Actions for CBD and South East Light Rail: follow-up performance audit

CBD and South East Light Rail: follow-up performance audit

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk
Service delivery

The CBD and South East Light Rail is a 12 km light rail network for Sydney. It extends from Circular Quay along George Street to Central Station, through Surry Hills to Moore Park, then to Kensington and Kingsford via Anzac Parade and Randwick via Alison Road and High Street. Transport for NSW (TfNSW) is responsible for planning, procuring and delivering the Central Business District and South East Light Rail (CSELR) project. In December 2014, TfNSW ent

Published

Actions for Destination NSW's support for major events

Destination NSW's support for major events

Treasury
Financial reporting
Management and administration
Procurement
Project management
Service delivery

This report focuses on whether Destination NSW (DNSW) can demonstrate that its support for major events achieves value for money. The audit found that DNSW’s processes for assessing and evaluating the major events it funds are mostly effective, but its public reporting does not provide enough transparency. DNSW provides clear information to event organisers seeking funding and has a comprehensive methodology for conducting detailed event assessments. H

Published

Actions for Volume Nine 2010 focus on Transport, Planning and Industry

Volume Nine 2010 focus on Transport, Planning and Industry

Transport
Planning
Industry
Asset valuation
Compliance
Internal controls and governance
Management and administration
Procurement
Project management
Regulation
Risk
Workforce and capability

The report includes comments on his financial audits of NSW Government transport, planning and industry agencies for 2009-10. A key recommendation from the report is that the New South Wales Government identify lessons learnt from the metro experience and ensure that future decision processes are developed to ensure the State never again expends such a large amount of scarce transport funding dollars and valuable time on a project that does not proceed.

Published

Actions for Coal Mining Royalties

Coal Mining Royalties

Industry
Treasury
Compliance
Internal controls and governance
Regulation

Department of Industry and Investment cannot assure the people of NSW that all royalties owed are being paid in full. This is because it does not have sufficiently robust systems and processes to identify what is owed and to make sure it is paid.   Parliamentary reference - Report number #208 - released 30 November 2010

Published

Actions for Volume Five 2010 focus on Public Financing Enterprises

Volume Five 2010 focus on Public Financing Enterprises

Industry
Transport
Finance
Treasury
Planning
Financial reporting
Information technology
Internal controls and governance
Management and administration
Regulation
Risk
Workforce and capability

The report includes comments on NSW Treasury and agencies in the finance and superannuation sectors. The New South Wales public sector superannuation funds’ investments were $42.2 billion at 30 June 2010, up from $38.5 billion in 2009. Investment returns reached 14.5 per cent in 2009-10. This is a significant improvement on the investment returns of up to negative 18.4 per cent at the peak of the global financial crisis in 2008.  

Published

Actions for Improving the Performance of Metropolitan Bus Services

Improving the Performance of Metropolitan Bus Services

Transport
Internal controls and governance
Management and administration
Procurement
Service delivery

The 2004 Review of Bus Services in NSW always envisaged that there would be a transition period as the new bus contracts were introduced. NSWTI has developed and implemented the new arrangements, and pursued a range of new initiatives including the network improvement program, strategic corridors and uniform bus fares and concessions. The new contracts provided for a performance management regime to hold operators accountable. But this is still being dev

In progress

Actions for WestConnex: Changes since 2014

WestConnex: Changes since 2014

Transport
Compliance
Financial reporting
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk
Service delivery

The WestConnex project is a motorway project that will link the M4 and M5 motorways with 33km of new motorway tunnels in Sydney. We conducted a performance audit of the WestConnex business case review process in 2014. Since then, the scope and projects included in WestConnex have changed. This audit will assess whether Transport for NSW and Infrastructure NSW effectively assessed and justified major scope changes to the WestConnex project since December