Refine search Expand filter

Reports

Published

Actions for One TAFE NSW modernisation program

One TAFE NSW modernisation program

Education
Finance
Management and administration
Project management
Shared services and collaboration

The Auditor-General for New South Wales, Margaret Crawford, released a report today examining the management of the One TAFE NSW modernisation program.

In 2016, the Government released 'A Vision for TAFE NSW' which stated that TAFE NSW needed to become more flexible, efficient and competitive. It set out the need to progressively reduce significant cost inefficiencies, including by moving away from separate institutes to a single institute model. TAFE NSW established the One TAFE NSW modernisation program to deliver on that vision.

The Auditor General found that the One TAFE NSW modernisation program did not deliver against its key objectives within planned timeframes. The modernisation program originally aimed to realise $250 million in annual savings from 2018–19. Because of project delays and higher than expected transition costs, TAFE NSW did not meet the original savings target. TAFE NSW has made progress on key elements of the program and anticipates that savings will be realised in coming years.

The report makes two recommendations to improve governance arrangements for delivering on commercial objectives and increasing transparency of non commercial activities. 

The report also identifies a series of lessons for future government transformation programs.

TAFE NSW is the public provider of Vocational Education and Training (VET) in New South Wales. In 2018, TAFE NSW enrolled 436,000 students in more than 1,200 courses at around 130 locations across the State.

There have been major policy changes impacting TAFE NSW over the past decade. Under the Smart and Skilled reform, TAFE NSW started to compete with other Registered Training Organisations (RTOs) for a share of the student market.

In 2016, the NSW Government released 'A Vision for TAFE NSW'. The Vision stated that a failure to adapt to market circumstances had left TAFE NSW with unsustainable costs and inefficiencies. To address this, TAFE NSW needed to become more flexible, efficient and competitive. It set out that TAFE NSW must progressively reduce significant cost inefficiencies, including by moving away from a model of separate institutes to a One  TAFE NSW model. The NSW Government set TAFE NSW a target to achieve savings through implementing the Vision.

TAFE NSW established the One TAFE NSW modernisation program to deliver on that vision. The program initially aimed to deliver savings of $250 million per year from 2018–19, but this target was reviewed and updated as the program was being delivered.

This audit assessed whether TAFE NSW effectively managed the One TAFE NSW modernisation program to deliver on the NSW Government's vision for TAFE NSW. In making this assessment, the audit examined whether:

  • delivery of the program was well planned
  • the program was driven by sound governance arrangements
  • TAFE NSW is making progress against the intended outcomes of the program.

The audit focused on the effectiveness of planning, governance and reporting arrangements. It examined five projects within the overall modernisation program as case studies.

Conclusion

The One TAFE NSW modernisation program was an ambitious plan to deliver on the NSW Government’s vision for TAFE NSW, while achieving ongoing savings. Several factors contributed to TAFE NSW not effectively managing the program to deliver on planned timeframes and objectives. These factors include unclear expectations of the primary role of TAFE NSW, unrealistic timeframes, undertaking a large number of complex projects concurrently, governance arrangements that were not fit-for-purpose and poor-quality data.

Planning for the modernisation program and its projects was driven by top-down savings targets and pre-determined timeframes. This led to TAFE NSW attempting to deliver a large number of programs concurrently within tight timeframes. Program management capability was underdeveloped at the commencement of the program and this affected the quality of planning for delivery.

There was a lack of clarity around TAFE NSW's primary purpose. Part of the NSW Government's vision for TAFE NSW was for it to be more commercial, competitive and efficient. These objectives were not fully supported by existing legislation. The commercial objectives of the modernisation program conflicted with legislated social objectives for TAFE NSW. TAFE NSW did not have the autonomy to operate like a government-owned business in a market environment. And while TAFE NSW received separate funding to support students facing disadvantage this did not cover the costs of other non-commercial activities undertaken for social purposes, such as delivering uneconomic courses. The role of the TAFE Commission Board was ambiguous during the initial years of the program, which increased reporting requirements and blurred accountabilities for decision-making.

TAFE NSW's Strategic Plan 2016-22 nominated ten key milestones for delivery by January 2019. TAFE NSW has made progress against several important milestones, including that TAFE ‘is a single TAFE NSW brand’ and has 'industry specific TAFE NSW SkillsPoints'. Other key elements have yet to be delivered, including that TAFE NSW achieves 'integrated enterprise-wide business systems'. Because of delays to projects and higher than expected transition costs, TAFE NSW reported that it did not meet the originally targeted $250 million in annual savings for 2018–19 (which was reviewed and updated as the program was being delivered). 

Appendix one – Response from agency

Appendix two – About the audit

Appendix three – Performance auditing

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #346 - released 17 December 2020

Published

Actions for Transport 2020

Transport 2020

Transport
Asset valuation
Cyber security
Financial reporting
Information technology
Infrastructure
Project management

1. Financial Reporting

Audit opinion Unmodified audit opinions issued for the financial statements of all Transport cluster entities.
Quality and timeliness of financial reporting All cluster agencies met the statutory deadlines for completing the early close and submitting the financial statements.

Transport cluster agencies continued to experience some challenges with accounting for land and infrastructure assets. The former Roads and Maritime Services and Sydney Metro recorded prior period corrections to property, plant and equipment balances.
Impact of COVID-19 on passenger revenue and patronage Total patronage and revenue for public transport decreased by approximately 18 per cent in 2019–20 due to COVID-19.

