What this report is about

Transport for NSW (TfNSW) uses the Driver vehicle System (DRIVES) to support its regulatory functions. The system covers over 6.2 million driver licences and over seven million vehicle registrations.

DRIVES first went live in 1991 and has been significantly extended and updated since, though is still based around the same core system. The system is at end of life but has become an important service for Service NSW and the NSW Police Force.

DRIVES now includes some services to other parts of government and non-government entities which have little or no connection to transport. There are 141 users of DRIVES in total, including commercial insurers, national regulators, and individual citizens.

This audit assessed whether TfNSW is effectively managing DRIVES and planning to transition it to a modernised system.

Audit findings

TfNSW has not effectively planned the replacement of DRIVES.

It is now working on its third business case for a replacement system but has failed to learn lessons from its past attempts.

In the meantime, TfNSW has not taken a strategic approach to managing DRIVES’ growth.

TfNSW has been slow to reduce the risk of misuse of personal information held in DRIVES. With its delivery partner Service NSW, TfNSW has also been slow to develop and implement automatic monitoring of access.

TfNSW uses recognised processes for managing most aspects of DRIVES, but has not kept the system consistently available for users. TfNSW has lacked accurate service availability information since June 2022, when it changed its technology support provider.

TfNSW needs to significantly prioritise cyber security improvements to DRIVES. TfNSW is seeking to lift DRIVES’ cyber defences, but it will not achieve its stated target safeguard level until December 2025.

Even then, one of the target safeguards will not be achieved in full until DRIVES is modernised.

Audit recommendations

TfNSW should:

  • implement a service management framework including insight into the views of DRIVES users, and ensuring users can influence the service
  • ensure it can accurately and cost effectively calculate when DRIVES is unavailable due to unplanned downtime
  • ensure implementation of a capability to automatically detect anomalous patterns of access to DRIVES
  • ensure that DRIVES has appropriate cyber security and resilience safeguards in place as a matter of priority
  • develop a clear statement of the future role in whole of government service delivery for the system
  • resolve key issues currently faced by the DRIVES replacement program including by:
    • clearly setting out a strategy and design for the replacement
    • preparing a specific business case for replacement.

Read the PDF report

Parliamentary reference - Report number #388 - released 20 February 2024

Published

Actions for Regional road safety

Regional road safety

Transport
Health
Community Services
Internal controls and governance
Management and administration
Project management
Risk

What this report is about

Around one-third of the state’s population lives in regional NSW, but deaths on regional roads make up around two-thirds of the state’s road toll.

Transport for NSW (TfNSW) is responsible for managing road safety outcomes across the NSW road network. This audit assessed the effectiveness of TfNSW’s delivery of road safety strategies, plans and policies in regional areas.

The NSW Road Safety Action Plan 2022–2026 has the stated goal of ‘no death or serious injury occurring on the road transport network’ by 2050.

What we found

There is a disproportionate amount of trauma on regional roads, but there are no specific road safety plans or trauma reduction targets for regional NSW.

TfNSW advises that the setting of state-wide road safety targets is consistent with other jurisdictions and international best practice. However, the proportion of road fatalities and serious injuries in regional NSW is almost the same as ten years ago.

There is no regional implementation plan to assist TfNSW to target the Road Safety Action Plan 2026 to regional areas.

TfNSW considers that local road safety outcomes should be managed by councils, but only 52% of regional councils participated in its Local Government Road Safety Program (LGRSP) in 2022–23. This program has not been updated since 2014, despite commitments to do so in 2021 and 2022.

TfNSW has not undertaken a systematic and integrated analysis of the combined impact of its road safety strategies and plans in regional NSW since 2012.

TfNSW reports against the Community Road Safety Fund (CRSF) annually but there is no consolidated, public reporting on total road safety funding allocated to regional NSW. The Fund underspend increased from 12% in 2019–20 to 20% in 2022–23.

What we recommended

We recommended TfNSW:

  • develop a regional implementation plan to support the NSW Road Safety Action Plan, including a framework to annually measure, analyse and publicly report on progress
  • develop a plan to measure and mitigate risks causing underspend in the CRSF
  • expedite the review of the LGRSP including recommendations to increase involvement of regional councils.

Disclosure of confidential information

Under the Government Sector Audit Act 1983 (the Act), the Auditor-General may disclose confidential information if, in the Auditor-General’s opinion, the disclosure is in the public interest, and that disclosure is necessary for the exercise of the Auditor-General’s functions.

Confidential information in the Act means Cabinet information or information subject to legal privilege. This performance audit report contained confidential information.

The NSW Premier has certified that in his opinion the disclosure of the confidential information was not in the public interest.

The confidential information has been redacted from this report.

Under section 36A(2) of the Government Sector Audit Act 1983, the Auditor-General may authorise the disclosure of confidential information if, in the Auditor-General’s opinion, the disclosure is in the public interest and necessary for the exercise of the Auditor-General’s functions. Confidential information under the Government Sector Audit Act 1983 means Cabinet information, or information that could be subject to a claim of privilege by the State or a public official in a court of law. This performance audit report contained confidential information which, in the opinion of the Auditor-General, is in the public interest to disclose and that disclosure is necessary for the exercise of the Auditor-General’s functions.

On 26 October 2023, pursuant to section 36A(2)(b) of the Government Sector Audit Act 1983, the Auditor-General notified the NSW Premier of the intention to include this information in the published report, having formed the opinion that its disclosure is in the public interest and is necessary for the exercise of the Auditor-General’s functions.

On 23 November 2023, pursuant to section 36A(2)(c) of the Government Sector Audit Act 1983, the NSW Premier certified that, in his opinion, the proposed disclosure of the confidential information contained in this report was not in the public interest. The Premier’s certificate follows. Section 36A(4) states that a certificate of the Premier that it is not in the public interest to disclose confidential information is conclusive evidence of that fact.

The issuance of the certificate by the NSW Premier prevents the publication of this information. The relevant sections of the report containing confidential information have been redacted.

One-third of the New South Wales population resides in regional areas, but two-thirds of the state’s road crash fatalities take place on regional roads.

Between 2017 and 2021, the average number of fatalities for every 100,000 of the population living in regional New South Wales was 8.33 — approximately four times higher than the equivalent measure for Greater Sydney. Similarly, the average number of serious injuries in regional New South Wales over the same period was 75.24 per 100,000 of the population, compared with 50.53 in Greater Sydney. Further, more than 70% of people who lose their lives in accidents on regional roads are residents of regional areas.

Residents of regional areas face particular transport challenges. They often need to travel longer distances for work, health care, or recreation purposes, yet their public transport options are more limited than metropolitan residents. Vehicle safety is also an issue. According to the NSW Road Safety Progress Report 2021, of the light vehicles registered in New South Wales that were manufactured in or after 2000, 48.4% of light vehicles in regional areas had a five-star Australasian New Car Assessment Program (ANCAP) rating, compared to 54.8% in metropolitan areas. Road conditions in regional areas can also be more challenging for drivers.

Regional New South Wales covers 98.5% of the total area of the state. The road network in New South Wales is vast — spanning approximately 200,000 kilometres.

The road network includes major highways, state roads and local roads. Speed limits range from 10 km/hr in high pedestrian shared zones, up to 110 km/hr on high volume and critical road corridors. Eighty per cent of the network has a 100 km/h speed limit, which is mostly applied as a default speed limit, regardless of the presence of safety features and treatments.

Speed is the primary causal factor in more crashes in New South Wales than any other factor, and car crashes in regional areas are more likely to be fatal because of the higher average speeds involved.

The responsibility for managing road safety outcomes across the entire New South Wales road network lies with Transport for NSW (TfNSW), pursuant to Schedule 1 of the Transport Administration Act 1988.

While its safety responsibilities are state-wide, TfNSW does not own or directly manage all of the road network in regional New South Wales, which spans approximately 200,000 kilometres. Approximately 80% of the roads are classified as Local Roads and are administered and managed by local councils. Local councils also maintain Regional Roads that run through their local government areas. TfNSW is responsible for managing State Roads (approximately 20% of roads), which are major arterial roads. It also provides funding for councils to manage over 18,000 km (approximately 10%) of state-significant Regional Roads.

According to TfNSW, between 2016 and 2020, there were 9,776 people killed or seriously injured on roads in regional New South Wales. Adding to the tragic loss of life, according to TfNSW, the estimated cost to the community between 2016 and 2020 resulting from regional road trauma and fatalities was around $13.7 billion.

TfNSW also noted that the ‘risk of road trauma is pervasive, and a combination of effective road safety measures is required to systematically reduce this risk’.

TfNSW released its first long-term road-safety strategy in December 2012, which introduced the goal of ‘Vision Zero’ — a long-term goal of zero deaths or serious injuries on NSW roads. The terminology was changed to ‘Towards Zero’ in the 2021 Road Safety Plan and has been retained in the NSW Road Safety Action Plan 2022–2026. Towards Zero has the stated goal of ‘no death or serious injury occurring on the road transport network’ by 2050.

The objective of this audit is to assess the effectiveness of TfNSW’s delivery of ‘Towards Zero’ in regional areas.

In making this assessment, the audit examined whether TfNSW:

  • is effectively reducing the number of fatalities and serious injuries on regional roads
  • has an effective framework, including governance arrangements, for designing and refreshing the NSW Road Safety Strategy 2012–2021 and the NSW Road Safety Action Plan 2022–2026
  • effectively makes use of whole-of-government and other relevant sources of data to support decision-making, and to evaluate progress and outcomes
  • effectively manages accountabilities, including roles and responsibilities, with respect to road safety outcomes and the use of data.

This audit focused on the policies and strategies used by TfNSW for managing road safety outcomes in regional areas. We did not evaluate individual road safety projects, programs and initiatives as part of this audit.

Whilst Regional Roads and Local Roads (as defined by the Road Network Classifications) are owned and maintained by local councils, we included these roads in this audit as TfNSW may advise and assist councils to promote and improve road safety, as well as manage grant programs that focus on improving road safety outcomes on these roads. Hereafter, unless otherwise stated, references to ‘regional roads’ refer to all classifications of roads in the state which are in regional New South Wales, irrespective of their ownership.

Local councils in regional areas are key stakeholders for the purposes of this audit, and we interviewed eight as part of the audit process (noting that this was not intended to be a representative sample). Road asset management by local councils is also out of scope for this audit as it is the focus of a subsequent performance audit by the Audit Office of New South Wales.b

The Audit Office of New South Wales has undertaken several performance audits relating to road safety since 2009 and these have been referenced while undertaking this audit. They include:

  • Condition of State Roads (August 2006)
  • Improving Road Safety: Heavy Vehicles (May 2009)
  • Improving Road Safety: School Zones (March 2010)
  • Improving Road Safety: Speed Cameras (July 2011)
  • Regional Assistance Programs (May 2018)
  • Mobile speed cameras (October 2018)
  • Rail freight and Greater Sydney (October 2021).

Conclusion

TfNSW has acknowledged that there is a disproportionate amount of road trauma on regional roads in the NSW Road Safety Strategy 2012–2021, the NSW Road Safety Plan 2021, and the NSW Road Safety Action Plan 2022–2026. However, TfNSW has not articulated or evaluated a strategy for implementing road safety policy in regional New South Wales to assist in guiding targeted activities to address regional road trauma. There is also no transparency about the total amount of funding invested in improving road safety outcomes for regional New South Wales.

People living in regional New South Wales make up one-third of the state’s population, but deaths on regional roads make up around two-thirds of the state’s total road toll. This statistic is almost the same in 2023 as it was ten years ago when TfNSW released its first long-term road safety strategy.

More than 70% of people who died on roads between 2012 and 2022 in regional New South Wales were residents of regional areas. Speed is the greatest contributing factor to road fatalities and serious injuries across the entire state. However, it is responsible for more fatalities on regional roads (43%) than in Greater Sydney (34%).

TfNSW’s road safety strategies and plans acknowledge that most road fatalities occur in regional New South Wales but none of its existing strategies or plans show evidence of tailoring measures to suit particular regional settings or ‘hot spots’. There are infrastructure initiatives (such as Saving Lives on Country Roads) and behavioural programs targeting regional areas (such as Driver Reviver). However, these activities are not aligned to a regional-specific strategy or plan that addresses issues specific to regional areas.

TfNSW has state-wide responsibility for managing road safety outcomes. TfNSW advised the audit that a regional plan and regional trauma reduction targets are not needed as the state-wide plan and targets apply equally for all areas of New South Wales, and local road safety factors are best managed by local councils. TfNSW partners with local councils. However, only 52% of councils in regional New South Wales participate in TfNSW’s Local Government Road Safety Program, compared to 84% of councils in metropolitan areas. TfNSW has not undertaken any evaluations to determine whether projects completed under the Local Government Road Safety Program have reduced road trauma at the local level.

Notwithstanding the above points, TfNSW works with local councils (who are road authorities for local roads in their respective areas under the Roads Act 1993) and other key stakeholders such as the NSW Police Force to achieve the NSW Government’s road safety policy objectives.

TfNSW advised that ‘the setting of state-wide road safety targets is consistent with other jurisdictions and international best practice. Importantly, delivery of road safety countermeasures is tailored and applied with a focus on road user groups across all geographic locations to maximise trauma reductions’. There may be legitimate reasons for the existing approach, as articulated by TfNSW. However, the proportion of road fatalities in regional New South Wales roads has not reduced since 2012 – despite a long-term reduction in the overall number of deaths on the state’s roads between 2012–2021. The audit report has recommended that a regionally focused implementation plan could address this issue. TfNSW has accepted this report’s recommendation that such a plan be developed.

Specific road safety initiatives targeted to regional areas have not been implemented or expanded

Text removed pursuant to section 36A of the Government Sector Audit Act 1983 (NSW), in compliance with the issuance of a Premier’s certificate preventing the publication of this information.

TfNSW increased the use of other forms of automated enforcement (such as tripling enforcement hours in mobile speed cameras).
However, the use of automated enforcement has a strong metropolitan focus with most red light and fixed speed cameras being in metropolitan areas. Average speed cameras are the only camera type overwhelmingly located in regional areas but these apply only to heavy vehicles and are positioned on major freight routes. 

There is no consolidated, public reporting of what proportion of total road safety funding is directed to regional New South Wales each year. The main source of funding for road safety in New South Wales, the Community Road Safety Fund, has been underspent since 2019.

Fines from camera-detected speeding, red-light and mobile phone use offences are required to be used solely for road safety purposes through the Community Road Safety Fund (CRSF), as set out in the Transport Administration Amendment (Community Road Safety Fund) Act 2012.

The CRSF has been underspent every year since 2019–20. The underspend has increased from 12% in 2019–20 to 20% in 2022–23 where the full year underspend was forecasted to be $104 million. Of this underspend, $13.5 million was dedicated for regional road infrastructure projects. TfNSW advised the audit that much of the underspend is the result of delays to infrastructure projects due to COVID-19, bushfires, and floods, as well as skills shortages. However, TfNSW has not provided any evidence that it had a plan to mitigate these risks – meaning the level of underspend could continue to grow. TfNSW also advised ‘there is no reason to expect budget management and controls will not return to pre-COVID circumstances’.

In total, TfNSW received $700 million in funding for road safety in 2021–22 (including federal contributions and the Community Road Safety Fund). Of this, $411 million (or ~59%) was directed to regional New South Wales. This is the most recent comprehensive financial data that was provided by TfNSW to the audit team. The 2022–23 NSW Budget allocated $880 million for road safety in 2022–23, with a forecasted total allocation for road safety of $1.6 billion in recurrent expenses and $0.8 billion in capital expenditure over the period 2022–23 to 2025–26.

Appendix one – Response from Transport for NSW

Appendix two – The Safe Systems framework and NSW road safety strategies and plans

Appendix three – About the audit

Appendix four – Performance auditing

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #386 - released 30 November 2023

Published

Actions for NSW government agencies' use of consultants

NSW government agencies' use of consultants

Treasury
Whole of Government
Compliance
Internal controls and governance
Management and administration
Procurement
Workforce and capability

What the report is about

This audit assessed how effectively NSW government agencies procure and manage consultants. It examined the role of the NSW Procurement Board and NSW Procurement (a unit within NSW Treasury) in supporting and monitoring agency procurement and management of consultants.

