Actions for Supply of secondary teachers in STEM-related disciplines

Supply of secondary teachers in STEM-related disciplines

Education
Management and administration
Service delivery
Workforce and capability

The NSW Department of Education’s plans and strategies to respond to the demand for secondary teachers in STEM-related disciplines are limited by incomplete data and underperforming scholarship and sponsorship program. The Department does not collect sufficient information to monitor what disciplines teachers actually teach nor does it predict supply and demand for teachers by discipline and location. This restricts the Department’s ability to track and forecast the supply and demand for secondary teachers in STEM-related disciplines.

In recent years, Australian and international education policy has focused on improving outcomes in Science, Technology, Engineering and Mathematics (STEM) subjects. However, research has identified a shortage of qualified secondary teachers in STEM-related disciplines 1. This is projected to worsen due to a combination of student population increases, an ageing workforce, and fewer people going into teaching. Shortfalls are likely to be more acute in rural and remote areas, and areas of low socio-economic status.

The Department of Education (the Department) has a variety of strategies to encourage teachers to practise in locations or disciplines of need. These include scholarships for tertiary students going into teaching, sponsorships for teachers seeking approval to teach additional disciplines, and incentives to attract teachers to rural and remote locations. 

This audit assessed the effectiveness of the Department's workforce plans and strategies in responding to the demand for secondary teachers in STEM-related disciplines. We assessed:

  • how well the Department tracks the supply and demand for secondary teachers in STEM-related disciplines across NSW
  • whether the Department has effective strategies to attract and retain secondary teachers in STEM-related disciplines.
Conclusion
There are two key shortcomings that fundamentally limit the effectiveness of the Department's plans and strategies to respond to the demand for secondary teachers in STEM-related disciplines. First, the Department is not accurately tracking the supply and demand for secondary teachers by discipline due to incomplete data. Second, not all scholarship and sponsorship places are allocated and many scholars withdraw from the programs before completion. The Department has recognised and started to address these problems with a new workforce model, revised incentives and scholarship programs. 

The Department’s current workforce planning model does not provide the information needed to target workforce plans and strategies to areas of need. This is because it does not predict supply and demand for teachers by discipline and location. An internal review in 2017 acknowledged the limitations of this model. In response the Department developed a new model, which it is currently enhancing, to predict supply and demand for teachers by discipline and location. For this to be successful, the Department needs to monitor the level of out-of-field teaching and improve data on the willingness of teachers to work in particular locations. 

The Department does not allocate all available scholarship and sponsorship places and around 30 per cent of recipients do not complete the term of their agreement. An internal review in 2017 highlighted that some programs were not targeting workforce need and that there were no key performance indicators to determine the overall effectiveness of these programs. However, scholarship programs and incentives are promoted well through social media and face-to-face events at Universities. Further, the Department has used findings from internal reviews of incentives and scholarships in 2016 and 2017 to inform recent changes to programs. 

The Department has little oversight of access to practicum placements for pre-service teachers in areas of need. Professional experience agreements were established with each University in 2015 to improve the placement process for disciplines of need. Initial teacher education students must complete several ‘practicum placements’ before they can be qualified to teach in a school. Several universities we consulted reported difficulties finding practicum placements for pre-service teachers specialising in STEM-related disciplines. The Department is now revising the agreements to improve the quality of data it collects on the number, location and subject area of practicum placements. 

1 Australian Council for Educational Research 2015, The teacher workforce in Australia - supply, demand and data issues.

 

The Department is not accurately tracking the supply and demand for secondary teachers by discipline due to incomplete data. 

The Department’s current workforce planning model does not accurately predict supply and demand for teachers by discipline and location. An internal review in 2017 acknowledged the limitations of this model. In response the Department developed a new model which it is currently enhancing to address the findings of the review. For this model to be successful, the Department needs to monitor the level of out-of-field teaching and improve data on the willingness of teachers to work in particular locations. Further work also needs to be undertaken to refine the assumptions that underpin the Department’s workforce planning models as it starts to predict the need for teachers by discipline.

The Department has not publicly reported on the supply and demand for teachers by discipline since 2015. While it does report annually on its current workforce profile, this information is not detailed enough to inform future strategies or programs. More detailed public reporting may help the Department to influence the future supply of teachers by communicating its projected areas of need. Planned improvements to the Department's workforce planning model, as relayed to us, will add to the data available on areas of need. Once available, this should be reported publicly. 

Recommendations
By December 2019, the Department of Education should:

  1. Improve its workforce planning model to better understand and communicate supply and demand for teachers by: 
    • determining the extent, and analysing the impact, of out-of-field teaching by permanent and temporary teachers in each school
    • sourcing additional data to more accurately reflect teacher location preferences
    • projecting supply and demand by subject level and geographic area
    • regularly reporting on the supply and demand for secondary teachers in each discipline to communicate future areas of need to future teacher education students.

The Department's current scholarship and sponsorship programs are not allocating all available places and many scholars withdraw from the programs before completion. An internal review in 2017 raised several issues with the effectiveness of programs and the Department has started to revise its scholarship, sponsorship and incentive programs. 

An internal review in 2017 highlighted that scholarship and sponsorship programs were not targeting workforce need, and that there were no key performance indicators to determine the overall effectiveness of these strategies. In addition, the review found that only 79 per cent of available scholarship placements are allocated each year, and 31 per cent of scholarship recipients withdraw prior to completing their required service period. The Department recently announced changes to its scholarship programs from 2019 onwards.

The Department has incentives to encourage teachers to work in rural and remote areas, including teachers in STEM-related disciplines. Incentives include access to priority transfers, rental subsidies and other allowances. Research conducted in 2016 examined the influence of incentives in encouraging teachers to work in rural and remote areas. The Department used findings of this research when updating its set of rural and remote incentives in 2017.

The Department promotes its scholarship and sponsorship programs through the teach.NSW website. It uses social media to direct applicants to this website. It also promotes its programs through careers fairs, University open days, and professional events. Past applicants have reported that the website clearly communicates eligibility criteria and the terms of agreement for all scholarship programs. 

The Department could strengthen its relationship with universities to attract teachers to areas of need by collecting and analysing data on practicum placements, facilitating placements for scholarship recipients, and communicating predicted teacher needs by discipline. 

Recommendations
By December 2019, the Department of Education should:

2. Implement changes to address the findings of the 'Teacher Scholarship Realignment' report, including by:

  • testing a range of program designs with target candidates to determine the best options to attract more suitable applicants
  • establishing key performance indicators, and setting targets, to better monitor the effectiveness of the programs
  • reducing the number of scholars appointed to over-establishment positions
  • increasing the proportion of scholars appointed to priority locations 
  • further analysing scholarship recipients career paths to inform future improvements to the scholarship programs.

3. Review its role in the practicum placement process of pre-service teachers by:

  • analysing how many students each school accommodates per year, to ensure there are appropriate placements available for students in high needs disciplines
  • working with universities to facilitate practicum placements for scholarship recipients
  • establishing mechanisms for ongoing monitoring of its partnerships with universities to ensure they are meeting their aims.

Appendix one - Response from agency

Appendix two - About the audit

Appendix three - Performance auditing

 

Parliamentary Reference - Report number #313 - released 29 January 2019.

Published

Actions for Newcastle Urban Transformation and Transport Program

Newcastle Urban Transformation and Transport Program

Transport
Planning
Compliance
Infrastructure
Management and administration
Procurement
Project management

The urban renewal projects on former railway land in the Newcastle city centre are well targeted to support the objectives of the Newcastle Urban Transformation and Transport Program (the Program), according to a report released today by the Auditor-General for New South Wales, Margaret Crawford. The planned uses of the former railway land achieve a balance between the economic and social objectives of the Program at a reasonable cost to the government. However, the evidence that the cost of the light rail will be justified by its contribution to the Program is not convincing.

The Newcastle Urban Transformation and Transport Program (the Program) is an urban renewal and transport program in the Newcastle city centre. The Hunter and Central Coast Development Corporation (HCCDC) has led the Program since 2017. UrbanGrowth NSW led the Program from 2014 until 2017. Transport for NSW has been responsible for delivering the transport parts of the Program since the Program commenced. All references to HCCDC in this report relate to both HCCDC and its predecessor, the Hunter Development Corporation. All references to UrbanGrowth NSW in this report relate only to its Newcastle office from 2014 to 2017.

This audit had two objectives:

  1. To assess the economy of the approach chosen to achieve the objectives of the Program.
  2. To assess the effectiveness of the consultation and oversight of the Program.

We addressed the audit objectives by answering the following questions:

a) Was the decision to build light rail an economical option for achieving Program objectives?
b) Has the best value been obtained for the use of the former railway land?
c) Was good practice used in consultation on key Program decisions?
d) Did governance arrangements support delivery of the program?

Conclusion
1. The urban renewal projects on the former railway land are well targeted to support the objectives of the Program. However, there is insufficient evidence that the cost of the light rail will be justified by its contribution to Program objectives.

The planned uses of the former railway land achieve a balance between the economic and social objectives of the Program at a reasonable cost to the Government. HCCDC, and previously UrbanGrowth NSW, identified and considered options for land use that would best meet Program objectives. Required probity processes were followed for developments that involved financial transactions. Our audit did not assess the achievement of these objectives because none of the projects have been completed yet.

Analysis presented in the Program business case and other planning documents showed that the light rail would have small transport benefits and was expected to make a modest contribution to broader Program objectives. Analysis in the Program business case argued that despite this, the light rail was justified because it would attract investment and promote economic development around the route. The Program business case referred to several international examples to support this argument, but did not make a convincing case that these examples were comparable to the proposed light rail in Newcastle.

