Reports

Published

Actions for Grants administration for disaster relief

Grants administration for disaster relief

Treasury
Finance
Compliance
Fraud
Management and administration
Project management

What the report is about

The report examined whether NSW Treasury, Service NSW and the Department of Customer Service effectively administered grants programs funded under the $750 million Small Business Support Fund, including:

  • $10,000 Small Business Support Grant
  • $3,000 Small Business Recovery Grant.

What we found

The agencies effectively implemented the grants within required timeframes, reflecting the NSW Government’s decision to deliver urgent financial support to small businesses impacted by the COVID-19 pandemic.

NSW Treasury met urgent timeframes to design the grants and Service NSW made timely payments in line with the grants' objectives and eligibility criteria.

Service NSW and the Department of Customer Service strengthened processes to detect and minimise fraud in response to identified external fraud risks, and to investigate suspected fraudulent applications.

Fraud security checks and investigations are ongoing, and the agencies will not know the full extent of fraud across the grants until these processes have been completed.

The agencies regularly monitored and reported on the timeliness of payments to small business applicants but have not yet measured all benefits of the grants programs.

The $10,000 Support Grant and the $3,000 Recovery Grant have provided around $630 million in one off grant payments to eligible small businesses.

What we recommended

NSW Treasury should finalise and implement an evaluation of both grants programs, including obtaining feedback from businesses.

Service NSW should develop a framework that documents expected controls for how it administers grants, including business processes, fraud control and governance and probity requirements.

Service NSW should publish information on all grants programs, including grants distribution and uptake.

The Department of Customer Service should ensure its processes for managing conflicts of interest meets its policy requirements.

Upcoming performance audit

The Audit Office is conducting a further performance audit into grants administration for disaster relief focussing on bushfire grants. This is planned to complete in 2021-22.

Fast facts

Small Business Support Fund
  • $630m Grant payments made to small businesses under two grants administered
  • Over 52,500 Applications received a $10,000 Grant payment
  • Over 23,000 Businesses paid both $10,000 Support Grant and $3,000 Recovery Grant
  • 36,700 Applications received a $3,000 grant payment
Grant program administration
  • 11 Days taken to deliver the $10,000 Small Business Support Grant application website
  • 26 Days taken to deliver the $3,000 Small Business Recovery Grant application website

Further information

Please contact Ian Goodwin, Deputy Auditor-General on 9275 7347 or by email.

The NSW Government responded to the partial shutdown of the NSW economy caused by the COVID-19 pandemic in 2020 by, among other measures, announcing on 3 April 2020 that it would place $750 million into the Small Business Support Fund (the Fund).

Under the Fund, the NSW Government would pay one-off grants of up to $10,000 to small business impacted by the shutdown. The objectives of the $10,000 Small Business Support Grant ($10,000 Support Grant) were to:

  • ease the pressure on small businesses that have been affected by the COVID-19 pandemic
  • support the ongoing operations of small businesses highly impacted by the COVID-19 restrictions
  • deliver cash-flow into small businesses as soon as possible so that small businesses could meet pressing financial needs.

Grant applications were assessed against eligibility criteria that were determined by the NSW Government. The eligibility criteria for the $10,000 Support Grant required an employing small business to demonstrate it was significantly impacted by the COVID-19 pandemic by self-declaring or demonstrating a significant decline of 75 per cent or more in turnover compared to 2019. Documentation requirements were relaxed for small businesses within highly impacted industries.

In June 2020, the NSW Government announced a second round of one-off grants of up to $3,000 to small businesses that were highly impacted by the COVID-19 pandemic ($3,000 Recovery Grant). The objective of the $3,000 Recovery Grant was to help small businesses in 'highly impacted industries' — those directly impacted by the restrictions and closures put in place under the Public Health Orders — to meet the costs of safely reopening or scaling up operations.

The eligibility criteria for the $3,000 Recovery Grant required that a small business be in a highly impacted industry, demonstrate that it was significantly impacted by the COVID-19 pandemic by declaring a significant decline in turnover, and had costs associated with reopening under the 'COVID-Safe' requirements.

NSW Treasury and Service NSW implemented both grants on behalf of the NSW Government. The process of applying for a grant was intended to be quick and easy, with Service NSW using automated assessments and simple online application forms to process applications. Applicants applied for the $10,000 Support Grant through the Service NSW website between 14 April 2020 to 30 June 2020 and applied for the $3,000 Small Business Recovery Grant between 1 July 2020 and 31 August 2020.

At May 2021, around $520 million has been paid to over 52,500 grant applicants under the $10,000 Support Grant and around $109 million had been paid to around 36,700 grant applicants under the $3,000 Recovery Grant.

The Audit Office plans to undertake a performance audit into grants administration for disaster relief focussing on bushfire grants in 2021–22.

