Reports
Actions for Report on Education 2017
Report on Education 2017
The Auditor-General, Margaret Crawford released her report on the results of the financial audits of agencies in the Education cluster. The report focuses on key observations and findings from the most recent audits of these agencies.
'I am pleased to report that unqualified audit opinions were issued on the financial statements for all agencies in the Education cluster', the Auditor-General said. 'The quality and timeliness of financial reporting remains strong'.
Actions for Managing demand for ambulance services 2017
Managing demand for ambulance services 2017
NSW Ambulance has introduced several initiatives over the past decade to better manage the number of unnecessary ambulance responses and transports to hospital emergency departments. However, there is no overall strategy to guide the development of these initiatives nor do NSW Ambulance's data systems properly monitor their impact. As a result, the Audit Office was unable to assess whether NSW Ambulance's approach to managing demand is improving the efficiency of ambulance services.
NSW Ambulance uses a telephone referral system to manage triple zero calls from people with medical issues that do not require an ambulance. This has the potential to achieve efficiency improvements but there are weaknesses in NSW Ambulance's use and monitoring of this system. Paramedics are now able to make decisions about whether patients need transport to a hospital emergency department. NSW Ambulance does not routinely measure or monitor the decisions paramedics make, so it does not know whether these decisions are improving efficiency. Extended Care Paramedics who have additional skills in diagnosing and treating patients with less urgent medical issues were introduced in 2007. NSW Ambulance analysis indicates that these paramedics have the potential to improve efficiency, but have not been used as effectively as possible.
Our 2013 audit of NSW Ambulance found that accurate monitoring of activity and performance was not being conducted. More than four years later, this remains the case.
NSW Ambulance has recognised the need to change the way it manages demand and has developed initiatives that have the potential to improve efficiency. However, there are significant weaknesses in the strategy for and implementation of its demand management initiatives.
NSW Ambulance has identified the goal of moving from an emergency transport provider to a mobile health service and developed several initiatives to support this. Its demand management initiatives have the potential to contribute to the broader policy directions for the health system in New South Wales. However, there is no clear overall strategy guiding these initiatives and their implementation has been poor.
NSW Ambulance's reasons for changing its approach to demand management have not been communicated proactively to the community. Demand management initiatives that have been operating for over a decade still do not have clear performance measures or targets. Project management of new initiatives has been inadequate, with insufficient organisational resources to oversee them and inadequate engagement with other healthcare providers.
NSW Ambulance uses an in-house Vocational Education and Training course to recruit some paramedics, as well as recruiting paramedics who have completed a university degree. No other Australian ambulance services continue to provide their own Vocational Education and Training qualifications. Paramedics will need more support in several key areas to be able to fulfil their expanded roles in providing a mobile health service. Performance and development systems for paramedics are not used effectively. Up to date technology would help paramedics make better decisions and improve NSW Ambulance's ability to monitor demand management activity.
There are gaps in NSW Ambulance's oversight of the risks of some of the initiatives it has introduced, particularly its lack of information on the outcomes for patients who are not transported to hospital. Weaknesses in the way NSW Ambulance uses its data limit its ability to properly assess the risks of the demand management initiatives it has introduced.
Parliamentary reference - Report number #295 - released 13 December 2017
Actions for Health 2017
Health 2017
The following report highlights results of the financial audits of entities in the NSW health cluster. The report focuses on key observations and findings from the most recent audits of these entities.
The report also includes a range of findings on service delivery. Overall, NSW Health is achieving most of their targets. Some local health districts are continuing to experience increased demand for their services and are finding it more difficult to meet their targets. For example, three local health districts had not achieved some emergency department response time targets for three consecutive years.
1. Financial reporting and controls
Financial Reporting |
All health cluster entities received unqualified audit opinions and the quality of financial reporting remains high across the cluster. Early close procedures were largely completed and all financial statements were submitted by the deadlines. |
Financial performance |
Overall, NSW Health recorded an operating surplus of $407 million in 2016–17. Eleven local health districts/specialty networks recorded operating deficits in 2016–17, four more than 2015–16. Expenses across NSW Health increased by 4.4 per cent in 2016–17 (6.0 per cent in 2015–16), lower than the expected long term annual expense growth rate. |
Excess annual leave | Managing excess annual leave is a continual challenge for NSW Health, with thirty–five per cent of the workforce having excess balances. |
Overtime payments | NSW Health entities are generally managing overtime well; however NSW Ambulance’s overtime payments, $74.6 million in 2016–17, remain significantly higher than other health entities. |
Time and leave recording practices | Unapproved employee timesheets continue to be a problem for health entities. Weak timesheet approval controls increase the risk of staff claiming and being paid for hours they have not worked. There is also an increased risk of high volumes of roster adjustments, manual pays, salary overpayments and leave not being recorded accurately. |
2. Service Delivery
Service Agreements | Most of the service agreements between the Secretary of NSW Health and health entities were signed earlier than prior years. |
Performance monitoring | Five NSW Health entities are not meeting the Ministry of Health’s performance expectations at 30 June 2017. |
Emergency department performance | Data provided by the Ministry indicates NSW Health, on average, met emergency department triage response time targets across all triage categories for the fourth consecutive year. |
Ambulance response times | Data provided by the Ministry shows NSW Ambulance response times for imminently life‑threatening incidents of 7.5 minutes in 2016–17 was within the Ministry’s target of 10.0 minutes. Data provided by the Ministry indicates NSW Ambulance response times for potentially life‑threatening incidents did not improve in 2016–17. The median response time of 11.1 minutes in 2016–17 was similar to 2015–16 (11.0 minutes). This is despite the number of Priority 1 responses reducing by 4.3 per cent. |
Unplanned hospital re-admissions | Data provided by the Ministry shows eight local health districts achieved the Ministry of Health’s unplanned hospital re‑admissions target in 2016–17. The target is for local health districts to reduce re‑admission rates from the previous financial year. |
This report sets out the results of the 30 June 2017 financial statement audits of Health cluster entities.
