Actions for Premier and Cabinet 2021

Premier and Cabinet 2021

Premier and Cabinet
Whole of Government
Asset valuation
Financial reporting
Infrastructure
Internal controls and governance
Shared services and collaboration

This report analyses the results of our audits of the Premier and Cabinet cluster agencies for the year ended 30 June 2021.

Our preferred approach is to table the ‘Report on State Finances’ in Parliament before any other cluster report. This is because the 'Report on State Finances' focuses on the audit results and observations relating to the Total State Sector Accounts, in effect a consolidation of all government agencies. This year the 'Report on State Finances' has been delayed due to significant accounting issues being considered in the Total State Sector Accounts and which may impact the Treasury and Transport clusters.

As there are no outstanding matters relating to audits in the Premier and Cabinet cluster impacting the Total State Sector Accounts we have decided to break with normal practice and table this cluster report ahead of the ‘Report on State Finances’.

What the report is about

The results of the Premier and Cabinet cluster (the cluster) agencies' financial statement audits for the year ended 30 June 2021.

What we found

Unmodified audit opinions were issued for all Premier and Cabinet cluster agencies.

The number of monetary misstatements decreased from 49 in 2019–20 to 38 in 2020–21.

The Library Council of New South Wales corrected a prior period error of $325 million. In 2017, the council split its collection assets into six asset classes, but not the related asset revaluation reserves. To correct this error, some revaluation decrements previously recognised in asset revaluation reserves were reclassified to accumulated funds.

Eight agencies did not complete all of the mandatory early close procedures.

What the key issues were

The Premier and Cabinet cluster was impacted by three Machinery of Government (MoG) changes during 2020–21.

The changes resulted in the transfer of activities and functions in and out of the cluster and the creation of a new entity - Investment NSW.

The transferor entities continued to provide services to Investment NSW subsequent to 30 June 2021. There were no formal service level agreements in place for the provision of these services.

The New South Wales Electoral Commission (the Commission) and Sydney Opera House Trust obtained letters of financial support from their relevant Minister and/or NSW Treasury in 2020–21. The postponement of local government elections impacted the Commission's operations due to increased planned expenditure to support a COVID-safe election. Sydney Opera House Trust's ability to generate revenue was impacted due to the closure of the Concert Hall partly due to COVID-19 and planned renovations.

The number of repeated audit issues raised with management and those charged with governance increased from 22 in 2019–20 to 24 in 2020–21.

There were 47 moderate risk and 28 low risk findings identified. Of the total findings there were 24 repeat issues.

What we recommended

Investment NSW should ensure services received from other agencies are governed by service level agreements.

Fast facts

The Department of Premier and Cabinet supports the Premier and Cabinet to deliver the government's objectives, infrastructure, preparedness for disaster, incident recovery, arts and culture.

  • $11.9b of property, plant and equipment as at 30 June 2021
  • $4.4b total expenditure incurred in 2020-21
  • 100% unqualified audit opinions were issued on agencies' 30 June 2021 financial statements
  • 47 moderate risk findings were reported to management 
  • 38 monetary misstatements were reported in 2020-21
  • 32% of all reported issues were repeat issues.

This report provides Parliament and other users of the Premier and Cabinet’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Premier and Cabinet cluster (the cluster) for 2021.

Section highlights

  • Unqualified audit opinions were issued on all completed cluster agencies' 2020–21 financial statements.
  • Monetary misstatements decreased from 49 in 2019–20 to 38 in 2020–21.
  • Thirteen agencies were exempt from financial reporting in 2020–21. 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from our financial statement audits of agencies in the Premier and Cabinet cluster.

Section highlights

  • The 2020–21 audits identified 47 moderate risk issues across the cluster. Sixteen of the moderate risk issues were repeat issues. Many repeat issues related to governance and oversight and information technology.
  • The number of moderate risk findings increased by 42 per cent in 2020–21.
  • The moderate risk issues included information technology improvements, lack of service level agreements, risk management, contract and procurement and asset management improvements.

Appendix one – Misstatements in financial statements submitted for audit

Appendix two – Early close procedures

Appendix three – Timeliness of financial reporting

Appendix four – Financial data

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Managing climate risks to assets and services

Managing climate risks to assets and services

Planning
Environment
Treasury
Industry
Infrastructure
Management and administration
Risk
Service delivery

What the report is about

This report assessed how effectively the Department of Planning, Industry and Environment (DPIE) and NSW Treasury have supported state agencies to manage climate risks to their assets and services.

Climate risks that can impact on state agencies' assets and services include flooding, bushfires, and extreme temperatures. Impacts can include damage to transport, communications and energy infrastructure, increases in hospital admissions, and making social housing or school buildings unsuitable.

NSW Treasury estimates these risks could have significant costs.

What we found

DPIE and NSW Treasury’s support to agencies to manage climate risks to their assets and services has been insufficient.

In 2021, key agencies with critical assets and services have not conducted climate risk assessments, and most lack adaptation plans.

DPIE has not delivered on the NSW Government commitment to develop a state-wide climate change adaptation action plan. This was to be complete in 2017.

There is also no adaptation strategy for the state. These have been released in all other Australian jurisdictions. The NSW Government’s draft strategic plan for its Climate Change Fund was also never finalised.

DPIE’s approach to developing climate projections is robust, but it hasn’t effectively educated agencies in how to use this information to assess climate risk.

NSW Treasury did not consistently apply dedicated resourcing to support agencies' climate risk management until late 2019.

In March 2021, DPIE and NSW Treasury released the Climate Risk Ready NSW Guide and Course. These are designed to improve support to agencies.

What we recommended

DPIE and NSW Treasury should, in partnership:

  • enhance the coordination of climate risk management across agencies
  • implement climate risk management across their clusters.

DPIE should:

  • update information and strengthen education to agencies, and monitor progress
  • review relevant land-use planning, development and building guidance
  • deliver a climate change adaptation action plan for the state.

NSW Treasury should:

  • strengthen climate risk-related guidance to agencies
  • coordinate guidance on resilience in infrastructure planning
  • review how climate risks have been assured in agencies’ asset management plans.

Fast facts

4 years

between commitments in the NSW Climate Change Policy Framework, and DPIE and NSW Treasury producing key supports to agencies for climate risk management.

$120bn

Value of physical assets held by nine NSW Government entities we examined that have not completed climate risk assessments.

Low capability to do climate risk assessment has been found across state agencies. The total value of NSW Government physical assets is $365 billion, as at 30 June 2020.

x3

NSW Treasury’s estimates of the annual fiscal and economic costs associated with natural disasters will triple by 2060–61.

According to the Intergovernmental Panel on Climate Change in 2021, each of the last four decades has been successively warmer and surface temperatures will continue to increase until at least the mid-century. The Commonwealth Scientific and Industrial Research Organisation (CSIRO) and the Bureau of Meteorology (BoM) have reported that extreme weather across Australia is more frequent and intense, and there have been longer-term changes to weather patterns. They also report sea levels are rising around Australia increasing the risk of inundation and damage to coastal infrastructure and communities.

According to the Department of Planning, Industry and Environment (the department), in New South Wales the impacts of a changing climate, and the risks associated with it, will be felt differently across regions, populations and economic sectors. The department's climate projections indicate the number of hot days will increase, rainfall will vary across the state, and the number of severe fire days will increase.

The NSW Government is a provider of essential services, such as health care, education and public transport. It also owns and manages around $365 billion in physical assets (as at June 2020). More than $180 billion of its assets are in major infrastructure such as roads and railway lines.

In NSW, climate risks that could directly impact on state agencies' assets and services include flooding, bushfires, and extreme temperatures. In recent years, natural hazards exacerbated by climate change have damaged and disrupted government transport, communications and energy infrastructure. As climate risks eventuate, they can also increase hospital admissions when people are affected by poorer air quality, and make social housing dwellings or schools unsafe and unusable during heatwaves. The physical impacts of a changing climate also have significant financial costs. Taking into account projected economic growth, NSW Treasury has estimated that the fiscal and economic costs associated with natural disasters due to climate change will more than triple per year by 2061.

The department and NSW Treasury advise that leading practice in climate risk management includes a process that explicitly identifies climate risks and integrates these into existing risk management, monitoring and reporting systems. This is in line with international risk management and climate adaptation standards. For agencies to manage the physical risks of climate change to their assets and services, leading practice identified by the department means that they need to:

  • use robust climate projection information to understand the potential climate impacts
  • undertake sound climate risk assessments, within an enterprise risk management framework
  • implement adaptation plans that reduce these risks, and harness opportunities.

Adaptation responses that could be planned for include: controlling development in flood-prone locations; ensuring demand for health services can be met during heatwaves; improving thermal comfort in schools to support student engagement; proactive asset maintenance to reduce disruption of essential services, and safeguarding infrastructure from more frequent and intense natural disasters.

According to NSW Treasury policy, agencies are individually responsible for risk management systems appropriate to their context. The department and NSW Treasury have key roles in ensuring that agencies are supported with robust information and timely, relevant guidance to help manage risks to assets and services effectively, especially for emerging risks that require coordinated responses, such as those posed by climate change.

This audit assessed whether the department and NSW Treasury are effectively supporting NSW Government agencies to manage climate risks to their assets and services. It focused on the management of physical risks to assets and services associated with climate change.

Conclusion

The Department of Planning, Industry and Environment (the department) has made climate projections available to agencies since 2014, but provided limited guidance to assist agencies to identify and manage climate risks. NSW Treasury first noted climate change as a contextual factor in its 2012 guidance on risk management. NSW Treasury only clarified requirements for agencies to integrate climate considerations into their risk management processes in December 2020.
The department has not delivered on a NSW Government commitment for a state-wide climate change adaptation action plan, which was meant to be completed in 2017. Currently many state agencies that own or manage assets and provide services do not have climate risk management in place.
Since 2019, the department and NSW Treasury have worked in partnership to develop a coordinated approach to supporting agencies to manage these risks. This includes guidance to agencies on climate risk assessment and adaptation planning published in 2021.
More work is needed to embed, sustain and lead effective climate risk management across the NSW public sector, especially for the state's critical infrastructure and essential services that may be exposed to climate change impacts.

The NSW Government set directions in the 2016 NSW Climate Change Policy Framework to 'manage the impact of climate change on its assets and services by embedding climate change considerations into asset and risk management’ and more broadly into 'government decision-making'.

The department released climate projections and has made information on projected climate change impacts available since 2014, but this has not been effectively communicated to agencies. The absence of a state-wide climate change adaptation action plan has limited the department's implementation of a coordinated, well-communicated program of support to agencies for their climate risk management.

NSW Treasury is responsible for managing the state's finances and providing stewardship to the public sector on financial and risk management, but it did not consistently apply dedicated resourcing to support agencies' climate risk management until late 2019. NSW Treasury estimates the financial costs of climate-related physical risks are significant and will continue to grow.

The partnership between the department and NSW Treasury has produced the 2021 Climate Risk Ready NSW Guide and Course, which aim to help agencies understand their exposure to climate risks and develop adaptation responses. The Guide maps out a process for climate risk assessment and adaptation planning and is referenced in NSW Treasury policy on internal audit and risk management. It is also referenced in NSW Treasury guidance to agencies on how to reflect the effects of climate-related matters in financial statements.

There is more work to be done by the department on maintaining robust, accessible climate information and educating agencies in its use. NSW Treasury will need to continue to update its policies, guidance and economic analyses with relevant climate considerations to support an informed, coordinated approach to managing physical climate risks to agencies' assets and services, and to the state's finances more broadly.

The effectiveness of the department and NSW Treasury's support involves the proactive and sustained take-up of climate risk management by state agencies. There is a key role for the department and NSW Treasury in monitoring this progress and its results.

Prior to 2021, support provided by the Department of Planning, Industry and Environment (the department) to agencies for managing physical climate risks to their assets and services has been limited. NSW Treasury has a stewardship role in public sector performance, including risk management, but has not had a defined role in working with the department on climate risk matters until mid-2019. The low capacity of agencies to undertake this work has been known to NSW Government through agency surveys by the department in 2015 and by the department and NSW Treasury in 2018.

The support delivered to agencies around climate risk management, including risk assessment and adaptation planning, has been slow to start and of limited impact. The department's capacity to implement a coordinated approach to supporting agencies has also been limited by the absence of a state-wide adaptation strategy and related action plan.

In 2021, products were released by the department and NSW Treasury with potential to improve support to agencies on climate risk assessment and adaption planning (that this, Climate Risk Ready NSW Guide and Course, which provides links to key NSW Treasury polices). The department and NSW Treasury are now leading work to develop a more coordinated approach to climate risk management for agencies' assets and services, and building the resilience of the state to climate risk more broadly.

Climate projections are a key means of understanding the potential impacts of climate change, which is an important step in the climate risk assessment process. The Department of Planning, Industry and Environment (the department) used a robust approach to develop its climate projections (NARCliM). The full version of NARCliM (v1.0) is based on 2007 models11 and while still relevant, this has limited its perceived usefulness and uptake. The process of updating these projections requires significant resourcing. The department has made recent updates to enhance the currency and usefulness of its climate projections. NARCliM (v2.0) should be available in 2022.

While climate projections have been available to agencies and the community more broadly since 2013–14, the department has not been effective in educating the relevant data users within agencies in how to use the information for climate risk assessments and adaptation planning.

The absence of a strategy focused on this is significant and has contributed to the current low levels of climate risk assessment uptake across agencies (see section 2). Agencies are required to use the climate projections developed by the department when developing long term plans and strategies as part of the NSW Government Common Planning Assumptions.


11 The department advises the 2007 global climate models were released to users by the Intergovernmental Panel on Climate Change in 2010.
It is too soon to determine the impact of the 2021 Climate Risk Ready NSW (CRR) Guide and Course, produced by the Department of Planning, Industry and Environment (the department) and NSW Treasury. But there are opportunities for these agencies to progress these developments in partnership: especially with the establishment of senior executive steering and oversight committees related to climate risk.

For the department, key opportunities to embed climate risk management include leveraging land use planning policies and guidance to drive adaptation, which has potential to better protect the state's assets and services. NSW Treasury has a role in continuing to update its policies, guidance and economic analyses with relevant climate change considerations to support an informed, coordinated approach to addressing physical climate risks to agencies' assets and services, and to the state's finances more broadly.

There is currently no plan on how the department and NSW Treasury intend to routinely monitor the progress of agencies with implementing the CRR Guide or developing climate risk 'maturity' more broadly. As agencies are responsible for implementing risk management systems that meet NSW Treasury standards, which now clearly includes consideration of climate risk (TPP20-08), establishing effective monitoring, reporting and accountability around this progress should be a priority for the department and NSW Treasury.

Appendix one – Response from agencies

Appendix two – Timeline of key activities 

Appendix three – About the audit 

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #355 - released (7 September 2021).

Published

Actions for Managing cyber risks

Managing cyber risks

Whole of Government
Transport
Cyber security
Information technology
Internal controls and governance
Procurement
Risk

What the report is about

This audit assessed how effectively Transport for NSW (TfNSW) and Sydney Trains identify and manage their cyber security risks.

The NSW Cyber Security Policy (CSP) sets out 25 mandatory requirements for agencies, including implementing the Australian Cyber Security Centre’s Essential 8 strategies to mitigate cyber security incidents, and identifying the agency’s most vital systems, their ‘crown jewels’. 

The audited agencies have requested that we do not disclose detail of the significant vulnerabilities detected during the audit, as these vulnerabilities are not yet remediated. We provided a detailed report to the agencies in December 2020 outlining significant issues identified in the audit. We have conceded to the agencies' request but it is disappointing that transparency to the Parliament and the public on issues that potentially directly affect them needs to be limited in this way.

What we found

TfNSW and Sydney Trains are not effectively managing their cyber security risks.

Both agencies have assessed their cyber security risks as unacceptably high and both agencies had not identified all of the risks we detected during this audit – some of which are significant.

Both agencies have cyber security plans in place that aim to address cyber security risks. TfNSW and Sydney Trains have combined this into the Transport Cyber Defence Rolling Program, part of the Cyber Defence Portfolio (CDP). 

However, neither agency has reached its target ratings for the CSP and the Essential 8 and maturity is low in relation to significant risks and vulnerabilities exposed.

Further, neither agency is fostering a culture where cyber security risk management is an important and valued aspect of decision-making.

TfNSW is not implementing cyber security training effectively across the cluster with only 7.2% of staff having completed basic cyber security training.

What we recommended

TfNSW and Sydney Trains should:

  • develop and implement a plan to uplift the Essential 8 controls to the agency's target state
  • as a matter of priority, address the vulnerabilities identified as part of this audit and previously described in a detailed Audit Office report provided to both agencies
  • ensure cyber security risk reporting to executives and the Audit and Risk Committee
  • collect supporting information for the CSP self assessments 
  • classify all information and systems according to importance and integrate this with the crown jewels identification process
  • require more rigorous analysis to re-prioritise CDP funding 
  • increase uptake of cyber security training.

TfNSW should assess the appropriateness of its target rating for each of the CSP mandatory requirements.

Department of Customer Service should:

  • clarify the requirement for the CSP reporting to apply to all systems
  • require agencies to report the target level of maturity for each mandatory requirement.

Fast facts

  • $42m Total value of the Transport Cyber Defence Rolling Program over three years.
  • 7.2% Percentage of staff across the Transport cluster who had completed introductory cyber security training

Response to requests by audited agencies to remove information from this report

In preparing this audit report, I have considered how best to balance the need to support public accountability and transparency with the need to avoid revealing information that could pose additional risk to agencies’ systems. This has involved an assessment of the appropriate level of detail to include in the report about the cyber security vulnerabilities identified in this audit.

In making this assessment, the audit team consulted with Transport for NSW (TfNSW), Sydney Trains, and Cyber Security NSW to identify content which could potentially pose a threat to the agencies’ cyber security.

In December 2020, my office also provided TfNSW and Sydney Trains with a detailed report of many of the significant vulnerabilities identified in this audit, to enable the agencies to address the cyber security risks identified. The detailed report was produced as a result of a 'red team' exercise, which was conducted with both agencies' knowledge and consent. The scope of this exercise reflected the significant input provided by both agencies. More information on this exercise is at page 12 of this report.

TfNSW and Sydney Trains have advised that in the six months from December 2020 and at the time of tabling this audit report, they have not yet remediated all the vulnerabilities identified. As a result, they, along with Cyber Security NSW, have requested that we not disclose all information contained in this audit report to reduce the likelihood of an attack on their systems and resulting harm to the community. I have conceded to this request because the vulnerabilities identified have not yet been remediated and leave the agencies exposed to significant risk.

It should be stressed that the risks identified in the detailed report exist due to the continued presence of these previously identified vulnerabilities, rather than due to their potential publication. The audited agencies, alone, are accountable for remediating these vulnerabilities and addressing the risks they pose.

It is disappointing that transparency to the Parliament and the public on issues that potentially directly affect them needs to be limited in this way.

That said, the conclusions drawn in this report are significant in terms of risk and remain valid, and the recommendations should be acted upon with urgency.

Cyber security risk is an increasing area of concern for governments in Australia and around the world. In recent years, there have been a number of high-profile cyber security attacks on government entities in Australia, including in New South Wales. Malicious cyber activity in Australia is increasing in frequency, scale, and sophistication. The Audit Office of New South Wales is responding to these risks with a program of audits in this area, which aim to identify the effectiveness of particular agencies in managing cyber risks, as well as their compliance with relevant policy.