This audit assessed whether the grants funded under the $750 million Small Business Support Fund were effectively administered and implemented to provide disaster relief. It addressed the following questions:

  • Were funded grants programs planned, designed and targeted effectively?
  • Were funded grants programs implemented in line with the objectives and criteria and delivery requirements?
  • Have agencies established measures to monitor intended benefits and outcomes?

This audit did not seek to assess the effectiveness of any other grant programs or stimulus measures. It also did not seek to assess the impact of the funding on applicants, or the future prospects of small businesses that received support.

Conclusion

NSW Treasury and Service NSW effectively implemented two grants within required timeframes reflecting the NSW Government's decision to deliver urgent financial support to small businesses impacted by the COVID-19 pandemic in 2020. The $10,000 Support Grant and the $3,000 Recovery Grant have provided around $630 million in one-off grant payments to eligible small businesses.
NSW Treasury met urgent timeframes to design the grants and Service NSW made timely payments in line with the grants' objectives and eligibility criteria.

NSW Treasury met urgent timeframes to provide advice to the NSW Government on the grant design, proposed delivery partner, expected numbers of eligible businesses and the suitability of the proposed grant payment amount within the required timeframes. This was achieved within one day for the $10,000 Support Grant and within four days for the $3,000 Support Grant. In the context of the complex and changing pandemic and economic conditions between March and July 2020, NSW Treasury's advice to government outlined the risk, feasibility, expected demand estimates and assumptions for the grants.

NSW Treasury's demand projections were limited by uncertainty as to the pandemic's economic impact. Estimated demand for the grants was not met, resulting in around $120 million from the Small Business Support Fund remaining unspent.

Service NSW met urgent timeframes to stand-up both grants: 11 days for the $10,000 Support Grant and 26 days for the $3,000 Recovery Grant. It met agreed delivery requirements and made timely payments to small businesses in line with the grants' objectives and eligibility criteria. Over 65,000 businesses have received a payment under either grant, and over 23,000 businesses received both grants.

Gaps in project and risk management processes were expected given the tight timeframe to implement the grants.

The tight timeframe in which the agencies had to implement the grants contributed to gaps in project and risk management. The agencies advised that compromises were understood by both parties and were a necessary trade-off to ensure payments were made quickly.

Service NSW and the Department of Customer Service have acted to strengthen their processes to detect and minimise fraud in response to identified external fraud risks and to investigate suspected fraudulent applications since the grants commenced. Service NSW intends to further enhance fraud controls for grants applications and payments for future grants by implementing a fraud control framework by December 2021.

The agencies regularly monitored and reported on the timeliness of payments to small business applicants but have not yet measured all benefits of the grants programs.

Service NSW and NSW Treasury established processes to monitor and report on the timeliness of payments to grant applicants.

NSW Treasury has not yet measured all intended impacts of the grants, nor undertaken processes to obtain detailed feedback from grant recipients. Without these measures, there is limited insight into the extent to which the grants helped to support small businesses or ability to capture lessons which could be applied in future grants programs. NSW Treasury advises that an evaluation will commence from mid-2021.

1. Key findings

Around $630 million in timely one-off grant payments have been made to small businesses

Service NSW and NSW Treasury have paid around $630 million in one-off grant payments to small businesses via two grants administered under the $750 million Small Business Support Fund. At May 2021:

  • around $520 million has been paid to over 52,500 grant applications received for the $10,000 Small Business Support Grant ($10,000 Support Grant)
  • around $109 million has been paid to 36,700 grant applications received for the $3,000 Small Business Recovery Grant ($3,000 Recovery Grant).

Across both grants, over 65,000 small businesses received a payment across either grant, and over 23,000 businesses received payments under both grants.

NSW Treasury advise that, while no data was collected on the time to pay applicants for the $10,000 Support Grant, from its monitoring of the grants' outputs it was satisfied that payment timeframes met its expectations. Service NSW met its targeted time to pay applicants with payments made within ten days for the $3,000 Recovery Grant.

Funds for both grants were not fully spent due to limitations in data and uncertainty of the COVID-19 pandemic's impact. At May 2021, the final demand for the $10,000 Support Grant was around 30 per cent less than initially anticipated and the final demand for the $3,000 Recovery Grant was around 40 per cent less than initially anticipated.

NSW Treasury developed proposals establishing high level design and delivery expectations within rapid timeframes

NSW Treasury put forward proposals to the NSW Government for the two grants administered under the $750 million Small Business Support Fund. It met rapid timeframes for producing this advice: within one day for the $10,000 Support Grant and within four days for the $3,000 Recovery Grant. NSW Treasury's advice to the NSW Government on how to best target the total funding, eligibility criteria and the feasibility of delivering the grants through Service NSW was based on comparable grants programs – including the $10,000 Small Business Bushfire Support Grant – which at that time were ongoing.

The proposals established, at a high-level, the rationale for the grants, expected financial costs, risks and analysis on budget impacts, and confirmation that Service NSW could deliver the grants applications platform. NSW Treasury's demand projections were uncertain due to limited data in the early stages of the pandemic regarding potential economic impact.

