Refine search Expand filter

Reports

Published

Actions for Waste levy and grants for waste infrastructure

Waste levy and grants for waste infrastructure

Planning
Environment
Management and administration
Regulation
Risk
Service delivery

The Auditor-General for New South Wales, Margaret Crawford, released a report today that examined the effectiveness of the waste levy and grants for waste infrastructure in minimising the amount of waste sent to landfill and increasing recycling rates.  

The audit found that the waste levy has a positive impact on diverting waste from landfill. However, while the levy rates increase each year in line with the consumer price index, the EPA has not conducted a review since 2009 to confirm whether they are set at the optimal level. The audit also found that there were no objective and transparent criteria for which local government areas should pay the levy, and the list of levied local government areas has not been reviewed since 2014. 

Grant funding programs for waste infrastructure administered by the EPA and the Environmental Trust have supported increases in recycling capacity. However, these grant programs are not guided by a clear strategy for investment in waste infrastructure. 

The Auditor-General made six recommendations aimed at ensuring the waste levy is as effective as possible at meeting its objectives and ensuring funding for waste infrastructure is contributing effectively to recycling and waste diversion targets.

 

Overall, waste generation in New South Wales (NSW) is increasing. This leads to an increasing need to manage waste in ways that reduce the environmental impact of waste and promote the efficient use of resources. In 2014, the NSW Government set targets relating to recycling rates and diversion of waste from landfill, to be achieved by 2021–22. The NSW Waste and Resource Recovery (WARR) Strategy 2014–21 identifies the waste levy, a strong compliance regime, and investment in recycling infrastructure as key tools for achieving these waste targets.

This audit assessed the effectiveness of the NSW Government in minimising waste sent to landfill and increasing recycling rates. The audit focused on the waste levy, which is paid by waste facility operators when waste is sent to landfill, and grant programs that fund infrastructure for waste reuse and recycling.

The waste levy is regulated by the Environment Protection Authority (EPA) and is generally paid when waste is disposed in landfill. The waste levy rates are set by the NSW Government and prescribed in the Protection of Environment Operations (Waste) Regulation 2014. As part of its broader role in reviewing the regulatory framework for managing waste and recycling, the EPA can provide advice to the government on the operation of the waste levy.

The purpose of the waste levy is to act as an incentive for waste generators to reduce, re-use or recycle waste by increasing the cost of sending waste to landfill. In 2019–20, around $750 million was collected through the waste levy in NSW. The government spends approximately one third of the revenue raised through the waste levy on waste and environmental programs.

One of the waste programs funded through the one third allocation of the waste levy is Waste Less, Recycle More (WLRM). This initiative funds smaller grant programs that focus on specific aspects of waste management. This audit focused on five grant programs that fund projects that provide new or enhanced waste infrastructure such as recycling facilities. Four of these programs were administered by the Environmental Trust and one by the EPA.

Conclusion

The waste levy has a positive impact on diverting waste from landfill. However, aspects of the EPA's administration of the waste levy could be improved, including the frequency of its modelling of the waste levy impact and coverage, and the timeliness of reporting. Grant funding programs have supported increases in recycling capacity but are not guided by a clear strategy for investment in waste infrastructure which would help effectively target them to where waste infrastructure is most needed. Data published by the EPA indicates that the NSW Government is on track to meet the recycling target for construction and demolition waste, but recycling targets for municipal solid waste and commercial and industrial waste are unlikely to be met.

Waste levy

The waste levy rate, including a schedule of annual increases to 2016, was set by the NSW Government in 2009. Since 2016, the waste levy rate has increased in line with the consumer price index (CPI). The EPA has not conducted recent modelling to test whether the waste levy is set at the optimal level to achieve its objectives. The waste levy operation was last reviewed in 2012, although some specific aspects of the waste levy have been reviewed more recently, including reviews of waste levy rates for two types of waste. The waste levy is applied at different rates across the state. Decisions about which local government areas (LGAs) are subject to the levy, and which rate each LGA pays, were made in 2009 and potential changes were considered but not implemented in 2014. Currently, there are no objective and transparent criteria for determining which LGAs pay the levy. The EPA collects waste data from waste operators. This data has improved since 2015, but published data is at least one year out of date which limits its usefulness to stakeholders when making decisions relating to waste management.

Grants for waste infrastructure

All state funding for new and enhanced waste infrastructure in NSW is administered through grants to councils and commercial waste operators. The government's Waste and Resource Recovery (WARR) Strategy 2014–21 includes few priorities for waste infrastructure and there is no other waste infrastructure strategy in place to guide investment. The absence of a formal strategy to guide infrastructure investment in NSW limits the ability of the State Government to develop a shared understanding between planners, councils and the waste industry about waste infrastructure requirements and priorities. The Department of Planning, Industry and Environment is currently developing a 20-year waste strategy and there is an opportunity for the government to take a more direct role in planning the type, location and timing of waste infrastructure needed in NSW.

The grants administration procedures used for the grant programs reviewed in this audit were well designed. However, we identified some gaps in risk management, record-keeping and consistency of information provided to applicants and assessment teams. In four of the five programs we examined, there was no direct alignment between program objectives and the NSW Government's overall waste targets.

Achievement of the 2014–21 state targets for waste and resource recovery (WARR targets) is reliant in part on the availability of infrastructure that supports waste diversion and recycling. The state WARR targets dependent on waste infrastructure are:

  • Increase recycling rates to 70 per cent for municipal solid waste and commercial and industrial waste, and 80 per cent for construction and demolition waste.
  • Increase waste diverted from landfill to 75 per cent.

A further target — manage problem waste better by establishing or upgrading 86 drop-off facilities or services for managing household problem wastes state-wide — is dependent on accessible community waste drop-off facilities across NSW.