The Transport cluster received additional funding from NSW Treasury during the year to support the reduced revenue and additional costs incurred such as cleaning on all modes of public transport and additional staff to manage physical distancing.
Completion of the CBD and South East Light Rail The CBD and South East Light Rail project was completed and commenced operations in this financial year. At 30 June 2020, the total cost of the project related to the CBD and South East Light Rail was $3.3 billion. Of this total cost, $2.6 billion was recorded as assets, whilst $700 million was expensed.

2. Audit Observations

Internal control While internal controls issues raised in management letters in the Transport cluster have decreased compared to the prior year, control weaknesses continue to exist in access security for financial systems. We identified 56 management letter findings across the cluster and 43 per cent of all issues were repeat issues. The majority of the repeat issues relate to information technology controls around user access management.

There were three high risk issues identified - two related to financial reporting of assets and one for implementation of TAHE (see below).
Agency responses to emergency events Transport for NSW established the COVID-19 Taskforce in March 2020 to take responsibility for the overall response of planning and coordination for the Transport cluster. It also implemented the COVIDSafe Transport Plan which incorporates guidance on physical distancing, increasing services to support social distancing and cleaning.
RailCorp transition to TAHE On 1 July 2020, RailCorp was renamed Transport Asset Holding Entity of New South Wales (TAHE) and converted to a for-profit statutory State-Owned Corporation. TAHE is a commercial for-profit Public Trading Entity with the intent to provide a commercial return to its shareholders.

A plan was established by NSW Treasury to transition RailCorp to TAHE which covered the period 1 July 2015 to 1 July 2019. A large portion of the planned arrangements were not implemented by 1 July 2020. As at the time of this report, the TAHE operating model, Statement of Corporate Intent (SCI) and other key plans and commercial agreements are not finalised. The State Owned Corporations Act 1989 generally requires finalisation of an SCI three months after the commencement of each financial year. However, under the Transport Administration Act 1988, TAHE received an extension from the voting shareholders, the Treasurer and Minister for Finance and Small Business, to submit its first SCI by 31 December 2020. In accordance with the original plan, interim commercial access arrangements were supposed to be in place with RailCorp prior to commencement of TAHE.

Under the transitional arrangements, TAHE is continuing to operate in accordance with the asset and safety management plans of RailCorp. The final operating model is expected to include considerations of safety, operational, financial and fiscal risks. This should include a consideration of the potential conflicting objectives of a commercial return, and maintenance and safety measures.

This matter has been included as a high risk finding in our management letter due to the significance of the financial reporting impacts and business risks for TAHE.

Recommendation: TAHE management should:
  • establish an operating model in line with the original intent of a commercial return
  • finalise commercial agreements with the public rail operators
  • confirm forecast financial information to assess valuation of TAHE infrastructure
  • finalise asset and safety management plans.

Resolution of the above matters are critical as they may significantly impact the financial reporting arrangements for TAHE for 2020–21, in particular, accounting policies adopted as well as measurement principles of its significant infrastructure asset base.

Completeness and accuracy of contracts registers Across the Transport cluster, contracts and agreements are maintained by the transport agencies using disparate registers.

Recommendation (repeat): Transport agencies should continue to implement a process to centrally capture all contracts and agreements entered. This will ensure:
  • agencies are fully aware of contractual and other obligations
  • appropriate assessment of financial reporting implications
  • ongoing assessments of accounting standards, in particular AASB 16 ‘Leases’, AASB 15 'Revenue from Contract with Customers', AASB 1058 'Income of Not-for-Profit Entities' and new accounting standard AASB 1059 'Service Concession Arrangements: Grantors' are accurate and complete.

 

This report provides parliament and other users of the Transport cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations
  • the impact of emergencies and the pandemic.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Transport cluster for 2020, including any financial implications from the recent emergency events.

Section highlights

  • Total patronage and revenue for public transport decreased by approximately 18 per cent in 2019–20 due to COVID-19.
  • Unqualified audit opinions were issued on all Transport agencies' financial statements.
  • Transport cluster agencies continued to experience challenges with accounting of land and infrastructure assets.

 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our:

  • observations and insights from our financial statement audits of agencies in the Transport cluster
  • assessment of how well cluster agencies adapted their systems, policies and procedures, and governance arrangements in response to recent emergencies.

Section highlights

  • While there was a decrease in findings on internal controls across the Transport cluster, 43 per cent of all issues were repeat issues. Many repeat issues related to information technology controls around user access management.
  • RailCorp transitioned to TAHE on 1 July 2020. TAHE's operating model and commercial arrangements with public rail operators has not been finalised despite government original plans to be operating from 1 July 2019. TAHE management should finalise its operating model and commercial agreements with public rail operators as they may significantly impact the financial reporting arrangements for TAHE for 2020–21.
  • Completeness and accuracy of contracts registers remains an ongoing issue for the Transport cluster.

Appendix one – List of 2020 recommendations

Appendix two – Status of 2019, 2018 and 2017 recommendations

Appendix three – Management letter findings

Appendix four – Financial data

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Stronger Communities 2020

Stronger Communities 2020

Justice
Community Services
Asset valuation
Compliance
Financial reporting
Information technology
Internal controls and governance
Management and administration
Service delivery

This report analyses the results of our audits of financial statements of the agencies comprising the Stronger Communities cluster for the year ended 30 June 2020. The table below summarises our key observations.

