Reports
Actions for Transport 2016
Transport 2016
Financial reporting within the Transport Cluster continues to improve with reported misstatements down 96 per cent since 2011-12 to just three in 2015-16, according to a report released today by the NSW Auditor-General, Margaret Crawford.
Actions for CBD and South East Light Rail Project
CBD and South East Light Rail Project
Transport for NSW did not effectively plan and procure the CBD and South East Light Rail (CSELR) project to achieve best value for money according to a report released today by NSW Auditor-General, Margaret Crawford.
Transport for NSW is on track to deliver the project, but it will come at a higher cost with lower benefits than in the approved business case.
Parliamentary reference - Report number #278 - released 30 November 2016
Actions for Fraud Survey
Fraud Survey
In a report released today, the NSW Auditor-General, Margaret Crawford provides a snapshot of reported fraud in the NSW public sector and an analysis of NSW Government agencies’ fraud controls based on a survey of 102 agencies.
Actions for Implementation of the NSW Government’s program evaluation initiative
Implementation of the NSW Government’s program evaluation initiative
The NSW Government’s ‘program evaluation initiative’, introduced to assess whether service delivery programs achieve expected outcomes and value for money, is largely ineffective according to a report released today by NSW Auditor-General, Margaret Crawford.
Government services, in areas such as public order and safety, health and education, are delivered by agencies through a variety of programs. In 2016–17, the NSW Government estimates that it will spend over $73 billion on programs to deliver services.
Parliamentary reference - Report number #277 - released 3 November 2016
Actions for Franchising of Sydney Ferries Network services
Franchising of Sydney Ferries Network services
Franchising services on the Sydney Ferries Network was justified, and Transport for NSW’s management of the franchise has been largely effective according to a report released today by the NSW Acting Auditor-General, Tony Whitfield.
'Franchising has resulted in cost savings, good service performance, and effective risk transfer from government to the private sector operator', said Mr Whitfield.
Parliamentary reference - Report number #265 - released 4 February 2016
Actions for Condition of State Roads
Condition of State Roads
The Roads and Traffic Authority (RTA) has improved the overall surface condition of State Roads in the last decade. Country road surfaces are now generally much better. Ride quality has improved and cracking has been reduced. The RTA has also achieved a substantial reduction in the number of structurally deficient bridges over the same period.
Despite a significant increase in the State’s contribution to maintenance since 1999-2000, the RTA has deferred road rebuilding projects. The RTA is rebuilding at less than half its long term target, and has not met this target at any time this decade. The RTA has not identified how it will address deferred rebuilding, although it advises it is developing a new road network management plan which will address this.
Parliamentary reference - Report number #157 - released 16 August 2006
Actions for The Cross City Tunnel Project
The Cross City Tunnel Project
In our opinion the Government’s ‘no net cost to government’ requirement was a legitimate (but not the only possible) basis for the tunnel bid process. The Government was entitled to decide that tunnel users meet the tunnel costs. Structuring the bid process on the basis of an upfront reimbursement of costs incurred (or to be incurred) by the Roads and Traffic Authority (RTA) was therefore appropriate.
In our opinion, however, the Government, Treasury and the RTA did not sufficiently consider the implications of an upfront payment involving more than simple project cost reimbursement (i.e. the ‘Business Consideration Fee’ component). In addition, the RTA was wrong to change the toll escalation factor late in 2002 to compensate the tunnel operator, Cross City Motorway Pty Ltd, for additional costs.
Parliamentary reference - Report number #152 - released 31 May 2006
Actions for Agencies working together to improve services
Agencies working together to improve services
In the cases we examined, we found that agencies working together can improve services or results. However, the changes were not always as great as anticipated or had not reached maximum potential. Establishing the right governance framework and accountability requirements between partners at the start of the project is critical to success. And joint responsibility requires new funding and reporting arrangements to be developed.
Parliamentary reference - Report number #149 - released 22 March 2006
Actions for The New Schools Privately Financed Project
The New Schools Privately Financed Project
In our view the contracts in the New Schools Privately Financed Project were established and let in a way that greatly assists their potential for delivering value for money. The contracts in the New Schools Privately Financed Project are at an early stage of their 30 year lives and the savings and other benefits are not guaranteed. The contracts will need to be carefully managed over the 30 year period to ensure that benefits are realised and that costs do not escalate beyond expectations.
Parliamentary reference - Report number #148 - released 8 March 2006