The report has been structured into two chapters focusing on:
- Financial reporting and controls
- Service delivery.
This chapter outlines audit observations, conclusions and recommendations related to financial reporting and internal controls of entities for 2016-17.
Observation | Conclusion or recommendation |
2.1 Quality of financial reporting |
|
All cluster entities received unqualified audit opinions and misstatements identified in financial statements fell. | The quality of financial reporting remains high across the cluster. |
2.2 Timeliness of financial reporting |
|
Early close procedures were largely completed and all financial statements were submitted by the deadlines. | Health entities controlled by the Ministry of Health continued submitting their financial statements well ahead of the statutory deadlines. |
2.4 Financial and sustainability analysis |
|
NSW Health recorded an operating surplus of $407 million in 2016–17.
|
The statewide operating surplus was $84 million higher than 2015–16. Net surpluses contribute to NSW Health’s ability to invest in new facilities, upgrades and redevelopments. The 2016–17 financial results were once again impacted by the NSW Government initiative to improve cash management across the sector. |
2.5 Performance against budget | |
Ten local health districts/specialty networks’ expense budget variance was outside performance expectations agreed with the Ministry at the beginning of 2016–17. | The Ministry continues to manage performance across NSW Health to improve the accuracy of budgeting practices. |
2.7 Human Resources | |
Thirty-five per cent of NSW Health’s workforce have excess annual leave balances.
NSW Ambulance had the highest average sick leave rate in NSW Health of 85.2 hours per FTE in 2016–17 (78.7 hours in 2015–16). This was higher than the statewide average of 62.1 hours (62.0 hours in 2015–16).
Unapproved employee timesheets continue to be a problem for health entities. Weak timesheet approval controls increase the risk of staff claiming and being paid for hours they have not worked.
|
Managing excess annual leave is a continual challenge for health entities.
Recommendation: NSW Ambulance should further review the effectiveness of its rostering practices to identify strategies to reduce excessive overtime payments. Recommendation: Health entities should conduct a risk‑based review of time and leave recording practices to ensure control weaknesses are identified and fixed. |
This chapter outlines our audit observations, conclusions and recommendations relating to service delivery for 2016–17.
Observation | Conclusion or recommendation |
3.1 Service agreements in NSW Health | |
Most of the service agreements between the Secretary of NSW Health and health entities were signed earlier than prior years. Thirteen local health districts/specialty networks signed their service agreements by the 31 July 2017 due date. This is a significant improvement with only seven local health districts/specialty networks meeting the date in 2015–16. |
Having service agreements signed as close as possible to the start of each year provides the Ministry and NSW Health entities with clarity around roles, responsibilities, performance measures, budgets, and service volumes and levels. |
3.2 Performance of NSW Health entities | |
Five NSW Health entities were not meeting the Ministry’s performance expectations at 30 June 2017. | The Ministry is managing the five entities in accordance with its performance review process. |
3.4 Emergency department response times | |
Data provided by the Ministry indicates NSW Health again, on average, met emergency department triage response time targets across all triage categories for the fourth consecutive year. The Ministry manages performance across NSW Health to ensure patients presenting at emergency departments receive care in a clinically appropriate timeframe. |
Based on the Ministry’s data, local health districts/specialty networks are, on average, meeting triage targets despite increasing emergency department attendances. The data shows eleven local health districts met all triage targets in 2016–17, compared to eight in |
3.5 Emergency treatment performance | |
The Ministry manages public patient access to emergency services in public hospitals. It has an emergency treatment performance target of 81 per cent of patients leaving emergency departments within four hours. |
Data provided by the Ministry indicates NSW Health maintained its overall emergency treatment performance in 2016–17, but did not achieve its target. The State average emergency treatment performance was 74.2 per cent (74.2 per cent in 2015–16). Based on the Ministry’s data, only four local health districts achieved the target in 2016–17, five in |
3.6 Ambulance response times | |
NSW Ambulance has a response time target of 10.0 minutes for imminently life‑threatening incidents in New South Wales. | Data provided by the Ministry indicates NSW Ambulance response times for imminently life-threatening incidents of 7.5 minutes in 2016–17 was within the Ministry’s target. |
3.7 Transfer of care | |
The Ministry has a target of 90 per cent for the number of ambulance arrivals within a 30 minute ‘transfer of care’ timeframe. | Data provided by the Ministry indicates the rate of ambulance arrivals within a 30 minute 'transfer of care' timeframe improved from 87.6 per cent in 2015–16 to 91.7 per cent in 2016–17, exceeding the Ministry’s target. |
3.8 Average length of stay in hospital | |
Based on the Ministry’s 2016–17 data, the average length of stay for acute episodes was 3.0 days. The average length of stay in New South Wales hospitals is lower than the national average of 3.2 days (in 2015–16). | The Ministry’s data shows the average length of stay by patients for acute episodes has remained stable in New South Wales hospitals for four years. |
3.9 Elective surgery access performance | |
Data provided by the Ministry indicates NSW Health continues to manage waiting times for elective surgery in public hospitals. | The Ministry’s data shows NSW Health improved on‑time admission of patients for elective surgery in 2016–17 despite a 1.8 per cent increase in admissions. While the result improved, only one of the three targets for elective surgery waiting times was met in 2016–17. |