The audited agencies argue that the contribution of light rail cannot be assessed separately because it is a part of a broader Program. The cost of the light rail makes up around 53 per cent of the total Program funding. Given the cost of the light rail, agencies need to be able to demonstrate that this investment provides value for money by making a measurable contribution to the Program objectives.

2. Consultation and oversight were mostly effective during the implementation stages of the Program. There were weaknesses in both areas in the planning stages.

Consultations about the urban renewal activities from around 2015 onward followed good practice standards. These consultations were based on an internationally accepted framework and met their stated objectives. Community consultations on the decision to close the train line were held in 2006 and 2009. However, the final decision in 2012 was made without a specific community consultation. There was no community consultation on the decision to build a light rail.

The governance arrangements that were in place during the planning stages of the Program did not provide effective oversight. This meant there was not a single agreed set of Program objectives until 2016 and roles and responsibilities for the Program were not clear. Leadership and oversight improved during the implementation phase of the Program. Roles and responsibilities were clarified and a multi-agency steering committee was established to resolve issues that needed multi-agency coordination.
The light rail is not justified by conventional cost-benefit analysis and there is insufficient evidence that the indirect contribution of light rail to achieving the economic development objectives of the Program will justify the cost.
Analysis presented in Program business cases and other planning documents showed that the light rail would have small transport benefits and was expected to make a modest contribution to broader Program objectives. Analysis in the Program business case argued that despite this, the light rail was justified because it would attract investment and promote economic development around the route. The Program business case referred to several international examples to support this argument, but did not make a convincing case that these examples were comparable to the proposed light rail in Newcastle.
The business case analysis of the benefits and costs of light rail was prepared after the decision to build light rail had been made and announced. Our previous reports, and recent reports by others, have emphasised the importance of completing thorough analysis before announcing infrastructure projects. Some advice provided after the initial light rail decision was announced was overly optimistic. It included benefits that cannot reasonably be attributed to light rail and underestimated the scope and cost of the project.
The audited agencies argue that the contribution of light rail cannot be assessed separately because it is part of a broader Program. The cost of the light rail makes up around 53 per cent of the total Program funding. Given the high cost of the light rail, we believe agencies need to be able to demonstrate that this investment provides value for money by making a measurable contribution to the Program objectives.

Recommendations
For future infrastructure programs, NSW Government agencies should support economical decision-making on infrastructure projects by:
  • providing balanced advice to decision makers on the benefits and risks of large infrastructure investments at all stages of the decision-making process
  • providing scope and cost estimates that are as accurate and complete as possible when initial funding decisions are being made
  • making business cases available to the public.​​​​​​
The planned uses of the former railway land achieve a balance between the economic and social objectives of the Program at a reasonable cost to the government.

The planned uses of the former railway land align with the objectives of encouraging people to visit and live in the city centre, creating attractive public spaces, and supporting growth in employment in the city. The transport benefits of the activities are less clear, because the light rail is the major transport project and this will not make significant improvements to transport in Newcastle.

The processes used for selling and leasing parts of the former railway land followed industry standards. Options for the former railway land were identified and assessed systematically. Competitive processes were used for most transactions and the required assessment and approval processes were followed. The sale of land to the University of Newcastle did not use a competitive process, but required processes for direct negotiations were followed.

Recommendation
By March 2019, the Hunter and Central Coast Development Corporation should:
  • work with relevant stakeholders to explore options for increasing the focus on the heritage objective of the Program in projects on the former railway land. This could include projects that recognise the cultural and industrial heritage of Newcastle.
Consultations about the urban renewal activities followed good practice standards, but consultation on transport decisions for the Program did not.

Consultations focusing on urban renewal options for the Program included a range of stakeholders and provided opportunities for input into decisions about the use of the former railway land. These consultations received mostly positive feedback from participants. Changes and additions were made to the objectives of the Program and specific projects in response to feedback received. 

There had been several decades of debate about the potential closure of the train line, including community consultations in 2006 and 2009. However, the final decision to close the train line was made and announced in 2012 without a specific community consultation. HCCDC states that consultation with industry and business representatives constitutes community consultation because industry representatives are also members of the community. This does not meet good practice standards because it is not a representative sample of the community.

There was no community consultation on the decision to build a light rail. There were subsequent opportunities for members of the community to comment on the implementation options, but the decision to build it had already been made. A community and industry consultation was held on which route the light rail should use, but the results of this were not made public. 

Recommendation
For future infrastructure programs, NSW Government agencies should consult with a wide range of stakeholders before major decisions are made and announced, and report publicly on the results and outcomes of consultations. 

The governance arrangements that were in place during the planning stages of the Program did not provide effective oversight. Project leadership and oversight improved during the implementation phase of the Program.

Multi-agency coordination and oversight were ineffective during the planning stages of the Program. Examples include: multiple versions of Program objectives being in circulation; unclear reporting lines for project management groups; and poor role definition for the initial advisory board. Program ownership was clarified in mid-2016 with the appointment of a new Program Director with clear accountability for the delivery of the Program. This was supported by the creation of a multi-agency steering committee that was more effective than previous oversight bodies.

The limitations that existed in multi-agency coordination and oversight had some negative consequences in important aspects of project management for the Program. This included whole-of-government benefits management and the coordination of work to mitigate impacts of the Program on small businesses.

Recommendations
For future infrastructure programs, NSW Government agencies should: 

  • develop and implement a benefits management approach from the beginning of a program to ensure responsibility for defining benefits and measuring their achievement is clear
  • establish whole-of-government oversight early in the program to guide major decisions. This should include:
    • agreeing on objectives and ensuring all agencies understand these
    • clearly defining roles and responsibilities for all agencies
    • establishing whole-of-government coordination for the assessment and mitigation of the impact of major construction projects on businesses and the community.

By March 2019, the Hunter and Central Coast Development Corporation should update and implement the Program Benefits Realisation Plan. This should include:

  • setting measurable targets for the desired benefits
  • clearly allocating ownership for achieving the desired benefits
  • monitoring progress toward achieving the desired benefits and reporting publicly on the results.

Appendix one - Response from agencies    

Appendix two - About the audit

Appendix three - Performance auditing

 

Parliamentary reference - Report number #310 - released 12 December 2018

Published

Actions for Matching skills training with market needs

Matching skills training with market needs

Industry
Compliance
Internal controls and governance
Management and administration
Risk
Service delivery
Workforce and capability

The NSW Department of Industry targets subsidies towards training programs delivering skills most needed in New South Wales. However, the Department still provides subsidies to qualifications that the market may no longer need, according to a report released by Margaret Crawford, Auditor-General for New South Wales. 

In 2012, governments across Australia entered into the National Partnership Agreement on Skills Reform. Under the National Partnership Agreement, the Australian Government provided incentive payments to States and Territories to move towards a more contestable Vocational Education and Training (VET) market. The aim of the National Partnership Agreement was to foster a more accessible, transparent, efficient and high quality training sector that is responsive to the needs of students and industry. 

The New South Wales Government introduced the Smart and Skilled program in response to the National Partnership Agreement. Through Smart and Skilled, students can choose a vocational course from a list of approved qualifications and training providers. Students pay the same fee for their chosen qualification regardless of the selected training provider and the government covers the gap between the student fee and the fixed price of the qualification through a subsidy paid to their training provider. 

Smart and Skilled commenced in January 2015, with the then Department of Education and Communities having primary responsibility for its implementation. Since July 2015, the NSW Department of Industry (the Department) has been responsible for VET in New South Wales and the implementation of Smart and Skilled. 

The NSW Skills Board, comprising nine part-time members appointed by the Minister for Skills, provides independent strategic advice on VET reform and funding. In line with most other States and Territories, the Department maintains a 'Skills List' which contains government subsidised qualifications to address identified priority skill needs in New South Wales.

This audit assessed the effectiveness of the Department in identifying, prioritising, and aligning course subsidies to the skill needs of NSW. To do this we examined whether:

  • the Department effectively identifies and prioritises present and future skill needs 
  • Smart and Skilled funding is aligned with the priority skill areas
  • skill needs and available VET courses are effectively communicated to potential participants and training providers.

Smart and Skilled is a relatively new and complex program, and is being delivered in the context of significant reform to VET nationally and in New South Wales. A large scale government funded contestable market was not present in the VET sector in New South Wales before the introduction of Smart and Skilled. This audit's findings should be considered in that context.
 

Conclusion
The Department effectively consults with industry, training providers and government departments to identify skill needs, and targets subsidies to meet those needs. However, the Department does not have a robust, data driven process to remove subsidies from qualifications which are no longer a priority. There is a risk that some qualifications are being subsidised which do not reflect the skill needs of New South Wales. 
The Department needs to better use the data it has, and collect additional data, to support its analysis of priority skill needs in New South Wales, and direct funding accordingly.
In addition to subsidising priority qualifications, the Department promotes engagement in skills training by:
  • funding scholarships and support for disadvantaged students
  • funding training in regional and remote areas
  • providing additional support to deliver some qualifications that the market is not providing.

The Department needs to evaluate these funding strategies to ensure they are achieving their goals. It should also explore why training providers are not delivering some priority qualifications through Smart and Skilled.

Training providers compete for funding allocations based on their capacity to deliver. The Department successfully manages the budget by capping funding allocated to each Smart and Skilled training provider. However, training providers have only one year of funding certainty at present. Training providers that are performing well are not rewarded with greater certainty.