Cyber Security NSW, part of the Department of Customer Service (DCS) releases and manages the NSW Cyber Security Policy (CSP). The CSP sets out 25 mandatory requirements for agencies, including making it mandatory for agencies to implement the Australian Cyber Security Centre Essential 8 Strategies to Mitigate Cyber Security Incidents (the Essential 8). The Essential 8 are key controls which serve as a baseline set of protections which agencies can put in place to make it more difficult for adversaries to compromise a system. Agencies are required to self-assess their maturity against the CSP and the Essential 8, and report that assessment to Cyber Security NSW annually.

The CSP makes agencies responsible for identifying and managing their cyber security risks. The CSP sets out responsibilities and governance regarding risk identification, including making agencies responsible for identifying their 'crown jewels', the agency's most valuable and operationally vital systems. Once these risks are identified, agencies are responsible for developing a cyber security plan to mitigate those risks.

This audit focussed on two agencies: Transport for NSW (TfNSW) and Sydney Trains. TfNSW is the lead agency for the Transport cluster and provides a number of IT services to the entire cluster, including Sydney Trains. This audit focussed on the activities of TfNSW's Transport IT function, which is responsible for providing cyber security across the cluster, as well as directly overseeing four of TfNSW's crown jewels. Sydney Trains is one of the agencies in the Transport cluster. While it receives some services from TfNSW, it is also responsible for implementing its own IT controls, as well as controls to protect its Operational Technology (OT) environment. This OT environment includes systems which are necessary for the operation and safety of the train network.

To test the mitigations in place and the effectiveness of controls, this audit involved a 'red team' simulated exercise. A red team involves authorised attackers seeking to achieve certain objectives within the target's environment. The red team simulated a determined external cyber threat actor seeking to gain access to TfNSW's systems. The red team also sought to test the physical security of some Sydney Trains' sites relevant to the agency's cyber security. The red team exercise was conducted with the knowledge of TfNSW and Sydney Trains.

This audit included the Department of Customer Service as an auditee, as they have ownership of the CSP through Cyber Security NSW. This audit did not examine the management of cyber risk in the Department of Customer Service.

This audit assessed how effectively selected agencies identify and manage their cyber security risks. The audit assessed this with the following criteria:

  • Are agencies effectively identifying and planning for their cyber security risks?
  • Are agencies effectively managing their cyber security risks?

Following this in-depth portfolio assessment, the Auditor-General for NSW will also table a report on NSW agencies' compliance with the CSP in the first quarter of 2021–22.

Conclusion

Transport for NSW and Sydney Trains are not effectively managing their cyber security risks. Significant weaknesses exist in their cyber security controls, and both agencies have assessed that their cyber risks are unacceptably high. Neither agency has reached its Essential 8 or Cyber Security Policy target levels. This low Essential 8 maturity exposes both agencies to significant risk. Both agencies are implementing cyber security plans to address identified cyber security risks.
This audit identified other weaknesses, such as low numbers of staff receiving basic cyber security awareness training. Cyber security training is important for building and supporting a cyber security culture. Not all of the weaknesses identified in this audit had previously been identified by the agencies, indicating that their cyber security risk identification is only partially effective.
Agency executives do not receive regular detailed information about cyber risks and how they are being managed, such as information on mitigations in place and the effectiveness of controls for cyber risk. As a result, neither agency is fostering a culture where cyber security risk management is an important and valued aspect of executive decision-making.
TfNSW and Sydney Trains are partially effective at identifying their cyber security risks and both agencies have cyber security plans in place

Both agencies regularly carry out risk assessments and have identified key cyber security risks, including risks that impact on the agencies' crown jewels. These risks have been incorporated into the overall enterprise risk process. However, neither agency regularly reports detailed cyber risk information to agency executives to adequately inform them about cyber risk. The Cyber Security Policy (CSP) requires agencies to foster a culture where cyber security risk management is an important and valued aspect of decision-making. By not informing agency executives in this way, TfNSW and Sydney Trains are not fulfilling this requirement.

Agencies' cyber security risk assessment processes are not sufficiently comprehensive to identify all potential risks. Not all of the weaknesses identified in this audit had previously been identified by the agencies.

To address identified cyber security risks, both agencies have received funding approval to implement cyber security plans. TfNSW first received approval for its cyber security plan in 2017. Sydney Trains received approval for its cyber security plan in February 2020. In 2020–21 TfNSW and Sydney Trains combined their plans into the Transport Cyber Defence Rolling Program business case valued at $42.0 million over three years. This is governed as part of a broader Cyber Defence Portfolio (CDP). The CDP largely takes a risk-based approach to annual funding. The Cyber Defence Portfolio Steering Committee and Board can re-allocate funds from an approved project to a different project. This re-allocation process could be improved by making it more risk-based.

TfNSW and Sydney Trains are not effectively managing their cyber security risks

Neither agency has fully mitigated its cyber security risks. These risks are significant. Neither TfNSW nor Sydney Trains have reduced their cyber risk to levels acceptable to the agencies. Both agencies have set a risk tolerance for cyber security risks, and the identified enterprise-level cyber security risks remain above this rating. Both agencies' self-attested maturity against the Essential 8 remains low in comparison to the agencies' target levels, and in relation to the significant risks and vulnerabilities that are exposed. Little progress was made against the Essential 8 in 2020.

Neither agency has reached its target levels of maturity for the CSP mandatory requirements. Not reaching the target rating of the CSP mandatory requirements risks information and systems being managed inconsistently or not in alignment with good governance principles. The Transport Cyber Defence Rolling Program has a KPI to achieve a target rating of three for all CSP requirements where business appropriate. TfNSW considers this target rating to be its target for all the CSP requirements. However TfNSW has not undertaken analysis to determine whether this target is appropriate to its business.

The CSP makes agencies accountable for the cyber risks of their ICT service providers. While both agencies usually included their cyber security expectations in contracts with third-party suppliers, neither agency was routinely conducting audits to ensure that these expectations were being met.

The CSP requires agencies to make staff aware of cyber security risks and deliver cyber security training. TfNSW is responsible for delivering cyber security training across the Transport cluster, including in Sydney Trains. TfNSW was not effectively delivering cyber security training across the cluster because training was not mandatory for all staff at the time of the audit and completion rates among those staff assigned the training was low. As such, only 7.2 per cent of staff across the Transport cluster had completed introductory cyber security training as at January 2021.

Agencies have assessed their cyber risks as being above acceptable levels

An agency's risk tolerance is the amount of risk which the agency will accept or tolerate without developing further strategies to modify the level of risk. Risks that are within an agency's risk tolerance may not require further mitigation and may be deemed acceptable, while risks which are above the agency's risk tolerance likely require further mitigation before they become acceptable to the agency.

Both agencies have defined their risk tolerance and have identified risks which are above this level, indicating that they are unacceptable to the agency. TfNSW has defined 'very high' risks as generally intolerable and 'high' risks as undesirable. Its risk tolerance is 'medium'. Sydney Trains has four classifications of risk: A, B, C and D. A and B risks are deemed 'unacceptable' and 'undesirable' respectively, while C risks are considered 'tolerable'. This aligns with the TfNSW definition of a medium risk tolerance.

Transport IT reported five enterprise-level cyber security risks through its enterprise risk reporting tool in September 2020, all of which relate to cyber security or have causes relating to cyber security. These risks are in aggregate form, rather than relating to specific vulnerabilities. At the time of the audit, one of these risks was rated as very high and the other four rated as high. At this time, Transport IT had identified a further seven divisional-level risks which were above the agency’s risk tolerance.

Similarly, Sydney Trains has identified one main cyber security risk in its IT enterprise-level risk register and another with a potential cyber cause. Both of these IT risks are deemed to have a residual risk of ‘unacceptable’.

Similarly, two cyber-related OT risks have been determined to be above the agency's risk tolerance. One risk is rated as 'unacceptable'. Another risk, while not entirely cyber rated, is rated 'undesirable' and is deemed to have some causes which may stem from a cyber-attack.

Agencies have assessed their current cyber risk mitigations as requiring improvement

In addition to the risk ratings stated above, at the time of the audit neither agency believed that its controls were operating effectively. Transport IT had rated the control environments for its cyber security enterprise risks as 'requires improvement'. Mitigations were listed in the risk register for these risks but, in some cases, they were unlikely to reduce the risk to the target state or by the target date. For example, one risk had actions listed as 'under review' and no further treatment actions listed, but a due date of July 2021, while another risk was being treated by the CDP with a due date of July 2021. The CDP identified in May 2020 that while the average risk identified as part of that program will be reduced to a medium level by this date, ten high risks will still remain. Given the delays in the program, this number may be higher. As such, it seems unlikely that the enterprise risk will be reduced to below a 'high' level by July 2021.

Sydney Trains’ IT and OT risk registers cross-reference controls and mitigations against the causes and consequences. The IT cyber security risk identified in the register had causes with no mitigations designed for them. Further, some of these causes did not have future mitigations designed for them. This risk also had controls in place which are identified as partially effective. For the unacceptable OT risk noted above, while there was a control designed for each of the potential causes, Sydney Trains had identified all of the controls in place as either partially effective or ineffective. This indicates that Sydney Trains was not effectively mitigating the causes of its cyber risks and, even where it had designed controls or mitigations, these were not always implemented to fully mitigate the cause of the risk.

Additional information on gaps in cyber mitigations which were exposed in the course of this audit has been detailed to both agencies. The Foreword of this report provides information about why this detail is not included here.

Essential 8 maturity is low across TfNSW and Sydney Trains and little progress was made in 2020

CSP mandatory requirement 3.2 states that agencies must implement the ACSC Essential 8. Agencies must also rate themselves against each of the Essential 8 on a maturity scale from zero to three and report this to Cyber Security NSW. A full list of the Essential 8 can be found in Exhibit 1. Both agencies have a low level of maturity against the Essential 8 not just in comparison to the targets they have set, but also in relation to the risks and vulnerabilities exposed. Both agencies have set target maturity ratings for the Essential 8 but none of the Essential 8 ratings across either agency are currently implemented to this level. Having a low level of Essential 8 maturity exposes both agencies to significant risks and vulnerabilities. Little progress was made between the 2019 and 2020 attestation periods.

Transport IT has set a target rating of three across all of the Essential 8. Sydney Trains has set a target rating of three for its IT systems. Sydney Trains had an interim target of two for its OT systems in 2020 and advised that this has since increased to three. It should be noted that not all the Essential 8 are applicable to OT systems.

None of the Essential 8 ratings across either agency are currently implemented to the target levels. Given that the Essential 8 provide the controls which are most commonly able to deter cyber-attacks, having maturity at a low level potentially exposes agencies to a cyber security attack.

Some work is underway across both TfNSW and Sydney Trains to improve the Essential 8 control ratings. The CDP provided some resources to the Essential 8 over 2019–20, with uplift focusing on specific systems. The CDP work in 2019 and 2020 relevant to the Essential 8 largely focussed on determining the current state of the Essential 8 and creating a target state roadmap. As a result, there was little improvement between the 2019 and 2020 attestation periods. The CDP has a workstream for the Essential 8 in its FY 2020–21 funding allocation, however as noted above in Exhibit 6 this was delayed as resources were redeployed to Project La Brea. Regardless, work on some specific aspects of the Essential 8 remain part of the 2020–21 CDP allocation, with workstreams allocated to improving three of the Essential 8. In addition, some work from Project La Brea should lead to an improvement in the Essential 8.

Sydney Trains' Cyber Uplift Program included a workstream which had in scope the uplift in the Essential 8 in IT. There were also other workstreams which aimed to improve some of the Essential 8 for OT systems. Work is also ongoing as part of the CDP to uplift these scores in Sydney Trains.

TfNSW and Sydney Trains have not reached their target maturity across the CSP mandatory requirements and TfNSW has not evaluated its cluster-wide target to ensure it is appropriate

Cyber Security NSW allows each agency to determine its target level of maturity for the first 20 CSP mandatory requirements. Agencies can tailor their target levels to their risk profile. Not reaching the target rating of the CSP mandatory requirements risks information and systems being managed inconsistently or not in alignment with good governance principles.

Sydney Trains has set its target level of maturity for IT and OT. All of Sydney Trains' target maturity levels are at least a three (defined), with a target of four (quantitatively managed) for many of the mandatory requirements. While Cyber Security NSW does not currently mandate a minimum level of maturity, in 2019 there was a requirement for each agency to target a minimum level of three.

Sydney Trains has not met its target ratings across the mandatory requirements.

The Transport Cyber Defence Rolling Program has a program KPI to ensure that the entire cluster reaches a minimum maturity level of three against all the CSP requirements by 2023. TfNSW has not reviewed its CSP mandatory requirement targets to determine if a three is desirable for all requirements or if a higher target level may be more appropriate. It is important for senior management to set cyber security objectives as a demonstration of leadership and a commitment to cyber security.

TfNSW has not met its target ratings across the mandatory requirements for its Group IT ISMS, which was the focus of this audit.

Both agencies claimed progress in their implementation of the mandatory requirements between 2019 and 2020. The audit did not seek to verify the self-assessed results from either agency.

Both agencies operate ISMS in line with the CSP

CSP mandatory requirement 3.1 requires agencies to implement an Information Security Management System (ISMS) or Cyber Security Framework (CSF), with scope at least covering systems identified as the agency's ‘crown jewels’. The ISMS or CSF should be compliant with, or modelled on, one or more recognised IT or OT standard. As noted in the introduction, an ISMS ‘consists of the policies, procedures, guidelines, and associated resources and activities, collectively managed by an organisation, in the pursuit of protecting its information assets.’ Both agencies operate an ISMS compliant with the CSP requirement.

As noted in the introduction, TfNSW operates four ISMS. The Transport IT ISMS is certified against ISO27001, the most common standard for ISMS certification. Three of TfNSW’s six crown jewels are managed within this ISMS. The other ISMS are not certified to relevant standards, though TfNSW claims that they align with relevant controls. This is sufficient for the purposes of the CSP.

Sydney Trains operates two ISMS, one for IT and another for OT. Neither of these are certified to relevant ISMS Standards, however there have been conformance reviews of both IT and OT with relevant standards. These ISMS cover all crown jewels in the agency.

There are currently 11 ISMS in operation across the Transport cluster. TfNSW has proposed moving towards a holistic approach to these ISMS, with the CDP Board responsible for governing the available security controls and directing agency IT and OT teams to implement these.

Agencies are not routinely conducting audits of third-party suppliers to ensure compliance with contractual obligations

CSP mandatory requirement 1.5 makes agencies accountable for the cyber risks of their ICT service providers and ensuring that providers comply with the CSP and any other relevant agency security policies. The ACSC has provided advice on what organisations should do when managing third party suppliers of ICT. The ACSC advises that organisations should use contracts to define cyber security expectations and seek assurance to ensure that these contract expectations are being met. While both agencies usually include specific cyber security expectations in contracts, neither is routinely seeking assurance that these expectations are being met.

The NSW Government has mandated the use of the 'Core& One' contract template for low-value IT procurements and the Procure IT contract template for high-value IT procurements. Both of these contracts contain space for the procuring agency to include cyber security controls for the contractor to implement. The Procure IT contract template also includes a right-to-audit clause which allows agencies to receive assurance around the implementation of these controls. TfNSW and Sydney Trains used the mandated contracts for relevant contracts examined as part of this audit.

TfNSW included security controls in all the contracts examined as part of this audit. Compliance with ISO27001 was the most commonly stated security expectation. Of the contracts examined as part of this audit, only one contract did not have a right-to-audit clause. This contract was signed in October 2016. While these clauses are in place, TfNSW rarely conducted these audits on its third-party providers. Of the eight TfNSW contracts examined in detail, only two of these had been audited to confirm compliance with the stated security controls.

Sydney Trains included security controls in all but one of the contracts examined as part of this audit. Sydney Trains did not require contractors to be compliant with ISO27001, but only required compliance with whole-of-government policies. Sydney Trains does not routinely conduct audits of its third-party suppliers, however it did conduct deep-dive risk analyses of its top ten highest risk IT suppliers. This involved a detailed review of both the suppliers' security posture and also the contract underpinning the relationship with the supplier.

The CDP funding for 2020–21 includes a workstream for strategic third-party contract remediation. This funding is to conduct some foundational work which will allow the CDP to make further improvements in future years. While this funding will not address gaps in contract requirements or management across all contracts, this workstream aims to reduce the risks posed by strategic suppliers covering critical assets. Similarly, work is currently underway as part of the CDP to conduct OT risk assessments for key suppliers to Sydney Trains in a similar way to the work undertaken for IT suppliers.

Sydney Trains has risk assessed its third-party suppliers but TfNSW has not done so

It is important to conduct a risk assessment of suppliers to identify high-risk contractors. This allows agencies to identify those contractors who may require additional controls stated in the contract, those who require additional oversight, and also where auditing resources are best targeted.

Sydney Trains has risk assessed all its IT suppliers and, as noted above, has conducted a deep-dive risk analysis of its top ten highest risk suppliers. TfNSW has not undertaken similar analysis of its key suppliers, however it has identified risks attached to each of its strategic suppliers and has documented these. As a result of not risk assessing its suppliers, TfNSW cannot take a targeted approach to its contract management.

TfNSW demonstrated poor records handling relating to the contracts examined as part of this audit

TfNSW was not able to locate one of the contracts requested as part of the audit's sample. Other documentation, such as contract management plans, could not be located for many of the other contracts requested as part of this audit. These poor document handling practices limits TfNSW's ability to effectively oversee service providers and ensure that they are implementing agreed controls. It also limits public transparency on the effectiveness of these controls.

The Transport cluster is not effectively implementing cyber security awareness training

Agencies are responsible for implementing regular cyber security education for all employees and contractors under mandatory requirement 2.1 in the CSP. TfNSW is responsible for delivering this training to the whole Transport cluster, including Sydney Trains. The Transport cluster has basic cyber awareness training available for all staff. TfNSW also offers additional training provided by Cyber Security NSW targeted at executives and executive assistants. While TfNSW has training available to staff, it is not delivering this effectively. TfNSW does not make training mandatory for most staff nor does it require staff to repeat training regularly. Even among those staff who have been assigned the training, completion rates are low, meaning that delivery is not effectively monitored. Cyber security training is important for building and supporting a cyber security culture.

TfNSW is responsible for creating and rolling out all forms of training to agencies within the Transport cluster. Both TfNSW and Sydney Trains have the same mandatory cyber awareness training that is automatically assigned to new starters. At the time of the audit, this training was not mandatory for ongoing staff. TfNSW does make additional cyber security training available to staff who can choose to undertake the training themselves, or can be assigned the training by their manager. All TfNSW cyber security training is delivered via online modules and it is the responsibility of managers to ensure that it is completed.

Cyber security training completion rates for both TfNSW and Sydney Trains are low. Only 13.5 per cent of staff across the Transport cluster had been assigned the Cyber Safety for New Starters training as of January 2021. Although this course is mandatory for new starters, only 53 per cent of staff assigned the Cyber Safety for New Starters training module had completed the course by January 2021. As a result, only 7.2 per cent of staff across the entire Transport cluster had completed this training at that time. In Sydney Trains, less than one per cent of staff had completed this training as at January 2021 and a further 7.6 per cent of staff have completed the 'Cyber Security: Beyond the Basics' training. These low completion rates indicate that TfNSW is not effectively rolling out cyber security training across the cluster.

In October 2020, the Department of Customer Service released 'DCS-2020-05 Cyber Security NSW Directive - Practice Requirement for NSW Government', which made annual cyber security training mandatory for all staff from 2021. In line with this requirement, TfNSW has advised that it will be gradually implementing mandatory annual training from July 2021 for all staff.