Given the tight timeframes, the proposals did not fully consider all planning and design aspects for both grants. For example, there was minimal identification of the costs and benefits of the programs, and a lack of detailed design and delivery requirements. The proposals outlined that arrangements to finalise the risk management, controls, and auditing plan would be agreed by Service NSW and NSW Treasury before implementation.

In future circumstances where urgent advice on program design is required, NSW Treasury could set clearer expectations for the delivery agency, including fully considering costs, benefits and delivery requirements that could be carried through to project governance and implementation.

Service NSW implemented both grants in line with delivery expectations

Service NSW met urgent timeframes to stand-up both grants: 11 days for the $10,000 Support Grant and 26 days for the $3,000 Recovery Grant. Delivery expectations for each grant were established under a grant project agreement (grant agreement). Service NSW delivered the online application platform, assessment of applications, payments and reporting of the grants' uptake as per the grant agreements.

The urgent timeframes to deliver the grants contributed to gaps in Service NSW's project and risk management processes throughout the lifecycle of both grants. For example, the requirement to meet pressing timeframes for the $10,000 Support Grant launch meant agencies had reduced time to achieve sign-off on key documentation. As a result, important documents and processes – including the grant agreement, risk documentation and key business process and quality assurance processes – were not finalised ahead of launch.

Quality assurance and compliance processes for detecting fraud were not settled until after the conclusion of the applications for the $10,000 Support Grant, and were not completed until late 2020. Some project documents, including risk registers, communication plans and project briefs are still not finalised.

The longer timeframe to develop the $3,000 Recovery Grant meant that agencies were able to build on their understanding of the implementation requirements from the $10,000 Support Grant, and better document these expectations and understanding while ensuring that key documents and sign-offs were in place prior to launch.

Service NSW tightened its risk management and controls in response to evidence of fraudulent applications

In May 2020, Service NSW and the Department of Customer Service (DCS) were alerted to suspected fraudulent activity within grants administered by Service NSW. Initially, Service NSW anticipated that up to $8.8 million of the $10,000 Support Grant was at risk of exposure to fraudulent applications. However, Service NSW reported that, at April 2021, $1.9 million for the $10,000 Support Grant and $254,000 for the $3,000 Recovery Grant from paid applications were at risk of fraud exposure.

Following an internal review of the potential exposure to fraudulent or ineligible applications, Service NSW implemented additional automated security checks on applications, increased manual assessments of grant applications, established a dedicated taskforce for grants administration and engaged a unit within DCS to manage high-risk investigations.

Service NSW and DCS's increased governance and oversight has resulted in an established case management function, increased referrals to law enforcement, prioritised investigations of suspicious applications and the development of a 'Fraud Control Framework' aimed at addressing external fraud risks. Given Service NSW had limited experience in these processes in context of administering grant payments, such actions were an appropriate response.

Security checks and investigations of suspicious applications are ongoing. Service NSW will not know the full extent of fraud across the grants until these processes have been fully completed.

Service NSW and Department of Customer Service can improve how conflicts of interest are managed for future programs

Compliance with agency policies and processes to manage conflicts of interest and financial subdelegations demonstrates that investment decisions are being made by appropriately skilled and experienced staff, allowing agencies to operate efficiently, and reducing the risk of internal fraud.

DCS was unable to produce employee conflicts of interest declarations for the $10,000 Support Grant. Therefore, it is not known how many employees had completed conflicts of interest declarations for this round.

DCS provided information on conflicts of interest declarations for the $3,000 Recovery Grant. Twenty-nine per cent of declarations provided for employees undertaking grant assessments for the $3,000 Recovery Grant were incomplete at March 2021, and a further nine per cent were not finalised even though they indicated a real, potential or perceived conflict.

For future grants programs, ensuring compliance with conflicts of interest policies would help DCS and Service NSW to have greater confidence that conflicts of interest are appropriately identified and managed.

NSW Treasury has not yet measured all benefits or outcomes of the grants

In April 2021, NSW Treasury updated its evaluation plan for the $10,000 Support Grant and $3,000 Recovery Grant in support of an economic evaluation to commence from mid-2021. The updated evaluation plan outlines inputs, activities, and outputs as well as immediate, short term and medium term outcomes for both grants.

The evaluation will consider the extent to which both grants achieved their intended outcomes, and whether the economic benefits exceeded the costs to help inform decisions about the nature and design of any future small business support programs. This will complement, and feed into a broader review of all NSW Government COVID-19 stimulus measures.

Service NSW rapidly developed an approach to administer the grants

Over recent disasters, such as the 2019–20 bushfires and the COVID-19 pandemic, Service NSW has been responsible for administering grant programs on behalf of other government agencies.

Service NSW implemented both grants under its Project Management Framework and under each grant agreement with NSW Treasury as it does not have its own grants administration framework. To address the risks that emerged during delivery, Service NSW developed an approach to standardise and monitor the administration of the grants while they were being implemented.

