Actions for Education 2021

Education 2021

Education
Asset valuation
Compliance
Financial reporting
Information technology
Internal controls and governance
Procurement

This report analyses the results of our audits of the Education cluster agencies for the year ended 30 June 2021.

Our preferred approach is to table the ‘Report on State Finances’ in Parliament before any other cluster report. This is because the 'Report on State Finances' focuses on the audit results and observations relating to the Total State Sector Accounts, in effect a consolidation of all government agencies. This year the 'Report on State Finances' has been delayed due to significant accounting issues being considered in the Total State Sector Accounts and which may impact the Treasury and Transport clusters.

As there are no outstanding matters relating to audits in the Education cluster impacting the Total State Sector Accounts we have decided to break with normal practice and table this cluster report ahead of the ‘Report on State Finances’.

What the report is about

The results of the Education cluster (the cluster) agencies' financial statements audits for the year ended 30 June 2021.

What we found

Unmodified audit opinions were issued on the Department of Education (the department), the NSW Education Standards Authority and the NSW Skills Board's financial statements.

An 'other matter' paragraph was included in the Technical and Further Education Commission's (the TAFE Commission) audit opinion drawing attention to legislative non-compliance concerning financial delegations during the reporting year.

The number of misstatements identified in the financial statements of cluster agencies decreased from 14 in 2019–20 to seven.

What the key issues were

The department and the TAFE Commission revalued their land assets this year, recognising collective increases of $863.8 million.

The department and the TAFE Commission are not scheduled to perform comprehensive revaluations of their buildings until 2022–23. Construction costs, which are a key input in their current replacement cost valuation methodologies for buildings, may have increased by an estimated nine per cent since the last comprehensive revaluation in 2017–18 based on broad based indices used by the department and the TAFE Commission. While the estimated index increase indicates the fair value of buildings may exceed the carrying values, the use of such high-level indicators has a degree of estimation uncertainty due to the specialised nature of the assets. Therefore, both agencies did not adjust the values of their buildings.

The number of issues we reported to management decreased. Fifty per cent of issues were repeated from prior years.

Of the 11 newly identified moderate rated issues, seven related to internal control deficiencies, with six identified in procurement and payroll controls.

What we recommended

The department and the TAFE Commission reconsider policy settings governing the frequency of revaluations; and refine and consider the outcomes of interim fair value assessments to ensure asset carrying values reflect fair value at each balance date.

Cluster agencies should prioritise and action recommendations to address internal control deficiencies.

Fast facts

The Education cluster, comprising four agencies, administers and delivers education and training services for NSW students, workers and industry.

  • $38.6b property, plant and equipment as at 30 June 2021
  • $21.2b total expenditure incurred in 2020–21
  • 100% unqualified audit opinions were issued on agencies’ 30 June 2021 financial statements
  • 22 moderate risk management letter findings were identified and reported to management
  • monetary misstatements were reported in 2020–21
  • 50% of reported issues were repeat issues

This report provides Parliament and other users of the Education cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Education cluster (the cluster) for 2021.

Section highlights

  • Unqualified audit opinions were issued on the financial statements of cluster agencies.

  • Comprehensive revaluations of the Department of Education (the department) and the Technical and Further Education Commission's (the TAFE Commission) land assets resulted in collective net increases of $863.8 million to the carrying values of these entities' land assets.

  • Fair value assessments, based on broad indices, of the department and the TAFE Commission's buildings, indicated that replacement costs may have increased by an estimated nine per cent. Whilst the next comprehensive valuation is not scheduled until 2022–23, the department and the TAFE Commission will need to consider the outcomes of their annual assessments to ensure that the carrying amounts continue to reflect the fair value of these specialised assets in their financial statements.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from our financial statement audits of agencies in the Education cluster.

Section highlights

  • The 2020–21 audits identified 22 moderate issues across the cluster. Eleven moderate risk issues were repeat issues and related to general and application information technology controls and deficiencies in procurement and payroll practices.
  • Of the 11 newly identified moderate rated issues, seven related to internal control deficiencies and improvements, with identified deficiencies in procurement and payroll accounting for six.
  • A high-risk issue identified in 2019–20 relating to the Department of Education's (the department) monitoring of privileged user activity has largely been addressed.

Findings reported to management

The number of findings reported to management has decreased. Fifty per cent of all issues were repeat issues

Breakdowns and weaknesses in internal controls increase the risk of fraud and error. Deficiencies in internal controls, matters of governance interest and unresolved issues were reported to management and those charged with governance of agencies. The Audit Office does this through management letters, which include observations, related implications, recommendations and risk ratings.

In 2020–21, there were 28 findings raised across the cluster (33 in 2019–20). Fifty per cent of all issues were repeat issues (45 per cent in 2019–20).

The most common repeat issues related to weaknesses in controls over information technology general controls, application controls, and identified deficiencies in procurement and payroll practices.

A delay in implementing audit recommendations increases the risk of intentional and accidental errors in processing information, producing management reports and generating financial statements. This can impair decision-making, affect service delivery and expose agencies to fraud, financial loss and reputational damage. Poor controls may also mean agency staff are less likely to follow internal policies, inadvertently causing the agency not to comply with legislation, regulation and central agency policies.

The table below describes the common issues identified across the cluster by category and risk rating.

Risk rating Issue
Information technology

Moderate2
2 new,
6 repeat

The financial audits identified areas for agencies to improve information technology processes and controls that support the integrity of financial data used to prepare agencies' financial statements. Of note were deficiencies identified in:
  • agencies' user access administration and change management procedures, notably in the timing and frequency of managerial reviews over the granting and revocation of access to key systems relevant to financial reporting
  • application controls and segregation of duties in payroll systems, allowing certain users to access or modify employee records as well as process payroll
  • system configurations whereby preparers of manual journals can also post without a secondary review
  • password reviews undertaken that align with approved password guidelines
  • the monitoring of privileged user activities.

Low1
2 new,
1 repeat

Internal control deficiencies or improvements

Moderate2
7 new,
4 repeat

The financial audits identified internal control weaknesses across key business processes relevant to financial reporting. Of note were deficiencies identified in:
  • the adequacy of monitoring and oversight activities over the use of multiple financial delegation configurations in finance systems for specific users
  • the timely recording and approval of overtime claims and higher duties allowances
  • the timely finalisation of policies and procedures
  • procurement practices including a high proportion of retrospective purchase orders and the timely receipting of goods and services
  • the timely notification of employee resignations or employees applying for leave without pay, leading to salary overpayments
  • the management of excessive annual leave balances
  • the extent of review or approval of changes to lease information.

 Low1
1 new,
2 repeat

Financial reporting

Moderate2
2 new,
1 repeat

The financial audits identified:
  • opportunities for agencies to strengthen their financial preparation processes to facilitate a timelier and more efficient year-end audit
  • the need for agencies with non-financial assets subject to fair value to reconsider policy settings governing the frequency of revaluations; and to refine and consider the outcomes of interim fair value assessments to ensure asset carrying values reflect fair value at each balance date.

Low1
0 new,
0 repeat


3 High risk from the consequence and/or likelihood of an event that has had, or may have a negative impact on the entity.
2 Moderate risk from the consequence and/or likelihood of an event that has had, or may have a negative impact on the entity.
1 Low risk from the consequence and/or likelihood of an event that has had, or may have a negative impact on the entity.

 
Note: Management letter findings are based on final management letters issued to agencies.

The department continues to address recommendations to improve monitoring of privileged user access

Privileged users have higher levels of access to systems, and in some instances, may include access that can bypass segregation of duty controls. If reviews of access logs are not fully embedded in the control environment, the risk of unauthorised transactions occurring and not being detected in a timely manner is elevated.

In 2019–20 a high-risk issue was reported at the department relating to the inadequate monitoring and follow up of privileged user activity in its enterprise resource planning system – SAP. This year the department has largely addressed our findings by initiating a review of the identified instances of privileged user activity and establishing periodic oversight controls. There remains a need to improve the timeliness and completeness of these newly implemented controls.

Data analytics identified the root cause of internal control deficiencies in procurement and payroll

Our 2020–21 agency management letters identified seven new moderate risk internal control deficiency matters, of which six related to payroll and procurement.

To enhance our financial statement audit of the department we applied data analytics over elements of the department's procurement and payroll control processes. Our procedures, conducted over periods across the financial year, helped identify the following:

  • a low level of compliance with procurement practices requiring the creation of purchase orders before invoices are received. The root cause was a lack of understanding by agency staff of the procurement processes
  • transactions related to previous years being recorded in the current year. The root cause was a lack of understanding of the three-way matching process and the goods received/not invoiced facilities within SAP
  • negative payments in fortnightly pay runs, predominantly representing deductions to recover salary payments made in error. The root cause was the lack of timeliness in notifying payroll for cessation of employment, or for employees undertaking secondments who should have been classified as being on leave without pay.
 
 

Recommendation

We recommend cluster agencies prioritise and action recommendations to address the internal control deficiencies outlined above. 

Appendix one – Early close procedures

 

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Published

Actions for Rail freight and Greater Sydney

Rail freight and Greater Sydney

Transport
Information technology
Infrastructure
Management and administration
Project management
Service delivery

What the report is about

The movement of freight contributes $66 billion annually to the NSW economy. Two thirds of all freight in NSW moves through Greater Sydney, and the volume of freight moving through Greater Sydney is expected to increase by 48 per cent by 2036.

This audit assessed the effectiveness of transport agencies in improving the use of rail freight capacity in Greater Sydney, and to meet current and future freight demand.

What we found

Transport agencies do not have strategies or targets in place to improve the efficiency or capacity of the metropolitan shared rail network for freight.

The transport agencies acknowledge that they do not have sufficient information to achieve the most efficient freight outcomes and they do not know how to use the shared rail network to maximise freight capacity without compromising passenger rail services.

The Freight and Ports Plan 2018-2023 contains one target for rail freight - to increase the use of rail at Port Botany to 28 per cent by 2021. However, Transport for NSW (TfNSW)'s data indicates this target will not be met.

Sydney Trains records data on train movements and collects some data on delays and incidents. TfNSW collects data for the construction of the Standard Working Timetable and third-party contracts.

However, a lack of clarity around what data is gathered and who has ownership of the data makes data sharing difficult and limits its analysis and reporting.

The Freight and Ports Plan 2018-2023 includes the goal of 'Reducing avoidable rail freight delays', but the transport agencies do not have any definition for an avoidable delay and, as a result, do not measure or report them.

TfNSW and Sydney Trains are appointed to manage and deliver the Transport Asset Holding Entity of New South Wales (TAHE)'s obligations to allow rail freight operators to use the shared rail network. There are no performance measures in rail freight operator contracts or inter-agency agreements. This limits transport agencies' ability to improve performance.

TfNSW’s Freight Branch is working on four freight-specific strategies; a review of the Plan, a freight rail strategy, a port efficiency strategy and a freight data strategy.

TfNSW has not yet determined the timeframes or intended outcomes of these strategies.

What we recommended

Transport agencies should:

  • commit, as part of the review of Future Transport 2056, to delivering the freight-specific strategies currently in development and develop whole-of-cluster accountability for this work including timeframes, specific targets and clear roles and responsibilities 
  • improve the collection and sharing of freight data
  • develop a plan to reduce avoidable freight delays
  • systematically collect data on the management of all delays involving and/or impacting rail-freight
  • develop and implement key performance indicators for the agreements between the transport agencies.

Fast facts    

  • 288 million tonnes of freight volume predicted to pass through Greater Sydney in 2036, up from 194 million in 2016 (an increase of 48%)

  • 54 trucks that can be replaced by one 600 m long port shuttle freight train    

  • 26,671 freight trains that passed through the metropolitan shared rail network between 1 July 2020 and 30 June 2021

The movement of freight contributes $66.0 billion annually to the New South Wales economy — or 13 per cent of the Gross State Product. Two thirds of all freight in New South Wales moves through Greater Sydney, and the volume of freight moving through Greater Sydney is expected to increase by 48 per cent by 2036. This increasing demand is driven by increasing population and economic growth.

The sequence of activities required to move goods from their point of origin to the eventual consumer (the supply chain) is what matters most to shippers and consumers. Road can provide a single-mode door-to-door service, whereas conveying goods by rail typically involves moving freight onto road at some point. In Greater Sydney, 80 per cent of all freight is moved on road. Freight often passes through intermodal terminals (IMTs) as it transitions from one mode of transport to the next.

In 2016, Transport for NSW (TfNSW) released Future Transport 2056 - the NSW Government's 40-year vision for transport in New South Wales, which is intended to guide investment over the longer term. In Future Transport 2056, TfNSW noted that New South Wales will struggle to meet increasing demand for freight movements unless rail plays a larger role in the movement of freight.

Sydney Trains manages the metropolitan shared rail network, which is made up of rail lines that are used by both passenger and freight trains. The Transport Administration Act 1988 requires that, for the purposes of network control and timetabling, NSW Government transport agencies give ‘reasonable priority’ to passenger trains on shared lines. As the Greater Sydney population and rail patronage continue to grow, so too will competition for access to the shared rail network. See Appendix two for details of the area encompassed by Greater Sydney.

Freight operators can also use dedicated rail freight lines operated by the Australian Rail Track Corporation (ARTC - an Australian Government statutory-owned corporation). As the metropolitan shared rail network connects with dedicated freight lines, freight operators often use both to complete a journey.

TfNSW, Sydney Trains and the Transport Asset Holding Entity (TAHE) work in conjunction with other rail infrastructure owners and private sector entities, including port operators, privately operated IMTs and freight-shipping companies. TfNSW and Sydney Trains are responsible for managing the movement of freight across the metropolitan shared rail network. TAHE is the owner of the rail infrastructure that makes up the metropolitan shared rail network. The NSW Government established TAHE, a NSW Government state-owned corporation, on 1 July 2020 to replace the former rail infrastructure owner - RailCorp. The Auditor-General for New South Wales has commenced a performance audit on TAHE which is expected to table in 2022.

On 1 July 2021, TAHE entered into new agreements with TfNSW and Sydney Trains to operate, manage and maintain the metropolitan shared rail network. Until 30 June 2021, and in accordance with TAHE's Implementation Deed, TAHE operated under the terms of RailCorp's existing arrangements and agreements.

This audit assessed the effectiveness of TfNSW, Sydney Trains and TAHE in improving the use of rail freight capacity in Greater Sydney, and to meet current and future freight demand.

The audit focused on:

  • the monitoring of access to shared rail lines
  • the management of avoidable delays of rail freight movements
  • steps to increase the use of rail freight capacity in Greater Sydney.

Conclusion

Transport agencies do not have clear strategies or targets in place to improve the freight efficiency or capacity of the metropolitan shared rail network. They also do not know how to make best use the rail network to achieve the efficient use of its rail freight capacity. These factors expose the risk that rail freight capacity will not meet anticipated increases in freight demand.

Future Transport 2056 notes that opportunities exist to shift more freight onto rail, and that making this change remains an important priority for the NSW Government. However, the transport agencies acknowledge that they do not have sufficient information to achieve the most efficient freight outcomes. In particular, transport agencies do not know how to use the shared rail network in a way that maximises freight capacity without compromising passenger rail services.

Neither Future Transport 2056 nor the Freight and Ports Plan 2018–2023 give any guidance on how transport agencies will improve the efficiency or capacity of the shared rail network. Other than a target for rail freight movements to and from Port Botany, which TfNSW's data indicates will not be met, there are no targets for improving rail freight capacity across the shared network. The lack of specific strategies, objectives and targets reduces accountability and makes it difficult for transport agencies to effectively improve the use of rail freight capacity in line with their commitment to do so.

Sydney Trains and Transport for NSW do not effectively use data to improve rail freight performance and capacity.

To drive performance improvement when planning for the future, transport agencies need good quality data on freight management and movements. Sydney Trains records data on train movements in real-time and collects some data on delays and incidents. TfNSW collects data for the construction of the Standard Working Timetable (SWTT) and third-party contracts. However, the different types of data gathered and the separation between the teams responsible mean that there is a lack of clarity around what data is gathered and who has ownership it. This lack of coordination prevents best use of the data to develop a single picture of how well the network is operating or how performance could be improved.

Sydney Trains' ability to evaluate the effectiveness of its incident and delay mitigation strategies is also limited by a lack of information on its management of rail-freight related delays or incidents. While Sydney Trains collects data on major incidents, it can only use this to conduct event-specific analysis on the causes of an incident, and to review the operational and management response. The use of complete and accurate incident data would assist to define, identify and reduce avoidable delays. Reducing avoidable delays is a goal of the Freight and Ports Plan 2018–2023. More complete data on all incidents would help TfNSW to have more effective performance discussions with rail freight operators to help improve performance.

TfNSW has started developing strategies to identify how it can use rail freight capacity to achieve efficient freight outcomes, but it has not committed to implementation timeframes for this work.

TfNSW’s Freight Branch has started work on four freight-specific strategies to improve freight efficiency: a review of the Plan, a freight rail strategy, a port efficiency strategy and a freight data strategy. However, none of these strategies will be fully developed before the end of 2022. TfNSW has not yet determined the implementation timeframes or intended outcomes of these strategies, although TfNSW reports that it is taking an iterative approach and some recommendations and initiatives will be developed during 2022. 

Appendix one - Response from agencies

Appendix two - The Greater Sydney region

Appendix three - TfNSW strategic projects 

Appendix four - Sydney Trains path priority principles 

Appendix five - Sydney Trains delay management

Appendix six - About the audit 

Appendix seven - Performance auditing
 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #357 - released (19 October 2021).

Published

Actions for Managing cyber risks

Managing cyber risks

Whole of Government
Transport
Cyber security
Information technology
Internal controls and governance
Procurement
Risk

What the report is about

This audit assessed how effectively Transport for NSW (TfNSW) and Sydney Trains identify and manage their cyber security risks.

The NSW Cyber Security Policy (CSP) sets out 25 mandatory requirements for agencies, including implementing the Australian Cyber Security Centre’s Essential 8 strategies to mitigate cyber security incidents, and identifying the agency’s most vital systems, their ‘crown jewels’. 

