Refine search Expand filter

Reports

Published

Actions for Volume Eight 2013 focusing on Transport and Ports

Volume Eight 2013 focusing on Transport and Ports

Transport
Industry
Compliance
Financial reporting
Procurement
Project management
Regulation
Workforce and capability

Unqualified audit opinions were issued on the above corporations’ 30 June 2013 financial statements. During the year, Treasury issued TC 13/01 ‘Mandatory early close procedures for 2013’. This Circular aimed to improve the quality and timeliness of agencies’ annual financial statements. In 2012-13, application of the circular was made mandatory for State owned corporations. As a result, the port corporations were required to perform the early close procedures. All the port corporations were successful in performing the procedures, which helped them submit financial statements by an earlier due date. The early close procedures also resulted in general improvements to the quality of most financial statements.

The report recommends all transport entities should do more to reduce excessive annual leave balances to ensure they will comply with new targets set by the Premier, RailCorp, Sydney Trains and NSW Trains should minimise the amount of overtime bonuses paid to train drivers and that Transport for NSW should set targets to measure the overall satisfaction of train users.

Published

Actions for Volume Seven 2013 focusing on Superannuation and Insurance

Volume Seven 2013 focusing on Superannuation and Insurance

Finance
Treasury
Compliance
Cyber security
Information technology
Management and administration
Procurement
Project management
Shared services and collaboration

Unqualified audit opinions were issued on the NSW Government controlled insurance and compensation entities’ 30 June 2013 financial statements, except the NSW Self Insurance Corporation (SICorp). SICorp’s audit opinion was qualified due to non-compliance with Australian Accounting Standards applicable to general insurance contracts. The auditor’s reports drew attention to the significant uncertainty in estimating outstanding claims liabilities of $14.0 billion in the Workers’ Compensation Nominal Insurer and $2.1 billion in the Lifetime Care and Support Authority. The audit of the Building Insurers’ Guarantee Corporation was not complete at the time of this report and is excluded from this commentary. 

Published

Actions for Government Advertising 2012-13

Government Advertising 2012-13

Premier and Cabinet
Health
Transport
Compliance
Procurement

The following report assessed the activities of the two agencies in relation to their government advertising campaigns in 2012-13 and tested compliance by tracking a campaign through from development to dissemination.

 

Parliamentary reference - Report number #236 - released 23 September 2013

Published

Actions for Bus Maintenance and Bus Contracts

Bus Maintenance and Bus Contracts

Transport
Management and administration
Procurement
Service delivery

State Transit has developed fleet management plans and maintenance standards that meet its regulatory and contractual obligations as a bus operator and are consistent with vehicle manufacturers’ standards and best practice. However, assumptions used in fleet management plans to forecast fleet growth may not result in the most efficient and effective outcome for State Transit. Forecasts fail to take account of opportunities to redesign or reduce services where they exceed contract requirements and are difficult to justify on a commercial basis. Of greater concern are the consequences arising from bus maintenance practices not meeting State Transit’s own standards.

 

Parliamentary reference - Report number #97 - released 29 May 2002

Published

Actions for Government office accommodation

Government office accommodation

Treasury
Finance
Asset valuation
Management and administration
Procurement

The Audit Office has undertaken an audit on Government Office Accommodation. The audit examined the cost effectiveness of long-term leasing versus ownership and the housing of agencies involved with the delivery of core government activities.  Core activities are those intrinsically linked to basic and ongoing functions of Government and Parliament.

It recommends that:

  • the Government consider owning office accommodation, as opposed to leasing, for its long-term core needs, subject to a case by case analysis of the relevant financial and nonfinancial factors

  • the Government undertake an analysis of the costs/savings from proposed asset sales of office accommodation in light of the demonstrated need for long-term office accommodation (for core needs) New, Expired and Expiring Leases

  • given the findings of the own versus lease case studies presented in this report, it is recommended that the Government require agencies to undertake, in collaboration with the Department of Public Works and Services (DPWS) a cost/benefit analysis of available accommodation options prior to committing to any proposed major new leases

  • the Government direct the DPWS, in collaboration with all agencies, to negotiate the renewal of all major expired/expiring leases (where continued occupancy is warranted) in order to reduce the financial risk of above-market rent increases and the risk of cancellation of leases (Major leases are defined, for the purposes of these recommendations, to be those over $500,000 rental per annum or a net lettable area over 1,000 square metres) Management of Property Information

  •  in order to improve the integrity of the Government Office Accommodation Database, agencies be required to respond to the annual data request from DPWS by a predetermined date

  • a senior officer within each agency be required to certify to the accuracy of information provided by an agency as input to the database maintained by DPWS

  • DPWS verify, on a sample basis, information provided by agencies as input to the Government Office Accommodation Database Premier’s Memorandum No 97-2

  • the compliance by agencies with Premier’s Memorandum No 97-2 Government Office Accommodation and Property Disposal be established by DPWS.

 

Parliamentary reference - Report number #45 - released 11 December 1997

Published

Actions for Review of Eastern Distributor

Review of Eastern Distributor

Transport
Infrastructure
Procurement
Project management

Following a resolution of the Legislative Council, the Audit Office has undertaken a performance audit of the Eastern Distributor. For a number of reasons, The Audit Office is not in the position to determine “whether the proposed toll and concession period represents the best deal”. In part this is the result of time constraints which do not allow a careful analysis of many toll and concession options. Similarly, the audit does not answer “whether the current proposal represents the best environmental outcome”. But each of these issues (toll and concession and environmental consequences) is discussed in the audit report.

The Audit Office recommends that the Roads and Traffic Authority (RTA), for any further major project of this type, ensures that it establishes a process which allows all decision makers to have a thorough understanding of the reasonableness of the proponents’ offers and their implications for the State and for the public. The Audit Office also recommends that the RTA should at the outset consult with TCorp in respect of each major project put to tender.

 

Parliamentary reference - Report number #42 - released 31 July 1997