3.10 Unplanned hospital re-admissions | |
Data provided by the Ministry indicates NSW Health, on average, did not reduce the rate of unplanned hospital re‑admissions in 2016–17. The Ministry has a target of reducing unplanned hospital re‑admissions compared to the previous financial year. Low re‑admission rates may indicate good patient management practices and post-discharge care. |
The Ministry’s data shows eight local health district met the target to reduce the rate of re‑admissions compared to the previous financial year. The statewide average rate increased from 6.3 per cent to 6.4 per cent. |
3.11 Post discharge care for acute mental health patients | |
NSW Health has a goal to increase community-based care to acute mental health patients after they are discharged. Continuity of care in the community can lead to reduced symptom severity, lower re‑admission rates, and improved quality of life. | The Ministry’s 2016–17 data shows the statewide average for post discharge follow-up of acute mental health patients within seven days was 70.0 per cent (66.0 per cent in 2015–16). The statewide average improved and met the NSW Health target of 70 per cent. Nine local health districts exceeded the NSW Health target. |
3.12 Mental health acute re-admissions | |
NSW Health has a goal to reduce acute public sector mental health re-admissions. High re‑admission rates may indicate deficiencies in inpatient treatment and follow up care. | The Ministry’s data shows twelve local health districts did not achieve the NSW Health target of 13 per cent mental health acute re‑admissions in 2016–17. |
3.13 Unplanned and emergency re‑presentations | |
NSW Health aims to reduce the number of unplanned and emergency re‑presentations to emergency departments. The Ministry’s 2016–17 data shows the State average of emergency department re‑presentations decreased marginally from 5.0 per cent in 2015–16 to 4.9 per cent. |
Patients attending rural emergency departments are more likely to re‑present within 48 hours of being discharged than those in regional or metropolitan emergency departments. |
3.14 Healthcare associated infection | |
The national target for the rate of Staphylococcus aureus (golden staph) bloodstream infection is two cases per 10,000 bed days. | Data provided by the Ministry indicates the rate of golden staph bloodstream infection in New South Wales hospitals continues to be well below the target and national benchmark at 0.72 cases per 10,000 bed days in 2016–17 (0.75 in 2015–16). |
3.15 Patient experience and satisfaction | |
The Bureau of Health Information analyses and reports on the results of patient surveys. The Bureau’s survey shows 65 per cent of adult admitted patients rated the care they received in hospital as ‘very good’ and 29 per cent rated it as ‘good’. |
NSW Health recognises that patient surveys are an important feedback mechanism on the health care system that can only come from personal experiences. |
Actions for Sharing school and community facilities
Sharing school and community facilities
Schools and the community would benefit if school facilities were shared more often.
The Department of Education’s ‘Community Use of School Facilities Policy’ encourages but does not require schools to share facilities. Sharing depends heavily on the willingness of school principals and there are few incentives. There are many challenges in developing agreements with community users and there is only limited support available from the Department.
There are strategies and plans to support the sharing of facilities between schools and the wider community, but none are backed up with budgets, specific plans or timeframes.
Governments should strive for the best use of assets. This is particularly important in the context of a growing New South Wales population, fiscal constraints and increasing demand for services.
Lack of available land, rising land costs and population growth highlighted in our April 2017 'Planning for school infrastructure' performance audit report mean that new and existing schools will need to share their facilities with communities more than is currently the case.
This audit assessed how effectively schools share facilities with each other, local councils and community groups. In making this assessment, the audit examined whether the Department of Education (Department):
- has a clear policy to encourage and support facilities sharing
- is implementing evidence-based strategies and procedures for facilities sharing
- can show it is realising an increasing proportion of sharing opportunities.
Facilities sharing is the use of a physical asset, such as a building, rooms, or open spaces, by more than one group for a range of activities at the same time or at different times. For the purposes of this audit, we have divided sharing arrangements into two types: shared use and joint use.
Shared use refers to arrangements where existing school assets are hired out for non-school purposes, usually for a limited time. The assets remain under the control of the school. Generally, there is little alteration or enhancement to the asset required to enable shared use. Shared use can also refer to schools using external facilities, such as council pools, but these arrangements are not included within the scope of this audit.
Joint use refers to arrangements where new or upgraded school and non-school facilities or community hubs are planned, funded, built and jointly shared between a school and other parties, usually involving significant investment.
Both shared use and joint use agreements are governed by contractual obligations.
The sharing of school facilities with the community is not fully effective. The Department of Education is implementing strategies to increase shared and joint use but several barriers, some outside the Department’s direct control, must be addressed to fully realise benefits to students and the community of sharing school facilities. In addition, the Department needs to do more to encourage individual schools to share facilities with the community.
A collaborative, multi-agency approach is needed to overcome barriers to the joint use of facilities, otherwise, the Department may need significantly more funds than planned to deliver sufficient fit-for-purpose school facilities where and when needed.