Exhibit 7 identifies the five grant programs that provide funding for new or enhanced waste infrastructure to increase capacity for reuse or recycling of waste. All five of these programs were examined in the audit.
In addition to the grant programs shown in Exhibit 7, other programs provide funding for infrastructure, but at a smaller scale. Examples of these include:

  • Bin Trim which provides rebates to small businesses for small scale recycling equipment such as cardboard and soft plastic balers.
  • Litter grants which provide funding for litter bins.
  • Weighbridges grants for installation of a weighbridge at waste facilities.
  • Landfill consolidation and environmental improvement grants for rural councils to replace old landfills with transfer stations or to improve the infrastructure at landfill sites.

Appendix one – Responses from audited agencies

Appendix two – About the audit

Appendix three – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #343 - released 26 November 2020

Published

Actions for Education 2020

Education 2020

Education
Asset valuation
Compliance
Financial reporting
Fraud
Information technology
Internal controls and governance
Management and administration
Procurement

The Auditor-General for New South Wales, Margaret Crawford, released a report today titled Education 2020. This report focuses on key observations and findings from the most recent audits of agencies in the Education cluster.

Unqualified audit opinions were issued for all cluster agencies’ financial statements. However, internal control deficiencies were identified across the cluster agencies, including deficiencies in the management of purchasing cards and 15 internal control issues that were repeated from the previous year.

The 2019–20 natural disasters caused widespread damage in both Northern and Southern NSW. The COVID‑19 pandemic further challenged agencies, requiring social distancing and other infection control measures which disrupted the traditional means of teaching students. Agencies have adjusted their operations to respond to these emergency events.

The TAFE Commission’s revenues 2019–20 were impacted by the pandemic. Lower enrolments and an increase in fee-free short courses offered during the year contributed to the result.

Read the PDF report

This report analyses the results of our audits of financial statements of entities within the Education cluster for the year ended 30 June 2020. The table below summarises our key observations and recommendations.

1. Financial reporting 

Audit opinions Unqualified audit opinions were issued for all cluster agencies' 30 June 2020 financial statements audits.
New accounting standards

Agencies implemented three new accounting standards during the year.

Our financial statement audits of the Department of Education (the Department) and NSW Education Standards Authority (NESA) identified issues with the leasing information provided by Property NSW (PNSW). Despite the outsourcing arrangement, both the Department and NESA remain ultimately responsible for the completeness and accuracy of this information, which would have benefited from a more thorough quality assurance, validation and review process before they placed reliance upon it.

Recommendation:

We recommend the Department and NESA:

  • quality assure and validate the information provided by PNSW
  • ensure changes made by PNSW to lease data are supported and that assumptions and judgements applied are appropriate
  • document their review of the data supplied.
Changes were made to the financial reporting requirements this year to account for the impact of the pandemic

Emergency legislation was enacted during the year in response to the COVID-19 pandemic. The legislation revised the statutory reporting deadlines for agencies to submit their financial statements and allowed the Treasurer to continue authorising payments from the consolidated fund until the enactment of the 2020–21 budget.

All cluster agencies prepared their financial statements on a going concern basis and submitted their financial statements within the revised statutory deadlines.

The State provided $159.0 million in stimulus funding to support the operations of cluster agencies during emergency events. Nearly half of this funding was to support cleaning activities by the Department and the Technical and Further Education Commission (the TAFE Commission) during the COVID-19 pandemic.

Quality and timeliness of financial reporting

The number of monetary misstatements identified in agencies' financial statements decreased to 14 (23 in 2018–19).

While the number of corrections made to the financial statements after the submission date increased to eight (two in 2018–19), it is important to note these corrections provide parliament and other users of the financial statements increased confidence in the accuracy and presentation of agencies' performance and financial position.

Sustainability of cluster agencies The TAFE Commission's enrolments declined, and operating margins reduced, both being impacted by the COVID-19 pandemic.

2. Audit observations

Internal control deficiencies

We identified 33 internal control issues, including 15 findings that were repeated from previous years.

A high-risk issue was reported at the Department relating to the inadequate monitoring and follow up of privileged user activity in its enterprise resource planning system – SAP.

Repeat findings relate to ongoing deficiencies in information technology controls and management policies, practices and procedures.

Recommendation:

Cluster agencies should:

  • prioritise and action recommendations to address internal control deficiencies
  • review and confirm the appropriateness of existing privileged user access accounts
  • implement a rigorous monitoring regime to ensure that any improper use of privileged user accounts can be detected in a timely manner.
Agency responses to emergency events

The Department established a separate bushfire relief directorate and COVID-19 Taskforce to assist and support school communities in response to recent emergencies.

Other cluster agencies have established committees or response teams to oversee and address all aspects of the impact of COVID-19.

Schools review 2019 We continue to identify instances of non-compliance in relation to cash management and procurement at schools.
Use of purchasing cards at the Department of Education

Since 2015, the NSW Government has encouraged the use of purchasing cards by public sector agencies. Purchasing cards are efficient to transact low value, high volume procurement of goods and services, but the use must be effectively monitored.

Our review of the Department's purchasing cards identified weaknesses in its oversight and monitoring controls, including the issue and cancellation of purchasing cards

Opportunities exist for the Department to better monitor card use. Tools such as data analytics are an efficient and effective detective control to identify irregular activity or misuse by cardholders.

Recommendation:

The Department should:

  • improve the accuracy and completeness of exit procedures for terminated employees to ensure cards are returned and cancelled
  • perform periodic reviews to ensure active cards are held only by current employees
  • set transaction limits that do not exceed the limits of the user’s financial delegation
  • establish a data analytics regime to help analyse and identify high risk patterns and anomalies in their purchasing card usage, augmenting their existing monitoring and detective controls.