Service NSW now has an opportunity to establish a grants administration framework, based on the processes, lessons and outcomes captured under the grants administration taskforce and in developing its fraud control framework. Embedding these processes into business as usual for grants administration will enable Service NSW to have a consistent set of expectations for controls, business processes and governance and probity requirements for future grants it implements.

2. Recommendations

By December 2021, NSW Treasury should:

1. finalise and implement an evaluation of the $10,000 Support Grant and $3,000 Recovery Grant, including obtaining direct feedback from businesses on how grant funds achieved the grant objectives.

By December 2021, Service NSW should:

2. develop a grants administration framework, which documents expected controls – including fraud controls – business processes and governance and probity requirements

3. publish information on all grants programs, including grants distribution and uptake.

By December 2021, the Department of Customer Service should:

4. ensure its process for managing conflicts of interest meets policy requirements by:

  • ensuring employees promptly declare any real, potential or perceived conflicts of interest
  • annually producing a list of conflicts of interest for records retention purposes
  • requiring a separate register of conflicts of interest declarations where a grant program is deemed as high risk.

3. Lessons for grants administered within urgent timeframes

The two grants this audit examined were administered within a context of urgent timeframes, and increased complexity and uncertainty about the impact of the COVID-19 pandemic. The following lessons are shared to assist sponsor and delivery agencies in administering future grants where rapid implementation is required.

Sponsor agencies should consider the following lessons:

1. develop an approach to define and measure benefits for rapidly developed programs and projects where a full business case and cost-benefit analysis is not feasible

2. establish common processes and expectations for co-administered grants:

  • periodically assure agencies' capability to deliver grants programs
  • agree and establish risk appetite statements with administering agencies
  • clearly establish expected performance levels and targets under any agreement

3. review the processes and outcomes of rapidly developed programs, capture lessons learned, and apply these in planning and delivering future programs.

Delivery agencies should consider the following lessons:

1. risk management and risk appetite:

  • perform robust assessment procedures to ensure risks associated with delivery of the project are identified
  • ensure the controls implemented adequately address identified risks
  • agree and document the acceptable risk appetite at the outset
  • review risk management processes after the grants are issued when unable to finalise risk management processes ahead of launch

2. grant agreements between NSW public sector agencies:

  • ensure agreements are finalised in a timely manner
  • ensure agreements clearly outline:
    • roles and responsibilities of both parties,
    • changes in scope of services provided
    • fees and charges applicable

3. frameworks for grants administration:

  • ensure that there is a common set of expectations in place to guide grants administration including standard controls and processes for managing risk, capturing lessons learned and reporting on outcomes.

Appendix one – Response from agencies

Appendix two – Summary of other COVID‑19 Stimulus and Support for small businesses in NSW in April 2020

Appendix three – Public Health Orders

Appendix four – Highly impacted industries

Appendix five – About the audit

Appendix six – Performance auditing

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #352 - released (24 June 2021).

 

Published

Actions for Acquisition of 4–6 Grand Avenue, Camellia

Acquisition of 4–6 Grand Avenue, Camellia

Transport
Asset valuation
Compliance
Fraud
Infrastructure
Internal controls and governance
Management and administration
Procurement
Risk

The Auditor-General for New South Wales, Margaret Crawford, has today released a report on Transport for NSW’s (TfNSW) acquisition of 4–6 Grand Avenue in Camellia.

This audit, which was requested on 17 November 2020 by the Hon. Andrew Constance MP, the Minister for Transport and Roads, examined:

  • whether TfNSW conducted an effective process to purchase 4–6 Grand Avenue, Camellia
  • whether TfNSW has effective processes and procedures to identify and acquire property required to deliver the NSW Government’s major infrastructure projects.

The audit found that TfNSW conducted an ineffective process when it purchased 4–6 Grand Avenue, Camellia. The audit also found that TfNSW’s internal policies and procedures to guide the transaction were, and continue to be, insufficient.

The Auditor-General has made seven recommendations to address the issues identified in the report.

On 17 November 2020, the Hon. Andrew Constance MP, the Minister for Transport and Roads, requested this audit under section 27B(3)(c) of the Public Finance and Audit Act 1983.

On 15 June 2016, Transport for New South Wales (TfNSW) acquired 6.3 hectares of land at 4–6 Grand Avenue, Camellia, by agreement from Grand 4 Investments Pty Ltd. Grand 4 Investments was a business entity established by the owners of Billbergia Pty Ltd, a property development and investment company.

TfNSW paid Grand 4 Investments $53.5 million and assumed liability for addressing environmental issues and contamination associated with the site. This took place seven months after the vendor acquired the land as part of a competitive Expression of Interest process, in which TfNSW also participated, for $38.15 million.

TfNSW is the NSW Government agency responsible for most major transport infrastructure projects in New South Wales. TfNSW acquired the Camellia site for use as a stabling and maintenance depot to support the Parramatta Light Rail (PLR) project.