The audit used four sources of data that contain information about spending on consultants by NSW government agencies, including annual report disclosures and the State's financial consolidation system (Prime). It also reviewed a sample of consulting engagements from ten NSW government agencies.

What we found

Our review of a selection of consulting engagements indicates that agencies do not procure and manage consultants effectively.

We found most agencies do not use consultants strategically and do not have systems for managing or evaluating consultant performance. We also found examples of non-compliance with procurement rules, including contract variations that exceeded procurement thresholds.

NSW Procurement has made improvements to the information available about spending on consultants, including additional analysis and reporting. However, there is no single data source that accurately captures spending on consultants.

Our analysis of data on whole-of-government spending on consultants, drawn from agency annual reports, indicates that four large professional services firms accounted for about a quarter of consultancy expenditure from 2017–18 to 2021–22. This concentration increases strategic risks, including over-reliance on a limited number of providers and potential reduction in the independence of advice.

It is also highly unlikely that NSW government agencies will meet the government's 2019 policy commitment to reduce consultancy expenses by 20% each year, over four years, from 2019–20. NSW Treasury advised that to implement this commitment, agency budgets were reduced in Prime in line with the savings targets. However, actual spending on consulting in NSW Treasury's Reports on State Finances 2020–21 and 2021–22 was almost $100 million higher than the savings targets over the first three years since 2019–20.

What we recommended

The report made seven recommendations which aim to improve:

  • the quality and transparency of data on spending on consultants
  • monitoring of strategic risks and agency compliance with procurement and recordkeeping rules
  • agencies' strategic use of consultants, including evaluation and knowledge retention.

Between 2017–18 and 2021–22, NSW government agency annual reports disclosed total spending of around $1 billion on consultants across more than 10,000 engagements. More than 1,000 consulting firms provided services to NSW government agencies during this period. Consulting is a classification of professional services that is characterised by giving advice or recommendations on a specific issue. The NSW Procurement Board Direction PBD-2021-03 defines a consultant as a person or organisation that provides 'recommendations or professional advice to assist decision-making by management'. PBD-2021-03 notes that the advisory nature of the work of consultants is the main factor that distinguishes them from other providers of professional services.

The NSW Procurement Board is responsible for setting procurement policy, issuing directions to support policies, and monitoring and reporting on agency compliance with policies and directions. NSW Procurement, a division within NSW Treasury, supports agencies to comply with the NSW Procurement Board’s policies and directions. A 'devolved governance model' is used for procurement in New South Wales. This means the heads of government entities that are covered by the NSW Procurement Board’s directions are responsible for managing the entity's procurement, including managing risks, reporting and ensuring compliance, in line with procurement laws and policies.

This audit assessed how effectively NSW government agencies procure and manage consultants. It assessed the role of the NSW Procurement Board and NSW Procurement in supporting and monitoring agency procurement and management of consultants. It also reviewed a sample of consulting engagements from ten NSW government agencies to examine how agencies procured, managed and reported on their use of consultants. The ten NSW government agencies were:

  • NSW Treasury
  • Department of Communities and Justice
  • Department of Customer Service
  • Department of Education
  • Department of Planning and Environment
  • Department of Premier and Cabinet
  • Department of Regional NSW
  • Infrastructure NSW
  • Sydney Metro
  • Transport for NSW

There are four different sources of data that contain information about spending on consultants by NSW government agencies: the State's financial consolidation system (Prime), disclosures of spending on consultants in agency annual reports, and two systems operated by NSW Procurement (the Business Advisory Services (BAS) dashboard and Spend Cube). Each of these data sources serves a different purpose, and collects and categorises information differently. None of these provide a complete source of data on spending on consultants, either in their own right or collectively.

NSW Treasury considers Prime to be the 'source of truth' on consulting expenditure across the NSW public sector. An account within Prime records recurrent spending on consultants, but this account does not include capital expenditure (that is, spending on consultants that has from a financial reporting perspective been 'capitalised' to a project on the balance sheet). As the State's financial consolidation system, Prime captures all financial information. However, capitalised consulting expenditure is recorded within various capital accounts, and is not identifiable within these accounts. While this is appropriate for accounting purposes, it means that the Prime account that records recurrent consulting expenditure does not reflect total spending on consultants by NSW government agencies. We used the data in Prime to assess whether NSW government agencies met the NSW Government's policy commitment—stated before the 2019 election and costed by the Parliamentary Budget Office—to reduce recurrent expenditure on consulting by 20% each year, over four years, from 2019–20. We did this because, while the Prime account for recurrent consulting expenditure does not reflect all spending on consultants, it does capture the recurrent spending that was subject to the policy commitment.

Most NSW government agencies are required by legislation to disclose spending on consultants (as defined in PBD-2021-03) in their annual reports. These disclosures include both recurrent and capital expenditure. For consulting engagements that cost more than $50,000, the disclosures also provide itemised information, including the names of the individual projects and the consultants used. While this data is more complete than Prime because it includes capital expenditure, it also has some gaps. Some entities are excluded from public reporting requirements on consultant use. For example, NSW Local Health Districts (LHD) are not required to produce annual reports, and the Ministry of Health does not include LHD consulting expenditure in its annual report.1 We used annual report disclosure data to report on total expenditure on consultants, and the concentration of suppliers of consulting services to NSW government agencies.

The BAS dashboard and Spend Cube are systems created by NSW Procurement to collect information about spending on suppliers of professional services. This includes consultants, but also includes other professional services providers. The systems were not designed for reporting on spending on consulting as defined in PBD-2021-03. However, we have used this data to assess specific aspects of NSW Procurement's monitoring of the use of consultants by NSW government agencies.

In 2018, we conducted an audit titled 'Procurement and reporting of consultancy services'. This assessed how 12 NSW government agencies complied with procurement requirements and how NSW Procurement supported the functions of the NSW Procurement Board. The 2018 audit found that none of the 12 agencies fully complied with NSW Procurement Board Directions on the use of consultants and that the NSW Procurement Board was not fully effective in overseeing and supporting agencies’ procurement of consultants. Specific findings from the 2018 audit included: 

  • Agencies applied the definition of consultant inconsistently, which affected the accuracy of reporting on consultancy expenditure.
  • There was inadequate guidance from NSW Procurement for agencies implementing the procurement framework, with a need for additional tools, automated processes, and other internal controls to improve compliance.
  • NSW Procurement had insufficient data for effective oversight of procurement and did not publish any data on the procurement of consultancy services by NSW government agencies.

Conclusion

Our review of a selection of consulting engagements from ten NSW government agencies indicates that these agencies do not procure and manage consultants effectively. We found that most agencies do not have a strategic approach to using consultants, or systems for managing or evaluating their performance. We also found examples of non-compliance with procurement rules, including contract variations that exceeded procurement thresholds. NSW Procurement, a division within NSW Treasury, provides frameworks and some guidance to agencies for procuring consultants. However, gaps in its data collection and analysis mean monitoring of strategic risks is limited and it does not respond to agency non-compliance consistently. There are limitations in ability of various data sources to accurately record spending on consultants. These limitations include incomplete recording of all spending, and different definitions of consulting for accounting and financial reporting purposes. Notwithstanding these limitations, and based on information in the State's financial consolidation system (Prime)—which records recurrent expenditure on consultants—it is highly unlikely that NSW government agencies will meet the government's 2019 policy commitment to reduce spending on consultants, as defined in the policy commitment and costed by the Parliamentary Budget Office. 

The use of a 'devolved governance model' for procurement means NSW government agencies are responsible for developing and implementing their own systems that align with the NSW Government Procurement Policy Framework. Agency heads are responsible for demonstrating compliance. Most agencies included in this audit did not have a clear strategic approach to how and when consultants should be used (for example, to seek advice and expertise not already available within the agency) and were using consultants in an ad hoc manner.

Our analysis of whole-of-government spending on consultants, drawn from agency annual reports, indicates that four large professional services firms account for around 27% of spending on consultants in the period from 2017–18 to 2021–22. The number of firms making up the top 50% of expenditure decreased from 11 to eight during this time, with the other 50% of expenditure spread across more than 1,000 firms. Concentration of consulting engagements within a small number of firms increases strategic risks, including that advice is not sufficiently objective and impartial, and that NSW government agencies become overly reliant on selected professional services firms.

Our review of a selection of consulting engagements by NSW government agencies found several examples of non-compliance with procurement policy. This included the use of variations to contract values which exceeded allowable limits. Record keeping was inadequate in many cases we reviewed, which limits transparency about government spending. Most agencies did not proactively manage their consulting engagements. The majority of consulting engagements that we reviewed were not evaluated or assessed by the agency for quality. Very few used any processes to ensure the transfer and retention of knowledge generated through consulting engagements. This means agencies miss opportunities to increase core staff skills and knowledge and to maximise value from these engagements.

NSW Procurement oversees a detailed policy framework that provides guidance and support to NSW government agencies when they are using consultants. The policy framework provides mandatory steps and some other guidance. Our audit on the procurement and reporting of consultancy services in 2018 found that agency reporting on the use of consultants was inconsistent and recommended that NSW Procurement should improve the quality, accuracy and completeness of data collection. NSW Procurement’s guidance on how agencies should classify and report on consulting engagements remains ambiguous. This contributes to continued inconsistent reporting by and across agencies, and reduces the quality of data on the use of consultants.

NSW Procurement has made some improvements to the information available about spending on consultants since our audit in 2018, including additional analysis and reporting that is available to agencies. However, there is still no single data source that accurately captures all spending on consultants. This is despite our recommendations in 2018 that NSW Procurement improve the quality of information collected from agencies and suppliers, which NSW Procurement accepted. This makes it harder for NSW Procurement or individual agencies to track trends and identify risks or improvement opportunities in the way consultants are used. 

In early 2019, the NSW Government made a policy commitment to reduce consultancy expenses by 20% each year, over four years, from 2019–20 (excluding capital-related consultancy expenses). This commitment was set out in the Parliamentary Budget Office's '2019 Coalition Election Policy Costings (Policy Costings)'. NSW Treasury subsequently advised that to implement this commitment, agency budgets were reduced in Prime in line with the savings targets. However, actual spending on consultants recorded in Prime in the first three years after the commitment was made was almost $100 million higher than the targets. We did not see any evidence that the financial data on actual expenditure was used to inform reporting on NSW government agencies' progress toward achieving the savings set out in the policy commitment.


1 The Government Sector Finance Legislation (Repeal and Amendment) Act 2018 No 70 will amend the Health Services Act 1997 to specify that annual reporting information for any or all NSW Health entities may be included in the annual reporting information prepared by the Ministry of Health under the Government Sector Finance Act 2018. This provision is expected to commence on 1 July 2023.

This chapter outlines our findings on the role of NSW Procurement in overseeing the use of consultants by NSW government agencies.

This chapter outlines our findings on the use of consultants by the ten NSW government agencies that were included in this audit.

Appendix one – Responses from auditees

Appendix two – About the audit

Appendix three – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #378 - released 2 March 2023

Published

Actions for Planning and managing bushfire equipment

Planning and managing bushfire equipment

Community Services
Justice
Planning
Environment
Local Government
Asset valuation
Compliance
Financial reporting
Information technology
Infrastructure
Internal controls and governance
Management and administration
Procurement
Regulation
Risk
Shared services and collaboration
Workforce and capability

What the report is about

This audit assessed the effectiveness of the NSW Rural Fire Service (RFS) and local councils in planning and managing equipment for bushfire prevention, mitigation, and suppression.

What we found

The RFS has focused its fleet development activity on modernising and improving the safety of its firefighting fleet, and on the purchase of new firefighting aircraft.

There is limited evidence that the RFS has undertaken strategic fleet planning or assessment of the capability of the firefighting fleet to respond to current bushfire events or emerging fire risks.

The RFS does not have an overarching strategy to guide its planning, procurement, or distribution of the firefighting fleet.

The RFS does not have effective oversight of fleet maintenance activity across the State, and is not ensuring the accuracy of District Service Agreements with local councils, where maintenance responsibilities are described.

What we recommended

  1. Develop a fleet enhancement framework and strategy that is informed by an assessment of current fleet capability, and research into appropriate technologies to respond to emerging fire risks.
  2. Develop performance measures to assess the performance and capabilities of the fleet in each RFS District by recording and publicly reporting on fire response times, fire response outcomes, and completions of fire hazard reduction works.
  3. Report annually on fleet allocations to RFS Districts, and identify the ways in which fleet resources align with district-level fire risks.
  4. Develop a strategy to ensure that local brigade volunteers are adequate in numbers and appropriately trained to operate fleet appliances in RFS Districts where they are required.
  5. Establish a fleet maintenance framework to ensure regular update of District Service Agreements with local councils.
  6. Review and improve processes for timely recording of fleet asset movements, locations, and maintenance status.

This audit assessed how effectively the NSW Rural Fire Service (the RFS) plans and manages the firefighting equipment needed to prevent, mitigate, and suppress bushfires. This audit also examined the role of local councils in managing bushfire equipment fleet assets. Local councils have vested legal ownership of the majority of the land-based firefighting fleet, including a range of legislated responsibilities to carry out fleet maintenance and repairs. The RFS has responsibilities to plan and purchase firefighting fleet assets, and ensure they are ready for use in response to fires and other emergencies.

This report describes the challenges in planning and managing the firefighting fleet, including a confusion of roles and responsibilities between the RFS and local councils in relation to managing certain land-based rural firefighting fleet – a point that has been made in our Local Government financial audits over several years. This role confusion is further demonstrated in the responses of the RFS and local councils to this audit report – included at Appendix one.

The lack of cohesion in roles and responsibilities for managing rural firefighting vehicles increases the risk that these firefighting assets are not properly maintained and managed, and introduces a risk that this could affect their readiness to be mobilised when needed.

While the audit findings and recommendations address some of the operational and organisational inefficiencies in relation to rural firefighting equipment management, they do not question the legislative arrangements that govern them. This is a matter for the NSW Government to consider in ensuring the fleet arrangements are fit for purpose, and are clearly understood by the relevant agencies.

The NSW Rural Fire Service (hereafter the RFS) is the lead combat agency for bushfires in New South Wales, and has the power to take charge of bushfire prevention and response operations anywhere in the State. The RFS has responsibilities to prevent, mitigate and suppress bushfires across 95% of the State, predominantly in the non-metropolitan areas of New South Wales. Fire and Rescue NSW is responsible for fire response activity in the cities and large townships that make up the remaining five per cent of the State.

The RFS bushfire fleet is an integral part of the agency's overall bushfire risk management. The RFS also uses this fleet to respond to other emergencies such as floods and storms, motor vehicle accidents, and structural fires. Fleet planning and management is one of a number of activities that is necessary for fire mitigation and suppression.

The Rural Fires Act 1997 (Rural Fires Act) imposes obligations on all landowners and land managers to prevent the occurrence of bushfires and reduce the risk of bushfires from spreading. Local councils have fire prevention responsibilities within their local government areas, principally to reduce fire hazards near council owned or managed assets, and minor roads.

The RFS is led by a Commissioner and is comprised of both paid employees and volunteer rural firefighters. Its functions are prescribed in the Rural Fires Act and related legislation such as the State Emergency Rescue Management Act 1989. The RFS functions are also described in Bush Fire Risk Management Plans, the State Emergency Management Plan, District Service Agreements, and RFS procedural documents. Some of the core responsibilities of the RFS include:

  • preventing, mitigating, and suppressing fires across New South Wales
  • recruiting and managing volunteer firefighters in rural fire brigades
  • purchasing and allocating firefighting fleet assets to local councils
  • establishing District Service Agreements with local councils to give the RFS permissions to use the fleet assets that are vested with local councils
  • carrying out fleet maintenance and repairs when authorised to do so by local councils
  • inspecting the firefighting fleet
  • supporting land managers and private property owners with fire prevention activity.

In order to carry out its legislated firefighting functions, the RFS relies on land-based vehicles, marine craft, and aircraft. These different firefighting appliance types are referred to in this report as the firefighting fleet or fleet assets.

