Refine search Expand filter

Reports

Published

Actions for Government Advertising 2012-13

Government Advertising 2012-13

Premier and Cabinet
Health
Transport
Compliance
Procurement

The following report assessed the activities of the two agencies in relation to their government advertising campaigns in 2012-13 and tested compliance by tracking a campaign through from development to dissemination.

 

Parliamentary reference - Report number #236 - released 23 September 2013

Published

Actions for Building Energy Use in NSW Public Hospitals

Building Energy Use in NSW Public Hospitals

Health
Treasury
Planning
Environment
Internal controls and governance
Management and administration

NSW Health has reduced its energy use and greenhouse gas emissions by two per cent over the last four years. It is pleasing that annual emissions are now 15,000 tonnes less than they were four years ago. However, this was not sufficient to meet its target of an 11 per cent drop in emissions. 

Despite a reduction in energy use, energy cost in NSW Health has increased by nearly 50 per cent over the last four years to $120 million per annum. This is expected to increase by another 50 per cent in the next five years.

 

Parliamentary reference - Report number #231 - released 4 June 2013

Published

Actions for Managing Gifts and Benefits

Managing Gifts and Benefits

Planning
Finance
Transport
Environment
Compliance
Fraud
Internal controls and governance
Management and administration

Overall, the audited entities are managing some aspects of gifts and benefits effectively but other aspects require improvement. We found that all five entities had gifts and benefits policies that addressed some but not all of the attributes of a sound policy. All five have communicated their gifts and benefits policies to staff and external stakeholders, although in each case we identified opportunities to better communicate their policies.

 

Parliamentary reference - Report number #228 - released 27 March 2013

Published

Actions for Signal failures on the metropolitan rail network

Signal failures on the metropolitan rail network

Transport
Information technology
Infrastructure
Internal controls and governance
Project management
Risk
Service delivery

Between 2004 and 2006, the number of signalling failures, signalling downtime and the number of trains delayed as a result of signal failures all fell. RailCorp’s on-time running performance improved over the same period. The fall in failures is a clear indication of improved performance. Changes in the definition of on-time and to the timetable during 2005 and 2006 however make it difficult to determine whether improvements in response downtime and signalling delays are due to a true performance improvement. To build upon this strong base, RailCorp needs to determine with more confidence the number and duration of signalling failures the network can tolerate without impacting on service levels.

 

Parliamentary reference - Report number #170 - released 15 August 2007

Published

Actions for Connecting with public transport

Connecting with public transport

Transport
Information technology
Infrastructure
Internal controls and governance
Management and administration
Project management
Service delivery
Workforce and capability

We see considerable potential for the Ministry of Transport to plan and manage interchanges more effectively, so as to make better use of our public transport network. We believe that the Ministry now needs to focus more on multi-modal transport planning and interchange performance. It needs to assign responsibility for the coordination and oversight of inter-modal operations to an entity resourced for the purpose. Without this it will continue to be very difficult to identify and address unmet needs, seek and secure stakeholder funding, and monitor and evaluate system performance.

 

Parliamentary reference - Report number #168 - released 6 June 2007

Published

Actions for Managing Risk in the NSW Public Sector

Managing Risk in the NSW Public Sector

Transport
Management and administration
Risk

The Audit Office is of the opinion that, while agencies are aware of the need to manage risk, their risk management falls short of better practice. Many agencies do not consider their risk management to be adequate. The survey suggests that some agencies, mainly those in the Public Trading Enterprise Sector have approached risk management in a systematic way and in accordance with the principles of better practice standards. Others, mainly departments not subject to commercial imperatives, have yet to progress the management of risk beyond the traditional response of insuring against the more common types of risk. Thus there is a danger that with a number of agencies, risk may not be managed adequately, especially in the General Government Sector.

 

Parliamentary reference - Report number #98 - released 19 June 2002

Published

Actions for Bus Maintenance and Bus Contracts

Bus Maintenance and Bus Contracts

Transport
Management and administration
Procurement
Service delivery

State Transit has developed fleet management plans and maintenance standards that meet its regulatory and contractual obligations as a bus operator and are consistent with vehicle manufacturers’ standards and best practice. However, assumptions used in fleet management plans to forecast fleet growth may not result in the most efficient and effective outcome for State Transit. Forecasts fail to take account of opportunities to redesign or reduce services where they exceed contract requirements and are difficult to justify on a commercial basis. Of greater concern are the consequences arising from bus maintenance practices not meeting State Transit’s own standards.

 

Parliamentary reference - Report number #97 - released 29 May 2002