The audited agencies have requested that we do not disclose detail of the significant vulnerabilities detected during the audit, as these vulnerabilities are not yet remediated. We provided a detailed report to the agencies in December 2020 outlining significant issues identified in the audit. We have conceded to the agencies' request but it is disappointing that transparency to the Parliament and the public on issues that potentially directly affect them needs to be limited in this way.

What we found

TfNSW and Sydney Trains are not effectively managing their cyber security risks.

Both agencies have assessed their cyber security risks as unacceptably high and both agencies had not identified all of the risks we detected during this audit – some of which are significant.

Both agencies have cyber security plans in place that aim to address cyber security risks. TfNSW and Sydney Trains have combined this into the Transport Cyber Defence Rolling Program, part of the Cyber Defence Portfolio (CDP). 

However, neither agency has reached its target ratings for the CSP and the Essential 8 and maturity is low in relation to significant risks and vulnerabilities exposed.

Further, neither agency is fostering a culture where cyber security risk management is an important and valued aspect of decision-making.

TfNSW is not implementing cyber security training effectively across the cluster with only 7.2% of staff having completed basic cyber security training.

What we recommended

TfNSW and Sydney Trains should:

  • develop and implement a plan to uplift the Essential 8 controls to the agency's target state
  • as a matter of priority, address the vulnerabilities identified as part of this audit and previously described in a detailed Audit Office report provided to both agencies
  • ensure cyber security risk reporting to executives and the Audit and Risk Committee
  • collect supporting information for the CSP self assessments 
  • classify all information and systems according to importance and integrate this with the crown jewels identification process
  • require more rigorous analysis to re-prioritise CDP funding 
  • increase uptake of cyber security training.

TfNSW should assess the appropriateness of its target rating for each of the CSP mandatory requirements.

Department of Customer Service should:

  • clarify the requirement for the CSP reporting to apply to all systems
  • require agencies to report the target level of maturity for each mandatory requirement.

Fast facts

  • $42m Total value of the Transport Cyber Defence Rolling Program over three years.
  • 7.2% Percentage of staff across the Transport cluster who had completed introductory cyber security training

Response to requests by audited agencies to remove information from this report

In preparing this audit report, I have considered how best to balance the need to support public accountability and transparency with the need to avoid revealing information that could pose additional risk to agencies’ systems. This has involved an assessment of the appropriate level of detail to include in the report about the cyber security vulnerabilities identified in this audit.

In making this assessment, the audit team consulted with Transport for NSW (TfNSW), Sydney Trains, and Cyber Security NSW to identify content which could potentially pose a threat to the agencies’ cyber security.

In December 2020, my office also provided TfNSW and Sydney Trains with a detailed report of many of the significant vulnerabilities identified in this audit, to enable the agencies to address the cyber security risks identified. The detailed report was produced as a result of a 'red team' exercise, which was conducted with both agencies' knowledge and consent. The scope of this exercise reflected the significant input provided by both agencies. More information on this exercise is at page 12 of this report.

TfNSW and Sydney Trains have advised that in the six months from December 2020 and at the time of tabling this audit report, they have not yet remediated all the vulnerabilities identified. As a result, they, along with Cyber Security NSW, have requested that we not disclose all information contained in this audit report to reduce the likelihood of an attack on their systems and resulting harm to the community. I have conceded to this request because the vulnerabilities identified have not yet been remediated and leave the agencies exposed to significant risk.

It should be stressed that the risks identified in the detailed report exist due to the continued presence of these previously identified vulnerabilities, rather than due to their potential publication. The audited agencies, alone, are accountable for remediating these vulnerabilities and addressing the risks they pose.

It is disappointing that transparency to the Parliament and the public on issues that potentially directly affect them needs to be limited in this way.

That said, the conclusions drawn in this report are significant in terms of risk and remain valid, and the recommendations should be acted upon with urgency.

Cyber security risk is an increasing area of concern for governments in Australia and around the world. In recent years, there have been a number of high-profile cyber security attacks on government entities in Australia, including in New South Wales. Malicious cyber activity in Australia is increasing in frequency, scale, and sophistication. The Audit Office of New South Wales is responding to these risks with a program of audits in this area, which aim to identify the effectiveness of particular agencies in managing cyber risks, as well as their compliance with relevant policy.

Cyber Security NSW, part of the Department of Customer Service (DCS) releases and manages the NSW Cyber Security Policy (CSP). The CSP sets out 25 mandatory requirements for agencies, including making it mandatory for agencies to implement the Australian Cyber Security Centre Essential 8 Strategies to Mitigate Cyber Security Incidents (the Essential 8). The Essential 8 are key controls which serve as a baseline set of protections which agencies can put in place to make it more difficult for adversaries to compromise a system. Agencies are required to self-assess their maturity against the CSP and the Essential 8, and report that assessment to Cyber Security NSW annually.

The CSP makes agencies responsible for identifying and managing their cyber security risks. The CSP sets out responsibilities and governance regarding risk identification, including making agencies responsible for identifying their 'crown jewels', the agency's most valuable and operationally vital systems. Once these risks are identified, agencies are responsible for developing a cyber security plan to mitigate those risks.

This audit focussed on two agencies: Transport for NSW (TfNSW) and Sydney Trains. TfNSW is the lead agency for the Transport cluster and provides a number of IT services to the entire cluster, including Sydney Trains. This audit focussed on the activities of TfNSW's Transport IT function, which is responsible for providing cyber security across the cluster, as well as directly overseeing four of TfNSW's crown jewels. Sydney Trains is one of the agencies in the Transport cluster. While it receives some services from TfNSW, it is also responsible for implementing its own IT controls, as well as controls to protect its Operational Technology (OT) environment. This OT environment includes systems which are necessary for the operation and safety of the train network.

To test the mitigations in place and the effectiveness of controls, this audit involved a 'red team' simulated exercise. A red team involves authorised attackers seeking to achieve certain objectives within the target's environment. The red team simulated a determined external cyber threat actor seeking to gain access to TfNSW's systems. The red team also sought to test the physical security of some Sydney Trains' sites relevant to the agency's cyber security. The red team exercise was conducted with the knowledge of TfNSW and Sydney Trains.

This audit included the Department of Customer Service as an auditee, as they have ownership of the CSP through Cyber Security NSW. This audit did not examine the management of cyber risk in the Department of Customer Service.

This audit assessed how effectively selected agencies identify and manage their cyber security risks. The audit assessed this with the following criteria:

  • Are agencies effectively identifying and planning for their cyber security risks?
  • Are agencies effectively managing their cyber security risks?

Following this in-depth portfolio assessment, the Auditor-General for NSW will also table a report on NSW agencies' compliance with the CSP in the first quarter of 2021–22.

Conclusion

Transport for NSW and Sydney Trains are not effectively managing their cyber security risks. Significant weaknesses exist in their cyber security controls, and both agencies have assessed that their cyber risks are unacceptably high. Neither agency has reached its Essential 8 or Cyber Security Policy target levels. This low Essential 8 maturity exposes both agencies to significant risk. Both agencies are implementing cyber security plans to address identified cyber security risks.
This audit identified other weaknesses, such as low numbers of staff receiving basic cyber security awareness training. Cyber security training is important for building and supporting a cyber security culture. Not all of the weaknesses identified in this audit had previously been identified by the agencies, indicating that their cyber security risk identification is only partially effective.
Agency executives do not receive regular detailed information about cyber risks and how they are being managed, such as information on mitigations in place and the effectiveness of controls for cyber risk. As a result, neither agency is fostering a culture where cyber security risk management is an important and valued aspect of executive decision-making.
TfNSW and Sydney Trains are partially effective at identifying their cyber security risks and both agencies have cyber security plans in place

Both agencies regularly carry out risk assessments and have identified key cyber security risks, including risks that impact on the agencies' crown jewels. These risks have been incorporated into the overall enterprise risk process. However, neither agency regularly reports detailed cyber risk information to agency executives to adequately inform them about cyber risk. The Cyber Security Policy (CSP) requires agencies to foster a culture where cyber security risk management is an important and valued aspect of decision-making. By not informing agency executives in this way, TfNSW and Sydney Trains are not fulfilling this requirement.

Agencies' cyber security risk assessment processes are not sufficiently comprehensive to identify all potential risks. Not all of the weaknesses identified in this audit had previously been identified by the agencies.

To address identified cyber security risks, both agencies have received funding approval to implement cyber security plans. TfNSW first received approval for its cyber security plan in 2017. Sydney Trains received approval for its cyber security plan in February 2020. In 2020–21 TfNSW and Sydney Trains combined their plans into the Transport Cyber Defence Rolling Program business case valued at $42.0 million over three years. This is governed as part of a broader Cyber Defence Portfolio (CDP). The CDP largely takes a risk-based approach to annual funding. The Cyber Defence Portfolio Steering Committee and Board can re-allocate funds from an approved project to a different project. This re-allocation process could be improved by making it more risk-based.

TfNSW and Sydney Trains are not effectively managing their cyber security risks

Neither agency has fully mitigated its cyber security risks. These risks are significant. Neither TfNSW nor Sydney Trains have reduced their cyber risk to levels acceptable to the agencies. Both agencies have set a risk tolerance for cyber security risks, and the identified enterprise-level cyber security risks remain above this rating. Both agencies' self-attested maturity against the Essential 8 remains low in comparison to the agencies' target levels, and in relation to the significant risks and vulnerabilities that are exposed. Little progress was made against the Essential 8 in 2020.

Neither agency has reached its target levels of maturity for the CSP mandatory requirements. Not reaching the target rating of the CSP mandatory requirements risks information and systems being managed inconsistently or not in alignment with good governance principles. The Transport Cyber Defence Rolling Program has a KPI to achieve a target rating of three for all CSP requirements where business appropriate. TfNSW considers this target rating to be its target for all the CSP requirements. However TfNSW has not undertaken analysis to determine whether this target is appropriate to its business.

The CSP makes agencies accountable for the cyber risks of their ICT service providers. While both agencies usually included their cyber security expectations in contracts with third-party suppliers, neither agency was routinely conducting audits to ensure that these expectations were being met.

The CSP requires agencies to make staff aware of cyber security risks and deliver cyber security training. TfNSW is responsible for delivering cyber security training across the Transport cluster, including in Sydney Trains. TfNSW was not effectively delivering cyber security training across the cluster because training was not mandatory for all staff at the time of the audit and completion rates among those staff assigned the training was low. As such, only 7.2 per cent of staff across the Transport cluster had completed introductory cyber security training as at January 2021.

Agencies have assessed their cyber risks as being above acceptable levels

An agency's risk tolerance is the amount of risk which the agency will accept or tolerate without developing further strategies to modify the level of risk. Risks that are within an agency's risk tolerance may not require further mitigation and may be deemed acceptable, while risks which are above the agency's risk tolerance likely require further mitigation before they become acceptable to the agency.

Both agencies have defined their risk tolerance and have identified risks which are above this level, indicating that they are unacceptable to the agency. TfNSW has defined 'very high' risks as generally intolerable and 'high' risks as undesirable. Its risk tolerance is 'medium'. Sydney Trains has four classifications of risk: A, B, C and D. A and B risks are deemed 'unacceptable' and 'undesirable' respectively, while C risks are considered 'tolerable'. This aligns with the TfNSW definition of a medium risk tolerance.

Transport IT reported five enterprise-level cyber security risks through its enterprise risk reporting tool in September 2020, all of which relate to cyber security or have causes relating to cyber security. These risks are in aggregate form, rather than relating to specific vulnerabilities. At the time of the audit, one of these risks was rated as very high and the other four rated as high. At this time, Transport IT had identified a further seven divisional-level risks which were above the agency’s risk tolerance.

Similarly, Sydney Trains has identified one main cyber security risk in its IT enterprise-level risk register and another with a potential cyber cause. Both of these IT risks are deemed to have a residual risk of ‘unacceptable’.

Similarly, two cyber-related OT risks have been determined to be above the agency's risk tolerance. One risk is rated as 'unacceptable'. Another risk, while not entirely cyber rated, is rated 'undesirable' and is deemed to have some causes which may stem from a cyber-attack.

Agencies have assessed their current cyber risk mitigations as requiring improvement

In addition to the risk ratings stated above, at the time of the audit neither agency believed that its controls were operating effectively. Transport IT had rated the control environments for its cyber security enterprise risks as 'requires improvement'. Mitigations were listed in the risk register for these risks but, in some cases, they were unlikely to reduce the risk to the target state or by the target date. For example, one risk had actions listed as 'under review' and no further treatment actions listed, but a due date of July 2021, while another risk was being treated by the CDP with a due date of July 2021. The CDP identified in May 2020 that while the average risk identified as part of that program will be reduced to a medium level by this date, ten high risks will still remain. Given the delays in the program, this number may be higher. As such, it seems unlikely that the enterprise risk will be reduced to below a 'high' level by July 2021.

Sydney Trains’ IT and OT risk registers cross-reference controls and mitigations against the causes and consequences. The IT cyber security risk identified in the register had causes with no mitigations designed for them. Further, some of these causes did not have future mitigations designed for them. This risk also had controls in place which are identified as partially effective. For the unacceptable OT risk noted above, while there was a control designed for each of the potential causes, Sydney Trains had identified all of the controls in place as either partially effective or ineffective. This indicates that Sydney Trains was not effectively mitigating the causes of its cyber risks and, even where it had designed controls or mitigations, these were not always implemented to fully mitigate the cause of the risk.

Additional information on gaps in cyber mitigations which were exposed in the course of this audit has been detailed to both agencies. The Foreword of this report provides information about why this detail is not included here.

Essential 8 maturity is low across TfNSW and Sydney Trains and little progress was made in 2020

CSP mandatory requirement 3.2 states that agencies must implement the ACSC Essential 8. Agencies must also rate themselves against each of the Essential 8 on a maturity scale from zero to three and report this to Cyber Security NSW. A full list of the Essential 8 can be found in Exhibit 1. Both agencies have a low level of maturity against the Essential 8 not just in comparison to the targets they have set, but also in relation to the risks and vulnerabilities exposed. Both agencies have set target maturity ratings for the Essential 8 but none of the Essential 8 ratings across either agency are currently implemented to this level. Having a low level of Essential 8 maturity exposes both agencies to significant risks and vulnerabilities. Little progress was made between the 2019 and 2020 attestation periods.

Transport IT has set a target rating of three across all of the Essential 8. Sydney Trains has set a target rating of three for its IT systems. Sydney Trains had an interim target of two for its OT systems in 2020 and advised that this has since increased to three. It should be noted that not all the Essential 8 are applicable to OT systems.

None of the Essential 8 ratings across either agency are currently implemented to the target levels. Given that the Essential 8 provide the controls which are most commonly able to deter cyber-attacks, having maturity at a low level potentially exposes agencies to a cyber security attack.

Some work is underway across both TfNSW and Sydney Trains to improve the Essential 8 control ratings. The CDP provided some resources to the Essential 8 over 2019–20, with uplift focusing on specific systems. The CDP work in 2019 and 2020 relevant to the Essential 8 largely focussed on determining the current state of the Essential 8 and creating a target state roadmap. As a result, there was little improvement between the 2019 and 2020 attestation periods. The CDP has a workstream for the Essential 8 in its FY 2020–21 funding allocation, however as noted above in Exhibit 6 this was delayed as resources were redeployed to Project La Brea. Regardless, work on some specific aspects of the Essential 8 remain part of the 2020–21 CDP allocation, with workstreams allocated to improving three of the Essential 8. In addition, some work from Project La Brea should lead to an improvement in the Essential 8.

Sydney Trains' Cyber Uplift Program included a workstream which had in scope the uplift in the Essential 8 in IT. There were also other workstreams which aimed to improve some of the Essential 8 for OT systems. Work is also ongoing as part of the CDP to uplift these scores in Sydney Trains.

TfNSW and Sydney Trains have not reached their target maturity across the CSP mandatory requirements and TfNSW has not evaluated its cluster-wide target to ensure it is appropriate

Cyber Security NSW allows each agency to determine its target level of maturity for the first 20 CSP mandatory requirements. Agencies can tailor their target levels to their risk profile. Not reaching the target rating of the CSP mandatory requirements risks information and systems being managed inconsistently or not in alignment with good governance principles.

Sydney Trains has set its target level of maturity for IT and OT. All of Sydney Trains' target maturity levels are at least a three (defined), with a target of four (quantitatively managed) for many of the mandatory requirements. While Cyber Security NSW does not currently mandate a minimum level of maturity, in 2019 there was a requirement for each agency to target a minimum level of three.

Sydney Trains has not met its target ratings across the mandatory requirements.

The Transport Cyber Defence Rolling Program has a program KPI to ensure that the entire cluster reaches a minimum maturity level of three against all the CSP requirements by 2023. TfNSW has not reviewed its CSP mandatory requirement targets to determine if a three is desirable for all requirements or if a higher target level may be more appropriate. It is important for senior management to set cyber security objectives as a demonstration of leadership and a commitment to cyber security.

TfNSW has not met its target ratings across the mandatory requirements for its Group IT ISMS, which was the focus of this audit.

Both agencies claimed progress in their implementation of the mandatory requirements between 2019 and 2020. The audit did not seek to verify the self-assessed results from either agency.

Both agencies operate ISMS in line with the CSP

CSP mandatory requirement 3.1 requires agencies to implement an Information Security Management System (ISMS) or Cyber Security Framework (CSF), with scope at least covering systems identified as the agency's ‘crown jewels’. The ISMS or CSF should be compliant with, or modelled on, one or more recognised IT or OT standard. As noted in the introduction, an ISMS ‘consists of the policies, procedures, guidelines, and associated resources and activities, collectively managed by an organisation, in the pursuit of protecting its information assets.’ Both agencies operate an ISMS compliant with the CSP requirement.

As noted in the introduction, TfNSW operates four ISMS. The Transport IT ISMS is certified against ISO27001, the most common standard for ISMS certification. Three of TfNSW’s six crown jewels are managed within this ISMS. The other ISMS are not certified to relevant standards, though TfNSW claims that they align with relevant controls. This is sufficient for the purposes of the CSP.