RFS records show that in 2021 there were 6,345 firefighting fleet assets across NSW. Most of the land-based appliances commonly associated with firefighting, such as water pumpers and water tankers, are purchased by the RFS and vested with local councils under the Rural Fires Act. The vesting of firefighting assets with local councils means that the assets are legally owned by the council for which the asset has been purchased. The RFS is able to use the firefighting assets through District Service Agreements with local councils or groups of councils.

In addition to the land-based firefighting fleet, the RFS owns a fleet of aircraft with capabilities for fire mitigation, suppression, and reconnaissance during fire events. The RFS hires a fleet of different appliances to assist with fire prevention and hazard reduction works. These include aircraft for firefighting and fire reconnaissance, and heavy plant equipment such as graders and bulldozers for hazard reduction. Hazard reduction works include the clearance of bush and grasslands around major roads and protected assets, and the creation and maintenance of fire trails and fire corridors to assist with fire response activity.

The RFS is organised into 44 RFS Districts and seven Area Commands. The RFS relies on volunteer firefighters to assist in carrying out most of its firefighting functions. These functions may include the operation of the fleet during fire response activities and training exercises, and the routine inspection of the fleet to ensure it is maintained according to fleet service standards. Volunteer fleet inspections are supervised by the RFS Fire Control Officer.

In 2021 there were approximately 73,000 volunteers located in 1,993 rural fire brigades across the State, making the RFS the largest volunteer fire emergency service in Australia. In addition to brigade volunteers, the RFS has approximately 1,100 salaried staff who occupy leadership and administrative roles at RFS headquarters and in the 44 RFS Districts.

Local councils have legislative responsibilities relating to bushfire planning and management. Some of the core responsibilities of local councils include:

  • establishing and equipping rural fire brigades
  • contributing to the Rural Fire Fighting Fund
  • vested ownership of land-based rural firefighting equipment
  • carrying out firefighting fleet maintenance and repairs
  • conducting bushfire prevention and hazard reduction activity.

The objective of this audit was to assess the effectiveness of the RFS and local councils in planning and managing equipment for bushfire prevention, mitigation, and suppression. From the period of 2017 to 2022 inclusive, we addressed the audit objective by examining whether the NSW RFS and local councils effectively:

  • plan for current and future bushfire fleet requirements
  • manage and maintain the fleet required to prevent, mitigate, and suppress bushfires in NSW.

This audit did not assess:

  • the operational effectiveness of the RFS bushfire response
  • the effectiveness of personal protective equipment and clothing
  • the process of vesting of rural firefighting equipment with local councils
  • activities of any other statutory authorities responsible for managing bushfires in NSW.

As the lead combat agency for the bushfire response in NSW, the RFS has primary responsibility for bushfire prevention, mitigation, and suppression.

Three local councils were selected as case studies for this audit, Hawkesbury City Council, Wagga Wagga City Council and Uralla Shire Council. These case studies highlight the ways in which the RFS and local councils collaborate and communicate in rural fire districts.

Conclusion

The RFS has focused its fleet development activity on modernising and improving the safety of its land-based firefighting fleet, and on the purchase of new firefighting aircraft

The RFS has reduced the average age of the firefighting fleet from approximately 21 years in 2017, to approximately 16 years in 2022. The RFS has also enhanced the aerial fleet with the addition of six new aircraft to add to the existing three aircraft.

Recommendations from inquiries into the 2019–20 bushfires have driven significant levels of fleet improvement activity, mainly focused on the addition of safety features to existing fleet appliances. The RFS has dedicated most of its efforts to purchasing and refurbishing firefighting appliances of the same type and in the same volumes year on year.

However, the RFS is unable to demonstrate how the composition, size, or the locations of the NSW firefighting fleet is linked to current fire prevention, mitigation, and suppression requirements, or future fire risks.

There is limited evidence that the RFS has undertaken strategic fleet planning or assessment of the capability of the firefighting fleet to respond to current bushfire events or emerging fire risks

The RFS has not established a methodology to assess the composition or volumes of the firefighting fleet against fire activity and fire risks in the 44 NSW Rural Fire Districts. The RFS has not developed performance measures or targets to assess or report on fire response times in each of its districts, nor has it developed measures to assess the effectiveness of responses according to fire sizes and fire types. Similarly, the RFS has limited performance measures to assess fire prevention activity, or to assess fuel load reduction works, so it is not possible to assess whether its fleet capabilities are fit for these purposes.

The RFS does not have an overarching strategy to guide its planning, procurement, or distribution of the firefighting fleet

RFS fleet planning and fleet allocations are based on historical fleet sizes and compositions, and distributed to locations where there are appropriately trained brigade volunteers.

The RFS takes an asset protection approach to bushfire prevention and planning that is based on the Australian and New Zealand Standard for Risk Management. This approach requires that the RFS identify assets at risk of fire, and develop treatment plans to protect these assets. However, fleet requirements are not linked to NSW asset protection plans, meaning that fleet is not allocated according to the identified risks in these plans. Further, the RFS does not develop fire prevention plans for areas where there are no identified assets.

The RFS has not conducted future-focused fleet research or planning into technologies that match fleet capabilities to emerging or future fire risks. Since the significant fire events of 2019–2020, the RFS has not changed its approach to planning for, or assessing, the operational capabilities of the fleet. The RFS advises it is scoping a project to match resources to risk, which it plans to commence in 2023.

The RFS does not have effective oversight of fleet maintenance activity across the State, and is not ensuring the accuracy of District Service Agreements where maintenance responsibilities are described

The RFS does not have a framework to ensure that District Service Agreements with local councils are accurate. Almost two thirds of service agreements have not been reviewed in the last ten years, and some do not reflect actual maintenance practices. There is no formalised process to ensure communication occurs between the RFS and local councils for fleet management and maintenance.

RFS fleet management systems at the central level are not integrated with RFS district-level databases to indicate when fleet assets are in workshops being maintained and serviced. The RFS has a new centralised Computer Aided Dispatch System that relies on accurate fleet locations and fleet condition information in order to dispatch vehicles to incidents and fires. A lack of interface between the district-level fleet systems and the centralised RFS fleet dispatch system, may impact on operational responses to bushfires. 

The RFS has not made significant changes to the size or composition of the firefighting fleet in the past five years and does not have an overarching strategy to drive fleet development

Since 2017, the RFS has made minimal changes to its firefighting fleet volumes or vehicle types. The RFS is taking a fleet renewal approach to fleet planning, with a focus on refurbishing and replacing ageing firefighting assets with newer appliances and vehicles of the same classification and type. While the RFS has adopted a fleet renewal approach, driven by its Appliance Replacement Program Guide, it does not have a strategy or framework to guide its future-focused fleet development. There is no document that identifies and analyses bushfire events and risks in NSW, and matches fleet resources and fleet technologies to meet those risks. The RFS does not have fleet performance measures or targets to assess whether the size and composition of the fleet is meeting current or emerging bushfire climate hazards, or fuel load risks across its 44 NSW Fire Districts.

The RFS fleet currently comprises approximately 4,000 frontline, operational firefighting assets such as tankers, pumpers, and air and marine craft, and approximately 2,300 logistical vehicles, such as personnel transport vehicles and specialist support vehicles. Of the land-based firefighting vehicles, the RFS has maintained a steady number of approximately 3,800 tankers and 65 pumpers, year on year, for the past five years. This appliance type is an essential component of the RFS land-based, firefighting fleet with capabilities to suppress and extinguish fires.

Since 2017, most RFS fleet enhancement activity has been directed to upgrades and the modernisation of older fleet assets with new safety features. There is limited evidence of research into new fleet technologies for modern firefighting. The RFS fleet volumes and fleet types have remained relatively static since 2017, with the exception of the aerial firefighting fleet. Since 2017, the RFS has planned for, and purchased, six additional aircraft to add to the existing three aircraft in its permanent fleet.

While the RFS has made minimal changes to its fleet since 2017, in 2016 it reduced the overall number of smaller transport vehicles, by purchasing larger vehicles with increased capacity for personnel transport. The consolidation of logistical and transport vehicles accounts for an attrition in fleet numbers from 7,058 in 2016, to 6,315 in 2017 as shown in Exhibit 2.

The firefighting fleet management system is not always updated in a timely manner due to insufficient RFS personnel with permissions to make changes in the system

The RFS uses a fleet management system known as SAP EAM to record the location and status of firefighting fleet assets. The system holds information about the condition of the firefighting fleet, the home location of each fleet asset, and the maintenance, servicing, and inspection records of all assets. The RFS uses the system for almost all functions related to the firefighting fleet, including the location of vehicles so that they can be dispatched during operational exercises or fire responses.

Staff at RFS Headquarters are responsible for creating and maintaining asset records in the fleet management system. RFS District staff have limited permissions in relation to SAP EAM. They are able to raise work orders for repairs and maintenance, upload evidence to show that work has been done, and close actions in the system.

RFS District staff are not able to enter or update some fleet information in the system, such as the location of vehicles. When an RFS District receives a fleet appliance, it cannot be allocated to a brigade until the location of the asset is accurately recorded in the system. The location of the asset must be updated in the SAP EAM system by staff at RFS Headquarters. District staff can request system support from staff at RFS Headquarters to enter this information. At the time of writing, the position responsible for updating the fleet management system at RFS Headquarters was vacant, and RFS District personnel reported significant wait times in response to their service requests.

The RFS conducts annual audits of SAP EAM system information to ensure data is accurate and complete. RFS staff are currently doing data cleansing work to ensure that fleet allocations are recorded correctly in the system.

Communication between brigades, local councils and the RFS needs improvement to ensure that fleet information is promptly updated in the fleet management system

RFS brigade volunteers do not have access to the fleet management system. When fleet assets are used or moved, volunteers report information about the location and condition of the fleet to RFS District staff using a paper-based form, or by email or phone. Information such as vehicle mileage, engine hours, and defects are all captured by volunteers in a logbook which is scanned and sent to RFS District staff. RFS District staff then enter the relevant information into the fleet management system, or raise a service ticket with RFS Headquarters to enter the information.

Brigade volunteers move fleet assets for a range of reasons, including for fire practice exercises. If volunteers are unable to report the movement of assets to RFS District staff in a timely manner, this can lead to system inaccuracies. Lapses and backlogs in record keeping can occur when RFS staff at district offices or at Headquarters are not available to update records at the times that volunteers report information. A lack of accurate record keeping can potentially impact on RFS operational activities, including fire response activity.

Brigade volunteers notify RFS District staff when fleet appliances are defective, or if they have not been repaired properly. District staff then enter the information into the fleet management system. The inability of volunteers to enter information into the system means they have no visibility over their requests, including whether they have been approved, actioned, or rejected.

Local councils are responsible for servicing and maintaining the firefighting fleet according to the Rural Fires Act, but this responsibility can be transferred to the RFS through arrangements described in local service agreements. Council staff record all fleet servicing and maintenance information in their local systems. The types of fleet information that is captured in local council records can vary between councils. RFS staff described the level of council reporting, and the effectiveness of this process, as 'mixed'.

Councils use different databases and systems to record fleet assets, and some councils are better resourced for this activity than others

Firefighting fleet information is recorded in different asset management systems across NSW. Each council uses its own asset management system to record details about the vested fleet assets. All three councils that were interviewed for this audit had different systems to record information about the fleet. In addition, the type of information captured by the three councils was varied.

Exhibit 10: Systems used by local councils to manage the firefighting fleet
System Hawkesbury City Council Uralla Shire Council Wagga Wagga City Council
Financial asset management system TechnologyOne Civica Assetic
Asset management system TechnologyOne Manual MEX

Source: Audit Office analysis of information provided by the RFS and local councils.

Local councils have varying levels of resources and capabilities to manage the administrative tasks associated with the firefighting fleet. Some of the factors that impact on the ability of councils to manage administrative tasks include: the size of the council; the capabilities of the information management systems, the size of the staff team, and the levels of staff training in asset management.

Uralla Shire Council is a small rural council in northern NSW. This council uses financial software to record information about the firefighting fleet. While staff record information about the condition of the asset, its replacement value, and its depreciation, staff do not record the age of the asset, or its location. Staff manually enter fleet maintenance information into their systems. Uralla Shire Council would like to purchase asset maintenance software that generates work orders for fleet repairs and maintenance. However, the council does not have trained staff in the use of asset management software, and the small size of the fleet may not make it financially worthwhile.

The Hawkesbury City Council uses a single system to capture financial and asset information associated with the firefighting fleet. Hawkesbury is a large metropolitan council located north-west of Sydney, with a relatively large staff team in comparison with Uralla Shire Council. The Hawkesbury City Council has given RFS District staff access to their fleet information system. RFS District staff can directly raise work orders for fleet repairs and maintenance through the council system, and receive automated notifications when the work is complete.

Two of the three audited councils report that they conduct annual reviews of fleet assets to assess whether the information they hold is accurate and up-to-date.

More than half of the fleet maintenance service agreements between the RFS and local councils have not been reviewed in ten years, and some do not reflect local practices

Local councils have a legislated responsibility to service, repair, and maintain the firefighting fleet to service standards set by the RFS. Councils may transfer this responsibility to the RFS through District Service Agreements. The RFS Districts are responsible for ensuring that the service agreements are current and effective.

The RFS does not have monitoring and quality control processes to ensure that service agreements with local councils are reviewed regularly. The RFS has 73 service agreements with local councils or groups of councils. Sixty-three per cent of service agreements had not been reviewed in the last ten years. Only four service agreements specify an end date and, of those, one agreement expired in 2010 and had not been reviewed at the time of this audit.

The RFS does not have a framework to ensure that service agreements with local councils reflect actual practices. Of the three councils selected for audit, one agreement does not describe the actual arrangements for fleet maintenance practices in RFS Districts. The service agreement with Hawkesbury City Council specifies that the RFS will maintain the firefighting fleet on behalf of council when, in fact, council maintains the firefighting fleet. The current agreement commenced in 2012, and at the time of writing had not been updated to reflect local maintenance practices.

When District Service Agreements are not reviewed periodically, there is a risk that neither local councils nor the RFS have clear oversight of the status of fleet servicing, maintenance, and repairs.

RFS District Service Agreements set out a requirement that RFS and local councils establish a liaison committee. Liaison committees typically include council staff, RFS District staff, and RFS brigade volunteers. While service agreements state that liaison committees must meet periodically to monitor and review the performance of the service agreement, committee members determine when and how often the committee meets.

RFS District staff and staff at the three audited councils are not meeting routinely to review or update their service agreements. At Wagga Wagga City Council, staff meet with RFS District staff each year to report on activity to fulfil service agreement requirements. Uralla Shire Council staff did not meet routinely with RFS District staff before 2021. When liaison committees do not meet regularly, there is a risk that the RFS and local councils have incorrect or outdated information about the location, status, or condition of the firefighting fleet. Given that councils lack systems to track and monitor fleet locations, regular communication between the RFS and local councils is essential.

The RFS has not established processes to ensure that local councils and RFS District personnel meet and exchange information about the fleet. Of the three councils selected for this audit, one council had not received information about the number, type, or status of the fleet for at least five years, and did not receive an updated list of appliances until there was a change in RFS District personnel. This has impacted on the accuracy of council record keeping. Councils do not always receive notification about new assets or information about the location of assets from the RFS, and therefore cannot reflect this information in their accounting and reporting.

RFS area commands audit system records to ensure fleet inspections occur as planned, but central systems are not always updated, creating operational risks

RFS District staff are required by the Rural Fires Act to ensure the firefighting fleet is inspected at least once a year. Regular inspections of the fleet are vital to ensure that vehicles are fit-for-purpose and safe for brigade volunteers. Inspections are also fundamental to the operational readiness and capability of RFS to respond to fire incidents.

RFS Area Command personnel conduct audits of fleet maintenance data to ensure that fleet inspections are occurring as planned. These inspections provide the RFS with assurance that the fleet is being maintained and serviced by local council workshops, or third-party maintenance contractors.

Some RFS Districts run their own fleet management systems outside of the central management system. They do this to manage their fleet inspection activity effectively. Annual fleet inspection dates are programmed by staff at RFS Headquarters. Most of the inspection dates generated by RFS Headquarters are clustered together and RFS Districts need to separate inspection times to manage workloads over the year. Spreading inspection dates is necessary to avoid exceeding the capacity of local council workshops or third party contractors, and to ensure that fleet are available during the bushfire season.