Since the early 2000’s, several reviews in NSW and other jurisdictions have commented on the benefits of and need to increase the sharing of school facilities.
Several NSW Government strategies and plans support shared and joint use of facilities between schools and the wider community, but none are backed up with financial incentives, or specific plans with implementation timeframes. In Victoria and Queensland whole-of-government processes are in place to support a more coordinated approach to planning, building and sharing community facilities. For example, Victoria has a comprehensive policy framework encompassing both existing and future use of community facilities and a $50 million program to seed the development of community facilities on school sites over the next four years.
There are examples of successful shared use, but more can be done. Information about the available facilities is not readily available to potential community users. Schools should work more closely with councils and other stakeholders to leverage shared use.
Currently, the administrative burden, costs and risks associated with shared use can exceed the perceived benefits to schools, leading to reluctance amongst some Principals to share. In addition, a substantial backlog of school-initiated infrastructure proposals awaiting Departmental approval means that schools that raise money from sharing their facilities find it difficult to use the funds they raise on improved infrastructure. Some of these proposals have been waiting for approval for more than 12 months.
The Department could do more to support Principals by ensuring the fees charged for facilities cover the costs incurred by schools, that Principals can access help with negotiating and managing contracts, and that infrastructure proposals initiated and funded by schools are approved in a timely manner.
The Department is not monitoring shared use across the State, and does not evaluate different approaches as evidence to influence policies and procedures.
Recommendations
By December, 2018, the Department should:
- increase incentives and reduce impediments for school Principals to share school facilities, including:
- review the methodology for calculating fees charged for facilities to ensure that shared use of school facilities does not result in a financial burden to schools or the Department
- improve support provided to Principals by School Infrastructure NSW, including reducing the backlog of school-initiated infrastructure proposals awaiting approval
- develop service standards, including timeframes, for assessing and approving school-initiated infrastructure proposals.
- provide readily-accessible information about available school facilities to community groups and local councils
- implement processes to monitor and regularly evaluate the implementation of the shared use policy and promote better practice to drive improvements.
As discussed in our 2017 audit report on ‘Planning for school infrastructure’, joint use agreements are a key direction of the School Assets Strategic Plan. Joint use of school facilities will be necessary to ensure that there will be enough fit-for-purpose learning spaces for students when and where needed. Under the ‘Community Use of School Facilities Policy’ Principals play the leading role in identifying opportunities, and developing and managing agreements for sharing school facilities. This is impractical for joint use projects which involve substantial investment in new or refurbished assets, in particular for joint use projects in schools that are yet to be built. In addition, the policy does not address joint-use facilities built on land not owned by the Department. For these reasons, the Department is developing a new policy.
The Department is planning to develop joint use agreements in a more systematic way as part of school community planning, previously known as cluster planning, with a special focus on local councils. Several agreements are currently being piloted, and will be evaluated to provide an evidence-based foundation for this new approach.
To develop or refurbish school facilities for joint use, the Department, councils and other key stakeholders must work together and prioritise joint use from the earliest stages of any project. A collaborative, multi-agency approach is needed to ensure sufficient fit-for-purpose facilities are available for school students within the funding framework proposed in the School Assets Strategic Plan.
To increase shared and joint use, the Department is recruiting specialist staff in its Asset Division to assist with the brokerage, community engagement and development of agreements, but these staff are not dedicated to joint use projects and their available time may not be sufficient to provide the necessary support in the timeframes required.
Recommendations
By December, 2018, the Department of Education should:
- ensure that the implementation of the new ‘Joint Use of School Facilities and Land Policy’ is adequately resourced, and has the support of Principals
- implement processes to monitor and regularly evaluate the implementation of joint use policy and promote better practice to drive improvements.
Appendix one - Response from agency
Appendix two - About the audit
Appendix three - Victoria's 30-Year Infrastructure Strategy
Appendix four - Not-for-profit hire changes
Appendix five - Performance Auditing
Parliamentary reference - Report number #293 - released 1 November 2017
Actions for State Finances 2017
State Finances 2017
Total State Sector Accounts received an unqualified audit opinion for the fifth consecutive year.
There was a $5.7 billion State budget surplus and continued investment in new infrastructure, in part funded by the long-term leases of Ausgrid and Endeavour Energy assets. This report also comments on key accounting matters, including the correction of some previously reported balances and the first time reporting of combined Cabinet members’ compensation in the Total State Sector Accounts.
Pursuant to the Public Finance and Audit Act 1983, I present my Report on State Finances 2017.
You will note that the format of this report has changed from previous years.
The intent of this change is to draw attention to the key matters that have been the focus of our audit and highlight significant factors that have contributed to the outcome.
First, it is pleasing to report once again that I issued a clear audit opinion on the State’s consolidated financial statements. This outcome demonstrates the Government’s continued focus on the quality of financial reporting across the NSW public sector.
High quality financial management and reporting are crucial to properly inform the public and build community confidence in our system of government.
The Treasury’s Financial Management Transformation program also aims to improve financial governance, budgeting and reporting arrangements across the sector. My Office is working collaboratively with The Treasury on reforms to reduce the burden of reporting, without weakening established safeguards.
The reforms should include measures to provide independent assurance of the budget process, of outcome reporting by agencies, and the power to “follow the dollar” given the increasing use of non-government organisations to deliver Government programs.