Sydney Trains operates two ISMS, one for IT and another for OT. Neither of these are certified to relevant ISMS Standards, however there have been conformance reviews of both IT and OT with relevant standards. These ISMS cover all crown jewels in the agency.

There are currently 11 ISMS in operation across the Transport cluster. TfNSW has proposed moving towards a holistic approach to these ISMS, with the CDP Board responsible for governing the available security controls and directing agency IT and OT teams to implement these.

Agencies are not routinely conducting audits of third-party suppliers to ensure compliance with contractual obligations

CSP mandatory requirement 1.5 makes agencies accountable for the cyber risks of their ICT service providers and ensuring that providers comply with the CSP and any other relevant agency security policies. The ACSC has provided advice on what organisations should do when managing third party suppliers of ICT. The ACSC advises that organisations should use contracts to define cyber security expectations and seek assurance to ensure that these contract expectations are being met. While both agencies usually include specific cyber security expectations in contracts, neither is routinely seeking assurance that these expectations are being met.

The NSW Government has mandated the use of the 'Core& One' contract template for low-value IT procurements and the Procure IT contract template for high-value IT procurements. Both of these contracts contain space for the procuring agency to include cyber security controls for the contractor to implement. The Procure IT contract template also includes a right-to-audit clause which allows agencies to receive assurance around the implementation of these controls. TfNSW and Sydney Trains used the mandated contracts for relevant contracts examined as part of this audit.

TfNSW included security controls in all the contracts examined as part of this audit. Compliance with ISO27001 was the most commonly stated security expectation. Of the contracts examined as part of this audit, only one contract did not have a right-to-audit clause. This contract was signed in October 2016. While these clauses are in place, TfNSW rarely conducted these audits on its third-party providers. Of the eight TfNSW contracts examined in detail, only two of these had been audited to confirm compliance with the stated security controls.

Sydney Trains included security controls in all but one of the contracts examined as part of this audit. Sydney Trains did not require contractors to be compliant with ISO27001, but only required compliance with whole-of-government policies. Sydney Trains does not routinely conduct audits of its third-party suppliers, however it did conduct deep-dive risk analyses of its top ten highest risk IT suppliers. This involved a detailed review of both the suppliers' security posture and also the contract underpinning the relationship with the supplier.

The CDP funding for 2020–21 includes a workstream for strategic third-party contract remediation. This funding is to conduct some foundational work which will allow the CDP to make further improvements in future years. While this funding will not address gaps in contract requirements or management across all contracts, this workstream aims to reduce the risks posed by strategic suppliers covering critical assets. Similarly, work is currently underway as part of the CDP to conduct OT risk assessments for key suppliers to Sydney Trains in a similar way to the work undertaken for IT suppliers.

Sydney Trains has risk assessed its third-party suppliers but TfNSW has not done so

It is important to conduct a risk assessment of suppliers to identify high-risk contractors. This allows agencies to identify those contractors who may require additional controls stated in the contract, those who require additional oversight, and also where auditing resources are best targeted.

Sydney Trains has risk assessed all its IT suppliers and, as noted above, has conducted a deep-dive risk analysis of its top ten highest risk suppliers. TfNSW has not undertaken similar analysis of its key suppliers, however it has identified risks attached to each of its strategic suppliers and has documented these. As a result of not risk assessing its suppliers, TfNSW cannot take a targeted approach to its contract management.

TfNSW demonstrated poor records handling relating to the contracts examined as part of this audit

TfNSW was not able to locate one of the contracts requested as part of the audit's sample. Other documentation, such as contract management plans, could not be located for many of the other contracts requested as part of this audit. These poor document handling practices limits TfNSW's ability to effectively oversee service providers and ensure that they are implementing agreed controls. It also limits public transparency on the effectiveness of these controls.

The Transport cluster is not effectively implementing cyber security awareness training

Agencies are responsible for implementing regular cyber security education for all employees and contractors under mandatory requirement 2.1 in the CSP. TfNSW is responsible for delivering this training to the whole Transport cluster, including Sydney Trains. The Transport cluster has basic cyber awareness training available for all staff. TfNSW also offers additional training provided by Cyber Security NSW targeted at executives and executive assistants. While TfNSW has training available to staff, it is not delivering this effectively. TfNSW does not make training mandatory for most staff nor does it require staff to repeat training regularly. Even among those staff who have been assigned the training, completion rates are low, meaning that delivery is not effectively monitored. Cyber security training is important for building and supporting a cyber security culture.

TfNSW is responsible for creating and rolling out all forms of training to agencies within the Transport cluster. Both TfNSW and Sydney Trains have the same mandatory cyber awareness training that is automatically assigned to new starters. At the time of the audit, this training was not mandatory for ongoing staff. TfNSW does make additional cyber security training available to staff who can choose to undertake the training themselves, or can be assigned the training by their manager. All TfNSW cyber security training is delivered via online modules and it is the responsibility of managers to ensure that it is completed.

Cyber security training completion rates for both TfNSW and Sydney Trains are low. Only 13.5 per cent of staff across the Transport cluster had been assigned the Cyber Safety for New Starters training as of January 2021. Although this course is mandatory for new starters, only 53 per cent of staff assigned the Cyber Safety for New Starters training module had completed the course by January 2021. As a result, only 7.2 per cent of staff across the entire Transport cluster had completed this training at that time. In Sydney Trains, less than one per cent of staff had completed this training as at January 2021 and a further 7.6 per cent of staff have completed the 'Cyber Security: Beyond the Basics' training. These low completion rates indicate that TfNSW is not effectively rolling out cyber security training across the cluster.

In October 2020, the Department of Customer Service released 'DCS-2020-05 Cyber Security NSW Directive - Practice Requirement for NSW Government', which made annual cyber security training mandatory for all staff from 2021. In line with this requirement, TfNSW has advised that it will be gradually implementing mandatory annual training from July 2021 for all staff.

The Transport cluster undertakes activities to build a cyber-aware culture in accordance with the CSP, but awareness remains low

Increasing staff awareness of cyber security risks and maintaining a cyber secure culture are both mandatory requirements of the CSP. While TfNSW does undertake some activities to build a cyber aware culture, awareness of cyber security risks remains low. This can be demonstrated by the low training rates outlined above, and the 'Spot the Scammer' exercise, described in Exhibit 7. TfNSW is responsible for delivering these awareness raising activities across the cluster.

TfNSW frequently communicates with staff across the Transport cluster about various cyber security risks through multiple avenues. Both agencies use the intranet, emails and other awareness raising activities to highlight the importance for staff to be aware of the seriousness of cyber risks. Advice given on the intranet includes tips for spotting scammers on mobile phones, promoting the cluster-wide training courses, as well as various advice that staff could use when dealing with cyber risks in the workplace.

In addition to these awareness raising activities, TfNSW has also undertaken a cluster-wide phishing email exercise called 'Spot the Scammer'. This is outlined in Exhibit 7. This exercise was carried out in 2019 and 2020 and allowed the Transport cluster to measure the degree to which staff were able to identify phishing emails. As can be seen in Exhibit 7, the results of this exercise indicate that staff awareness of phishing emails remains low.

Exhibit 7 - Spot the Scammer exercise
In both 2019 and 2020, TfNSW performed a ‘Spot the Scammer’ exercise in which they sent out over 25,000 emails to staff based on a real phishing attack in order to measure awareness and response. The exercise tested staff 'click through rate', the percentage of staff who clicked on the fake phishing link. In 2019, these results were then compared to industry benchmarks, with over a 20 per cent click through rate being considered 'very high'. Both TfNSW and Sydney Trains were considered to have a ‘very high’ click through rate in comparison to these benchmarks in both 2019 and 2020. This indicates that staff awareness of phishing emails was low. The click through rate for TfNSW was 24 per cent in 2020, an increase from 22 per cent in 2019. For Sydney Trains, the click through rate in 2020 was 32 per cent, which was a decrease from 40 per cent in 2019.
Source: Audit Office analysis of TfNSW documents.

Appendix one – Response from agencies

Appendix two – Cyber Security Policy mandatory requirements

Appendix three – About the audit

Appendix four – Performance auditing

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #353 - released (13 July 2021).

Published

Actions for Grants administration for disaster relief

Grants administration for disaster relief

Treasury
Finance
Compliance
Fraud
Management and administration
Project management

What the report is about

The report examined whether NSW Treasury, Service NSW and the Department of Customer Service effectively administered grants programs funded under the $750 million Small Business Support Fund, including:

  • $10,000 Small Business Support Grant
  • $3,000 Small Business Recovery Grant.

What we found

The agencies effectively implemented the grants within required timeframes, reflecting the NSW Government’s decision to deliver urgent financial support to small businesses impacted by the COVID-19 pandemic.

NSW Treasury met urgent timeframes to design the grants and Service NSW made timely payments in line with the grants' objectives and eligibility criteria.

Service NSW and the Department of Customer Service strengthened processes to detect and minimise fraud in response to identified external fraud risks, and to investigate suspected fraudulent applications.

Fraud security checks and investigations are ongoing, and the agencies will not know the full extent of fraud across the grants until these processes have been completed.

The agencies regularly monitored and reported on the timeliness of payments to small business applicants but have not yet measured all benefits of the grants programs.

The $10,000 Support Grant and the $3,000 Recovery Grant have provided around $630 million in one off grant payments to eligible small businesses.

What we recommended

NSW Treasury should finalise and implement an evaluation of both grants programs, including obtaining feedback from businesses.

Service NSW should develop a framework that documents expected controls for how it administers grants, including business processes, fraud control and governance and probity requirements.

Service NSW should publish information on all grants programs, including grants distribution and uptake.

The Department of Customer Service should ensure its processes for managing conflicts of interest meets its policy requirements.

Upcoming performance audit

The Audit Office is conducting a further performance audit into grants administration for disaster relief focussing on bushfire grants. This is planned to complete in 2021-22.

Fast facts

Small Business Support Fund
  • $630m Grant payments made to small businesses under two grants administered
  • Over 52,500 Applications received a $10,000 Grant payment
  • Over 23,000 Businesses paid both $10,000 Support Grant and $3,000 Recovery Grant
  • 36,700 Applications received a $3,000 grant payment
Grant program administration
  • 11 Days taken to deliver the $10,000 Small Business Support Grant application website
  • 26 Days taken to deliver the $3,000 Small Business Recovery Grant application website

Further information

Please contact Ian Goodwin, Deputy Auditor-General on 9275 7347 or by email.

The NSW Government responded to the partial shutdown of the NSW economy caused by the COVID-19 pandemic in 2020 by, among other measures, announcing on 3 April 2020 that it would place $750 million into the Small Business Support Fund (the Fund).

Under the Fund, the NSW Government would pay one-off grants of up to $10,000 to small business impacted by the shutdown. The objectives of the $10,000 Small Business Support Grant ($10,000 Support Grant) were to:

  • ease the pressure on small businesses that have been affected by the COVID-19 pandemic
  • support the ongoing operations of small businesses highly impacted by the COVID-19 restrictions
  • deliver cash-flow into small businesses as soon as possible so that small businesses could meet pressing financial needs.

Grant applications were assessed against eligibility criteria that were determined by the NSW Government. The eligibility criteria for the $10,000 Support Grant required an employing small business to demonstrate it was significantly impacted by the COVID-19 pandemic by self-declaring or demonstrating a significant decline of 75 per cent or more in turnover compared to 2019. Documentation requirements were relaxed for small businesses within highly impacted industries.

In June 2020, the NSW Government announced a second round of one-off grants of up to $3,000 to small businesses that were highly impacted by the COVID-19 pandemic ($3,000 Recovery Grant). The objective of the $3,000 Recovery Grant was to help small businesses in 'highly impacted industries' — those directly impacted by the restrictions and closures put in place under the Public Health Orders — to meet the costs of safely reopening or scaling up operations.

The eligibility criteria for the $3,000 Recovery Grant required that a small business be in a highly impacted industry, demonstrate that it was significantly impacted by the COVID-19 pandemic by declaring a significant decline in turnover, and had costs associated with reopening under the 'COVID-Safe' requirements.

NSW Treasury and Service NSW implemented both grants on behalf of the NSW Government. The process of applying for a grant was intended to be quick and easy, with Service NSW using automated assessments and simple online application forms to process applications. Applicants applied for the $10,000 Support Grant through the Service NSW website between 14 April 2020 to 30 June 2020 and applied for the $3,000 Small Business Recovery Grant between 1 July 2020 and 31 August 2020.

At May 2021, around $520 million has been paid to over 52,500 grant applicants under the $10,000 Support Grant and around $109 million had been paid to around 36,700 grant applicants under the $3,000 Recovery Grant.

The Audit Office plans to undertake a performance audit into grants administration for disaster relief focussing on bushfire grants in 2021–22.

This audit assessed whether the grants funded under the $750 million Small Business Support Fund were effectively administered and implemented to provide disaster relief. It addressed the following questions:

  • Were funded grants programs planned, designed and targeted effectively?
  • Were funded grants programs implemented in line with the objectives and criteria and delivery requirements?
  • Have agencies established measures to monitor intended benefits and outcomes?

This audit did not seek to assess the effectiveness of any other grant programs or stimulus measures. It also did not seek to assess the impact of the funding on applicants, or the future prospects of small businesses that received support.

Conclusion

NSW Treasury and Service NSW effectively implemented two grants within required timeframes reflecting the NSW Government's decision to deliver urgent financial support to small businesses impacted by the COVID-19 pandemic in 2020. The $10,000 Support Grant and the $3,000 Recovery Grant have provided around $630 million in one-off grant payments to eligible small businesses.
NSW Treasury met urgent timeframes to design the grants and Service NSW made timely payments in line with the grants' objectives and eligibility criteria.

NSW Treasury met urgent timeframes to provide advice to the NSW Government on the grant design, proposed delivery partner, expected numbers of eligible businesses and the suitability of the proposed grant payment amount within the required timeframes. This was achieved within one day for the $10,000 Support Grant and within four days for the $3,000 Support Grant. In the context of the complex and changing pandemic and economic conditions between March and July 2020, NSW Treasury's advice to government outlined the risk, feasibility, expected demand estimates and assumptions for the grants.

NSW Treasury's demand projections were limited by uncertainty as to the pandemic's economic impact. Estimated demand for the grants was not met, resulting in around $120 million from the Small Business Support Fund remaining unspent.

Service NSW met urgent timeframes to stand-up both grants: 11 days for the $10,000 Support Grant and 26 days for the $3,000 Recovery Grant. It met agreed delivery requirements and made timely payments to small businesses in line with the grants' objectives and eligibility criteria. Over 65,000 businesses have received a payment under either grant, and over 23,000 businesses received both grants.

Gaps in project and risk management processes were expected given the tight timeframe to implement the grants.

The tight timeframe in which the agencies had to implement the grants contributed to gaps in project and risk management. The agencies advised that compromises were understood by both parties and were a necessary trade-off to ensure payments were made quickly.

Service NSW and the Department of Customer Service have acted to strengthen their processes to detect and minimise fraud in response to identified external fraud risks and to investigate suspected fraudulent applications since the grants commenced. Service NSW intends to further enhance fraud controls for grants applications and payments for future grants by implementing a fraud control framework by December 2021.

The agencies regularly monitored and reported on the timeliness of payments to small business applicants but have not yet measured all benefits of the grants programs.

Service NSW and NSW Treasury established processes to monitor and report on the timeliness of payments to grant applicants.

NSW Treasury has not yet measured all intended impacts of the grants, nor undertaken processes to obtain detailed feedback from grant recipients. Without these measures, there is limited insight into the extent to which the grants helped to support small businesses or ability to capture lessons which could be applied in future grants programs. NSW Treasury advises that an evaluation will commence from mid-2021.

1. Key findings

Around $630 million in timely one-off grant payments have been made to small businesses

Service NSW and NSW Treasury have paid around $630 million in one-off grant payments to small businesses via two grants administered under the $750 million Small Business Support Fund. At May 2021:

  • around $520 million has been paid to over 52,500 grant applications received for the $10,000 Small Business Support Grant ($10,000 Support Grant)
  • around $109 million has been paid to 36,700 grant applications received for the $3,000 Small Business Recovery Grant ($3,000 Recovery Grant).

Across both grants, over 65,000 small businesses received a payment across either grant, and over 23,000 businesses received payments under both grants.

NSW Treasury advise that, while no data was collected on the time to pay applicants for the $10,000 Support Grant, from its monitoring of the grants' outputs it was satisfied that payment timeframes met its expectations. Service NSW met its targeted time to pay applicants with payments made within ten days for the $3,000 Recovery Grant.

Funds for both grants were not fully spent due to limitations in data and uncertainty of the COVID-19 pandemic's impact. At May 2021, the final demand for the $10,000 Support Grant was around 30 per cent less than initially anticipated and the final demand for the $3,000 Recovery Grant was around 40 per cent less than initially anticipated.

NSW Treasury developed proposals establishing high level design and delivery expectations within rapid timeframes

NSW Treasury put forward proposals to the NSW Government for the two grants administered under the $750 million Small Business Support Fund. It met rapid timeframes for producing this advice: within one day for the $10,000 Support Grant and within four days for the $3,000 Recovery Grant. NSW Treasury's advice to the NSW Government on how to best target the total funding, eligibility criteria and the feasibility of delivering the grants through Service NSW was based on comparable grants programs – including the $10,000 Small Business Bushfire Support Grant – which at that time were ongoing.

The proposals established, at a high-level, the rationale for the grants, expected financial costs, risks and analysis on budget impacts, and confirmation that Service NSW could deliver the grants applications platform. NSW Treasury's demand projections were uncertain due to limited data in the early stages of the pandemic regarding potential economic impact.

Given the tight timeframes, the proposals did not fully consider all planning and design aspects for both grants. For example, there was minimal identification of the costs and benefits of the programs, and a lack of detailed design and delivery requirements. The proposals outlined that arrangements to finalise the risk management, controls, and auditing plan would be agreed by Service NSW and NSW Treasury before implementation.