The fleet inspection records at RFS Headquarters are not always updated in a timely manner to reflect actual inspection and service dates of vehicles. District staff are not able to change fleet inspection and service dates in the central management system because they do not have the necessary permissions to access the system. The usual practice is for RFS District staff to notify staff at RFS Headquarters, and ask them to retrospectively update the system. As there is a lag in updating the central database, at a point in time, the actual inspection and service dates of vehicles can be different to the dates entered in the central fleet management system.

Fleet inspection and maintenance records must be accurately recorded in the central RFS management system for operational reasons. RFS Headquarters personnel need to know the location and maintenance status of fleet vehicles at all times in order to dispatch vehicles to incidents and fires. The RFS fleet management system is integrated with a new Computer Aided Dispatch System. The Computer Aided Dispatch System assigns the nearest and most appropriate vehicles to fire incidents. The system relies on accurate fleet locations and fleet condition information in order to dispatch these vehicles.

There is a risk that RFS Headquarters' systems do not contain accurate information about the location and status of vehicles. Some may be in workshops for servicing and repair, while the system may record them as available for dispatch. As there are many thousands of fleet vehicles, all requiring an annual service and inspection, a lack of accurate record keeping has wide implications for State fire operations.

RFS is currently exploring ways to improve the ways in which fleet inspections are programmed into the fleet management system.

RFS provides funds to councils to assist with maintaining the firefighting fleet, but does not receive fleet maintenance cost information from all local councils

Each year the RFS provides local councils with a lump sum to assist with the cost of repairing and maintaining the firefighting fleet. This lump sum funding is also used for meeting the costs of maintaining brigade stations, utilities, and other miscellaneous matters associated with RFS business.

In 2020–21, the RFS provided NSW local councils with approximately $23 million for maintenance and repairs of appliances, buildings, and utilities. Ninety councils were provided with lump sum funding in 2021, receiving on average $257,000. The amounts received by individual councils ranged from $56,200 to $1,029,884.

Some councils provide itemised repairs and maintenance reports to RFS District staff, showing the work completed and the cost of that work. However, not all councils collect this information or provide it to the RFS. Local councils collect fleet maintenance information in their local council systems. In some cases, the responsibility for fleet maintenance is shared across a group of councils, and not all councils have oversight of this process.

The RFS has not taken steps to require local councils to provide itemised maintenance costings for the firefighting fleet. Thus, the RFS does not have a clear understanding of how local councils are spending their annual fleet maintenance funding allocations. The RFS does not know if the funding allocations are keeping pace with the actual cost of repairing and maintaining the fleet.

RFS District staff report that funding shortfalls are impacting on the prioritisation of fleet servicing and maintenance works in some council areas. When fleet servicing and maintenance is not completed routinely or effectively, there is a risk that it can negatively impact the overall condition and lifespan of the vehicle. Poor processes in relation to fleet maintenance and repair risk impacting on the operational capabilities of the fleet during fire events.

The timeliness and effectiveness of fleet servicing and maintenance is affected by resource levels in RFS Districts and local councils

Local councils have a legislated responsibility to service and maintain the firefighting fleet to the service standards set by the RFS. Fleet maintenance is usually done by the entity with the appropriate workshops and resources, and the maintenance arrangements are described in District Service Agreements. RFS District staff conduct annual inspections to ensure that the firefighting fleet has been serviced and maintained appropriately, and is safe for use by brigade volunteers. If the fleet has not been maintained to RFS service standards or timelines, RFS District staff may work with local councils to support or remediate these works.

The effectiveness of this quality control activity is dependent on relationships and communication between the RFS Districts and local councils. While some RFS staff reported having positive relationships with local councils, others said they struggled to get fleet maintenance work done in a timely manner. Some councils reported that funding shortfalls for fleet maintenance activity was impacting on the prioritisation of RFS fleet maintenance works. When fleet maintenance work is not completed routinely or effectively, it can negatively impact on the overall condition and lifespan of the vehicle. It can also reduce the capacity of the RFS to respond to fire events.

Fleet quality control activities are carried out by RFS District staff. In some of the smaller RFS Districts, one person is responsible for liaising with local councils and brigade volunteers about fleet maintenance and repairs. In the regions where resources are limited, there is less ability to maintain ongoing communication. This is impacting on fleet service and maintenance timelines and the timeliness of fleet monitoring activity.

The RFS has mutual support arrangements with agencies in NSW and interstate, though shared fleet levels are yet to be quantified

The RFS has arrangements with state, federal, and international fire authorities to provide mutual support during fire incidents. In NSW, the RFS has agreements with the three statutory authorities – Fire and Rescue NSW, the Forestry Corporation of NSW, and the NSW National Parks and Wildlife Service. The agreement with Fire and Rescue NSW provides a framework for cooperation and joint operations between the agencies. The agreements with the Forestry Corporation of NSW and the NSW National Parks and Wildlife Service describe the control and coordination arrangements for bush and grass fires across NSW. These arrangements are set out in legislation and incorporated into local Bush Fire Risk Management Plans.

The RFS has agreements with fire authorities in three of the four Australian states and territories that share a border with NSW – the Australian Capital Territory, Queensland, and South Australia. Each agreement sets out the arrangements for mutual assistance and joint operations, including arrangements for sharing aircraft. The agreement between the RFS and Victoria had lapsed. The RFS told the NSW Bushfire Inquiry that the agreement with Victoria would be finalised by June 2020. In June 2022, the RFS reported that the agreement was in the process of being finalised.

The arrangements for mutual aid from Western Australia, Northern Territory and Tasmania, are managed by the National Resource Sharing Centre. These agreements set out the arrangements for interstate assistance between Australian fire services, emergency services, and land management agencies in those states and territories.

These mutual support arrangements may assist during state-based fire events. However, when there are competing demands for resources, such as during the bushfires of 2019–2020, there can be limits on fleet availability. During the 2019–2020 fires, resources were stretched in all jurisdictions as these fires affected NSW, Victoria, and Queensland.

There are opportunities for the RFS and other NSW agencies to quantify fleet resources across the State and identify assets that can be mobilised for different fire activities. This form of fleet planning may be used to enhance surge capabilities during times of high fire activity. There are also opportunities for the RFS and other agencies to match the levels of shared assets to projected bushfire risks.

Appendix one – Responses from agencies 

Appendix two – About the audit 

Appendix three – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #376 - released 27 February 2023

 

Published

Actions for Government's acquisition of private property: Sydney Metro project

Government's acquisition of private property: Sydney Metro project

Transport
Planning
Whole of Government
Compliance
Infrastructure
Internal controls and governance
Project management
Risk

What the report is about

Sydney Metro is Australia’s largest public transport project. It requires the acquisition of many private properties, including residential and business properties.

This audit assessed the effectiveness of the acquisition of private properties for the Sydney Metro project. The audited agencies were Sydney Metro, the Department of Planning and Environment (Valuer General NSW) and Transport for NSW (the Centre for Property Acquisition).

The audit assessed agencies against the framework for property acquisitions in New South Wales. It did not re-perform the valuations done for individual properties that were acquired by Sydney Metro.

What we found

Acquisitions of private property for the Sydney Metro project were mostly effective in the sample of acquisitions we assessed. We found Sydney Metro:

  • complied with legislative and policy requirements for compensation and communication with people subject to property acquisitions
  • kept accurate records of its acquisitions and applied probity controls consistently
  • did not complete detailed plans or negotiation strategies for the high-risk and high-value acquisitions we reviewed
  • did not comply with legislative timelines for most compulsory acquisitions because of delays in receiving the required information from the Valuer General in these cases.

The Centre for Property Acquisition has overseen the implementation of reforms to residential acquisition processes, but its assessment of the effectiveness of these reforms has not been comprehensive.

What we recommended

The audit made four recommendations to the audited agencies to improve:

  • plans and strategies for the acquisition of high-risk and high-value properties
  • timeliness of issuing compensation determinations for compulsory acquisitions
  • data quality on the experience of people subject to property acquisitions.

The NSW Government has the power to acquire land that is owned or leased by individuals or businesses, if it is needed for a public purpose. The power arises from the Land Acquisition (Just Terms Compensation) Act 1991 (the Just Terms Act). Government agencies that have the power to compulsorily acquire private property are referred to as ‘acquiring authorities’. People who are subject to acquisitions are referred to as ‘affected parties’ and include property owners (business or residential), businesses with a commercial lease on a property, or individuals with residential tenancy leases. In recent years, the vast majority of acquisitions by the NSW Government have been for public transport or road projects.

Sydney Metro is a NSW Government agency with responsibility for building the Sydney Metro railway project. Sydney Metro is Australia’s largest public transport project. The project requires the acquisition of a large number of private properties. Sydney Metro has been one of the largest acquirers of private property in recent years, completing over 500 acquisitions between 2020 and mid-2022, with a total acquisition value of over $2 billion. Other agencies and statutory officers involved in the acquisition of property for the Sydney Metro project include:

  • the Department of Planning and Environment (DPE), which supports the minister responsible for the Just Terms Act. DPE also provides staff to the Valuer General of NSW
  • the Valuer General of NSW, an independent statutory officer that determines compensation in cases where the acquiring authority and the affected party cannot agree on compensation for property that has been acquired
  • Transport for NSW, which includes the Centre for Property Acquisition (CPA). The CPA does not have a direct role in acquiring properties, but its responsibilities include developing guidance for acquiring agencies and monitoring and reporting on their activities.

About this audit

The objective of this audit was to assess the effectiveness of acquisitions of private properties for Sydney Metro projects. The audit assessed agencies against the legislative and policy requirements in place for government acquisitions of private property in New South Wales. In line with the Audit Office's legislative mandate, the audit does not comment on the merits of the policy objectives reflected in the Just Terms Act.

The audit examined a sample of 20 property acquisitions. This was not a statistically representative sample. While our report provides comments on Sydney Metro’s overall acquisition processes, it does not provide assurance regarding the acquisitions that were not examined for this audit.

The audit did not re-perform the valuations done for individual properties that were acquired by Sydney Metro. Affected parties who disagree with the valuation of their property have the right to seek independent assessment of this via the Valuer General and the Land and Environment Court.

Conclusion

Acquisitions of property for the Sydney Metro project were mostly effective in the sample of acquisitions we assessed. Sydney Metro followed requirements for communication with affected parties. Compensation processes were conducted in compliance with legislative requirements, but compensation determinations for compulsory acquisitions were not completed within legislated time frames due to delays in receiving these from the Valuer General. Governance and probity processes were followed consistently, with some relatively minor exceptions. 

Sydney Metro has detailed guidelines for acquisitions that are based on relevant legislation and government policy. In the 20 acquisitions we assessed for this audit, these procedures were followed consistently. This included adhering to minimum timelines for negotiation periods, engaging independent valuers and other experts when needed, and complying with governance and probity processes.

Sydney Metro staff followed requirements for communication and support for residential acquisitions by assigning ‘personal managers’ and providing additional support to affected parties when needed. The Centre for Property Acquisition (CPA) has overseen reforms to the residential property acquisition process in recent years. These reforms include the introduction of the NSW Property Acquisition Standards and the use of personal managers, in addition to the existing acquisition managers, for residential acquisitions. However, the CPA has not assessed the impact of these changes on the experiences on people affected by property acquisitions.

Sydney Metro did not comply with the legislative requirement to provide a formal compensation notice to the affected party within 45 days of a compulsory acquisition starting in any of the eight relevant acquisitions in our sample. This was because Sydney Metro must wait for the Valuer General to complete a compensation determination before Sydney Metro can send the compensation notice, and the Valuer General did not do this within 45 days. We acknowledge that Sydney Metro does not have full control over this process, and that it has taken steps to mitigate the impact of delays on affected parties. 

This chapter presents our findings on Sydney Metro's acquisition of industrial and commercial properties. Industrial properties include construction businesses and manufacturing facilities. Commercial properties were mostly properties such as shopping centres and office towers. Many of these acquisitions involve businesses and properties that are relatively complex and have high values. This means the valuation process can require multiple experts and can be lengthy and contested. Adherence to governance and probity requirements is important for these acquisitions in order to demonstrate that the acquiring authority has achieved value for money.

This chapter presents our findings on Sydney Metro's acquisition of residential properties, which include apartments and houses, and small business leases, which mostly affected businesses in small shopping centres or arcades. Most of these acquisitions were lower value compared to industrial and commercial property acquisitions and did not require as much expert advice on complex technical issues. However, residential property acquisitions can be personally distressing for the affected parties and require staff from the acquiring authority to provide support and show empathy while ensuring legislative compliance and value for money.

Appendix one – Responses from agencies

Appendix two – About the audit 

Appendix three – Performance auditing 

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #375 - released 9 February 2023

Published

Actions for Bushfire recovery grants

Bushfire recovery grants

Environment
Industry
Compliance
Internal controls and governance
Management and administration
Service delivery

What the report is about

The Bushfire Local Economic Recovery (BLER) program was created after the 2019–20 bushfires, and commits $541.8 million to bushfire affected areas in New South Wales. It is co-funded by the Commonwealth and NSW governments.

This audit assessed how effectively the Department of Regional NSW (the department) and Resilience NSW administered rounds one and two of the BLER program. These rounds were:

  • Round one: early co-funding, split between two streams:
    • ­Fast-Tracked projects 
    • ­Sector Development Grants (SDG)
  • Round two: open round.

What we found

The Department of Regional NSW did not effectively administer the Fast-Tracked stream of the BLER. 

The administration process lacked integrity, given it did not have sufficiently detailed guidelines and the assessment process for projects lacked transparency and consistency. 

At the request of the Deputy Premier's office, a $1 million threshold was applied, below which projects were not approved for funding. The department advises that some of the projects excluded were subsequently funded from other programs. 

This threshold resulted in a number of shortlisted projects in areas highly impacted by the bushfires being excluded, including all shortlisted projects located in Labor Party-held electorates.

The department's administration of the SDG stream had a detailed and transparent assessment process. However, conflicts of interest were not effectively managed. 

The department's administration of the open round included a clearly documented, detailed and transparent assessment framework. Some weaknesses in the approach to conflicts of interest remained.

What we recommended

The Department of Regional NSW should ensure that for all future grant programs it:

  1. establishes and follows guidelines that align with relevant good practice guidance 
  2. ensures a communications plan is in place, including the communication of guidelines to potential applicants
  3. ensures staff declare conflicts of interest prior to the commencement of a grants stream, and that these conflicts of interest are recorded and managed
  4. ensures regular monitoring is in place as part of funding deeds 
  5. documents all key decisions and approvals in line with record keeping obligations.

This audit assessed how effectively the Department of Regional NSW and Resilience NSW administered rounds one and two of the Bushfire Local Economic Recovery (BLER) program.

As noted in this report, Resilience NSW was involved in the set-up and ongoing administration and monitoring of the BLER program. During the audited period, Resilience NSW was tasked with working with the Department of Regional NSW to create program objectives, guidelines and criteria. Their role also involved liaising with the Commonwealth Government, which provided co-funding for the program. Resilience NSW also had an ongoing role in quality assurance and compliance to ensure agencies administering disaster assistance did so in accordance with relevant guidelines. On 16 December 2022, the NSW Government abolished Resilience NSW.

Our work for this performance audit was completed on 3 November 2022, when we issued the final report to the two audited agencies. The audit report does not make specific recommendations to Resilience NSW. On 24 November 2022, the then Commissioner of Resilience NSW provided a response to the final report, which we include as it is the formal response from the audited entity at the time the audit was conducted.

During the 2019–20 bushfire season, New South Wales experienced 11,774 fire incidents, burning 5.5 million hectares of the state. There were 26 fatalities and 2,476 homes destroyed. The agriculture sector was heavily impacted with 601,858 hectares of pasture damaged.

Due to the widespread impacts of these fires on the state, the NSW and Commonwealth governments committed $4.4 billion toward bushfire response, recovery, and preparedness. This included the establishment of the Bushfire Local Economic Recovery (BLER) program, with $541.8 million committed to support job retention and creation in areas impacted by bushfires. The program also aims to strengthen community resilience and reduce the impact of future natural disasters. The BLER program is co-funded, with the Commonwealth and NSW governments funding 50% each.

