robust and transparent.

Following our 2014 performance audit, 'WestConnex: Assurance to the government', the NSW Government established the Infrastructure Investor Assurance Framework (IIAF) to improve accountability and transparency over major projects that are developed, procured, or delivered by government agencies. Under the framework, TfNSW, as project sponsor, is responsible for ensuring the WestConnex project meets all IIAF requirements. These include ensuring the project remains strategically aligned and viable, and benefits are on track. INSW is responsible for coordinating the assurance review process and reporting directly to NSW Cabinet on project delivery against time, budget and risks to project delivery.

The objective of this performance audit is to assess whether TfNSW and INSW effectively assessed and justified major scope changes to the WestConnex project since 2014.

 

Conclusion

Government decisions to separate WestConnex related projects and deliver them outside WestConnex's 2015 business case budget of $16.812 billion has understated the total cost of WestConnex achieving its objectives. The rationale for separating these elements from the WestConnex project scope has not been transparent. Together, these projects represent costs of $4.26 billion funded outside the $16.812 billion WestConnex budget.

Since 2015, the NSW Government has removed several projects from the scope described in the 2015 WestConnex business case, and funded them separately:
  • In mid‑2017, the Sydney Gateway became a separate project outside WestConnex. This project, estimated in 2015 to cost $800 million, now has an estimated cost of $2.56 billion. The project remains partly funded by an $800 million contribution from the $16.812 billion WestConnex budget, with $1.76 billion funded outside the WestConnex budget.
  • In late 2018, the Parramatta Road Urban Amenity Improvement Program became a separate project outside the 2015 WestConnex budget. This project was part of the 2015 WestConnex Business Case and is intended to create urban renewal opportunities around Paramatta Road. It is estimated to cost $198 million.

Work required to integrate WestConnex with existing roads ('network integration') was funded outside the $16.812 billion budget for the November 2015 WestConnex business case. TfNSW is obliged to deliver network integration works to meet the conditions of planning approval for WestConnex. As such, these costs should be included in the WestConnex budget. The current estimated cost of these network integration works is $2.3 billion.

The rationale to exclude or remove each of these elements from the WestConnex project scope has not been transparent, nor supported by robust analysis and justification. These elements are required for WestConnex to achieve its objectives. The additional project costs will also deliver additional benefits not included in the 2015 WestConnex business case. Removing them understates the total cost of achieving the objectives set out in the 2013 and 2015 WestConnex business cases.

WestConnex's complex financing arrangements further reduce transparency on costs.

Transparency over the total cost of WestConnex – including elements funded from other project budgets – is further limited by the project's complex financing arrangements.

Prior to 2018, the Audit Office provided assurance on costs borne and levied by Sydney Motorway Corporation and its controlled entities. Since the NSW Government sold its majority stake in WestConnex in August 2018, the Auditor‑General no longer has the mandate to provide this assurance. Considering this, and the lack of transparency on the cost of projects removed from the WestConnex project scope, there is no transparent or comprehensive view of the total cost to deliver WestConnex – nor of how these cost would be offset by the sale of the government's remaining stake.

There is no 'whole‑of‑program' assurance over the WestConnex program of works. This limits transparency and confidence that WestConnex will meet intended objectives within its budget.

After INSW conducted a gateway review of a draft of the 2015 WestConnex Business Case under the IIAF, the project was broken up into separate components to support staged delivery. Each of these projects, including the Sydney Gateway, as well as the Network Integration Program, underwent the required assurance reviews under the IIAF. INSW also provided monthly progress updates to government. These individual projects are, in themselves, significant in scale and complexity. Addressing them as discrete components for the purposes of the assurance review process is justified and there is no requirement under the IIAF to holistically review projects which together deliver final benefits of the WestConnex program. However, whole‑of‑program review would improve transparency over total costs and benefits.

In 2016, TfNSW revised the design of the M4‑M5 Link and Rozelle to address traffic and integration issues.

TfNSW identified that the concept designs used for the M4‑M5 Link and Rozelle Interchange in the 2015 WestConnex Business Case would not integrate well with surface roads, including the proposed Bays Precinct, and would result in increased traffic on Victoria Road and the ANZAC Bridge. Following a comprehensive review conducted in mid‑2016, TfNSW refined the design of the M4‑M5 Link and Rozelle Interchange to address these limitations without increasing the cost of delivery. TfNSW documented the rationale for the design changes, including how the changes improved on the original design to increase capacity, improve traffic conditions and create more open space.

1. Key findings

Government decisions to fund WestConnex related projects outside of WestConnex's $16.812 billion reported budget have reduced transparency over costs and understate the full cost of WestConnex

In 2015, the work required to integrate WestConnex with existing roads ('network integration') was funded as a separate project with an estimated cost of $1.534 billion outside the 2015 WestConnex budget of $16.812 billion. TfNSW then created the Network Integration Program to respond to the conditions of planning approval for WestConnex. The current estimated cost to deliver all network integration works is $2.3 billion.

Since the 2015 WestConnex Business Case, the NSW Government has removed several elements from the scope of WestConnex and funded them as separate projects, while keeping the published WestConnex budget at an estimated $16.812 billion. Projects removed include:

  • Sydney Gateway, currently costed at $2.56 billion (with an $800 million contribution from WestConnex)
  • Parramatta Road Urban Amenity Improvement Program, costed at $198 million in late 2018 and funded though new funding to the Greater Sydney Commission.

Together, these projects represent costs of $4.26 billion that are not included in the WestConnex budget, but are required for WestConnex to achieve the objectives of the 2013 and 2015 WestConnex Business Cases. The costs of these elements in supporting the objectives of WestConnex is not tracked centrally, and there is no single point of oversight over them. Exhibit 1 compares total WestConnex forecast costs (including related projects) between November 2015 and April 2021.

 

November 2015
($ million)

April 2021
($ million)
WestConnex
Stage 1
Stage 1A (M4 Widening) 497 517
Stage 1B (M4 East) 3,802 3,782
Total 4,299 4,299
Stage 2
King Georges Road Interchange 131 131
New M5 4,335 4,335
Sydney Gateway Contribution 800 800
Total 5,266 5,266
Stage 3
M4‑M5 Link and Rozelle Interchange 7,049 7,049
Urban renewal (Parramatta Road) 198 ‑‑
Urban renewal (Rozelle) ‑‑ 198
Total 7,247 7,247
Total reportable WestConnex 16,812 16,812

Exhibit 1: WestConnex and related projects forecast costs
  November 2015
($ million)
April 2021
($ million)
Related projects
Network integration 1,534 2,300
Urban renewal (Parramatta Road) ‑‑ 198
Sydney Gateway Road Component ‑‑ 1,760
Total 1,534 4,258

Source: AO research.

Many network integration costs are directly attributable to WestConnex and ought to be included in the reported budget for WestConnex

Prior to 2015, the scope of WestConnex included enabling works needed before or during construction, as well as funding for future works to address any adverse traffic outcomes created by WestConnex which become apparent after its opening. These works are also known as network integration works.