The Department needs to improve its communication with prospective students to ensure they can make informed decisions in the VET market.

The Department also needs to communicate more transparently to training providers about its funding allocations and decisions about changes to the NSW Skills List. 

The NSW Skills List is unlikely to be missing high priority qualifications, but may include lower priority qualifications because the Department does not have a robust process to identify and remove these qualifications from the list. The Department needs to better use available data, and collect further data, to support decisions about which qualifications should be on the NSW Skills List.

The Department relies on stakeholder proposals to update the NSW Skills List. Stakeholders include industry, training providers and government departments. These stakeholders, particularly industry, are likely to be aware of skill needs, and have a strong incentive to propose qualifications that address these needs. The Department’s process of collecting stakeholder proposals helps to ensure that it can identify qualifications needed to address material skill needs. 

It is also important that the Department ensures the NSW Skills List only includes priority qualifications that need to be subsidised by government. The Department does not have robust processes in place to remove qualifications from the NSW Skills List. As a result, there is a risk that the list may include lower priority skill areas. Since the NSW Skills List was first created, new additions to the list have outnumbered those removed by five to one.

The Department does not always validate information gathered from stakeholder proposals, even when it has data to do so. Further, its decision making about what to include on, or delete from, the NSW Skills List is not transparent because the rationale for decisions is not adequately documented. 

The Department is undertaking projects to better use data to support its decisions about what should be on the NSW Skills List. Some of these projects should deliver useful data soon, but some can only provide useful information when sufficient trend data is available. 

Recommendation

The Department should: 

  • by June 2019, increase transparency of decisions about proposed changes to the NSW Skills List and improve record-keeping of deliberations regarding these changes
  • by December 2019, use data more effectively and consistently to ensure that the NSW Skills List only includes high priority qualifications
The Department funds training providers that deliver qualifications on the NSW Skills List. Alignment of funding to skill needs relies on the accuracy of the NSW Skills List, which may include some lower priority qualifications.

Only qualifications on the NSW Skills List are eligible for subsidies under Smart and Skilled. As the Department does not have a robust process for removing low priority qualifications from the NSW Skills list, some low priority qualifications may be subsidised. 

The Department allocates the Smart and Skilled budget through contracts with Smart and Skilled training providers. Training providers that meet contractual obligations and perform well in terms of enrolments and completion rates are rewarded with renewed contracts and more funding for increased enrolments, but these decisions are not based on student outcomes. The Department reduces or removes funding from training providers that do not meet quality standards, breach contract conditions or that are unable to spend their allocated funding effectively. Contracts are for only one year, offering training providers little funding certainty. 

Smart and Skilled provides additional funding for scholarships and for training providers in locations where the cost of delivery is high or to those that cater to students with disabilities. The Department has not yet evaluated whether this additional funding is achieving its intended outcomes. 

Eight per cent of the qualifications that have been on the NSW Skills List since 2015 are not delivered under Smart and Skilled anywhere in New South Wales. A further 14 per cent of the qualifications that are offered by training providers have had no student commencements. The Department is yet to identify the reasons that these high priority qualifications are either not offered or not taken up by students.

Recommendation

The Department should:

  • by June 2019, investigate why training providers do not offer, and prospective students do not enrol in, some Smart and Skilled subsidised qualifications 
  • by December 2019, evaluate the effectiveness of Smart and Skilled funding which supplements standard subsidies for qualifications on the NSW Skills List, to determine whether it is achieving its objectives
  • by December 2019, provide longer term funding certainty to high performing training providers, while retaining incentives for them to continue to perform well.
The Department needs to improve its communication, particularly with prospective students.

In a contestable market, it is important for consumers to have sufficient information to make informed decisions. The Department does not provide some key information to prospective VET students to support their decisions, such as measures of provider quality and examples of employment and further education outcomes of students completing particular courses. Existing information is spread across numerous channels and is not presented in a user friendly manner. This is a potential barrier to participation in VET for those less engaged with the system or less ICT literate.

The Department conveys relevant information about the program to training providers through its websites and its regional offices. However, it could better communicate some specific information directly to individual Smart and Skilled training providers, such as reasons their proposals to include new qualifications on the NSW Skills List are accepted or rejected. 

While the Department is implementing a communication strategy for VET in New South Wales, it does not have a specific communications strategy for Smart and Skilled which comprehensively identifies the needs of different stakeholders and how these can be addressed. 

Recommendation

By December 2019, the Department should develop and implement a specific communications strategy for Smart and Skilled to:

  • support prospective student engagement and informed decision making
  • meet the information needs of training providers 

Appendix one - Response from agency

Appendix two - About the audit

Appendix three - Performance auditing

 

Parliamentary reference - Report number #305 - released 26 July 2018

Published

Actions for Regional Assistance Programs

Regional Assistance Programs

Premier and Cabinet
Planning
Transport
Compliance
Infrastructure
Management and administration
Project management

Infrastructure NSW effectively manages how grant applications for regional assistance programs are assessed and recommended for funding. Its contract management processes are also effective. However, we are unable to conclude whether the objectives of these programs have been achieved as the relevant agencies have not yet measured their benefits, according to a report released today by the Auditor-General for New South Wales, Margaret Crawford. 

In 2011, the NSW Government established Restart NSW to fund new infrastructure with the proceeds from the sale and lease of government assets. From 2011 to 2017, the NSW Government allocated $1.7 billion from the fund for infrastructure in regional areas, with an additional commitment of $1.3 billion to be allocated by 2021. The NSW Government allocates these funds through regional assistance programs such as Resources for Regions and Fixing Country Roads. NSW councils are the primary recipients of funding provided under these programs.

The NSW Government announced the Resources for Regions program in 2012 with the aim of addressing infrastructure constraints in mining affected communities. Infrastructure NSW administers the program, with support from the Department of Premier and Cabinet.

The NSW Government announced the Fixing Country Roads program in 2014 with the aim of building more efficient road freight networks. Transport for NSW and Infrastructure NSW jointly administer this program, which funds local councils to deliver projects that help connect local and regional roads to state highways and freight hubs.

This audit assessed whether these two programs (Resources for Regions and Fixing Country Roads) were being effectively managed and achieved their objectives. In making this assessment, we answered the following questions:

  • How well are the relevant agencies managing the assessment and recommendation process?
  • How do the relevant agencies ensure that funded projects are being delivered?
  • Do the funded projects meet program and project objectives?

The audit focussed on four rounds of Resources for Regions funding between 2013–14 to 2015–16, as well as the first two rounds of Fixing Country Roads funding in 2014–15 and 2015–16.

Conclusion
Infrastructure NSW effectively manages how grant applications are assessed and recommended for funding. Infrastructure NSW’s contract management processes are also effective. However, we are unable to conclude on whether program objectives are being achieved as Infrastructure NSW has not yet measured program benefits.
While Infrastructure NSW and Transport for NSW managed the assessment processes effectively overall, they have not fully maintained all required documentation, such as conflict of interest registers. Keeping accurate records is important to support transparency and accountability to the public about funding allocation. The relevant agencies have taken steps to address this in the current funding rounds for both programs.
For both programs assessed, the relevant agencies have developed good strategies over time to support councils through the application process. These strategies include workshops, briefings and feedback for unsuccessful applicants. Transport for NSW and the Department of Premier and Cabinet have implemented effective tools to assist applicants in demonstrating the economic impact of their projects.
Infrastructure NSW is effective in identifying projects that are 'at‑risk' and assists in bringing them back on track. Infrastructure NSW has a risk‑based methodology to verify payment claims, which includes elements of good practice in grants administration. For example, it requires grant recipients to provide photos and engages Public Works Advisory to review progress claims and visit project sites.
Infrastructure NSW collects project completion reports for all Resources for Regions and Fixing Country Roads funded projects. Infrastructure NSW intends to assess benefits for both programs once each project in a funding round is completed. To date, no funding round has been completed. As a result, no benefits assessment has been done for any completed project funded in either program.
 

The project selection criteria are consistent with the program objectives set by the NSW Government, and the RIAP applied the criteria consistently. Probity and record keeping practices did not fully comply with the probity plans.

The assessment methodology designed by Infrastructure NSW is consistent with2 the program objectives and criteria. In the rounds that we reviewed, all funded projects met the assessment criteria.

Infrastructure NSW developed probity plans for both programs which provided guidance on the record keeping required to maintain an audit trail, including the use of conflict of interest registers. Infrastructure NSW and Transport for NSW did not fully comply with these requirements. The relevant agencies have taken steps to address this in the current funding rounds for both programs.

NSW Procurement Board Directions require agencies to ensure that they do not engage a probity advisor that is engaged elsewhere in the agency. Infrastructure NSW has not fully complied with this requirement. A conflict of interest arose when Infrastructure NSW engaged the same consultancy to act as its internal auditor and probity advisor.

While these infringements of probity arrangements are unlikely to have had a major impact on the assessment process, they weaken the transparency and accountability of the process.

Some councils have identified resourcing and capability issues which impact on their ability to participate in the application process. For both programs, the relevant agencies conducted briefings and webinars with applicants to provide advice on the objectives of the programs and how to improve the quality of their applications. Additionally, Transport for NSW and the Department of Premier and Cabinet have developed tools to assist councils to demonstrate the economic impact of their applications.

The relevant agencies provided feedback on unsuccessful applications to councils. Councils reported that the quality of this feedback has improved over time.