The Transport cluster undertakes activities to build a cyber-aware culture in accordance with the CSP, but awareness remains low

Increasing staff awareness of cyber security risks and maintaining a cyber secure culture are both mandatory requirements of the CSP. While TfNSW does undertake some activities to build a cyber aware culture, awareness of cyber security risks remains low. This can be demonstrated by the low training rates outlined above, and the 'Spot the Scammer' exercise, described in Exhibit 7. TfNSW is responsible for delivering these awareness raising activities across the cluster.

TfNSW frequently communicates with staff across the Transport cluster about various cyber security risks through multiple avenues. Both agencies use the intranet, emails and other awareness raising activities to highlight the importance for staff to be aware of the seriousness of cyber risks. Advice given on the intranet includes tips for spotting scammers on mobile phones, promoting the cluster-wide training courses, as well as various advice that staff could use when dealing with cyber risks in the workplace.

In addition to these awareness raising activities, TfNSW has also undertaken a cluster-wide phishing email exercise called 'Spot the Scammer'. This is outlined in Exhibit 7. This exercise was carried out in 2019 and 2020 and allowed the Transport cluster to measure the degree to which staff were able to identify phishing emails. As can be seen in Exhibit 7, the results of this exercise indicate that staff awareness of phishing emails remains low.

Exhibit 7 - Spot the Scammer exercise
In both 2019 and 2020, TfNSW performed a ‘Spot the Scammer’ exercise in which they sent out over 25,000 emails to staff based on a real phishing attack in order to measure awareness and response. The exercise tested staff 'click through rate', the percentage of staff who clicked on the fake phishing link. In 2019, these results were then compared to industry benchmarks, with over a 20 per cent click through rate being considered 'very high'. Both TfNSW and Sydney Trains were considered to have a ‘very high’ click through rate in comparison to these benchmarks in both 2019 and 2020. This indicates that staff awareness of phishing emails was low. The click through rate for TfNSW was 24 per cent in 2020, an increase from 22 per cent in 2019. For Sydney Trains, the click through rate in 2020 was 32 per cent, which was a decrease from 40 per cent in 2019.
Source: Audit Office analysis of TfNSW documents.

Appendix one – Response from agencies

Appendix two – Cyber Security Policy mandatory requirements

Appendix three – About the audit

Appendix four – Performance auditing

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #353 - released (13 July 2021).

Published

Actions for WestConnex: changes since 2014

WestConnex: changes since 2014

Transport
Compliance
Infrastructure
Internal controls and governance
Management and administration
Project management
Risk

What the report is about

The report examined whether Transport for NSW (TfNSW) and Infrastructure NSW (INSW) effectively assessed and justified major scope changes to the WestConnex project since 2014.

What we found

NSW Government decisions to fund WestConnex-related projects outside WestConnex's $16.812 billion budget have reduced transparency and understate the full cost of WestConnex.

The NSW Government's decision to separate Sydney Gateway from WestConnex has reduced transparency over the cost of the road component of Sydney Gateway. $1.76 billion of the cost to complete Sydney Gateway is funded outside the WestConnex budget.

Network integration costs, currently estimated at $2.3 billion, are also funded outside the WestConnex budget. Many of these costs are directly attributable to WestConnex and ought to be included in the reported budget.

The Parramatta Road Urban Amenity Improvement Program, costing $198 million, should also be included as part of the WestConnex reported budget.

Decisions to exclude or remove these elements from WestConnex without justification have seen $4.26 billion of projects funded outside the $16.8 billion budget.

Positively, robust analysis was used to develop and incorporate design improvements into the 2015 WestConnex Updated Strategic Business Case.

The separate components of WestConnex underwent all required assurance reviews. However, the NSW Government's assurance framework does not require ongoing ‘whole-of-program’ assurance for large and complex projects like WestConnex. The absence of a holistic review of WestConnex allows for some costs and benefits to avoid scrutiny.

What we recommended

TfNSW should:

  • review the impact of scope changes on project objectives, costs and benefits for complex infrastructure projects
  • ensure that estimated costs and benefits of works which are reasonably required to meet consent conditions are included in business cases for complex large infrastructure projects
  • establish centralised and project specific record keeping for major infrastructure projects.

Infrastructure NSW should provide transparent whole of program assurance on total costs and benefits when complex projects are split into sub-projects.

Government should consider enhancing public transparency of existing infrastructure assurance processes by requiring that large complex infrastructure programs undergo periodic review at a whole-of-program level.

Fast facts

  • $16.812b 2015 WestConnex business case budget
  • $2.3b current estimated cost of network integration works to enable WestConnex, funded outside the WestConnex budget
  • $1.76b cost to complete Sydney Gateway to enable WestConnex and also funded outside the WestConnex budget
  • $198m Parramatta Road Urban Amenity Improvement Program, originally part of WestConnex but now funded outside the WestConnex budget

WestConnex

WestConnex is a 33 km motorway network that will link the western and south‑western suburbs with the Sydney CBD and the Airport and Port Botany precinct. It will also connect with proposed future motorway links to the north shore, northern beaches, and southern Sydney. The project is being delivered in three stages, with completion scheduled for 2023.

When first conceived by Infrastructure NSW (INSW) in 2012, WestConnex was described as a single integrated concept. In August 2013, government approved a business case for an integrated concept of WestConnex, with an estimated cost of $14.881 billion (in nominal outturn costs). Transport for NSW (TfNSW) is the government agency (sponsor agency) accountable for the delivery of WestConnex in accordance with the business case. In August 2014, the NSW Government established the Sydney Motorway Corporation to fund, deliver and operate WestConnex.

In November 2015, the NSW Government publicly released an updated WestConnex business case with greater detail and design enhancements, which increased the estimated cost to $16.812 billion.

Subsequent to this update, further changes were made to the design, including realignment of the M4 to M5 Link connection to the Western Harbour Tunnel project, an expanded interchange at Rozelle, the deletion of the Camperdown Intersection, and the addition of the Iron Cove Link. The reported budget for WestConnex was not changed as a result of these design updates.

To fund WestConnex, Sydney Motorway Corporation consolidated a concessional loan of $2 billion from the Australian Government, private sector debt and equity funding from the State. The Australian Government also provided a $1.5 billion contribution to the State to partially fund construction of WestConnex.

In August 2018, the NSW Government sold 51 per cent of its stake in Sydney Motorway Corporation for $9.26 billion. At the time of writing, the NSW Government is in the process of selling its remaining 49 per cent stake of Sydney Motorway Corporation.

About this audit

In the course of delivering a complex major infrastructure project, it is reasonable to expect changes to the original design and scope. Changes may occur as the design moves from a high‑level concept to a detailed design for project delivery, as new risks or issues are identified, as demands change, or as other interdependent projects are approved. Changes can also occur in response to potential cost or delivery overruns which arise as a result of planning deficiencies. Where design and scope changes significantly change the project costs and/or expected benefits, the justification for these changes should be robust and transparent.

Following our 2014 performance audit, 'WestConnex: Assurance to the government', the NSW Government established the Infrastructure Investor Assurance Framework (IIAF) to improve accountability and transparency over major projects that are developed, procured, or delivered by government agencies. Under the framework, TfNSW, as project sponsor, is responsible for ensuring the WestConnex project meets all IIAF requirements. These include ensuring the project remains strategically aligned and viable, and benefits are on track. INSW is responsible for coordinating the assurance review process and reporting directly to NSW Cabinet on project delivery against time, budget and risks to project delivery.

The objective of this performance audit is to assess whether TfNSW and INSW effectively assessed and justified major scope changes to the WestConnex project since 2014.

 

Conclusion

Government decisions to separate WestConnex related projects and deliver them outside WestConnex's 2015 business case budget of $16.812 billion has understated the total cost of WestConnex achieving its objectives. The rationale for separating these elements from the WestConnex project scope has not been transparent. Together, these projects represent costs of $4.26 billion funded outside the $16.812 billion WestConnex budget.

Since 2015, the NSW Government has removed several projects from the scope described in the 2015 WestConnex business case, and funded them separately:
  • In mid‑2017, the Sydney Gateway became a separate project outside WestConnex. This project, estimated in 2015 to cost $800 million, now has an estimated cost of $2.56 billion. The project remains partly funded by an $800 million contribution from the $16.812 billion WestConnex budget, with $1.76 billion funded outside the WestConnex budget.
  • In late 2018, the Parramatta Road Urban Amenity Improvement Program became a separate project outside the 2015 WestConnex budget. This project was part of the 2015 WestConnex Business Case and is intended to create urban renewal opportunities around Paramatta Road. It is estimated to cost $198 million.

Work required to integrate WestConnex with existing roads ('network integration') was funded outside the $16.812 billion budget for the November 2015 WestConnex business case. TfNSW is obliged to deliver network integration works to meet the conditions of planning approval for WestConnex. As such, these costs should be included in the WestConnex budget. The current estimated cost of these network integration works is $2.3 billion.

The rationale to exclude or remove each of these elements from the WestConnex project scope has not been transparent, nor supported by robust analysis and justification. These elements are required for WestConnex to achieve its objectives. The additional project costs will also deliver additional benefits not included in the 2015 WestConnex business case. Removing them understates the total cost of achieving the objectives set out in the 2013 and 2015 WestConnex business cases.

WestConnex's complex financing arrangements further reduce transparency on costs.

Transparency over the total cost of WestConnex – including elements funded from other project budgets – is further limited by the project's complex financing arrangements.

Prior to 2018, the Audit Office provided assurance on costs borne and levied by Sydney Motorway Corporation and its controlled entities. Since the NSW Government sold its majority stake in WestConnex in August 2018, the Auditor‑General no longer has the mandate to provide this assurance. Considering this, and the lack of transparency on the cost of projects removed from the WestConnex project scope, there is no transparent or comprehensive view of the total cost to deliver WestConnex – nor of how these cost would be offset by the sale of the government's remaining stake.

There is no 'whole‑of‑program' assurance over the WestConnex program of works. This limits transparency and confidence that WestConnex will meet intended objectives within its budget.

After INSW conducted a gateway review of a draft of the 2015 WestConnex Business Case under the IIAF, the project was broken up into separate components to support staged delivery. Each of these projects, including the Sydney Gateway, as well as the Network Integration Program, underwent the required assurance reviews under the IIAF. INSW also provided monthly progress updates to government. These individual projects are, in themselves, significant in scale and complexity. Addressing them as discrete components for the purposes of the assurance review process is justified and there is no requirement under the IIAF to holistically review projects which together deliver final benefits of the WestConnex program. However, whole‑of‑program review would improve transparency over total costs and benefits.

In 2016, TfNSW revised the design of the M4‑M5 Link and Rozelle to address traffic and integration issues.

TfNSW identified that the concept designs used for the M4‑M5 Link and Rozelle Interchange in the 2015 WestConnex Business Case would not integrate well with surface roads, including the proposed Bays Precinct, and would result in increased traffic on Victoria Road and the ANZAC Bridge. Following a comprehensive review conducted in mid‑2016, TfNSW refined the design of the M4‑M5 Link and Rozelle Interchange to address these limitations without increasing the cost of delivery. TfNSW documented the rationale for the design changes, including how the changes improved on the original design to increase capacity, improve traffic conditions and create more open space.

1. Key findings

Government decisions to fund WestConnex related projects outside of WestConnex's $16.812 billion reported budget have reduced transparency over costs and understate the full cost of WestConnex

In 2015, the work required to integrate WestConnex with existing roads ('network integration') was funded as a separate project with an estimated cost of $1.534 billion outside the 2015 WestConnex budget of $16.812 billion. TfNSW then created the Network Integration Program to respond to the conditions of planning approval for WestConnex. The current estimated cost to deliver all network integration works is $2.3 billion.

Since the 2015 WestConnex Business Case, the NSW Government has removed several elements from the scope of WestConnex and funded them as separate projects, while keeping the published WestConnex budget at an estimated $16.812 billion. Projects removed include:

  • Sydney Gateway, currently costed at $2.56 billion (with an $800 million contribution from WestConnex)
  • Parramatta Road Urban Amenity Improvement Program, costed at $198 million in late 2018 and funded though new funding to the Greater Sydney Commission.

Together, these projects represent costs of $4.26 billion that are not included in the WestConnex budget, but are required for WestConnex to achieve the objectives of the 2013 and 2015 WestConnex Business Cases. The costs of these elements in supporting the objectives of WestConnex is not tracked centrally, and there is no single point of oversight over them. Exhibit 1 compares total WestConnex forecast costs (including related projects) between November 2015 and April 2021.

 

November 2015
($ million)

April 2021
($ million)
WestConnex
Stage 1
Stage 1A (M4 Widening) 497 517
Stage 1B (M4 East) 3,802 3,782
Total 4,299 4,299
Stage 2
King Georges Road Interchange 131 131
New M5 4,335 4,335
Sydney Gateway Contribution 800 800
Total 5,266 5,266
Stage 3
M4‑M5 Link and Rozelle Interchange 7,049 7,049
Urban renewal (Parramatta Road) 198 ‑‑
Urban renewal (Rozelle) ‑‑ 198
Total 7,247 7,247
Total reportable WestConnex 16,812 16,812

Exhibit 1: WestConnex and related projects forecast costs
  November 2015
($ million)
April 2021
($ million)
Related projects
Network integration 1,534 2,300
Urban renewal (Parramatta Road) ‑‑ 198
Sydney Gateway Road Component ‑‑ 1,760
Total 1,534 4,258

Source: AO research.

Many network integration costs are directly attributable to WestConnex and ought to be included in the reported budget for WestConnex

Prior to 2015, the scope of WestConnex included enabling works needed before or during construction, as well as funding for future works to address any adverse traffic outcomes created by WestConnex which become apparent after its opening. These works are also known as network integration works.

When government approved the 2015 WestConnex Business Case, it noted that the project would require $1.534 billion for network integration works to address the impacts of WestConnex on the road network. However, the WestConnex project budget of $16.812 billion did not include funding for network integration works. Instead, Roads and Maritime Services (RMS, now TfNSW) was to fund network integration through its normal budget allocation.

It is important to recognise these costs as part of the total WestConnex project cost because:

  • TfNSW created the Network Integration Program to respond to network traffic and transport elements of the planning conditions of approval for WestConnex granted by the then NSW Department of Planning and Environment under the Environment, Planning and Assessment Act 1979.
  • NSW Treasury guidelines for business cases note that accurate cost estimates include assessment of the financial impact of meeting the conditions of planning approval.
  • Travel time and vehicle operating cost benefits attributed to the WestConnex project in the 2015 WestConnex Business Case assume that some network integration works, then costed at $373 million, were in place.

Refer to Appendix two for more detail on network integration works.

Some of the projects in the WestConnex Network Integration Program provide community and place benefits, such as parklands and cycleways. These benefits have not been attributed to WestConnex. Additionally, some network integration works are likely to deliver additional traffic related benefits to WestConnex. As the Network Integration Program’s primary purpose is to meet the conditions of planning approval for WestConnex, TfNSW should attribute all the costs and benefits of the program to WestConnex.

To September 2021, the total funded cost of the Network Integration Program is approximately $2.077 billion. TfNSW estimates that it will need a further $222 million to complete all expected network integration works.

The NSW Government's decision to separate Sydney Gateway from WestConnex has reduced transparency and accountability for TfNSW's underestimation of the cost of the road component of Sydney Gateway

Sydney Gateway is a high‑capacity connection between the new St Peters Interchange and the Sydney Airport and Port Botany precinct. It includes a road and rail components. The road component was included in the scope of WestConnex in the 2015 WestConnex Business Case. The November 2015 design, which TfNSW costed at $800 million, involved separate roadways from the St Peters Interchange to the International terminal, and to the domestic terminals and Mascot airport precinct.

By October 2016, TfNSW was aware that the $800 million budget for Sydney Gateway was insufficient and revised the forecast cost for the road component to $1.8 billion. The original cost estimate did not sufficiently consider the cost of:

  • constructing a complex design adjacent to the airport precinct
  • obtaining access to land required for the project
  • managing environmental contamination.

On 9 August 2017, the then Minister for WestConnex announced that the Sydney Gateway project was not part of WestConnex.

The 2015 WestConnex Business Case notes that material changes to the WestConnex budget, funding, scope, or timeframe are subject to Cabinet approval processes. It states that, when seeking approval for material changes, the portfolio Minister will make a submission to the relevant Cabinet Committee. Changes in project scope required the approval of the then Cabinet Committee on Infrastructure and should have been endorsed by the WestConnex Interdepartmental Steering Committee.

TfNSW and the NSW Department of Premier and Cabinet (DPC) assert that there is no documentation to support the government’s decision to separate Sydney Gateway from the WestConnex Program, or the WestConnex Interdepartmental Steering Committee's endorsement of a submission to Cabinet seeking approval for the separation.

The established governance processes for major scope changes were not followed in this instance. The lack of transparency regarding government's decision to separate Sydney Gateway from WestConnex also reduces visibility of TfNSW's underestimation of the cost of delivering the road component of Sydney Gateway.

The November 2018 Final Business Case for Sydney Gateway, which was approved by the government, included an estimate of $2.45 billion (nominal outturn cost) for the road component. This estimate included an $800 million contribution from WestConnex. A more recent estimate (late 2020) for this project is $2.56 billion (nominal outturn cost).

The Parramatta Road Urban Amenity Improvement Program should be included as part of the WestConnex budget

A specific objective of the 2015 WestConnex Business Case was the creation of opportunities for urban renewal along and around Parramatta Road. The business case included an allocation of $198 million in the $16.812 billion WestConnex budget for the Parramatta Road Urban Amenity Improvement program, designed to implement aspects of the objective. In November 2018, the NSW Government removed the Parramatta Road Urban Amenity Improvement Program from the WestConnex program of works and reallocated the $198 million (inside the $16.812 billion WestConnex budget) for urban renewal works around the Rozelle Interchange. As part of this decision, government approved new funding of $198 million to the Greater Sydney Commission for the urban amenity program, outside the $16.812 billion WestConnex budget. This understates the cost of WestConnex meeting its objectives by $198 million.

There is no requirement for ongoing ‘whole‑of‑program’ assurance of the WestConnex program of works, including related projects

In August 2015, INSW conducted its first Gateway Review of WestConnex as a program consisting of composite projects. Following that review, TfNSW registered each of the components of WestConnex with INSW as individual projects, rather than keeping WestConnex registered as a program or mega‑project. This is not inconsistent with the IIAF and all WestConnex related projects, including Sydney Gateway and the Network Integration Program, have undergone independent assurance reviews as individual projects under the IIAF.

Once a program like WestConnex is broken down into its composite parts, there is no requirement for the sponsor agency (TfNSW) or INSW to provide independent assurance on the program as a whole until it is completed. This is then done as part of the Gateway review for benefits realisation, which examines whether project benefits are being measured and meet expectations. These individual projects are, in themselves, significant in scale and complexity. While addressing them as discrete components for the purposes of the assurance review process can be justified, the absence of strategic, holistic reviews of WestConnex allows for total costs and benefits to become opaque and avoid scrutiny. Programs of this scale require greater ongoing transparency on total costs and benefits in order to ensure confidence they will meet intended objectives within budget.

There is a lack of public transparency on the total costs and benefits of the WestConnex project

Prior to 2018, the Audit Office provided assurance on costs borne and levied by Sydney Motorway Corporation and its controlled entities. Since the NSW Government sold 51 per cent of its stake in WestConnex in August 2018, the Auditor‑General no longer has the mandate to provide this assurance. The Audit Office is also unable to provide any assurance regarding the performance of tolling concessions.

This means that the total costs of WestConnex, including those levied on road users through tolling, are not reported alongside the full cost of delivering the project. This information, and independent assurance over that information, would provide transparency and context to the outcome of government's sale of its interest in WestConnex.