When government approved the 2015 WestConnex Business Case, it noted that the project would require $1.534 billion for network integration works to address the impacts of WestConnex on the road network. However, the WestConnex project budget of $16.812 billion did not include funding for network integration works. Instead, Roads and Maritime Services (RMS, now TfNSW) was to fund network integration through its normal budget allocation.

It is important to recognise these costs as part of the total WestConnex project cost because:

  • TfNSW created the Network Integration Program to respond to network traffic and transport elements of the planning conditions of approval for WestConnex granted by the then NSW Department of Planning and Environment under the Environment, Planning and Assessment Act 1979.
  • NSW Treasury guidelines for business cases note that accurate cost estimates include assessment of the financial impact of meeting the conditions of planning approval.
  • Travel time and vehicle operating cost benefits attributed to the WestConnex project in the 2015 WestConnex Business Case assume that some network integration works, then costed at $373 million, were in place.

Refer to Appendix two for more detail on network integration works.

Some of the projects in the WestConnex Network Integration Program provide community and place benefits, such as parklands and cycleways. These benefits have not been attributed to WestConnex. Additionally, some network integration works are likely to deliver additional traffic related benefits to WestConnex. As the Network Integration Program’s primary purpose is to meet the conditions of planning approval for WestConnex, TfNSW should attribute all the costs and benefits of the program to WestConnex.

To September 2021, the total funded cost of the Network Integration Program is approximately $2.077 billion. TfNSW estimates that it will need a further $222 million to complete all expected network integration works.

The NSW Government's decision to separate Sydney Gateway from WestConnex has reduced transparency and accountability for TfNSW's underestimation of the cost of the road component of Sydney Gateway

Sydney Gateway is a high‑capacity connection between the new St Peters Interchange and the Sydney Airport and Port Botany precinct. It includes a road and rail components. The road component was included in the scope of WestConnex in the 2015 WestConnex Business Case. The November 2015 design, which TfNSW costed at $800 million, involved separate roadways from the St Peters Interchange to the International terminal, and to the domestic terminals and Mascot airport precinct.

By October 2016, TfNSW was aware that the $800 million budget for Sydney Gateway was insufficient and revised the forecast cost for the road component to $1.8 billion. The original cost estimate did not sufficiently consider the cost of:

  • constructing a complex design adjacent to the airport precinct
  • obtaining access to land required for the project
  • managing environmental contamination.

On 9 August 2017, the then Minister for WestConnex announced that the Sydney Gateway project was not part of WestConnex.

The 2015 WestConnex Business Case notes that material changes to the WestConnex budget, funding, scope, or timeframe are subject to Cabinet approval processes. It states that, when seeking approval for material changes, the portfolio Minister will make a submission to the relevant Cabinet Committee. Changes in project scope required the approval of the then Cabinet Committee on Infrastructure and should have been endorsed by the WestConnex Interdepartmental Steering Committee.

TfNSW and the NSW Department of Premier and Cabinet (DPC) assert that there is no documentation to support the government’s decision to separate Sydney Gateway from the WestConnex Program, or the WestConnex Interdepartmental Steering Committee's endorsement of a submission to Cabinet seeking approval for the separation.

The established governance processes for major scope changes were not followed in this instance. The lack of transparency regarding government's decision to separate Sydney Gateway from WestConnex also reduces visibility of TfNSW's underestimation of the cost of delivering the road component of Sydney Gateway.

The November 2018 Final Business Case for Sydney Gateway, which was approved by the government, included an estimate of $2.45 billion (nominal outturn cost) for the road component. This estimate included an $800 million contribution from WestConnex. A more recent estimate (late 2020) for this project is $2.56 billion (nominal outturn cost).

The Parramatta Road Urban Amenity Improvement Program should be included as part of the WestConnex budget

A specific objective of the 2015 WestConnex Business Case was the creation of opportunities for urban renewal along and around Parramatta Road. The business case included an allocation of $198 million in the $16.812 billion WestConnex budget for the Parramatta Road Urban Amenity Improvement program, designed to implement aspects of the objective. In November 2018, the NSW Government removed the Parramatta Road Urban Amenity Improvement Program from the WestConnex program of works and reallocated the $198 million (inside the $16.812 billion WestConnex budget) for urban renewal works around the Rozelle Interchange. As part of this decision, government approved new funding of $198 million to the Greater Sydney Commission for the urban amenity program, outside the $16.812 billion WestConnex budget. This understates the cost of WestConnex meeting its objectives by $198 million.

There is no requirement for ongoing ‘whole‑of‑program’ assurance of the WestConnex program of works, including related projects

In August 2015, INSW conducted its first Gateway Review of WestConnex as a program consisting of composite projects. Following that review, TfNSW registered each of the components of WestConnex with INSW as individual projects, rather than keeping WestConnex registered as a program or mega‑project. This is not inconsistent with the IIAF and all WestConnex related projects, including Sydney Gateway and the Network Integration Program, have undergone independent assurance reviews as individual projects under the IIAF.

Once a program like WestConnex is broken down into its composite parts, there is no requirement for the sponsor agency (TfNSW) or INSW to provide independent assurance on the program as a whole until it is completed. This is then done as part of the Gateway review for benefits realisation, which examines whether project benefits are being measured and meet expectations. These individual projects are, in themselves, significant in scale and complexity. While addressing them as discrete components for the purposes of the assurance review process can be justified, the absence of strategic, holistic reviews of WestConnex allows for total costs and benefits to become opaque and avoid scrutiny. Programs of this scale require greater ongoing transparency on total costs and benefits in order to ensure confidence they will meet intended objectives within budget.

There is a lack of public transparency on the total costs and benefits of the WestConnex project

Prior to 2018, the Audit Office provided assurance on costs borne and levied by Sydney Motorway Corporation and its controlled entities. Since the NSW Government sold 51 per cent of its stake in WestConnex in August 2018, the Auditor‑General no longer has the mandate to provide this assurance. The Audit Office is also unable to provide any assurance regarding the performance of tolling concessions.

This means that the total costs of WestConnex, including those levied on road users through tolling, are not reported alongside the full cost of delivering the project. This information, and independent assurance over that information, would provide transparency and context to the outcome of government's sale of its interest in WestConnex.

To enhance the transparency of existing infrastructure assurance processes, government could consider requiring large and complex infrastructure programs to undergo periodic review at a whole‑of‑program level. This could take the form of annual reports to Parliament on the total costs and benefits of selected large and complex projects by the responsible agency. The reports could include an assessment of the cost to government and cost to the community of funding and financing. Independent assurance of the agency report would provide Parliament with greater confidence that infrastructure is delivered economically and providing value for money for the people of NSW.

The Australian National Audit Office provides similar assurance on selected Department of Defence acquisition projects as part of its annual Major Projects Report.