Consistent with the minister’s request, this audit assessed:

  • whether TfNSW conducted an effective process to purchase 4–6 Grand Avenue, Camellia
  • whether TfNSW has effective processes and procedures to identify and acquire property required to deliver the NSW Government’s major infrastructure projects.

In considering the effectiveness of the processes for this purchase, the audit considered:

  • the requirements of the Land Acquisition (Just Terms Compensation) Act 1991 (the Act)
  • the application of sound processes to manage risk to the NSW Government and to achieve value for money
  • the application of disciplines associated with complex procurement, such as probity, in a NSW Government context.
The acquisition of the 4–6 Grand Avenue site in Camellia was consistent with a 2014 feasibility study for the PLR, but occurred before the completion of detailed project planning or an acquisition strategy.

TfNSW made two attempts to acquire the 4–6 Grand Avenue site in Camellia, and was successful on the second attempt. TfNSW recognised the risks associated with early acquisition and had high-level strategies in place should the site not be required.

The specific site had been identified in a feasibility study for the PLR commissioned by TfNSW in 2014 as one of several options in Camellia for a stabling and maintenance depot. However, TfNSW had not done any substantive analysis of the various options to identify a preferred location before the two opportunities to acquire 4–6 Grand Avenue were brought to TfNSW’s attention by the landowners (or their agents). On both occasions, TfNSW chose to actively pursue acquisition in advance of any such analysis.

The acquisition was also not informed by a Property Acquisition Strategy, which TfNSW policy recommends in order to guide the process and manage acquisition specific risks.

In 2015, TfNSW identified that it would require a stabling and maintenance depot in the Camellia area for the Parramatta Light Rail

In 2014, TfNSW commissioned an external engineering consultancy to undertake a feasibility design study for the Parramatta Light Rail - the Parramatta Transport Corridor Strategy Feasibility Design study (herein referred to as ‘the feasibility study’). In early 2015, TfNSW received the feasibility study, which was one of several key sources that informed the development of business cases for the PLR.

The feasibility study recommended that TfNSW should consolidate the maintenance and cleaning operations with overnight stabling facilities on one site. The study noted that the optimal location for any such site would be in close proximity to the proposed network, and noted that the site must have access to road connections to accommodate access for cars and trucks.

The study found that a centrally located stabling and maintenance facility would be required for all routes serving the Parramatta CBD, and that the Camellia industrial area was a preferred location for such a facility. The study noted that the Camellia area was contaminated.

The feasibility study notes that its conclusions were based on assumptions about the light rail system adopted and decisions made by the future operator of the system, who had not yet been selected or appointed.

TfNSW's decision to progress a potential acquisition in 2015 considered the risk that the site may not be required

TfNSW's FIC was responsible for making decisions on funding allocations at a whole of program level within TfNSW. FIC was also responsible for approving ‘high-risk/high-value’ variations to program budgets. Members of the FIC included:

  • Secretary of Transport for NSW
  • Deputy Secretary, Infrastructure and Services
  • Deputy Secretary, Freight, Strategy and Planning
  • Deputy Secretary, Customer Services
  • Deputy Secretary Finance and Investment
  • Deputy Secretary People and Corporate Services.

An April 2015 submission, from the then Deputy Director-General to the agency’s FIC, sought authorisation and funding approval to participate in an Expression of Interest sale process. It noted the risk that the project may not go ahead. The submission advised that:

By acquiring a strategic site now, it reduces the risk of having to pay an improved value or a value that may be subject to rapidly improving land values due to changes in land use and rezoning.

The property can be acquired for the project, held strategically and income generated by leasing the site as hardstand 1 space until the project requires the land for the Parramatta Light Rail project.

If the project does not proceed in the medium to longer term, the property can be sold at a premium to what has been paid today as property fundamentals improve.

This submission acknowledged the risks associated with environmental contamination and proposed that these risks would be managed by negotiating a contract where the remediation and associated expenses would be at the landowner’s cost. 

TfNSW assessed the 4–6 Grand Avenue site as one of several sites in Camellia that was a feasible location for a stabling and maintenance facility

The Departmental feasibility study assessed six potential sites for a stabling and maintenance facility, including 4–6 Grand Avenue, noting strengths and weaknesses of each site. A different site on Grand Avenue was assessed as the ‘base case’ option (1 Grand Avenue). The study’s comments on the 4–6 Grand Avenue site included the following:

With an area of approximately 63,000m2, this site has sufficient space for a depot with the required stabling yard and maintenance facilities. The location allows for good road access and LRT [light rail transit] access would be from Grand Avenue, which may require a road crossing or signalised intersection. The site has been used for general industrial uses; however the land has been cleared and is currently undergoing remediation 2. The site is not affected by flooding based on one in 100-year flood data.