1. Financial reporting

Quality of financial reporting Unqualified audit opinions were issued for all agencies' 30 June 2020 financial statements.
Compliance with financial reporting requirements

The Treasury extended the statutory deadline for the submission of the 2019–20 financial statements. For agencies subject to Treasurer's Directions, Treasury required agencies to submit their 30 June 2020 financial statements by 5 August 2020. For other agencies, the deadline was extended to 31 October 2020. All agencies in the cluster met the revised statutory deadlines.

Cluster agencies substantially completed the mandatory early close procedures set by NSW Treasury. However, nine agencies including the Department of Communities and Justice (the department) did not complete one or more mandatory requirements, such as assessing the impact of new and updated accounting standards.

Financial implications of recent emergencies

Emergency events significantly impacted cluster agencies in 2019–20. Our review of seven cluster agencies most affected highlighted some had incurred additional expenditure because of the bushfires and floods. Others lost revenue due to the COVID-19 pandemic.

During the year these agencies collectively received additional funding of $1.1 billion from the State to respond to:

  • increased demand for homeless people seeking temporary accommodation
  • additional cleaning requirements
  • bushfire recovery efforts
  • emergency support for eligible small businesses.

The Sydney Cricket Ground Trust, Venues NSW and Office of Sport lodged insurance claims of $51.3 million with the Treasury Managed Fund with respect to lost revenues from the pandemic. The losses were mainly due to event cancellations and covered various periods ranging from mid-March to 31 December 2020.

The change in economic conditions caused by the COVID-19 pandemic resulted in the NSW Government cancelling the refurbishment of Stadium Australia it had previously approved in August 2019. Venues NSW wrote off $16.8 million of redevelopment costs during 2019–20.

Restatement of the Sydney Cricket Ground valuation The valuation of the Sydney Cricket Ground (the Stadium) included costs of $28.6 million which were not eligible for capitalisation. The financial statements were restated to reflect the reduction in the value of the Stadium and the asset revaluation reserve.
Unresolved data quality issues in the VS Connect system

The department continues to address significant data quality issues resulting from its implementation of the VS Connect system (the System) in 2019. The issues relate to the completeness and accuracy of the data transferred from the legacy system. The System is used by the department to manage its Victims Support Services (VSS) and for financial reporting purposes.

An independent actuary helps the department estimate its liability for VSS claims. The actuary's valuation at 30 June 2020 was again impacted by the data quality issues. Consequently, the actuary adopted a revised valuation methodology compared to previous years.

Recommendation (repeat issue):

The department should resolve the data quality issues in the VS Connect System before 31 March 2021.

AASB 16 'Leases' resulted in significant changes to agencies' financial position

Cluster agencies implemented three new accounting standards for the first time in 2019–20. Adoption of AASB 16 'Leases' resulted in cluster agencies collectively recognising right-of-use assets and lease liabilities of $1.7 billion and $1.1 billion respectively on 1 July 2019.

Significant misstatements in how lease related balances had been calculated were found in 17 of the 29 cluster agencies. The cluster outsources the management of most of its owned and leased property portfolio to Property NSW, but cluster agencies remain responsible for any deliverables under that arrangement. The misstatements were mainly caused by late revisions of key assumptions and issues with the accuracy and completeness of Property NSW's lease information.

2. Audit observations

Internal control deficiencies

Our 2019–20 financial audits identified 191 internal control issues. Of these, two were high risk and almost one-third were repeat findings from previous audits. While repeat findings reduced by 5.7 percentage points in 2019–20, the number remains high.

Recommendation (repeat issue):

Cluster agencies should action recommendations to address internal control weaknesses promptly. Focus should be given to addressing high risk and repeat issues.

Agencies response to recent emergencies

The severity of the recent bushfires and floods meant natural disaster expenses incurred by emergency services agencies rose from $67.4 million in 2018–19 to $497 million in 2019–20.

The COVID-19 pandemic presented unprecedented challenges for the cluster. Social distancing and other infection control measures disrupted the traditional means of delivering services. Agencies established committees or response teams to respond to these challenges.

The department introduced measures to minimise the risk of the spread of COVID-19 amongst inmates in custodial settings.

Managing excess annual leave

Managing excess annual leave was a challenge for cluster agencies directly involved in the government's response to the emergency events. Employees in frontline cluster agencies deferred leave plans and many have taken little or no annual leave during the reporting period.

Annual leave liabilities rose at the department, NSW Police Force, Fire and Rescue NSW, Office of the NSW Rural Fire Service, the Legal Aid Commission of New South Wales and the Office of the Director of Public Prosecutions. The combined liabilities increased from $620 million to $692 million or 11.6 per cent between 30 June 2019 and 30 June 2020.

Implementation of Machinery of Government (MoG) changes

Administrative Arrangement Orders effective from 1 July 2019, created the department of Communities and Justice and transferred functions and staff, together with associated assets and liabilities into the department from the former departments of Justice and Family and Community Services.

The department continues to establish its governance arrangements following the MoG changes.