Recommendations

  1. By June 2018, Infrastructure NSW should:
    • ensure probity reports address whether all elements of the probity plan have been effectively implemented.
  1. By June 2018, Infrastructure NSW and Transport for NSW should:
    • maintain and store all documentation regarding assessment and probity matters according to the State Records Act 1998, the NSW Standard on Records Management and the relevant probity plans

Infrastructure NSW is responsible for overseeing and monitoring projects funded under Resources for Regions and Fixing Country Roads. Infrastructure NSW effectively manages projects to keep them on track, however it could do more to assure itself that all recipients have complied with funding deeds. Benefits and outcomes should also start to be measured and reported as soon as practicable after projects are completed to inform assessment of future projects.

Infrastructure NSW identifies projects experiencing unreasonable delays or higher than expected expenses as 'at‑risk'. After Infrastructure NSW identifies a project as 'at‑risk', it puts in place processes to resolve issues to bring them back on track. Infrastructure NSW, working with Public Works Advisory regional offices, employs a risk‑based approach to validate payment claims, however this process should be strengthened. Infrastructure NSW would get better assurance by also conducting annual audits of compliance with the funding deed for a random sample of projects.

Infrastructure NSW collects project completion reports for all Resources for Regions and Fixing Country Roads funded projects. It applies the Infrastructure Investor Assurance Framework to Resources for Regions and Fixing Country Roads at a program level. This means that each round of funding (under both programs) is treated as a distinct program for the purposes of benefits realisation. It plans to assess whether benefits have been realised once each project in a funding round is completed. As a result, no benefits realisation assessment has been done for any project funded under either Resources for Regions or Fixing Country Roads. Without project‑level benefits realisation, future decisions are not informed by the lessons from previous investments.

Recommendations

  1. By December 2018, Infrastructure NSW should:
    • conduct annual audits of compliance with the funding deed for a random sample of projects funded under Resources for Regions and Fixing Country Roads
    • publish the circumstances under which unspent funds can be allocated to changes in project scope
    • measure benefits delivered by projects that were completed before December 2017
    • implement an annual process to measure benefits for projects completed after December 2017
  1. By December 2018, Transport for NSW and Infrastructure NSW should:
    • incorporate a benefits realisation framework as part of the detailed application.

Published

Actions for Grants to non-government schools

Grants to non-government schools

Education
Compliance
Internal controls and governance
Management and administration

The NSW Department of Education could strengthen its management of the $1.2 billion provided to non-government schools annually. This would provide greater accountability for the use of public funds, according to a report released today by the Auditor-General for New South Wales, Margaret Crawford.

Non‑government schools educate 418,000 school children each year, representing 35 per cent of all students in NSW. The NSW Department of Education administers several grant schemes to support these schools, with the aim of improving student learning outcomes and supporting parent choice. To be eligible for NSW Government funding, non‑government schools must be registered with the NSW Education Standards Authority (NESA) and not operate 'for profit' as per section 83C of the NSW Education Act 1990 (the Act). Non‑government schools can either be registered as independent or part of a System Authority.

In 2017–18, non‑government schools in NSW will receive over $1.2 billion from the NSW Government, as well as $3.4 billion from the Australian Government. Recently, the Australian Government has changed the way it funds schools. The NSW Government is assessing how these changes will impact State funding for non‑government schools.

This audit assessed how effectively and efficiently NSW Government grants to non‑government schools are allocated and managed. This audit did not assess the use of NSW Government grants by individual non‑government schools or System Authorities because the Auditor‑General of New South Wales does not have the mandate to assess how government funds are spent by non‑government entities.

Conclusion

The Department of Education effectively and efficiently allocates grants to non‑government schools. Clarifying the objectives of grants, monitoring progress towards these objectives, and improving oversight, would strengthen accountability for the use of public funds by non‑government schools.

We tested a sample of grants provided to non‑government schools under all major schemes, and found that the Department of Education consistently allocates and distributes grants in line with its methodology. The Department has clear processes and procedures to efficiently collect data from schools, calculate the level of funding each school or System should receive, obtain appropriate approvals, and make payments.

We identified three areas where the Department could strengthen its management of grants to provide greater accountability for the use of public funds. First, the Department’s objectives for providing grants to non‑government schools are covered by legislation, intergovernmental agreements and grant guidelines. The Department could consolidate these objectives to allow for more consistent monitoring. Second, the Department relies on schools or System Authorities to engage a registered auditor to certify the accuracy of information on their enrolments and usage of grants. Greater scrutiny of the registration and independence of the auditors would increase confidence in the accuracy of this information. Third, the Department does not monitor how System Authorities reallocate grant funding to their member schools. Further oversight in this area would increase accountability for the use of public funds.

The Department effectively and efficiently allocates grants to non‑government schools. Strengthening its processes would provide greater assurance that the information it collects is accurate.

The Department provides clear guidelines to assist schools to provide the necessary census information to calculate per capita grants. Schools must get an independent external auditor, registered with ASIC, to certify their enrolment figures. The Department checks a sample of the auditors to ensure that they are registered with ASIC. Some other jurisdictions perform additional procedures to increase confidence in the accuracy of the census (for example, independently checking a sample of schools’ census data).

The Department accurately calculates and distributes per capita grants in accordance with its methodology. The previous methodology, used prior to 2018, was not updated frequently enough to reflect changes in schools' circumstances. Over 2014 to 2017, the Department provided additional grants to non‑government schools under the National Education Reform Agreement (NERA), to bring funding more closely in line with the Australian Department of Education and Training's Schooling Resource Standard (SRS). From 2018, the Department has changed the way it calculates per capita grants to more closely align with the Australian Department of Education and Training's approach.

The Department determines eligibility for grants by checking a school's registration status with NESA. However, NESA's approach to monitoring compliance with the registration requirements prioritises student learning and wellbeing requirements over the requirement for policies and procedures for proper governance. Given their importance to the appropriate use of government funding, NESA could increase its monitoring of policies and procedures for proper governance through its program of random inspections. Further, the Department and NESA should enter into a formal agreement to share information to more accurately determine the level of risk of non‑compliance at each school. This may help both agencies more effectively target their monitoring to higher‑risk schools.

By December 2018, the NSW Department of Education should:

  1. Strengthen its processes to provide greater assurance that the enrolment and expenditure information it collects from non‑government schools is accurate. This should build on the work the Australian Government already does in this area.
  2. Establish formal information‑sharing arrangements with the NSW Education Standards Authority to more effectively monitor schools' eligibility to receive funding.
     

By December 2018, the NSW Education Standards Authority should:

  1. Extend its inspection practices to increase coverage of the registration requirement for policies and procedures for the proper governance of schools.
  2. Establish formal information‑sharing arrangements with the NSW Department of Education to more effectively monitor schools' continued compliance with the registration requirements.

The Department’s current approach to managing grants to non‑government schools could be improved to provide greater confidence that funds are being spent in line with the objectives of the grant schemes.

The NSW Government provides funding to non‑government schools to improve student learning outcomes, and to support schooling choices by parents, but does not monitor whether these grants are achieving this. In addition, each grant program has specific objectives. The main objectives for the per capita grant program is to increase the rate of students completing Year 12 (or equivalent), and to improve education outcomes for students. While non‑government schools publicly report on some educational measures via the MySchool website, these measures do not address all the objectives. Strengthened monitoring and reporting of progress towards objectives, at a school level, would increase accountability for public funding. This may require the Department to formalise its access to student level information.

The Department has listed five broad categories of acceptable use for per capita grants, however, provides no further guidance on what expenditure would fit into these categories. Clarifying the appropriate use of grants would increase confidence that funding is being used as intended. Schools must engage an independent auditor, registered with ASIC, to certify that the funding has been spent. The Department could strengthen this approach by improving its processes to check the registration of the auditor, and to verify their independence.

The Department has limited oversight of funding provided to System Authorities (Systems). The Department provides grants to Systems for all their member schools. The Systems can distribute the grants to their schools according to their own methodology. Systems are not required to report to the Department how much of their grant was retained for administrative or centralised expenses. Increased oversight over how the Systems distribute this grant could provide increased transparency for the use of public funds by systems.

By December 2018, the NSW Department of Education should:

  1. Establish and communicate funding conditions that require funded schools to:
    • adhere to conditions of funding, such as the acceptable use of grants, and accounting requirements to demonstrate compliance
    • report their progress towards the objectives of the scheme or wider Government initiatives
    • allow the Department to conduct investigations to verify enrolment and expenditure of funds
    • provide the Department with access to existing student level data to inform policy development and analysis.
  1. Increase its oversight of System Authorities by requiring them to:
    • re‑allocate funds across their system on a needs basis, and report to the Department on this
    • provide a yearly submission with enough detail to demonstrate that each System school has spent their State funding in line with the Department's requirements.

Published

Actions for Sharing school and community facilities

Sharing school and community facilities

Education
Infrastructure
Management and administration
Risk
Shared services and collaboration

Schools and the community would benefit if school facilities were shared more often. 

The Department of Education’s ‘Community Use of School Facilities Policy’ encourages but does not require schools to share facilities. Sharing depends heavily on the willingness of school principals and there are few incentives. There are many challenges in developing agreements with community users and there is only limited support available from the Department.

There are strategies and plans to support the sharing of facilities between schools and the wider community, but none are backed up with budgets, specific plans or timeframes.

Governments should strive for the best use of assets. This is particularly important in the context of a growing New South Wales population, fiscal constraints and increasing demand for services. 