The BLER program is comprised of three funding rounds:

  • round one early co-funding, split between
    • Fast-Tracked projects
    • Sector Development Grants (SDG)
  • round two: open round
  • round three: final projects and initiatives.

Resilience NSW was involved in setting up the BLER program and the Department of Regional NSW (the department) is responsible for administering it. The Commonwealth National Recovery and Resilience Agency must also endorse any projects proposed by the NSW Government for funding as part of the funding agreement between the State and Commonwealth governments.

Successful projects under the SDG stream were announced in September 2020 and projects funded through the Fast-Tracked stream were announced in October 2020. Round two (the open round) was administered after these two streams and successful projects were announced in June 2021.

The Department of Premier and Cabinet established the 'Good Practice Guide to Grants Administration' (the Good Practice Guide) in 2010 to assist the NSW Government in ensuring grants administration was performed consistently across all NSW Government grants programs. Compliance with the Good Practice Guide was not compulsory, but provided an outline of best practice covering the entire lifecycle of a grants program. This guide was in place at the time these grants were designed and administered.

The design and delivery of round one of the program occurred quickly, as part of the response to the 2019–20 bushfires, and was responding to a request from the Commonwealth Government for rapid project identification.

The objective of this audit was to assess how effectively the Department of Regional NSW and Resilience NSW administered rounds one and two of the BLER program. Round three was excluded from this audit because it had not been announced at the time of the audit.

We addressed this objective by examining whether the audited agencies:

  • effectively planned administration of the BLER program and established appropriate guidelines
  • implemented an effective assessment process for the BLER program
  • are effectively monitoring implementation of projects and program outcomes.

Conclusion

The Department of Regional NSW did not effectively administer the Fast-Tracked stream of the Bushfire Local Economic Recovery program. The administration process lacked integrity, given it did not have sufficiently detailed guidelines, and the assessment process for projects lacked transparency and consistency.

There were significant gaps in the documentation of decision-making throughout this funding stream. At the request of the Deputy Premier's office, a $1 million threshold was applied, below which projects were not approved for funding. This threshold was applied without a documented reason and was not part of the program guidelines. The department advises that some of the projects excluded through application of the threshold were subsequently funded from other programs.

The department's administration of the Sector Development Grants stream had a detailed and transparent assessment process. That said, conflicts of interest were not effectively managed, and the department did not effectively engage with stakeholders during the grants process.

The department's administration of the open round included a clearly documented, detailed and transparent assessment framework that it followed throughout. The department also implemented probity arrangements in the open round, although some weaknesses in the department's approach to conflicts of interest remained.

Fast-Tracked stream

Following requests from the Commonwealth Government in May and June 2020 to identify projects rapidly and as soon as practical, the department used an expedited process to identify relevant projects that had applied for other grants programs but had not received funding or which were identified as local priority projects. The department developed a set of guidelines for the Fast-Tracked stream based on draft Commonwealth funding criteria, but the department's guidelines lacked sufficient detail to ensure transparent and consistent decision-making. The guidelines also did not contain detailed information on how the assessment and approval processes would work. The department did not implement conflict of interest declarations for staff involved in the assessment process.

The assessment process implemented for the Fast-Tracked stream deviated from the guidelines. For example, the guidelines did not set out a role for the then Deputy Premier or his office in the assessment process, but the Deputy Premier's office played a key role in project selection. At the direction of the Deputy Premier's office, a $1 million minimum threshold, not mentioned in the guidelines, was applied to projects, below which, projects would not be funded. This resulted in a number of shortlisted projects in areas highly impacted by the bushfires, including all shortlisted projects located in Labor Party-held electorates, being excluded without a rationale being documented at the time. The department advised that some of these projects were subsequently funded through other funding streams.

The department's assessment process was inconsistent, poorly documented and lacked transparency. The department initially identified 445 potential projects through consultation with councils and through identifying projects that had been unsuccessful for other grant programs. The department only assessed 164 of these 445 projects for funding against the criteria in the guidelines. The department did not document the rationale for not assessing the remaining 281 projects against the criteria. The department also sought advice from Public Works Advisory (PWA) on whether projects could commence within six months, which was an eligibility criterion for the Fast-Tracked stream. PWA were only asked to assess 25 of the 445 projects, of which 19 were funded through the Fast-Tracked stream. The department also did not consistently follow PWA's advice and funded projects which PWA had advised were unable to commence within six months, which was not in line with the guidelines.

The department monitors 21 of the 22 Fast-Tracked projects on a quarterly basis to ensure projects are on track. Resilience NSW is responsible for the remaining project and does not monitor this on a quarterly basis but has established a project control group that performs a similar function. The agencies advised that this project is being transitioned to the department's management.

Sector Development Grants (SDG)

The department designed and published guidelines for the SDG stream. The guidelines largely align with the Department of Premier and Cabinet's 'Good Practice Guide to Grants Administration', although they could have been strengthened by including more detail on the eligibility of projects and the role of cost benefit analyses in the assessment process. The guidelines included a detailed and transparent assessment process which the department largely followed.

There were gaps in the administration of the SDG stream assessment process. The department did not effectively manage conflicts of interest as it did not ensure all required conflict of interest forms were completed and some forms were completed after the assessment process was finalised. The department also advised that the final version of the conflict of interest register, which contained the declarations for the SDG stream, was lost during a record management system change. The department did not develop guidance for communicating with stakeholders for the SDG stream. Feedback was received from industries which had been excluded from the SDG stream, relaying their concerns, and requesting a broader range of agribusiness sectors be considered for eligibility. A communications plan or strategy could have incorporated guidance on engaging agribusiness stakeholders during the planning stages of the stream, ensuring they were aware of the rationale for the eligible industries selected.

The majority of SDG funding went to areas highly impacted by the bushfires, although some highly impacted areas received less funding than lower impacted areas, and there is no clear reason for this.

The department does not monitor SDG projects on a quarterly basis to ensure that they remain on track but it ensures it has sufficient evidence that milestones have been completed before making funding payments.

Open round

The department designed and implemented a clearly documented and detailed assessment process for the open round. There were some areas where the process could have been improved, for example, the published guidelines did not set out the role of the former Deputy Premier or include reference to consultation with members of Parliament (MP) as part of the process, despite the fact that MPs were consulted as part of this round.

The department improved its management of conflicts of interest compared to the Fast-Tracked and SDG streams by maintaining a conflict of interest register, though not all conflict of interest declarations were collected. The department also developed a communications plan which led to improvements in stakeholder engagement.

One of the purposes of the open round was to distribute funding to local government areas (LGA) which did not receive funding through the Fast-Tracked stream. This intention was not outlined in the guidelines for this funding stream. The majority of funding from the open round went to LGAs which had been highly impacted by the bushfires.

The department monitors the open round projects on a quarterly basis to ensure that they are on track.

1. Recommendations

To promote integrity and transparency, the Department of Regional NSW should ensure that for all future grant programs it:

  1. establishes and follows guidelines that align with relevant good practice guidance including accountabilities, key assessment steps and clear assessment criteria
  2. ensures a communications plan is in place, including the communication of guidelines to potential applicants
  3. ensures staff declare conflicts of interest prior to the commencement of a grants stream, and that these conflicts of interest are recorded and managed
  4. ensures regular monitoring is in place as part of funding deeds
  5. documents all key decisions and approvals in line with record keeping obligations.

Stage one of the BLER program consisted of early co-funded projects valued at a total of $180 million. This included 22 Fast-Tracked priority projects valued at a total of $107.8 million. The purpose of these projects was to deliver immediate and significant economic impacts to high and moderate bushfire-impacted areas.

A timeline of key dates may be found at Exhibit 5.

Fifty-two projects worth a total of $73.2 million were funded through the SDG stream. One grantee withdrew their project from the stream in early 2021, leaving a total of 51 projects (of which 49 are co-funded with the Commonwealth Government).

A timeline of key dates may be found at Exhibit 9.

The department distributed $283 million to 195 successful projects as part of the open round of the BLER program.

A timeline of key dates may be found at Exhibit 11.

The department entered into funding deeds with successful applicants

The Good Practice Guide advises that the agency administering a grant should enter into a formal agreement with each grant recipient which sets out the arrangements under which a grant is provided, received, managed and acquitted. Across all three streams, the department sent out a letter of offer to successful project managers to let them know that they had been successful in receiving funding, and then entered into funding deeds with grantees. The one exception was the project that RNSW managed, discussed below.

The reviewed funding deeds were signed by department staff with the appropriate level of delegation. They contained an appropriate level of information and key clauses that would allow the department to monitor the progress of the grant to ensure its completion as agreed with the grantee. The reviewed funding deeds contained key information, including:

  • total value of the grant
  • key deliverables at each milestone
  • expected completion date of both the overall project and each milestone
  • reporting requirements, including provisions to allow the department to request relevant information
  • variation procedures.

The department only makes payments after confirming that milestones have been reached

The department has provided payments to grantees only after they could demonstrate that they had completed the agreed milestone. To ensure each milestone has been completed, the department requires grantees to provide evidence that they have fulfilled the milestone. Types of evidence provided includes photographs and invoices. Where the grantee provides insufficient evidence to the department, the department follows-up with the grantee to ensure that enough information is provided to justify the milestone payment.

The department also plans to undertake site visits of projects at select milestones and at the completion of most projects. The department has undertaken a risk assessment of each SDG and open round project, and uses this risk assessment to determine the number of milestones for the project, as well as the number of site visits that the department will undertake. Fast-Tracked projects all had PWA providing either project management or assurance and as such oversight is being provided through that mechanism. The milestones and site visits at each level of risk can be seen in Exhibit 15 for SDG and Exhibit 16 for open round.

Exhibit 15: Milestones and site visits for each level of risk - SDG
Risk rating Milestones Site visits
Low Two Zero
Medium Three One
High Four Two
Source: Department of Regional NSW.
 
Exhibit 16: Milestones and site visits for each level of risk - open round
Risk rating Milestones Site visits
Low Three One
Medium Four Two
High Five Three
 Source: Department of Regional NSW.

The department does not monitor quarterly progress for SDG grants

As part of the LER framework, the department reports to the Commonwealth every quarter on the status and financials of each project, including whether there are any risks to project delivery and the mitigations in place for those risks. For projects funded through the Fast-Tracked stream and the open round, the department collects quarterly progress reports from the grantees. These progress reports allow the department to determine if there are project risks, which can then be reported to the Commonwealth. The progress reports also allow the department to determine if a milestone is likely to be met within the next quarter or whether a project variation may be needed.

While the department monitors projects funded through the Fast-Tracked stream and the open round on a quarterly basis, there is no quarterly monitoring of progress for projects funded through the SDG stream. The SDG funding deeds do not include a provision to require quarterly reporting to the department. The department only collects progress reports from grantees when the grantee reports that it has completed a milestone. Quarterly monitoring of the SDG stream would allow the department to determine if projects require corrective action.

Resilience NSW is not collecting quarterly reports for the Fast-Tracked grant it is responsible for administering

One of the projects funded through the Fast-Tracked stream was the rebuilding of three local halls across two LGAs, for a total value of $3 million. RNSW is responsible for managing this grant and entered into funding deeds with the relevant councils. It is not documented why RNSW is responsible for these funding deeds rather than the department, which is the signatory for all of the other Fast-Tracked stream funding deeds. RNSW advised it was due to the responsible RNSW Director having a strong working relationship with the relevant councils.

The funding deeds which RNSW signed with the relevant councils set out a requirement that the councils would report on this project to RNSW every quarter. The second milestone of each of these projects involved the submission of a quarterly report. However, RNSW was unable to provide evidence that it carried out this monitoring of the project. At the time of the audit, no second milestone payment had been made. Undertaking quarterly monitoring would provide RNSW with assurance that the money is being expended for the proper purpose and whether the projects will be completed by the target date.

RNSW and the relevant councils developed project control groups for each project, which allows it to monitor the implementation of the projects. PWA is also represented on these project control groups and provides an advisory role in the implementation of the projects.

RNSW and the department advised that responsibility for this project will be transitioned to the department and it will be monitored on a quarterly basis, in line with the other Fast-Tracked projects.

The department has a consistent approach to validating variations

The department's funding deeds with grantees allow for the variation of contracts at the department's discretion after the grantee has written to the department. It is important for the department to consider the impact of any project variation request on the overall program objectives, because a project which costs more than was originally planned or which takes additional time may put at risk the objectives of the BLER program. To ensure that requests for variation are handled consistently and appropriately, the department's Grants Management Office (GMO) has developed a process document which applies to variation requests across the BLER program.

For the grants reviewed as part of this audit, the GMO applied this variation process consistently and has documented the outcomes. Larger variations are reviewed at a higher level of delegation and sign-off. To determine whether a variation is accepted, the GMO considers the following factors:

  • consistency with BLER program objectives
  • delivery within the timeframes of the BLER program
  • eligibility under the BLER program guidelines
  • financial viability to deliver within the requested budget.

The department is preparing multiple evaluations, but it has delayed its process evaluation

When developing round one of the BLER program, the department developed an evaluation plan. A total of $1.1 million has been reserved for conducting process, outcome, and economic evaluations of the BLER program and two other bushfire recovery grant programs.

To assist with evaluating program outcomes and economic impact, the department is planning a post-completion survey in 2023–24. This timeline will allow most projects to be completed and enough time for project outcomes to be realised. The department advised that the data collected through this survey would allow the department to determine whether the BLER program has achieved its objectives, as it includes information such as the number of jobs created through each project.

The process evaluation was initially planned for March to June 2021. This would have aligned with the announcement of the open round funding and would have allowed for the learnings from rounds one and two of the BLER program to be applied to the development of round three. However, the department did not conduct this evaluation in a timely way. The department advised that this was because funding deed negotiations were still ongoing, and the department was waiting for 50% of funding deeds to be signed. Given this, the department was not in a position to commence its process evaluation. In December 2021, the department revised its evaluation plan and advised that it commenced its process evaluation in April 2022. It is unlikely that this will allow time for the department to apply learnings to round three, which is currently underway.

Appendix one – Responses from agencies

Appendix two – BLER program distribution

Appendix three – About the audit

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #373 - released 2 February 2023

Published

Actions for Design and implementation of the Transport Asset Holding Entity

Design and implementation of the Transport Asset Holding Entity

Transport
Treasury
Asset valuation
Financial reporting
Infrastructure
Procurement
Risk
Service delivery

What the report is about

The Transport Asset Holding Entity (TAHE) is the State's custodian of rail assets. It is a state owned corporation and commenced operating on 1 July 2020.

This audit assessed the effectiveness of NSW Government agencies' design and implementation of TAHE. We audited TAHE, Transport for NSW (TfNSW) and NSW Treasury.

Separate and related audits on TAHE are reported in 'State Finances 2022', 'State Finances 2021' and 'Transport and Infrastructure 2022' reports.

What we found

The design and implementation of TAHE, which spanned seven years, was not effective.

The process was not cohesive or transparent. It delivered an outcome that is unnecessarily complex in order to support an accounting treatment to meet the NSW Government's short-term Budget objectives, while creating an obligation for future governments.

The benefits of TAHE were claimed in the 2015–16 NSW Budget before the enabling legislation was passed by Parliament in 2017. This committed the agencies to implement a solution that justified the 2015–16 Budget impacts, regardless of any challenges that arose.

Rail safety arrangements were a priority throughout TAHE's design and implementation, and risks were raised and addressed.

Agencies relied heavily on consultants on matters related to the creation of TAHE, but failed to effectively manage these engagements. Agencies failed to ensure that consultancies delivered independent advice as an input to decision-making. A small number of firms were used repeatedly to provide advice on the same topic. The final cost of TAHE-related consultancies was $22.6 million compared to the initial estimated cost of $12.9 million.

What we recommended

We recommended that the audited agencies should:

  • improve accountability and transparency for major new fiscal transformation initiatives
  • ensure entities do not reflect the financial impact of significant initiatives in the Budget when there is uncertainty, or it creates perverse incentives
  • review record keeping practices, systems and policies to ensure compliance with the State Records Act 1998, and the NSW Government Information Classification, Labelling and Handling Guidelines
  • review procurement policies to ensure that consultant use complies with all NSW Government policy requirements.

