Actions for WestConnex: Assurance to the Government
WestConnex: Assurance to the Government
This audit assesses the assurance provided to the NSW Government for the initial stages of the WestConnex project.
The audit examined the WestConnex project from concept development to the pre-tender phase for Stage 1A – M4 (Parramatta to Homebush Bay). It did not examine the merit of the project or whether it represented value-for-money.
This audit found a number of shortcomings with the governance of the WestConnex project during its early stages and makes recommendations on how to better govern the remainder of the project to minimise the risk of failure.
Parliamentary reference - Report number #247 - released 18 December 2014
Actions for Volume Ten 2014 Focusing on Treasury and Finance (including Superannuation and Insurance)
Volume Ten 2014 Focusing on Treasury and Finance (including Superannuation and Insurance)
The quality of financial reporting in the Finance and Treasury cluster continues to improve with fewer reported misstatements over the last three years. The financial statements of all cluster agencies received unqualified audit opinions, except for the New South Wales Self Insurance Corporation.
Actions for Volume Seven 2014 Focusing on Transport
Volume Seven 2014 Focusing on Transport
All agencies in transport cluster received unqualified audit opinions for the year ended 30 June 2014. The quality of financial reporting continues to improve with the number of misstatements identified during audits falling for the fifth year in a row.
Actions for Volume Four 2014 focusing on New South Wales State Finances
Volume Four 2014 focusing on New South Wales State Finances
For the second consecutive year, the General Government and Total State Sector Accounts received an unqualified auditor’s opinion following more than a decade of qualifications. The quality and timeliness of financial reporting across the NSW public sector has continued to improve. Compared to previous years, there were fewer errors in agencies’ 2013–14 financial statements submitted for audit and used for whole-of-government financial reporting.
Actions for Use of Purchasing Cards and Electronic Payment Methods
Use of Purchasing Cards and Electronic Payment Methods
NSW government agencies are not making sufficient use of purchasing cards and EFTs to pay for goods and services. There are potential savings in processing costs of around $22 per transaction from purchasing cards and over $7 when using EFTs instead of cheques.
Parliamentary reference - Report number #243 - released 5 June 2014
Actions for Regional Road Funding - Block Grant and REPAIR Programs
Regional Road Funding - Block Grant and REPAIR Programs
In 2013–14, Roads and Maritime Services (RMS) provided over $170 million to local councils through the Block Grant and REPAIR programs to spend on Regional Roads. Regional Roads are the link between State Roads and Local Roads.
Parliamentary reference - Report number #241 - released 8 May 2014
Actions for Volume One 2014 - Areas of focus from 2013
Volume One 2014 - Areas of focus from 2013
Today the Auditor-General of New South Wales, Grant Hehir, released his Volume One Report to Parliament for 2014. The observations included in this report are designed to inform readers of common findings from the 2013 financial and performance audits so agencies and audit committees can use them to identify issues that may be relevant to their organisations.
Actions for Condition of State Roads
Condition of State Roads
The Roads and Traffic Authority (RTA) has improved the overall surface condition of State Roads in the last decade. Country road surfaces are now generally much better. Ride quality has improved and cracking has been reduced. The RTA has also achieved a substantial reduction in the number of structurally deficient bridges over the same period.
Despite a significant increase in the State’s contribution to maintenance since 1999-2000, the RTA has deferred road rebuilding projects. The RTA is rebuilding at less than half its long term target, and has not met this target at any time this decade. The RTA has not identified how it will address deferred rebuilding, although it advises it is developing a new road network management plan which will address this.
Parliamentary reference - Report number #157 - released 16 August 2006
Actions for The Cross City Tunnel Project
The Cross City Tunnel Project
In our opinion the Government’s ‘no net cost to government’ requirement was a legitimate (but not the only possible) basis for the tunnel bid process. The Government was entitled to decide that tunnel users meet the tunnel costs. Structuring the bid process on the basis of an upfront reimbursement of costs incurred (or to be incurred) by the Roads and Traffic Authority (RTA) was therefore appropriate.
In our opinion, however, the Government, Treasury and the RTA did not sufficiently consider the implications of an upfront payment involving more than simple project cost reimbursement (i.e. the ‘Business Consideration Fee’ component). In addition, the RTA was wrong to change the toll escalation factor late in 2002 to compensate the tunnel operator, Cross City Motorway Pty Ltd, for additional costs.
Parliamentary reference - Report number #152 - released 31 May 2006
Actions for Agencies working together to improve services
Agencies working together to improve services
In the cases we examined, we found that agencies working together can improve services or results. However, the changes were not always as great as anticipated or had not reached maximum potential. Establishing the right governance framework and accountability requirements between partners at the start of the project is critical to success. And joint responsibility requires new funding and reporting arrangements to be developed.
Parliamentary reference - Report number #149 - released 22 March 2006