This Report also highlights another year of strong financial performance. The State’s budget result was a $5.7 billion surplus, and investment in new infrastructure has continued, in part funded by the long-term leases of Ausgrid and Endeavour Energy assets.
Finally, could I take this opportunity to thank the staff of The Treasury for the way they approached this audit. Our partnership is critical to ensuring NSW is an exemplar of quality financial management and reporting.
Margaret Crawford
24 October 2017
A clear audit opinion on the State’s consolidated financial statements was issued.
Timely and accurate financial reporting is essential for informed decision making, effective management of public funds and enhancing public accountability.
This year’s clear audit opinion reflects the Government’s continued efforts to improve the quality of financial reporting across the NSW public sector.
Since the introduction of ‘early close procedures’ in 2011-12, the number of significant errors in financial statements of agencies has generally fallen largely due to identifying and resolving complex accounting issues early. Agencies’ 2016-17 financial statements submitted for audit contained nine errors exceeding $20 million. All errors were subsequently corrected in the individual agencies financial statements.
Agencies should continue to respond to key accounting issues as soon as they are identified. Where issues are identified, accounting position papers should be prepared for consideration by the Audit Office, their Audit and Risk Committee members, and when relevant, The Treasury.
The State addressed the following key accounting matters during 2016-17.
The State recognised rail tunnels and earthworks valued at $8.5 billion.
Some rail tunnels and earthworks have never been valued by the State. These include the City Circle, the country rail network and other tunnels and earthworks built before the year 2000. Some of these tunnels and earthworks date back to the early 1900s.
For many years, the State did not account for these assets as they believed that their value could not be reliably measured. This year an independent valuer was engaged to perform a comprehensive valuation. The methodology used demonstrated
that the assets could have been reflected in the financial statements earlier.
The State recorded an additional $8.5 billion to correct the value of infrastructure assets at 1 July 2016.
Cabinet member’s compensation and related party transactions were reviewed.
Due to changes in Accounting Standards, the State had to consider 'related party information' in the financial statements. Previously this only applied to for-profit entities.
This year, requirements to report related party information extended to members of Cabinet, considered to be “key management personnel” of the State, as defined by Accounting Standards.
The Treasury implemented a process to assess and report Cabinet member’s compensation, and transactions between Cabinet members and/or their close family members, and government agencies.
Collectively, Cabinet members’ remuneration was $8.8 million, which was mainly salaries and allowances, and $3.5 million of non-monetary benefits such as security and drivers. The Treasury determined there were no other specific “related party” transactions or balances that required disclosure in the State’s financial statements.
Information system limitations continue at TAFE NSW.
TAFE NSW has experienced ongoing issues with its student administration system.
TAFE NSW has again implemented additional processes to verify the accuracy and completeness of revenue from sales of goods and services.
TAFE NSW expects to spend up to $89 million on a new information system to address these issues. Modules of the new student enrolment system are expected to be in place for the 2018 enrolment period.
Restatements relating to the General Government Sector's investment in the commercial sector.
The State corrected two previously reported balances relating to the General Government Sector’s investment in the commercial sector.
Accounting Standards require the General Government Sector to effectively store gains or losses related to its investment in the commercial sector in reserves until the investment is derecognised.
When these investments are disposed of, the cumulative gains and losses must be cleared and recognised in the operating result. However, the Government had previously cleared the cumulative gains and losses directly to Accumulated Funds within equity.
To comply with Accounting Standards, a total of $6 billion previously reported as a movement in equity at 30 June 2016, has now been corrected to the operating result.
In addition, Accounting Standards only allow gains or losses on its investments to be stored in reserves. In past years, the State recognised all changes in the value of its investment in Available for Sale Reserves, including the capital contributed to establish the State’s investment. In 2016-17, a total of $23.4 billion of contributed capital was corrected to accumulated funds at 1 July 2015.
The State’s budget result was a $5.7 billion surplus, $2.0 billion higher than the budget estimate.
The Total State Sector comprises 310 entities controlled by the NSW Government.
Of the total, the General Government Sector comprises 215 entities that provide goods and services not directly paid for by consumers.
The non-General Government Sector comprises 95 Government businesses that provide goods and services such as water and electricity, or financial services.
A principal measure of a Government’s overall performance is its Net Operating Balance, or Budget Result. The Net Operating Balance reports the difference between the cost of General Government service delivery and the revenue earned to fund these sectors.
The State has recorded budget surpluses and exceeded the original budget result in nine of the last ten years.
The State maintained its AAA credit rating.
The object of the Act is to maintain the AAA credit rating.
NSW’s finances are managed in alignment with the Fiscal Responsibility Act 2012 (the Act).
The Act established the framework for fiscal responsibility and strategy needed to protect the State’s AAA credit rating and service delivery to the people of NSW.
The purpose of maintaining the AAA credit rating is to reduce the cost of, and ensure the broadest access to, borrowings.
A triple-A credit rating also helps maintain business and consumer confidence so economic activity and employment are sustained. The legislation sets out targets and principles for financial management to achieve this.
New South Wales has credit ratings of AAA/Negative from Standard & Poor’s and Aaa/Stable from Moody’s Investors Service.
The fiscal targets for achieving this objective are:
General Government expenditure growth is lower than long term revenue growth.
General Government expenditure growth was 4.2 per cent in 2016-17, below the long-term revenue growth of 5.6 per cent.
Eliminating unfunded superannuation liabilities by 2030.