To enhance the transparency of existing infrastructure assurance processes, government could consider requiring large and complex infrastructure programs to undergo periodic review at a whole‑of‑program level. This could take the form of annual reports to Parliament on the total costs and benefits of selected large and complex projects by the responsible agency. The reports could include an assessment of the cost to government and cost to the community of funding and financing. Independent assurance of the agency report would provide Parliament with greater confidence that infrastructure is delivered economically and providing value for money for the people of NSW.

The Australian National Audit Office provides similar assurance on selected Department of Defence acquisition projects as part of its annual Major Projects Report.

Design enhancements included in the 2015 WestConnex Updated Strategic Business Case were supported by robust analysis

The 2015 WestConnex Business Case contained more detail than the 2013 WestConnex business case. Design enhancements were made as a result of modelling analysis conducted over the two years since the 2013 business case. Enhancements included a full underground link between Kingsgrove and St Peters as part of the New M5 and re‑alignment of the M4‑M5 link tunnel (Stage 3) to include the Rozelle Interchange. The Rozelle Interchange will provide a direct connection to the Anzac Bridge and Victoria Road, and will enable a connection to the proposed Western Harbour Tunnel and Beaches Link. A map and description of these elements can be found at Exhibits 2 and 3 of this report.

In 2016, TfNSW revised the design of the M4‑M5 Link and Rozelle to address traffic and integration issues

As part of preparing the 2015 WestConnex Business Case, TfNSW prepared a Project Definition and Delivery Report (PDDR) for the M4‑M5 Link. This report describes the scope of the project, including a high‑level concept design. TfNSW identified limitations with the proposed design of the M4‑M5 in the PDDR, which it would need to address as the project moved to a detailed design stage. In particular, these limitations included:

  • poor integration with the Bays Precinct masterplan
  • traffic capacity constraints on Victoria Road and Anzac Bridge
  • construction complexity.

Following a comprehensive review in mid‑2016, TfNSW changed the design of the M4‑M5 Link and Rozelle Interchange to address these limitations. These changes included:

  • deletion of the Camperdown intersection to improve traffic conditions on Parramatta Road
  • a fully underground and larger Rozelle Interchange with 10‑hectare dedicated parklands
  • a toll‑free tunnel link from Iron Cove Bridge to Anzac Bridge
  • increasing the lanes in the dual tunnels from three to four each way.

TfNSW documented, but did not publish, the rationale for the design changes, including how the changes addressed the limitations of the previous design while providing increased community benefit through the creation of open space. TfNSW undertook cost comparison studies which estimated that these changes would have a neutral impact on the estimated project cost while achieving the same or improved benefits.

TfNSW's record‑keeping systems for large infrastructure investments negatively impact accountability and transparency

In response to our formal requests for relevant information, made during the conduct of this audit, TfNSW advised that complete and valid records of key decision‑making processes, analysis and advice were unavailable. Additionally, TfNSW often provided information that was incomplete or unverifiable (for instance, unsigned briefing notes). This is not consistent with accepted governance practices and does not comply with the requirements of the State Records Act 1998.

We also requested that TfNSW provide a list of relevant documents held by the Sydney Motorway Corporation (SMC). While TfNSW acknowledged that SMC may hold material relevant to the audit, TfNSW did not have a list or description of these documents. As SMC is now a majority privately held entity, both the Audit Office and TfNSW have limited power to require SMC to provide documentation.

The delivery timeframe for large and complex infrastructure projects such as WestConnex frequently exceeds five years, and some projects can take over a decade to deliver. These projects represent a significant investment of public resources and government agencies should expect independent review and assurance activities such as performance audits. The establishment of dedicated record keeping facilities for major infrastructure projects, such as data rooms, would improve transparency and accountability. This would ensure that the use of public resources is fully auditable in line with public expectations and the requirements of the Government Sector Finance Act 2018, the State Records Act 1998 and the Public Finance and Audit Act 1983.

2. Recommendations

By December 2021, TfNSW should:

1. review the impact of scope changes on project objectives, costs and benefits for complex infrastructure projects

2. when preparing business cases for complex large infrastructure projects, ensure that the estimated costs and benefits of works which are reasonably expected to meet consent conditions are included in the overall project cost and its benefits (as per Treasury guidelines)

3. establish and maintain centralised and project‑specific record keeping, including through dedicated project data rooms, to ensure major infrastructure projects can readily be subject to external oversight and assurance.

By June 2022, INSW should:

4. provide transparent whole‑of‑program assurance on total costs and benefits throughout the project life‑cycle when complex projects are split into sub‑projects.

By June 2022, NSW Government should:

5. consider enhancing the public transparency of existing infrastructure assurance processes by requiring that large complex infrastructure programs undergo periodic review at a whole‑of‑program level. This could take the form of reports to Parliament on the total costs and benefits on selected large and complex projects by the responsible agency, including cost to government and cost to community of funding and financing, as well as an accompanying independent assessment of the agency report.

Following our 2014 performance audit report 'WestConnex: Assurance to the government', the NSW Government established the Infrastructure Investor Assurance Framework (IIAF). INSW is responsible for the development, implementation and administration of the IIAF. The assurance framework involves gateway reviews, health checks, deep dive reviews, and project monitoring and reporting at various stages in the lifecycle of a project. The main aims of the IIAF are to help ensure major infrastructure projects are delivered on time and on budget, and to ensure that reports are regularly monitored by the Cabinet of the NSW Government. The IIAF gateway review process is compulsory for all significant investments and expenditure under the NSW Treasury Gateway Policy.

In accordance with the IIAF, INSW is responsible for the following:

  • providing a dedicated Assurance Team including Gateway Review Managers to coordinate Reviews
  • determining appropriate expert reviewers, and manages scheduling, commissioning and administration of Assurance Review reports. Infrastructure NSW is independent of the Expert Review Team
  • monitoring Tier 1 – High Profile/High Risk projects, Tier 2 and Tier 3 (if required) project performance through independent Assurance Reviews
  • providing independent analysis and advice on key risks and any corrective actions recommended for Tier 1 – High Profile/High Risk, Tier 2 and Tier 3 projects
  • escalating projects to Infrastructure Investor Assurance Committee (IIAC) and Cabinet where projects present ‘red flag issues’ and where corrective action is needed
  • working with delivery agencies to register all capital projects with an estimated cost greater than $10.0 million and ensures they are risk profiled and assigned a risk‑based project tier with an endorsed IIAF Project Registration report
  • preparing forward looking annual Cluster Assurance Plans
  • maintaining and continuously improves the IIAF process
  • reporting to the IIAC, Cabinet and Infrastructure NSW Board
  • regularly report to NSW Treasury on the performance of the IIAF.

In relation to WestConnex, TfNSW is the sponsor agency responsible for meeting relevant IIAF requirements, including:

  • registering and risk profiling projects
  • IIAF gateway, health check, and deep dive assurance reviews
  • regular reporting.

Under the IIAF, it is mandatory for all capital projects valued over $10.0 million to be registered with INSW. Capital projects can be registered either as a program (comprising of a group of related projects or activities) or as a project (which may or may not be part of a program).

According to the IIAF, programs tend to have a lifespan of several years and aim to deliver outcomes and benefits related to an organisation's strategic objectives. Projects tend to have a shorter lifespan, and deal with outputs. Projects can, however, be grouped under a single program if they are similar in nature or if they are aimed at collectively achieving a strategic objective. Complex projects can be delivered in multiple stages, under different contracts, and across different time periods.

The last assurance review of the entire WestConnex program of works as a whole was in 2015

INSW conducted the first IIAF gateway review of WestConnex in August 2015. TfNSW developed a draft WestConnex Updated Strategic Business Case to consolidate the latest analysis on WestConnex, and to confirm that the project remained fit for purpose, economically viable, and financially deliverable. The review followed a recommendation in our 2014 performance audit report that business cases be thoroughly revisited.

During September 2015, INSW conducted additional informal reviews to identify strategic risks associated with public release of the WestConnex business case. Subsequently, INSW gave the Premier of NSW its views on the draft business case, including the following points:

  • The $398 million budget for Sydney Gateway was insufficient to meet the benefits claimed in the business case for a ‘functional’ connection to Sydney Airport and Port Botany. INSW studies indicate a future‑proof solution would require a minimum spend of $755 million.
  • Enabling works for WestConnex estimated at $1.534 billion were excluded from the cost of WestConnex. Significant work remained for RMS to identify mitigation measures to address planning approvals and network performance issues.
  • Enabling works (a Southern Connector), an access ramp and surface road improvements within St Peters were excluded from the draft 2015 business case despite their inclusion in the WestConnex scope in the 2014–15 State Budget.
  • The overall cost of works not funded within the WestConnex budget ranged from $2.011 billion to $2.196 billion. This included the enabling works, access ramp and surface road improvements and the shortfall for Sydney Gateway.

All WestConnex related projects, including Sydney Gateway have undergone independent assurance reviews under the IIAF

Since INSW submitted the first WestConnex progress update report to Cabinet in June 2015, INSW has been reporting monthly on the different stages of the WestConnex Program, including Sydney Gateway, as the projects were registered with INSW as High‑Profile, High‑Risk projects. Separate reporting enabled INSW to report and review each stage with more detailed scrutiny, compared to the reporting and reviewing at a program level.

WestConnex Stage 2 (New M5) underwent both mandatory and non‑mandatory reviews at key points in the project lifecycle. Three mandatory gateway reviews – at Gate 2 (Final business case), Gate 3 (Readiness for market), and Gate 4 (Tender evaluation) – were conducted by TfNSW before the introduction of IIAF. Four non‑mandatory health check reviews and one non‑mandatory deep dive review were conducted after the introduction of the IIAF managed by INSW.

Similarly, WestConnex Stage 3 projects – M4‑M5 link, M4‑M5 Tunnels, and Rozelle Interchange – also underwent mandatory and non‑mandatory reviews at key points in their lifecycle under IIAF.

The M4‑M5 Link had two mandatory gateway reviews and one non‑mandatory health check review under IIAF. These reviews were conducted before Stage 3 was split into two stages, due to major design changes to the Rozelle Interchange and the M4‑M5 tunnels.

The M4‑M5 tunnels had two mandatory gateway reviews (at Gates 3 and 4), one non‑mandatory health check review, and one non‑mandatory deep dive review under IIAF.

Rozelle Interchange also underwent three mandatory gateway reviews at Gate 3 (part 1), Gate 3 (part 2), and Gate 4, two non‑mandatory health check reviews, and one non‑mandatory deep dive review under IIAF.

Since mid‑2017, the Sydney Gateway project has undergone required independent assurance reviews, as well as a number of optional assurance reviews

In November 2016, INSW conducted a mandatory Gate 1 gateway review on a strategic business case for the Sydney Gateway Project. TfNSW did not proceed with this business case. Following the separation of Sydney Gateway from WestConnex in mid‑2017, TfNSW developed a new business case for Sydney Gateway. It has undergone the required Gate 1, Gate 2, and Gate 3 gateway reviews, as well as two non‑mandatory health check reviews, and three non‑mandatory deep dive reviews under IIAF.

Network integration works have undergone all IIAF required assurance reviews

TfNSW completed a strategic business case for the Network Integration Program in August 2020, and INSW completed a gateway review in November 2020. This is despite network integration projects starting as early as 2015, with $645 million having been spent by June 2020. The strategic business case included a prioritisation process for completing remaining works in the program. Prior to November 2020, TfNSW registered individual network integration projects with INSW, and these projects have undergone gateway reviews where required.

The Network Integration Program strategic business case does not include Rozelle interchange network integration works ($353 million) and additional network integration works to settle a contractor claim adjacent to St Peters Interchange ($190 million). These were excluded from the business case on the basis they had already been approved by government, and as such were not subject to the prioritisation elements of the business case. TfNSW has not developed separate business cases for these works, although the scope of the St Peters Interchange works was developed through a negotiated process.

TfNSW did not prepare business cases for some network integration works which have commenced, including the $323 million Campbell Road/Euston Road works

Prior to its development of the August 2020 strategic business case, TfNSW did not prepare business cases for many network integration works that have commenced, and in some instances were completed, before 2019. Significantly, TfNSW did not prepare a business case for the Campbell Road/Euston Road works, which cost $323 million and have been completed.

In 2016, TfNSW’s Business Case Policy requires the creation of business cases for capital projects costing over $1.0 million. At the time of writing this report, TfNSW’s draft policy requires full business cases for capital projects costing $10.0 million or more.

There is no requirement for ongoing ‘whole‑of‑program’ assurance of the WestConnex program of works, including related projects

INSW conducted its first gateway review of WestConnex (as a program, which consisted of composite projects) in August 2015. Following that review, TfNSW registered each of the components of WestConnex with INSW as individual projects, rather than keeping WestConnex registered as a program or complex project. The IIAF allows this to occur.

Separate registration enabled INSW to report and review each stage with more scrutiny compared to whole‑of‑program level review.

Such an approach has merit, considering the individual stages (and components of these stages) are multi‑million dollar works in their own right. Each project has its own timing for gateway reviews at stages such as 'Readiness for Market' and 'Tender Evaluation'.

Once a program such as WestConnex is broken down into its composite parts, there is no requirement for the sponsor agency (TfNSW) or INSW to conduct independent assurance on the program of works as a whole until the whole program is completed as part of the Benefits Realisation (Gate 6) gateway review. The absence of strategic, holistic reviews of projects of the scale and complexity such as WestConnex during their delivery allows for total costs and benefits to become opaque and avoid scrutiny. Projects of this scale require greater ongoing transparency on total costs and benefits in order to ensure confidence they will meet intended objectives within budget.

INSW has advised us that it has prepared a proposal to expand its assurance function to include whole‑of‑program review of inter‑related infrastructure projects.

Appendix one – Responses from agencies

Appendix two – Network integration works

Appendix three – About the audit

Appendix four – Performance auditing

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #351 - released (17 June 2021).

Published

Actions for Acquisition of 4–6 Grand Avenue, Camellia

Acquisition of 4–6 Grand Avenue, Camellia

Transport
Asset valuation
Compliance
Fraud
Infrastructure
Internal controls and governance
Management and administration
Procurement
Risk

The Auditor-General for New South Wales, Margaret Crawford, has today released a report on Transport for NSW’s (TfNSW) acquisition of 4–6 Grand Avenue in Camellia.

This audit, which was requested on 17 November 2020 by the Hon. Andrew Constance MP, the Minister for Transport and Roads, examined:

  • whether TfNSW conducted an effective process to purchase 4–6 Grand Avenue, Camellia
  • whether TfNSW has effective processes and procedures to identify and acquire property required to deliver the NSW Government’s major infrastructure projects.

The audit found that TfNSW conducted an ineffective process when it purchased 4–6 Grand Avenue, Camellia. The audit also found that TfNSW’s internal policies and procedures to guide the transaction were, and continue to be, insufficient.

The Auditor-General has made seven recommendations to address the issues identified in the report.

On 17 November 2020, the Hon. Andrew Constance MP, the Minister for Transport and Roads, requested this audit under section 27B(3)(c) of the Public Finance and Audit Act 1983.

On 15 June 2016, Transport for New South Wales (TfNSW) acquired 6.3 hectares of land at 4–6 Grand Avenue, Camellia, by agreement from Grand 4 Investments Pty Ltd. Grand 4 Investments was a business entity established by the owners of Billbergia Pty Ltd, a property development and investment company.

TfNSW paid Grand 4 Investments $53.5 million and assumed liability for addressing environmental issues and contamination associated with the site. This took place seven months after the vendor acquired the land as part of a competitive Expression of Interest process, in which TfNSW also participated, for $38.15 million.

TfNSW is the NSW Government agency responsible for most major transport infrastructure projects in New South Wales. TfNSW acquired the Camellia site for use as a stabling and maintenance depot to support the Parramatta Light Rail (PLR) project.

Consistent with the minister’s request, this audit assessed:

  • whether TfNSW conducted an effective process to purchase 4–6 Grand Avenue, Camellia
  • whether TfNSW has effective processes and procedures to identify and acquire property required to deliver the NSW Government’s major infrastructure projects.

In considering the effectiveness of the processes for this purchase, the audit considered:

  • the requirements of the Land Acquisition (Just Terms Compensation) Act 1991 (the Act)
  • the application of sound processes to manage risk to the NSW Government and to achieve value for money
  • the application of disciplines associated with complex procurement, such as probity, in a NSW Government context.
The acquisition of the 4–6 Grand Avenue site in Camellia was consistent with a 2014 feasibility study for the PLR, but occurred before the completion of detailed project planning or an acquisition strategy.

TfNSW made two attempts to acquire the 4–6 Grand Avenue site in Camellia, and was successful on the second attempt. TfNSW recognised the risks associated with early acquisition and had high-level strategies in place should the site not be required.

The specific site had been identified in a feasibility study for the PLR commissioned by TfNSW in 2014 as one of several options in Camellia for a stabling and maintenance depot. However, TfNSW had not done any substantive analysis of the various options to identify a preferred location before the two opportunities to acquire 4–6 Grand Avenue were brought to TfNSW’s attention by the landowners (or their agents). On both occasions, TfNSW chose to actively pursue acquisition in advance of any such analysis.

The acquisition was also not informed by a Property Acquisition Strategy, which TfNSW policy recommends in order to guide the process and manage acquisition specific risks.

In 2015, TfNSW identified that it would require a stabling and maintenance depot in the Camellia area for the Parramatta Light Rail

In 2014, TfNSW commissioned an external engineering consultancy to undertake a feasibility design study for the Parramatta Light Rail - the Parramatta Transport Corridor Strategy Feasibility Design study (herein referred to as ‘the feasibility study’). In early 2015, TfNSW received the feasibility study, which was one of several key sources that informed the development of business cases for the PLR.

The feasibility study recommended that TfNSW should consolidate the maintenance and cleaning operations with overnight stabling facilities on one site. The study noted that the optimal location for any such site would be in close proximity to the proposed network, and noted that the site must have access to road connections to accommodate access for cars and trucks.

The study found that a centrally located stabling and maintenance facility would be required for all routes serving the Parramatta CBD, and that the Camellia industrial area was a preferred location for such a facility. The study noted that the Camellia area was contaminated.

The feasibility study notes that its conclusions were based on assumptions about the light rail system adopted and decisions made by the future operator of the system, who had not yet been selected or appointed.

TfNSW's decision to progress a potential acquisition in 2015 considered the risk that the site may not be required

TfNSW's FIC was responsible for making decisions on funding allocations at a whole of program level within TfNSW. FIC was also responsible for approving ‘high-risk/high-value’ variations to program budgets. Members of the FIC included:

  • Secretary of Transport for NSW
  • Deputy Secretary, Infrastructure and Services
  • Deputy Secretary, Freight, Strategy and Planning
  • Deputy Secretary, Customer Services
  • Deputy Secretary Finance and Investment
  • Deputy Secretary People and Corporate Services.

An April 2015 submission, from the then Deputy Director-General to the agency’s FIC, sought authorisation and funding approval to participate in an Expression of Interest sale process. It noted the risk that the project may not go ahead. The submission advised that:

By acquiring a strategic site now, it reduces the risk of having to pay an improved value or a value that may be subject to rapidly improving land values due to changes in land use and rezoning.

The property can be acquired for the project, held strategically and income generated by leasing the site as hardstand 1 space until the project requires the land for the Parramatta Light Rail project.

If the project does not proceed in the medium to longer term, the property can be sold at a premium to what has been paid today as property fundamentals improve.

This submission acknowledged the risks associated with environmental contamination and proposed that these risks would be managed by negotiating a contract where the remediation and associated expenses would be at the landowner’s cost. 