The NSW Government established the Transport Asset Holding Entity (TAHE), a statutory State Owned Corporation (SOC), on 1 July 2020 to replace the former rail infrastructure owner – RailCorp. It is the State's custodian of rail network assets, including rail tracks and other infrastructure, rolling stock, land, train stations and facilities, retail space, and signal and power systems, within metropolitan and regional New South Wales. It is responsible for $2.8 billion of major capital projects in 2022–23.

TAHE was established under Part 2 of the Transport Administration Act 1988 and is governed by a decision-making board. The Treasurer and the Minister for Finance and Employee Relations are the Shareholding Ministers of TAHE, and they annually agree performance expectations articulated in a Statement of Corporate Intent.

Whereas TAHE is the custodian of rail assets, Sydney Trains and NSW Trains operate public rail services. TAHE does not have responsibility for the operation of the heavy rail network or train services, nor does it have network control functions. TAHE, Sydney Trains and NSW Trains are in the Transport and Infrastructure cluster in the public sector (formerly the Transport cluster and renamed in April 2022), which also includes Sydney Metro and Transport for NSW (TfNSW).

TfNSW leads the Transport and Infrastructure cluster. Its role is to set the strategic direction for transport across the State. This involves the shaping of planning, policy, strategy, regulation, resource allocation and other service and non-service delivery functions for all modes of transport.

TAHE's Operating Licence is granted by the Portfolio Minister and authorises the entity to perform the functions required to acquire, develop, finance, divest and hold assets, pursuant to the Transport Administration Act 1988. The Portfolio Minister also issues a Statement of Expectations which outlines the government’s expectation for the business for the next three to five years.

TAHE's original Portfolio Minister was the Minister for Transport who approved, on 30 June 2020, the issuing of an interim 12-month Operating Licence to enable TAHE to commence operating on 1 July 2020. The Portfolio Minister then granted TAHE's current Operating Licence in 2021. After TAHE requested a 12-month extension to its current Operating Licence, its next Operating Licence is due on 1 July 2024. The current Portfolio Minister is the Minister for Infrastructure, Cities and Active Transport.

About this audit

This audit assessed the effectiveness of NSW Government agencies' design and implementation of TAHE. In making this assessment, we considered whether: 

  • the process of designing and implementing TAHE was cohesive and transparent, and delivered an effective outcome
  • agencies' roles and responsibilities were clear in the planning of TAHE
  • agencies effectively identified and managed certain risks.

Conclusion

The design and implementation of TAHE was not effective. The process was not cohesive or transparent. It delivered an outcome that is unnecessarily complex in order to meet the NSW Government's short-term Budget objectives, while creating an obligation for future governments to sustain TAHE through continuing investment, and funding of the state owned rail operators. The ineffective process to design TAHE delivered a model that entails significant uncertainty as to whether the anticipated longer-term financial improvements to the Budget position can be achieved or sustained.

NSW Treasury and TfNSW had different objectives for TAHE

Up to June 2013, RailCorp had been the owner and operator of rail services and maintainer of the metropolitan rail network for almost a decade. It had been operating as a not-for-profit Public Non-Financial Corporation (PNFC).

In 2012, NSW Treasury (hereafter Treasury) decided there was a risk that the Australian Bureau of Statistics (ABS) would reclassify RailCorp to the General Government Sector (GGS), meaning depreciation expenses of approximately $870 million would be reflected in the GGS Budget. Treasury wanted to avoid this impact on the GGS Budget, and considered the establishment of a transport asset holding entity as a means to do so. Capital grants to RailCorp were being treated as an expense to the GGS Budget.

TfNSW also wanted an asset holding entity – but one that would be a non-trading ‘shell’ company with no staff that would hold and manage all public transport assets. TfNSW's concept envisaged the entity would have a structure that would enable future public transport reforms and strategic directions while ensuring vertical integration of operations between asset owners and the rail operators to maintain rail safety.

However, Treasury pursued its objective to improve the GGS Budget result, and sought to expand on TfNSW's 'shell' asset holding entity concept. Treasury wanted an entity that could generate a return on investment, as this meant that government investment in transport assets could be treated as equity investments, rather than a Budget expense, and in turn improve the GGS Budget position. As an example of the potential impact of creating this new entity, capital grants of $2.3 billion were paid to RailCorp in 2013–14. If Treasury's objective was met, grants of this significance would then be treated as an equity investment, rather than an expense in the GGS Budget.

In 2017, Treasury's preferred option was progressed through legislation, but both agencies' central objectives for the proposed asset holding entity would continue to prove difficult to reconcile. To achieve Treasury's objective to improve the Budget result, the entity would need to generate a return on investment (this is further discussed below). However, TfNSW expressed concerns that the prioritisation of rail safety, and the effective management of governance, regulation and operations would be more complex in an entity with commercial imperatives.

Asset holding entities are a common approach to the management of transport assets in Australia and internationally, and there are a range of approaches to how they are structured and used. Such structures should be driven by the goal of improved asset management. Ultimately, TfNSW's objectives could have been delivered through a simpler entity structure. However, reconciling TfNSW's objectives with Treasury's imperative to deliver and justify a Budget improvement in the short-term resulted in an overly lengthy process and an unnecessarily complex outcome that places an obligation on future governments to sustain. There is still significant uncertainty as to whether the short-term improvements to the Budget can continue to be realised in the longer-term.

The Budget benefits of TAHE were claimed before the entity was legislated, committing the agencies to deliver, regardless of the complexities that subsequently arose

The 2015–16 GGS Budget treated the government's investment in TAHE (still known at this time as RailCorp) as an equity contribution. This had the immediate impact of improving the Budget result by $1.8 billion per annum. However, the legislation to enable the establishment of TAHE had not yet been passed by Parliament, key elements of the operating model were still under development, and imminent changes in accounting standards had the potential to impact TAHE's financial model. The decision to book the benefits in the Budget early committed the involved agencies to implement a solution that justified the 2015–16 Budget impacts, irrespective of the challenges that arose. 

TAHE's financial structure requires circular government investment to work

For the NSW Government to continue to treat its investment in TAHE as an equity contribution, rather than an expense to the Budget, there must be a reasonable expectation that TAHE will generate a sufficient rate of return as required by the Government Finance Statistics (GFS) framework. In doing so, it needs to recover a revaluation loss created by a $20.3 billion reduction in the value of its assets which was incurred in its first full year of operation. This loss occurred as a result of a revaluation of TAHE's assets when RailCorp (a not-for profit entity) became TAHE (a for-profit commercial entity) – and is discussed further in the 'Key findings' below.

TAHE generates a small portion of its income from transactions with the private sector but, as noted in our report 'State Finances 2021', TAHE receives the majority of its revenue (more than 80%) from access and licence fee agreements with Sydney Trains and NSW Trains. Both of these entities are funded by grants (a Budget expense) to TfNSW from the GGS Budget.

Based on Treasury’s correspondence with the ABS in 2015, TAHE was initially expected to pay a return on equity of 7% in 2016–17. The assumption of a 7% return persisted through to 2018, after the legislation enabling the establishment of TAHE was passed by Parliament. However, when the initial access and licence fees were agreed on 1 July 2020, this figure had been revised to an expected rate of return of 1.5% excluding the revaluation loss. This was below the long-term inflation target and did not include the recovery of the revaluation loss – risking the government's ability to treat its investment in TAHE as an equity contribution. Importantly, as TAHE is primarily reliant on fees paid by the state owned rail operators that, in turn, are funded by the GGS Budget (as an expense), the decision to change the returns model from 7% to 1.5% would in its own right have had a positive impact on the GGS Budget. However, the decision to use a 1.5% return would ultimately be problematic as it made it difficult to treat the government's contributions to TAHE as an equity investment, as discussed below.

On 14 December 2021, to avoid a qualified audit opinion, the NSW Government made the decision to increase TAHE's expected rate of return to 2.5%, equal to the Reserve Bank’s long-term inflation target.

In 2021-22, TAHE needed to start charging rail operators higher access and licence fees in order to generate a return of 2.5%, so as to support the government's treatment of its investment in TAHE as an equity contribution in the GGS Budget. This meant the government needed to provide additional grant (expense) funding to the state owned rail operators so they could pay the increased access and licence fees to TAHE. Based on current projections, TAHE is not expected to recover the revaluation loss until 2046.

There remains a risk that TAHE will not be able to generate a sufficient return on the NSW Government's investment without relying on increased funding to state owned rail operators so that they can in turn pay the higher access and licence fees. TAHE's ability to generate returns on government investment from other sources are uncertain and may not be achievable or sustainable. Current modelling highlights that TAHE remains largely reliant, through to 2046, on increasing fees (which are assumed to increase at 2.5% per annum from 2031 onwards when the current 10 year contracts with rail operators expire) paid by the state owned rail operators that remain principally reliant on GGS Budget grants.

The process of designing and implementing TAHE was not transparent to independent scrutiny

Our report 'State Finances 2021' commented that Treasury did not always provide this Office with information relating to TAHE on a timely basis. Similarly, during this performance audit, there were also multiple instances where auditees were unable to provide documentation regarding key activities in the process to deliver TAHE. Agencies also applied higher sensitivity classifications to large tranches of documents than was justified or required by policy. Of particular concern is the incorrect classification of documents as Cabinet sensitive information. The incorrect or over-classification of documentation as Cabinet sensitive delayed this Office's ability to provide scrutiny or independent assurance.

There was a lack of clarity around the roles and responsibilities of governance structures set up to oversee the design and implementation of TAHE

From 2014, multiple workstreams and advisory committees were established to progress the design and implementation of TAHE. For some of these committees and workstreams, there is limited information on what they were tasked to do and what they achieved. Most had ceased meeting by 2018, before significant work needed to deliver TAHE was completed.

The lack of clarity around the roles and responsibilities of these governance structures reduced opportunities for TfNSW and Treasury to reconcile their differing objectives for TAHE, and resolve key questions earlier in the process.

There was a heavy reliance on consulting firms throughout the process to establish TAHE, and the management of consultant engagements failed to ensure that agencies received independent advice to support objective decision-making

In 2020, Treasury and TfNSW failed to prevent, identify, or adequately manage a conflict of interest when they engaged the same 'Big 4' consulting firm to work on separate TAHE-related projects. Both agencies used the firm's work to further their respective views with regard to the financial implications of TAHE's operating model. At this time those views were still unreconciled.

Treasury engaged the firm to provide a fiscal risk management strategy and advice on the impact of changes to accounting standards. TfNSW engaged the same firm to develop operating and financial models for TAHE, which raised concerns regarding the viability of TAHE. Disputes arose around the findings of these reports. Treasury disagreed with some of the outcomes of the work commissioned by TfNSW, relating to accounting treatment and fiscal advice.

The management of this conflict (real or perceived) was left to the 'Big 4' consulting firm when it was more appropriate for it to be managed by Treasury and TfNSW. If these agencies had communicated more effectively, used available governance structures consistently, and shared information openly about their use of the firm and the nature of their respective engagements, these disputes might have been avoided. This issue, coupled with deficiencies in procurement by both agencies, reflected and further perpetuated the lack of cohesion in the design and implementation of TAHE.

More broadly, over the period 2014 – 2021, 16 separate consulting firms were employed to work on 36 contracts, valued at over $22.56 million, relating to TAHE ranging from accounting and legal advice, project management, and the provision of administrative support and secretariat services.

Consultants are legitimately used by agencies to provide advice on how to achieve the outcomes determined by government, including advising agencies on the risks and challenges in achieving those outcomes. Similarly, consultants can provide expert knowledge in the service of achieving those outcomes and managing the risks. However, the heavy reliance on consulting firms during the design and implementation of TAHE heightened the risk that agencies were not receiving value for money, were outsourcing tasks that should be performed by the public service, and did not mitigate the risk that the advice received was not objective and impartial. The risk that the role of consultants could have been blurred between providing independent advice to government on options and facilitating a pre-determined outcome was not effectively treated or mitigated. This risk was amplified because a small number of firms were used repeatedly to provide advice on one topic. The effective procurement and management of consultants is an obligation of government agencies.

Appendix one – Responses from audited agencies, and Audit Office clarification of matters raised in the TAHE formal response 

Appendix two – Classification of government entities 

Appendix three – About the audit 

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #372 - released 24 January 2023

 

Published

Actions for Effectiveness of the Biodiversity Offsets Scheme

Effectiveness of the Biodiversity Offsets Scheme

Planning
Environment
Infrastructure
Internal controls and governance
Management and administration
Regulation

What the report is about

This audit examined whether the Department of Planning and Environment (DPE) and the Biodiversity Conservation Trust (BCT) have effectively designed and implemented the Biodiversity Offsets Scheme (‘the Scheme’) to compensate for the loss of biodiversity due to development.

Under the Biodiversity Conservation Act 2016, the Scheme enables landholders to establish in-perpetuity Biodiversity Stewardship Agreements on sites to generate credits for the unique biodiversity on that land. These credits can be sold to offset the negative impact of development on biodiversity.

What we found

DPE has not effectively designed core elements of the Scheme. DPE did not establish a clear strategic plan to guide the implementation of the Scheme.

The BCT has various roles in the Scheme but lacked safeguards against potential conflicts, creating risks to credit supply.

The effectiveness of its implementation has also been limited. Key concerns around the Scheme’s transparency, sustainability and integrity are yet to be fully resolved.

A market-based approach to biodiversity offsetting is central to the Scheme's operation but credit supply is lacking and poorly matched to growing demand. DPE has not established a clear, resourced plan to manage the shortage in credit supply. Data about the market, published by the DPE and the BCT, does not provide an adequate picture of credit supply, demand and price to readily support market participation.

These factors create a risk that biodiversity gains made through the Scheme will not be sufficient to offset losses resulting from development, and that the DPE will not be able to assess the Scheme’s overall effectiveness.

DPE is leading work with the BCT to improve the Scheme, but this is not yet guided by a long-term strategy with clear goals.

What we recommended

The audit made 11 recommendations to DPE and the BCT, focusing on:

  • a long-term strategic plan for the Scheme
  • improvements to the operation and transparency of the market and credit supply
  • frameworks to ensure the financial and ecological sustainability of biodiversity stewardship sites
  • enhanced public reporting and data management
  • resolving issues in conflicting governance and oversight.

 

 Fast facts

  • 96% –  proportion of developer demand for species credits not met by current supply
  • 97% – proportion of species credits that have never been traded on the biodiversity market
  • 60% – proportion of the 226 Biodiversity Stewardship sites under active land management
  • $90m – value of developers’ obligations paid directly into the Biodiversity Conservation Fund
  • 20% – proportion of developer obligations transferred to the BCT that have been acquitted.

The NSW Government's Biodiversity Outlook Report 2020 estimates that, without effective management, only 50% of species and 59% of ecological communities that are listed as threatened in New South Wales will still exist in 100 years. The NSW State of the Environment 2021 report identifies habitat destruction and native vegetation clearing as presenting the single greatest threat to biodiversity in the State.

According to the Organisation for Economic Co-operation and Development (OECD), biodiversity offsets are 'measurable conservation outcomes that result from actions designed to compensate for significant, residual biodiversity loss from development projects'. The OECD states that a feature of such schemes is that biodiversity offsets are intended to be implemented as the 'final step of a mitigation hierarchy' whereby reasonable first steps are taken to avoid and minimise the negative impacts.

The NSW Biodiversity Offsets Scheme was established in 2017 under the Biodiversity Conservation Act 2016 (the Act). The purpose of the Act is to 'maintain a healthy, productive and resilient environment for the greatest well-being of the community, now and into the future, consistent with the principles of ecologically sustainable development'.

The Department of Planning and Environment (DPE) designed and manages this Scheme. Under the Act, a feature of the Scheme is a 'market-based conservation mechanism through which the impacts to biodiversity can be offset.' The Scheme enables landholders to establish in-perpetuity Biodiversity Stewardship Agreements (BSAs) on sites to generate biodiversity credits, which can be sold to offset the negative impact of development on biodiversity. BSA sites are intended to be managed over the long term to generate the biodiversity gains required to offset the impact.

The Biodiversity Conservation Trust (BCT) monitors and supports landholders to manage BSA sites under the Scheme. This includes making payments to landholders from funds held in the Biodiversity Stewardship Payments Fund for undertaking the required biodiversity management actions.