Design enhancements included in the 2015 WestConnex Updated Strategic Business Case were supported by robust analysis

The 2015 WestConnex Business Case contained more detail than the 2013 WestConnex business case. Design enhancements were made as a result of modelling analysis conducted over the two years since the 2013 business case. Enhancements included a full underground link between Kingsgrove and St Peters as part of the New M5 and re‑alignment of the M4‑M5 link tunnel (Stage 3) to include the Rozelle Interchange. The Rozelle Interchange will provide a direct connection to the Anzac Bridge and Victoria Road, and will enable a connection to the proposed Western Harbour Tunnel and Beaches Link. A map and description of these elements can be found at Exhibits 2 and 3 of this report.

In 2016, TfNSW revised the design of the M4‑M5 Link and Rozelle to address traffic and integration issues

As part of preparing the 2015 WestConnex Business Case, TfNSW prepared a Project Definition and Delivery Report (PDDR) for the M4‑M5 Link. This report describes the scope of the project, including a high‑level concept design. TfNSW identified limitations with the proposed design of the M4‑M5 in the PDDR, which it would need to address as the project moved to a detailed design stage. In particular, these limitations included:

  • poor integration with the Bays Precinct masterplan
  • traffic capacity constraints on Victoria Road and Anzac Bridge
  • construction complexity.

Following a comprehensive review in mid‑2016, TfNSW changed the design of the M4‑M5 Link and Rozelle Interchange to address these limitations. These changes included:

  • deletion of the Camperdown intersection to improve traffic conditions on Parramatta Road
  • a fully underground and larger Rozelle Interchange with 10‑hectare dedicated parklands
  • a toll‑free tunnel link from Iron Cove Bridge to Anzac Bridge
  • increasing the lanes in the dual tunnels from three to four each way.

TfNSW documented, but did not publish, the rationale for the design changes, including how the changes addressed the limitations of the previous design while providing increased community benefit through the creation of open space. TfNSW undertook cost comparison studies which estimated that these changes would have a neutral impact on the estimated project cost while achieving the same or improved benefits.

TfNSW's record‑keeping systems for large infrastructure investments negatively impact accountability and transparency

In response to our formal requests for relevant information, made during the conduct of this audit, TfNSW advised that complete and valid records of key decision‑making processes, analysis and advice were unavailable. Additionally, TfNSW often provided information that was incomplete or unverifiable (for instance, unsigned briefing notes). This is not consistent with accepted governance practices and does not comply with the requirements of the State Records Act 1998.

We also requested that TfNSW provide a list of relevant documents held by the Sydney Motorway Corporation (SMC). While TfNSW acknowledged that SMC may hold material relevant to the audit, TfNSW did not have a list or description of these documents. As SMC is now a majority privately held entity, both the Audit Office and TfNSW have limited power to require SMC to provide documentation.

The delivery timeframe for large and complex infrastructure projects such as WestConnex frequently exceeds five years, and some projects can take over a decade to deliver. These projects represent a significant investment of public resources and government agencies should expect independent review and assurance activities such as performance audits. The establishment of dedicated record keeping facilities for major infrastructure projects, such as data rooms, would improve transparency and accountability. This would ensure that the use of public resources is fully auditable in line with public expectations and the requirements of the Government Sector Finance Act 2018, the State Records Act 1998 and the Public Finance and Audit Act 1983.

2. Recommendations

By December 2021, TfNSW should:

1. review the impact of scope changes on project objectives, costs and benefits for complex infrastructure projects

2. when preparing business cases for complex large infrastructure projects, ensure that the estimated costs and benefits of works which are reasonably expected to meet consent conditions are included in the overall project cost and its benefits (as per Treasury guidelines)

3. establish and maintain centralised and project‑specific record keeping, including through dedicated project data rooms, to ensure major infrastructure projects can readily be subject to external oversight and assurance.

By June 2022, INSW should:

4. provide transparent whole‑of‑program assurance on total costs and benefits throughout the project life‑cycle when complex projects are split into sub‑projects.

By June 2022, NSW Government should:

5. consider enhancing the public transparency of existing infrastructure assurance processes by requiring that large complex infrastructure programs undergo periodic review at a whole‑of‑program level. This could take the form of reports to Parliament on the total costs and benefits on selected large and complex projects by the responsible agency, including cost to government and cost to community of funding and financing, as well as an accompanying independent assessment of the agency report.

Following our 2014 performance audit report 'WestConnex: Assurance to the government', the NSW Government established the Infrastructure Investor Assurance Framework (IIAF). INSW is responsible for the development, implementation and administration of the IIAF. The assurance framework involves gateway reviews, health checks, deep dive reviews, and project monitoring and reporting at various stages in the lifecycle of a project. The main aims of the IIAF are to help ensure major infrastructure projects are delivered on time and on budget, and to ensure that reports are regularly monitored by the Cabinet of the NSW Government. The IIAF gateway review process is compulsory for all significant investments and expenditure under the NSW Treasury Gateway Policy.

In accordance with the IIAF, INSW is responsible for the following:

  • providing a dedicated Assurance Team including Gateway Review Managers to coordinate Reviews
  • determining appropriate expert reviewers, and manages scheduling, commissioning and administration of Assurance Review reports. Infrastructure NSW is independent of the Expert Review Team
  • monitoring Tier 1 – High Profile/High Risk projects, Tier 2 and Tier 3 (if required) project performance through independent Assurance Reviews
  • providing independent analysis and advice on key risks and any corrective actions recommended for Tier 1 – High Profile/High Risk, Tier 2 and Tier 3 projects
  • escalating projects to Infrastructure Investor Assurance Committee (IIAC) and Cabinet where projects present ‘red flag issues’ and where corrective action is needed
  • working with delivery agencies to register all capital projects with an estimated cost greater than $10.0 million and ensures they are risk profiled and assigned a risk‑based project tier with an endorsed IIAF Project Registration report
  • preparing forward looking annual Cluster Assurance Plans
  • maintaining and continuously improves the IIAF process
  • reporting to the IIAC, Cabinet and Infrastructure NSW Board
  • regularly report to NSW Treasury on the performance of the IIAF.

In relation to WestConnex, TfNSW is the sponsor agency responsible for meeting relevant IIAF requirements, including:

  • registering and risk profiling projects
  • IIAF gateway, health check, and deep dive assurance reviews
  • regular reporting.

Under the IIAF, it is mandatory for all capital projects valued over $10.0 million to be registered with INSW. Capital projects can be registered either as a program (comprising of a group of related projects or activities) or as a project (which may or may not be part of a program).

According to the IIAF, programs tend to have a lifespan of several years and aim to deliver outcomes and benefits related to an organisation's strategic objectives. Projects tend to have a shorter lifespan, and deal with outputs. Projects can, however, be grouped under a single program if they are similar in nature or if they are aimed at collectively achieving a strategic objective. Complex projects can be delivered in multiple stages, under different contracts, and across different time periods.