Recommendation:

The department should finalise appropriate governance arrangements for its new organisational structure as soon as possible. This includes:

  • harmonising policies and procedures to ensure a unified approach across the department
  • finalising risk management and monitoring processes across the department
  • updating its delegation instruments to reflect the current organisational structure, delegation limits and roles and responsibilities.
Delivery of the Prison Bed Capacity Program

The department continued to expand prison system capacity through the NSW Government's $3.8 billion Prison Bed Capacity Program. The department reported it spent $480 million on the Program in 2019–20. Six prison expansion projects were completed during the year, which added 1,660 new and 395 refurbished beds to the NSW prison system.

Data from the department shows the number of adult inmates in the NSW prison system reached a maximum of 14,165 during the year. Operational capacity was 16,096 beds on 19 August 2020.

 

This report provides parliament and other users of the financial statements of agencies in the Stronger Communities cluster with the results of our audits, our observations, analysis, conclusions and recommendations.

Agencies in the Stronger Communities cluster were significantly impacted by the bushfires, floods and the COVID-19 pandemic in 2019–20. Our 2019–20 financial audits of the seven cluster agencies most significantly impacted by the recent emergency events considered:

  • the financial implications of the emergency events
  • changes to agencies' operating models and control environments
  • delivery of new or expanded projects, programs or services at short notice.

Our findings on these seven agencies' responses to the recent emergencies are included throughout this report. These agencies are:

  • Department of Communities and Justice
  • Fire and Rescue NSW
  • NSW Police Force
  • Office of the NSW Rural Fire Service
  • Office of the NSW State Emergency Service
  • Sydney Cricket and Sports Ground Trust
  • Venues NSW.

The Department of Communities and Justice is the principal agency of the cluster. The names of all agencies in the Stronger Communities cluster are included in Appendix one.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Stronger Communities cluster for 2020, including any financial implications from the recent emergency events.

Section highlights

  • Unqualified audit opinions were issued for all agencies' 30 June 2020 financial statements. All agencies met the revised statutory deadlines for completing early close procedures and submitting their financial statements.
  • Emergency events significantly impacted cluster agencies in 2019–20. Agencies received additional funding of $1.1 billion to respond to the emergencies.
  • Cluster agencies implemented three new accounting standards in 2019–20. Adoption of AASB 16 'Leases' resulted in significant changes to agencies' financial statements.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our:

  • observations and insights from our financial statement audits of agencies in the Stronger Communities cluster
  • assessment of how well cluster agencies adapted their systems, policies and procedures, and governance arrangements in response to recent emergencies
  • review of how the cluster agencies managed the increased risks associated with new programs aimed at stemming the spread of COVID-19 and stimulating the economy.

Section highlights

  • Almost one-third of internal control issues reported were repeat findings. Cluster agencies should address these issues more promptly.
  • The severity of the recent bushfires and floods meant natural disaster expenses incurred by emergency services agencies increased by $430 million in 2019–20.
  • The department continues to establish its governance arrangements following Machinery of Government changes effective 1 July 2019.

 

Appendix one – Timeliness of financial reporting by agency

Appendix two – Management letter findings by agency

Appendix three – List of 2020 recommendations 

Appendix four – Status of 2019 recommendations 

Appendix five – Selected agencies for review of response to emergency events 

Appendix six – Financial data 

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Education 2020

Education 2020

Education
Asset valuation
Compliance
Financial reporting
Fraud
Information technology
Internal controls and governance
Management and administration
Procurement

The Auditor-General for New South Wales, Margaret Crawford, released a report today titled Education 2020. This report focuses on key observations and findings from the most recent audits of agencies in the Education cluster.

Unqualified audit opinions were issued for all cluster agencies’ financial statements. However, internal control deficiencies were identified across the cluster agencies, including deficiencies in the management of purchasing cards and 15 internal control issues that were repeated from the previous year.

The 2019–20 natural disasters caused widespread damage in both Northern and Southern NSW. The COVID‑19 pandemic further challenged agencies, requiring social distancing and other infection control measures which disrupted the traditional means of teaching students. Agencies have adjusted their operations to respond to these emergency events.

The TAFE Commission’s revenues 2019–20 were impacted by the pandemic. Lower enrolments and an increase in fee-free short courses offered during the year contributed to the result.

Read the PDF report

This report analyses the results of our audits of financial statements of entities within the Education cluster for the year ended 30 June 2020. The table below summarises our key observations and recommendations.

1. Financial reporting 

Audit opinions Unqualified audit opinions were issued for all cluster agencies' 30 June 2020 financial statements audits.
New accounting standards

Agencies implemented three new accounting standards during the year.

Our financial statement audits of the Department of Education (the Department) and NSW Education Standards Authority (NESA) identified issues with the leasing information provided by Property NSW (PNSW). Despite the outsourcing arrangement, both the Department and NESA remain ultimately responsible for the completeness and accuracy of this information, which would have benefited from a more thorough quality assurance, validation and review process before they placed reliance upon it.

Recommendation:

We recommend the Department and NESA:

  • quality assure and validate the information provided by PNSW
  • ensure changes made by PNSW to lease data are supported and that assumptions and judgements applied are appropriate
  • document their review of the data supplied.
Changes were made to the financial reporting requirements this year to account for the impact of the pandemic

Emergency legislation was enacted during the year in response to the COVID-19 pandemic. The legislation revised the statutory reporting deadlines for agencies to submit their financial statements and allowed the Treasurer to continue authorising payments from the consolidated fund until the enactment of the 2020–21 budget.

All cluster agencies prepared their financial statements on a going concern basis and submitted their financial statements within the revised statutory deadlines.