In early 2015, once the opportunity to acquire 4–6 Grand Avenue emerged, TfNSW commissioned a specific feasibility study of the 4–6 Grand Avenue site. The feasibility studies clearly documented the existence of environmental contamination. In April 2015, the report concluded:

Given the limitations of this report and within the parameters that have been set it is concluded that from a spatial and geographic perspective the site at 6 Grand Avenue would be suitable as a stabling and maintenance depot for the Parramatta light rail project. There are few engineering and environmental constraints that would affect the feasibility level analysis of this site and all issues identified, within this desk study, are considered to be resolvable. However this being said there is a significant amount of work necessary to reach the final layout and definition of the stabling and maintenance depot. There are numerous items which require further consideration and conformation; planning approvals could impose restrictions on building heights, noise mitigation measures, light and visual impact requirements all of which can have significant impacts on the spatial requirements of any stabling and maintenance depot. 

The acquisition of 4–6 Grand Avenue was not informed by a Property Acquisition Strategy

For major projects, TfNSW typically requires the project team to complete a Property Acquisition Strategy, which is intended to guide both process as well as specific acquisition issues expected to be faced during the project. The Property Acquisition Strategy is not a mandated document but is a recommended tool to support property acquisition as part of major projects.

TfNSW did not have a Property Acquisition Strategy in place to guide the 2015 Expression of Interest process. On 6 November 2015, the then Project Director for the PLR project emailed the property team, noting a need to develop a Property Acquisition Strategy to close off the scoping design and preliminary business case.

In January 2016, TfNSW developed a draft Property Acquisition Strategy for the Parramatta Light Rail Project, although it was silent on the potential sites for the stabling and maintenance facility.

TfNSW focussed on 4–6 Grand Avenue because it was available and aligned to TfNSW's strategic interests

In early 2015, officials commenced monitoring the market for industrial real estate in the Camellia area and surrounds for possible sites for a stabling and maintenance facility.

In March 2015, then owner of the site, Akzo Nobel Pty Limited released the 4–6 Grand Avenue site through an Expression of Interest process managed by CBRE.

TfNSW’s then Deputy Director-General, Planning, sought approval from FIC to lodge an Expression of Interest up to $30.0 million. Approval was sought on the basis that it would ‘provide certainty for the Parramatta Light Rail project by allowing for a depot site in a suitable location and potentially avoid higher costs or longer timeframes associated with compulsory acquisition following completion of the project’s business case’. FIC approved the request at its meeting on 9 April 2015.

At this time, TfNSW had not conducted any analysis of financial or operational benefits and costs of the potential sites identified in earlier feasibility studies. TfNSW staff advised us that the decision to participate in the Expression of Interest process for 4–6 Grand Avenue was because it was available. There is no documentation substantiating this statement, which TfNSW staff provided verbally as part of this audit.

In November 2015, TfNSW was advised that it was unsuccessful in the Expression of Interest process and that Grand 4 Investments (a related entity of Billbergia) had purchased 4–6 Grand Avenue. TfNSW did not conduct any further analysis of alternative potential sites in Camellia between this date and commencing discussions with Grand 4 Investments in April 2016. In that time there had been some movement on other properties that were included in the feasibility study, including 37–39a Grand Avenue being under offer in September 2015.

In March 2016, TfNSW approached CBRE to organise a meeting with Grand 4 Investments. On 1 April 2016, TfNSW met with Grand 4 Investments.

TfNSW advises that a perceived benefit of the 4–6 Grand Avenue site was that it was not subject to other uses or leaseholds that would increase the cost of compulsory acquisition. Officers involved in the acquisition advised that other nominated sites in the feasibility study were subject to other uses or leaseholds. 


1  A hardstand space is a large, paved area to store cars, heavy vehicles and machinery.
2  Officers familiar with the acquisition could not confirm the nature of remediation being undertaken, but noted that the previous landowner had cleared buildings from the site, which may have been considered part of remediation.
TfNSW's independent valuation, which it commissioned and received after the acquisition, specifically excluded consideration of environmental contamination risk. As a result, TfNSW is exposed to the risk that the acquisition was not fully compliant with the Land Acquisition (Just Terms Compensation) Act 1991 (the Act) because it did not use an accurate estimate of market value during negotiations. That said, the acquisition of 4–6 Grand Avenue by agreement was consistent with preferred processes described in the Act.

TfNSW acquired the site from the landowner by agreement, and this is consistent with provisions in the Act. Obtaining approval for compulsory acquisition should negotiations for agreement break down is also consistent with the Act. That said, TfNSW did not at any time assess whether a compulsory acquisition could have resulted in acquisition at a lower cost than what was negotiated by agreement.

Despite the high risks associated with the acquisition, TfNSW did not commission a formal valuation in time to inform the negotiation and purchase. Instead, TfNSW relied on internal advice to estimate market value, but did not obtain a formal valuation from those advisors. For high-risk transactions, the greater expertise and arm's-length independence of an external specialist valuer should be preferred over an agency's own staff.