Lack of available land, rising land costs and population growth highlighted in our April 2017 'Planning for school infrastructure' performance audit report mean that new and existing schools will need to share their facilities with communities more than is currently the case.

This audit assessed how effectively schools share facilities with each other, local councils and community groups. In making this assessment, the audit examined whether the Department of Education (Department):

  • has a clear policy to encourage and support facilities sharing
  • is implementing evidence-based strategies and procedures for facilities sharing
  • can show it is realising an increasing proportion of sharing opportunities.

Facilities sharing is the use of a physical asset, such as a building, rooms, or open spaces, by more than one group for a range of activities at the same time or at different times. For the purposes of this audit, we have divided sharing arrangements into two types: shared use and joint use.

Shared use refers to arrangements where existing school assets are hired out for non-school purposes, usually for a limited time. The assets remain under the control of the school. Generally, there is little alteration or enhancement to the asset required to enable shared use. Shared use can also refer to schools using external facilities, such as council pools, but these arrangements are not included within the scope of this audit. 

Joint use refers to arrangements where new or upgraded school and non-school facilities or community hubs are planned, funded, built and jointly shared between a school and other parties, usually involving significant investment. 

Both shared use and joint use agreements are governed by contractual obligations.

Conclusion
The sharing of school facilities with the community is not fully effective. The Department of Education is implementing strategies to increase shared and joint use but several barriers, some outside the Department’s direct control, must be addressed to fully realise benefits to students and the community of sharing school facilities. In addition, the Department needs to do more to encourage individual schools to share facilities with the community. 

A collaborative, multi-agency approach is needed to overcome barriers to the joint use of facilities, otherwise, the Department may need significantly more funds than planned to deliver sufficient fit-for-purpose school facilities where and when needed.
Government policies encourage, but do not mandate, shared and joint use of facilities.

Since the early 2000’s, several reviews in NSW and other jurisdictions have commented on the benefits of and need to increase the sharing of school facilities. 

Several NSW Government strategies and plans support shared and joint use of facilities between schools and the wider community, but none are backed up with financial incentives, or specific plans with implementation timeframes. In Victoria and Queensland whole-of-government processes are in place to support a more coordinated approach to planning, building and sharing community facilities. For example, Victoria has a comprehensive policy framework encompassing both existing and future use of community facilities and a $50 million program to seed the development of community facilities on school sites over the next four years.  
The Department recognises benefits from the shared use of school facilities, but provides insufficient support to Principals to ensure costs are recovered and that money raised from shared use can be spent by the school in a timely manner. 

There are examples of successful shared use, but more can be done. Information about the available facilities is not readily available to potential community users. Schools should work more closely with councils and other stakeholders to leverage shared use. 

Currently, the administrative burden, costs and risks associated with shared use can exceed the perceived benefits to schools, leading to reluctance amongst some Principals to share. In addition, a substantial backlog of school-initiated infrastructure proposals awaiting Departmental approval means that schools that raise money from sharing their facilities find it difficult to use the funds they raise on improved infrastructure. Some of these proposals have been waiting for approval for more than 12 months. 

The Department could do more to support Principals by ensuring the fees charged for facilities cover the costs incurred by schools, that Principals can access help with negotiating and managing contracts, and that infrastructure proposals initiated and funded by schools are approved in a timely manner. 

The Department is not monitoring shared use across the State, and does not evaluate different approaches as evidence to influence policies and procedures.

Recommendations
By December, 2018, the Department should:
  • increase incentives and reduce impediments for school Principals to share school facilities, including:
    • review the methodology for calculating fees charged for facilities to ensure that shared use of school facilities does not result in a financial burden to schools or the Department 
    • improve support provided to Principals by School Infrastructure NSW, including reducing the backlog of school-initiated infrastructure proposals awaiting approval
    • develop service standards, including timeframes, for assessing and approving school-initiated infrastructure proposals.
  • provide readily-accessible information about available school facilities to community groups and local councils
  • implement processes to monitor and regularly evaluate the implementation of the shared use policy and promote better practice to drive improvements.
The Department is planning a more strategic approach to increase the joint use of school facilities. However, several barriers, some outside the Department’s control, must be addressed to fully realise benefits of joint use agreements.

As discussed in our 2017 audit report on ‘Planning for school infrastructure’, joint use agreements are a key direction of the School Assets Strategic Plan. Joint use of school facilities will be necessary to ensure that there will be enough fit-for-purpose learning spaces for students when and where needed. Under the ‘Community Use of School Facilities Policy’ Principals play the leading role in identifying opportunities, and developing and managing agreements for sharing school facilities. This is impractical for joint use projects which involve substantial investment in new or refurbished assets, in particular for joint use projects in schools that are yet to be built. In addition, the policy does not address joint-use facilities built on land not owned by the Department. For these reasons, the Department is developing a new policy. 

The Department is planning to develop joint use agreements in a more systematic way as part of school community planning, previously known as cluster planning, with a special focus on local councils. Several agreements are currently being piloted, and will be evaluated to provide an evidence-based foundation for this new approach. 

To develop or refurbish school facilities for joint use, the Department, councils and other key stakeholders must work together and prioritise joint use from the earliest stages of any project. A collaborative, multi-agency approach is needed to ensure sufficient fit-for-purpose facilities are available for school students within the funding framework proposed in the School Assets Strategic Plan. 

To increase shared and joint use, the Department is recruiting specialist staff in its Asset Division to assist with the brokerage, community engagement and development of agreements, but these staff are not dedicated to joint use projects and their available time may not be sufficient to provide the necessary support in the timeframes required.

Recommendations
By December, 2018, the Department of Education should:
  • ensure that the implementation of the new ‘Joint Use of School Facilities and Land Policy’ is adequately resourced, and has the support of Principals
  • implement processes to monitor and regularly evaluate the implementation of joint use policy and promote better practice to drive improvements.  

Published

Actions for Energy rebates for low income households

Energy rebates for low income households

Planning
Industry
Compliance
Fraud
Internal controls and governance
Management and administration

The Department of Planning and Environment provides more than $245 million in energy rebates to around 27 percent of NSW households. This report highlights that the department is not monitoring the rebate schemes to understand whether they are delivering the best outcomes.

Most rebates are ongoing payments applied directly to energy bills reducing the amount payable by the householder. The structure of these rebates is complex and can be inequitable. Some households are eligible for four different rebates, each with its own eligibility criteria.  Also, some households in very similar circumstances receive different levels of support depending on what type of energy is used in their home or which adult in the house is the energy account holder. For example, a household using both electricity and gas receives more assistance than a household with electricity alone even if total energy bills are the same. 

The Department of Planning and Environment (Department) administers five energy rebate schemes targeted to low-income households. The five rebates are of two key types:

1. Ongoing support to pay energy bills
2. Crisis Support  

More than one million rebates are paid each year to over 800,000, or around 27 per cent, of NSW households. Households learn about rebates from a variety of sources including: Service NSW, government and energy retailer websites, energy retailer welcome packs, Department marketing efforts, information on energy bills, and Centrelink.  

The budget for energy rebates is increasing every year and in 2017–18 is more than $245 million. The Department delivers most rebates through a network of partnership arrangements with:

  • energy retailers, who apply rebates directly onto energy bills
  • more than 340 charities and other NGOs who assess households' eligibility for crisis support and distribute support through the Energy Accounts Payment Assistance scheme (EAPA)
  • Service NSW, who informs NSW households about rebates through their call centre.

The energy rebates budget is substantial and the distribution arrangements are complex. The objective of the audit was to assess whether the current design and distribution of energy rebates schemes is effective.

Conclusion
The Department administers the rebate schemes using partners to ensure funds are directed towards energy bills as intended. Ongoing support schemes provide assistance to low-income households as intended, but have no measurable objectives or outcome measures and therefore can't be assessed for their effectiveness. Crisis support (EAPA) has a clear objective, to keep households experiencing financial crisis connected to energy services, but the Department does not monitor the performance of EAPA against this objective.  

The structure of rebates providing ongoing support is complex and can be inequitable for some households. Reducing the number of separate schemes and simplifying eligibility requirements offers the most scope for improving effectiveness of ongoing support schemes.  

The growth of embedded networks1 represents a future administrative risk to the Department.

Partnering with energy retailers, charities and NGOs delivers advantages, but stronger oversight is required over partner organisations.

The Department and partner organisations administer the rebate schemes as designed

The Department oversees a complex package of rebate schemes in partnership with 25 retailers and around 340 charities and NGOs. The partnership arrangements ensure that funds are distributed directly to energy bills as intended. The schemes provide support to recipients and are administered in line with government decisions about eligibility.  

Communication about rebates does not reach all eligible households

Households learn about rebate schemes through a mix of communication channels including retailer websites and call centres, Department websites, Centrelink, financial counsellors, EAPA Providers, the Energy and Water Ombudsman and Service NSW. Some low-income groups, such as those with poor English language skills, do not find out about energy rebates.

Scheme objectives are not measurable

Rebate schemes that provide ongoing support do not have measurable objectives or outcome measures. Without clear and measurable objectives, the Department cannot report to government on whether the schemes are achieving the intended policy outcomes, nor recommend improvements to ensure the schemes deliver the greatest benefit to the most financially vulnerable households.

The EAPA crisis support scheme has a clearer objective in that it aims to keep households experiencing financial crisis connected to energy services. However, the Department does not measure outcomes from providing this type of support, and does not know if the crisis support achieves this objective.  