This Scheme was preceded by several other offsetting schemes in New South Wales, including the BioBanking scheme that started in 2008. DPE has arrangements to transition sites, credits, and offset obligations from this and other previous schemes.

The current biodiversity credit market in New South Wales consists of 1394 different types of ecosystem credits, which are approved to be traded in 364 different offset trading groups, and 867 different species credits. Trading rules, set out in the Biodiversity Conservation Regulation 2017 (the Regulation), prioritise offsetting the obligations of a development with like-for-like ecosystem or species credits.

The Scheme is implemented through the planning system in New South Wales. Proposed development that involves the clearing of native vegetation, and meets certain thresholds, is required to undertake a Biodiversity Development Assessment Report. These reports determine an offset obligation, in biodiversity credits, to compensate for the biodiversity loss proposed. These reports are considered by consent authorities (such as a council, for local development, or by the Minister for Planning for major projects). An offset obligation is then included in the conditions of development approval.

In addition to establishing a market for trading between developers, with offset obligations, and landholders, who sell credits from their BSA sites, the Scheme allows developers to pay into the Biodiversity Conservation Fund and transfer their obligations to the BCT. This allows the developer to proceed with their project. The BCT must then meet these acquired obligations by buying the required credits, or by undertaking other approved activities set out in the Regulation. The BCT has more options than developers on how and when it acquits its obligations.

This audit examined whether DPE and the BCT have effectively designed and implemented the Biodiversity Offsets Scheme to compensate for the loss of biodiversity due to development.

Conclusion

The Department of Planning and Environment (DPE) has not effectively designed core elements of the NSW Biodiversity Offsets Scheme. DPE did not establish a clear strategy to develop the biodiversity credit market or determine whether the Scheme’s operation and outcomes are consistent with the purposes of the Biodiversity Conservation Act 2016.

The effectiveness of the Scheme's implementation by DPE and the BCT has been limited. A market-based approach to biodiversity offsetting is central to the Scheme's operation but credit supply is lacking and poorly matched to growing demand: this includes a potential undersupply of in-demand credits for numerous endangered species. Key concerns around the Scheme’s integrity, transparency, and sustainability are also yet to be fully resolved. As such, there is a risk that biodiversity gains made through the Scheme will not be sufficient to offset losses resulting from the impacts of development, and that DPE will not be able to assess the Scheme’s overall effectiveness.

DPE developed the Scheme following a 2014 review of the State's biodiversity legislation and building on previous offsetting arrangements in New South Wales. At the time the Scheme commenced in 2017, DPE lacked a strategic plan to guide its implementation, set clear outcomes and performance measures, and respond effectively to risks. DPE did establish a detailed scientific method for assessing biodiversity impacts under the Scheme and a system for accrediting assessors to undertake this technical work. These are important foundations for the robustness of the Scheme.

The Scheme has been in place for five years, but the biodiversity credit market is not well developed. Most credit types have never been traded. Also, according to DPE data, around 90% of demand cannot be matched to credit supply – and there is likely to be a substantial credit undersupply for at least seven endangered flora species, three endangered fauna species, and eight threatened ecological communities. Credit demand is projected to grow – especially in relation to the NSW Government’s $112.7 billion four-year infrastructure pipeline.

As with any market, potential participants need information about demand and price in order to understand risks and opportunities. But information about the biodiversity credit market, published by DPE and the BCT, does not provide an adequate picture of credit supply, demand and price to support market participation. This can create uncertainty for landholders who may be weighing the costs and benefits of establishing Biodiversity Stewardship Agreement (BSA) sites, and for development proponents who need to know whether they can purchase sufficient credits and at what price. Development proponents who lack market information are being incentivised to meet their offset obligations by paying into the Biodiversity Conservation Fund, which is managed by the BCT. This option provides developers with more certainty that enables them to progress their projects, but does not result in the development being offset until the BCT later acquits the obligation.

The BCT has multiple roles in the Scheme. These include setting-up and administering BSAs which generate credits, acquiring offset obligations from developers who pay into the Biodiversity Conservation Fund, and purchasing credits to meet its acquired obligations. There have been inadequate safeguards to mitigate the potential for conflicts between these roles. As the BCT directs its efforts towards facilitating BSA sites and purchasing credits to meet its obligations, there is a risk that government is insufficiently focused on supporting overall credit supply.

DPE has begun developing a credit supply strategy. Its absence, and a lack of clarity around responsibility for credit supply under the Scheme, has contributed to the significant risk of insufficient and poorly matched credits to meet the growing demand. The BCT's acquired obligations from developers have been increasing year-on-year, and are likely to continue to grow. 

There is a risk that the BCT will not have sufficient funds to acquit its growing obligations with like-for-like credits, which could result in sub-optimal biodiversity outcomes. The Scheme rules allow the BCT to acquit its obligations with measures other than like-for-like credits. DPE has not provided clear guidance to the BCT on when or how to do so, or how this would fulfil the 'no net loss' of biodiversity standard.

There are transparency and integrity risks to the Scheme. DPE does not maintain a public register of biodiversity credits with complete information, including credits' transaction histories, consistent with the legislative intent for a single register. DPE also does not have ready access to information to check that developments have been acquitted with the required credits.

Risks to the sustainability of the Scheme and its outcomes remain. DPE and the BCT have not yet implemented a decision-making and intervention framework to ensure adequate initial and ongoing funding for the long-term management of new and existing BSA sites. DPE also did not collect ecological data from sites under previous schemes before they were transitioned, and BCT only introduced ecological monitoring requirements for new BSA sites in March 2021. The lack of monitoring requirements creates a risk that the biodiversity gains, which BSA sites are required to generate to offset biodiversity losses, will not be measured and achieved under the Scheme.

This section presents an overview of the status of the biodiversity credit market in New South Wales. It describes development of the market under the Scheme in the context of transitional arrangements from previous schemes, and the extent of market participation and transactions to date. It also presents information about emerging trends in credit demand and supply.

Background

A purpose of the Biodiversity Conservation Act 2016 (the Act) is to establish a market-based conservation mechanism through which impacts on biodiversity can be offset. Sufficient credits of appropriate types, which are well matched to demand, are necessary for enough transactions to inform prices and enable efficient like-for-like offsetting. For transactions to occur efficiently in the market, participants require reliable and easy-to-access information about supply, demand and price.

The Scheme was established in 2017 with an existing credit supply and offset obligations (credit demand) as regulations had been introduced to preserve and transition credits and obligations from previous schemes including the BioBanking Scheme, which started in 2008.

Credits under the BioBanking scheme are referred to as 'BBAM credits', and credits under the current Scheme are referred to as 'BAM credits'. BBAM credits are still available, and the transitional arrangements enable DPE to determine the 'reasonable equivalence' of these to the current Scheme's credit numbers and classes. DPE has stated that reasonable equivalence of credits is based on ecological not financial equivalence. 

This section assesses the clarity and alignment of the goals of the Scheme to key features of its design and operations. It also examines structural elements of the Scheme that aim to maintain integrity within administering agencies, and the status of actions to address risks or issues.

Background

The Biodiversity Conservation Act 2016 (the Act) sets out the legal framework for the Scheme. Given the complexities, financial interests, and range of stakeholders associated with the Scheme, it requires strong safeguards. Transparency and assurances around the Scheme's integrity are also relevant to participants' confidence in it, which in turn is important for market development.

Core components of the Scheme, identified in section 1.3 of the Act, are to be consistent with the ‘principles of ecologically sustainable development’.

The Act and other administrative arrangements of government allocate responsibility to DPE and the Minister for Environment and Heritage for the Scheme’s design and elements of its implementation. This includes responsibility for the Scheme’s policy, legislative and regulatory framework.

Responsibility is allocated to the BCT for implementing and operating certain elements of the Scheme. This includes administering Biodiversity Stewardship Agreements (which generate credits) and securing offsets on behalf of development proponents who pay into the Biodiversity Conservation Fund to meet their offset obligations.

This broad legislative framework is not intended to detail responsibilities for the full range of roles and activities that agencies need to take to implement and regulate the Scheme effectively, and ensure its good governance. Agencies should do this as part of sound and transparent public administration. 

This section assesses how effectively components of the Scheme have been designed and are being implemented to provide assurance that the impacts of development are being avoided and minimised such that only ‘unavoidable’ impacts remain to be offset. The section also assesses whether the Scheme and its market embeds the necessary controls to ensure that obligations are offset as required.

Background

The Biodiversity Assessment Method, and the quality of its application by DPE-Accredited Assessors, is critical to the robustness the Scheme. The method is designed to be applied to avoid and minimise impacts at proposed development sites before identifying offset obligations. The effectiveness of Scheme outcomes requires that obligations are offset with the retirement of the necessary and appropriate credits.

The Biodiversity Conservation Act 2016 (the Act) requires the relevant Minister (the current Minister for Environment and Heritage) to establish a method for the purpose of assessing the impacts of actions on threatened species and ecological communities.

The Act also specifies that this method must be applied by an accredited person. DPE is responsible for the design and implementation of this accreditation system, arrangements for which are set out in an instrument under the Act.

A Biodiversity Development Assessment Report is a report by a DPE-Accredited Assessor using the Biodiversity Assessment Method. These reports assess the biodiversity impacts of the proposed development and establish offset obligations as part of the development approval process. It is important that local councils and other development consent authorities understand and can assess the quality of these reports.

DPE manages the process of ‘retiring’ credits against the identified offset obligations. Once a credit is retired it cannot be reused to acquit another obligation, which is critical to Scheme outcomes. DPE is also responsible for maintaining records of credit transactions, which results in a legally binding transfer of credit ownership from seller to buyer. 

This section assesses how effectively the supply of biodiversity credits has been supported by encouraging and enabling landholders to participate in the Scheme. It also assesses whether sufficient action is underway to address issues and risks to the establishment of BSA sites, especially in the context of known credit supply issues (section 2).

Background

Credit supply is generated when a landholder establishes a Biodiversity Stewardship Agreement (BSA) on their land. Establishing a BSA site requires landholders agree to an in-perpetuity management plan, so it is important that they have sufficient support and access to relevant information about risks and opportunities when deciding to do so. Ensuring adequate credits supply underpins the Scheme's ability to deliver the intended biodiversity outcomes.

A landholder establishes an offset site through a BSA, which is a legal agreement with the Minister of Environment and Heritage (delegated to the Biodiversity Conservation Trust). The BSA is registered on the title of the land.

DPE-Accredited Assessors develop Biodiversity Stewardship Site Assessment Reports, which are submitted by landholders to the BCT as part of the BSA application. These reports apply the Biodiversity Assessment Method to detail the number and types of credits that a BSA site is expected to generate by implementing a 20-year management plan. The BCT issues credits to landholders on registration of the BSA.

Ensuring an adequate and appropriate supply of credits is important so that like-for-like matches between credits and obligations can be efficiently secured in a timely way. This minimises the use of offset variation rules, and can avoid potential delays in developers securing appropriate offsets to meet their offset obligations. It also makes it easier for the BCT to locate the necessary credits to acquit the obligations it acquires from developers. 

This section assesses how effectively BSA sites, which need to be managed by landholders to generate the biodiversity gains represented by credits, are regulated and supported by the Biodiversity Conservation Trust. It also assesses whether actions have been taken to address identified risks to the suitability of funds required to ensure long-term BSA site management.

Background

For Biodiversity Stewardship Agreement (BSA) sites to achieve the expected biodiversity gains to offset losses from development impact, they need sufficient funding for the required management actions, and to be effectively regulated and supported over the long-term. Funding for these sites is generated through the returns on landholders' initial investment (Total Fund Deposit). The BCT is required to monitor landholders' compliance with BSAs and should also ensure ecological outcomes on sites are measured.

DPE and the BCT are responsible for developing and implementing a system of oversight to ensure the implementation of management actions at BSA sites is delivering the intended outcomes in a financially and environmentally sustainable way. The agencies' key mechanisms for delivering this are:

  • calculating the costs of the required land management actions in perpetuity
  • annual reporting systems for monitoring compliance with land management requirements
  • reporting systems for monitoring ecological outcomes arising from land management actions.

Landholders are required to pay the required Total Fund Deposit amount for their BSA accounts into the Biodiversity Stewardship Payments Fund, which is held in trust and managed by the BCT. A costing tool is used by landholders to calculate the value of the deposit, based on the required management payments (in perpetuity), administrative fees, and the discount rate applied.

The Total Fund Deposit can be paid upfront but is usually paid from the proceeds of the sale of credits. Once this occurs the BSA site becomes 'active' and management payments commence to enable the landholder to undertake the required management actions. BSA sites that have not yet sold enough credits to make the deposit are 'passive' sites that do not require active land management.

Sites in passive management for an extended duration present risks to biodiversity outcomes, and potentially to Scheme integrity, if the quality of credits is undermined due to an absence of active site management. 

Appendix one – Response from agencies 

Appendix two – Like-for-like, variation and ancillary rules

Appendix three – Detail on progress of the IIAP

Appendix four – About the audit 

Appendix five – Performance auditing 

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #367 - released 30 August 2022

Published

Actions for Rail freight and Greater Sydney

Rail freight and Greater Sydney

Transport
Information technology
Infrastructure
Management and administration
Project management
Service delivery

What the report is about

The movement of freight contributes $66 billion annually to the NSW economy. Two thirds of all freight in NSW moves through Greater Sydney, and the volume of freight moving through Greater Sydney is expected to increase by 48 per cent by 2036.

This audit assessed the effectiveness of transport agencies in improving the use of rail freight capacity in Greater Sydney, and to meet current and future freight demand.

What we found

Transport agencies do not have strategies or targets in place to improve the efficiency or capacity of the metropolitan shared rail network for freight.

The transport agencies acknowledge that they do not have sufficient information to achieve the most efficient freight outcomes and they do not know how to use the shared rail network to maximise freight capacity without compromising passenger rail services.

The Freight and Ports Plan 2018-2023 contains one target for rail freight - to increase the use of rail at Port Botany to 28 per cent by 2021. However, Transport for NSW (TfNSW)'s data indicates this target will not be met.

Sydney Trains records data on train movements and collects some data on delays and incidents. TfNSW collects data for the construction of the Standard Working Timetable and third-party contracts.

However, a lack of clarity around what data is gathered and who has ownership of the data makes data sharing difficult and limits its analysis and reporting.

The Freight and Ports Plan 2018-2023 includes the goal of 'Reducing avoidable rail freight delays', but the transport agencies do not have any definition for an avoidable delay and, as a result, do not measure or report them.

TfNSW and Sydney Trains are appointed to manage and deliver the Transport Asset Holding Entity of New South Wales (TAHE)'s obligations to allow rail freight operators to use the shared rail network. There are no performance measures in rail freight operator contracts or inter-agency agreements. This limits transport agencies' ability to improve performance.

TfNSW’s Freight Branch is working on four freight-specific strategies; a review of the Plan, a freight rail strategy, a port efficiency strategy and a freight data strategy.

TfNSW has not yet determined the timeframes or intended outcomes of these strategies.

What we recommended

Transport agencies should:

  • commit, as part of the review of Future Transport 2056, to delivering the freight-specific strategies currently in development and develop whole-of-cluster accountability for this work including timeframes, specific targets and clear roles and responsibilities 
  • improve the collection and sharing of freight data
  • develop a plan to reduce avoidable freight delays
  • systematically collect data on the management of all delays involving and/or impacting rail-freight
  • develop and implement key performance indicators for the agreements between the transport agencies.

Fast facts    

  • 288 million tonnes of freight volume predicted to pass through Greater Sydney in 2036, up from 194 million in 2016 (an increase of 48%)

  • 54 trucks that can be replaced by one 600 m long port shuttle freight train    

  • 26,671 freight trains that passed through the metropolitan shared rail network between 1 July 2020 and 30 June 2021

The movement of freight contributes $66.0 billion annually to the New South Wales economy — or 13 per cent of the Gross State Product. Two thirds of all freight in New South Wales moves through Greater Sydney, and the volume of freight moving through Greater Sydney is expected to increase by 48 per cent by 2036. This increasing demand is driven by increasing population and economic growth.