On 15 June 2016, the settlement date for the acquisition, TfNSW commissioned a formal independent valuation of the site. On 23 November 2016, TfNSW received the final formal valuation report. By not obtaining a formal independent valuation of the property in advance of acquisition to inform the acquisition value, TfNSW exposed itself to non-compliance with the Act by not establishing the market value as the basis for the acquisition price. TfNSW also breached its own internal policies.

TfNSW instructed the valuer to conduct its valuation within the following parameters:

  • Market valuation on an ‘as is’ basis – market value based on the methodology described in the Act. This approach valued the site at $25.0 million.
  • Market valuation on a speculative development basis – market value based on the financial value of the vendor's intended use of the site which, in this case, involved leasing the site for industrial use. This approach valued the site at $52.0 million, and TfNSW advised us this valuation supported the purchase price.
  • Disregard the impact of environmental contamination – TfNSW specifically instructed the independent valuer to disregard any known (or unknown) site contamination. As TfNSW knew of the significant environmental contamination affecting the site, this parameter resulted in a valuation that overstated the value of the site as it did not consider the cost of environmental remediation. The valuer applied this assumption for both market valuation approaches.

Additionally, as the independent valuer completed the valuation after the purchase was finalised, there is a risk that the valuation may have been influenced by the known purchase price.

TfNSW's failure to acquire a formal valuation and an assessment of the financial impact of environmental remediation before it purchased 4–6 Grand Avenue represents ineffective administration and governance.
TfNSW acquired the site at a time when there was demand and increasing prices for industrial property in the area. However, TfNSW did not effectively assess and manage the risks associated with the acquisition, and gaps in process led to increased risk. Briefings to decision-makers did not contain important information, and we found no evidence that gaps in advice were queried or explored by decision-makers.

TfNSW did not have plans or advice in place to assist in managing risk, such as:

  • a property acquisition plan
  • a comprehensive and up-to-date risk management plan
  • a negotiation strategy, or any authorisation limit or minimal acceptable position
  • an independent professional evaluation
  • external expert advice (with the exception of legal advice relating to the contract of sale).

TfNSW was aware of contamination issues affecting the land and had access to considerable information about the environmental conditions, such as site environmental audit reports and information on the NSW Environment Protection Authority's contaminated land register. However, TfNSW had not analysed specific technical information about the contamination and therefore was not aware of the risk implications and cost for remediation. Despite this, TfNSW changed its position from not accepting the risks and costs of contamination, to acquiring the site unconditionally. The basis for this decision is unclear and undocumented.

Briefing to senior leaders on the acquisition was silent on a number of important matters that would have been important for approvers to consider, including:

  • an explanation of the 40 per cent increase in purchase price between November 2015 and May 2016, and a 165 per cent increase from TfNSW’s offer in April 2015
  • the contamination risks associated with the site and an evidence-based estimate of potential costs to remediate the site
  • advice that an independent valuation had not been obtained, inconsistent with TfNSW policy.

Consideration of the acquisition by FIC was based on a summary business paper and was managed out-of-session, thereby removing the ability for comprehensive consideration of the acquisition proposal and its risks.

The probity management controls and assurances in place for the acquisition of the 4–6 Grand Avenue site were insufficient. These insufficiencies were exacerbated by the probity risk profile of the transaction.

The 4–6 Grand Avenue acquisition was a high-risk/high-value transaction, undertaken in a volatile property market in a short timeframe under pressure from Grand 4 Investments. TfNSW was engaging in a direct negotiation in advance of detailed planning for the acquisition, or the PLR as a whole. These circumstances contribute to heightened probity risk.

TfNSW did not establish a probity plan and sought no probity support throughout the acquisition. Also, with one exception, the staff involved in the acquisition did not complete conflict of interest declarations.

TfNSW was aware of the potential for probity or integrity issues with the transaction when it commissioned an internal audit in connection with the transaction in 2019. Internal discussions considered whether a misconduct investigation may be more appropriate, however no such investigation was undertaken.

TfNSW's insufficient probity practices, in addition to its failure to keep complete or comprehensive records of negotiations or decisions, reduce transparency of the process and its outcome and expose TfNSW to a greater risk of misconduct, corruption and maladministration.

At the time of the transaction, the TfNSW policy framework was not sufficiently risk-focussed and did not provide clarity on when officers ought to apply specific guidance or procedures. TfNSW's policies and procedures are more focussed on acquiring land to meet project needs and timeframes, and less on assuring value for money and managing risks.

At the time of its acquisition of 4–6 Grand Avenue, TfNSW had property acquisitions policies and procedures in place. Each of these were broadly sound in their content and intent. However, they lacked specificity on how or when to apply guidance, and when risk levels should elevate the importance of recommended guidance.

TfNSW's key guidance was principles based and relied on agency staff using their experience and expertise to apply guidance according to the circumstances of an individual transaction. This guidance was not duly applied in the acquisition of 4–6 Grand Avenue, Camellia. In addition, TfNSW does not have quality or control assurance to identify when TfNSW officers did not apply important policies or processes.