The last assurance review of the entire WestConnex program of works as a whole was in 2015

INSW conducted the first IIAF gateway review of WestConnex in August 2015. TfNSW developed a draft WestConnex Updated Strategic Business Case to consolidate the latest analysis on WestConnex, and to confirm that the project remained fit for purpose, economically viable, and financially deliverable. The review followed a recommendation in our 2014 performance audit report that business cases be thoroughly revisited.

During September 2015, INSW conducted additional informal reviews to identify strategic risks associated with public release of the WestConnex business case. Subsequently, INSW gave the Premier of NSW its views on the draft business case, including the following points:

  • The $398 million budget for Sydney Gateway was insufficient to meet the benefits claimed in the business case for a ‘functional’ connection to Sydney Airport and Port Botany. INSW studies indicate a future‑proof solution would require a minimum spend of $755 million.
  • Enabling works for WestConnex estimated at $1.534 billion were excluded from the cost of WestConnex. Significant work remained for RMS to identify mitigation measures to address planning approvals and network performance issues.
  • Enabling works (a Southern Connector), an access ramp and surface road improvements within St Peters were excluded from the draft 2015 business case despite their inclusion in the WestConnex scope in the 2014–15 State Budget.
  • The overall cost of works not funded within the WestConnex budget ranged from $2.011 billion to $2.196 billion. This included the enabling works, access ramp and surface road improvements and the shortfall for Sydney Gateway.

All WestConnex related projects, including Sydney Gateway have undergone independent assurance reviews under the IIAF

Since INSW submitted the first WestConnex progress update report to Cabinet in June 2015, INSW has been reporting monthly on the different stages of the WestConnex Program, including Sydney Gateway, as the projects were registered with INSW as High‑Profile, High‑Risk projects. Separate reporting enabled INSW to report and review each stage with more detailed scrutiny, compared to the reporting and reviewing at a program level.

WestConnex Stage 2 (New M5) underwent both mandatory and non‑mandatory reviews at key points in the project lifecycle. Three mandatory gateway reviews – at Gate 2 (Final business case), Gate 3 (Readiness for market), and Gate 4 (Tender evaluation) – were conducted by TfNSW before the introduction of IIAF. Four non‑mandatory health check reviews and one non‑mandatory deep dive review were conducted after the introduction of the IIAF managed by INSW.

Similarly, WestConnex Stage 3 projects – M4‑M5 link, M4‑M5 Tunnels, and Rozelle Interchange – also underwent mandatory and non‑mandatory reviews at key points in their lifecycle under IIAF.

The M4‑M5 Link had two mandatory gateway reviews and one non‑mandatory health check review under IIAF. These reviews were conducted before Stage 3 was split into two stages, due to major design changes to the Rozelle Interchange and the M4‑M5 tunnels.

The M4‑M5 tunnels had two mandatory gateway reviews (at Gates 3 and 4), one non‑mandatory health check review, and one non‑mandatory deep dive review under IIAF.

Rozelle Interchange also underwent three mandatory gateway reviews at Gate 3 (part 1), Gate 3 (part 2), and Gate 4, two non‑mandatory health check reviews, and one non‑mandatory deep dive review under IIAF.

Since mid‑2017, the Sydney Gateway project has undergone required independent assurance reviews, as well as a number of optional assurance reviews

In November 2016, INSW conducted a mandatory Gate 1 gateway review on a strategic business case for the Sydney Gateway Project. TfNSW did not proceed with this business case. Following the separation of Sydney Gateway from WestConnex in mid‑2017, TfNSW developed a new business case for Sydney Gateway. It has undergone the required Gate 1, Gate 2, and Gate 3 gateway reviews, as well as two non‑mandatory health check reviews, and three non‑mandatory deep dive reviews under IIAF.

Network integration works have undergone all IIAF required assurance reviews

TfNSW completed a strategic business case for the Network Integration Program in August 2020, and INSW completed a gateway review in November 2020. This is despite network integration projects starting as early as 2015, with $645 million having been spent by June 2020. The strategic business case included a prioritisation process for completing remaining works in the program. Prior to November 2020, TfNSW registered individual network integration projects with INSW, and these projects have undergone gateway reviews where required.

The Network Integration Program strategic business case does not include Rozelle interchange network integration works ($353 million) and additional network integration works to settle a contractor claim adjacent to St Peters Interchange ($190 million). These were excluded from the business case on the basis they had already been approved by government, and as such were not subject to the prioritisation elements of the business case. TfNSW has not developed separate business cases for these works, although the scope of the St Peters Interchange works was developed through a negotiated process.

TfNSW did not prepare business cases for some network integration works which have commenced, including the $323 million Campbell Road/Euston Road works

Prior to its development of the August 2020 strategic business case, TfNSW did not prepare business cases for many network integration works that have commenced, and in some instances were completed, before 2019. Significantly, TfNSW did not prepare a business case for the Campbell Road/Euston Road works, which cost $323 million and have been completed.

In 2016, TfNSW’s Business Case Policy requires the creation of business cases for capital projects costing over $1.0 million. At the time of writing this report, TfNSW’s draft policy requires full business cases for capital projects costing $10.0 million or more.

There is no requirement for ongoing ‘whole‑of‑program’ assurance of the WestConnex program of works, including related projects

INSW conducted its first gateway review of WestConnex (as a program, which consisted of composite projects) in August 2015. Following that review, TfNSW registered each of the components of WestConnex with INSW as individual projects, rather than keeping WestConnex registered as a program or complex project. The IIAF allows this to occur.

Separate registration enabled INSW to report and review each stage with more scrutiny compared to whole‑of‑program level review.

Such an approach has merit, considering the individual stages (and components of these stages) are multi‑million dollar works in their own right. Each project has its own timing for gateway reviews at stages such as 'Readiness for Market' and 'Tender Evaluation'.

Once a program such as WestConnex is broken down into its composite parts, there is no requirement for the sponsor agency (TfNSW) or INSW to conduct independent assurance on the program of works as a whole until the whole program is completed as part of the Benefits Realisation (Gate 6) gateway review. The absence of strategic, holistic reviews of projects of the scale and complexity such as WestConnex during their delivery allows for total costs and benefits to become opaque and avoid scrutiny. Projects of this scale require greater ongoing transparency on total costs and benefits in order to ensure confidence they will meet intended objectives within budget.

INSW has advised us that it has prepared a proposal to expand its assurance function to include whole‑of‑program review of inter‑related infrastructure projects.

Appendix one – Responses from agencies

Appendix two – Network integration works

Appendix three – About the audit

Appendix four – Performance auditing

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #351 - released (17 June 2021).

Published

Actions for Transport 2020

Transport 2020

Transport
Asset valuation
Cyber security
Financial reporting
Information technology
Infrastructure
Project management

1. Financial Reporting

Audit opinion Unmodified audit opinions issued for the financial statements of all Transport cluster entities.
Quality and timeliness of financial reporting All cluster agencies met the statutory deadlines for completing the early close and submitting the financial statements.