The sequence of activities required to move goods from their point of origin to the eventual consumer (the supply chain) is what matters most to shippers and consumers. Road can provide a single-mode door-to-door service, whereas conveying goods by rail typically involves moving freight onto road at some point. In Greater Sydney, 80 per cent of all freight is moved on road. Freight often passes through intermodal terminals (IMTs) as it transitions from one mode of transport to the next.

In 2016, Transport for NSW (TfNSW) released Future Transport 2056 - the NSW Government's 40-year vision for transport in New South Wales, which is intended to guide investment over the longer term. In Future Transport 2056, TfNSW noted that New South Wales will struggle to meet increasing demand for freight movements unless rail plays a larger role in the movement of freight.

Sydney Trains manages the metropolitan shared rail network, which is made up of rail lines that are used by both passenger and freight trains. The Transport Administration Act 1988 requires that, for the purposes of network control and timetabling, NSW Government transport agencies give ‘reasonable priority’ to passenger trains on shared lines. As the Greater Sydney population and rail patronage continue to grow, so too will competition for access to the shared rail network. See Appendix two for details of the area encompassed by Greater Sydney.

Freight operators can also use dedicated rail freight lines operated by the Australian Rail Track Corporation (ARTC - an Australian Government statutory-owned corporation). As the metropolitan shared rail network connects with dedicated freight lines, freight operators often use both to complete a journey.

TfNSW, Sydney Trains and the Transport Asset Holding Entity (TAHE) work in conjunction with other rail infrastructure owners and private sector entities, including port operators, privately operated IMTs and freight-shipping companies. TfNSW and Sydney Trains are responsible for managing the movement of freight across the metropolitan shared rail network. TAHE is the owner of the rail infrastructure that makes up the metropolitan shared rail network. The NSW Government established TAHE, a NSW Government state-owned corporation, on 1 July 2020 to replace the former rail infrastructure owner - RailCorp. The Auditor-General for New South Wales has commenced a performance audit on TAHE which is expected to table in 2022.

On 1 July 2021, TAHE entered into new agreements with TfNSW and Sydney Trains to operate, manage and maintain the metropolitan shared rail network. Until 30 June 2021, and in accordance with TAHE's Implementation Deed, TAHE operated under the terms of RailCorp's existing arrangements and agreements.

This audit assessed the effectiveness of TfNSW, Sydney Trains and TAHE in improving the use of rail freight capacity in Greater Sydney, and to meet current and future freight demand.

The audit focused on:

  • the monitoring of access to shared rail lines
  • the management of avoidable delays of rail freight movements
  • steps to increase the use of rail freight capacity in Greater Sydney.

Conclusion

Transport agencies do not have clear strategies or targets in place to improve the freight efficiency or capacity of the metropolitan shared rail network. They also do not know how to make best use the rail network to achieve the efficient use of its rail freight capacity. These factors expose the risk that rail freight capacity will not meet anticipated increases in freight demand.

Future Transport 2056 notes that opportunities exist to shift more freight onto rail, and that making this change remains an important priority for the NSW Government. However, the transport agencies acknowledge that they do not have sufficient information to achieve the most efficient freight outcomes. In particular, transport agencies do not know how to use the shared rail network in a way that maximises freight capacity without compromising passenger rail services.

Neither Future Transport 2056 nor the Freight and Ports Plan 2018–2023 give any guidance on how transport agencies will improve the efficiency or capacity of the shared rail network. Other than a target for rail freight movements to and from Port Botany, which TfNSW's data indicates will not be met, there are no targets for improving rail freight capacity across the shared network. The lack of specific strategies, objectives and targets reduces accountability and makes it difficult for transport agencies to effectively improve the use of rail freight capacity in line with their commitment to do so.

Sydney Trains and Transport for NSW do not effectively use data to improve rail freight performance and capacity.

To drive performance improvement when planning for the future, transport agencies need good quality data on freight management and movements. Sydney Trains records data on train movements in real-time and collects some data on delays and incidents. TfNSW collects data for the construction of the Standard Working Timetable (SWTT) and third-party contracts. However, the different types of data gathered and the separation between the teams responsible mean that there is a lack of clarity around what data is gathered and who has ownership it. This lack of coordination prevents best use of the data to develop a single picture of how well the network is operating or how performance could be improved.

Sydney Trains' ability to evaluate the effectiveness of its incident and delay mitigation strategies is also limited by a lack of information on its management of rail-freight related delays or incidents. While Sydney Trains collects data on major incidents, it can only use this to conduct event-specific analysis on the causes of an incident, and to review the operational and management response. The use of complete and accurate incident data would assist to define, identify and reduce avoidable delays. Reducing avoidable delays is a goal of the Freight and Ports Plan 2018–2023. More complete data on all incidents would help TfNSW to have more effective performance discussions with rail freight operators to help improve performance.

TfNSW has started developing strategies to identify how it can use rail freight capacity to achieve efficient freight outcomes, but it has not committed to implementation timeframes for this work.

TfNSW’s Freight Branch has started work on four freight-specific strategies to improve freight efficiency: a review of the Plan, a freight rail strategy, a port efficiency strategy and a freight data strategy. However, none of these strategies will be fully developed before the end of 2022. TfNSW has not yet determined the implementation timeframes or intended outcomes of these strategies, although TfNSW reports that it is taking an iterative approach and some recommendations and initiatives will be developed during 2022. 

Appendix one - Response from agencies

Appendix two - The Greater Sydney region

Appendix three - TfNSW strategic projects 

Appendix four - Sydney Trains path priority principles 

Appendix five - Sydney Trains delay management

Appendix six - About the audit 

Appendix seven - Performance auditing
 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #357 - released (19 October 2021).

Published

Actions for Managing climate risks to assets and services

Managing climate risks to assets and services

Planning
Environment
Treasury
Industry
Infrastructure
Management and administration
Risk
Service delivery

What the report is about

This report assessed how effectively the Department of Planning, Industry and Environment (DPIE) and NSW Treasury have supported state agencies to manage climate risks to their assets and services.

Climate risks that can impact on state agencies' assets and services include flooding, bushfires, and extreme temperatures. Impacts can include damage to transport, communications and energy infrastructure, increases in hospital admissions, and making social housing or school buildings unsuitable.

NSW Treasury estimates these risks could have significant costs.

What we found

DPIE and NSW Treasury’s support to agencies to manage climate risks to their assets and services has been insufficient.

In 2021, key agencies with critical assets and services have not conducted climate risk assessments, and most lack adaptation plans.

DPIE has not delivered on the NSW Government commitment to develop a state-wide climate change adaptation action plan. This was to be complete in 2017.

There is also no adaptation strategy for the state. These have been released in all other Australian jurisdictions. The NSW Government’s draft strategic plan for its Climate Change Fund was also never finalised.

DPIE’s approach to developing climate projections is robust, but it hasn’t effectively educated agencies in how to use this information to assess climate risk.

NSW Treasury did not consistently apply dedicated resourcing to support agencies' climate risk management until late 2019.

In March 2021, DPIE and NSW Treasury released the Climate Risk Ready NSW Guide and Course. These are designed to improve support to agencies.

What we recommended

DPIE and NSW Treasury should, in partnership:

  • enhance the coordination of climate risk management across agencies
  • implement climate risk management across their clusters.

DPIE should:

  • update information and strengthen education to agencies, and monitor progress
  • review relevant land-use planning, development and building guidance
  • deliver a climate change adaptation action plan for the state.

NSW Treasury should:

  • strengthen climate risk-related guidance to agencies
  • coordinate guidance on resilience in infrastructure planning
  • review how climate risks have been assured in agencies’ asset management plans.

Fast facts

4 years

between commitments in the NSW Climate Change Policy Framework, and DPIE and NSW Treasury producing key supports to agencies for climate risk management.

$120bn

Value of physical assets held by nine NSW Government entities we examined that have not completed climate risk assessments.

Low capability to do climate risk assessment has been found across state agencies. The total value of NSW Government physical assets is $365 billion, as at 30 June 2020.

x3

NSW Treasury’s estimates of the annual fiscal and economic costs associated with natural disasters will triple by 2060–61.

According to the Intergovernmental Panel on Climate Change in 2021, each of the last four decades has been successively warmer and surface temperatures will continue to increase until at least the mid-century. The Commonwealth Scientific and Industrial Research Organisation (CSIRO) and the Bureau of Meteorology (BoM) have reported that extreme weather across Australia is more frequent and intense, and there have been longer-term changes to weather patterns. They also report sea levels are rising around Australia increasing the risk of inundation and damage to coastal infrastructure and communities.

According to the Department of Planning, Industry and Environment (the department), in New South Wales the impacts of a changing climate, and the risks associated with it, will be felt differently across regions, populations and economic sectors. The department's climate projections indicate the number of hot days will increase, rainfall will vary across the state, and the number of severe fire days will increase.

The NSW Government is a provider of essential services, such as health care, education and public transport. It also owns and manages around $365 billion in physical assets (as at June 2020). More than $180 billion of its assets are in major infrastructure such as roads and railway lines.

In NSW, climate risks that could directly impact on state agencies' assets and services include flooding, bushfires, and extreme temperatures. In recent years, natural hazards exacerbated by climate change have damaged and disrupted government transport, communications and energy infrastructure. As climate risks eventuate, they can also increase hospital admissions when people are affected by poorer air quality, and make social housing dwellings or schools unsafe and unusable during heatwaves. The physical impacts of a changing climate also have significant financial costs. Taking into account projected economic growth, NSW Treasury has estimated that the fiscal and economic costs associated with natural disasters due to climate change will more than triple per year by 2061.

The department and NSW Treasury advise that leading practice in climate risk management includes a process that explicitly identifies climate risks and integrates these into existing risk management, monitoring and reporting systems. This is in line with international risk management and climate adaptation standards. For agencies to manage the physical risks of climate change to their assets and services, leading practice identified by the department means that they need to:

  • use robust climate projection information to understand the potential climate impacts
  • undertake sound climate risk assessments, within an enterprise risk management framework
  • implement adaptation plans that reduce these risks, and harness opportunities.

Adaptation responses that could be planned for include: controlling development in flood-prone locations; ensuring demand for health services can be met during heatwaves; improving thermal comfort in schools to support student engagement; proactive asset maintenance to reduce disruption of essential services, and safeguarding infrastructure from more frequent and intense natural disasters.

According to NSW Treasury policy, agencies are individually responsible for risk management systems appropriate to their context. The department and NSW Treasury have key roles in ensuring that agencies are supported with robust information and timely, relevant guidance to help manage risks to assets and services effectively, especially for emerging risks that require coordinated responses, such as those posed by climate change.

This audit assessed whether the department and NSW Treasury are effectively supporting NSW Government agencies to manage climate risks to their assets and services. It focused on the management of physical risks to assets and services associated with climate change.

Conclusion

The Department of Planning, Industry and Environment (the department) has made climate projections available to agencies since 2014, but provided limited guidance to assist agencies to identify and manage climate risks. NSW Treasury first noted climate change as a contextual factor in its 2012 guidance on risk management. NSW Treasury only clarified requirements for agencies to integrate climate considerations into their risk management processes in December 2020.
The department has not delivered on a NSW Government commitment for a state-wide climate change adaptation action plan, which was meant to be completed in 2017. Currently many state agencies that own or manage assets and provide services do not have climate risk management in place.
Since 2019, the department and NSW Treasury have worked in partnership to develop a coordinated approach to supporting agencies to manage these risks. This includes guidance to agencies on climate risk assessment and adaptation planning published in 2021.
More work is needed to embed, sustain and lead effective climate risk management across the NSW public sector, especially for the state's critical infrastructure and essential services that may be exposed to climate change impacts.

The NSW Government set directions in the 2016 NSW Climate Change Policy Framework to 'manage the impact of climate change on its assets and services by embedding climate change considerations into asset and risk management’ and more broadly into 'government decision-making'.

The department released climate projections and has made information on projected climate change impacts available since 2014, but this has not been effectively communicated to agencies. The absence of a state-wide climate change adaptation action plan has limited the department's implementation of a coordinated, well-communicated program of support to agencies for their climate risk management.

NSW Treasury is responsible for managing the state's finances and providing stewardship to the public sector on financial and risk management, but it did not consistently apply dedicated resourcing to support agencies' climate risk management until late 2019. NSW Treasury estimates the financial costs of climate-related physical risks are significant and will continue to grow.

The partnership between the department and NSW Treasury has produced the 2021 Climate Risk Ready NSW Guide and Course, which aim to help agencies understand their exposure to climate risks and develop adaptation responses. The Guide maps out a process for climate risk assessment and adaptation planning and is referenced in NSW Treasury policy on internal audit and risk management. It is also referenced in NSW Treasury guidance to agencies on how to reflect the effects of climate-related matters in financial statements.

There is more work to be done by the department on maintaining robust, accessible climate information and educating agencies in its use. NSW Treasury will need to continue to update its policies, guidance and economic analyses with relevant climate considerations to support an informed, coordinated approach to managing physical climate risks to agencies' assets and services, and to the state's finances more broadly.

The effectiveness of the department and NSW Treasury's support involves the proactive and sustained take-up of climate risk management by state agencies. There is a key role for the department and NSW Treasury in monitoring this progress and its results.

Prior to 2021, support provided by the Department of Planning, Industry and Environment (the department) to agencies for managing physical climate risks to their assets and services has been limited. NSW Treasury has a stewardship role in public sector performance, including risk management, but has not had a defined role in working with the department on climate risk matters until mid-2019. The low capacity of agencies to undertake this work has been known to NSW Government through agency surveys by the department in 2015 and by the department and NSW Treasury in 2018.

The support delivered to agencies around climate risk management, including risk assessment and adaptation planning, has been slow to start and of limited impact. The department's capacity to implement a coordinated approach to supporting agencies has also been limited by the absence of a state-wide adaptation strategy and related action plan.

In 2021, products were released by the department and NSW Treasury with potential to improve support to agencies on climate risk assessment and adaption planning (that this, Climate Risk Ready NSW Guide and Course, which provides links to key NSW Treasury polices). The department and NSW Treasury are now leading work to develop a more coordinated approach to climate risk management for agencies' assets and services, and building the resilience of the state to climate risk more broadly.

Climate projections are a key means of understanding the potential impacts of climate change, which is an important step in the climate risk assessment process. The Department of Planning, Industry and Environment (the department) used a robust approach to develop its climate projections (NARCliM). The full version of NARCliM (v1.0) is based on 2007 models11 and while still relevant, this has limited its perceived usefulness and uptake. The process of updating these projections requires significant resourcing. The department has made recent updates to enhance the currency and usefulness of its climate projections. NARCliM (v2.0) should be available in 2022.

While climate projections have been available to agencies and the community more broadly since 2013–14, the department has not been effective in educating the relevant data users within agencies in how to use the information for climate risk assessments and adaptation planning.

The absence of a strategy focused on this is significant and has contributed to the current low levels of climate risk assessment uptake across agencies (see section 2). Agencies are required to use the climate projections developed by the department when developing long term plans and strategies as part of the NSW Government Common Planning Assumptions.


11 The department advises the 2007 global climate models were released to users by the Intergovernmental Panel on Climate Change in 2010.
It is too soon to determine the impact of the 2021 Climate Risk Ready NSW (CRR) Guide and Course, produced by the Department of Planning, Industry and Environment (the department) and NSW Treasury. But there are opportunities for these agencies to progress these developments in partnership: especially with the establishment of senior executive steering and oversight committees related to climate risk.

For the department, key opportunities to embed climate risk management include leveraging land use planning policies and guidance to drive adaptation, which has potential to better protect the state's assets and services. NSW Treasury has a role in continuing to update its policies, guidance and economic analyses with relevant climate change considerations to support an informed, coordinated approach to addressing physical climate risks to agencies' assets and services, and to the state's finances more broadly.

There is currently no plan on how the department and NSW Treasury intend to routinely monitor the progress of agencies with implementing the CRR Guide or developing climate risk 'maturity' more broadly. As agencies are responsible for implementing risk management systems that meet NSW Treasury standards, which now clearly includes consideration of climate risk (TPP20-08), establishing effective monitoring, reporting and accountability around this progress should be a priority for the department and NSW Treasury.

Appendix one – Response from agencies

Appendix two – Timeline of key activities 

Appendix three – About the audit 

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #355 - released (7 September 2021).