In future circumstances where urgent advice on program design is required, NSW Treasury could set clearer expectations for the delivery agency, including fully considering costs, benefits and delivery requirements that could be carried through to project governance and implementation.

Service NSW implemented both grants in line with delivery expectations

Service NSW met urgent timeframes to stand-up both grants: 11 days for the $10,000 Support Grant and 26 days for the $3,000 Recovery Grant. Delivery expectations for each grant were established under a grant project agreement (grant agreement). Service NSW delivered the online application platform, assessment of applications, payments and reporting of the grants' uptake as per the grant agreements.

The urgent timeframes to deliver the grants contributed to gaps in Service NSW's project and risk management processes throughout the lifecycle of both grants. For example, the requirement to meet pressing timeframes for the $10,000 Support Grant launch meant agencies had reduced time to achieve sign-off on key documentation. As a result, important documents and processes – including the grant agreement, risk documentation and key business process and quality assurance processes – were not finalised ahead of launch.

Quality assurance and compliance processes for detecting fraud were not settled until after the conclusion of the applications for the $10,000 Support Grant, and were not completed until late 2020. Some project documents, including risk registers, communication plans and project briefs are still not finalised.

The longer timeframe to develop the $3,000 Recovery Grant meant that agencies were able to build on their understanding of the implementation requirements from the $10,000 Support Grant, and better document these expectations and understanding while ensuring that key documents and sign-offs were in place prior to launch.

Service NSW tightened its risk management and controls in response to evidence of fraudulent applications

In May 2020, Service NSW and the Department of Customer Service (DCS) were alerted to suspected fraudulent activity within grants administered by Service NSW. Initially, Service NSW anticipated that up to $8.8 million of the $10,000 Support Grant was at risk of exposure to fraudulent applications. However, Service NSW reported that, at April 2021, $1.9 million for the $10,000 Support Grant and $254,000 for the $3,000 Recovery Grant from paid applications were at risk of fraud exposure.

Following an internal review of the potential exposure to fraudulent or ineligible applications, Service NSW implemented additional automated security checks on applications, increased manual assessments of grant applications, established a dedicated taskforce for grants administration and engaged a unit within DCS to manage high-risk investigations.

Service NSW and DCS's increased governance and oversight has resulted in an established case management function, increased referrals to law enforcement, prioritised investigations of suspicious applications and the development of a 'Fraud Control Framework' aimed at addressing external fraud risks. Given Service NSW had limited experience in these processes in context of administering grant payments, such actions were an appropriate response.

Security checks and investigations of suspicious applications are ongoing. Service NSW will not know the full extent of fraud across the grants until these processes have been fully completed.

Service NSW and Department of Customer Service can improve how conflicts of interest are managed for future programs

Compliance with agency policies and processes to manage conflicts of interest and financial subdelegations demonstrates that investment decisions are being made by appropriately skilled and experienced staff, allowing agencies to operate efficiently, and reducing the risk of internal fraud.

DCS was unable to produce employee conflicts of interest declarations for the $10,000 Support Grant. Therefore, it is not known how many employees had completed conflicts of interest declarations for this round.

DCS provided information on conflicts of interest declarations for the $3,000 Recovery Grant. Twenty-nine per cent of declarations provided for employees undertaking grant assessments for the $3,000 Recovery Grant were incomplete at March 2021, and a further nine per cent were not finalised even though they indicated a real, potential or perceived conflict.

For future grants programs, ensuring compliance with conflicts of interest policies would help DCS and Service NSW to have greater confidence that conflicts of interest are appropriately identified and managed.

NSW Treasury has not yet measured all benefits or outcomes of the grants

In April 2021, NSW Treasury updated its evaluation plan for the $10,000 Support Grant and $3,000 Recovery Grant in support of an economic evaluation to commence from mid-2021. The updated evaluation plan outlines inputs, activities, and outputs as well as immediate, short term and medium term outcomes for both grants.

The evaluation will consider the extent to which both grants achieved their intended outcomes, and whether the economic benefits exceeded the costs to help inform decisions about the nature and design of any future small business support programs. This will complement, and feed into a broader review of all NSW Government COVID-19 stimulus measures.

Service NSW rapidly developed an approach to administer the grants

Over recent disasters, such as the 2019–20 bushfires and the COVID-19 pandemic, Service NSW has been responsible for administering grant programs on behalf of other government agencies.

Service NSW implemented both grants under its Project Management Framework and under each grant agreement with NSW Treasury as it does not have its own grants administration framework. To address the risks that emerged during delivery, Service NSW developed an approach to standardise and monitor the administration of the grants while they were being implemented.

Service NSW now has an opportunity to establish a grants administration framework, based on the processes, lessons and outcomes captured under the grants administration taskforce and in developing its fraud control framework. Embedding these processes into business as usual for grants administration will enable Service NSW to have a consistent set of expectations for controls, business processes and governance and probity requirements for future grants it implements.

2. Recommendations

By December 2021, NSW Treasury should:

1. finalise and implement an evaluation of the $10,000 Support Grant and $3,000 Recovery Grant, including obtaining direct feedback from businesses on how grant funds achieved the grant objectives.

By December 2021, Service NSW should:

2. develop a grants administration framework, which documents expected controls – including fraud controls – business processes and governance and probity requirements

3. publish information on all grants programs, including grants distribution and uptake.

By December 2021, the Department of Customer Service should:

4. ensure its process for managing conflicts of interest meets policy requirements by:

  • ensuring employees promptly declare any real, potential or perceived conflicts of interest
  • annually producing a list of conflicts of interest for records retention purposes
  • requiring a separate register of conflicts of interest declarations where a grant program is deemed as high risk.

3. Lessons for grants administered within urgent timeframes

The two grants this audit examined were administered within a context of urgent timeframes, and increased complexity and uncertainty about the impact of the COVID-19 pandemic. The following lessons are shared to assist sponsor and delivery agencies in administering future grants where rapid implementation is required.

Sponsor agencies should consider the following lessons:

1. develop an approach to define and measure benefits for rapidly developed programs and projects where a full business case and cost-benefit analysis is not feasible

2. establish common processes and expectations for co-administered grants:

  • periodically assure agencies' capability to deliver grants programs
  • agree and establish risk appetite statements with administering agencies
  • clearly establish expected performance levels and targets under any agreement

3. review the processes and outcomes of rapidly developed programs, capture lessons learned, and apply these in planning and delivering future programs.

Delivery agencies should consider the following lessons:

1. risk management and risk appetite:

  • perform robust assessment procedures to ensure risks associated with delivery of the project are identified
  • ensure the controls implemented adequately address identified risks
  • agree and document the acceptable risk appetite at the outset
  • review risk management processes after the grants are issued when unable to finalise risk management processes ahead of launch

2. grant agreements between NSW public sector agencies:

  • ensure agreements are finalised in a timely manner
  • ensure agreements clearly outline:
    • roles and responsibilities of both parties,
    • changes in scope of services provided
    • fees and charges applicable

3. frameworks for grants administration:

  • ensure that there is a common set of expectations in place to guide grants administration including standard controls and processes for managing risk, capturing lessons learned and reporting on outcomes.

Appendix one – Response from agencies

Appendix two – Summary of other COVID‑19 Stimulus and Support for small businesses in NSW in April 2020

Appendix three – Public Health Orders

Appendix four – Highly impacted industries

Appendix five – About the audit

Appendix six – Performance auditing

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #352 - released (24 June 2021).

 

Published

Actions for WestConnex: changes since 2014

WestConnex: changes since 2014

Transport
Compliance
Infrastructure
Internal controls and governance
Management and administration
Project management
Risk

What the report is about

The report examined whether Transport for NSW (TfNSW) and Infrastructure NSW (INSW) effectively assessed and justified major scope changes to the WestConnex project since 2014.

What we found

NSW Government decisions to fund WestConnex-related projects outside WestConnex's $16.812 billion budget have reduced transparency and understate the full cost of WestConnex.

The NSW Government's decision to separate Sydney Gateway from WestConnex has reduced transparency over the cost of the road component of Sydney Gateway. $1.76 billion of the cost to complete Sydney Gateway is funded outside the WestConnex budget.

Network integration costs, currently estimated at $2.3 billion, are also funded outside the WestConnex budget. Many of these costs are directly attributable to WestConnex and ought to be included in the reported budget.

The Parramatta Road Urban Amenity Improvement Program, costing $198 million, should also be included as part of the WestConnex reported budget.

Decisions to exclude or remove these elements from WestConnex without justification have seen $4.26 billion of projects funded outside the $16.8 billion budget.

Positively, robust analysis was used to develop and incorporate design improvements into the 2015 WestConnex Updated Strategic Business Case.

The separate components of WestConnex underwent all required assurance reviews. However, the NSW Government's assurance framework does not require ongoing ‘whole-of-program’ assurance for large and complex projects like WestConnex. The absence of a holistic review of WestConnex allows for some costs and benefits to avoid scrutiny.

What we recommended

TfNSW should:

  • review the impact of scope changes on project objectives, costs and benefits for complex infrastructure projects
  • ensure that estimated costs and benefits of works which are reasonably required to meet consent conditions are included in business cases for complex large infrastructure projects
  • establish centralised and project specific record keeping for major infrastructure projects.

Infrastructure NSW should provide transparent whole of program assurance on total costs and benefits when complex projects are split into sub-projects.

Government should consider enhancing public transparency of existing infrastructure assurance processes by requiring that large complex infrastructure programs undergo periodic review at a whole-of-program level.

Fast facts

  • $16.812b 2015 WestConnex business case budget
  • $2.3b current estimated cost of network integration works to enable WestConnex, funded outside the WestConnex budget
  • $1.76b cost to complete Sydney Gateway to enable WestConnex and also funded outside the WestConnex budget
  • $198m Parramatta Road Urban Amenity Improvement Program, originally part of WestConnex but now funded outside the WestConnex budget

WestConnex

WestConnex is a 33 km motorway network that will link the western and south‑western suburbs with the Sydney CBD and the Airport and Port Botany precinct. It will also connect with proposed future motorway links to the north shore, northern beaches, and southern Sydney. The project is being delivered in three stages, with completion scheduled for 2023.

When first conceived by Infrastructure NSW (INSW) in 2012, WestConnex was described as a single integrated concept. In August 2013, government approved a business case for an integrated concept of WestConnex, with an estimated cost of $14.881 billion (in nominal outturn costs). Transport for NSW (TfNSW) is the government agency (sponsor agency) accountable for the delivery of WestConnex in accordance with the business case. In August 2014, the NSW Government established the Sydney Motorway Corporation to fund, deliver and operate WestConnex.

In November 2015, the NSW Government publicly released an updated WestConnex business case with greater detail and design enhancements, which increased the estimated cost to $16.812 billion.

Subsequent to this update, further changes were made to the design, including realignment of the M4 to M5 Link connection to the Western Harbour Tunnel project, an expanded interchange at Rozelle, the deletion of the Camperdown Intersection, and the addition of the Iron Cove Link. The reported budget for WestConnex was not changed as a result of these design updates.

To fund WestConnex, Sydney Motorway Corporation consolidated a concessional loan of $2 billion from the Australian Government, private sector debt and equity funding from the State. The Australian Government also provided a $1.5 billion contribution to the State to partially fund construction of WestConnex.

In August 2018, the NSW Government sold 51 per cent of its stake in Sydney Motorway Corporation for $9.26 billion. At the time of writing, the NSW Government is in the process of selling its remaining 49 per cent stake of Sydney Motorway Corporation.

About this audit

In the course of delivering a complex major infrastructure project, it is reasonable to expect changes to the original design and scope. Changes may occur as the design moves from a high‑level concept to a detailed design for project delivery, as new risks or issues are identified, as demands change, or as other interdependent projects are approved. Changes can also occur in response to potential cost or delivery overruns which arise as a result of planning deficiencies. Where design and scope changes significantly change the project costs and/or expected benefits, the justification for these changes should be robust and transparent.

Following our 2014 performance audit, 'WestConnex: Assurance to the government', the NSW Government established the Infrastructure Investor Assurance Framework (IIAF) to improve accountability and transparency over major projects that are developed, procured, or delivered by government agencies. Under the framework, TfNSW, as project sponsor, is responsible for ensuring the WestConnex project meets all IIAF requirements. These include ensuring the project remains strategically aligned and viable, and benefits are on track. INSW is responsible for coordinating the assurance review process and reporting directly to NSW Cabinet on project delivery against time, budget and risks to project delivery.

The objective of this performance audit is to assess whether TfNSW and INSW effectively assessed and justified major scope changes to the WestConnex project since 2014.

 

Conclusion

Government decisions to separate WestConnex related projects and deliver them outside WestConnex's 2015 business case budget of $16.812 billion has understated the total cost of WestConnex achieving its objectives. The rationale for separating these elements from the WestConnex project scope has not been transparent. Together, these projects represent costs of $4.26 billion funded outside the $16.812 billion WestConnex budget.

Since 2015, the NSW Government has removed several projects from the scope described in the 2015 WestConnex business case, and funded them separately:
  • In mid‑2017, the Sydney Gateway became a separate project outside WestConnex. This project, estimated in 2015 to cost $800 million, now has an estimated cost of $2.56 billion. The project remains partly funded by an $800 million contribution from the $16.812 billion WestConnex budget, with $1.76 billion funded outside the WestConnex budget.
  • In late 2018, the Parramatta Road Urban Amenity Improvement Program became a separate project outside the 2015 WestConnex budget. This project was part of the 2015 WestConnex Business Case and is intended to create urban renewal opportunities around Paramatta Road. It is estimated to cost $198 million.

Work required to integrate WestConnex with existing roads ('network integration') was funded outside the $16.812 billion budget for the November 2015 WestConnex business case. TfNSW is obliged to deliver network integration works to meet the conditions of planning approval for WestConnex. As such, these costs should be included in the WestConnex budget. The current estimated cost of these network integration works is $2.3 billion.

The rationale to exclude or remove each of these elements from the WestConnex project scope has not been transparent, nor supported by robust analysis and justification. These elements are required for WestConnex to achieve its objectives. The additional project costs will also deliver additional benefits not included in the 2015 WestConnex business case. Removing them understates the total cost of achieving the objectives set out in the 2013 and 2015 WestConnex business cases.

WestConnex's complex financing arrangements further reduce transparency on costs.

Transparency over the total cost of WestConnex – including elements funded from other project budgets – is further limited by the project's complex financing arrangements.

Prior to 2018, the Audit Office provided assurance on costs borne and levied by Sydney Motorway Corporation and its controlled entities. Since the NSW Government sold its majority stake in WestConnex in August 2018, the Auditor‑General no longer has the mandate to provide this assurance. Considering this, and the lack of transparency on the cost of projects removed from the WestConnex project scope, there is no transparent or comprehensive view of the total cost to deliver WestConnex – nor of how these cost would be offset by the sale of the government's remaining stake.

There is no 'whole‑of‑program' assurance over the WestConnex program of works. This limits transparency and confidence that WestConnex will meet intended objectives within its budget.

After INSW conducted a gateway review of a draft of the 2015 WestConnex Business Case under the IIAF, the project was broken up into separate components to support staged delivery. Each of these projects, including the Sydney Gateway, as well as the Network Integration Program, underwent the required assurance reviews under the IIAF. INSW also provided monthly progress updates to government. These individual projects are, in themselves, significant in scale and complexity. Addressing them as discrete components for the purposes of the assurance review process is justified and there is no requirement under the IIAF to holistically review projects which together deliver final benefits of the WestConnex program. However, whole‑of‑program review would improve transparency over total costs and benefits.

In 2016, TfNSW revised the design of the M4‑M5 Link and Rozelle to address traffic and integration issues.

TfNSW identified that the concept designs used for the M4‑M5 Link and Rozelle Interchange in the 2015 WestConnex Business Case would not integrate well with surface roads, including the proposed Bays Precinct, and would result in increased traffic on Victoria Road and the ANZAC Bridge. Following a comprehensive review conducted in mid‑2016, TfNSW refined the design of the M4‑M5 Link and Rozelle Interchange to address these limitations without increasing the cost of delivery. TfNSW documented the rationale for the design changes, including how the changes improved on the original design to increase capacity, improve traffic conditions and create more open space.

1. Key findings

Government decisions to fund WestConnex related projects outside of WestConnex's $16.812 billion reported budget have reduced transparency over costs and understate the full cost of WestConnex

In 2015, the work required to integrate WestConnex with existing roads ('network integration') was funded as a separate project with an estimated cost of $1.534 billion outside the 2015 WestConnex budget of $16.812 billion. TfNSW then created the Network Integration Program to respond to the conditions of planning approval for WestConnex. The current estimated cost to deliver all network integration works is $2.3 billion.

Since the 2015 WestConnex Business Case, the NSW Government has removed several elements from the scope of WestConnex and funded them as separate projects, while keeping the published WestConnex budget at an estimated $16.812 billion. Projects removed include:

  • Sydney Gateway, currently costed at $2.56 billion (with an $800 million contribution from WestConnex)
  • Parramatta Road Urban Amenity Improvement Program, costed at $198 million in late 2018 and funded though new funding to the Greater Sydney Commission.

Together, these projects represent costs of $4.26 billion that are not included in the WestConnex budget, but are required for WestConnex to achieve the objectives of the 2013 and 2015 WestConnex Business Cases. The costs of these elements in supporting the objectives of WestConnex is not tracked centrally, and there is no single point of oversight over them. Exhibit 1 compares total WestConnex forecast costs (including related projects) between November 2015 and April 2021.

 

November 2015
($ million)

April 2021
($ million)
WestConnex
Stage 1
Stage 1A (M4 Widening) 497 517
Stage 1B (M4 East) 3,802 3,782
Total 4,299 4,299
Stage 2
King Georges Road Interchange 131 131
New M5 4,335 4,335
Sydney Gateway Contribution 800 800
Total 5,266 5,266
Stage 3
M4‑M5 Link and Rozelle Interchange 7,049 7,049
Urban renewal (Parramatta Road) 198 ‑‑
Urban renewal (Rozelle) ‑‑ 198
Total 7,247 7,247
Total reportable WestConnex 16,812 16,812

Exhibit 1: WestConnex and related projects forecast costs
  November 2015
($ million)
April 2021
($ million)
Related projects
Network integration 1,534 2,300
Urban renewal (Parramatta Road) ‑‑ 198
Sydney Gateway Road Component ‑‑ 1,760
Total 1,534 4,258

Source: AO research.