 

This report provides parliament and other users of the Education cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations
  • the impact of emergencies and the COVID-19 pandemic.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

The COVID-19 Legislation Amendment (Emergency Measures–Treasurer) Act 2020 amended legislation administered by the Treasurer to implement further emergency measures as a result of the COVID-19 pandemic. These amendments:

  • allowed the Treasurer to authorise payments from the consolidated fund until the enactment of the 2020–21 budget – supporting the going concern assessments of cluster agencies
  • revised budgetary, financial and annual reporting time frames – impacting the timeliness of financial reporting
  • exempted certain statutory bodies and departments from preparing financial statements.

This chapter outlines our audit observations related to the financial reporting of agencies in the Education cluster for 2020, including any financial implications from the recent emergency events.

Section highlights 

Unqualified audit opinions were issued on the financial statements of cluster agencies.

All cluster agencies met the revised statutory deadlines for completing early close procedures and submitting their financial statements.
 
Emergency legislation allowing the Treasurer to continue authorising payments from the consolidated fund under the existing Appropriations Act enabled cluster agencies to prepare financial statements on a going concern basis.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our:

  • observations and insights from our financial statement audits of agencies in the Education cluster. It also comments on our review of elements of the financial control framework applied by schools in NSW whose financial results form part of the Department of Education's (the Department) financial statements.
  • assessment of how well cluster agencies adapted their systems, policies and procedures, and governance arrangements in response to recent emergencies.

Section highlights

  • A high-risk issue regarding inadequate monitoring of privileged user access was identified at the Department.
  • We continue to observe issues by schools in relation to cash management and non-compliance with procurement guidelines and purchasing card use.
  • Opportunities exist for the Department and cluster agencies to enhance their monitoring and review of purchasing card activities. Tools such as data analytics procedures provide an efficient and effective detective control, particularly when used in conjunction with independent spot-checks.

Appendix one – List of 2020 recommendations

Appendix two – Status of 2019 and 2018 recommendations

Appendix three – Financial data

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Internal controls and governance 2020

Internal controls and governance 2020

Education
Environment
Community Services
Finance
Health
Industry
Justice
Premier and Cabinet
Transport
Treasury
Compliance
Cyber security
Information technology
Internal controls and governance
Management and administration
Procurement

The Auditor-General for New South Wales, Margaret Crawford today released her report on the findings and recommendations from the 2019–20 financial audits that relate to internal controls and governance at 40 of the largest agencies in the NSW public sector.

The bushfire and flood emergencies and the COVID‑19 pandemic continue to have a significant impact on the people and public sector of New South Wales. The scale of the government response to these events has been significant. The report focuses on the effectiveness of internal controls and governance processes, including relevant agencies’ response to the emergencies. In particular, the report focuses on:

  • financial and information technology controls
  • business continuity and disaster recovery planning arrangements
  • procurement, including emergency procurement
  • delegations that support timely and effective decision-making.

Due to the ongoing impact of COVID‑19 agencies have not yet returned to a business‑as‑usual environment. ‘Agencies will need to assess their response to the recent emergencies and update their business continuity, disaster recovery and other business resilience frameworks to reflect the lessons learnt from these events’ the Auditor-General said.

The report noted that special procurement provisions were put in place to allow agencies to better respond to the COVID-19 pandemic. The Auditor-General recommended agencies update their procurement policies to reflect the current requirements of the NSW Procurement Framework and the emergency procurement requirements.

Read the PDF report

This report analyses the internal controls and governance of 40 of the largest agencies in the NSW public sector for the year ended 30 June 2020. These 40 agencies constitute an estimated 85 per cent of total expenditure for all NSW public sector agencies.

1. Internal control trends
New, repeat and high risk findings

Internal control deficiencies increased by 13 per cent compared to last year. This is predominately due to a seven per cent increase in new internal control deficiencies and 24 per cent increase in repeat internal control deficiencies. There were ten high risk findings compared to four last year.

The recent emergencies have consumed agency time and resources and may have contributed to the increase in internal control deficiencies, particularly repeat deficiencies.

Agencies should:

  • prioritise addressing high-risk findings
  • address repeat internal control deficiencies by re-setting action plans and timeframes and monitoring the implementation status of recommendations.
Common findings

A number of findings remain common across multiple agencies over the last four years, including:

  • out of date or missing policies to guide appropriate decisions
  • poor record keeping and document retention
  • incomplete or inaccurate centralised registers or gaps in these registers.
2. Information technology controls
IT general controls

We found deficiencies in information security controls over key financial systems including:

  • user access administration deficiencies relating to inadequate oversight of the granting, review and removal of user access at 53 per cent of agencies
  • privileged users were not appropriately monitored at 43 per cent of agencies
  • deficient password controls that did not align to the agency's own password policies at 25 per cent of agencies.

The deficiencies above increase the risk of non-compliance with the NSW Cyber Security Policy, which requires agencies to have processes in place to manage user access, including privileged user access to sensitive information or systems and remove that access once it is not required or employment is terminated.

3. Business continuity and disaster recovery planning
Assessing risks to business continuity and Scenario testing

The response to the recent emergencies and the COVID-19 pandemic has encompassed a wide range of activities, including policy setting, on-going service delivery, safety and availability of staff, availability of IT and other systems and financial management. Agencies were required to activate their business continuity plans in response, and with the continued impact of COVID-19 have not yet returned to a business-as-usual environment.

Our audits focused on the preparedness of agency business continuity and disaster recovery planning arrangements prior to the onset of the COVID-19 pandemic.

We identified deficiencies in agency business continuity and disaster recovery planning arrangements. Twenty-three per cent of agencies had not conducted a business impact analysis (BIA) to identify critical business functions and determine business continuity priorities. Agencies can also improve the content of their BIA. For example, ten per cent of agencies' BIAs did not include recovery time objectives and six per cent of agencies did not identify key IT systems that support critical business functions. Scenario testing improves the effectiveness with which a live crisis is handled, but 40 per cent of agencies had not conducted a business continuity scenario testing exercise in the period from 1 January 2019 to 31 December 2019. There were also opportunities to improve the effectiveness of scenario testing exercises by:

  • involving key dependent or inter-dependent third parties who support or deliver critical business functions
  • testing one or more high impact scenarios identified in their business continuity plan
  • preparing a formalpost-exercise report documenting the outcome of their scenario testing.