The structure of rebate schemes for ongoing support is complex

The Low Income Household Rebate accounts for 80 per cent of the budget for ongoing support rebates. The remaining 20 per cent of the budget is administered through four separate schemes: Gas Rebate, Medical Energy Rebate, Family Energy Rebate and Life Support Rebate.

Each of these rebates has its own eligibility criteria and some require separate application processes. The Family Energy Rebate is complex to access and apply for, and around one third of households do not reapply each year. Eligible households that receive energy through embedded networks apply directly to the Department for rebates, which are paid by the Department into bank accounts. Embedded networks are energy supply arrangements where the manager of a residential facility such as a caravan park, retirement village or apartment block, buys energy in bulk and then on-sells it to residents. The Department is yet to develop strategies to address a forecast increase in such households.

The design of the rebate schemes creates some inequities

Households in similar circumstances can receive different levels of assistance depending on which adult in the house is the energy account holder, the mix of energy types used in the home, or the EAPA Provider they turn to when in financial crisis.

Households with both gas and electricity connections receive more assistance than those with only electricity. Households in rural and regional areas receive the same value rebate as households closer to Sydney, despite higher distribution charges. Family Energy Rebate is a two-tier payment, with a higher amount available to families with greater means. Lower-income families receive a much smaller Family Energy Rebate on the assumption that they already receive Low Income Household Rebate. Charities and NGOs distributing EAPA crisis support apply inconsistent standards when assessing household need, which leads to inequitable levels of assistance.

Departmental oversight of energy retailers and EAPA Providers is not strong enough

While partnering with energy retailers and EAPA Providers delivers advantages, stronger management is needed to ensure that partners follow Departmental guidelines and to minimise the potential for fraud. The Department's accreditation process for potential EAPA Providers does not consider the applicant's financial governance standards and the most recent audit of EAPA Providers was 2013.


[1] Embedded networks are energy supply arrangements where the manager of a residential facility such as a caravan park, retirement village or apartment block, buys energy in bulk and then on-sells it to residents.

By September 2018, the Department of Planning and Environment should:

  1. Ensure effective strategies are in place to make information about rebates available to all eligible, low-income households
     
  2. Evaluate alternative models and develop advice for government to reduce complexity and improve equity of ongoing rebates
     
  3. Establish measurable objectives for schemes that provide ongoing support, and monitor and measure performance of all schemes against objectives and outcome measures
     
  4. Assess the impacts of the forecast increase in embedded networks and develop strategies to manage any increased administrative risk
     
  5. Strengthen assurance that EAPA is being provided in accordance with its objectives and guidelines by implementing accreditation and compliance programs
     
  6. Ensure those eligible for EAPA financial support are not disadvantaged by inflexible payments, inconsistent provider practices, or inability to access an EAPA provider in a timely manner. Options include:
    • moving from a fixed-value voucher to a flexible payment based on need irrespective of energy type
    • establishing a ‘Provider of Last Resort’ facility for households that cannot access an EAPA Provider.

Appendix one - Response from the Agency

Appendix two - About the audit

 

Parliamentary reference - Report number #292 - released 19 September 2017 

Published

Actions for Office of Strategic Lands

Office of Strategic Lands

Planning
Environment
Management and administration
Procurement

The Office of Strategic Lands effectively fulfils most aspects of its defined role, however, it could do more to support strategic land planning by identifying and acquiring land for future public use proactively rather than waiting for agencies or landholders to approach it. It may also have greater impact if it expanded its activities beyond greater Sydney.

The Office of Strategic Lands (OSL) was established under the Environmental Planning and Assessment Act 1979 (EP&A Act) to identify, acquire, manage and divest land required for long-term planning by the NSW Government, particularly for open space and public purposes. 

OSL is a Corporation Sole acting on behalf of the Minister for Planning and is run within the Department of Planning and Environment (DPE). OSL is a self-funding entity, and is responsible for administering the Sydney Region Development Fund (SRDF), a statutory fund used for ongoing land acquisition and management. OSL currently only operates within greater Sydney and holds over a billion dollars in land assets in this region. 

This audit assessed whether OSL effectively fulfils its role to identify, acquire, manage and dispose of land, and whether OSL ensures it is sustainable over the long-term to meet its objectives. 

Conclusion:

OSL effectively fulfils most aspects of its defined role, but is not supporting strategic land planning through proactive identification and acquisition of land for future public use. OSL is diligent in its financial management over the short and medium terms. However, it has identified that relying on the sale of surplus land to continue funding its ongoing operations is not sustainable, and it is yet to finalise a strategy to address this.


OSL does not currently have a strategic or proactive focus to improve land planning outcomes. This is primarily due to the lack of a clear strategy and business plan to direct its work which defines OSL’s purpose, objectives, goals and performance targets.

OSL expects to finalise and implement a Strategic Business Plan to guide its future direction and long-term sustainability, in late 2017. 

OSL has three primary sources of funding. The largest source is Treasury loans which it needs to repay. The next most significant source of funding is from sales of land no longer required for government’s long-term needs. OSL has identified that it is likely to run out of surplus land within ten years. This is a significant financial risk for OSL, which should be addressed through a long-term financial strategy. 

Contributions by Sydney councils into the SRDF are OSL’s only regular and consistent income stream. The formula to calculate these contributions has not been reviewed for over 25 years, and recent council mergers and border changes have increased the need to review the formula. 

OSL is not used as extensively as it could be by other NSW Government agencies. It has the potential to play a much bigger role in assisting NSW Government agencies with longer term planning by partnering with them to identify, acquire, hold and manage land for future needs. For example, it could acquire land in future residential growth areas for needed public services such as schools, hospitals and transport corridors. There is also potential for OSL to expand its operations beyond the greater Sydney region into other parts of NSW to provide a statewide benefit from its unique role in government.

OSL has a unique role amongst government agencies, and could be used across NSW

NSW Government agencies we spoke with consider OSL fulfils an important role for the state that no other government agency performs. As a self-funding long-term land holder and manager, OSL can acquire and manage land beyond the four-year budget cycle that other government agencies face. Consideration should be given to expanding to other growth areas in NSW, where its unique role could assist in longer term land planning.

OSL has established good processes and procedures for most aspects of its role. This includes governance processes that we found to have been applied effectively. There was also adequate oversight and approvals for land transactions.

OSL has yet to finalise a business strategy to ensure long-term sustainability

OSL has shown that it is financially and operationally viable in the short to medium term. However, it does not have an overarching business strategy to guide its operations and ensure it is financially sustainable for the long-term. With a unique role in government, it is important for OSL to clarify its direction and implement a strategic business plan to drive its progress.

While there is no overarching long-term strategy, OSL has documented operating plans which guide its land acquisition and land divestment activities over the short to medium term. It has not developed a plan for its ongoing land management activities.
OSL advised that its Strategic Business Plan will be finalised and implemented in late 2017. This Plan should clarify OSL’s long-term direction, and guide its business to ensure it is financially sustainable.

OSL does not have adequate performance targets and measures

OSL has four key deliverables as part of DPE’s business plan. These deliverables cover land management, working with other agencies, and ensuring the SRDF is sustainable. There was no evidence that OSL or DPE monitor whether OSL achieves all key deliverables.

Currently, OSL’s performance targets are limited to meeting dollar values. OSL does not have any measures to demonstrate the achievement of outcomes that align with its core business, such as its success in land management or in working with other agencies. OSL staff also said that dollar targets were not always adequate or appropriate to measure its business performance.

With the development of its Strategic Business Plan, OSL has the opportunity to clarify its future business direction. This includes ensuring it has a range of relevant goals and performance measures that will support it becoming a strategic land planning partner with NSW Government agencies and local councils, and a land holder for the long-term.

OSL’s current financial management approach may impact long-term sustainability

OSL has valued the land that it needs to purchase on behalf of government to meet long-term strategic land needs in the Greater Sydney region, at $1.2 billion. However, OSLs annual budget for purchasing land is only between $40 million and $50 million until 2021. Also, in each of the last four years, OSL has not spent more than $30 million on land purchases because it relies on landowners to initiate contact when they are ready to sell their land.

Without a more proactive approach, it is not possible for OSL to make needed purchases in a timely manner. OSL acknowledges the substantial gap between these values, but has not established a budget or plan for how it will purchase all the identified land.

OSL has developed a Divestment Strategy which provides a five-year schedule of planned divestments. This is land OSL owns which has been identified as no longer required for government purposes. OSL has established an approach to generate the best and highest price for these sales. While funds are generated through the sale of surplus land, it also means that OSL holds fewer land assets to sell. OSL has identified it will run out of surplus land within ten years.

OSL needs to finalise and implement a business model to ensure it is financially and operationally capable to sustain and grow its business for the long-term.

OSL is working to improve transparency and engagement with key stakeholders

To deliver on its role, OSL needs to be able to effectively engage and work with its stakeholders, including NSW Government agencies, local councils, and people selling or buying land.

NSW Government agencies we spoke with are generally satisfied with OSL’s level of engagement and consultation. However, it would be beneficial for all parties to clarify and document their expectations of each other through a formal arrangement. OSL could also be more proactive in promoting its services, and working with additional NSW Government agencies to identify strategic lands.

The local councils in the Sydney region we spoke with are not as satisfied with OSL’s engagement and communication. The councils advised that they do not consider they are well-informed of OSL’s plans for their area, or how their contributions to the SRDF are spent.

More broadly, the activities of OSL are not reported transparently to stakeholders or the general public. OSL is developing a communication package for local councils and the community. This is an opportunity for OSL to improve the transparency of its role, operations, projects, and the SRDF, as well as promote its services and achievements.