TfNSW assessed the 4–6 Grand Avenue site as one of several sites in Camellia that was a feasible location for a stabling and maintenance facility

The Departmental feasibility study assessed six potential sites for a stabling and maintenance facility, including 4–6 Grand Avenue, noting strengths and weaknesses of each site. A different site on Grand Avenue was assessed as the ‘base case’ option (1 Grand Avenue). The study’s comments on the 4–6 Grand Avenue site included the following:

With an area of approximately 63,000m2, this site has sufficient space for a depot with the required stabling yard and maintenance facilities. The location allows for good road access and LRT [light rail transit] access would be from Grand Avenue, which may require a road crossing or signalised intersection. The site has been used for general industrial uses; however the land has been cleared and is currently undergoing remediation 2. The site is not affected by flooding based on one in 100-year flood data.

In early 2015, once the opportunity to acquire 4–6 Grand Avenue emerged, TfNSW commissioned a specific feasibility study of the 4–6 Grand Avenue site. The feasibility studies clearly documented the existence of environmental contamination. In April 2015, the report concluded:

Given the limitations of this report and within the parameters that have been set it is concluded that from a spatial and geographic perspective the site at 6 Grand Avenue would be suitable as a stabling and maintenance depot for the Parramatta light rail project. There are few engineering and environmental constraints that would affect the feasibility level analysis of this site and all issues identified, within this desk study, are considered to be resolvable. However this being said there is a significant amount of work necessary to reach the final layout and definition of the stabling and maintenance depot. There are numerous items which require further consideration and conformation; planning approvals could impose restrictions on building heights, noise mitigation measures, light and visual impact requirements all of which can have significant impacts on the spatial requirements of any stabling and maintenance depot. 

The acquisition of 4–6 Grand Avenue was not informed by a Property Acquisition Strategy

For major projects, TfNSW typically requires the project team to complete a Property Acquisition Strategy, which is intended to guide both process as well as specific acquisition issues expected to be faced during the project. The Property Acquisition Strategy is not a mandated document but is a recommended tool to support property acquisition as part of major projects.

TfNSW did not have a Property Acquisition Strategy in place to guide the 2015 Expression of Interest process. On 6 November 2015, the then Project Director for the PLR project emailed the property team, noting a need to develop a Property Acquisition Strategy to close off the scoping design and preliminary business case.

In January 2016, TfNSW developed a draft Property Acquisition Strategy for the Parramatta Light Rail Project, although it was silent on the potential sites for the stabling and maintenance facility.

TfNSW focussed on 4–6 Grand Avenue because it was available and aligned to TfNSW's strategic interests

In early 2015, officials commenced monitoring the market for industrial real estate in the Camellia area and surrounds for possible sites for a stabling and maintenance facility.

In March 2015, then owner of the site, Akzo Nobel Pty Limited released the 4–6 Grand Avenue site through an Expression of Interest process managed by CBRE.

TfNSW’s then Deputy Director-General, Planning, sought approval from FIC to lodge an Expression of Interest up to $30.0 million. Approval was sought on the basis that it would ‘provide certainty for the Parramatta Light Rail project by allowing for a depot site in a suitable location and potentially avoid higher costs or longer timeframes associated with compulsory acquisition following completion of the project’s business case’. FIC approved the request at its meeting on 9 April 2015.

At this time, TfNSW had not conducted any analysis of financial or operational benefits and costs of the potential sites identified in earlier feasibility studies. TfNSW staff advised us that the decision to participate in the Expression of Interest process for 4–6 Grand Avenue was because it was available. There is no documentation substantiating this statement, which TfNSW staff provided verbally as part of this audit.

In November 2015, TfNSW was advised that it was unsuccessful in the Expression of Interest process and that Grand 4 Investments (a related entity of Billbergia) had purchased 4–6 Grand Avenue. TfNSW did not conduct any further analysis of alternative potential sites in Camellia between this date and commencing discussions with Grand 4 Investments in April 2016. In that time there had been some movement on other properties that were included in the feasibility study, including 37–39a Grand Avenue being under offer in September 2015.

In March 2016, TfNSW approached CBRE to organise a meeting with Grand 4 Investments. On 1 April 2016, TfNSW met with Grand 4 Investments.

TfNSW advises that a perceived benefit of the 4–6 Grand Avenue site was that it was not subject to other uses or leaseholds that would increase the cost of compulsory acquisition. Officers involved in the acquisition advised that other nominated sites in the feasibility study were subject to other uses or leaseholds. 


1  A hardstand space is a large, paved area to store cars, heavy vehicles and machinery.
2  Officers familiar with the acquisition could not confirm the nature of remediation being undertaken, but noted that the previous landowner had cleared buildings from the site, which may have been considered part of remediation.
TfNSW's independent valuation, which it commissioned and received after the acquisition, specifically excluded consideration of environmental contamination risk. As a result, TfNSW is exposed to the risk that the acquisition was not fully compliant with the Land Acquisition (Just Terms Compensation) Act 1991 (the Act) because it did not use an accurate estimate of market value during negotiations. That said, the acquisition of 4–6 Grand Avenue by agreement was consistent with preferred processes described in the Act.

TfNSW acquired the site from the landowner by agreement, and this is consistent with provisions in the Act. Obtaining approval for compulsory acquisition should negotiations for agreement break down is also consistent with the Act. That said, TfNSW did not at any time assess whether a compulsory acquisition could have resulted in acquisition at a lower cost than what was negotiated by agreement.

Despite the high risks associated with the acquisition, TfNSW did not commission a formal valuation in time to inform the negotiation and purchase. Instead, TfNSW relied on internal advice to estimate market value, but did not obtain a formal valuation from those advisors. For high-risk transactions, the greater expertise and arm's-length independence of an external specialist valuer should be preferred over an agency's own staff.

On 15 June 2016, the settlement date for the acquisition, TfNSW commissioned a formal independent valuation of the site. On 23 November 2016, TfNSW received the final formal valuation report. By not obtaining a formal independent valuation of the property in advance of acquisition to inform the acquisition value, TfNSW exposed itself to non-compliance with the Act by not establishing the market value as the basis for the acquisition price. TfNSW also breached its own internal policies.

TfNSW instructed the valuer to conduct its valuation within the following parameters:

  • Market valuation on an ‘as is’ basis – market value based on the methodology described in the Act. This approach valued the site at $25.0 million.
  • Market valuation on a speculative development basis – market value based on the financial value of the vendor's intended use of the site which, in this case, involved leasing the site for industrial use. This approach valued the site at $52.0 million, and TfNSW advised us this valuation supported the purchase price.
  • Disregard the impact of environmental contamination – TfNSW specifically instructed the independent valuer to disregard any known (or unknown) site contamination. As TfNSW knew of the significant environmental contamination affecting the site, this parameter resulted in a valuation that overstated the value of the site as it did not consider the cost of environmental remediation. The valuer applied this assumption for both market valuation approaches.

Additionally, as the independent valuer completed the valuation after the purchase was finalised, there is a risk that the valuation may have been influenced by the known purchase price.

TfNSW's failure to acquire a formal valuation and an assessment of the financial impact of environmental remediation before it purchased 4–6 Grand Avenue represents ineffective administration and governance.
TfNSW acquired the site at a time when there was demand and increasing prices for industrial property in the area. However, TfNSW did not effectively assess and manage the risks associated with the acquisition, and gaps in process led to increased risk. Briefings to decision-makers did not contain important information, and we found no evidence that gaps in advice were queried or explored by decision-makers.

TfNSW did not have plans or advice in place to assist in managing risk, such as:

  • a property acquisition plan
  • a comprehensive and up-to-date risk management plan
  • a negotiation strategy, or any authorisation limit or minimal acceptable position
  • an independent professional evaluation
  • external expert advice (with the exception of legal advice relating to the contract of sale).

TfNSW was aware of contamination issues affecting the land and had access to considerable information about the environmental conditions, such as site environmental audit reports and information on the NSW Environment Protection Authority's contaminated land register. However, TfNSW had not analysed specific technical information about the contamination and therefore was not aware of the risk implications and cost for remediation. Despite this, TfNSW changed its position from not accepting the risks and costs of contamination, to acquiring the site unconditionally. The basis for this decision is unclear and undocumented.

Briefing to senior leaders on the acquisition was silent on a number of important matters that would have been important for approvers to consider, including:

  • an explanation of the 40 per cent increase in purchase price between November 2015 and May 2016, and a 165 per cent increase from TfNSW’s offer in April 2015
  • the contamination risks associated with the site and an evidence-based estimate of potential costs to remediate the site
  • advice that an independent valuation had not been obtained, inconsistent with TfNSW policy.

Consideration of the acquisition by FIC was based on a summary business paper and was managed out-of-session, thereby removing the ability for comprehensive consideration of the acquisition proposal and its risks.

The probity management controls and assurances in place for the acquisition of the 4–6 Grand Avenue site were insufficient. These insufficiencies were exacerbated by the probity risk profile of the transaction.

The 4–6 Grand Avenue acquisition was a high-risk/high-value transaction, undertaken in a volatile property market in a short timeframe under pressure from Grand 4 Investments. TfNSW was engaging in a direct negotiation in advance of detailed planning for the acquisition, or the PLR as a whole. These circumstances contribute to heightened probity risk.

TfNSW did not establish a probity plan and sought no probity support throughout the acquisition. Also, with one exception, the staff involved in the acquisition did not complete conflict of interest declarations.

TfNSW was aware of the potential for probity or integrity issues with the transaction when it commissioned an internal audit in connection with the transaction in 2019. Internal discussions considered whether a misconduct investigation may be more appropriate, however no such investigation was undertaken.

TfNSW's insufficient probity practices, in addition to its failure to keep complete or comprehensive records of negotiations or decisions, reduce transparency of the process and its outcome and expose TfNSW to a greater risk of misconduct, corruption and maladministration.

At the time of the transaction, the TfNSW policy framework was not sufficiently risk-focussed and did not provide clarity on when officers ought to apply specific guidance or procedures. TfNSW's policies and procedures are more focussed on acquiring land to meet project needs and timeframes, and less on assuring value for money and managing risks.

At the time of its acquisition of 4–6 Grand Avenue, TfNSW had property acquisitions policies and procedures in place. Each of these were broadly sound in their content and intent. However, they lacked specificity on how or when to apply guidance, and when risk levels should elevate the importance of recommended guidance.

TfNSW's key guidance was principles based and relied on agency staff using their experience and expertise to apply guidance according to the circumstances of an individual transaction. This guidance was not duly applied in the acquisition of 4–6 Grand Avenue, Camellia. In addition, TfNSW does not have quality or control assurance to identify when TfNSW officers did not apply important policies or processes.

The primary focus of the TfNSW’s property acquisition guidance is to achieve vacant possession of land in a timeframe that meets the need of the relevant transport project. There is less specific focus on the need to meet the requirements of the NSW Government financial management framework.

Appendix one – Response from agency 

Appendix two – About the audit 

Appendix three – Performance auditing

 

Copyright Notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #349 - released (18 May 2021).

Published

Actions for Central Agencies 2020

Central Agencies 2020

Premier and Cabinet
Treasury
Financial reporting
Internal controls and governance
Management and administration
Risk

This report analyses the results of our audits of the financial statements of the Treasury, Premier and Cabinet, Customer Service cluster agencies (central agencies), and the Legislature for the year ended 30 June 2020. The table below summarises our key observations.

1. Financial reporting

Audit opinions and timeliness of reporting

Unqualified audit opinions were issued on the 2019–20 financial statements of central agencies and the Legislature.

The audit opinion on the Social and Affordable Housing NSW Fund's compliance with the payment requirements of the Social and Affordable Housing NSW Fund Act 2016 was qualified.

All agencies met statutory deadlines for submitting
financial statements. 

Agencies were financially impacted by recent emergency events The NSW Government allocated $1.4 billion to provide small business support and bushfire recovery relief, support COVID-19 quarantine compliance management, recruit more staff to respond to increased customer demand, and meet additional COVID-19 cleaning requirements. Agencies spent $901 million (64 per cent of the allocated funding) for the financial year ended 30 June 2020. NSW Self Insurance Corporation reported an increase of $850 million in its liability for claims related to emergency events.
AASB 16 'Leases' resulted in significant changes to agencies' financial position The implementation of new accounting standards was challenging for many agencies. The New South Wales Government Telecommunications Authority was not well-prepared to implement AASB 16 'Leases' and had not completely assessed contracts that contained leases. This resulted in understatements of leased assets and liabilities by $56 million which were subsequently corrected.
Implementation of new revenue standards NSW Treasury did not adequately implement the new revenue standard AASB 1058 ‘Income of Not-for-Profit Entities’ for the Crown Entity. This resulted in understatements of $274 million in opening equity and $254 million to current year revenue, which have been corrected in the final financial statements.

2. Audit observations

Management letter findings and repeat issues Our 2019–20 audits identified nine high risk and 122 moderate risk issues across central agencies and the Legislature. The high risk issues were identified in the audits of:
  • Insurance and Care NSW
  • New South Wales Government Telecommunications Authority
  • Rental Bond Board
  • Independent Commission Against Corruption
  • NSW Treasury
  • Crown Entity
  • Department of Premier and Cabinet.

High risk findings include:

  • Insurance and Care NSW (icare) allocates service costs to the Workers Compensation Nominal Insurer, and the other schemes it supports. The documentation supporting cost allocations does not demonstrate how these allocations reflect actual costs. There is a risk of the Workers Compensation Nominal Insurer being overcharged.
  • New South Wales Government Telecommunications Authority's delay in capitalisation and valuation of material capital projects; and insufficient work performed to implement the new accounting standard AASB 16 ‘Leases’.
  • NSW Treasury's four-year plan to transition RailCorp to a for-profit State Owned Corporation called Transport Asset Holding Entity of New South Wales (TAHE) by 1 July 2019, remains to be implemented. On 1 July 2020, RailCorp converted to TAHE. A large portion of the planned arrangements are still to be implemented. As at the time of the audit, the TAHE operating model, Statement of Corporate Intent (SCI) and other key plans and commercial agreements were not finalised. In the absence of commercial arrangements with the public rail operators, there is a lack of evidence to demonstrate TAHE’s ability to create a commercial return in the long term. This matter has been included as a high risk finding in our management letter as there may be financial reporting implications to the State if TAHE does not generate a commercial return for its shareholders in line with the original intent. NSW Treasury and TAHE should ensure the commercial arrangements, operating model and SCI are finalised in 2020–21.

Of the 122 moderate risk issues, 36 per cent were repeat issues. The most common repeat issue related to weaknesses in controls over information technology user access administration, which increases the risk of inappropriate access to systems and records.

Grants administration for disaster relief Service NSW delivers grants responding to emergency events on behalf of other NSW Public Sector agencies. Since the first grant program commenced in January 2020, Service NSW processed approximately $791 million to NSW citizens and businesses impacted by emergency events for the financial year ended 30 June 2020. A performance audit of grants administration for disaster relief is planned for 2020–21. It will assess whether grants programs administered under the Small Business Support Fund were effectively designed and implemented to provide disaster relief.
Internal controls at GovConnect NSW service providers require enhancement

GovConnect NSW provides transactional and information technology services to central agencies. It engages an independent service auditor (service auditor) from the private sector to perform annual assurance reviews of controls at service providers, namely Infosys, Unisys and the Department of Customer Service (DCS). The service auditor issued:

  • unqualified opinions on information technology and business process controls at Infosys and Unisys, but there was an increase in control deficiencies identified in the user access controls at these service providers
  • a qualified opinion on DCS's information technology (IT) security monitoring controls because security tools were not implemented and monitored for the entire financial year. Responsibility for IT security monitoring transitioned from Unisys to DCS in 2019–20. These control deficiencies can increase the risk of fraud and inappropriate use of sensitive data.

These may impact on the ability of agencies to detect and respond to a cyber incident.

Recommendation:

We recommend DCS work with GovConnect service providers to resolve the identified control deficiencies as a matter of priority.

The NSW Public Sector's cyber security resilience needs to improve

The NSW Cyber Security Policy requires agencies to provide a maturity self-assessment against the Australian Cyber Security Centre (ACSC) Essential 8 to the head of the agency and Cyber Security NSW annually. Completed self-assessment returns highlighted limited progress in implementing the Essential 8.

Repeat recommendation:

Cyber Security NSW and NSW government agencies need to prioritise improvements to their cyber security resilience as a matter of urgency

Three Insurance and Care NSW (icare) entities had net asset deficiencies at 30 June 2020 The Workers Compensation Nominal Insurer, NSW Self Insurance Corporation and the Lifetime Care and Support Authority of NSW all had negative net assets at 30 June 2020. These icare entities did not hold sufficient assets to meet the estimated present value of all of their future payment obligations at 30 June 2020. The deterioration in net assets was largely due to increases in outstanding claims liabilities. Notwithstanding the overall net asset deficiencies, the financial statements for these entities were prepared on a going concern basis. This is because future payment obligations are not all due within the next 12 months. Settlement is instead expected to occur over years into the future, depending on the nature of the benefits provided by each scheme.
icare has not been able to demonstrate that its allocation of costs reflects the actual costs incurred by the Workers Compensation Nominal Insurer and other schemes

Costs are incurred by icare as the 'service entity' of the statutory scheme it administers, and then subsequently recovered from the schemes through 'service fees'. In the absence of documentation supported by robust supporting analysis, there is a risk of the schemes being overcharged, and the allocation of costs being in breach of legislative requirements.

Recommendation:

icare should ensure its approach to allocating service fees to the Workers Compensation Nominal Insurer and the other schemes it manages, is transparent and reflects actual costs.

icare did not comply with GIPA requirements icare did not comply with the Government Information (Public Access) Act 2009 (GIPA) contract disclosure requirements in 2019–20 and has not complied for several years. A total of 417 contracts were identified by management as not having been published on the NSW Government’s eTendering website. The final upload of these past contracts occurred on 20 August 2020.
Implementation of Machinery of Government (MoG) changes MoG changes impacted the governance and business processes of some agencies. Our audits identified and reported areas for improvement in the consolidation of corporate functions following MoG implementation processes at Infrastructure NSW and in the Customer Service cluster.

This report provides Parliament and other users of NSW Government central agencies' financial statements and the Legislature's financial statements with the results of our financial audits, observations, analyses, conclusions and recommendations.

Emergency events, such as bushfires, floods and the COVID-19 pandemic significantly impacted agencies in 2019–20. Our findings on nine agencies that were most impacted by recent emergency events are included throughout this report.

Refer to Appendix one for the names of all central agencies and Appendix four for the nine agencies most impacted by emergency events.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely. This chapter outlines our audit observations on the financial reporting of central agencies and the Legislature for 2020, including the financial implications from recent emergency events.

Section highlights

  • Unqualified audit opinions were issued on the 2019–20 financial statements of central agencies and the Legislature. All agencies met the statutory deadlines for submitting their financial statements.
  • The audit opinion on the Social and Affordable Housing NSW Fund's compliance with the payment requirements of the Social and Affordable Housing NSW Fund Act 2016 was qualified as a result of a payment made without a Treasurer's delegation.
  • Agencies were impacted by emergency events during 2019–20. This included additional grants to fund specific deliverables.
  • The implementation of new accounting standards was challenging for many agencies. The New South Wales Government Telecommunications Authority was not well-prepared to implement AASB 16 'Leases' and had not completely assessed contracts that contained leases. This resulted in understatements of leased assets and liabilities by $56 million which were subsequently corrected.
  • NSW Treasury did not adequately implement the new revenue standard AASB 1058 ‘Income of Not-for-Profit Entities’ for the Crown Entity. This resulted in understatements of $274 million in opening equity and $254 million to current year revenue in the financial statements. These misstatements were due to incorrect revenue calculations performed by the Transport agencies. The Crown Entity relies on information from Transport agencies as they are responsible for carrying out the State’s contractual obligations for Commonwealth funded transport projects. The extent of misstatements could have been reduced with more robust quality review processes in place by Treasury and Transport.