The State provided $159.0 million in stimulus funding to support the operations of cluster agencies during emergency events. Nearly half of this funding was to support cleaning activities by the Department and the Technical and Further Education Commission (the TAFE Commission) during the COVID-19 pandemic.

Quality and timeliness of financial reporting

The number of monetary misstatements identified in agencies' financial statements decreased to 14 (23 in 2018–19).

While the number of corrections made to the financial statements after the submission date increased to eight (two in 2018–19), it is important to note these corrections provide parliament and other users of the financial statements increased confidence in the accuracy and presentation of agencies' performance and financial position.

Sustainability of cluster agencies The TAFE Commission's enrolments declined, and operating margins reduced, both being impacted by the COVID-19 pandemic.

2. Audit observations

Internal control deficiencies

We identified 33 internal control issues, including 15 findings that were repeated from previous years.

A high-risk issue was reported at the Department relating to the inadequate monitoring and follow up of privileged user activity in its enterprise resource planning system – SAP.

Repeat findings relate to ongoing deficiencies in information technology controls and management policies, practices and procedures.

Recommendation:

Cluster agencies should:

  • prioritise and action recommendations to address internal control deficiencies
  • review and confirm the appropriateness of existing privileged user access accounts
  • implement a rigorous monitoring regime to ensure that any improper use of privileged user accounts can be detected in a timely manner.
Agency responses to emergency events

The Department established a separate bushfire relief directorate and COVID-19 Taskforce to assist and support school communities in response to recent emergencies.

Other cluster agencies have established committees or response teams to oversee and address all aspects of the impact of COVID-19.

Schools review 2019 We continue to identify instances of non-compliance in relation to cash management and procurement at schools.
Use of purchasing cards at the Department of Education

Since 2015, the NSW Government has encouraged the use of purchasing cards by public sector agencies. Purchasing cards are efficient to transact low value, high volume procurement of goods and services, but the use must be effectively monitored.

Our review of the Department's purchasing cards identified weaknesses in its oversight and monitoring controls, including the issue and cancellation of purchasing cards

Opportunities exist for the Department to better monitor card use. Tools such as data analytics are an efficient and effective detective control to identify irregular activity or misuse by cardholders.

Recommendation:

The Department should:

  • improve the accuracy and completeness of exit procedures for terminated employees to ensure cards are returned and cancelled
  • perform periodic reviews to ensure active cards are held only by current employees
  • set transaction limits that do not exceed the limits of the user’s financial delegation
  • establish a data analytics regime to help analyse and identify high risk patterns and anomalies in their purchasing card usage, augmenting their existing monitoring and detective controls.

 

This report provides parliament and other users of the Education cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations
  • the impact of emergencies and the COVID-19 pandemic.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

The COVID-19 Legislation Amendment (Emergency Measures–Treasurer) Act 2020 amended legislation administered by the Treasurer to implement further emergency measures as a result of the COVID-19 pandemic. These amendments:

  • allowed the Treasurer to authorise payments from the consolidated fund until the enactment of the 2020–21 budget – supporting the going concern assessments of cluster agencies
  • revised budgetary, financial and annual reporting time frames – impacting the timeliness of financial reporting
  • exempted certain statutory bodies and departments from preparing financial statements.

This chapter outlines our audit observations related to the financial reporting of agencies in the Education cluster for 2020, including any financial implications from the recent emergency events.

Section highlights 

Unqualified audit opinions were issued on the financial statements of cluster agencies.

All cluster agencies met the revised statutory deadlines for completing early close procedures and submitting their financial statements.
 
Emergency legislation allowing the Treasurer to continue authorising payments from the consolidated fund under the existing Appropriations Act enabled cluster agencies to prepare financial statements on a going concern basis.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our:

  • observations and insights from our financial statement audits of agencies in the Education cluster. It also comments on our review of elements of the financial control framework applied by schools in NSW whose financial results form part of the Department of Education's (the Department) financial statements.
  • assessment of how well cluster agencies adapted their systems, policies and procedures, and governance arrangements in response to recent emergencies.

Section highlights

  • A high-risk issue regarding inadequate monitoring of privileged user access was identified at the Department.
  • We continue to observe issues by schools in relation to cash management and non-compliance with procurement guidelines and purchasing card use.
  • Opportunities exist for the Department and cluster agencies to enhance their monitoring and review of purchasing card activities. Tools such as data analytics procedures provide an efficient and effective detective control, particularly when used in conjunction with independent spot-checks.

Appendix one – List of 2020 recommendations

Appendix two – Status of 2019 and 2018 recommendations

Appendix three – Financial data

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Health capital works

Health capital works

Health
Compliance
Infrastructure
Procurement
Project management

This report examines whether NSW Health effectively planned and delivered major capital works to meet the demand for health services in New South Wales.

The report found that NSW Health has substantially expanded health infrastructure across New South Wales since 2015. However, the program was driven by Local Health District priorities without assessment of the State’s broader and future‑focussed health requirements.

The report found that unclear decision making roles and responsibilities between Health Infrastructure and the Ministry of Health limited the ability of NSW Health to effectively test and analyse investment options.

Project delays and budget overruns on some major projects indicate that Health Infrastructure's project governance, risk assessment and management systems could be improved.

The Auditor‑General recommends that NSW Health ensure its capital projects offer the greatest value to New South Wales by establishing effective policy guidance and enhancing project governance and management systems.