The Office of Strategic Lands (OSL) was established in 1951 to identify, acquire, manage and divest land required for the NSW Government's long term planning purposes. OSL acts on behalf of the Minister for Planning, as a Corporation Sole, under the Environmental Planning and Assessment Act 1979 (EP&A Act).

OSL acquires and manages land identified for long-term strategic needs, and then transfers or sells it to other government agencies for ultimate use. It also sells land identified as surplus to government’s long term strategic requirements. Surplus land can also be transferred to local councils. OSL operates only in the greater Sydney region (from Wyong in the north, to the base of the Blue Mountains in the west, and south to Wollondilly). OSL has 20 staff who manage over 6,000 parcels of land.
 

The Department of Planning and Environment (Office of Strategic Lands) should:

By December 2017:  

  1. clarify and document its long-term purpose, role and goals in line with its mandate. This includes:
    • finalising and implementing a business plan with outcome-based performance measures that support the achievement of its goals
    • establishing and implementing a business and financial model, including resourcing, that supports its long-term strategy
    • exploring options for expanding the operation of OSL to other areas of NSW.

By July 2018:

2. develop and implement an approach for working with NSW Government agencies to improve its efficacy in strategic land identification, acquisition and management.

On an ongoing basis:

3. improve the transparency of its operations, and its communication and engagement with all stakeholders. This includes developing engagement strategies appropriate for different stakeholder groups.

Published

Actions for Information and Communication Technologies in schools for teaching and learning

Information and Communication Technologies in schools for teaching and learning

Education
Information technology
Infrastructure
Management and administration
Service delivery
Workforce and capability

Several factors are reducing effective use of information and communication technology (ICT) in the classroom.

These are primarily:

  • ageing ICT equipment and inadequate wireless networks
  • variable student access to devices at school
  • variable teacher access to centrally provided devices for use outside of the classroom.

Information and communication technologies (ICT) are pervasive in modern life. Australian research has identified that the workforce demand for digital literacy and advanced digital skills is growing across most areas of work. There is broad agreement internationally and in Australian school systems that digital literacy is a core skill for the workforce and students will need to be confident with ICT. Education systems around the world are using ICT in classrooms to support learning and employment goals.  

The New South Wales Department of Education’s (the Department’s) overall strategic directions for teaching and learning with ICT are set in the 'Strategic Information Technology Plan 2016–19'. The Department centrally provides a base level of resources to schools for ICT and schools supplement funding from their existing school budget and Parents and Citizens Associations. Each school decides how to allocate these funds to meet local needs. Schools also set expectations for how teachers and students will use technology to help deliver outcomes.

This audit assessed how well New South Wales public schools are using ICT to improve teaching and learning. It focussed on planning and teacher and student use of ICT. We examined whether:

  • the Department identifies key strategic opportunities to enhance the use of ICT platforms and technologies in schools
  • teachers are integrating ICT into classroom practice
  • the Department monitors the impact of ICT on student learning.
Conclusion 

Several factors are reducing the effective use of ICT in the classroom. These are primarily:

  • ageing ICT equipment and inadequate wireless networks
  • variable student access to devices at school
  • variable teacher access to centrally provided devices to use outside of the classroom.

Many schools are struggling to keep up with growing ICT needs within available funding. The Department needs to review whether its current technology programs provide schools with sufficient resources and support to meet the Department’s strategic goals for 21st Century classrooms. The Department should also target additional support to schools to improve planning for ICT resources.  

Most teachers are using ICT in the classroom, however, teacher access to devices outside the classroom varies between schools. In practice, teacher working days extend outside classroom hours. Teachers need access to devices for activities such as lesson preparation and student assessment. With limited access to devices outside of the classroom, teachers may not be able to effectively integrate ICT into lessons. Teachers also require further professional learning to support them to develop their skills in using ICT.  

The Department is not sufficiently monitoring the digital literacy of New South Wales students, which has declined in national tests. Teachers could benefit from support to assess these skills at a school level. The Department also needs to investigate links between student use of ICT and learning outcomes, so they can better support teachers with evidence-based approaches to enhancing learning through ICT.

Old equipment and wireless networks are not keeping pace with modern demands

The Department’s vision for ICT is to enable ‘any learning opportunity, anywhere, anytime’. This vision is at risk due to an ageing stock of devices and wireless networks. The average age of devices in New South Wales schools is over four years. Older devices are less reliable, require greater maintenance and support, and cannot run demanding applications. Further, many school wireless networks are beyond the end of their useful life. This limits the number of teachers and students who can access online content on wireless networks at the same time.

The central funding model for ICT in schools is not meeting current needs

Funding for the Technology for Learning program to deliver ICT in schools has not increased since 2004, despite an increase in the number of students and emphasis placed on ICT in teaching and learning during this time. Schools supplement funding for ICT from their existing school budget and Parents and Citizens Associations.  

The Department’s current funding model for ICT is not adequately addressing a growing gap in the provision of contemporary ICT in classrooms between schools able to access funding from other sources and those which cannot. The Department needs to review whether the Technology for Learning program is equitable in equipping all schools with the modern technology needed to achieve its vision.

Many teachers are not provided with devices for use outside of the classroom

School Principals we interviewed reported that technology is an essential part of a modern classroom and teacher access to devices outside of the classroom can impact how they use ICT. This is because, in practice, teacher working days extend outside classroom hours and teachers need access to devices for activities such as lesson preparation and student assessment. The Department provides teachers with access to a suite of software tools for these tasks.

The Commonwealth Government’s Digital Education Revolution program provided teachers of secondary school students with laptops from 2009 to 2013. The Department’s evaluation of the Digital Education Revolution program found that teachers reported greater confidence with, and use of, ICT throughout the program.  
Providing desktop computers, laptops or tablets for teachers is now a school level decision and arrangements vary across schools. Each school must trade-off between allocating devices for students and teachers. Most other States and Territories provide all teachers with a laptop for use in and outside of the classroom or offer subsidised access to one.  

There is limited teacher professional learning in the use of ICT

The Department’s research has identified that professional learning is an important factor in how effectively teachers use ICT to enhance teaching and learning. Despite this, the Department provides few courses on using ICT in the classroom directly, and most of these are offered in Sydney. This limits accessibility for teachers outside of the metropolitan area. Schools we visited reported that the costs of courses and providing relief teachers limits the number of external courses or events that teachers attend, especially for rural and regional schools. Increasing the use of online learning would improve access for teachers in these areas.  

The Department is not adequately monitoring trends in professional learning in ICT or evaluating the overall effectiveness of courses. A recent upgrade to the professional learning system may provide the Department with better quality data to do this.

Greater monitoring and reporting on technology use in schools is required

The Local Schools, Local Decisions policy gives schools greater authority to make strategic decisions on the use of ICT appropriate to their local contexts. To support this, the Department needs to better monitor current trends, and identify emerging needs to determine future direction and how best to support schools.  

For example, the Department does not currently know how many devices are allocated to teachers or how many schools have implemented a student Bring Your Own Device scheme. This affects how schools are using ICT, and places demand on the network and the type of support the Department must provide. An assessment of the ICT maturity of schools would help the Department target its resources to schools requiring greater assistance with planning.

The Department does not regularly monitor or report on student capabilities with ICT. A national assessment found that the ICT literacy of a sample of Year 6 and Year 10 New South Wales students fell between 2011 and 2014. The fall was greater in New South Wales than in other States and Territories. Without more regular assessment or reporting, the reasons behind this fall and the distribution of student capabilities between schools will remain unknown. 

By July 2018, the Department of Education should:

  1. Review the Technology for Learning program and school ICT support resourcing to determine whether resourcing is adequate for modern school requirements.
     
  2. Develop a program to improve wireless networks in all NSW schools, for instance by expanding the Connecting Country Schools Program to all NSW schools.  
     
  3. Implement an assessment of school ‘ICT maturity’ and use this to target assistance to those schools requiring support with forward planning for ICT.
     
  4. Improve the use of evidence to inform plans and strategies, including:
    • more detailed monitoring of teacher and student access to and use of ICT
    • evaluating the impact of teacher professional learning on student outcomes 
    • further examining the links between ICT and student outcomes.
       
  5. Improve teacher access to devices for use outside of the classroom to improve how effectively they integrate ICT into teaching and learning.
     
  6. Improve teacher professional learning by providing more:
    • online learning opportunities for teachers in regional and remote areas
    • courses focused on pedagogy to make best use of ICT.
       
  7. Identify the ICT skills students need, and provide teaching resources to develop these skills and monitor their achievement.

Appendix One - Response from the Agency

Appendix Two - About the audit

Appendix Three - Performance auditing

 

Parliamentary reference - Report number #289 - released 6 July 2017 

Published

Actions for Mining Rehabilitation Security Deposits

Mining Rehabilitation Security Deposits

Planning
Industry
Environment
Infrastructure
Management and administration
Project management

The Department of Planning and Environment requires mining companies to rehabilitate sites according to conditions set in the mining development approval. The Department holds mining rehabilitation security deposits that are meant to cover the full cost of rehabilitation if a mining company defaults on its rehabilitation obligations.

The total value of security deposits held has increased from $500 million in 2005 to around $2.2 billion in 2016, covering around 450 mine sites in New South Wales.

While there have been substantial increases in total deposits held, mine rehabilitation security deposits are still not likely to be sufficient to cover the full costs of each mine's rehabilitation in the event of a default.