Many network integration costs are directly attributable to WestConnex and ought to be included in the reported budget for WestConnex

Prior to 2015, the scope of WestConnex included enabling works needed before or during construction, as well as funding for future works to address any adverse traffic outcomes created by WestConnex which become apparent after its opening. These works are also known as network integration works.

When government approved the 2015 WestConnex Business Case, it noted that the project would require $1.534 billion for network integration works to address the impacts of WestConnex on the road network. However, the WestConnex project budget of $16.812 billion did not include funding for network integration works. Instead, Roads and Maritime Services (RMS, now TfNSW) was to fund network integration through its normal budget allocation.

It is important to recognise these costs as part of the total WestConnex project cost because:

  • TfNSW created the Network Integration Program to respond to network traffic and transport elements of the planning conditions of approval for WestConnex granted by the then NSW Department of Planning and Environment under the Environment, Planning and Assessment Act 1979.
  • NSW Treasury guidelines for business cases note that accurate cost estimates include assessment of the financial impact of meeting the conditions of planning approval.
  • Travel time and vehicle operating cost benefits attributed to the WestConnex project in the 2015 WestConnex Business Case assume that some network integration works, then costed at $373 million, were in place.

Refer to Appendix two for more detail on network integration works.

Some of the projects in the WestConnex Network Integration Program provide community and place benefits, such as parklands and cycleways. These benefits have not been attributed to WestConnex. Additionally, some network integration works are likely to deliver additional traffic related benefits to WestConnex. As the Network Integration Program’s primary purpose is to meet the conditions of planning approval for WestConnex, TfNSW should attribute all the costs and benefits of the program to WestConnex.

To September 2021, the total funded cost of the Network Integration Program is approximately $2.077 billion. TfNSW estimates that it will need a further $222 million to complete all expected network integration works.

The NSW Government's decision to separate Sydney Gateway from WestConnex has reduced transparency and accountability for TfNSW's underestimation of the cost of the road component of Sydney Gateway

Sydney Gateway is a high‑capacity connection between the new St Peters Interchange and the Sydney Airport and Port Botany precinct. It includes a road and rail components. The road component was included in the scope of WestConnex in the 2015 WestConnex Business Case. The November 2015 design, which TfNSW costed at $800 million, involved separate roadways from the St Peters Interchange to the International terminal, and to the domestic terminals and Mascot airport precinct.

By October 2016, TfNSW was aware that the $800 million budget for Sydney Gateway was insufficient and revised the forecast cost for the road component to $1.8 billion. The original cost estimate did not sufficiently consider the cost of:

  • constructing a complex design adjacent to the airport precinct
  • obtaining access to land required for the project
  • managing environmental contamination.

On 9 August 2017, the then Minister for WestConnex announced that the Sydney Gateway project was not part of WestConnex.

The 2015 WestConnex Business Case notes that material changes to the WestConnex budget, funding, scope, or timeframe are subject to Cabinet approval processes. It states that, when seeking approval for material changes, the portfolio Minister will make a submission to the relevant Cabinet Committee. Changes in project scope required the approval of the then Cabinet Committee on Infrastructure and should have been endorsed by the WestConnex Interdepartmental Steering Committee.

TfNSW and the NSW Department of Premier and Cabinet (DPC) assert that there is no documentation to support the government’s decision to separate Sydney Gateway from the WestConnex Program, or the WestConnex Interdepartmental Steering Committee's endorsement of a submission to Cabinet seeking approval for the separation.

The established governance processes for major scope changes were not followed in this instance. The lack of transparency regarding government's decision to separate Sydney Gateway from WestConnex also reduces visibility of TfNSW's underestimation of the cost of delivering the road component of Sydney Gateway.

The November 2018 Final Business Case for Sydney Gateway, which was approved by the government, included an estimate of $2.45 billion (nominal outturn cost) for the road component. This estimate included an $800 million contribution from WestConnex. A more recent estimate (late 2020) for this project is $2.56 billion (nominal outturn cost).

The Parramatta Road Urban Amenity Improvement Program should be included as part of the WestConnex budget

A specific objective of the 2015 WestConnex Business Case was the creation of opportunities for urban renewal along and around Parramatta Road. The business case included an allocation of $198 million in the $16.812 billion WestConnex budget for the Parramatta Road Urban Amenity Improvement program, designed to implement aspects of the objective. In November 2018, the NSW Government removed the Parramatta Road Urban Amenity Improvement Program from the WestConnex program of works and reallocated the $198 million (inside the $16.812 billion WestConnex budget) for urban renewal works around the Rozelle Interchange. As part of this decision, government approved new funding of $198 million to the Greater Sydney Commission for the urban amenity program, outside the $16.812 billion WestConnex budget. This understates the cost of WestConnex meeting its objectives by $198 million.

There is no requirement for ongoing ‘whole‑of‑program’ assurance of the WestConnex program of works, including related projects

In August 2015, INSW conducted its first Gateway Review of WestConnex as a program consisting of composite projects. Following that review, TfNSW registered each of the components of WestConnex with INSW as individual projects, rather than keeping WestConnex registered as a program or mega‑project. This is not inconsistent with the IIAF and all WestConnex related projects, including Sydney Gateway and the Network Integration Program, have undergone independent assurance reviews as individual projects under the IIAF.

Once a program like WestConnex is broken down into its composite parts, there is no requirement for the sponsor agency (TfNSW) or INSW to provide independent assurance on the program as a whole until it is completed. This is then done as part of the Gateway review for benefits realisation, which examines whether project benefits are being measured and meet expectations. These individual projects are, in themselves, significant in scale and complexity. While addressing them as discrete components for the purposes of the assurance review process can be justified, the absence of strategic, holistic reviews of WestConnex allows for total costs and benefits to become opaque and avoid scrutiny. Programs of this scale require greater ongoing transparency on total costs and benefits in order to ensure confidence they will meet intended objectives within budget.

There is a lack of public transparency on the total costs and benefits of the WestConnex project

Prior to 2018, the Audit Office provided assurance on costs borne and levied by Sydney Motorway Corporation and its controlled entities. Since the NSW Government sold 51 per cent of its stake in WestConnex in August 2018, the Auditor‑General no longer has the mandate to provide this assurance. The Audit Office is also unable to provide any assurance regarding the performance of tolling concessions.

This means that the total costs of WestConnex, including those levied on road users through tolling, are not reported alongside the full cost of delivering the project. This information, and independent assurance over that information, would provide transparency and context to the outcome of government's sale of its interest in WestConnex.

To enhance the transparency of existing infrastructure assurance processes, government could consider requiring large and complex infrastructure programs to undergo periodic review at a whole‑of‑program level. This could take the form of annual reports to Parliament on the total costs and benefits of selected large and complex projects by the responsible agency. The reports could include an assessment of the cost to government and cost to the community of funding and financing. Independent assurance of the agency report would provide Parliament with greater confidence that infrastructure is delivered economically and providing value for money for the people of NSW.

The Australian National Audit Office provides similar assurance on selected Department of Defence acquisition projects as part of its annual Major Projects Report.

Design enhancements included in the 2015 WestConnex Updated Strategic Business Case were supported by robust analysis

The 2015 WestConnex Business Case contained more detail than the 2013 WestConnex business case. Design enhancements were made as a result of modelling analysis conducted over the two years since the 2013 business case. Enhancements included a full underground link between Kingsgrove and St Peters as part of the New M5 and re‑alignment of the M4‑M5 link tunnel (Stage 3) to include the Rozelle Interchange. The Rozelle Interchange will provide a direct connection to the Anzac Bridge and Victoria Road, and will enable a connection to the proposed Western Harbour Tunnel and Beaches Link. A map and description of these elements can be found at Exhibits 2 and 3 of this report.

In 2016, TfNSW revised the design of the M4‑M5 Link and Rozelle to address traffic and integration issues

As part of preparing the 2015 WestConnex Business Case, TfNSW prepared a Project Definition and Delivery Report (PDDR) for the M4‑M5 Link. This report describes the scope of the project, including a high‑level concept design. TfNSW identified limitations with the proposed design of the M4‑M5 in the PDDR, which it would need to address as the project moved to a detailed design stage. In particular, these limitations included:

  • poor integration with the Bays Precinct masterplan
  • traffic capacity constraints on Victoria Road and Anzac Bridge
  • construction complexity.

Following a comprehensive review in mid‑2016, TfNSW changed the design of the M4‑M5 Link and Rozelle Interchange to address these limitations. These changes included:

  • deletion of the Camperdown intersection to improve traffic conditions on Parramatta Road
  • a fully underground and larger Rozelle Interchange with 10‑hectare dedicated parklands
  • a toll‑free tunnel link from Iron Cove Bridge to Anzac Bridge
  • increasing the lanes in the dual tunnels from three to four each way.

TfNSW documented, but did not publish, the rationale for the design changes, including how the changes addressed the limitations of the previous design while providing increased community benefit through the creation of open space. TfNSW undertook cost comparison studies which estimated that these changes would have a neutral impact on the estimated project cost while achieving the same or improved benefits.

TfNSW's record‑keeping systems for large infrastructure investments negatively impact accountability and transparency

In response to our formal requests for relevant information, made during the conduct of this audit, TfNSW advised that complete and valid records of key decision‑making processes, analysis and advice were unavailable. Additionally, TfNSW often provided information that was incomplete or unverifiable (for instance, unsigned briefing notes). This is not consistent with accepted governance practices and does not comply with the requirements of the State Records Act 1998.

We also requested that TfNSW provide a list of relevant documents held by the Sydney Motorway Corporation (SMC). While TfNSW acknowledged that SMC may hold material relevant to the audit, TfNSW did not have a list or description of these documents. As SMC is now a majority privately held entity, both the Audit Office and TfNSW have limited power to require SMC to provide documentation.

The delivery timeframe for large and complex infrastructure projects such as WestConnex frequently exceeds five years, and some projects can take over a decade to deliver. These projects represent a significant investment of public resources and government agencies should expect independent review and assurance activities such as performance audits. The establishment of dedicated record keeping facilities for major infrastructure projects, such as data rooms, would improve transparency and accountability. This would ensure that the use of public resources is fully auditable in line with public expectations and the requirements of the Government Sector Finance Act 2018, the State Records Act 1998 and the Public Finance and Audit Act 1983.

2. Recommendations

By December 2021, TfNSW should:

1. review the impact of scope changes on project objectives, costs and benefits for complex infrastructure projects

2. when preparing business cases for complex large infrastructure projects, ensure that the estimated costs and benefits of works which are reasonably expected to meet consent conditions are included in the overall project cost and its benefits (as per Treasury guidelines)

3. establish and maintain centralised and project‑specific record keeping, including through dedicated project data rooms, to ensure major infrastructure projects can readily be subject to external oversight and assurance.

By June 2022, INSW should:

4. provide transparent whole‑of‑program assurance on total costs and benefits throughout the project life‑cycle when complex projects are split into sub‑projects.

By June 2022, NSW Government should:

5. consider enhancing the public transparency of existing infrastructure assurance processes by requiring that large complex infrastructure programs undergo periodic review at a whole‑of‑program level. This could take the form of reports to Parliament on the total costs and benefits on selected large and complex projects by the responsible agency, including cost to government and cost to community of funding and financing, as well as an accompanying independent assessment of the agency report.

Following our 2014 performance audit report 'WestConnex: Assurance to the government', the NSW Government established the Infrastructure Investor Assurance Framework (IIAF). INSW is responsible for the development, implementation and administration of the IIAF. The assurance framework involves gateway reviews, health checks, deep dive reviews, and project monitoring and reporting at various stages in the lifecycle of a project. The main aims of the IIAF are to help ensure major infrastructure projects are delivered on time and on budget, and to ensure that reports are regularly monitored by the Cabinet of the NSW Government. The IIAF gateway review process is compulsory for all significant investments and expenditure under the NSW Treasury Gateway Policy.

In accordance with the IIAF, INSW is responsible for the following:

  • providing a dedicated Assurance Team including Gateway Review Managers to coordinate Reviews
  • determining appropriate expert reviewers, and manages scheduling, commissioning and administration of Assurance Review reports. Infrastructure NSW is independent of the Expert Review Team
  • monitoring Tier 1 – High Profile/High Risk projects, Tier 2 and Tier 3 (if required) project performance through independent Assurance Reviews
  • providing independent analysis and advice on key risks and any corrective actions recommended for Tier 1 – High Profile/High Risk, Tier 2 and Tier 3 projects
  • escalating projects to Infrastructure Investor Assurance Committee (IIAC) and Cabinet where projects present ‘red flag issues’ and where corrective action is needed
  • working with delivery agencies to register all capital projects with an estimated cost greater than $10.0 million and ensures they are risk profiled and assigned a risk‑based project tier with an endorsed IIAF Project Registration report
  • preparing forward looking annual Cluster Assurance Plans
  • maintaining and continuously improves the IIAF process
  • reporting to the IIAC, Cabinet and Infrastructure NSW Board
  • regularly report to NSW Treasury on the performance of the IIAF.

In relation to WestConnex, TfNSW is the sponsor agency responsible for meeting relevant IIAF requirements, including:

  • registering and risk profiling projects
  • IIAF gateway, health check, and deep dive assurance reviews
  • regular reporting.

Under the IIAF, it is mandatory for all capital projects valued over $10.0 million to be registered with INSW. Capital projects can be registered either as a program (comprising of a group of related projects or activities) or as a project (which may or may not be part of a program).

According to the IIAF, programs tend to have a lifespan of several years and aim to deliver outcomes and benefits related to an organisation's strategic objectives. Projects tend to have a shorter lifespan, and deal with outputs. Projects can, however, be grouped under a single program if they are similar in nature or if they are aimed at collectively achieving a strategic objective. Complex projects can be delivered in multiple stages, under different contracts, and across different time periods.

The last assurance review of the entire WestConnex program of works as a whole was in 2015

INSW conducted the first IIAF gateway review of WestConnex in August 2015. TfNSW developed a draft WestConnex Updated Strategic Business Case to consolidate the latest analysis on WestConnex, and to confirm that the project remained fit for purpose, economically viable, and financially deliverable. The review followed a recommendation in our 2014 performance audit report that business cases be thoroughly revisited.

During September 2015, INSW conducted additional informal reviews to identify strategic risks associated with public release of the WestConnex business case. Subsequently, INSW gave the Premier of NSW its views on the draft business case, including the following points:

  • The $398 million budget for Sydney Gateway was insufficient to meet the benefits claimed in the business case for a ‘functional’ connection to Sydney Airport and Port Botany. INSW studies indicate a future‑proof solution would require a minimum spend of $755 million.
  • Enabling works for WestConnex estimated at $1.534 billion were excluded from the cost of WestConnex. Significant work remained for RMS to identify mitigation measures to address planning approvals and network performance issues.
  • Enabling works (a Southern Connector), an access ramp and surface road improvements within St Peters were excluded from the draft 2015 business case despite their inclusion in the WestConnex scope in the 2014–15 State Budget.
  • The overall cost of works not funded within the WestConnex budget ranged from $2.011 billion to $2.196 billion. This included the enabling works, access ramp and surface road improvements and the shortfall for Sydney Gateway.

All WestConnex related projects, including Sydney Gateway have undergone independent assurance reviews under the IIAF

Since INSW submitted the first WestConnex progress update report to Cabinet in June 2015, INSW has been reporting monthly on the different stages of the WestConnex Program, including Sydney Gateway, as the projects were registered with INSW as High‑Profile, High‑Risk projects. Separate reporting enabled INSW to report and review each stage with more detailed scrutiny, compared to the reporting and reviewing at a program level.

WestConnex Stage 2 (New M5) underwent both mandatory and non‑mandatory reviews at key points in the project lifecycle. Three mandatory gateway reviews – at Gate 2 (Final business case), Gate 3 (Readiness for market), and Gate 4 (Tender evaluation) – were conducted by TfNSW before the introduction of IIAF. Four non‑mandatory health check reviews and one non‑mandatory deep dive review were conducted after the introduction of the IIAF managed by INSW.

Similarly, WestConnex Stage 3 projects – M4‑M5 link, M4‑M5 Tunnels, and Rozelle Interchange – also underwent mandatory and non‑mandatory reviews at key points in their lifecycle under IIAF.

The M4‑M5 Link had two mandatory gateway reviews and one non‑mandatory health check review under IIAF. These reviews were conducted before Stage 3 was split into two stages, due to major design changes to the Rozelle Interchange and the M4‑M5 tunnels.

The M4‑M5 tunnels had two mandatory gateway reviews (at Gates 3 and 4), one non‑mandatory health check review, and one non‑mandatory deep dive review under IIAF.

Rozelle Interchange also underwent three mandatory gateway reviews at Gate 3 (part 1), Gate 3 (part 2), and Gate 4, two non‑mandatory health check reviews, and one non‑mandatory deep dive review under IIAF.

Since mid‑2017, the Sydney Gateway project has undergone required independent assurance reviews, as well as a number of optional assurance reviews

In November 2016, INSW conducted a mandatory Gate 1 gateway review on a strategic business case for the Sydney Gateway Project. TfNSW did not proceed with this business case. Following the separation of Sydney Gateway from WestConnex in mid‑2017, TfNSW developed a new business case for Sydney Gateway. It has undergone the required Gate 1, Gate 2, and Gate 3 gateway reviews, as well as two non‑mandatory health check reviews, and three non‑mandatory deep dive reviews under IIAF.

Network integration works have undergone all IIAF required assurance reviews

TfNSW completed a strategic business case for the Network Integration Program in August 2020, and INSW completed a gateway review in November 2020. This is despite network integration projects starting as early as 2015, with $645 million having been spent by June 2020. The strategic business case included a prioritisation process for completing remaining works in the program. Prior to November 2020, TfNSW registered individual network integration projects with INSW, and these projects have undergone gateway reviews where required.