 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines:

  • our observations and insights from the financial statement audits of agencies in the central agencies and the Legislature
  • our assessment of how well agencies adapted their systems, policies, procedures and governance arrangements in response to recent emergencies.

Section highlights

  • The 2019–20 audits identified nine high risk and 122 moderate risk issues across the agencies. Of the 122 moderate risk issues, 44 (36 per cent) were repeat issues. The most common repeat issue relates to weaknesses in controls over information technology user access administration.
  • Service NSW delivers grants responding to emergency events on behalf of other NSW Public Sector agencies. Since the first grant program commenced in January 2020, Service NSW processed approximately $791 million to NSW citizens and businesses impacted by these emergency events for the financial year ended 30 June 2020.
  • GovConnect NSW engaged an independent auditor (the service auditor) from the private sector to evaluate the internal controls of its service providers. DCS's information technology security monitoring controls were qualified by the service auditor because security tools were not implemented and monitored for the entire financial year. These may impact on the ability of agencies to detect and respond to a cyber incident.
  • NSW Government agency self-assessment results show that the NSW Public Sector's cyber security resilience needs urgent attention.
  • The Workers Compensation Nominal Insurer, NSW Self Insurance Corporation and the Lifetime Care and Support Authority of NSW all had negative net assets at 30 June 2020. The financial statements for these entities continued to be prepared on a going concern basis as their liabilities are not all due for settlement within the next 12 months.
  • icare did not comply with the Government Information (Public Access) Act 2009 (GIPA) contract disclosure requirements in 2019–20, and has not complied for several years. A total of 417 contracts were identified by management as not having been published on the NSW Government’s eTendering website. The final upload of these past contracts occurred on 20 August 2020.
  • Machinery of Government (MoG) changes impacted the governance and business processes of affected agencies. Our audits identified and reported areas for improvement in the consolidation of corporate functions following MoG changes at Infrastructure NSW and in the Customer Service cluster.

 

Published

Actions for Transport 2020

Transport 2020

Transport
Asset valuation
Cyber security
Financial reporting
Information technology
Infrastructure
Project management

1. Financial Reporting

Audit opinion Unmodified audit opinions issued for the financial statements of all Transport cluster entities.
Quality and timeliness of financial reporting All cluster agencies met the statutory deadlines for completing the early close and submitting the financial statements.

Transport cluster agencies continued to experience some challenges with accounting for land and infrastructure assets. The former Roads and Maritime Services and Sydney Metro recorded prior period corrections to property, plant and equipment balances.
Impact of COVID-19 on passenger revenue and patronage Total patronage and revenue for public transport decreased by approximately 18 per cent in 2019–20 due to COVID-19.

The Transport cluster received additional funding from NSW Treasury during the year to support the reduced revenue and additional costs incurred such as cleaning on all modes of public transport and additional staff to manage physical distancing.
Completion of the CBD and South East Light Rail The CBD and South East Light Rail project was completed and commenced operations in this financial year. At 30 June 2020, the total cost of the project related to the CBD and South East Light Rail was $3.3 billion. Of this total cost, $2.6 billion was recorded as assets, whilst $700 million was expensed.

2. Audit Observations

Internal control While internal controls issues raised in management letters in the Transport cluster have decreased compared to the prior year, control weaknesses continue to exist in access security for financial systems. We identified 56 management letter findings across the cluster and 43 per cent of all issues were repeat issues. The majority of the repeat issues relate to information technology controls around user access management.

There were three high risk issues identified - two related to financial reporting of assets and one for implementation of TAHE (see below).
Agency responses to emergency events Transport for NSW established the COVID-19 Taskforce in March 2020 to take responsibility for the overall response of planning and coordination for the Transport cluster. It also implemented the COVIDSafe Transport Plan which incorporates guidance on physical distancing, increasing services to support social distancing and cleaning.
RailCorp transition to TAHE On 1 July 2020, RailCorp was renamed Transport Asset Holding Entity of New South Wales (TAHE) and converted to a for-profit statutory State-Owned Corporation. TAHE is a commercial for-profit Public Trading Entity with the intent to provide a commercial return to its shareholders.

A plan was established by NSW Treasury to transition RailCorp to TAHE which covered the period 1 July 2015 to 1 July 2019. A large portion of the planned arrangements were not implemented by 1 July 2020. As at the time of this report, the TAHE operating model, Statement of Corporate Intent (SCI) and other key plans and commercial agreements are not finalised. The State Owned Corporations Act 1989 generally requires finalisation of an SCI three months after the commencement of each financial year. However, under the Transport Administration Act 1988, TAHE received an extension from the voting shareholders, the Treasurer and Minister for Finance and Small Business, to submit its first SCI by 31 December 2020. In accordance with the original plan, interim commercial access arrangements were supposed to be in place with RailCorp prior to commencement of TAHE.

Under the transitional arrangements, TAHE is continuing to operate in accordance with the asset and safety management plans of RailCorp. The final operating model is expected to include considerations of safety, operational, financial and fiscal risks. This should include a consideration of the potential conflicting objectives of a commercial return, and maintenance and safety measures.

This matter has been included as a high risk finding in our management letter due to the significance of the financial reporting impacts and business risks for TAHE.

Recommendation: TAHE management should:
  • establish an operating model in line with the original intent of a commercial return
  • finalise commercial agreements with the public rail operators
  • confirm forecast financial information to assess valuation of TAHE infrastructure
  • finalise asset and safety management plans.

Resolution of the above matters are critical as they may significantly impact the financial reporting arrangements for TAHE for 2020–21, in particular, accounting policies adopted as well as measurement principles of its significant infrastructure asset base.

Completeness and accuracy of contracts registers Across the Transport cluster, contracts and agreements are maintained by the transport agencies using disparate registers.

Recommendation (repeat): Transport agencies should continue to implement a process to centrally capture all contracts and agreements entered. This will ensure:
  • agencies are fully aware of contractual and other obligations
  • appropriate assessment of financial reporting implications
  • ongoing assessments of accounting standards, in particular AASB 16 ‘Leases’, AASB 15 'Revenue from Contract with Customers', AASB 1058 'Income of Not-for-Profit Entities' and new accounting standard AASB 1059 'Service Concession Arrangements: Grantors' are accurate and complete.

 

This report provides parliament and other users of the Transport cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations
  • the impact of emergencies and the pandemic.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Transport cluster for 2020, including any financial implications from the recent emergency events.

Section highlights

  • Total patronage and revenue for public transport decreased by approximately 18 per cent in 2019–20 due to COVID-19.
  • Unqualified audit opinions were issued on all Transport agencies' financial statements.
  • Transport cluster agencies continued to experience challenges with accounting of land and infrastructure assets.

 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our:

  • observations and insights from our financial statement audits of agencies in the Transport cluster
  • assessment of how well cluster agencies adapted their systems, policies and procedures, and governance arrangements in response to recent emergencies.

Section highlights

  • While there was a decrease in findings on internal controls across the Transport cluster, 43 per cent of all issues were repeat issues. Many repeat issues related to information technology controls around user access management.
  • RailCorp transitioned to TAHE on 1 July 2020. TAHE's operating model and commercial arrangements with public rail operators has not been finalised despite government original plans to be operating from 1 July 2019. TAHE management should finalise its operating model and commercial agreements with public rail operators as they may significantly impact the financial reporting arrangements for TAHE for 2020–21.
  • Completeness and accuracy of contracts registers remains an ongoing issue for the Transport cluster.

Appendix one – List of 2020 recommendations

Appendix two – Status of 2019, 2018 and 2017 recommendations

Appendix three – Management letter findings

Appendix four – Financial data

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Internal controls and governance 2020

Internal controls and governance 2020

Education
Environment
Community Services
Finance
Health
Industry
Justice
Premier and Cabinet
Transport
Treasury
Compliance
Cyber security
Information technology
Internal controls and governance
Management and administration
Procurement

The Auditor-General for New South Wales, Margaret Crawford today released her report on the findings and recommendations from the 2019–20 financial audits that relate to internal controls and governance at 40 of the largest agencies in the NSW public sector.

The bushfire and flood emergencies and the COVID‑19 pandemic continue to have a significant impact on the people and public sector of New South Wales. The scale of the government response to these events has been significant. The report focuses on the effectiveness of internal controls and governance processes, including relevant agencies’ response to the emergencies. In particular, the report focuses on:

  • financial and information technology controls
  • business continuity and disaster recovery planning arrangements
  • procurement, including emergency procurement
  • delegations that support timely and effective decision-making.

Due to the ongoing impact of COVID‑19 agencies have not yet returned to a business‑as‑usual environment. ‘Agencies will need to assess their response to the recent emergencies and update their business continuity, disaster recovery and other business resilience frameworks to reflect the lessons learnt from these events’ the Auditor-General said.

The report noted that special procurement provisions were put in place to allow agencies to better respond to the COVID-19 pandemic. The Auditor-General recommended agencies update their procurement policies to reflect the current requirements of the NSW Procurement Framework and the emergency procurement requirements.

Read the PDF report

This report analyses the internal controls and governance of 40 of the largest agencies in the NSW public sector for the year ended 30 June 2020. These 40 agencies constitute an estimated 85 per cent of total expenditure for all NSW public sector agencies.

1. Internal control trends
New, repeat and high risk findings

Internal control deficiencies increased by 13 per cent compared to last year. This is predominately due to a seven per cent increase in new internal control deficiencies and 24 per cent increase in repeat internal control deficiencies. There were ten high risk findings compared to four last year.

The recent emergencies have consumed agency time and resources and may have contributed to the increase in internal control deficiencies, particularly repeat deficiencies.

Agencies should:

  • prioritise addressing high-risk findings
  • address repeat internal control deficiencies by re-setting action plans and timeframes and monitoring the implementation status of recommendations.
Common findings

A number of findings remain common across multiple agencies over the last four years, including:

  • out of date or missing policies to guide appropriate decisions
  • poor record keeping and document retention
  • incomplete or inaccurate centralised registers or gaps in these registers.
2. Information technology controls
IT general controls

We found deficiencies in information security controls over key financial systems including:

  • user access administration deficiencies relating to inadequate oversight of the granting, review and removal of user access at 53 per cent of agencies
  • privileged users were not appropriately monitored at 43 per cent of agencies
  • deficient password controls that did not align to the agency's own password policies at 25 per cent of agencies.

The deficiencies above increase the risk of non-compliance with the NSW Cyber Security Policy, which requires agencies to have processes in place to manage user access, including privileged user access to sensitive information or systems and remove that access once it is not required or employment is terminated.

3. Business continuity and disaster recovery planning
Assessing risks to business continuity and Scenario testing

The response to the recent emergencies and the COVID-19 pandemic has encompassed a wide range of activities, including policy setting, on-going service delivery, safety and availability of staff, availability of IT and other systems and financial management. Agencies were required to activate their business continuity plans in response, and with the continued impact of COVID-19 have not yet returned to a business-as-usual environment.

Our audits focused on the preparedness of agency business continuity and disaster recovery planning arrangements prior to the onset of the COVID-19 pandemic.

We identified deficiencies in agency business continuity and disaster recovery planning arrangements. Twenty-three per cent of agencies had not conducted a business impact analysis (BIA) to identify critical business functions and determine business continuity priorities. Agencies can also improve the content of their BIA. For example, ten per cent of agencies' BIAs did not include recovery time objectives and six per cent of agencies did not identify key IT systems that support critical business functions. Scenario testing improves the effectiveness with which a live crisis is handled, but 40 per cent of agencies had not conducted a business continuity scenario testing exercise in the period from 1 January 2019 to 31 December 2019. There were also opportunities to improve the effectiveness of scenario testing exercises by:

  • involving key dependent or inter-dependent third parties who support or deliver critical business functions
  • testing one or more high impact scenarios identified in their business continuity plan
  • preparing a formalpost-exercise report documenting the outcome of their scenario testing.

Agencies have responded to the recent emergencies but addressing deficiencies will ensure agencies have adequate safeguards in their processes to again respond in the future, if required.

During 2020–21 we plan to conduct a performance audit on 'Business continuity and disaster recovery planning'. This audit will consider the effectiveness of agency business continuity planning arrangements to maintain business continuity through the recent emergencies and/or COVID-19 pandemic and return to a business-as-usual environment. We also plan to conduct a performance audit on whole-of-government 'Coordination of emergency responses'.

Responding to disruptions

We found agencies' governance functions could have been better informed about responses to disruptive incidents that had activated a business continuity or disaster recovery response between 1 January 2019 to 31 December 2019. For instance:

in 89 per cent of instances where a business continuity response was activated, a post-incident review had been performed. In 82 per cent of these instances, the outcomes were reported to a relevant governance or executive management committee

in 95 per cent of instances where a disaster recovery response was activated, a post incident review had been performed. In 86 per cent of these instances, the outcomes were reported to a relevant governance committee or executive management committee.

Examples of recorded incidents included extensive air quality issues and power outages due to bushfires, system and network outages, and infected and hijacked servers.

Agencies should assess their response to the recent emergencies and the COVID-19 pandemic and update business continuity, disaster recovery and other business resilience frameworks to incorporate lessons learned. Agencies should report to those charged with governance on the results and planned actions.

Management review and oversight Eighty-two per cent and 86 per cent of agencies report to their audit and risk committees (ARC) on their business continuity and disaster recovery planning arrangements, respectively. Only 18 per cent and five per cent of ARCs are briefed on the results of respective scenario testing. Briefing ARCs on the results of scenario testing exercises helps inform their decisions about whether sound and effective business continuity and disaster recovery arrangements have been established.
4. Procurement, including emergency procurement
Policy framework

Agency procurement policies did not capture the requirements of several key NSW Procurement Board Directions (the Directions), increasing the risk of non-compliance with the Directions. We noted: 

  • 67 per cent of agencies did specify that procurement above $650,000 must be open to market unless exempt or procured through an existing Whole of Government Scheme or contract
  • 36 per cent of agencies did specify that procurements above $500,000 payable in foreign currencies must be hedged
  • 69 per cent of agencies' policies did specify that the agency head or cluster CFO must authorise the engagement of consultants where the engagement of the supplier does not comply with the standard commercial framework.

Recommendation: Agencies should review their procurement policies and guidelines to ensure they capture the key requirements of the NSW Government Procurement Policy Framework, including NSW Procurement Board Directions.

Managing contracts

Eighty-eight per cent of agencies maintain a central contract register to record all details of contracts above $150,000, which is a requirement of GIPA legislation. Of the agencies that maintained registers, 13 per cent did not capture all contracts and eight per cent did not include all relevant contract details.

Sixteen per cent of agencies did not periodically review their contract register. Timely review increases compliance with GIPA legislation, and enhances the effectiveness with which procurement business units monitor contract end dates, contract extensions and commence new procurement.

Training and support

Ninety-three per cent of agencies provide training to staff involved in procurement processes, and a further 77 per cent of agencies provide this training on an on-going basis. Of the seven per cent of agencies that had not provided training to staff, we noted gaps in aspects of their procurement activity, including:

  • not conducting value for money assessments prior to renewing or extending the contract with their existing supplier
  • not obtaining approval from a delegated authority to commence the procurement process
  • procurement documentation not specifying certain key details such as the conditions for participation including any financial guarantees and dates for the delivery of goods or supply of services.

Training on procurement activities ensures there is effective management of procurement processes to support operational requirements, and compliance with procurement directions.

Procurement activities While agencies had implemented controls for tender activities above $650,000, 43 per cent of unaccredited agencies did not comply with the NSW Procurement Policy Framework because they had not had their procurement endorsed by an accredited agency within the cluster or by NSW Procurement. This endorsement aims to ensure the procurement is properly planned to deliver a value for money outcome before it commences.
Emergency procurement

As at 30 June 2020, agencies within the scope of this report reported conducting 32,239 emergency procurements with a total contract value of $316,908,485. Emergency procurement activities included the purchase of COVID-19 cleaning and hygiene supplies.

The government, through NSW Procurement released the 'COVID-19 Emergency procurement procedure', which relaxed procurement requirements to allow agencies to make COVID-19 emergency procurements. Our review against the emergency procurement measures found most agencies complied with requirements. For example:

  • 95 per cent of agencies documented an assessment of the need for the emergency procurement for the good and/or service
  • 86 per cent of agencies obtained authorisation of the emergency procurement by the agency head or the nominated employee under Public Works and Procurement Regulation 2019
  • 76 per cent of agencies reported the emergency procurement to the NSW Procurement Board.

Complying with the procedure helps to ensure government resources are being efficiently, effectively, economically and in accordance with the law.

Recommendation: Agency procurement frameworks should be reviewed and updated so they can respond effectively to emergency situations that may arise in the future. This includes:

  • updating procurement policies and guidelines to define an emergency situation, specify who can approve emergency procurement and capture other key requirements
  • using standard templates and documentation to prompt users to capture key requirements, such as needs analysis, supplier selection criteria, price assessment criteria, licence and insurance checks
  • having processes for reporting on emergency procurements to those charged with governance and NSW Procurement.
5. Delegations
Instruments of delegation

We found that agencies have established financial and human resources delegations, but some had not revisited their delegation manuals following the legislative and machinery of government changes. For those agencies impacted by machinery of government changes we noted:

  • 16 per cent of agencies had not updated their financial delegations to reflect the changes
  • 16 per cent of agencies did not update their human resources delegations to reflect the changes.

Delegations manuals are not always complete; 16 per cent of agencies had no delegation for writing off bad debts and 26 per cent of agencies had no delegation for writing off capital assets.

Recommendation: Agencies should ensure their financial and human resources delegation manuals contain regular set review dates and are updated to reflect the Government Sector Finance Act 2018, machinery of government changes and their current organisational structure and roles and responsibilities.

Compliance with delegations

Agencies did not understand or correctly apply the requirements of the Government Sector Finance Act 2018 (GSF Act), resulting in non-compliance with the Act. We found that 18 per cent of agencies spent deemed appropriations without obtaining an authorised delegation from the relevant Minister(s), as required by sections 4.6(1) and 5.5(3) of the GSF Act.

Further detail on this issue will be included in our Auditor-General's Reports to Parliament on Central Agencies, Education, Health and Stronger Communities, which will be tabled throughout December 2020.

Recommendation: Agencies should review financial and human resources delegations to ensure they capture all key functions of laws and regulations, and clearly specify the relevant power or function being conferred on the officer.

6. Status of 2019 recommendations
Progress implementing last year's recommendations

Recommendations were made last year to improve transparency over reporting on gifts and benefits and improve the visibility management and those charged with governance had over actions taken to address conflicts of interest that may arise. This year, we continue to note:

  • 38 per cent of agencies have not updated their gifts and benefits register to include all the key fields required under the minimum standards set by the Public Service Commission
  • 56 per cent of agencies have not provided training to staff and 63 per cent of agencies have not implemented an annual attestation process for senior management
  • 97 per cent of agencies have not published their gifts and benefits register on their website and 41 per cent of agencies are not reporting on trends in the gifts and benefits register to those charged with governance.

While we acknowledge the significance of the recent emergencies, which have consumed agency time and resources, we note limited progress has been made implementing these recommendations. Further detail on the status of implementing all recommendations is in Appendix 2.

Recommendation: Agencies should re-visit the recommendations made in last year's report on internal controls and governance and action these recommendations.

Internal controls are processes, policies and procedures that help agencies to:

  • operate effectively and efficiently
  • produce reliable financial reports
  • comply with laws and regulations
  • support ethical government.