This audit was undertaken when the Department of Industry, Skills and Regional Development was responsible for ensuring land disturbed by mining activities is rehabilitated in accordance with the relevant development approval, including the administration of mining rehabilitation security deposits. On 1 April 2017, this responsibility was transferred to the Department of Planning and Environment (the Department).  

This audit assessed whether the Department maintains adequate security deposits to cover the liabilities associated with mine closures, including rehabilitation. Companies authorised by the Department to undertake mining activities must provide a security deposit to cover the full costs of rehabilitation in the event of default by the company. Rehabilitation is the treatment of disturbed land or water to establish a safe, stable, non-polluting and sustainable environment.

Mining companies must provide an estimate of rehabilitation costs for each site. The Department provides a Rehabilitation Cost Calculation tool to assist companies calculate the deposit amount. Companies are also required to ensure that the cost estimate is in accordance with the approved Mining Operations Plan (MOP). The MOP is intended to be a mine rehabilitation and closure plan, and forms the basis for the estimation of the security deposit. The Department reviews the estimates and determines the deposit for each site.  

Security deposits are an option of last resort. The Department has other legislative and regulatory tools which it normally uses to promote compliance with rehabilitation requirements before accessing a security deposit. It can direct action by the mining company, issue fines and even have the Minister revoke a mining lease. To date, the Department has never had to access a security deposit for a state significant development mine site.

Conclusion

The Department holds security deposits for mining rehabilitation consistent with the amounts it has requested from mining companies, and it should be able to claim on a deposit if a mining company defaults on its rehabilitation obligations. The total value of deposits has increased from $500 million in 2005 to around $2.2 billion in 2016, covering around 450 mine sites. The Department’s management of the security deposit process has improved in recent years, and it has well advanced plans for further improvement, including a revised cost calculation tool.

The Department’s policy is that each mine’s security deposit should cover the full costs of rehabilitation for that mine. The security deposits the Department holds are not likely to be sufficient to cover the full costs of each mine’s rehabilitation in the event of a default. The rates and allowances in the current cost calculation tool have not been updated since 2013 and some activities required for effective rehabilitation are not covered, or not covered adequately.

Security deposits also do not include sufficient contingency given the substantial risks and uncertainties associated with mine rehabilitation and closure, particularly in the absence of a detailed closure plan. This risk is exacerbated by the limited independent verification of mining company claims about the size of the outstanding rehabilitation task, which remains the case despite recent improvements to monitoring and review procedures and practices.  

There is also no financial assurance held over the risk of significant unexpected environmental degradation in the long-term after a mine is deemed to be rehabilitated and the security deposit is returned. A security deposit is not an appropriate vehicle for covering this risk.

Security deposits are close to calculated value and should be accessible if needed

The value of securities held by the Department aligns with the latest approved rehabilitation cost estimates. This contrasts with the situation found by investigations in Victoria and Queensland, where deposit amounts held fell below the calculated costs.

The security deposits are usually in the form of a bank guarantee or cash. The Department has obtained legal advice indicating that it should be able to claim on these bank guarantees if the need arises. As the guarantee is between the financial institution and the Department, if a mining company goes into liquidation the Department should still be able to access the funds.  

When the latest estimate of rehabilitation costs is higher than the existing deposit, the Department will request additional security. It has experienced extensive delays in obtaining additional security for some sites, increasing the risk that available funds will be insufficient if needed.

Rehabilitation cost estimates are not yet adequate, but improvements are planned

The Department’s policy is for security deposits to cover the full cost of rehabilitation. No discounts are provided to mining companies for past good behaviour or low likelihood of default, unlike in some other states. Discounting could undermine the policy position.  

Current security deposits are unlikely to cover the full cost of rehabilitation on each mine site. The Department provides a rehabilitation cost calculation tool to help mining companies calculate the cost of rehabilitation and the required deposit amount, but:

  • several activities required to effect closure are not included and others underestimated
  • it does not make provision for industry cost changes over time
  • the rates used in the tool have not been updated since 2013
  • it was not able to provide the basis for the rates and allowances in the tool.

The Department reviews cost estimates provided by mining companies, but its verification of the extent of rehabilitation work on which these estimates are based is limited. It relies instead on section 387C of the Mining Act 1992 which makes it an offence for mining companies to provide false or misleading information. It is not evident how the Department would establish that information provided was false or misleading without more verification work, and six of the 14 cost estimates we reviewed were not signed by the mine manager, making enforcement more difficult.  

The Department has developed a new calculation tool, and recently released it for industry consultation. The new tool should improve rehabilitation estimates. It updates rates and allowances, and includes additional items to better cover required rehabilitation tasks. While a substantial improvement, the new tool could be further improved by providing additional coverage for stakeholder engagement, additional planning approvals, insurance costs, and any additional design, research and verification work required for successful closure.

There is no financial assurance over long-term environmental risks

The Department does not hold any financial assurance to cover the costs associated with mitigating any future environmental degradation once a mine closes and the security deposit is relinquished to the mining company. Security deposits are probably not the appropriate mechanism to cover these long-term risks but the risk of potential post-closure environmental degradation still needs to be costed and covered. A fund to cover the state-wide risk, to which all mines would contribute, is a possible mechanism.

Rehabilitation and closure outcomes are vague, particularly for unplanned closure

Rehabilitation outcomes in the MOPs we reviewed were generally not specific. Any lack of specificity in MOPs translates into uncertainty about rehabilitation work required if a mining company defaults. Part of the problem is that rehabilitation outcomes established in planning approvals are usually not specific and may not address all closure requirements. The Department has recognised there is scope to improve the clarity and specificity of rehabilitation requirements in planning approvals, and has started a review focusing on open-cut mines.

Rehabilitation outcomes are even less specific in the event of an unexpected early closure because they will probably be different from that achievable from a planned closure.  

MOP guidelines do not cover management of some key closure matters, such as the requirements of environment protection licences issued by the Environment Protection Authority and the management of heritage sites during closure.

There were significant variations in quality of MOPs we reviewed and the way closure risks and uncertainties were identified and addressed. The Department plans to improve the quality of rehabilitation programs through enhanced guidance and oversight.

Monitoring is not adequate to effectively gauge rehabilitation progress

The Department was not able to show it has been monitoring operational mine sites effectively to gauge the progress of ongoing site rehabilitation and the management of closure risks. There was no protocol for site inspections and limited evidence of inspections for the sites we reviewed.

The Department receives annual environmental management reports from mining companies, with most describing the areas of disturbance and rehabilitation occurring at each mine site. The Department recently established procedures for reviewing these annual reports, and has developed a risk-based process for prioritising reviews.

Most annual reports we reviewed did not explain environmental changes over time, nor the risks to mine closure and the measures required to mitigate them. For example, analysis of changes to surface water and groundwater quality was limited despite its relevance for assessing future contamination risks.

The Department does not currently have adequate processes in place to effectively verify the reported areas of disturbance and rehabilitation. It is developing geographic information system-based tools to better measure areas of disturbance and rehabilitation, new rehabilitation guidelines, and a procedure for determining whether rehabilitation has been successful. These initiatives should improve the monitoring and reporting of rehabilitation progress at mine sites.

There is no mechanism to prevent a mine being in ‘care and maintenance’ indefinitely

The Department does not have a clear policy on the length of time and circumstances under which a mine can remain in ‘care and maintenance’. Indefinite postponement of rehabilitation and closure is therefore possible. 'Care and maintenance' is the period following temporary cessation of operations when infrastructure remains largely intact and the site continues to be managed. There are a range of valid reasons for a mining company to put a mine in ‘care and maintenance’, but it is also reasonable for the community to expect a limit to how long it has to wait for proper rehabilitation.

Mining operations make a significant contribution to the NSW economy, including over $1.3 billion in royalties each year. Around 400 mine sites throughout NSW provide over 40,000 jobs and are a major source of economic activity for many communities. Despite these benefits, it is important to ensure that mining companies fulfil their obligations to rehabilitate land disturbed as a result of mining activity.

We recommend that the Department should, by January 2018:

1. Improve the quality of rehabilitation and closure plans by:

  • ensuring plans submitted by mining companies include robust mine rehabilitation and closure risk assessments
  • clarifying the level of detail required in plans at each stage of a mine’s operation
  • specifying how requirements set under other legislative instruments (e.g. environment protection licences, heritage assets) should be addressed.

2. Improve assurance that security deposits are sufficient by:

  • ensuring its new cost calculation tool adequately covers all works needed for rehabilitation and closure
  • increasing the contingency for uncertainties associated with mine rehabilitation and closure, at least until the mining company provides a detailed closure plan
  • verifying the cost estimates for a sample of high risk sites annually
  • ensuring that when mining companies are required to provide increased security deposits, they do so with minimal delay.

3. Enhance oversight of mine rehabilitation by:

  • developing a protocol to ensure sufficient and adequate site inspections
  • ensuring mining companies report performance against rehabilitation targets and environmental changes clearly, including an analysis of long-term surface water and groundwater trends in terms of levels, flow and quality
  • improving how it determines the progress and success of mine rehabilitation
  • developing clear policy and procedures for ensuring a mine cannot be put into ‘care and maintenance’ indefinitely.

4. Collaborate with relevant agencies to establish a financial assurance mechanism, such as a sinking fund, to cover the risk of long-term environmental degradation after mines are closed and security deposits returned.

Appendix One - Response from the Department

Appendix Two - About the audit

 

Parliamentary reference - Report number #285 - released 11 May 2017