The Network Integration Program strategic business case does not include Rozelle interchange network integration works ($353 million) and additional network integration works to settle a contractor claim adjacent to St Peters Interchange ($190 million). These were excluded from the business case on the basis they had already been approved by government, and as such were not subject to the prioritisation elements of the business case. TfNSW has not developed separate business cases for these works, although the scope of the St Peters Interchange works was developed through a negotiated process.

TfNSW did not prepare business cases for some network integration works which have commenced, including the $323 million Campbell Road/Euston Road works

Prior to its development of the August 2020 strategic business case, TfNSW did not prepare business cases for many network integration works that have commenced, and in some instances were completed, before 2019. Significantly, TfNSW did not prepare a business case for the Campbell Road/Euston Road works, which cost $323 million and have been completed.

In 2016, TfNSW’s Business Case Policy requires the creation of business cases for capital projects costing over $1.0 million. At the time of writing this report, TfNSW’s draft policy requires full business cases for capital projects costing $10.0 million or more.

There is no requirement for ongoing ‘whole‑of‑program’ assurance of the WestConnex program of works, including related projects

INSW conducted its first gateway review of WestConnex (as a program, which consisted of composite projects) in August 2015. Following that review, TfNSW registered each of the components of WestConnex with INSW as individual projects, rather than keeping WestConnex registered as a program or complex project. The IIAF allows this to occur.

Separate registration enabled INSW to report and review each stage with more scrutiny compared to whole‑of‑program level review.

Such an approach has merit, considering the individual stages (and components of these stages) are multi‑million dollar works in their own right. Each project has its own timing for gateway reviews at stages such as 'Readiness for Market' and 'Tender Evaluation'.

Once a program such as WestConnex is broken down into its composite parts, there is no requirement for the sponsor agency (TfNSW) or INSW to conduct independent assurance on the program of works as a whole until the whole program is completed as part of the Benefits Realisation (Gate 6) gateway review. The absence of strategic, holistic reviews of projects of the scale and complexity such as WestConnex during their delivery allows for total costs and benefits to become opaque and avoid scrutiny. Projects of this scale require greater ongoing transparency on total costs and benefits in order to ensure confidence they will meet intended objectives within budget.

INSW has advised us that it has prepared a proposal to expand its assurance function to include whole‑of‑program review of inter‑related infrastructure projects.

Appendix one – Responses from agencies

Appendix two – Network integration works

Appendix three – About the audit

Appendix four – Performance auditing

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #351 - released (17 June 2021).

Published

Actions for Delivering school infrastructure

Delivering school infrastructure

Education
Infrastructure
Management and administration
Project management

The Auditor-General for New South Wales, Margaret Crawford, released a report today examining the planning and delivery of new, redeveloped and upgraded public schools.

School Infrastructure NSW has identified the need to accommodate an additional 180,000 enrolments in public schools by 2039 with a large portion of this growth expected in metropolitan Sydney. It has also identified that around 34,000 teaching spaces will require upgrading to be fit-for-purpose.

Although School Infrastructure NSW has developed a long-term strategic plan that advises government of ongoing funding requirements, it has not presented a list of priorities to meet those needs. Developing a longer-term list of priorities would help signal the areas of greatest need and allow more time to develop the best options to meet those needs.

The audit found that School Infrastructure NSW has focused on delivering existing projects, election commitments and other government announcements. This has diverted attention from identifying and delivering projects that would have better met present and future needs. 

The report makes eight recommendations to improve long-term planning for future needs, strengthen the quality of estimated project costs and benefits, and embed a continuous improvement program. 

In 2016, the Department of Education prepared a School Assets Strategic Plan (2016 SASP) which outlined long-term funding needs to support the expected growth in enrolments to 2031. Following the release of the 2016 SASP, the NSW Government substantially increased funding for new and upgraded schools from $2.4 billion in the 2016–17 State Budget to $4.2 billion in 2017–18.

In 2017, the Department of Education established School Infrastructure NSW (SINSW) to lead the delivery of the 2016 SASP and the 123 new projects announced in the 2017–18 Budget. This significantly larger program of work required rapid development of internal capacity, governance arrangements, and project management systems. This needed to be done at the same time as scoping and planning for the list of announced projects.

As there are limited funds available to meet growing needs across the State, it is important that SINSW has effective methods to prioritise projects to communities with the greatest need. To ensure that projects deliver value for money, business cases need to have robust estimates of project costs and benefits. Business cases also need to account for the inherent risks in delivering infrastructure projects. Unplanned cost escalations can reduce the number of new or modernised classrooms SINSW can deliver. Unforeseen delays may also impact families who make significant life choices based on their expectations that a school will open at the beginning of the school year.

The objective of this audit was to assess the effectiveness of planning and delivery of new, upgraded and redeveloped schools to meet demand for public school education in New South Wales. To address this objective, the audit examined whether the Department:

  • has effective procedures for planning and prioritising school capital works to meet present and future demands
  • develops robust business cases for school capital works that reliably inform decision-making
  • has effective program/project governance and management systems that support delivering projects on-time, within budget and achievement of intended benefits.

The audit examined business cases for 12 projects as case studies. These include a mix of projects initiated before and after the establishment of SINSW.

This audit commenced in June 2020 and examined strategies and demographic projections developed prior to the emergence of COVID-19. This audit did not examine potential longer-term impacts of COVID-19 on future demands for public school education.

Conclusion

School Infrastructure NSW has been focused on delivering existing projects, election commitments and other government announcements. This has diverted attention from identifying and delivering projects that would have better met present and future student and classroom needs. While it has developed a long-term strategic plan that advises government of ongoing funding requirements, it has not presented a list of priorities to meet these needs.

In its first years of operation, SINSW has focused on delivering existing projects and the 123 new projects announced in the 2017–18 Budget. Further NSW Government announcements in the 2018–19 Budget, election commitments in the 2019–20 Budget, and announcements in the 2020–21 Budget, made up the majority of new projects, rather than projects prioritised by SINSW. 

In early 2020, SINSW advised the NSW Government that the currently funded infrastructure program would not meet forecast classroom requirements for 2023 and beyond. The School Asset Strategic Plan 2020 estimates the annual level of investment needed over the next 20 years to meet growth, update and upgrade facilities to meet compliance obligations. However, SINSW’s ten-year Capital Investment Plans for 2018–19, 2019–20 and 2020–21 only identified priorities over a two-year horizon.

Developing a longer-term pipeline of priorities would signal the areas of greatest need and allow greater scope to consider a range of options to best meet those needs.

SINSW has made progress in planning across geographic areas but needs to better prioritise which projects move forward.

Given the current and projected needs for new classrooms, it is vital that SINSW provides long-term advice based on thorough state-wide analysis to help prioritise projects that best meet this demand.

SINSW has improved its capabilities, processes, and systems to support planning in ‘School Community Groups’, which are clusters of between 5 to 15 schools in a geographic area. This addresses a key direction identified in the School Assets Strategic Plan 2016. It has developed a planning tool which allows it to prioritise School Community Groups based on weighted criteria. It has also developed an approach to identify potential projects within School Community Groups but has not yet put in place a structured process to prioritise which projects move to the business case stage to seek funding for delivery.

Business cases we examined established service needs, but several had shortcomings in scope definition, cost estimation and risk identification.

Most business cases we examined demonstrated the service need and consultation with stakeholders helped to incorporate educational requirements. Common templates and specific cost-benefit guidance developed in partnership with NSW Treasury has helped to promote consistency across business cases.

However, there were shortcomings in several business cases we reviewed. Business cases for projects already announced by government presented a limited number of options, and the process for eliminating other options was not transparent. Cost increases and contingency drawdowns for several projects indicate that scoping, costing and risk assessments could be improved, especially for complex projects.

Standard program management systems and governance arrangements support project delivery, however, there is scope for better ongoing oversight of benefits.

SINSW applies standard governance arrangements to projects based on their size. Higher value projects have executive oversight while lower value projects are overseen on a regional basis. SINSW has improved its project management systems to provide more consistent data and greater transparency to senior management over project status, cost and use of contingencies.

SINSW has worked with NSW Treasury to define a consistent set of benefits for new and redeveloped schools. Estimated benefits are currently based on international contexts but SINSW advises it is undertaking further research to improve the evidence base in this area. The current approach to ongoing monitoring, reporting and evaluation of project benefits places responsibility on the infrastructure delivery team. This team is not the most appropriate area to monitor ongoing benefits, which are expected to accrue many years after delivery and depend on actions in other areas of the Department.

1. Key findings

SINSW delivered projects against an established program of works in its first years of operation

At establishment, SINSW inherited a portfolio of existing projects and 123 new projects announced as part of the 2017–18 Budget (to commence over 2017–18 and 2018–19). It has progressively worked through individual project planning to deliver against these projects.

The 2018–19 Budget funded two new projects that had not already been announced. Both projects were identified by SINSW as a priority. The 2018–19 Budget also allocated funding for 'planning' 22 new projects. Seventeen of the 22 projects had been identified by SINSW as a priority.

SINSW identified 31 new priority projects in its Capital Investment Plan for 2019–20. Thirteen of these projects were funded in that year with a further 27 projects included as election commitments. SINSW identified 20 new projects in its Capital Investment Plan for 2020–21 but only two of these were funded. SINSW advised this was due to a constrained budget environment.

There is an anticipated shortfall of classrooms based on the current funded program

Despite increased funding since 2017–18, SINSW advised the NSW Government in early 2020 that the currently funded infrastructure program would not meet forecast classroom requirements for 2023 and beyond. Accordingly, it is vital that new funding is prioritised to projects which best meet demand.

SINSW only identified specific priorities over a two-year horizon in its Capital Investment Plans for 2018–19, 2019–20 and 2020–21. The School Assets Strategic Plan 2016 and the 2020 update make the case for sustained funding for school building and redevelopment. These plans estimate annual funding requirements and show geographic areas with increasing forecast enrolments. Detailing how priorities over a ten-year timeframe fit within a ten-year capital planning limit would create more certainty about meeting growth demands.

There has been progress in formalising prioritisation frameworks, data tools and supporting governance arrangements

SINSW committed to planning for new and redeveloped schools in 'School Community Groups' in the School Assets Strategic Plan 2016. This is a new way of planning which considers the educational needs over a defined geographical area. It has developed a planning tool to prioritise School Community Groups based on weighted criteria. It has also established governance frameworks to improve transparency over decisions to reprioritise this list.

SINSW has refined its approach to planning in School Community Groups over the past four years. It now prepares Service Needs Reports to investigate needs, identify projects, prioritise, determine scope and timing, and assess non-capital options. SINSW has yet to finalise arrangements for how needs identified in Service Needs Reports progress to the strategic business case stage.

Projects announced prior to developing a business case have less opportunity to consider a range of options to meet the service needs

Business cases for projects already announced by government (or announced for planning) go through the same process of determining the service need and impacts on surrounding schools. However, for some announced projects, the range of options considered in the business case is influenced by the parameters of the announcement. This makes it more difficult to genuinely pursue alternate options that could better meet the identified service need.

Projects identified by SINSW have a more rigorous process of considering options. Service Needs Reports explore a wide range of asset and non-asset interventions across the School Community Group. Options are narrowed as the projects move through the strategic and final business case stages. SINSW uses its Investment Review Committee to engage key stakeholders early in the process so that they are informed about how non-asset solutions have been considered and why SINSW is progressing the business case for a capital solution for particular projects.

Several business cases underestimated project costs and risks, leading to scope and budget increases

Several business cases we reviewed did not adequately identify the initial scope requirements, project-specific risks or the likely project cost. For two business cases, this appeared to be due to an attempt to fit the project within a predetermined amount. Announcing a project’s scope, budget and timeframe before proper planning increases risks to successful delivery against expectations.

Several of the projects we examined required drawdowns on contingency funds due to inadequate consideration of scope, costs and project risks at the planning stage. Contingency funds are intended for unanticipated extra costs rather than those that could have or should have been identified at the planning stage.

Guidance on benefit calculations has provided a consistent framework for business cases

Business cases we examined presented a consistent set of benefits based on guidance developed in partnership with NSW Treasury. Following this guidance helps to compare cost-benefit analyses across business cases. However, the evidence for the estimated benefits is based on contexts outside of NSW. SINSW has the tools and data sources to calculate benefits more suited to the context of particular schools. Doing so would improve the accuracy of cost-benefit analyses. SINSW advised that it is currently updating the guidance in partnership with NSW Treasury.

SINSW involves school principals, executives and teaching staff in developing education rationales when commencing projects. These documents help align projects with education outcomes. They also provide a baseline for post-occupancy evaluation, which is important to determine whether the new school infrastructure is being used in the ways that were anticipated in the business case.

SINSW could elevate its existing assurance review process to consolidate lessons learned

SINSW engages external peer reviewers to conduct assurance reviews on its projects at multiple stages of planning and delivery. It has established a Community of Practice for external reviewers to keep them up to date on new developments and requirements. Higher value projects are also subject to review by Infrastructure NSW under the Investor Assurance Framework.

By looking at all projects at all stages, assurance reviews can identify systematic issues across the full portfolio of projects. A recent assurance review analysed common findings from reviews of strategic and final business cases. This provides a helpful way to improve internal processes. SINSW advised that it is implementing a continuous improvement program, which will be able to take findings from assurance reviews to build organisational capabilities.

2. Recommendations

By September 2021, the Department of Education should:

  1. finalise the investment prioritisation approach with agreement from key stakeholders
  2. finalise and update on an ongoing basis a ten-year list of priorities to meet the forecast demand for new classrooms and contemporary fit for purpose learning environments, which identifies individual projects and programs in the short-term and priority geographic areas and programs in the medium-term
  3. seek a ten-year Capital Planning Limit from NSW Treasury to ensure the needs identified in the ten-year list of priorities are met and are coordinated with the forward capital programs of other agencies
  4. improve the quality of data on cost benchmarks that underpin the annual ten-year Capital Investment Plan and updates to the School Assets Strategic Plan
  5. embed an evidence-based cost benefit analysis framework for school investment, in consultation with NSW Treasury, by:
    • validating benefits estimated in previous business cases with actual results
    • building the evidence base in relation to contemporary learning environments
  6. regularly share data on forecast needs with relevant planning agencies to promote strategic opportunities for servicing education needs
  7. implement the continuous improvement program for service planning, options assessment, business case development, project delivery and handover. The program should be informed by findings from assurance reviews, post-occupancy evaluations and project lessons learned
  8. establish benefits realisation processes and practices that:
    • ensure business cases set baselines and targets for benefits
    • review benefits during delivery, prior to handover and as part of Post Occupancy Evaluations
    • identify which part(s) of the Department are best placed to develop, manage and evaluate benefits on an ongoing basis.

Note:

The Department's formal response to this report at Appendix one states that while it 'supports the recommendations, it considers the proposed six-month timeframe to be an unreasonably short period for a large and complex organisation to effectively implement many of these recommendations'. It suggests 12 months would be needed to implement the recommendations.

The recommendations stemming from this audit are core business for SINSW. The Audit Office considers it important for SINSW to place priority on implementing the recommendations in time to inform the 2022–23 budget cycle. Extending the deadline to April 2022 would place action outside of that budget cycle.

There have been significant increases in funding for education infrastructure since the 2017–18 Budget and further growth in demand for places in schools is forecast. SINSW has the challenge, not only of meeting the need for new classrooms due to population growth, but also upgrading facilities to enable modern teaching techniques. In addition, community expectations of what constitutes a vibrant and successful school community continues to increase.

Given growing demand and budget constraints, projects must be selected to best meet the needs of the community and planning and prioritisation are vital. SINSW has been progressing planning for announced projects as well as implementing a new type of strategic state-wide planning and prioritisation, cluster planning, where options are developed for School Community Groups.

The primary role of a business case is to reliably inform an investment and/or policy decision. Over the period of review, the NSW Government's guidelines for business cases have established this requires recommendations based on convincing arguments, sufficient evidence, and accurate costing of alternatives and expected benefits. Business case guidelines are underpinned by guides for economic appraisal and cost-benefit analysis.

As SINSW moves to prioritise business cases for interventions in School Community Groups, it will increasingly need to demonstrate rigour in its assessment of all options. It will also need to ensure that scope identification, cost and risk planning and the setting of contingencies are accurate. This will help decision-makers better understand, plan for and manage the investment required to meet the demand for school infrastructure.

For this audit, we examined business cases and related documentation for 12 projects. Several of these projects were developed before School Infrastructure NSW was established in mid-2017.

Over the period of review, NSW Government policies for business case development and submission have emphasised that effective governance arrangements are critical to a proposal's successful implementation.

SINSW's guidance similarly highlight the importance of effective governance and project management for achieving good outcomes. It prescribes a general governance structure managed by SINSW that can be tailored to the planning and delivery of school infrastructure projects.

Appendix one – Response from agency
 
Appendix two – About the audit 

Appendix three – Performance auditing 


Copyright Notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #347 - released (8 April 2021).

Auditor-General’s Report to Parliament on Delivering School Infrastructure 

This corrigendum has been prepared to amend the following text within my Auditor-General’s Report to Parliament on Delivering School Infrastructure, dated 8 April 2021. 

On page two, the original text was as follows: 

Further NSW Government announcements in the 2018–19 Budget and election commitments in the 2019–20 Budget made up the majority of new projects, rather than projects prioritised by SINSW. 

The original text has now been changed to 

Further NSW Government announcements in the 2018–19 Budget, election commitments in the 2019–20 Budget, and announcements in the 2020–21 Budget, made up the majority of new projects, rather than projects prioritised by SINSW. 

On page three, the original text was as follows: 

The 2018–19 Budget funded three new projects that had not already been announced. One of the three projects was identified by SINSW as a priority. 

The original text has now been changed to: 

The 2018–19 Budget funded two new projects that had not already been announced. Both projects were identified by SINSW as a priority. 

On page three the original text was as follows: 

SINSW identified 33 priority projects in its Capital Investment Plan for 2019–20.