Read full report (PDF)

Since 2011–12, NSW Health has aimed to improve its facilities and build 'future focused' infrastructure. The NSW Government’s 2015–16 election commitments established a four-year $5.0 billion capital program for NSW Health to build and upgrade more than 60 hospitals and health services. The 2019–20 State Budget committed a further $10.1 billion over four years for another 29 projects. This is the largest investment to date on health capital works in New South Wales.

Recent reviews of infrastructure have recognised that population and demographic growth will require a change in the delivery and composition of health infrastructure, including considering greater use of non-traditional, non-capital health service options and assets.

To ensure that expenditure on capital works represents the best value for money, NSW Health's business cases need to be robust and supported by evidence that demonstrates they are worthy investments. The NSW Process of Facility Planning has been the main framework guiding the detailed planning and development of NSW Health's capital works proposals. This framework was developed by the then NSW Department of Health in 2010. Its aim is to ensure investment proposals are supported by rigorous planning processes that address health service needs and provide value for money.

Infrastructure projects of the complexity and scale being delivered by NSW Health carry inherent risks. For example, unplanned cost escalations can potentially impact on the State’s finances. Unforeseen delays can also reduce the intended benefits. The growth in the State’s health capital spend and project profile, means its exposure to such risks has increased over time.

The objective of this audit was to assess the effectiveness of planning and delivery of major capital works to meet demand for health services in New South Wales. To address this objective, the audit examined whether:

  • the Ministry of Health has effective procedures for planning and prioritising investments in major health capital works
  • Health Infrastructure develops robust business cases for initiated major capital works that reliably inform government decision making
  • Health Infrastructure has effective project governance and management systems that support delivering projects on-time, within budget and achievement of intended benefits.

The audit focused on the Ministry of Health and Health Infrastructure – being the lead agencies within NSW Health responsible for prioritising, planning and delivering major health capital works across the State. The audit examined 13 business cases for eight discrete projects over a ten-year period.

Conclusion

NSW Health has substantially expanded health infrastructure across New South Wales since 2015. However, its planning and prioritisation processes were not assessed against a long-term statewide health infrastructure plan and lacked rigorous assessment against non-capital options creating a risk that they do not maximise value for New South Wales.

The scale of NSW Health's capital investment is significant and has grown substantially in recent years. The NSW Government’s election commitments in 2015–16 and 2019–20 collectively set out a $15.0 billion capital program to build and upgrade 89 hospitals and health services. NSW Health developed this infrastructure program in the absence of a statewide health infrastructure strategy and investment framework to focus its planning and decisions on the types of capital investments required to meet the long-term needs of the NSW health system.

Consequently, locally focused priorities of the State’s 17 Local Health Districts have been the primary drivers of NSW Health’s capital investments since 2015–16. Local Health District investment proposals for hospitals were developed without consideration of alternative health options such as community health service models, technology-driven eHealth care, or private sector options. Without rigorous assessment against a range of potential health service options, there is a risk that selected projects do not maximise value for New South Wales.

In recognition of the need for a statewide approach to infrastructure planning, the Ministry of Health recently developed a 20-year Health Infrastructure Strategy and prioritisation framework in 2019. The strategy was approved by the NSW Government in April 2020.

NSW Health's ability to effectively test and analyse its capital investment options has been compromised by unclear decision-making roles and responsibilities between its Health Infrastructure and the Ministry of Health agencies.

While both Health Infrastructure and the Ministry of Health have responsibilities for the assessment of business cases for proposed infrastructure projects, confusion about the roles of each agency at key steps compromised the efficacy of the process. Health Infrastructure and the Ministry of Health have differing views about which agency is responsible for testing business case inputs and conducting comprehensive options appraisals.

As a result of this confusion, Health Infrastructure and the Ministry of Health did not rigorously test Local Health District capital investment proposals against defined statewide health infrastructure investment priorities. The NSW Process of Facility Planning does not clarify the responsibilities of all parties in validating and prioritising Local Health District's Clinical Service Plans and progressing them to business cases.

NSW Health's infrastructure priorities are not sufficiently supported by transparent documentation of selection methodology and the rationale for decisions. Consequently, there is a risk that recommended options, whilst having some economic and health service merit, do not represent the greatest value.

Substantial delays and budget overruns on some major projects indicate that Health Infrastructure's project governance, risk assessment and management systems could be improved.

Health Infrastructure did not fully comply with NSW Government guidelines for developing business cases and making economic appraisals for proposed capital investments. These weaknesses, along with delays and budget overruns on some projects, demonstrate a need for Health Infrastructure to strengthen its project governance, management and quality control systems.

 

Over the period of review, NSW Government policies for business case development and submission have emphasised that effective governance arrangements are critical to a proposal's successful implementation.

NSW Health's Process of Facility Planning similarly highlights the importance of effective governance and project management for achieving good outcomes. It prescribes a general governance structure managed by Health Infrastructure that can be tailored to the planning and delivery of health infrastructure projects greater than $10.0 million.

Project challenges indicate opportunities for strengthening governance and project management

The three major hospital redevelopments examined in metropolitan, regional and rural areas had a combined Estimated Total Cost of more than $1.2 billion and comprised eight discrete projects and 13 separate business cases.