The primary focus of the TfNSW’s property acquisition guidance is to achieve vacant possession of land in a timeframe that meets the need of the relevant transport project. There is less specific focus on the need to meet the requirements of the NSW Government financial management framework.

Appendix one – Response from agency 

Appendix two – About the audit 

Appendix three – Performance auditing

 

Copyright Notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #349 - released (18 May 2021).

Published

Actions for Education 2016

Education 2016

Education
Asset valuation
Compliance
Financial reporting
Fraud
Information technology
Internal controls and governance
Procurement
Project management

The Auditor-General, Margaret Crawford released a report today highlighting the impact of the growing student population on school infrastructure and the increasing cost of psychological injury workers' compensation claims in Education. The report also gives updates on an initiative designed to create new out of school hours care (OSHC) places and on the expected final cost and completion date for the Learning Management and Business Reform (LMBR) program.

Published

Actions for Health 2016

Health 2016

Health
Asset valuation
Compliance
Cyber security
Financial reporting
Fraud
Information technology
Internal controls and governance
Project management

This report analyses the results of the financial statement audits of the Health cluster agencies for 2015–16.

Published

Actions for Transport 2016

Transport 2016

Transport
Asset valuation
Compliance
Financial reporting
Fraud
Information technology
Internal controls and governance
Procurement
Project management

Financial reporting within the Transport Cluster continues to improve with reported misstatements down 96 per cent since 2011-12 to just three in 2015-16, according to a report released today by the NSW Auditor-General, Margaret Crawford.

Published

Actions for Justice 2016

Justice 2016

Justice
Asset valuation
Compliance
Financial reporting
Fraud
Information technology
Internal controls and governance
Procurement
Project management
Risk

Overcrowding in the NSW prison system continues to worsen along with the backlog of cases in the District Court, according to a report released by the New South Wales Auditor-General, Margaret Crawford on the annual financial statements audits in the Justice cluster.

Published

Actions for Fraud Survey

Fraud Survey

Education
Community Services
Finance
Health
Industry
Justice
Local Government
Planning
Premier and Cabinet
Transport
Treasury
Universities
Whole of Government
Environment
Fraud
Information technology
Internal controls and governance
Procurement
Risk

In a report released today, the NSW Auditor-General, Margaret Crawford provides a snapshot of reported fraud in the NSW public sector and an analysis of NSW Government agencies’ fraud controls based on a survey of 102 agencies.

Published

Actions for Volume Eleven 2012 focusing on Health

Volume Eleven 2012 focusing on Health

Health
Compliance
Financial reporting
Fraud
Information technology
Internal controls and governance
Management and administration
Procurement
Project management
Workforce and capability

One in three ambulance crews were delayed for longer than 30 minutes at hospital. Over the year these delays totalled 84,680 hours of lost time, up from 78,224 last year and 58,399 the year before. The longer ambulance crews are at hospitals the less time they are available to respond to the next emergency.

Published

Actions for Volume Eight 2012 focusing on Transport and Ports

Volume Eight 2012 focusing on Transport and Ports

Transport
Industry
Compliance
Financial reporting
Fraud
Information technology
Infrastructure
Management and administration
Procurement
Project management
Regulation
Risk
Workforce and capability

We issued unqualified audit opinions on the transport entities’ 30 June 2012 financial statements.

Some of the findings of the report include:

  • government funding to the public transport operators totalled $4.4 billion in 2011-12 ($3.7 billion in 2010-11)

  • passenger services revenue only covered 20 per cent of RailCorp's operating costs

  • Transport for NSW has formalised a protocol to mitigate the risk of potential conflicts of interests

  • At present, no sustainability framework exists for the transport agencies around environment and sustainability. Transport for NSW should complete its Environment and Sustainability Policy Framework by June 2013 and should publicly report its results annually

  • Transport patronage continued to grow with 510 million journeys on train, bus and ferry services

  • CityRail had two peak hour periods where only 36 per cent and 39 per cent of services were on time

  • On-time running performance for Sydney Ferries was above the NSW 2021 plan target of 98.5 per cent for most routes in 2011-12

  • Customer surveys by transport agencies no longer specifically address crowding on public transport. Transport for NSW should observe and report on crowding on all transport modes

  • Over 2,500 transport staff, or 8.3 per cent of the workforce, have excessive leave balances. All transport entities should do more to reduce excessive annual leave balances to ensure they will comply with new targets set by the Premier.

 

Published

Actions for Volume Seven 2012 focusing on Law, Order and Emergency Services

Volume Seven 2012 focusing on Law, Order and Emergency Services

Justice
Compliance
Fraud
Internal controls and governance
Management and administration
Procurement
Project management
Workforce and capability

Since the Victims’ Compensation Scheme started in 1989, $1.6 billion has been paid to victims of crime, but only $57.4 million or nearly four per cent has been recovered from convicted offenders. The remaining 96 per cent has been funded by the taxpayer.