The original text has now been changed to  

SINSW identified 31 new priority projects in its Capital Investment Plan for 2019–20. 

On page eleven, in Exhibit 4, the original text was as follows: 

The 2018–19 NSW Budget announced funding for an additional 43 new and upgraded schools to commence works in 2018–19. Of the 43 projects: 

•    1 was identified by SINSW as a priority in its Capital Investment Plan (SINSW requested funding for one new project)
•    40 had already been announced
•    2 were new announcements (not identified as a priority by SINSW in its Capital Investment Plan).

The original text has now been changed to: 

The 2018–19 NSW Budget announced funding for an additional 42 new and upgraded schools to commence works in 2018–19. Of the 42 projects: 

•    2 were identified by SINSW as a priority in its Capital Investment Plan (SINSW requested funding for two new projects)
•    40 had already been announced.

On page eleven, the original text was as follows: 

The 2019–20 NSW Budget announced funding for an additional 40 new and upgraded schools as election commitments. Of the 40 election commitment projects: 

•    13 were identified by SINSW as priorities in its Capital Investment Plan (SINSW requested funding for a total of 33 new projects)
•    27 were new announcements (not identified as a priority by SINSW in its Capital Investment Plan).

The original text has now been changed to: 

The 2019–20 NSW Budget announced funding for an additional 40 new and upgraded schools as election commitments. Of the 40 election commitment projects: 

•    13 were identified by SINSW as priorities in its Capital Investment Plan (SINSW requested funding for a total of 31 new projects)
•    27 were new announcements (not identified as a priority by SINSW in its Capital Investment Plan).

The above changes will be reflected in the version of the report published on the Audit Office website and should be considered the true and accurate version.  

 

Published

Actions for Service NSW's handling of personal information

Service NSW's handling of personal information

Premier and Cabinet
Finance
Cyber security
Fraud
Information technology
Internal controls and governance
Management and administration
Risk
Service delivery

The Auditor-General for New South Wales, Margaret Crawford, released a report today examining the effectiveness of Service NSW’s handling of customers’ personal information to ensure its privacy.

The audit found that Service NSW is not effectively handling personal customer and business information to ensure its privacy. Service NSW continues to use business processes that pose a risk to the privacy of personal information. This includes the routine emailing of personal information between Service NSW service centres and other agencies, which is one of the processes that contributed to the data breach earlier this year. The audit found that previously identified risks and recommended solutions had not been implemented on a timely basis.

The Auditor-General made eight recommendations aimed at ensuring improved processes, technologies, and governance arrangements for how Service NSW handles customers’ personal information.

The Hon. Victor Dominello, MP, Minister for Customer Service, requested this audit under section 27(B)(3)(c) of the Public Finance and Audit Act 1983 following public reports in May 2020 of a cyber security attack which had led to a breach of Service NSW customer information. This audit also included the Department of Customer Service which supports Service NSW with privacy, risk and governance functions.

Service NSW was established in 2013 with the intention that it would, over time, 'become the primary interaction point for customers accessing New South Wales Government transaction services'.

Service NSW's functions are set out in the Service NSW (One stop Access to Government Services) Act 2013. This legislation allows for other NSW Government agencies to delegate to and enter into agreements with the Chief Executive Officer of Service NSW in order for Service NSW to undertake service functions for the agency.

Service NSW now has agreements with 36 NSW Government client agencies to facilitate over 1,200 types of interactions and transactions for the community.

The nature of each agreement between Service NSW and its client agencies varies. Some client agencies have delegated authority to allow Service NSW staff to conduct transactions on their behalf in the agencies' systems. Other arrangements do not include the same degree of delegation. In these cases, Service NSW provides services such as responding to enquiries and validating documents.

In addition, Service NSW conducts transactions for its own programs, such as the Seniors Card. Personal information for these programs, as well as information for customers' MyServiceNSW accounts, are stored by Service NSW on its Salesforce Customer Relationship Management (CRM) system.

In March 2020, Service NSW suffered two cyber security attacks in short succession. Technical analysis undertaken by the Department of Customer Service (DCS) concluded that these attacks resulted from a phishing exercise through which external threat actors gained access to the email accounts of 47 staff members. These attacks resulted in the breach of a large amount of personal customer information that was contained in these email accounts. See Section 1.1 for further details.

This audit is being conducted in response to a request from the Hon. Victor Dominello, Minister for Customer Service, under section 27B(3)(c) of the Public Finance and Audit Act 1983. Minister Dominello requested that the Auditor General conduct a performance audit in relation to Service NSW's handling of sensitive customer and business information.

This audit assessed how effectively Service NSW handles personal customer and business information to ensure its privacy.

It addressed the following:

  • Does Service NSW have processes and governance in place to identify and manage risks to the privacy of personal customer and business information?
  • Does Service NSW have policies, processes and systems in place that support the effective handling of personal customer and business information to ensure its privacy?
  • Has Service NSW effectively implemented its policies, processes and systems for managing personal customer and business information?

Conclusion

Service NSW is not effectively handling personal customer and business information to ensure its privacy. It continues to use business processes that pose a risk to the privacy of personal information. These include routinely emailing personal customer information to client agencies, which is one of the processes that contributed to the March 2020 data breach. Previously identified risks and recommended solutions had not been implemented on a timely basis.

Service NSW identifies privacy as a strategic risk in both its Risk Management Guideline and enterprise risk register and sets out a zero level appetite for privacy risk in its risk appetite statement. That said, the governance, policies, and processes established by Service NSW to mitigate privacy risk are not effective in ensuring the privacy of personal customer and business information. While Service NSW had risk identification and management processes in place at the time of the March 2020 data breach, these did not prevent the breach occurring.

Some of the practices that contributed to the data breach are still being followed by Service NSW staff. For example, business processes still require Service NSW staff to scan and email personal information to some client agencies.

The lack of multi factor authentication has been identified as another key contributing factor to the March 2020 data breach as this enabled the external threat actors to gain access to staff email accounts once they had obtained the user account details through a phishing exercise. Service NSW had identified the lack of multi factor authentication on its webmail platform as a risk more than a year prior to the breach and had committed to addressing this by June 2019. It was not implemented until after the breach occurred.

There are weaknesses in the general IT and security controls implemented by Service NSW over its Salesforce Customer Relationship Management (CRM) system, which holds the personal information of over four million NSW residents.

Internal audits carried out by Service NSW, including one completed in August 2020, have identified significant weaknesses in the general IT and security controls implemented by Service NSW over its Salesforce CRM system. These include deficiencies in the management of role based access, monitoring and audit of user access, and partitioning of program specific transaction information. These deficiencies create an increased risk of unauthorised access to the personal information of over four million customers held in the system.

Lines of responsibility for meeting privacy obligations are not clearly drawn between Service NSW and its client agencies.

Service NSW has agreements in place with client agencies. However, the agreements lack detail and clarity about the roles and responsibilities of the agencies in relation to the collection, storage and security of customer's personal information. This lack of clarity raises the risk that privacy obligations will become confused and missed between the agencies.

Service NSW carries out privacy impact assessments for major new projects but does not routinely review existing processes and systems.

Service NSW carries out privacy impact assessments as part of its routine processes for implementing major new projects, ensuring that privacy management is considered as part of project design. Service NSW does not regularly undertake privacy impact assessments or reviews of existing or legacy processes and systems, which has resulted in some processes continuing despite posing significant risks to the privacy of personal information, such as the scanning, emailing, and storing of identification documents.

1. Key findings

Service NSW identifies privacy risks, but the controls and processes it put in place to mitigate these privacy risks were not adequate to prevent or limit the extent of the data breach that occurred in March 2020

Service NSW’s approach to risk management is framed by its Risk Management Guideline, which defines 'privacy and compliance' as one of the key types of risk for the agency. Service NSW's enterprise risk register identifies four strategic privacy related risks. Service NSW has set out a zero level appetite for privacy risk in its risk appetite statement.

Service NSW has assessed the adequacy of its controls for privacy risks as needing improvement. To be fully effective, the Risk Management Guideline says that these controls should have a focus that is ‘largely preventative and address the root causes’.

One of the business processes that was a key contributing factor to the data breach was the emailing of personal information by Service NSW staff to client agencies.

This process had been identified as a risk prior to the breach and some steps had been put in place to mitigate the risk. In particular, staff were required to manually delete emails that contained personal information. However, these measures were ineffective in preventing the breach, as the external threat actors still gained access to 47 staff email accounts that contained a large amount of personal information.

It is unclear why Service NSW did not effectively mitigate this risk prior to the breaches. However, Service NSW has advised that it implemented measures in June and October 2020 to automatically archive emails likely to contain personal information. This is expected to limit the quantity of information retained in email accounts for extended periods.

Service NSW has not put in place any technical or other solutions to avoid Service NSW staff having to scan and email personal information to some client agencies. Urgent action is needed to remove the requirement for staff to email personal information to client agencies, thereby mitigating the risk inherent in sending and storing this information using email.

There are weaknesses in the general IT and security controls implemented by Service NSW over its Salesforce CRM system, which holds the personal information of over four million customers

There are weaknesses in the general IT and security controls implemented by Service NSW over its Salesforce CRM system. These weaknesses include deficiencies in governance of role based access, monitoring and audit of staff access, and partitioning of program specific transaction information. These deficiencies create an increased risk of unauthorised access to the personal information of over four million customers which is stored in this system.

In addition, there is an absence of important controls to safeguard customers' privacy, such as multi factor authentication and reviewable logs of access history to their information. Such controls, when properly implemented, would enhance the control that customers are able to exercise over their personal information.

A privacy impact assessment conducted on Service NSW’s Salesforce CRM system in 2015 recommended that the system include the ability for customers to review access history to their personal information, as well as the option for customers to apply multi factor authentication to their accounts. While both these recommendations appeared positively received by Service NSW, neither have been implemented.

Since its inception, Service NSW’s use of Salesforce has extended to storing transaction data, particularly for transactions for which Service NSW is responsible, such as the Seniors Card. It also holds details of over four million MyServiceNSW account holders, including name, email address and phone number, and optional address details. It was not originally intended for the system to hold this volume and nature of customer information.

Lines of responsibility for meeting privacy obligations are unclear between Service NSW and its client agencies

Service NSW's privacy management plan does not clearly set out the privacy obligations of Service NSW and its client agencies. It sets out that 'compliance with the privacy principles will primarily be the responsibility of that [client] agency'. However, Service NSW has its own obligations under the security principles of the Privacy and Personal Information Protection Act 1998 (PPIP Act) to take reasonable steps to prevent unauthorised access to personal information, which is not made clear in the privacy management plan.

The agreements between Service NSW and client agencies reviewed for this audit only include general and high level references to privacy. Most do not include details of each parties' privacy responsibilities such as: which agency will provide the customer with a privacy notice explaining how their personal information will be handled, how personal information will be kept secure, how long Service NSW will retain information, what processes will be followed for internal reviews, and what specific planning is in place to respond to data breaches.

Service NSW's privacy management plan has not been updated to include new programs and governance changes

Service NSW's privacy management plan includes most of the matters required by law or good practice, with some exceptions. It does not explain any exemptions that the agency commonly relies on under the PPIP Act and does not address any health information that Service NSW may handle. It had also not been updated to reflect governance changes and the fact that, at the time this audit commenced, Service NSW was disclosing the content of internal review applications (the formal expression for 'complaints') to the Department of Customer Service (DCS). These governance changes were part of the centralisation of Service NSW's corporate support functions into DCS in late 2019, though internal review staff were seconded back into Service NSW during the course of this audit.

The current July 2019 privacy management plan has also not been updated since the rollout of a number of major new initiatives in 2020. These include 2019–20 bushfire emergency recovery initiatives (such as small business grants) and COVID 19 pandemic response initiatives (such as small business grants, border permits and the COVID safe check in app).

Service NSW routinely conducts privacy impact assessments for new initiatives, though privacy risks remain in legacy systems and processes

Service NSW routinely conducts privacy impact assessments for major new initiatives and the assessments reviewed for this audit largely accorded with good practice guidance.

Service NSW does not routinely review existing processes and systems to ensure that they are effective in ensuring the privacy of customer personal information. Business processes that create the highest risk to privacy, such as emailing of personal information, are more common in these longstanding legacy systems.

Service NSW's significant and rapid growth has outpaced the establishment of a robust control environment which has exacerbated privacy risks

Since it was established in 2013, Service NSW has experienced significant growth in the number and diversity of the types of transactions it provides, as well as the number of client agencies with which it works. The pace and extent of this growth has contributed to important controls not being properly implemented on a timely basis, which has heightened privacy risks, particularly in regard to existing, legacy systems and processes.

The pace of change and increasing demand for new program implementation has limited the opportunity for Service NSW, in collaboration with its client agencies, to revisit and redesign legacy business practices which pose a greater privacy risk. This includes the scanning and emailing of personal information.

While 2019–20 has seen additional demands placed on Service NSW in responding to the 2019–20 bushfire emergency and COVID 19 pandemic, it is the nature of the agency’s work that it operates in a fast paced and complex environment, where it is required to respond to multiple client agencies and stakeholders. Ensuring customer privacy should be integral to Service NSW’s business as usual operations.

2. Recommendations

Service NSW commissioned a number of external reviews and investigations stemming from the data breaches. The Auditor General's recommendations below have taken these other reviews into account. In order to offer assurance that it is appropriately protecting the privacy of its customers, Service NSW should address the full breadth of findings and recommendations made across all relevant reviews.

As a matter of urgency, Service NSW should:

1. in consultation with relevant client agencies and the Department of Customer Service, implement a solution for a secure method of transferring personal information between Service NSW and client agencies

2. review the need to store scanned copies of personal information and, if still required, implement a more secure method of storing this information and regular deletion of material.

By March 2021, Service NSW should:

3. ensure that all new agreements entered into with client agencies from 1 April 2021 address the deficiencies identified in this audit, including that they provide clarity on:

  • the content and provision of privacy collection notices
  • the terms by which personal information will be retained, stored, archived, and disposed of when no longer required
  • steps that will be taken by each agency to ensure that personal information is kept secure
  • the circumstances in which, and processes by which, applications for internal review will be referred by one agency to the other
  • how identified breaches of privacy will be handled between agencies

4. in collaboration with the Department of Customer Service, review its privacy management plan to address the deficiencies raised in this audit, including:

  • to clarify Service NSW's understanding of how responsibility for meeting privacy obligations are delineated between Service NSW and client agencies
  • to better reflect the full scope and complexity of personal information handled by Service NSW
  • to better explain how applications for internal review are handled between Service NSW and the Department of Customer Service
  • to ensure regular ongoing review, either according to a schedule or when Service NSW experiences substantial change to its programs and handling of personal information

5. in consultation with the Department of Customer Service, review its policies and processes for the management of privacy risks, including to:

  • ensure that there are appropriate mechanisms to escalate identified privacy risks from business units to the Executive Leadership Team
  • ensure that there are action plans to address strategic privacy risks that are assessed as having ineffective controls.
By June 2021, Service NSW should:

6. address deficiencies in the controls over, and security for, its Salesforce customer relationship management and related systems that hold customer personal information, including:

  • establish policies and processes for regular access reviews and monitoring of user activity in these systems, including for privileged users
  • enable partitioning and role based access restrictions to personal information collected for different programs
  • provide customers the choice to use multi factor authentication to further secure their MyServiceNSW accounts
  • enable customers to view the transaction history of their personal information to detect possible mishandling.
By December 2021, Service NSW should:

7. ensure that all existing agreements with client agencies address the deficiencies identified in this audit, including that they provide clarity on:

  • the content and provision of privacy collection notices
  • the terms by which personal information will be retained, stored, archived, and disposed of when no longer required
  • steps that will be taken by each agency to ensure that personal information is kept secure
  • the circumstances in which, and processes by which, applications for internal review will be referred by one agency to the other
  • how identified breaches of privacy will be handled between agencies

8. carry out a risk assessment of all processes, systems and transactions that involve the handling of personal information and undertake a privacy impact assessment for those that:

  • are identified as high risk and have not previously had a privacy impact assessment
  • have had major changes or updates since the privacy impact assessment was completed.

Appendix one – Responses from agencies

Appendix two – About the audit

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for One TAFE NSW modernisation program

One TAFE NSW modernisation program

Education
Finance
Management and administration
Project management
Shared services and collaboration

The Auditor-General for New South Wales, Margaret Crawford, released a report today examining the management of the One TAFE NSW modernisation program.

In 2016, the Government released 'A Vision for TAFE NSW' which stated that TAFE NSW needed to become more flexible, efficient and competitive. It set out the need to progressively reduce significant cost inefficiencies, including by moving away from separate institutes to a single institute model. TAFE NSW established the One TAFE NSW modernisation program to deliver on that vision.

The Auditor General found that the One TAFE NSW modernisation program did not deliver against its key objectives within planned timeframes. The modernisation program originally aimed to realise $250 million in annual savings from 2018–19. Because of project delays and higher than expected transition costs, TAFE NSW did not meet the original savings target. TAFE NSW has made progress on key elements of the program and anticipates that savings will be realised in coming years.

The report makes two recommendations to improve governance arrangements for delivering on commercial objectives and increasing transparency of non commercial activities. 

The report also identifies a series of lessons for future government transformation programs.

TAFE NSW is the public provider of Vocational Education and Training (VET) in New South Wales. In 2018, TAFE NSW enrolled 436,000 students in more than 1,200 courses at around 130 locations across the State.

There have been major policy changes impacting TAFE NSW over the past decade. Under the Smart and Skilled reform, TAFE NSW started to compete with other Registered Training Organisations (RTOs) for a share of the student market.

In 2016, the NSW Government released 'A Vision for TAFE NSW'. The Vision stated that a failure to adapt to market circumstances had left TAFE NSW with unsustainable costs and inefficiencies. To address this, TAFE NSW needed to become more flexible, efficient and competitive. It set out that TAFE NSW must progressively reduce significant cost inefficiencies, including by moving away from a model of separate institutes to a One  TAFE NSW model. The NSW Government set TAFE NSW a target to achieve savings through implementing the Vision.