Agencies have responded to the recent emergencies but addressing deficiencies will ensure agencies have adequate safeguards in their processes to again respond in the future, if required.

During 2020–21 we plan to conduct a performance audit on 'Business continuity and disaster recovery planning'. This audit will consider the effectiveness of agency business continuity planning arrangements to maintain business continuity through the recent emergencies and/or COVID-19 pandemic and return to a business-as-usual environment. We also plan to conduct a performance audit on whole-of-government 'Coordination of emergency responses'.

Responding to disruptions

We found agencies' governance functions could have been better informed about responses to disruptive incidents that had activated a business continuity or disaster recovery response between 1 January 2019 to 31 December 2019. For instance:

in 89 per cent of instances where a business continuity response was activated, a post-incident review had been performed. In 82 per cent of these instances, the outcomes were reported to a relevant governance or executive management committee

in 95 per cent of instances where a disaster recovery response was activated, a post incident review had been performed. In 86 per cent of these instances, the outcomes were reported to a relevant governance committee or executive management committee.

Examples of recorded incidents included extensive air quality issues and power outages due to bushfires, system and network outages, and infected and hijacked servers.

Agencies should assess their response to the recent emergencies and the COVID-19 pandemic and update business continuity, disaster recovery and other business resilience frameworks to incorporate lessons learned. Agencies should report to those charged with governance on the results and planned actions.

Management review and oversight Eighty-two per cent and 86 per cent of agencies report to their audit and risk committees (ARC) on their business continuity and disaster recovery planning arrangements, respectively. Only 18 per cent and five per cent of ARCs are briefed on the results of respective scenario testing. Briefing ARCs on the results of scenario testing exercises helps inform their decisions about whether sound and effective business continuity and disaster recovery arrangements have been established.
4. Procurement, including emergency procurement
Policy framework

Agency procurement policies did not capture the requirements of several key NSW Procurement Board Directions (the Directions), increasing the risk of non-compliance with the Directions. We noted: 

  • 67 per cent of agencies did specify that procurement above $650,000 must be open to market unless exempt or procured through an existing Whole of Government Scheme or contract
  • 36 per cent of agencies did specify that procurements above $500,000 payable in foreign currencies must be hedged
  • 69 per cent of agencies' policies did specify that the agency head or cluster CFO must authorise the engagement of consultants where the engagement of the supplier does not comply with the standard commercial framework.

Recommendation: Agencies should review their procurement policies and guidelines to ensure they capture the key requirements of the NSW Government Procurement Policy Framework, including NSW Procurement Board Directions.

Managing contracts

Eighty-eight per cent of agencies maintain a central contract register to record all details of contracts above $150,000, which is a requirement of GIPA legislation. Of the agencies that maintained registers, 13 per cent did not capture all contracts and eight per cent did not include all relevant contract details.

Sixteen per cent of agencies did not periodically review their contract register. Timely review increases compliance with GIPA legislation, and enhances the effectiveness with which procurement business units monitor contract end dates, contract extensions and commence new procurement.

Training and support

Ninety-three per cent of agencies provide training to staff involved in procurement processes, and a further 77 per cent of agencies provide this training on an on-going basis. Of the seven per cent of agencies that had not provided training to staff, we noted gaps in aspects of their procurement activity, including:

  • not conducting value for money assessments prior to renewing or extending the contract with their existing supplier
  • not obtaining approval from a delegated authority to commence the procurement process
  • procurement documentation not specifying certain key details such as the conditions for participation including any financial guarantees and dates for the delivery of goods or supply of services.

Training on procurement activities ensures there is effective management of procurement processes to support operational requirements, and compliance with procurement directions.

Procurement activities While agencies had implemented controls for tender activities above $650,000, 43 per cent of unaccredited agencies did not comply with the NSW Procurement Policy Framework because they had not had their procurement endorsed by an accredited agency within the cluster or by NSW Procurement. This endorsement aims to ensure the procurement is properly planned to deliver a value for money outcome before it commences.
Emergency procurement

As at 30 June 2020, agencies within the scope of this report reported conducting 32,239 emergency procurements with a total contract value of $316,908,485. Emergency procurement activities included the purchase of COVID-19 cleaning and hygiene supplies.

The government, through NSW Procurement released the 'COVID-19 Emergency procurement procedure', which relaxed procurement requirements to allow agencies to make COVID-19 emergency procurements. Our review against the emergency procurement measures found most agencies complied with requirements. For example:

  • 95 per cent of agencies documented an assessment of the need for the emergency procurement for the good and/or service
  • 86 per cent of agencies obtained authorisation of the emergency procurement by the agency head or the nominated employee under Public Works and Procurement Regulation 2019
  • 76 per cent of agencies reported the emergency procurement to the NSW Procurement Board.

Complying with the procedure helps to ensure government resources are being efficiently, effectively, economically and in accordance with the law.

Recommendation: Agency procurement frameworks should be reviewed and updated so they can respond effectively to emergency situations that may arise in the future. This includes:

  • updating procurement policies and guidelines to define an emergency situation, specify who can approve emergency procurement and capture other key requirements
  • using standard templates and documentation to prompt users to capture key requirements, such as needs analysis, supplier selection criteria, price assessment criteria, licence and insurance checks
  • having processes for reporting on emergency procurements to those charged with governance and NSW Procurement.
5. Delegations
Instruments of delegation

We found that agencies have established financial and human resources delegations, but some had not revisited their delegation manuals following the legislative and machinery of government changes. For those agencies impacted by machinery of government changes we noted:

  • 16 per cent of agencies had not updated their financial delegations to reflect the changes
  • 16 per cent of agencies did not update their human resources delegations to reflect the changes.