Transport cluster agencies continued to experience some challenges with accounting for land and infrastructure assets. The former Roads and Maritime Services and Sydney Metro recorded prior period corrections to property, plant and equipment balances.
Impact of COVID-19 on passenger revenue and patronage Total patronage and revenue for public transport decreased by approximately 18 per cent in 2019–20 due to COVID-19.

The Transport cluster received additional funding from NSW Treasury during the year to support the reduced revenue and additional costs incurred such as cleaning on all modes of public transport and additional staff to manage physical distancing.
Completion of the CBD and South East Light Rail The CBD and South East Light Rail project was completed and commenced operations in this financial year. At 30 June 2020, the total cost of the project related to the CBD and South East Light Rail was $3.3 billion. Of this total cost, $2.6 billion was recorded as assets, whilst $700 million was expensed.

2. Audit Observations

Internal control While internal controls issues raised in management letters in the Transport cluster have decreased compared to the prior year, control weaknesses continue to exist in access security for financial systems. We identified 56 management letter findings across the cluster and 43 per cent of all issues were repeat issues. The majority of the repeat issues relate to information technology controls around user access management.

There were three high risk issues identified - two related to financial reporting of assets and one for implementation of TAHE (see below).
Agency responses to emergency events Transport for NSW established the COVID-19 Taskforce in March 2020 to take responsibility for the overall response of planning and coordination for the Transport cluster. It also implemented the COVIDSafe Transport Plan which incorporates guidance on physical distancing, increasing services to support social distancing and cleaning.
RailCorp transition to TAHE On 1 July 2020, RailCorp was renamed Transport Asset Holding Entity of New South Wales (TAHE) and converted to a for-profit statutory State-Owned Corporation. TAHE is a commercial for-profit Public Trading Entity with the intent to provide a commercial return to its shareholders.

A plan was established by NSW Treasury to transition RailCorp to TAHE which covered the period 1 July 2015 to 1 July 2019. A large portion of the planned arrangements were not implemented by 1 July 2020. As at the time of this report, the TAHE operating model, Statement of Corporate Intent (SCI) and other key plans and commercial agreements are not finalised. The State Owned Corporations Act 1989 generally requires finalisation of an SCI three months after the commencement of each financial year. However, under the Transport Administration Act 1988, TAHE received an extension from the voting shareholders, the Treasurer and Minister for Finance and Small Business, to submit its first SCI by 31 December 2020. In accordance with the original plan, interim commercial access arrangements were supposed to be in place with RailCorp prior to commencement of TAHE.

Under the transitional arrangements, TAHE is continuing to operate in accordance with the asset and safety management plans of RailCorp. The final operating model is expected to include considerations of safety, operational, financial and fiscal risks. This should include a consideration of the potential conflicting objectives of a commercial return, and maintenance and safety measures.

This matter has been included as a high risk finding in our management letter due to the significance of the financial reporting impacts and business risks for TAHE.

Recommendation: TAHE management should:
  • establish an operating model in line with the original intent of a commercial return
  • finalise commercial agreements with the public rail operators
  • confirm forecast financial information to assess valuation of TAHE infrastructure
  • finalise asset and safety management plans.

Resolution of the above matters are critical as they may significantly impact the financial reporting arrangements for TAHE for 2020–21, in particular, accounting policies adopted as well as measurement principles of its significant infrastructure asset base.

Completeness and accuracy of contracts registers Across the Transport cluster, contracts and agreements are maintained by the transport agencies using disparate registers.

Recommendation (repeat): Transport agencies should continue to implement a process to centrally capture all contracts and agreements entered. This will ensure:
  • agencies are fully aware of contractual and other obligations
  • appropriate assessment of financial reporting implications
  • ongoing assessments of accounting standards, in particular AASB 16 ‘Leases’, AASB 15 'Revenue from Contract with Customers', AASB 1058 'Income of Not-for-Profit Entities' and new accounting standard AASB 1059 'Service Concession Arrangements: Grantors' are accurate and complete.

 

This report provides parliament and other users of the Transport cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations
  • the impact of emergencies and the pandemic.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Transport cluster for 2020, including any financial implications from the recent emergency events.

Section highlights

  • Total patronage and revenue for public transport decreased by approximately 18 per cent in 2019–20 due to COVID-19.
  • Unqualified audit opinions were issued on all Transport agencies' financial statements.
  • Transport cluster agencies continued to experience challenges with accounting of land and infrastructure assets.

 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our:

  • observations and insights from our financial statement audits of agencies in the Transport cluster
  • assessment of how well cluster agencies adapted their systems, policies and procedures, and governance arrangements in response to recent emergencies.

Section highlights

  • While there was a decrease in findings on internal controls across the Transport cluster, 43 per cent of all issues were repeat issues. Many repeat issues related to information technology controls around user access management.
  • RailCorp transitioned to TAHE on 1 July 2020. TAHE's operating model and commercial arrangements with public rail operators has not been finalised despite government original plans to be operating from 1 July 2019. TAHE management should finalise its operating model and commercial agreements with public rail operators as they may significantly impact the financial reporting arrangements for TAHE for 2020–21.
  • Completeness and accuracy of contracts registers remains an ongoing issue for the Transport cluster.

Appendix one – List of 2020 recommendations

Appendix two – Status of 2019, 2018 and 2017 recommendations

Appendix three – Management letter findings

Appendix four – Financial data

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for CBD South East Sydney Light Rail: follow-up performance audit

CBD South East Sydney Light Rail: follow-up performance audit

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk
Service delivery

This is a follow-up to the Auditor-General's November 2016 report on the CBD South East Sydney Light Rail project. This follow-up report assessed whether Transport for NSW has updated and consolidated information about project costs and benefits.

The audit found that Transport for NSW has not consistently and accurately updated project costs, limiting the transparency of reporting to the public.

The Auditor-General reports that the total cost of the project will exceed $3.1 billion, which is above the revised cost of $2.9 billion published in November 2019. $153.84 million of additional costs are due to omitted costs for early enabling works, the small business assistance package and financing costs attributable to project delays.

The report makes four recommendations to Transport for NSW to publicly report on the final project cost, the updated expected project benefits, the benefits achieved in the first year of operations and the average weekly journey times.

Read full report (PDF)

The CBD and South East Light Rail is a 12 km light rail network for Sydney. It extends from Circular Quay along George Street to Central Station, through Surry Hills to Moore Park, then to Kensington and Kingsford via Anzac Parade and Randwick via Alison Road and High Street.

Transport for NSW (TfNSW) is responsible for planning, procuring and delivering the Central Business District and South East Light Rail (CSELR) project. In December 2014, TfNSW entered into a public private partnership with ALTRAC Light Rail as the operating company (OpCo) responsible for delivering, operating and maintaining the CSELR. OpCo engaged Alstom and Acciona, who together form its Design and Construct Contractor (D&C).

