Refine search Expand filter

Reports

Published

Actions for Implementation of the NSW Government’s program evaluation initiative

Implementation of the NSW Government’s program evaluation initiative

Industry
Justice
Planning
Premier and Cabinet
Treasury
Environment
Financial reporting
Internal controls and governance
Management and administration
Risk
Service delivery
Shared services and collaboration
Workforce and capability

The NSW Government’s ‘program evaluation initiative’, introduced to assess whether service delivery programs achieve expected outcomes and value for money, is largely ineffective according to a report released today by NSW Auditor-General, Margaret Crawford. Government services, in areas such as public order and safety, health and education, are delivered by agencies through a variety of programs. In 2016–17, the NSW Government estimates that it will sp

Published

Actions for Red tape reduction

Red tape reduction

Premier and Cabinet
Finance
Financial reporting
Internal controls and governance
Management and administration
Project management
Regulation
Shared services and collaboration

Overall, NSW Government initiatives and processes to prevent and reduce red tape were not effective, according to a report released today by the NSW Auditor-General. In 2015, the Government reported that its red tape reduction initiatives, implemented between 2011 and 2015, had resulted in $896 million in savings. While these initiatives resulted in some savings, the total value of savings is unknown because estimates for some initiatives were based on

Published

Actions for Early childhood education

Early childhood education

Education
Compliance
Information technology
Management and administration
Project management
Regulation
Risk
Service delivery
Workforce and capability

Enrolments in quality early childhood education programs in New South Wales are increasing but are below the national benchmark, according to a report released today by the NSW Auditor-General, Margaret Crawford. Ninety-five per cent of children should be enrolled in at least 600 hours in the year before school, but according to the latest NSW figures 77 per cent of children were enrolled in quality early childhood education programs. This 2015 figure i

Published

Actions for Supporting students with disability in NSW public schools

Supporting students with disability in NSW public schools

Education
Information technology
Management and administration
Service delivery
Workforce and capability

The Department of Education is doing a reasonable job in managing how well students with disability transition to a new school and supporting teachers to improve these students’ educational outcomes, according to a report released today by the NSW Auditor-General, Margaret Crawford. The level of support provided to students with disability can vary between schools. This is partly due to cultural resistance in some schools and teachers not always having

Published

Actions for Responding to Domestic and Family Violence

Responding to Domestic and Family Violence

Community Services
Justice
Health
Internal controls and governance
Management and administration
Service delivery

Organisations generally work together to improve the safety of victims when there is an overt and serious crisis, particularly where children are involved. There are no standard ways for victims and perpetrators to access help that might prevent ongoing violence and address underlying issues. This is particularly problematic where there are repeat victims and perpetrators, many of whom have complex mental health, drug and alcohol problems and are difficu

Published

Actions for Government expenditure and transport planning in relation to implementing Barangaroo

Government expenditure and transport planning in relation to implementing Barangaroo

Industry
Treasury
Transport
Compliance
Internal controls and governance
Management and administration
Project management
Service delivery

Barangaroo is an ambitious and significant development on Government-owned Sydney Harbour foreshore. Construction on the 22 hectare CBD site is expected to take 12 years to 2023. Developer contributions to Government of $1 billion are to provide for public domain and other Government development costs, including a six hectare Headland Park. When completed the precinct is to service an anticipated 26,000 workers and residents and up to 33,000 visitors a d

Published

Actions for Two Ways Together - NSW Aboriginal Affairs Plan

Two Ways Together - NSW Aboriginal Affairs Plan

Community Services
Premier and Cabinet
Internal controls and governance
Management and administration
Project management
Service delivery

To date the Two Ways Together Plan (the Plan) has not delivered the improvement in overall outcomes for Aboriginal people that was intended. Stronger partnerships between the government and Aboriginal people are only beginning to emerge. The disadvantage still experienced by some of the estimated 160,000 Aboriginal people in NSW is substantial. For example, the unemployment rate for Aboriginal people is at least three times higher than the rate for all N

Published

Actions for Transport of Dangerous Goods

Transport of Dangerous Goods

Planning
Finance
Compliance
Management and administration
Project management
Regulation
Risk
Service delivery

Dangerous goods make up 10-15% of domestic freight and have potential to harm people, property and the environment. They include substances such as explosives, flammable liquids and gases, and oxidising agents. However, Government inspection programs were limited. The Office of Environment and Heritage carried out very few checks in the four years up to 2010, with no inspections made in the metropolitan area. This is despite Port Botany handling around 5

Published

Actions for Helping older people access a residential aged care facility

Helping older people access a residential aged care facility

Health
Community Services
Compliance
Internal controls and governance
Management and administration
Risk
Service delivery
Shared services and collaboration
Workforce and capability

Assessment processes for older people needing to go to an Residential Aged Care Facility (RACF) vary depending on the processes of the Aged Care Assessement Teams (ACAT) they see and whether or not they are in hospital. The data collected on ACAT performance was significantly revised during 2004 making comparisons with subsequent years problematic. ACATs have more responsibilities than assessing older people for residential care. It is not clea

Published

Actions for Educating primary school students with disabilities

Educating primary school students with disabilities

Education
Internal controls and governance
Management and administration
Service delivery
Workforce and capability

Special education programs so far have been able to support schools to accommodate these students and as a result, we have an inclusive education system. Our concern is that as the number of students with disabilities increases, pressure will be placed on both funding and the capacity of schools to provide quality services. The Government’s special education initiative is a positive step towards addressing these problems. Nevertheless, other changes nee