Delegations manuals are not always complete; 16 per cent of agencies had no delegation for writing off bad debts and 26 per cent of agencies had no delegation for writing off capital assets.

Recommendation: Agencies should ensure their financial and human resources delegation manuals contain regular set review dates and are updated to reflect the Government Sector Finance Act 2018, machinery of government changes and their current organisational structure and roles and responsibilities.

Compliance with delegations

Agencies did not understand or correctly apply the requirements of the Government Sector Finance Act 2018 (GSF Act), resulting in non-compliance with the Act. We found that 18 per cent of agencies spent deemed appropriations without obtaining an authorised delegation from the relevant Minister(s), as required by sections 4.6(1) and 5.5(3) of the GSF Act.

Further detail on this issue will be included in our Auditor-General's Reports to Parliament on Central Agencies, Education, Health and Stronger Communities, which will be tabled throughout December 2020.

Recommendation: Agencies should review financial and human resources delegations to ensure they capture all key functions of laws and regulations, and clearly specify the relevant power or function being conferred on the officer.

6. Status of 2019 recommendations
Progress implementing last year's recommendations

Recommendations were made last year to improve transparency over reporting on gifts and benefits and improve the visibility management and those charged with governance had over actions taken to address conflicts of interest that may arise. This year, we continue to note:

  • 38 per cent of agencies have not updated their gifts and benefits register to include all the key fields required under the minimum standards set by the Public Service Commission
  • 56 per cent of agencies have not provided training to staff and 63 per cent of agencies have not implemented an annual attestation process for senior management
  • 97 per cent of agencies have not published their gifts and benefits register on their website and 41 per cent of agencies are not reporting on trends in the gifts and benefits register to those charged with governance.

While we acknowledge the significance of the recent emergencies, which have consumed agency time and resources, we note limited progress has been made implementing these recommendations. Further detail on the status of implementing all recommendations is in Appendix 2.

Recommendation: Agencies should re-visit the recommendations made in last year's report on internal controls and governance and action these recommendations.

Internal controls are processes, policies and procedures that help agencies to:

  • operate effectively and efficiently
  • produce reliable financial reports
  • comply with laws and regulations
  • support ethical government.

This chapter outlines the overall trends for agency controls and governance issues, including the number of audit findings, the degree of risk those deficiencies pose to the agency, and a summary of the most common deficiencies we found across agencies. The rest of this report presents this year’s controls and governance findings in more detail.

Section highlights

We identified ten high risk findings, compared to four last year with two findings repeated from the previous year. There was an overall increase of 13 per cent in the number of internal control deficiencies compared to last year due to a seven per cent increase in new internal control deficiencies, and a 24 per cent increase in repeat internal control deficiencies. The recent emergencies have consumed agency time and resources and may have contributed to the increase in internal control deficiencies, particularly repeat deficiencies.

We identified a number of findings that remain common across multiple agencies over the last four years. Some of these findings related to areas that are fundamental to good internal control environments and effective organisational governance. Examples include:

  • out of date or missing policies to guide appropriate decisions
  • poor record keeping and document retention
  • incomplete or inaccurate centralised registers, or gaps in these registers.

Policies, procedures and internal controls should be properly designed, be appropriate for the current organisational structure and its business activities, and work effectively.

This chapter outlines our audit observations, conclusions and recommendations, arising from our review of agency controls to manage key financial systems.

Section highlights

Government agencies’ financial reporting is heavily reliant on information technology (IT). We continue to see a high number of deficiencies related to IT general controls, particularly those related to user access administration. These controls are key in adequately protecting IT systems from inappropriate access and misuse.

IT is also important to the delivery of agency services. These systems often provide the data to help monitor the efficiency and effectiveness of agency processes and services they deliver. Our financial audits do not review all agency IT systems. For example, IT systems used to support agency service delivery are generally outside the scope of our financial audit. However, agencies should also consider the relevance of our findings to these systems.

Agencies need to continue to focus on assessing the risks of inappropriate access and misuse and the implementation of controls to adequately protect their systems, focussing on the processes in place to grant, remove and monitor user access, particularly privileged user access.

 

This chapter outlines our audit observations, conclusions and recommendations, arising from our review of agency business continuity and disaster recovery planning arrangements.

Section highlights

We identified deficiencies in agency business continuity and disaster recovery planning arrangements and opportunities for agencies to enhance their business continuity management and disaster recovery planning arrangements. This will better prepare them to respond to a disruption to their critical functions, resulting from an emergency or other serious event. Twenty-three per cent of agencies had not conducted a business impact analysis (BIA) to identify critical business functions and determine business continuity priorities and 40 per cent of agencies had not conducted a business continuity scenario testing exercise in the period from 1 January 2019 to 31 December 2019. Scenario testing improves the effectiveness with which a live crisis is handled.

This section focusses on the preparedness of agency business continuity and disaster recovery planning arrangements prior to the onset of the COVID-19 pandemic. While agencies have responded to the recent emergencies, proactively addressing deficiencies will ensure agencies have adequate safeguards in their processes to again respond in the future, if required.

During 2020–21 we plan to conduct a performance audit on 'Business continuity and disaster recovery planning'. This audit will consider the effectiveness of agency business continuity planning arrangements to maintain business continuity through the recent emergencies and/or COVID-19 pandemic and return to a business-as-usual environment. We also plan to conduct a performance audit on whole-of-government 'Coordination of emergency responses'.

 

This chapter outlines our audit observations, conclusions and recommendations, arising from our review of procurement agency procurement policies and procurement activity.

Section highlights

We found agencies have procurement policies in place to manage procurement activity, but the content of these policies was not sufficiently detailed to ensure compliance with NSW Procurement Board Directions (the Directions). The Directions aim to ensure procurement activity achieves value for money and meets the principles of probity and fairness.