On 14 December 2019, passenger services started on the line between Circular Quay and Randwick. Passenger services on the line between Circular Quay and Kingsford commenced on 3 April 2020.

In November 2016, the Auditor-General published a performance audit report on the CSELR project. The audit found that TfNSW would deliver the CSELR at a higher cost with lower benefits than in the approved business case, and recommended that TfNSW update and consolidate information about project costs and benefits and ensure the information is readily accessible to the public.

In November 2018, the Public Accounts Committee (PAC) examined TfNSW's actions taken in response to our 2016 performance audit report on the CSELR project. The PAC recommended that the Auditor-General consider undertaking a follow-up audit on the CSELR project. The purpose of this follow-up performance audit is to assess whether TfNSW has effectively updated and consolidated information about project costs and benefits for the CSELR project.

Conclusion

Transport for NSW has not consistently and accurately updated CSLER project costs, limiting the transparency of reporting to the public. In line with the NSW Government Benefits Realisation Management Framework, TfNSW intends to measure benefits after the project is completed and has not updated the expected project benefits since April 2015.

Between February 2015 and December 2019, Transport for NSW (TfNSW) regularly updated capital expenditure costs for the CSELR in internal monthly financial performance and risk reports. These reports did not include all the costs incurred by TfNSW to manage and commission the CSELR project.

Omitted costs of $153.84 million for early enabling works, the small business assistance package and financing costs attributable to project delays will bring the current estimated total cost of the CSELR project to $3.147 billion.

From February 2015, TfNSW did not regularly provide the financial performance and risk reports to key CSELR project governance bodies. TfNSW publishes information on project costs and benefits on the Sydney Light Rail website. However, the information on project costs has not always been accurate or current.

TfNSW is working with OpCo partners to deliver the expected journey time benefits. A key benefit defined in the business plan was that bus services would be reduced owing to transfer of demand to the light rail - entailing a saving. However, TfNSW reports that the full expected benefit of changes to bus services will not be realised due to bus patronage increasing above forecasted levels.

Appendix one – Response from agency

Appendix two – Governance and reporting arrangements for the CSELR

Appendix three – 2018 CSELR governance changes

Appendix four – About the audit

Appendix five – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #335 - released 11 June 2020

Published

Actions for Train station crowding

Train station crowding

Transport
Management and administration
Risk
Service delivery
Workforce and capability

This report focuses on how Transport for NSW and Sydney Trains manage crowding at selected metropolitan train stations.

The audit found that while Sydney Trains has identified platform crowding as a key strategic risk, it does not have an overarching strategy to manage crowding in the short to medium term. Sydney Trains 'do not have sufficient oversight to know if crowding is being effectively managed’, the Auditor-General said.

Sydney Trains' operational response to crowding involves restricting customer access to platforms or station entries before crowding reaches unsafe levels or when it impacts on-time running. Assuming rail patronage increases, it is likely that Sydney Trains will restrict more customers from accessing platforms or station entries, causing customer delay. ‘Restricting customer access to platforms or station entries is not a sustainable approach to manage station crowding’, said the Auditor-General.

The Auditor-General made seven recommendations to improve Transport for NSW and Sydney Trains' management of station crowding. Transport for NSW have accepted these recommendations on behalf of the Transport cluster.

Public transport patronage has been impacted by COVID-19. This audit was conducted before these impacts occurred.

Read full report (PDF)

Sydney Trains patronage has increased by close to 34 per cent over the last five years, and Transport for NSW (TfNSW) expects the growth in patronage to continue over the next 30 years. As patronage increases there are more passengers entering and exiting stations, moving within stations to change services, and waiting on platforms. As a result, some Sydney metropolitan train stations are becoming increasingly crowded.

There are three main causes of station crowding:

  • patronage growth exceeding the current capacity limits of the rail network
  • service disruptions
  • special events.

Crowds can inhibit movement, cause discomfort and can lead to increased health and safety risks to customers. In the context of a train service, unmanaged crowds can affect service operation as trains spend longer at platforms waiting for customers to alight and board services which can cause service delays. Crowding can also prevent customers from accessing services.

Our 2017 performance audit, ‘Passenger Rail Punctuality’, found that rail agencies would find it hard to maintain train punctuality after 2019 unless they significantly increased the capacity of the network to carry trains and people. TfNSW and Sydney Trains have plans to improve the network to move more passengers. These plans are set out in strategies such as More Trains, More Services and in the continued implementation of new infrastructure such as the Sydney Metro. Since 2017, TfNSW and Sydney Trains have introduced 1,500 more weekly services to increase capacity. Additional network capacity improvements are in progress for delivery from 2022 onwards.

In the meantime, TfNSW and Sydney Trains need to use other ways of managing crowding at train stations until increased capacity comes on line.

This audit examined how effectively TfNSW and Sydney Trains are managing crowding at selected metropolitan train stations in the short and medium term. In doing so, the audit examined how TfNSW and Sydney Trains know whether there is a crowding problem at stations and how they manage that crowding.

TfNSW is the lead agency for transport in NSW. TfNSW is responsible for setting the standard working timetable that Sydney Trains must implement. Sydney Trains is responsible for operating and maintaining the Sydney metropolitan heavy rail passenger service. This includes operating, staffing and maintaining most metropolitan stations. Sydney Trains’ overall responsibility is to run a safe rail network to timetable.

Conclusion

Sydney Trains has identified platform crowding as a key strategic risk, but does not have an overarching strategy to manage crowding in the short to medium term. TfNSW and Sydney Trains devolve responsibility for managing crowding at stations to Customer Area Managers, but do not have sufficient oversight to know if crowding is being effectively managed. TfNSW is delivering a program to influence demand for transport in key precincts but the effectiveness of this program and its impact on station crowding is unclear as Transport for NSW has not evaluated the outcomes of the program.

TfNSW and Sydney Trains do not directly measure or collect data on station crowding. Data and observation on dwell time, which is the time a train waits at a platform for customers to get on and off trains, inform the development of operational approaches to manage crowding at stations. Sydney Trains has KPIs on reliability, punctuality and customer experience and use these to indirectly assess the impact of station crowding. TfNSW and Sydney Trains only formally assess station crowding as part of planning for major projects, developments or events.

Sydney Trains devolve responsibility for crowd management to Customer Area Managers, who rely on frontline Sydney Trains staff to understand how crowding affects individual stations. Station staff at identified key metropolitan train stations have developed customer management plans (also known as crowd management plans). However, Sydney Trains does not have policies to support the creation, monitoring and evaluation of these plans and does not systematically collect data on when station staff activate crowding interventions under these plans.