The Act sets a target of eliminating unfunded defined benefit superannuation liabilities by 2030. The State’s net superannuation liability was $58.6 billion at 30 June 2017 ($71.2 billion at 30 June 2016).
The Government predicts the 2030 target will be achieved. The State’s funding plan is to contribute amounts escalated by five per cent each year so the schemes will be fully funded by 2030. In 2016-17, the State made employer contributions of $1.5 billion, which is largely consistent with contributions over the past five years.
The liability values in the graph below do not reflect the values recorded in the Total State Sector Accounts. For financial reporting purposes, Accounting Standards (AASB 119 Employee Benefits) require the State to discount its superannuation liability using the government bond rate (refer to page 10 of this report).
The relevant government bond rate in the current economic climate is 2.62 per cent.
The State’s target for the unfunded superannuation liability is measured using AASB 1056 Superannuation Entities. This is because it adopts a measurement basis that reflects expected earnings on fund assets, which are currently between 5.9 and 7.4 per cent. Using these rates, the liability is $15.0 billion at 30 June 2017 ($16.1 billion at 30 June 2016). The unfunded liability is $2.4 billion less than when the Act was introduced.
The State’s assets grew by $31.6 billion during 2016-17 to $409 billion.
Valuing the State’s physical assets.
When we audit the financial statements, we focus on areas we consider as higher risk. These areas are often complex, and require the use of estimates and judgements.
The State has $307.2 billion of physical assets measured at fair value in accordance with Australian Accounting Standards. Fair value calculations are inherently complex and sensitive to assumptions and estimates, increasing the risk these assets are incorrectly valued.
In our audits, we assess the reasonableness and appropriateness of assumptions used in valuing physical assets. This includes obtaining an understanding of the valuation methodologies applied and judgements made. We also review the completeness of asset registers, and the mathematical accuracy of valuation models.
Net movements between years includes additions, disposals, depreciation and valuations. This year, valuations of physical assets added $16.2 billion to the State’s assets, comprising:
-
Transport for NSW and Railcorp $8.5 billion
-
New South Wales Land and Housing Corporation $4.8 billion
-
Roads and Maritime Services $930 million
-
Crown Entity $400 million.
The State’s financial assets increased $27.5 billion in 2016-17
The State’s financial assets have increased by 88 per cent over the past four years. In 2016-17, financial assets increased primarily due to proceeds from the sale of government assets and businesses.
The Government implemented reforms to better use the State’s financial assets. A key element was the creation of an Asset and Liability Committee (ALCO) to provide advice on ways to improve balance sheet management.
Since the creation of the ALCO, reforms include:
-
Establishment of the New South Wales Infrastructure Future Fund (NIFF). The net proceeds from the State’s asset recycling program are invested into the NIFF, which is managed by TCorp, with a balance of $14.6 billion by 30 June 2017. Funds raised are invested through the NIFF until the Government requires them for critical infrastructure projects that are part of the Restart NSW and Rebuilding NSW program of works. ALCO and TCorp provide advice on the NIFF’s performance and management
-
Establishment of the Social and Affordable Housing Fund ($1.1 billion at 30 June 2017). ALCO oversees the Fund to ensure an appropriate investment approach that will maintain funding certainty for new social and affordable housing stock
-
Cash and liquidity management reforms to centralise cash previously held by agencies in the Treasury Banking System. This reform is designed to ensure agencies have adequate levels of liquidity but with surplus funds invested centrally for better returns.
The State’s liabilities decreased by $13.1 billion during 2016-17 to $182 billion.
Valuing the State’s liabilities relies on an actuarial assessment.
Nearly half of the State’s liabilities relate to its employees. This includes unfunded superannuation, and employee benefits, such as long service and recreation leave.
Valuation of these obligations is subject to complex estimation techniques and significant judgements. Small changes in assumptions can materially impact the financial statements.
We address the risk associated with auditing these balances:
-
using actuarial specialists
-
testing controls around underlying employee data used in data models, and testing the accuracy of the calculations
-
evaluating assumptions applied in calculating employee entitlements such as the discount rate and the probability of long service leave vesting conditions being met.
The State’s superannuation obligations reduced by $12.6 billion in 2016-17.
The State’s $58.6 billion superannuation liability represents obligations for past and present employees, less the value of assets set aside to meet those obligations. The superannuation liability decreased from $71.2 billion to $58.6 billion, largely due to an increase in the discount rate from 1.99 per cent to 2.62 per cent. This alone reduced the liability by $9.2 billion
The State’s borrowings totalled $70.6 billion at 30 June 2017.
The State’s borrowings totalled $70.6 billion at 30 June 2017, $9.5 billion less than the previous year. This was largely due to the repayment of borrowings when the assets of Ausgrid and Endeavour Energy were leased to the private sector.
TCorp issues bonds to raise funds for NSW Government agencies. The bonds are actively traded in financial markets providing price transparency and liquidity to public sector borrowers and institutional investors. All TCorp bonds are guaranteed by the NSW Government.
The Government manages its debt liabilities through its balance sheet management strategy. The strategy extends to TCorp, which applies an active risk management strategy to the Government’s debt portfolio.
General Government Sector debt is being restructured by replacing shorter-term debt with longer-term debt. This lengthens the portfolio to better match liabilities with the funding requirements of infrastructure assets and reduces refinancing risks. It also allows the Government to take advantage of the low interest rate environment.