Almost all these projects experienced delivery challenges which impacted achievement of their original objectives and intended benefits. This is expected in complex and large-scale health infrastructure programs. However, in some projects the impacts were significant and resulted in substantial delays, unforeseen costs, and diversion of resources from other priority areas.

Our review of the selected case studies highlighted opportunities for enhancing governance and project management. Specifically, it indicates a need for improving transparency in the management of contingencies, risk management and assessments particularly relating to adverse site conditions and the selection of contractors. There is also a need to strengthen forward planning for options to address unfunded priorities within business cases that risk complicating the delivery of future project stages resulting in unforeseen costs and potentially avoidable budget overruns.

Need for increased transparency and accountability in the management of contingency funds

In February 2017, the Ministry's Capital Strategy Group approved the use of surplus funds of $13.76 million from Stage 1 of the Hornsby Ku-ring-gai Hospital Redevelopment for new works deemed needed to support Stage 2. Following this decision, Health Infrastructure finalised and submitted a business case addendum for Stage 1 to the Ministry in March 2017, addressing the new works comprising a two-storey building for medical imaging and paediatric floors. The business case addendum also addressed options to fit out and procure major medical imaging equipment. The Ministry approved the Stage 1 business case in July 2017, noting the Ministry's Capital Strategy Group had already approved the use of remaining Stage 1 funds to deliver the new works.

Stage 1 was completed in 2015, almost two years before the Stage 1 business case addendum was prepared in February 2017.

The Ministry's decision to approve the new works using $13.76 million of surplus Stage 1 funds did not comply with the NSW Treasury Circular TC 12/20. This policy establishes the Treasurer's approval must be sought and received before a new capital project with an Estimated Total Cost of $5.0 million or more can be approved by NSW Health. The Ministry therefore exceeded its delegated authority in making this decision, as it was not evident it had sought and received the Treasurer's approval prior to doing so.

Consequently, the surplus Stage 1 funds should not have been used by the Ministry to deliver new works in the circumstances. Instead, they should have been released from the Stage 1 project in accordance with established NSW Health procedures, and the Stage 1 Estimated Total Cost revised down accordingly. This did not occur, and NSW Health ultimately directed $11.0 million in surplus Stage 1 funds to the new works.

These circumstances indicate a need to strengthen transparency and accountability within NSW Health for the approval of new projects, and how contingency funds are used in the management of major health capital works. They also demonstrate the impact of weaknesses with options appraisal as the initial Stage 1 business case did not consider alternative options for addressing the initially unfunded works later covered by the Stage 1 business case addendum and ultimately funded from the Stage 1 contingency provision.

Weaknesses in service delivery planning resulted in unaccounted-for costs

In addition to proposing the above-noted new works, the 2017 Stage 1 Business Case Addendum for the Hornsby-Ku-ring-gai development sought to retrospectively address the estimated funding gap of around $14.0 million for the internal fit out, supply of major medical imaging equipment, and cost to operate the medical imaging service at Hornsby Ku-ring-gai Hospital also not addressed in the originally Stage 1 business case.

The Stage 1 business case addendum considered various procurement options to purchase and run the medical imaging services ranging from State operation purchase options to private operation purchase options.

It recommended outsourcing the operation and provision of equipment to the private sector based on estimated savings to the public sector initially of around $650,000 per annum reducing over time to $270,000. The Ministry endorsed this option in June 2017, but it did not ultimately proceed.

A July 2018 report to the Executive Steering Committee on the project shows NSW Health later decided to deliver operation of the medical imaging unit 'traditionally' with an updated estimate of the cost at approximately $16.4 million. The report also shows the Ministry supported the costs now being met by the Northern Sydney Local Health District.

This means the funding gap previously identified in the Stage 1 business case addendum for fitting out the medical imaging building and supply of major medical equipment would need to be met fully by the State, representing a $16.4 million cost overrun for the project.

Examined reports to the Executive Steering Committee show this was largely funded by the Northern Sydney Local Health District via the disposal of land realising approximately $15.0 million in proceeds.

This initially unforeseen cost, along with the additional $11.0 million for the new works approved under the Stage 1 business case addendum, were ultimately merged with the Stage 2 project initially approved in 2017–18 with an Estimated Total Cost of $200 million.

The extent of budget variation on the Hornsby Kur-ring-gai development has not been transparent

The 2019–20 State Budget provided an additional $65.0 million for a further Stage 2A to deliver additional built capacity to support outpatient services, enhanced allied health services, re-housed community health services and the delivery of prioritised clinical services unfunded as part of Stage 2. The funds were approved based on an Investment Decision Template (IDT) that examined two options in addition to the base case representing scoping alternatives to the preferred master planned capital solution.

However, we found the IDT showed around 23 per cent of the $65.0 million sought (i.e. $15.0 million) was to be allocated to fund the deficit in Stage 2, which had arisen as a result of project delays due to adverse site conditions. This was not discussed in the IDT.

The February 2020 report to the Executive Steering Committee shows a combined Stage 2 and 2A final forecast cost of $292.6 million against a potential budget of $290.7 million representing an overall deficit for the project of around 0.6 per cent.

However, this favourable final budget position does not transparently show the funding challenges experienced over the project's implementation to-date. The three major budget issues include:

  • inappropriate use of around $11.0 million in Stage 1 contingency for originally unfunded works contrary to Treasury policy
  • the additional $16.4 million cost unforeseen in the Stage 1 business case for delivering medical imaging services mostly funded through the sale of land
  • an additional $15.0 million from Stage 2A to cover the budget overrun in Stage 2 due to adverse site conditions.