Sydney Trains stated focus is on providing a safe and reliable rail service. As such, management of station crowding is a by-product of its strategies to manage customer safety and ensure on-time running of services. Sydney Trains' operational response to crowding involves restricting customer access to platforms or stations before crowding reaches unsafe levels, or when it impacts on-time running. As rail patronage increases, it is likely that Sydney Trains will need to increase its use of interventions to manage crowding. As Sydney Trains restrict more customers from accessing platforms or station entries, it is likely these customers will experience delays caused by these interventions.

Since 2015, TfNSW has been delivering the 'Travel Choices' program which aims to influence customer behaviour and to manage the demand for public transport services in key precincts. TfNSW is unable to provide data demonstrating the overall effectiveness of this program and the impact the program has on distributing public transport usage out of peak AM and PM times. TfNSW and Sydney Trains continue to explore initiatives to specifically address crowd management.

Conclusion

TfNSW and Sydney Trains do not directly measure or collect data on station crowding. There are no key performance indicators directly related to station crowding. Sydney Trains uses performance indicators on reliability, punctuality and customer experience to indirectly assess the impact of station crowding. Sydney Trains does not have a routine process for identifying whether crowding contributed to minor safety incidents. TfNSW and Sydney Trains formally assess station crowding as part of planning for major projects, developments or events.

 

Conclusion

Sydney Trains has identified platform crowding as a strategic risk but does not have an overarching strategy to manage station crowding. Sydney Trains' stated focus is on providing a safe and reliable rail service. As such, management of station crowding is a by-product of its strategies to manage customer safety and ensure on-time running of services.

Sydney Trains devolve responsibility for managing crowding at stations to Customer Area Managers but does not have sufficient oversight to know that station crowding is effectively managed. Sydney Trains does not have policies to support the creation, monitoring or evaluation of crowd management plans at key metropolitan train stations. The use of crowding interventions is likely to increase due to increasing patronage, causing more customers to experience delays directly caused by these activities.

TfNSW and Sydney Trains have developed interventions to influence customer behaviour and to manage the demand for public transport services but are yet to evaluate these interventions. As such, their impact on managing station crowding is unclear.

Appendix one – Response from agency

Appendix two – Sydney rail network

Appendix three – Rail services contract

Appendix four – Crowding pedestrian modelling

Appendix five – Airport Link stations case study

Appendix six – About the audit

Appendix seven – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #333 - released 30 April 2020

 

Published

Actions for Transport 2019

Transport 2019

Transport
Asset valuation
Financial reporting
Infrastructure
Internal controls and governance
Management and administration
Service delivery
Workforce and capability

This report details the results of the financial audits of NSW Government's Transport cluster for the financial year ended 30 June 2019. The report focuses on key observations and findings from the most recent financial statement audits of agencies in the Transport cluster.

Unqualified audit opinions were issued for all agencies' financial statements. However, valuations of assets continue to create challenges across the cluster. The Audit Office identified some deficiencies in relation to asset valuations at Transport for NSW, Roads and Maritime Services, Rail Corporation New South Wales and Sydney Metro.

The Audit Office noted an increase in findings on internal controls across the Transport cluster. Key themes related to information technology, asset management and employee leave entitlements. The report also highlights the status of significant infrastructure projects across the Transport cluster.

The report makes several recommendations including:

  • agency finance teams need to be consulted on major business decisions and commercial transactions at the time of their execution to assess the financial reporting impacts
  • the Department of Transport should ensure consistent accounting policies are applied across its controlled entities.

Download the Transport 2019 report (PDF)

This report analyses the results of our audits of financial statements of the Transport cluster for the year ended 30 June 2019. The table below summarises our key observations.

1. Machinery of Government changes
Transport for NSW, as the
lead agency, will absorb the
functions of Roads and
Maritime Services

The NSW Government announced its intention to integrate Roads and Maritime Services (RMS) into Transport for NSW (TfNSW) as part of the Machinery of Government changes.

This change was not included in the Administrative Orders as the Transport Administration Act 1988 No. 109 governs the composition of the Transport cluster. The Transport Administration Amendment (RMS Dissolution) Act 2019 (the Act) received assent on 22 November 2019. The Act dissolves RMS and transfers the assets, rights and liabilities of RMS to TfNSW. As at the date of this Report, the Act is not yet in force.

Transport is considering the impact of the changes on its operating model and financial reporting.

2. Financial reporting
Audit opinions

Unqualified audit opinions were issued on the 2018–19 financial statements of all agencies in the Transport cluster.

TfNSW and Sydney Metro obtained a three-week extension from NSW Treasury to submit their financial statements for audit to resolve accounting issues surrounding the valuation of property, plant and equipment.

The Department of Transport reported total consolidated property, plant and equipment of $158 billion at 30 June 2019. In 2018–19, there were issues with asset valuations at TfNSW, RMS, Sydney Metro and Rail Corporation New South Wales (RailCorp), resulting in adjustments after the submission of financial statements for audit and the correction of a prior period error.

There was also a prior period error resulting from an agreement between TfNSW and the former UrbanGrowth Development Corporation due to a lack of assessment of the financial reporting implications at the time of signing the agreement.

Recommendation: Agency finance teams need to be consulted on major business decisions and commercial transactions to assess their accounting impacts at the time of their execution, rather than at the end of a financial year. Agencies also need to resolve all key accounting issues such as valuations as part of the early close procedures.

This would improve the quality of financial reporting and avoid the need for extensions for agencies to submit their financial statements for audit.

Preparedness for new
accounting standards
Agencies across the cluster are progressing in their implementation of the new accounting standards.

Transport cluster agencies need to improve their contracts registers to ensure they have a complete list of contracts and agreements to assess the impact of the new accounting standards.
Valuation of assets remains
a challenge in the
Transport cluster

Whilst agencies complied with the requirements of the accounting standards and NSW Treasury policies on valuations, the Audit Office identified some deficiencies in relation to asset valuations across the cluster.

TfNSW reported a retrospective correction of a prior period error at 1 July 2017 which resulted in a reduction in the valuation of its Country Rail Network earthworks by $2.1 billion. This was due to survey results which identified the earthworks were flatter and lower than estimated in the valuation at 30 June 2017.

RMS made several adjustments during the year to correct asset values due to changes to valuation assumptions or data improvements. This included:

  • reduction of $318 million in the value of land under roads
  • decrease of $84.9 million to the value of land and buildings
  • changes to the value of traffic control and traffic signal network assets, due to data improvements.

Sydney Metro North West officially opened in May 2019 and reported total assets of $9.1 billion. Sydney Metro derecognised $322 million in assets constructed to facilitate its operation but transferred to councils and utilities.

Inconsistent accounting
policies across the
Transport cluster

There was an inconsistency identified in the cluster relating to the valuation of substratum land. In 2018–19, RailCorp derecognised $109 million of substratum land to ensure consistency in its approach with other Transport agencies.

As the parent entity, the Department of Transport needs to ensure accounting policies are consistently applied across all controlled entities for consolidation purposes. Inconsistencies in the application of accounting standards across agencies will impact comparability of financial reporting and decision making across the Transport cluster.