The State recorded revenue of $83.5 billion in 2016-17, an increase of $5.3 billion from 2015-16.
The State’s results are underpinned by revenue growth in taxation, fees and fines.
Taxation, fees, fines and other revenue comprises $30.5 billion of taxation ($28.7 billion in 2015-16) and $5.3 billion of fees, fines and other revenue ($4.6 billion).
Tax revenue for the Total State Sector increased by $1.8 billion, or 6.4 per cent compared to 2015-16, primarily due to:
-
one-off business asset sales and lease transactions, including $718 million in transfer duty from the Ausgrid and Endeavour Energy lease transactions
-
$385 million increase in payroll tax from growth in NSW employment and average employee compensation
-
a $426 million increase in land taxes.
Growth in stamp duty is expected to slow over the next 4 years.
General Government Sector stamp duties have increased from $6.2 billion in 2012-13 to $11.5 billion in 2016-17, an annual average growth rate of 16.5 per cent. The Government’s budget forecasts the growth in stamp duties to decline, to an average annual growth rate of 2.6 per cent between 2016-17 and 2020-21.
The State received Commonwealth grants and subsidies of $30.8 billion in 2016-17.
The State received $30.8 billion from the Commonwealth Government in 2016-17, $1.6 billion more than in 2015-16. This was primarily due to transaction based asset recycling grants of $1.0 billion and a $720 million increase in national land transport grants. This increase was offset by a $435 million decrease in General Purpose Grants, which mainly comprises New South Wales’ share of the Goods and Services Tax (GST).
The State spent $79.4 billion in 2016-17 to deliver services to the community, an increase of $3.9 billion from 2015-16.
Overall expenses increased 5.2 per cent from last year. Most of the increase was due to higher employee costs and operating costs.
Total salaries and wages increased by 4.2 per cent from 2015-16.
Total salaries and wages increased to $30 billion from $28.8 billion in 2015-16. The Government wages policy aims to limit the growth in remuneration and other employee costs to no more than 2.5 per cent per annum.
Operating expenses increased by 12.4 per cent from 2015-16.
Within operating expenses, payments for supplies, services and other expenses increased, in part, due to the State:
-
reacquiring mining licenses worth $482 million and additional land remediation costs of $101 million
-
spending more on health including additional drug supplies relating to Hepatitis C.
State spend on transport and communications increased by 68.1 per cent since 2012-13.
While spending on health and education remain the largest functional areas provided by Government, expenditure on transport and communication increased, on average, by 13.9 per cent annually between 2012-13 and 2016-17. This increase reflects the Government’s investment in transport infrastructure such as the Sydney Metro and Westconnex. Over the same period, spending on health increased by $3.9 billion.
Expenditure on fuel and energy has decreased by an average of 44.7 per cent since 2012-13, reflecting the State’s leases of electricity network assets.
In 2011, the Government established Restart NSW to fund high priority infrastructure projects.
Restart NSW projects are primarily funded from the proceeds from the asset recycling program enabling Government to deliver new infrastructure investment.
Restart NSW provides funding for the delivery of Rebuilding NSW, which is the Government’s 10-year plan to invest $20 billion in new infrastructure.
The State finalised long-term leases of Ausgrid and Endeavour Energy assets.
In June 2017, the Government finalised its long-term lease of 50.4 per cent of Endeavour Energy. This transaction follows on from the long-term leases of TransGrid in December 2015 and 50.4 per cent of Ausgrid in December 2016. Net proceeds of $15.0 billion were paid into Restart NSW relating to these transactions.
The Government also finalised an arrangement for the private sector to provide land titling and registry services to the public for 35 years. The State, through Restart NSW, received an upfront payment of $2.6 billion from the new operator.
Restart NSW is funding $29.8 billion of new infrastructure.
The Government has detailed its plan to invest $20 billion into the Rebuilding NSW plan from Restart NSW.
At 30 June 2017, around $2.9 billion has already been spent on Rebuilding NSW projects from Restart NSW, with a further $9 billion included in the budget aggregates. The Government has also earmarked a further $8.1 billion in Restart NSW for future projects.
The most significant project is the Sydney Metro. The Government has committed $7.0 billion from Restart NSW to build a 30-kilometre metro line, linking Sydney Metro Northwest at Chatswood, through new stations in the lower North Shore, the Sydney CBD and southwest to Bankstown. At 30 June 2017, $2.4 billion has been spent on this project from Restart NSW.
Other significant projects funded by Restart NSW include a $1.8 billion contribution to WestConnex and reserved funding of $1 billion towards the State’s Major Stadia Network program.
The Treasury initiated the Financial Management Transformation (FMT) program with the aim of changing and improving financial governance, budgeting and reporting arrangements of the New South Wales public sector.
FMT aims to deliver better outcomes for the people of New South Wales and focuses on transparency and accountability for expenditure, and better value for money.
New Financial Management System
PRIME is the Information Technology (IT) solution component of the FMT program, replacing several historical systems. PRIME will provide both financial and performance information within one IT platform for all agencies in the NSW public sector.
It is expected to give Government more timely information to plan and deliver its policy priorities and the budget.
Independent assurance over the budget process would improve confidence in the reliability of the State’s financial information.
Actions for Planning and evaluating palliative care services in NSW
Planning and evaluating palliative care services in NSW
NSW Health’s approach to planning and evaluating palliative care is not effectively coordinated. There is no overall policy framework for palliative and end-of-life care, nor is there comprehensive monitoring and reporting on services and outcomes.