Agencies have generally implemented controls over their procurement process. In relation to emergency procurement activity, agencies reported conducting 32,239 emergency procurements with a total contract value of $316,908,485 up to 30 June 2020. Our review of emergency procurement activity conducted during 2019–20 identified areas where some agencies did not fully comply with the 'COVID-19 Emergency procurement procedure'.

We also found not all agencies are maintaining complete and accurate contract registers. This not only increases the risk of non-compliance with GIPA legislation, but also limits the effectiveness of procurement business units to monitor contract end dates, contract extensions and commence new procurement in a timely manner. We noted instances where agencies renewed or extended contracts without going through a competitive tender process during the year.

 

This chapter outlines our audit observations, conclusions and recommendations, arising from our review of agency compliance with financial and human resources delegations.

Section highlights
We found that agencies are not always regularly reviewing and updating their financial and human resources delegations when there are changes to legislation or other organisational changes within the agency or from machinery of government changes. For example, agencies did not understand or correctly apply the requirements of the GSF Act, resulting in non-compliance with the Act. We found that 18 per cent of agencies spent deemed appropriations without obtaining an authorised delegation from the relevant Minister(s), as required by sections 4.6(1) and 5.5(3) of the GSF Act.
In order for agencies to operate efficiently, make necessary expenditure and human resource decisions quickly and lawfully, particularly in emergency situations, it is important that delegations are kept up to date, provide clear authority to decision makers and are widely communicated.

Appendix one – List of 2020 recommendations 

Appendix two – Status of 2019 recommendations

Appendix three – Cluster agencies

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Support for regional town water infrastructure

Support for regional town water infrastructure

Industry
Environment
Local Government
Infrastructure
Management and administration
Regulation
Risk

The Auditor-General for New South Wales, Margaret Crawford, released a report today examining whether the Department of Planning, Industry and Environment has effectively supported the planning for, and funding of, town water infrastructure in regional NSW.

The audit found that the department has not effectively supported or overseen town water infrastructure planning since at least 2014. It does not have a clear regulatory approach and lacks internal procedures and data to guide its support for local water utilities that service around 1.85 million people in regional NSW.

The audit also found that the department has not had a strategy in place to target investments in town water infrastructure to the areas of greatest priority. A state-wide plan is now in development.

The Auditor-General made seven recommendations to the department, aimed at improving the administration and transparency of its oversight, support and funding for town water infrastructure, and at strengthening its sector engagement and interagency coordination on town water planning issues and investments.

According to the Auditor-General, ‘A continued focus on coordinating town water planning, investments and sector engagement is needed for the department to more effectively support, plan for and fund town water infrastructure, and to work with local water utilities to help avoid future shortages of safe water in regional towns and cities.’ 

This report is part of a multi-volume series on the theme of water. Refer to ‘Water conservation in Greater Sydney’ and ‘Water management and regulation – undertaking in 2020-21’.

Read full report (PDF)

Safe and reliable water and sewer services are essential for community health and wellbeing, environmental protection, and economic productivity. In 2019, during intense drought, around ten regional New South Wales (NSW) cities or towns were close to ‘zero’ water and others had six to 12 months of supply. In some towns, water quality was declared unsafe.

Ensuring the right water and sewer infrastructure in regional NSW to deliver these services (known as 'town water infrastructure') involves a strategic, integrated approach to water management. The NSW Government committed to ‘secure long-term potable water supplies for towns and cities’ in 2011. In 2019, it reiterated a commitment to invest in water security by funding town water infrastructure projects.

The New South Wales’ Water Management Act 2000 (WM Act) aims to promote the sustainable, integrated and best practice management of the State’s water resources, and establishes the priority of town water for meeting critical human needs.

The Department of Planning, Industry and Environment (the department) is the lead agency for water resource policy, regulation and planning in NSW. It is also responsible for ensuring water management is consistent with the shared commitments of the Australian, State and Territory Governments under the National Water Initiative. This includes the provision of healthy, safe and reliable water supplies, and reporting on the performance of water utilities.

Ninety-two Local Water Utilities (LWUs) plan for, price and deliver town water services in regional NSW. Eighty-nine are operated by local councils under the New South Wales’ Local Government Act 1993, and other LWUs exercise their functions under the WM Act. The Minister for Water, Property and Housing is the responsible minister for water supply functions under both acts.

The department is the primary regulator of LWUs. NSW Health, the NSW Environment Protection Authority (EPA) and the Natural Access Resource Regulator (NRAR) also regulate aspects of LWUs' operations. The department’s legislative powers with respect to LWUs cover approving infrastructure developments and intervening where there are town water risks, or in emergencies. In this context, the department administers the Best Practice Management of Water Supply and Sewerage Guidelines (BPM Guidelines) to support its regulation and to assist LWUs to strategically plan and price their services, including their planning for town water infrastructure.

Under the BPM Guidelines, the department supports LWU’s town water infrastructure planning with the Integrated Water Cycle Management (IWCM) Checklist. The Checklist outlines steps for LWUs to prepare an IWCM strategy: a long-term planning document that sets out town water priorities, including infrastructure and non-infrastructure investments, water conservation and drought measures. The department's objective is to review and approve (i.e. give ‘concurrence to’) an IWCM strategy before the LWU implements it. In turn, these documents should provide the department with evidence of town water risks, issues and infrastructure priorities.

The department also assesses and co-funds LWU's town water infrastructure projects. In 2017, the department launched the $1 billion Safe and Secure Water Program to ensure town water infrastructure in regional NSW is secure and meets current health and environmental standards. The program was initially established under the Restart NSW Fund.

This audit examined whether the department has effectively supported the planning for and funding of town water infrastructure in regional NSW. It focused on the department’s activities since 2014. This audit follows a previous Audit Office of NSW report which found that the department had helped to promote better management practices in the LWU sector, up to 2012–13.