Recommendation: The Department of Transport should ensure consistent accounting policies are applied across its controlled entities.

Revenue growth

Public transport passenger revenue increased by $89.0 million (5.9 per cent) in 2018–19, and patronage increased by 37.8 million (4.9 per cent) across all modes of transport based on data provided by TfNSW.

The increase in revenue is mainly due to an increase in patronage as well as the annual increase in fares.

Negative Opal cards

Negative balance Opal cards resulted in $2.9 million in revenue not collected in 2018–19 ($10.4 million since the introduction of Opal).

In January 2019, Transport made a change to the Sydney Airport stations to prevent customers with high negative balances exiting the station. In addition, in late 2018, Transport increased the minimum top up values for new cards at the airport stations.

Recommendation (repeat): TfNSW should implement further measures to prevent the loss of revenue from passengers tapping off with negative balance Opal cards.

3. Audit observations
Internal controls There was an increase in findings on internal controls across the Transport cluster. Key themes relate to information technology, employee leave entitlements and asset management.

Twenty-nine per cent of all issues were repeat issues. The majority of the repeat issues related to information technology controls.
Write-off of assets In addition to a $322 million derecognition of assets transferred to councils and utilities by Sydney Metro and a $109 million derecognition of substratum land at RailCorp, the Transport cluster wrote-off $278 million of assets related to roads, bridges, maritime assets, traffic signals and controls network.

These mainly related to roads, bridges, maritime assets, traffic signals and the control network where new infrastructure assets substantially replaced an existing asset as part of construction activities.
Transport Asset Holding
Entity (TAHE)
TAHE was established to be a dedicated asset manager for the delivery of public transport asset management. The Transport Administration Amendment (Transport Entities) Act 2017 will transition RailCorp into TAHE. RailCorp is now expected to transition to TAHE from 1 July 2020 (previously 1 July 2019). Several working groups have been considering various aspects of the TAHE transition including its status as a for profit Public Trading Enterprise, the operating model and the impact of the new accounting standards AASB 16 'Leases' and AASB 1059 'Service Concession Arrangements: Grantors'. The considerations of these aspects identified several challenges in the implementation of TAHE which has led to the revised transition date. Given the delays in implementation, it is important to clarify the intent of the TAHE model.
Excess annual leave

Twenty-six per cent of Transport employees have annual leave balances exceeding 30 days. Of the employees with excess leave balances, 732 (10.3 per cent) did not take any annual leave in 2018–19.

Recommendation (repeat): Transport entities should further review the approach to managing excess annual leave in 2019–20. They should:

  • monitor current and projected leave balances to the end of the financial year each month
  • agree formal leave plans with employees to reduce leave balances over an acceptable timeframe
  • ensure leave plans are actioned appropriately
  • encourage all staff with excess leave balances take a minimum two-week period of leave per year.
Completeness and
accuracy of contracts
registers

There are no centralised processes to record all significant contracts and agreements in a register across the Transport cluster.

Across the Transport cluster, contracts and agreements are maintained by the individual agencies using disparate registers. Agencies must perform detailed assessments of their existing contracts and agreements to quantify the impact of the new accounting standards (AASB 16 ‘Leases’, AASB 15 ‘Revenue from Contracts with Customers’, AASB 1058 ‘Income of Not-for-Profit Entities’ and AASB 1059 'Service Concession Arrangements: Grantors').

In 2018–19, there was also a prior period error resulting from an agreement between TfNSW and another government agency due to a lack of assessment of the financial reporting implications at the time of signing the agreement.

A lack of a complete register of all contracts and agreements increases the risk that agencies may not be able to assess the full impact of the new accounting standards, as well as perform a complete assessment of the financial reporting implications of contracts and agreements.

Recommendation: Transport agencies should implement a process to centrally capture all significant contracts and agreements entered. This will ensure:

  • agencies are fully aware of contractual and other obligations
  • appropriate assessment of financial reporting implications
  • assessment of new accounting standards, in particular AASB 16 ‘Leases’, AASB 15 'Revenue from Contract with Customers', AASB 1058 'Income of Not-for-Profit Entities ' and AASB 1059 'Service Concession Arrangements: Grantors' are accurate and complete.

 

This report provides parliament and other users of the Transport cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

This cluster was impacted by the Machinery of Government changes on 1 July 2019. The NSW Government announced its intention to integrate Roads and Maritime Services (RMS) into Transport for NSW (TfNSW). This report is focused on the Transport cluster prior to these changes. Please refer to the section on Machinery of Government changes for more details.

Machinery of Government refers to how the government organises the structures and functions of the public service. Machinery of Government changes are where the government reorganises these structures and functions, and are given effect by Administrative orders.

The Transport cluster was impacted by recent Machinery of Government changes. These changes were announced by the Department of Premier and Cabinet but were not included in the Administrative Orders as the Transport Administration Act 1988 No. 109 governs the composition of the Transport cluster. It was the intention of government to transfer the functions of the RMS into TfNSW. This requires legislative changes to the Transport Administration Act 1988 No. 109.

Section highlights

Under the Machinery of Government changes, the NSW Government will transfer the functions of RMS into TfNSW.

  • The Transport Administration Amendment (RMS Dissolution) Act 2019 (the Act) received assent on 22 November 2019.
  • The Act will dissolve RMS and transfer its functions, assets, rights and liabilities to TfNSW.
  • As at the date of this report, the Act is not yet in force.
  • There are risks and challenges for asset and liability transfers, governance and retention of knowledge.
  • As of 1 July 2019, administrative arrangements (delegations and reporting line changes) were put in place to enable TfNSW and RMS to operate within a single management structure, while still remaining as separate legal entities.
  • Transport is working on a number of options as to how to implement the changes. 

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Transport cluster for 2019.

Section highlights

  • Unqualified audit opinions were issued on all agencies' financial statements.
  • RMS required an extension from NSW Treasury for their early close procedures.
  • TfNSW and Sydney Metro required extensions to submit their year-end financial statements.
  • Valuation of assets remains a challenge across the cluster.
  • There remains Opal cards with negative balances.
  • Sydney Metro derecognised assets of $322 million in relation to assets constructed for third parties.
  • Inconsistencies in the application of accounting policies across cluster agencies impact comparability of financial reporting across the Transport cluster.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from our financial statement audits of agencies in the Transport cluster.

Section highlights

  • There was an increase in findings on internal controls across the Transport cluster. Twenty-nine per cent of all issues were repeat issues.
  • Transport entities wrote-off over $278 million of assets which were replaced by new assets or technology.
  • Twenty-six per cent of Transport employees have excess annual leave.
  • There are no processes to ensure all significant contracts and agreements are captured by agencies in a centralised register.

Appendix one – Timeliness of financial reporting by agency 

Appendix two – Management letter findings by agency 

Appendix three – List of 2019 recommendations 

Appendix four – Status of 2017 and 2018 recommendations 

Appendix five – Cluster agencies 

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.