This chapter outlines the overall trends for agency controls and governance issues, including the number of audit findings, the degree of risk those deficiencies pose to the agency, and a summary of the most common deficiencies we found across agencies. The rest of this report presents this year’s controls and governance findings in more detail.

Section highlights

We identified ten high risk findings, compared to four last year with two findings repeated from the previous year. There was an overall increase of 13 per cent in the number of internal control deficiencies compared to last year due to a seven per cent increase in new internal control deficiencies, and a 24 per cent increase in repeat internal control deficiencies. The recent emergencies have consumed agency time and resources and may have contributed to the increase in internal control deficiencies, particularly repeat deficiencies.

We identified a number of findings that remain common across multiple agencies over the last four years. Some of these findings related to areas that are fundamental to good internal control environments and effective organisational governance. Examples include:

  • out of date or missing policies to guide appropriate decisions
  • poor record keeping and document retention
  • incomplete or inaccurate centralised registers, or gaps in these registers.

Policies, procedures and internal controls should be properly designed, be appropriate for the current organisational structure and its business activities, and work effectively.

This chapter outlines our audit observations, conclusions and recommendations, arising from our review of agency controls to manage key financial systems.

Section highlights

Government agencies’ financial reporting is heavily reliant on information technology (IT). We continue to see a high number of deficiencies related to IT general controls, particularly those related to user access administration. These controls are key in adequately protecting IT systems from inappropriate access and misuse.

IT is also important to the delivery of agency services. These systems often provide the data to help monitor the efficiency and effectiveness of agency processes and services they deliver. Our financial audits do not review all agency IT systems. For example, IT systems used to support agency service delivery are generally outside the scope of our financial audit. However, agencies should also consider the relevance of our findings to these systems.

Agencies need to continue to focus on assessing the risks of inappropriate access and misuse and the implementation of controls to adequately protect their systems, focussing on the processes in place to grant, remove and monitor user access, particularly privileged user access.

 

This chapter outlines our audit observations, conclusions and recommendations, arising from our review of agency business continuity and disaster recovery planning arrangements.

Section highlights

We identified deficiencies in agency business continuity and disaster recovery planning arrangements and opportunities for agencies to enhance their business continuity management and disaster recovery planning arrangements. This will better prepare them to respond to a disruption to their critical functions, resulting from an emergency or other serious event. Twenty-three per cent of agencies had not conducted a business impact analysis (BIA) to identify critical business functions and determine business continuity priorities and 40 per cent of agencies had not conducted a business continuity scenario testing exercise in the period from 1 January 2019 to 31 December 2019. Scenario testing improves the effectiveness with which a live crisis is handled.

This section focusses on the preparedness of agency business continuity and disaster recovery planning arrangements prior to the onset of the COVID-19 pandemic. While agencies have responded to the recent emergencies, proactively addressing deficiencies will ensure agencies have adequate safeguards in their processes to again respond in the future, if required.

During 2020–21 we plan to conduct a performance audit on 'Business continuity and disaster recovery planning'. This audit will consider the effectiveness of agency business continuity planning arrangements to maintain business continuity through the recent emergencies and/or COVID-19 pandemic and return to a business-as-usual environment. We also plan to conduct a performance audit on whole-of-government 'Coordination of emergency responses'.

 

This chapter outlines our audit observations, conclusions and recommendations, arising from our review of procurement agency procurement policies and procurement activity.

Section highlights

We found agencies have procurement policies in place to manage procurement activity, but the content of these policies was not sufficiently detailed to ensure compliance with NSW Procurement Board Directions (the Directions). The Directions aim to ensure procurement activity achieves value for money and meets the principles of probity and fairness.

Agencies have generally implemented controls over their procurement process. In relation to emergency procurement activity, agencies reported conducting 32,239 emergency procurements with a total contract value of $316,908,485 up to 30 June 2020. Our review of emergency procurement activity conducted during 2019–20 identified areas where some agencies did not fully comply with the 'COVID-19 Emergency procurement procedure'.

We also found not all agencies are maintaining complete and accurate contract registers. This not only increases the risk of non-compliance with GIPA legislation, but also limits the effectiveness of procurement business units to monitor contract end dates, contract extensions and commence new procurement in a timely manner. We noted instances where agencies renewed or extended contracts without going through a competitive tender process during the year.

 

This chapter outlines our audit observations, conclusions and recommendations, arising from our review of agency compliance with financial and human resources delegations.

Section highlights
We found that agencies are not always regularly reviewing and updating their financial and human resources delegations when there are changes to legislation or other organisational changes within the agency or from machinery of government changes. For example, agencies did not understand or correctly apply the requirements of the GSF Act, resulting in non-compliance with the Act. We found that 18 per cent of agencies spent deemed appropriations without obtaining an authorised delegation from the relevant Minister(s), as required by sections 4.6(1) and 5.5(3) of the GSF Act.
In order for agencies to operate efficiently, make necessary expenditure and human resource decisions quickly and lawfully, particularly in emergency situations, it is important that delegations are kept up to date, provide clear authority to decision makers and are widely communicated.

Appendix one – List of 2020 recommendations 

Appendix two – Status of 2019 recommendations

Appendix three – Cluster agencies

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Government advertising 2018-19 and 2019-20

Government advertising 2018-19 and 2019-20

Whole of Government
Finance
Community Services
Compliance
Management and administration
Procurement

A report released today by the Auditor-General for New South Wales, Margaret Crawford found that select advertising campaigns conducted by Service NSW and the NSW Rural Fire Service met most requirements of the Government Advertising Act, regulations, Guidelines and other laws. However, the audit found that Service NSW inappropriately used its post campaign evaluation to measure sentiment towards and confidence in the NSW Government.  

While agency analysis shows that the ‘Cost of Living’ (phases 2 and 3)  and ‘How Fireproof is Your Plan?’ campaigns achieved most of their objectives, the campaign objectives and targets set by both agencies were not sufficient to measure all aspects of campaign effectiveness. 

The report makes two recommendations to the Department of Customer Service. The first is to review its guidance to ensure agencies are not using post campaign evaluations to measure sentiment towards the government. The second, to review its guidance and the new process of peer review to ensure they support agencies to comply with the Act, the regulations and the Guidelines. 

The Government Advertising Act 2011 requires the Auditor General to conduct an annual performance audit of one or more government agencies to see whether their advertising activities were carried out in an effective, economical and efficient manner and in compliance with the Government Advertising Act 2011.
 

Read full report (PDF)

The Government Advertising Act 2011 (the Act) requires the Auditor-General to conduct a performance audit on the activities of one or more government agencies in relation to government advertising campaigns in each financial year. The performance audit assesses whether a government agency or agencies have carried out activities in relation to government advertising in an effective, economical and efficient manner and in compliance with the Act, the regulations, other laws and the Government Advertising Guidelines (the Guidelines). This audit examined two campaigns run during the 2018–19 and 2019–20 financial years respectively:

  • the 'Cost of Living' campaign run by Service NSW (phases 2 and 3 delivered in 2018–19)
  • the 'How Fireproof Is Your Plan?' (Fireproof) campaign run by NSW Rural Fire Service (year two of a three-year campaign delivered in 2019–20).

Section 6 of the Act prohibits political advertising. Under this section, material that is part of a government advertising campaign must not contain the name, voice or image of a minister, member of parliament or a candidate nominated for election to parliament or the name, logo or any slogan of a political party. Further, a campaign must not be designed to influence (directly or indirectly) support for a political party.

Conclusion

Neither campaign breached the prohibition on political advertising contained in section 6 of the Act. While both campaigns met most requirements of the Act, the regulations, other laws and the Guidelines, we identified some instances of non-compliance. Service NSW inappropriately used its post campaign evaluation to measure sentiment towards and confidence in the NSW Government.

Service NSW used its post-campaign evaluation to measure sentiment towards and confidence in the NSW Government. While neither campaign breached the prohibition on political advertising contained in section 6 of the Act, measuring sentiment towards and confidence in the NSW Government is not an appropriate use of the post-campaign evaluation and creates a risk that the results may be used for party political purposes. This risk is heightened as both phases 2 and 3 of the Cost of Living campaign were run immediately before the NSW state election. We have made this finding previously in our report 'Government advertising 2017–18'.

The campaign objectives and targets set by both agencies were not sufficient to fully measure campaign effectiveness. Service NSW advertised seven rebates in phase 2 of the campaign but only set targets for the awareness and uptake of three of these rebates. NSW Rural Fire Service set objectives and targets to be achieved over the life of the three-year campaign but did not set targets to be achieved for each year of the campaign. While the Fireproof campaign is a three-year campaign, each year of the campaign is subject to a separate approval and peer review process.

Agency analysis shows that both campaigns achieved most of their objectives. There was some overlap in the timing of phases 2 and 3 of the Cost of Living campaign and both phases had similar high-level objectives to increase awareness of rebates, making it difficult to evaluate the effectiveness of each distinct campaign phase. NSW Rural Fire Service conducted a post-campaign evaluation for year two of the Fireproof campaign (2019–20) but although this showed positive results against the overall objectives of the three-year campaign, NSW Rural Fire Service did not set specific targets for year two of the campaign, making it difficult to evaluate effectiveness for that year.

Service NSW was not able to demonstrate that its campaign was economical as it directly negotiated with a single supplier for the creative materials for phase 2. This is contrary to the NSW Government's procurement rules which require agencies to obtain three quotes when using suppliers on a prequalification scheme. Service NSW did not comply with its own procurement policy, which restricts Service NSW employees from entering into discussions with a supplier until the appropriate delegate approves a direct procurement. NSW Rural Fire Service achieved cost efficiencies by re-using creative material developed in the first year of the campaign. NSW Rural Fire Service also received $4 million worth of free advertising time and space.

The cost benefit analyses prepared by both agencies did not fully meet the requirements in the Guidelines. Both agencies identified an alternative to advertising but did not assess the costs and benefits of that alternative. We have made this finding previously in our report 'Government advertising 2017–18' and in our report 'Government advertising 2015–16 and 2016–17'.

In 2018–19, Service NSW delivered phases 2 and 3 of the 'Cost of Living' campaign. The Cost of Living advertising campaign aimed to build awareness of the help available to ease the cost of living for people under financial pressure including awareness of specific rebates that can be claimed. As part of the Cost of Living program, Service NSW developed a webpage designed as a single portal to access more than 40 NSW Government savings, rebates and initiatives (which originated from over 12 different agencies). It also launched the Cost of Living service which includes face to face meetings and phone interviews to help people claim rebates from the NSW Government. Phase 2 of the campaign ran from September 2018 to August 2019. Phase 3 of the campaign ran from January 2019 to July 2019. The budgets for phases 2 and 3 were $4.127 million and $934,800 respectively. See Appendix two for more details on this campaign.

Service NSW complied with most requirements of the Act, the Regulations and the Guidelines. Campaign materials that we reviewed did not breach the prohibition on political advertising contained in section 6 of the Act. However, Service NSW used its post-campaign evaluation to measure sentiment towards, and confidence in, the NSW Government. This is not an appropriate use of the post-campaign evaluation and creates a risk that the results may be used for party political purposes. This risk is heightened as both phases 2 and 3 of the Cost of Living campaign were run immediately before the NSW state election.
The post-campaign evaluation shows that the campaign was effective in achieving most of its objectives. However, in phase 2, Service NSW did not set targets for all of the rebates it advertised. There was some overlap in the timing of phases 2 and 3 of the Cost of Living campaign and both phases had similar high-level objectives to increase awareness of rebates, making it difficult to evaluate the effectiveness of each distinct campaign phase.
Service NSW was not able to demonstrate that its campaign was economical as it directly negotiated with a single supplier for the creative materials in phase 2 (total cost $731,480). This is contrary to the NSW Government's procurement rules which require agencies to obtain three quotes when using suppliers on a prequalification scheme where the estimated cost is more than $150,000. Service NSW did not comply with its own procurement policy, which restricts Service NSW employees from entering into discussions with a supplier until the appropriate delegate approves a direct procurement.
The cost benefit analysis for phase 2 did not accurately assess the benefits of the campaign as Service NSW did not know which rebates would be included in the advertisements at the time the cost benefit analysis was developed. The cost benefit analysis for phase 2 did not assess the costs and benefits of alternatives to advertising.

Campaign materials we reviewed did not breach section 6 of the Act

The audit team reviewed campaign materials developed as part of the paid advertising campaign including radio transcripts, digital videos and display. The audit team did not review the use of social media outside paid social media content as section four of the Act defines government advertising as the dissemination of information which is funded by or on behalf of a government agency. See Appendix two for examples of campaign materials for this campaign.

Section 6 of the Act prohibits political advertising as part of a government advertising campaign. A government advertising campaign must not:

  • be designed to influence (directly or indirectly) support for a political party
  • contain the name, voice or image of a minister, a member of parliament or a candidate nominated for election to parliament
  • contain the name, logo, slogan or any other reference to a political party.

The audit found no breaches of section 6 of the Act in the campaign material we reviewed. 

Post-campaign evaluations measured sentiment towards and confidence in the NSW Government

The post-campaign evaluation for phases 2 and 3 measured levels of confidence with the statement ‘the NSW Government has your best interests at heart’, despite the fact this was not a stated objective of the campaign. This is not an appropriate use of the post-campaign evaluation, which should measure the success of the campaign against its stated objectives. The post-campaign evaluation for phase 3 found that exposure to the campaign improved sentiment towards the government amongst those who did not have confidence in the NSW Government.

Service NSW advised that it was important to measure the sentiment of the advertising including the wording 'best interests' as it did not want the whole of government brand to be detrimental to customer engagement with applying for the rebates.

Following phase 2, Service NSW conducted analysis of media sentiment using the key words 'cost of living' and the names of the Premier, Treasurer and Minister for Customer Service. The analysis presented the level of positive, negative and neutral media sentiment. The Government Advertising Guidelines 2012 list the purposes that government advertising may serve which do not include improving the perception of the government. The inclusion of this analysis in Service NSW's post-campaign evaluation creates a risk that the results may be used for party political purposes.

Section 10 of the Act restricts agencies from carrying out a campaign after 26 January in the calendar year before the Legislative Assembly is due to expire and before the election for the Legislative Assembly in that year. Service NSW authorised a media agency to book media in line with the media plans for the campaign. The media plans for the campaign show that Service NSW did not authorise or plan to run any advertisements between 27 January 2019 and 23 March 2019.

Service NSW did not set targets for all rebates advertised in phase 2

Service NSW did not set targets for four of the seven rebates that were advertised as part of phase 2 of the campaign. These rebates were the Family Energy Rebate, Appliance Replacement Offer, National Parks Concession Offer and the Pensioner Travel Voucher. As a result, it was unable to evaluate whether the advertisements for these rebates were effective. Service NSW advised that at the time the campaign went to peer review, when campaign objectives are set, it did not know which rebates would be included in the advertisements.

Service NSW stated in its submission to the Department of Premier and Cabinet that it may change the creative content for phase 2 as it announced new initiatives and rebates. The peer review process should have ensured that Service NSW set targets for any additional rebates or savings it intended to advertise before that advertising commenced to ensure a strategic approach to the campaigns that clearly demonstrated anticipated benefits were in place.

The post-campaign evaluation for phase 2 shows that the advertising campaign met most of its objectives

Service NSW set overall campaign objectives and specific targets for some rebates advertised as part of phase 2 of the campaign. The objectives, targets and results for phase 2 are shown in Exhibit 5. In phase 2, Service NSW established baseline data on levels of awareness of government rebates during the peer review process. The baseline level of awareness for government rebates was 44 per cent. The level of awareness for specific rebates was 46 per cent for the Compulsory Third Party (CTP) green slip refund, and 21 per cent for both Active Kids and Toll Relief.

Post-campaign evaluation reports for phase 2 show that the campaign met its objective to raise awareness of NSW Government rebates, achieving a 16 per cent increase in awareness from 44 per cent to 51 per cent. The campaign did not meet its target to increase awareness of the CTP green slip refund by ten per cent.

Service NSW did not report the results of the uptake of the CTP green slip refund, Active Kids and Toll Relief in its post campaign effectiveness report submitted to the Department of Premier and Cabinet. However, other post-campaign evaluation documentation, which Service NSW advise was submitted to the Department of Premier and Cabinet, show that these targets were met.

Service NSW did not report to the Department of Premier and Cabinet on whether it achieved the target of a ten per cent increase of average monthly visits to the Cost of Living webpage. Service NSW reported that it had achieved an average of 11,753 visitors to the webpage per day during the campaign. These average daily results indicate that the target was met.

Exhibit 5: Phase 2 - campaign objectives, targets and results
Campaign objectives and targets Does the post-campaign evaluation show that the target was met?
1. a) Increase awareness of rebates from the NSW Government by ten per cent.
Image
mauve circle with tick inside

    b) Increase average monthly visits to the Cost of Living webpage by ten per cent.

Image
mauve circle with tick inside and asterisk to the right

2. Increase awareness of rebates and savings by ten per cent for:

 
  • CTP green slip refund
Image
gold circle with white minus symbol inside
  • Active Kids
Image
mauve circle with tick inside
  • Toll Relief.
Image
mauve circle with tick inside
3. Increase awareness that NSW Government initiatives relating to the cost of living are available via Service NSW by ten per cent.
Image
mauve circle with tick inside
4. Increase the uptake of rebates and savings for the CTP green slip refund, Active Kids and Toll Relief by ten per cent.
Image
mauve circle with tick inside and asterisk to the right
Key
Image
mauve circle with tick inside
Yes
Image
gold circle with white minus symbol inside
Not Fully

*  Some issues with reporting on target.
Source: Service NSW. Audit Office analysis.

The post-campaign evaluation for phase 3 shows that the advertising campaign met most of its objectives

Service NSW set overall campaign objectives and specific targets for the two rebates advertised as part of phase 3 of the campaign. The objectives, targets and results for phase 3 are shown in Exhibit 6.

In phase 3, Service NSW established baseline data on levels of awareness during the peer review process. The baseline level of awareness for government rebates was 44 per cent. This is the same baseline that was used to measure performance for phase 2 of the campaign. Service NSW did not set baselines for awareness and uptake of Energy Switch and Creative Kids as these were new services.

Post-campaign evaluation reports for phase 3 show that the campaign met its objective to raise awareness of NSW Government rebates by ten per cent, achieving a 30 per cent increase in awareness from 44 per cent to 57 per cent. The overall increase in message take-out was met with 43 per cent agreeing with the message that the NSW Government is taking steps to ease the cost of living. The campaign achieved awareness and uptake targets for the specific rebates included in phase 3, except for awareness of Creative Kids which achieved 28 per cent awareness, falling short of the 30 per cent awareness target.

Exhibit 6: Phase 3 - campaign objectives, targets and results
Campaign objectives and targets Does the post-campaign evaluation show that the target was met?
1. Increase message takeout that ‘The NSW Government is taking steps to help ease the cost of living in NSW’ by ten per cent for those who can recall the campaign.
2. Increase awareness that the NSW Government has a range of rebates and savings by ten per cent.
3. Generate awareness with NSW residents aged 18+ of:
 
 
  • Energy Switch (15 per cent awareness)
  • Creative Kids (30 per cent awareness).
4. Create uptake of Energy Switch and Creative Kids (8,356 clicks on the Energy Switch website and 107,938 Creative Kids vouchers downloaded with 70 per cent conversion).
Key
Yes
Not Fully

Source: Service NSW. Audit Office analysis.