Parliamentary reference - Report number #291 - released 17 August 2017
Actions for Information and Communication Technologies in schools for teaching and learning
Information and Communication Technologies in schools for teaching and learning
Several factors are reducing effective use of information and communication technology (ICT) in the classroom.
These are primarily:
Parliamentary reference - Report number #289 - released 6 July 2017
Actions for Passenger Rail Punctuality
Passenger Rail Punctuality
Rail agencies are well placed to manage the forecast increase in passengers up to 2019, including joining the Sydney Metro Northwest to the network at Chatswood. Their plans and strategies are evidence-based, and mechanisms to assure effective implementation are sound.
Appendix one - Response from the agencies
Appendix two - Response from Audit Office
Appendix three - About the audit
Appendix four - Accuracy of punctuality measurement
Appendix five - Train and customer punctuality
Parliamentary reference - Report number #281 - released 11 April 2017
Actions for 2016 - An overview
2016 - An overview
This report focuses on key observations and findings from 2016 audits and highlights key areas of focus for financial and performance audits in 2017.
Financial reporting | |
Observation | Conclusion |
Only one qualified audit opinion was issued on the 2015–16 financial statements of NSW public sector agencies, compared to two in 2014–15. | The quality of financial reporting continued to improve across the NSW public sector. |
More 2015–16 financial statements and audit opinions were signed within three months of the year end. | Timely financial reporting was facilitated by more agencies resolving significant accounting issues early, completing asset valuations on time and compiling sufficient evidence to support financial statement balances. |
NSW Treasury’s early close procedures in 2015–16 were again successful in improving the quality and timeliness of financial reporting, largely facilitated by the early resolution of accounting issues. For 2016–17, NSW Treasury has narrowed the scope of mandatory early close procedures. |
The narrowed scope of mandatory early close procedures may diminish the good performance in ensuring the quality and timeliness of financial reporting achieved in recent years. To mitigate this risk, NSW Treasury has mandated that agencies perform non-financial asset valuations and prepare proforma financial statements in their early close procedures. It also encourages them to continue with the good practices embedded in recent years. |
Although most agencies complied with NSW Treasury’s early close asset revaluation procedures we identified areas where they can improve. | Asset revaluations need to commence early enough to ensure all assets are identified and the results are analysed, recorded and reflected accurately in the early close financial statements. |
Number of misstatements | |||||
Year ended 30 June | 2015-16 | 2014-15 | 2013-14 | 2012-13 | 2011-12 |
Total reported misstatements | 298 | 396 | 459 | 661 | 1,077 |
All material misstatements identified by agencies and audit teams were corrected before the financial statements and audit opinions were signed. A material misstatement relates to an incorrect amount, classification, presentation or disclosure in the financial statements that could reasonably be expected to influence the economic decisions of users.
Significant matters reported to the portfolio Minister, Treasurer and Agency Head
In 2015–16, we reported the following significant matters to the portfolio Minister, Treasurer and agency head in our Statutory Audit Reports:
Appropriate financial controls help ensure the efficient and effective use of resources and the implementation and administration of agency policies. They are essential for quality and timely decision making.
In 2015–16, our audit teams made the following key observations on the financial controls of NSW public sector agencies.
Financial controls | |
Observation | Conclusion |
More needs to be done to implement audit recommendations on a timely basis. We found 212 internal control issues identified in previous audits had not been adequately addressed by 30 June 2016. |
Delays in implementing audit recommendations can impact the quality of financial information and the effectiveness of decision making. Agencies need to ensure they have action plans, timeframes and assigned responsibilities to address recommendations in a timely manner. |
Agencies continue to face challenges managing information security. Most information technology issues we identified related to poor IT user administration in areas like password controls and inappropriate access. | Agencies should review the design and effectiveness of information security controls to ensure data is adequately protected. |
We found shared service provider agreements did not always adequately address information security requirements. |
Where agencies use shared service providers they should consider whether the service level arrangements adequately address information security. |
Thirteen of 108 agencies required to attest to having a minimum set of information security controls did not do so in their 2015 annual reports. | The 'NSW Government Digital Information Security Policy' recognises the growing need for effective information security. With cyber security threats continuing to increase as digital services expand we plan to look at cyber security as part of our 2017–18 performance audit program. |
We identified instances where service level agreements with shared service providers were outdated, signed too late or did not exist. | Corporate and shared service arrangements are more effective when service level arrangements are negotiated and signed in time, clearly detail rights and responsibilities and include meaningful KPIs, fee arrangements and dispute resolution processes. |
Internal controls at GovConnect, the private sector provider of transactional and information technology services to many NSW public sector agencies were ineffective in 2015–16. We found mitigating actions taken to manage transition risks from ServiceFirst to GovConnect were ineffective in ensuring effective control over client transactions and data. | The Department of Finance, Services and Innovation should ensure GovConnect addresses the control deficiencies. It should also examine the breakdowns in the transition of the shared service arrangements and apply the learnings to other services being transitioned to the private sector. |
Maintenance backlogs exist in several NSW public sector agencies, including Roads and Maritime Services, Sydney Trains, NSW Health, the Department of Education and the Department of Justice. | To address backlog maintenance it is important for agencies to have asset lifecycle planning strategies that ensure newly built and existing assets are funded and maintained to a desired service level. |