TAFE NSW established the One TAFE NSW modernisation program to deliver on that vision. The program initially aimed to deliver savings of $250 million per year from 2018–19, but this target was reviewed and updated as the program was being delivered.

This audit assessed whether TAFE NSW effectively managed the One TAFE NSW modernisation program to deliver on the NSW Government's vision for TAFE NSW. In making this assessment, the audit examined whether:

  • delivery of the program was well planned
  • the program was driven by sound governance arrangements
  • TAFE NSW is making progress against the intended outcomes of the program.

The audit focused on the effectiveness of planning, governance and reporting arrangements. It examined five projects within the overall modernisation program as case studies.

Conclusion

The One TAFE NSW modernisation program was an ambitious plan to deliver on the NSW Government’s vision for TAFE NSW, while achieving ongoing savings. Several factors contributed to TAFE NSW not effectively managing the program to deliver on planned timeframes and objectives. These factors include unclear expectations of the primary role of TAFE NSW, unrealistic timeframes, undertaking a large number of complex projects concurrently, governance arrangements that were not fit-for-purpose and poor-quality data.

Planning for the modernisation program and its projects was driven by top-down savings targets and pre-determined timeframes. This led to TAFE NSW attempting to deliver a large number of programs concurrently within tight timeframes. Program management capability was underdeveloped at the commencement of the program and this affected the quality of planning for delivery.

There was a lack of clarity around TAFE NSW's primary purpose. Part of the NSW Government's vision for TAFE NSW was for it to be more commercial, competitive and efficient. These objectives were not fully supported by existing legislation. The commercial objectives of the modernisation program conflicted with legislated social objectives for TAFE NSW. TAFE NSW did not have the autonomy to operate like a government-owned business in a market environment. And while TAFE NSW received separate funding to support students facing disadvantage this did not cover the costs of other non-commercial activities undertaken for social purposes, such as delivering uneconomic courses. The role of the TAFE Commission Board was ambiguous during the initial years of the program, which increased reporting requirements and blurred accountabilities for decision-making.

TAFE NSW's Strategic Plan 2016-22 nominated ten key milestones for delivery by January 2019. TAFE NSW has made progress against several important milestones, including that TAFE ‘is a single TAFE NSW brand’ and has 'industry specific TAFE NSW SkillsPoints'. Other key elements have yet to be delivered, including that TAFE NSW achieves 'integrated enterprise-wide business systems'. Because of delays to projects and higher than expected transition costs, TAFE NSW reported that it did not meet the originally targeted $250 million in annual savings for 2018–19 (which was reviewed and updated as the program was being delivered). 

Appendix one – Response from agency

Appendix two – About the audit

Appendix three – Performance auditing

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #346 - released 17 December 2020

Published

Actions for Health 2020

Health 2020

Health
Compliance
Financial reporting
Infrastructure
Internal controls and governance
Service delivery

This report analyses the results of our audits of financial statements of the Health cluster for the year ended 30 June 2020. The table below summarises our key observations.

1. Financial reporting

Financial reporting

Unqualified financial audit opinions

The financial statements of NSW Health and its 25 controlled entities received unqualified opinions.

The number of corrected and uncorrected misstatements increased from the prior year. Misstatements related predominantly to the implementation of new accounting standards, asset revaluations and accounting for new revenue streams to cover the cost of HSW Health’s response to the COVID-19 pandemic.

Qualified compliance audit opinion

We issued a qualified audit opinion for the Ministry of Health’s Annual Prudential Compliance Statement for aged care facilities operated by NSW Health. We identified 18 instances of material non-compliance with the Fees and Payments Principles 2014 (No. 2) (the Principles) in 2019–20 (30 in 2018–19).

Financial performance

NSW Health received an additional $3.3 billion in funding to cover costs associated with its response to the COVID-19 pandemic.

The impacts of the COVID-19 pandemic on the cluster were significant for health entities and included changes to operations, increased revenues, expenditure, assets and liabilities. Cancellation of elective surgery and decreased emergency department presentations meant that despite the pandemic, activity levels at many health entities decreased. Health Pathology and HealthShare were notable exceptions.

In the period to the 30 June 2020, NSW Health reported that over 900,000 COVID-19 tests were conducted. Health Pathology conducted over 500,000 of these tests. Health Pathology's surge requirements were enhanced through arrangements with 13 private sector providers. HealthShare purchased $864.2 million of personal protective equipment.

Overall, NSW Health recorded an operating surplus of $3.1 billion in 2019–20, an increase of $2.0 billion from 2018–19. As in previous years, the surplus largely resulted from additional revenue received to fund capital projects including the construction of new facilities, upgrades and redevelopments. In 2019–20 additional Commonwealth and State funding for the purchase and stockpiling of personal protective equipment also contributed to the operating surplus.

Overtime payments The Ambulance Service of NSW’s (NSW Ambulance) reduced their overtime payments to $79.7 million in 2019–20 ($83.1 million in 2018–19). Overtime payments in 2019–20 included $6.8 million related to the response to the 2019–20 bushfire season. NSW Ambulance overtime payments represent 16.8 per cent of total overtime payments in the cluster.

2. Audit observations

Internal control deficiencies

We identified more internal control deficiencies in 2019–20. The number of repeat issues from prior years also remains high.

NSW Health addressed 18 out of the 25 information system control deficiencies during the year.

Several key agreements lacked formal documentation. This included agreements between the Ministry and health entities, between health entities and agencies in other clusters and between the Ministry and health departments in other jurisdictions.

Infrastructure delivery NSW Health had 44 ongoing major capital projects at 30 June 2020 with a total revised budget of $12.3 billion. The revised total budget of $12.3 billion is $2.0 billion more than the original budget. NSW Health revises budgets when it combines project stages.

This report provides parliament and other users of the Health cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

The impacts of the COVID-19 pandemic on the cluster were significant and included changes to the operations of the health entities and increased revenue, expenditure, assets and liabilities.

As a part of this year's audits of health entities, we have considered:

  • financial implications of the COVID-19 emergency at both health entity and cluster levels
  • changes to agencies' operating models
  • agencies' access to technology and the maturity of systems and controls to prevent unauthorised and fraudulent access to data.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

The response to the COVID-19 pandemic primarily impacted the financial reporting of NSW Health through:

  • additional revenue from the State government in the form of grants and stimulus payments
  • additional revenue from the Commonwealth government under the National Partnership Agreement for COVID-19 to cover part of the cost of responding to the COVID-19 pandemic
  • increased expenses, largely due to increased payments to private health operators to maintain their viability during the COVID-19 pandemic and later to assist with public patient elective surgery waitlists and increased cleaning costs
  • increased purchases of personal protective equipment.

Chapter one outlines the impacts of NSW Health’s response to the COVID-19 pandemic. This chapter outlines our other audit observations related to the financial reporting of agencies in the Health cluster for 2020.

Section highlights

  • Unqualified audit opinions were issued for all health entities’ financial statements, although more misstatements were identified than last year.
  • NSW Health recorded an operating surplus of $3.1 billion, an increase of $2.0 billion from 2018–19. This is largely due to additional capital grants for new facilities, upgrades and redevelopments and additional Commonwealth and State funding for the purchase of personal protective equipment.
  • NSW Health’s expenses increased by 5.5 per cent in 2019–20 (7.0 per cent in 2018–19) despite the impact of the COVID-19 pandemic. The primary causes for the growth in expenses are increases in:
    • employee related expenses due to higher employee numbers, increased overtime and a 2.5 per cent award increase
    • payments to private health operators to maintain their viability during the COVID-19 pandemic and later to assist with public patient elective surgery waitlists
    • payments to private health operators due to the first full year of operation of the Northern Beaches hospital.
  • The Ambulance Service of NSW (NSW Ambulance) continued to report higher overtime payments than other health entities. However, despite the response to the 2019–20 bushfire season, their overtime payments were lower than last year. NSW Ambulance paid $79.7 million in overtime payments in 2019–20 ($83.1 million in 2018–19).
  • A qualified audit opinion was issued for the Ministry of Health’s Annual Prudential Compliance Statement for aged care facilities operated by NSW Health. There were 18 instances of material non-compliance with the Fees and Payments Principles 2014 (No. 2) (the Principles) in 2019–20 (30 in 2018–19)

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

The primary impact of the COVID-19 pandemic on the effectiveness of the internal controls of NSW Health and health entities relates to the effectiveness of controls implemented by HealthShare relating to the stocktake of personal protective equipment inventories. Inventory managed by HealthShare increased by 2,746 per cent during 2019–20. HealthShare’s inventory controls did not maintain pace with the sudden, significant increase.

The impacts of NSW Health’s response to the COVID-19 pandemic are outlined in chapter one. This chapter outlines other observations and insights from our financial statement audits of agencies in the Health cluster.

Section highlights

  • The number of internal control deficiencies has increased since 2018–19. More than a third of control deficiencies are repeat issues.
  • Control deficiencies that relate to managing employees’ leave and employee’s time recording continue to be difficult for entities to resolve, particularly during the ongoing response to the COVID-19 pandemic.
  • Several key agreements were undocumented. These included agreements between the Ministry and the health entities, between health entities, and between the Ministry and entities in other clusters and jurisdictions. These related to:
    • a loan arrangement between the Ministry and HealthShare for $319 million.
    • Northern Sydney Local Health District's use of land and buildings owned by the Graythwaite Charitable Trust
    • agreements for the treatment of New South Wales residents while they are interstate, and interstate residents receiving treatment while they are in New South Wales from Queensland, Victoria, South Australia and the ACT for both 2019–20 and 2018–19.
  • NSW Health reported that they completed nine major capital projects during 2019–20. As at 30 June 2020 there were 44 ongoing major capital health projects in NSW. The revised capital budget for these projects in total was $2.0 billion more than the original budget of $10.3 billion. NSW Health reported the budget revisions are largely the result of combining project stages.

Appendix one – List of 2020 recommendations 

Appendix two – Status of 2019 recommendations 

Appendix three – Financial data

Appendix four – Analysis of financial indicators 

Appendix five – Analysis of performance against budget

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Auditor-General’s Report to Parliament

Health 2020

11 December 2020

This corrigendum has been prepared to amend the following text within the Auditor-General’s Report to Parliament on Health 2020, dated 10 December 2020.

NSW Health emergency department treatment times

On page five the original text was as follows:

NSW Health also measures the percentage of patients whose clinical care in emergency departments is completed within four hours. The measure is used as an indicator of accessibility to public hospital services.

NSW Health aims to complete clinical care in the emergency department for 81 per cent of patients within four hours. In 2019–20 NSW Health reports it completed clinical care within four hours for 72.1 per cent of patients (a 7.3 per cent decrease from 2018–19).

At Western Sydney Local Health District, 59 per cent of patients were treated within the targeted timeframe. NSW Health attribute this to the profile of patients presenting in emergency departments and additional time taken processing COVID-19 patients to ensure staff safety.

The original text has now been changed to:

NSW Health also measures the percentage of patients with total time in the emergency department of four hours or less for each local health district. The measure is used as an indicator of accessibility to public hospital services.

Local Health Districts Target % (2019–20) Actual % (2019–20)
Central Coast 77.0 59.9
Far West 90.2 86.6
Hunter New England 81.0 72.5
Illawarra Shoalhaven 79.0 60.2
Mid North Coast 82.0 76.7
Murrumbidgee 85.3 81.9
Nepean Blue Mountains 79.0 65.5
Northern NSW 81.0 78.2
Northern Sydney 79.0 73.9
South Eastern Sydney 78.0 70.3
South Western Sydney 78.0 61.2
Southern NSW 85.0 83.0
Sydney 76.0 70.9
Sydney Children’s Hospitals Network 80.0 72.1
Western NSW 85.9 81.0
Western Sydney 78.0 59.0
St Vincent's Health Network* 75.0 65.4
* St Vincent’s Health Network Sydney (SVHNS) comprises of St Vincent’s Hospital Sydney Limited as the affiliated health organisation in respect of four recognised establishments under the Health Services Act 1997 (NSW) (Health Services Act). Under the Health Services Act, St Vincent’s Hospital Sydney Limited, is treated as a Network for the purposes of the National Health Reform Agreement in respect of the three recognised establishments: St Vincent’s Hospital, Darlinghurst; Sacred Heart Health Service, Darlinghurst; St Joseph’s Hospital, Auburn; and St Vincent's Correctional Health, Parklea.
Source: NSW Health (unaudited)

The above changes will be reflected in the version of the report published on the Audit Office website and should be considered the true and accurate version.

Published

Actions for Transport 2020

Transport 2020

Transport
Asset valuation
Cyber security
Financial reporting
Information technology
Infrastructure
Project management

1. Financial Reporting

Audit opinion Unmodified audit opinions issued for the financial statements of all Transport cluster entities.
Quality and timeliness of financial reporting All cluster agencies met the statutory deadlines for completing the early close and submitting the financial statements.

Transport cluster agencies continued to experience some challenges with accounting for land and infrastructure assets. The former Roads and Maritime Services and Sydney Metro recorded prior period corrections to property, plant and equipment balances.
Impact of COVID-19 on passenger revenue and patronage Total patronage and revenue for public transport decreased by approximately 18 per cent in 2019–20 due to COVID-19.

The Transport cluster received additional funding from NSW Treasury during the year to support the reduced revenue and additional costs incurred such as cleaning on all modes of public transport and additional staff to manage physical distancing.
Completion of the CBD and South East Light Rail The CBD and South East Light Rail project was completed and commenced operations in this financial year. At 30 June 2020, the total cost of the project related to the CBD and South East Light Rail was $3.3 billion. Of this total cost, $2.6 billion was recorded as assets, whilst $700 million was expensed.

2. Audit Observations

Internal control While internal controls issues raised in management letters in the Transport cluster have decreased compared to the prior year, control weaknesses continue to exist in access security for financial systems. We identified 56 management letter findings across the cluster and 43 per cent of all issues were repeat issues. The majority of the repeat issues relate to information technology controls around user access management.

There were three high risk issues identified - two related to financial reporting of assets and one for implementation of TAHE (see below).
Agency responses to emergency events Transport for NSW established the COVID-19 Taskforce in March 2020 to take responsibility for the overall response of planning and coordination for the Transport cluster. It also implemented the COVIDSafe Transport Plan which incorporates guidance on physical distancing, increasing services to support social distancing and cleaning.
RailCorp transition to TAHE On 1 July 2020, RailCorp was renamed Transport Asset Holding Entity of New South Wales (TAHE) and converted to a for-profit statutory State-Owned Corporation. TAHE is a commercial for-profit Public Trading Entity with the intent to provide a commercial return to its shareholders.

A plan was established by NSW Treasury to transition RailCorp to TAHE which covered the period 1 July 2015 to 1 July 2019. A large portion of the planned arrangements were not implemented by 1 July 2020. As at the time of this report, the TAHE operating model, Statement of Corporate Intent (SCI) and other key plans and commercial agreements are not finalised. The State Owned Corporations Act 1989 generally requires finalisation of an SCI three months after the commencement of each financial year. However, under the Transport Administration Act 1988, TAHE received an extension from the voting shareholders, the Treasurer and Minister for Finance and Small Business, to submit its first SCI by 31 December 2020. In accordance with the original plan, interim commercial access arrangements were supposed to be in place with RailCorp prior to commencement of TAHE.

Under the transitional arrangements, TAHE is continuing to operate in accordance with the asset and safety management plans of RailCorp. The final operating model is expected to include considerations of safety, operational, financial and fiscal risks. This should include a consideration of the potential conflicting objectives of a commercial return, and maintenance and safety measures.

This matter has been included as a high risk finding in our management letter due to the significance of the financial reporting impacts and business risks for TAHE.

Recommendation: TAHE management should:
  • establish an operating model in line with the original intent of a commercial return
  • finalise commercial agreements with the public rail operators
  • confirm forecast financial information to assess valuation of TAHE infrastructure
  • finalise asset and safety management plans.

Resolution of the above matters are critical as they may significantly impact the financial reporting arrangements for TAHE for 2020–21, in particular, accounting policies adopted as well as measurement principles of its significant infrastructure asset base.

Completeness and accuracy of contracts registers Across the Transport cluster, contracts and agreements are maintained by the transport agencies using disparate registers.

Recommendation (repeat): Transport agencies should continue to implement a process to centrally capture all contracts and agreements entered. This will ensure:
  • agencies are fully aware of contractual and other obligations
  • appropriate assessment of financial reporting implications
  • ongoing assessments of accounting standards, in particular AASB 16 ‘Leases’, AASB 15 'Revenue from Contract with Customers', AASB 1058 'Income of Not-for-Profit Entities' and new accounting standard AASB 1059 'Service Concession Arrangements: Grantors' are accurate and complete.

 

This report provides parliament and other users of the Transport cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations
  • the impact of emergencies and the pandemic.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Transport cluster for 2020, including any financial implications from the recent emergency events.

Section highlights

  • Total patronage and revenue for public transport decreased by approximately 18 per cent in 2019–20 due to COVID-19.
  • Unqualified audit opinions were issued on all Transport agencies' financial statements.
  • Transport cluster agencies continued to experience challenges with accounting of land and infrastructure assets.

 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our:

  • observations and insights from our financial statement audits of agencies in the Transport cluster
  • assessment of how well cluster agencies adapted their systems, policies and procedures, and governance arrangements in response to recent emergencies.

Section highlights

  • While there was a decrease in findings on internal controls across the Transport cluster, 43 per cent of all issues were repeat issues. Many repeat issues related to information technology controls around user access management.
  • RailCorp transitioned to TAHE on 1 July 2020. TAHE's operating model and commercial arrangements with public rail operators has not been finalised despite government original plans to be operating from 1 July 2019. TAHE management should finalise its operating model and commercial agreements with public rail operators as they may significantly impact the financial reporting arrangements for TAHE for 2020–21.
  • Completeness and accuracy of contracts registers remains an ongoing issue for the Transport cluster.

Appendix one – List of 2020 recommendations

Appendix two – Status of 2019, 2018 and 2017 recommendations

Appendix three – Management letter findings

Appendix four – Financial data

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.