The timing of campaign phases meant that it was difficult for Service NSW to evaluate each distinct campaign phase and reduced opportunities to incorporate learnings from previous phases

Service NSW commenced planning for phase 2 of the campaign while phase 1 was still underway. This limited the opportunity for Service NSW to incorporate learnings from phase 1 into phase 2. There was some overlap in the timing of phase 2 and the start of phase 3 of the campaign, making it difficult to evaluate the effectiveness of each distinct campaign phase. Both phases 2 and 3 had the same high-level outcome objective to raise awareness of rebates by ten per cent. The baseline measures that were used to evaluate performance for phase 3 were the same as those used to evaluate phase 2. As a result, Service NSW was not able to separately evaluate these two phases of the campaign. This is important given the budgets for phases 2 and 3 were $4.127million and $934,800 respectively.

Service NSW allocated 7.5 per cent of its media budget to communications with culturally and linguistically diverse (CALD) and Aboriginal audiences

The NSW Government CALD and Aboriginal Advertising Policy requires that agencies spend at least 7.5 per cent of an advertising campaign media budget on direct communications with CALD and Aboriginal audiences. Service NSW authorised a media company to book media in line with the media plans for the campaign. The media plans for phases 2 and 3 of the campaign indicate that Service NSW met this requirement, with 7.5 per cent of the budget allocated to these audiences in phase 2 and 10.4 per cent in phase 3.

The post campaign evaluation for phases 1 and 2 of the Cost of Living campaign contained a recommendation to look at other opportunities to reach CALD audiences. Effective communication with CALD audiences was particularly important in phase 3 of the campaign, where they made up 30 per cent of the target audience for the Creative Kids advertisement. The post-campaign analysis for phase 3 showed that the campaign performed well with some, but not all CALD audiences. The post-campaign analysis also showed low awareness and uptake with Aboriginal audiences. Pre-campaign focus groups in phase 3 found Aboriginal audiences had a negative reaction to the campaign tag line ‘NSW Government is helping with the cost of living’ however this tagline was still used in some advertisements in phase 3.

The cost-benefit analysis (CBA) for phase 2 did not accurately assess the benefits of the campaign and did not assess the costs and benefits of alternatives to advertising

Under the Government Advertising Act 2011, agencies are required to prepare a CBA when the cost of the campaign is likely to exceed $1 million. The CBA conducted by Service NSW for phase 2 includes $8 million in benefits attributed to the advertisements for the Energy Switch tool and $6.9 million in benefits attributed to the advertisements for Creative Kids vouchers. These benefits should not have been included in the CBA for phase 2 as they were not included in this phase of the campaign. The CBA did not estimate the benefits of some other rebates and savings advertised in phase 2 of the campaign. This means that the CBA did not accurately assess the benefits of the campaign. Service NSW advised that at the time the CBA was developed it had not selected the rebates to be included in the campaign.

The Government Advertising Guidelines require agencies to consider options other than advertising to achieve the desired objective including a comparison of costs and benefits. The CBA developed as part of phase 2 identified using existing NSW Government communication channels as an alternative to advertising but did not assess the costs and benefits of this alternative.

This is a repeat finding from two previous government advertising audits. The report ‘Government Advertising: 2015–16 and 2016–17’ found that both agencies subject to the audit did not meet the requirements in the guidelines to consider alternatives to advertising. The report made a recommendation to the Department of Premier and Cabinet to work with Treasury to ensure the requirements of the guidelines are fully reflected in the 'Cost-Benefit Analysis Framework for Government Advertising and Information Campaigns'. The report ‘Government advertising 2017–18’ found that one agency subject to the audit did not identify to what extent the benefits could be achieved without advertising, nor did it consider alternatives to advertising which could achieve the same impact as the advertising campaign.

Service NSW negotiated with a single creative agency in phase 2, making it difficult to demonstrate value for money

Agencies are required to obtain three quotes when procuring a creative agency on the prequalification scheme if the estimated cost of the creative content is greater than $150,000. In phase 2 of the campaign, Service NSW extended the contract with the creative agency used for phase 1 of the campaign and did not obtain three quotes despite the cost of the creative content for phase 2 being $731,480. The requirement to obtain three quotes was met in phase 1 when initially selecting this creative agency.

Service NSWs procurement policy details that direct negotiation may be appropriate where there is a compelling reason to renew or rollover a contract beyond temporal or convenience reasons or in the cases of a genuine emergency. In its briefing to the Chief Executive, Service NSW stated that this contract extension was sought due to the time-sensitive nature of the project and that if work was delayed by a tender process, Service NSW may not be able to meet marketing milestones and this could result in limited customer uptake. This reason is not a genuine emergency and is not compelling as it does not explain what consequences would occur if it did not meet the marketing milestones or if there was limited customer uptake.

Service NSW's procurement policy also states that under no circumstances must Service NSW employees enter into discussions with a supplier until the delegate has formally made their decision to enter into direct negotiation. Service NSW briefed the Chief Executive of Service NSW in relation to extending the contract on 5 September 2018. The briefing states that the creative agency had already begun developing creative content for phase 2 and Service NSW had already received quotes from the creative provider for the proposed work prior to 5 September 2018. Procurement sign-offs were not completed until 7 September 2018. The engagement of the creative provider prior to appropriate approvals was contrary to Service NSWs procurement policy.

The economy of the campaign may have been limited by not meeting the procurement requirements in phase 2. It is possible that the creative provider may have offered a more competitive rate if it was aware that Service NSW was seeking quotes from other creative providers. Additionally, it is possible that another creative provider could have provided better value for money.

In phase 3 of the campaign, the estimated cost of the creative exceeded $150,000 however Service NSW chose to contract two different creative agencies, and the cost for each agency fell below the threshold to obtain three quotes. Agencies are permitted to obtain one quote when using a creative provider on the prequalification scheme if the cost is between $50,000 to $150,000. Service NSW advised that it contracted two creative providers as two different project teams were responsible for the rebates, each with separate marketing budgets.

Service NSW allowed sufficient time for cost-efficient media placement

During the peer review process, the Department of Premier and Cabinet advised agencies about the time they should allow to ensure cost-efficient media placement. For example, the Department of Premier and Cabinet advised that agencies book television advertising six to 12 weeks in advance and that agencies book radio advertising two to eight weeks in advance.

Service NSW allowed sufficient time between the completion of the peer review process and the commencement of the first advertising. Service NSW signed the agreement with the approved Media Agency Services provider with sufficient time to achieve cost-efficient media placement for all types of media used in this campaign.

The campaign may have been misleading for some people who were not eligible for rebates

Advertisements we reviewed focused on the amount of savings that could be obtained from rebates, for example ‘Save up to $285’, and ended with a statement ‘To save, visit service.nsw.gov.au. This directed viewers to the Cost of Living website which contains eligibility information. However, the advertisements in phases 2 and 3 we reviewed did not contain any details on the eligibility for these rebates and not all advertisements stated that eligibility criteria apply. Service NSW advised that the eligibility criteria for each rebate is extensive and that it was not possible to include this in the creative material.

Post-campaign evaluations in phase 3 recommended that advertisements for Creative Kids should indicate eligibility (e.g. age criteria) as statements on savings have the potential to be misleading when not all viewers will be eligible for rebates. Social media analysis conducted following phase 2 showed ineligibility or inability to claim rebates or refunds caused anger for some respondents.

Some advertisements in phase 2 stated ‘we've got something for everyone’. However, as rebates were subject to eligibility criteria, it is possible that some residents in NSW would not be eligible for any rebates as part of the Cost of Living initiative. As such, this statement has the potential to be misleading.

The campaign included statements that underestimated the savings that some customers could obtain

The Guidelines require accuracy in the presentation of all facts, statistics, comparisons and other arguments. The Guidelines also require that all claims of fact included in government advertising campaigns must be able to be substantiated.

In phase 2, the possible savings customers could obtain for two rebates or savings exceeded the amounts stated in the advertising campaign. Exhibit 7 shows some advertisements in phase 2 which stated, ‘My Green Slip Saving Save up to $60’. However, the State Insurance Regulatory Authority website shows that savings for some types of motor vehicles under the 2017 CTP scheme exceed $60. The State Insurance Regulatory Authority website states that the average saving under this scheme has been $129. Service NSW advised that these advertisements were designed for regional markets and that it used different advertisements for metropolitan areas which contained different amounts of savings.

Some advertisements in phase 2 stated, ‘My Toll Relief save up to $700’. The Service NSW website states that drivers can obtain free vehicle registration if they have spent $1,352 or more in tolls in the previous financial year. The cost of registration for some vehicles exceeds $700. This means the savings detailed in the advertisement were lower than what some customers could actually save.

NSW Rural Fire Service conducted the 'How FireProof Is Your Plan?' (Fireproof) campaign. The Fireproof campaign is a three-year campaign which ran in 2018–19 (year one), 2019–20 (year two) and is planned for 2020–21 (year three). This audit examined year two of the campaign (2019–20).

The Fireproof campaign is a public safety campaign encouraging people to plan and prepare for bush fires across the summer period. The campaign aims to improve the quality of bush fire planning and preparation in the community and decrease the impact of fires on the community when they occur.

The Fireproof campaign (year two) complied with most requirements of the Act, the Regulations and the Guidelines. The campaign materials that we reviewed did not breach the prohibition on political advertising contained in section 6 of the Act. NSW Rural Fire Service set objectives and targets to be achieved over the life of the three-year Fireproof campaign. Post-campaign evaluation shows that the Fireproof campaign was effective in achieving increases against its three-year objectives during year two. However, NSW Rural Fire Service did not set targets to be achieved for each year of the campaign, making it difficult to evaluate the effectiveness of year two of the campaign. NSW Rural Fire Service achieved cost efficiencies by re-using creative material developed in the first year of the campaign. NSW Rural Fire Service received $4 million worth of free advertising time and space. The cost benefit analysis for the Fireproof campaign did not assess the costs and benefits of alternatives to advertising.

Campaign materials we reviewed did not breach section 6 of the Act

The audit team reviewed campaign materials developed as part of the paid advertising campaign for example radio advertisements, television commercials and digital displays. The audit team did not review the use of social media outside paid social media content as section four of the Act defines government advertising as the dissemination of information which is funded by or on behalf of a government agency. Examples of campaign materials are shown in Appendix two.

Section 6 of the Act prohibits political advertising as part of a government advertising campaign. A government advertising campaign must not:

  • be designed to influence (directly or indirectly) support for a political party
  • contain the name, voice or image of a minister, a member of parliament or a candidate nominated for election to parliament
  • contain the name, logo, slogan or any other reference to a political party.

The audit found no breaches of section 6 of the Act in the campaign material we reviewed. 

NSW Rural Fire Service did not set targets for the second year of the campaign

The second year of the Fireproof campaign (2019–20) had the same objectives as the first year of the campaign (2018–19), however no specific targets were set for the second year. The advertising submission for the first year of the campaign (2018–19) details the targets for each objective as an increase of ten per cent against the baseline data to be achieved by March 2021, at the end of the three-year campaign.

The second year of the Fireproof campaign (2019–20) was one of the first campaigns approved under the new budget and peer review processes introduced by the Department of Customer Service in 2019–20. The new process for peer review introduced a new template for campaign submissions. The former template for campaign submissions contained more prompts for agencies to ensure the submission contained sufficient detail of campaign objectives, baseline measures, targets, dates for measurement and detail on how they would measure objectives. Despite this, the peer review process should have identified that NSW Rural Fire Service did not set targets for the second year of the campaign.

The 2016 Guidelines for Implementing NSW Government Evaluation Framework for Advertising and Communications requires campaign objectives to be SMART (specific, measurable, achievable, realistic and timed). NSW Rural Fire Service did not meet this requirement for year two of the Fireproof campaign.

Post-campaign evaluations showed increases against four out of five objectives, however there were no specific targets

NSW Rural Fire Service set three campaign objectives at the time it submitted the second year of the campaign (2019–20) to the Department of Customer Service for peer review. However, the post-campaign effectiveness report submitted to the Department of Customer Service measured campaign effectiveness against five campaign objectives. The objectives in the post-campaign effectiveness report were the same objectives set for the first year of the campaign, which is appropriate as this was a repeat campaign.

NSW Rural Fire Service achieved increases against four of their five objectives. However, as noted above there were no specific targets (such as percentage increases) against which performance of the 2019–20 campaign could be measured. Despite this, at the end of the second year, the Fireproof campaign had already achieved some of the targets that NSW Rural Fire Service had set for the end of the third year of the campaign. The post-campaign research showed that both audience recall and exposure to the campaign increased significantly from the prior year. The campaign objectives and results are shown in Exhibit 8.

For those people who already have a bush fire plan, the campaign aimed to increase the number of those plans which have included two or more elements from the Guide to Making a Bush Fire Survival Plan. Elements from the Guide to Making A Bush Fire Survival Plan include actions such as deciding what to take with you if you leave, ensuring you have the right equipment for defending your home and allocating responsibilities to members of a household. The post-campaign evaluation showed that the campaign did not achieve an increase against this objective for people who planned to stay and defend their property rather than leave.

Exhibit 8: Campaign objectives and results
Campaign objectives Does the post-campaign evaluation show increases against the objective?
1. Continue to increase the number of people that have discussed and/or written a plan with regards to what they will do in the event of a fire.
2. Of those who indicate they have a plan, increase the number of people who have included two or more elements from the Guide to Making a Bush Fire Survival Plan:  
  • for those who plan to leave
  • for those who plan to stay and defend.
3. Increase the frequency in completing preparation activities around a person’s property.
4. Increase the number of people who correctly assess it is their responsibility to complete preparation activities and enact their plan without direct intervention from emergency services.
5. Visits to MyFirePlan website.
Key
Yes
No

Source: NSW Rural Fire Service. Audit Office analysis.

NSW Rural Fire Service achieved cost efficiencies by reusing creative content developed in the first year of the campaign

Total creative and production costs incurred in year one of the campaign were $1.08 million. Rather than commissioning new creative materials, NSW Rural Fire Service re-used the same creative content in year two of the campaign. NSW Rural Fire Service incurred $100,000 in creative and production costs in year two of the campaign and achieved cost-efficiencies by reusing the same creative developed in the prior year.

NSW Rural Fire Service allowed sufficient time for cost-efficient media placement and received free media placements

The Department of Customer Service advises agencies to work with media contacts to book media in advance to ensure a cost-efficient placement. Prior to 2019–20, the Department of Premier and Cabinet provided suggested timeframes for agencies to book media as part of the peer review process. For example, it advised agencies to book television six to 12 weeks in advance and book radio advertising two to eight weeks in advance. NSW Rural Fire Service allowed sufficient time for a cost-efficient media placement.

NSW Rural Fire Service received $4 million of free advertising time and space donated by media companies due to the extent and impact of the 2019–20 fire season.

The cost benefit analysis (CBA) did not assess the costs and benefits of alternatives to advertising

Under the Government Advertising Act 2011, agencies are required to prepare a CBA when the cost of the campaign is likely to exceed $1 million. As part of the CBA, the Government Advertising Guidelines require agencies to consider options other than advertising to achieve the desired objective including a comparison of costs and benefits.

The CBA for the Fireproof campaign (year two) notes that the proposed campaign is one component of a broader community engagement strategy which has been developed over time and is based on research and evaluation. The CBA considers two options to achieve the objectives of the campaign. The first option is community engagement activities without an advertising campaign and the second option is community engagement activities alongside an advertising campaign. The CBA does not identify and assess the costs and benefits of both of the options in order to assess the most cost-efficient option.

This is a repeat finding from two previous government advertising audits. The report ‘Government Advertising: 2015–16 and 2016–17’ found that both agencies subject to the audit did not meet the requirements in the guidelines to consider alternatives to advertising. The report made a recommendation to the Department of Premier and Cabinet to work with Treasury to ensure the requirements of the guidelines are fully reflected in the 'Cost-Benefit Analysis Framework for Government Advertising and Information Campaigns'. The report ‘Government advertising 2017–18’ found that one agency subject to the audit did not identify to what extent the benefits could be achieved without advertising, nor did it consider alternatives to advertising which could achieve the same impact as the advertising campaign.

Appendix one – Responses from agencies

Appendix two – About the campaigns

Appendix three – About the audit

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #342 - released 19 November 2020

Published

Actions for CBD South East Sydney Light Rail: follow-up performance audit

CBD South East Sydney Light Rail: follow-up performance audit

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk
Service delivery

This is a follow-up to the Auditor-General's November 2016 report on the CBD South East Sydney Light Rail project. This follow-up report assessed whether Transport for NSW has updated and consolidated information about project costs and benefits.

The audit found that Transport for NSW has not consistently and accurately updated project costs, limiting the transparency of reporting to the public.

The Auditor-General reports that the total cost of the project will exceed $3.1 billion, which is above the revised cost of $2.9 billion published in November 2019. $153.84 million of additional costs are due to omitted costs for early enabling works, the small business assistance package and financing costs attributable to project delays.

The report makes four recommendations to Transport for NSW to publicly report on the final project cost, the updated expected project benefits, the benefits achieved in the first year of operations and the average weekly journey times.

Read full report (PDF)

The CBD and South East Light Rail is a 12 km light rail network for Sydney. It extends from Circular Quay along George Street to Central Station, through Surry Hills to Moore Park, then to Kensington and Kingsford via Anzac Parade and Randwick via Alison Road and High Street.

Transport for NSW (TfNSW) is responsible for planning, procuring and delivering the Central Business District and South East Light Rail (CSELR) project. In December 2014, TfNSW entered into a public private partnership with ALTRAC Light Rail as the operating company (OpCo) responsible for delivering, operating and maintaining the CSELR. OpCo engaged Alstom and Acciona, who together form its Design and Construct Contractor (D&C).

On 14 December 2019, passenger services started on the line between Circular Quay and Randwick. Passenger services on the line between Circular Quay and Kingsford commenced on 3 April 2020.

In November 2016, the Auditor-General published a performance audit report on the CSELR project. The audit found that TfNSW would deliver the CSELR at a higher cost with lower benefits than in the approved business case, and recommended that TfNSW update and consolidate information about project costs and benefits and ensure the information is readily accessible to the public.

In November 2018, the Public Accounts Committee (PAC) examined TfNSW's actions taken in response to our 2016 performance audit report on the CSELR project. The PAC recommended that the Auditor-General consider undertaking a follow-up audit on the CSELR project. The purpose of this follow-up performance audit is to assess whether TfNSW has effectively updated and consolidated information about project costs and benefits for the CSELR project.

Conclusion

Transport for NSW has not consistently and accurately updated CSLER project costs, limiting the transparency of reporting to the public. In line with the NSW Government Benefits Realisation Management Framework, TfNSW intends to measure benefits after the project is completed and has not updated the expected project benefits since April 2015.

Between February 2015 and December 2019, Transport for NSW (TfNSW) regularly updated capital expenditure costs for the CSELR in internal monthly financial performance and risk reports. These reports did not include all the costs incurred by TfNSW to manage and commission the CSELR project.

Omitted costs of $153.84 million for early enabling works, the small business assistance package and financing costs attributable to project delays will bring the current estimated total cost of the CSELR project to $3.147 billion.

From February 2015, TfNSW did not regularly provide the financial performance and risk reports to key CSELR project governance bodies. TfNSW publishes information on project costs and benefits on the Sydney Light Rail website. However, the information on project costs has not always been accurate or current.

TfNSW is working with OpCo partners to deliver the expected journey time benefits. A key benefit defined in the business plan was that bus services would be reduced owing to transfer of demand to the light rail - entailing a saving. However, TfNSW reports that the full expected benefit of changes to bus services will not be realised due to bus patronage increasing above forecasted levels.

Appendix one – Response from agency

Appendix two – Governance and reporting arrangements for the CSELR

Appendix three – 2018 CSELR governance changes

Appendix four – About the audit

Appendix five – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #335 - released 11 June 2020