Conclusion

The Department of Planning, Industry and Environment has not effectively supported or overseen town water infrastructure planning in regional NSW since at least 2014. It has also lacked a strategic, evidence-based approach to target investments in town water infrastructure.

A continued focus on coordinating town water planning, investments and sector engagement is needed for the department to more effectively support, plan for and fund town water infrastructure, and work with Local Water Utilities to help avoid future shortages of safe water in regional towns and cities.

The department has had limited impact on facilitating Local Water Utilities’ (LWU) strategic town water planning. Its lack of internal procedures, records and data mean that the department cannot demonstrate it has effectively engaged, guided or supported the LWU sector in Integrated Water Cycle Management (IWCM) planning over the past six years. Today, less than ten per cent of the 92 LWUs have an IWCM strategy approved by the department.

The department did not design or implement a strategic approach for targeting town water infrastructure investment through its $1 billion Safe and Secure Water Program (SSWP). Most projects in the program were reviewed by a technical panel but there was limited evidence available about regional and local priorities to inform strategic project assessments. About a third of funded SSWP projects were recommended via various alternative processes that were not transparent. The department also lacks systems for integrated project monitoring and program evaluation to determine the contribution of its investments to improved town water outcomes for communities. The department has recently developed a risk-based framework to inform future town water infrastructure funding priorities.

The department does not have strategic water plans in place at state and regional levels: a key objective of these is to improve town water for regional communities. The department started a program of regional water planning in 2018, following the NSW Government’s commitment to this in 2014. It also started developing a state water strategy in 2020, as part of an integrated water planning framework to align local, regional and state priorities. One of 12 regional water strategies has been completed and the remaining strategies are being developed to an accelerated timeframe: this has limited the department’s engagement with some LWUs on town water risks and priorities.

Regional New South Wales (NSW) is home to about a third of the state's population. Infrastructure that provides safe and reliable water and sewer services (also known simply as 'town water infrastructure') is essential for community health and wellbeing, environmental protection, and economic productivity. Planning for and meeting these infrastructure needs, as well as identifying when non-infrastructure options may be a better solution, involves a strategic and integrated approach to water resource management in regional NSW.

We examined whether the department has effectively supported planning for town water infrastructure since 2014. This assessment was made in the context of its current approach to LWU sector regulation. The findings below focus on whether the department has an effective framework including governance arrangements for town water issues to inform state-wide strategic water planning, and whether (at the local level) the department has effectively overseen and facilitated town water infrastructure planning through its Integrated Water Cycle Management (IWCM) planning guidance to LWUs.

We examined whether the department has effectively targeted town water infrastructure funding to policy objectives, with a focus on the design and implementation of the Safe and Secure Water Program (SSWP) since its commencement in 2017. The program’s aim was to fund town water infrastructure projects that would deliver health, social and environmental benefits, and support economic growth and productivity. We also assessed the department’s capacity to demonstrate the outcomes of the SSWP funding and the contributions of its town water infrastructure investments more broadly. Finally, we identified risks to the effectiveness of the department’s work underway since 2018–19, which is intended to enhance its strategic water planning and approach to prioritising investments in reducing town water risks.

Appendix one – Response from agency

Appendix two – Key terms

Appendix three – About the audit

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #341 - released 24 September 2020

Published

Actions for Water conservation in Greater Sydney

Water conservation in Greater Sydney

Environment
Industry
Infrastructure
Internal controls and governance
Management and administration
Regulation
Risk

This report examines whether the Department of Planning, Industry and Environment, and Sydney Water have effectively progressed water conservation initiatives in Greater Sydney.

The report found that the department and Sydney Water have not effectively investigated, implemented or supported water conservation initiatives in Greater Sydney. The agencies have not met key requirements of the current Metropolitan Water Plan and Sydney Water has not met all its operating licence requirements for water conservation. There has been little policy or regulatory reform, little focus on identifying new options and investments, and limited planning and implementation of water conservation initiatives.

As a result, Greater Sydney's water supply may be less resilient to population growth and climate variability, including drought.

The Metropolitan Water Plan states that water conservation, including recycling water, makes the drinking water supply go further. The plan also states that increasing water conservation efforts may be cheaper than building new large-scale supply options and can delay the timing of investment in new supply infrastructure.

The Auditor-General recommends the department develop a clear policy and regulatory position on water conservation options, improve governance and funding for water conservation, and work with Sydney Water to assess the viability of water conservation initiatives. The report also recommends improvements to Sydney Water’s planning for and reporting on water conservation, including the transparency of this information.

This report is part of a multi-volume series on the theme of water. Refer to ‘Support for regional town water infrastructure’ and ‘Water management and regulation – undertaking in 2020-21’.

Read full report (PDF)

The current, 2017 Metropolitan Water Plan states that water conservation, including recycling water, makes the drinking water supply go further. The plan also states that increasing water conservation efforts may be cheaper than building new large-scale supply options and can delay the timing of investment in new supply infrastructure.

Water conservation refers to water recycling, leakage management and programs to enhance water efficiency. Water recycling refers to both harvesting stormwater for beneficial use and reusing wastewater.

This audit examined whether water conservation initiatives for the Greater Sydney Metropolitan area are effectively investigated, implemented and supported. We audited the Department of Planning, Industry and Environment (the Department) and the Sydney Water Corporation (Sydney Water), with a focus on activities since 2016.

The Department is responsible for the integrated and sustainable management of the state’s water resources under the Water Management Act 2000, which includes encouraging ‘best practice in the management and use of water’ as an objective. The Department is also responsible for strategic water policy and planning for Greater Sydney, including implementing the Metropolitan Water Plan.

Sydney Water is a state-owned corporation and the supplier of water, wastewater, recycled water and some stormwater services to more than five million people in Greater Sydney. It is regulated by an operating licence that is issued by the Governor on the recommendation of the Independent Pricing and Regulatory Tribunal (IPART). The Tribunal determines Sydney Water’s maximum prices, reviews its operating licence and monitors compliance. Sydney Water's operating licence and reporting manual set out requirements for its planning, implementing and reporting of water conservation.

From 2007 to 2012, the Climate Change Fund was a source of funds for water conservation activities to be undertaken by the Department and Sydney Water. The Climate Change Fund was established under the Energy and Utilities Administration Act 1987. Four of its six objectives relate to water savings. Water distributors such as Sydney Water can be issued with orders to contribute funds for water-related programs. The Fund is administered by the Department.

In 2016, Sydney Water developed a method for determining whether and how much to invest in water conservation. Known as the ‘Economic Level of Water Conservation’ (ELWC), the method identifies whether it costs less to implement a water conservation initiative than the value of the water saved, in which case the initiative should be implemented.

Conclusion

The Department and Sydney Water have not effectively investigated, implemented or supported water conservation initiatives in Greater Sydney.

The agencies have not met key requirements of the Metropolitan Water Plan and Sydney Water has not met all its operating licence requirements for water conservation. There has been little policy or regulatory reform, little focus on identifying new options and investments, and limited planning and implementation of water conservation initiatives.

As a result, Greater Sydney's water supply may be less resilient to population growth and climate variability, including drought.

The Department has not undertaken an annual assessment of Sydney Water’s level of investment in water conservation against water security risks and the capacity to respond when drought conditions return, as required by the Metropolitan Water Plan. It did not complete identified research and planning activities to support the plan, such as developing and using a framework for assessing the potential for water conservation initiatives for Greater Sydney, and developing a long-term strategy for water conservation and water recycling. It also did not finalise a monitoring, evaluation, reporting and improvement strategy to support the plan.

Sydney Water has been ineffective in driving water conservation initiatives, delivering detailed planning and resourcing for ongoing initiatives, and in increasing its investment in water conservation during drought. These were requirements of the Metropolitan Water Plan. Sydney Water's reporting on water conservation has not met all its operating licence requirements and lacked transparency with limited information on key aspects such as planning for leakage management, how the viability of potential initiatives were assessed, and how adopted initiatives are tracking.

The Department and Sydney Water did not put in place sufficient governance arrangements, including clarifying and agreeing responsibilities for key water conservation planning, delivery and reporting activities. There has also been limited collaboration, capacity building and community engagement to support water conservation, particularly outside times of drought.

Appendix one – Responses from agencies

Appendix two – About the audit

Appendix three – Glossary

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #336 - released 23 June 2020

Published

Actions for Freedom of Information

Freedom of Information

Transport
Premier and Cabinet
Education
Management and administration
Regulation
Service delivery

Freedom of Information (FOI) Coordinators and their staff were supportive of the legislation. However, the agencies examined can do considerably more to fully achieve the intentions of the Act. On the positive side, all three agencies had processes in place to handle requests and had made a number of changes to improve the effectiveness of the FOI process. Fees and charges had also been kept to a minimum. No processing fees were requested in the majority of cases, and if charged, were not unreasonable.

 

Parliamentary reference - Report number #114 - released 28 August 2003

Published

Actions for Northside Storage Tunnel Project

Northside Storage Tunnel Project

Planning
Environment
Infrastructure
Internal controls and governance
Procurement
Project management
Service delivery

The Northside Storage Tunnel was the first major public sector construction project using an alliance approach. In our opinion, the outcome of the project suggests that an alliance approach, when applied to a suitable project and managed appropriately, can support positive project outcomes. And in many respects the Alliance worked well. There are, however, a number of issues that we believe need to be addressed for future alliances.

 

Parliamentary reference - Report number #113 - released 24 July 2003

Published

Actions for Protecting Our Rivers

Protecting Our Rivers

Environment
Internal controls and governance
Regulation
Shared services and collaboration

The Audit Office is of the opinion that responsibility for protecting the quality of river water is not clearly delineated. The current arrangements lack the structure to ensure success. There is no lead entity to co-ordinate efforts to protect river water. New South Wales has no overarching water quality or river health strategy and no water quality management plans to ensure clear outcomes and responsibilities for protecting river water quality and integrated decision-making to protect areas of greatest risk to water quality.

 

Parliamentary reference - Report number #108 - released 7 May 2003

Published

Actions for Environmental impact assessment of major projects in NSW

Environmental impact assessment of major projects in NSW

Environment
Management and administration
Regulation
Service delivery

The Audit Office is of the opinion that the basis for environmental impact assessment of major projects in NSW is sound. The key concept of 'environmental significance' is well defined. The system is closely specified. The Department of Urban Affairs and Planning (DUAP) leads a whole-of-government approach to environmental impact assessment and its assessments are comprehensive. However, the Audit Office considers that there are opportunities for improvement by more actively managing the participants and the performance of the environmental impact assessment system. DUAP needs to strengthen its internal documentation and must ensure the public have greater involvement.

 

Parliamentary reference - Report number #92 - released 28 November 2001

Published

Actions for Controlling and reducing pollution from industry

Controlling and reducing pollution from industry

Planning
Environment
Compliance
Management and administration
Regulation

The regulatory framework introduced under the Protection of the Environment Operations Act 1997, along with other initiatives progressively being implemented by the Environment Protection Authority (EPA), should enhance the overall effectiveness of environment protection in NSW. The Audit Office is of the opinion that the framework is consistent with best practice and once fully implemented, should contribute to the achievement of further improvements in the environmental performance of industry.

However while the legislative framework supports best practice in regulation and enforcement, there are a number of issues which limit the effectiveness of the reforms. Some of the problems, such as the quality of licences and the effectiveness of compliance activities, have been identified by the EPA and may be addressed through recent initiatives.

 

Parliamentary reference - Report number #82 - released 18 April 2001