The cumulative impact of these events is that Stages 1 and 2 of the Hornsby project cost approximately $42.4 million than it should have in the circumstances around 14 per cent more than what the revised combined Estimated Total Cost for both stages should have been after releasing the $11.0 million in surplus Stage 1 funds, with Stage 2 delayed by around 14 months.

Opportunity for strengthening risk management for adverse site conditions

Major construction projects often experience adverse site conditions which can be difficult to fully detect in advance. However, we found this was a common occurrence in the projects we examined sometimes with significant time and/or budget impacts indicating scope to enhance related risk and cost assessments. Specifically:

  • Hornsby Ku-ring-gai Hospital Redevelopment Stage 2: adverse site conditions during demolition works resulted in an 11-month delay for delivering the medical imaging unit and 14-month delay completing Stage 2 main works including need for additional $15.0 million in funds to cover the resultant budget deficit for the project.
  • Blacktown Mt Druitt Hospital Redevelopment Stage 2: adverse site conditions combined with project complexity delayed completion of the early works by approximately five months. This contributed to the delay in completing the main construction works which occurred around nine months later than planned in the business case.
  • Dubbo Health Service Redevelopment Stages 3 and 4: Health Infrastructure advised adverse site conditions including asbestos containing materials and ground conditions delayed works for the main building with completion forecast for March 2021, around 21 months later than planned in the final business case. This resulted in the need for additional $13.5 million to cover increased construction costs and risks, increasing the Stage 3 and 4 forecast final cost from $150 million to $163.5 million as at February 2020.

These examples indicate a risk the cumulative impact of adverse site conditions may be substantial when measured across both time and Health Infrastructure's full delivery program. They also point to potential for Health Infrastructure to achieve efficiencies and improved outcomes from strengthening its approach to assessing and mitigating the risks from adverse site conditions.

Limited due diligence with prospective contractors risks avoidable delays and costs

Main construction works on Stage 1 of the Dubbo Health Service Redevelopment were completed in October 2015, approximately 13 months later than planned in the final business case. Delays were mainly due to insolvency of the early works contractor resulting in their departure from the project. The ensuing 11-month delay in completing the early works significantly impacted the overall schedule and delivery of main construction works.

The insolvency event was significant as it affected nine separate Health Infrastructure projects – three of which had yet to reach practical completion. It also affected state-funded projects in other sectors. It resulted in the need for additional funding of $11.5 million that was provided in the 2014–15 State Budget increasing the total Stage 1 and 2 budget from $79.8 million to $91.3 million.

Health Infrastructure’s analysis of lessons learned shows it worked actively to mitigate the impacts of the insolvency event across all affected projects. However, it also indicates a risk the lessons were mainly focused on mitigating the impacts after an insolvency event occurred rather than on prevention.

Although Health Infrastructure initially commissioned a financial assessment of the now insolvent early works contractor before engagement, it did not detect any risks of the impending insolvency and instead concluded the contractor was in a strong financial position. However, the contractor became insolvent shortly after commencement approximately seven months later. This indicates a risk of weaknesses in the assessment performed that was not explicitly addressed by the lessons learned.

Delivery of the main construction works were further impacted by disputes with the main works contractor over the scope of works for the renal unit resulting in Health Infrastructure terminating the contract in November 2016 following lengthy negotiations over several months.

The scope of works relating to the renal unit were ultimately transferred to Stages 3 and 4 and were delivered in December 2019, around five years later than originally planned in the business case.

Health Infrastructure advised the delay was ultimately beneficial to the project because the refurbishment works for the renal unit, initially scheduled for Stages 1 and 2, would have been demolished to accommodate the new Western Cancer Centre proposed after Stages 1 and 2 and currently being delivered in parallel with Stages 3 and 4.

Health Infrastructure advised the actual cost of Stages 1 and 2 was $84.7 million against the budget of $91.3 million. The residual $6.6 million relates to the renal works not delivered during Stage 1 and 2 and transferred to Stage 3 and 4.

Health Infrastructure advised the contractual provisions for mitigating insolvency events 'in-flight' are limited highlighting the importance of proactive and effective due diligence prior to engaging contractors for significant construction projects.

Need for a quality framework linked to staff training and capability development

Health Infrastructure's 2017-20 Corporate Plan identifies the development of a quality framework to support delivery of future-focused outcomes as a key organisational priority. Related initiatives within the Corporate Plan describe a framework underpinned by a Quality Committee providing advice on:

  • records management, to meet the requirements of the State Records Act 1998
  • project assurance, to ensure future focused outcomes and enhance Health Infrastructure's Standards, Policies, Procedures and Guidelines, Templates and Design Guidance Notes
  • knowledge management and library services, to promote and leverage from project learnings.

Although Health Infrastructure has some elements of a quality framework it is not yet fully in place. Health Infrastructure advised it had yet to establish the quality framework and related committee described in its Corporate Plan due in part to its focus on responding to the growth of its capital program.

Health Infrastructure's Development and Innovation team has been active in supporting continuous improvement in knowledge and project management including development of business cases. Although useful, these initiatives have relied heavily on leveraging and disseminating insights from Gateway reviews and have not formed part of a systematic quality and continuous improvement framework.

The limited focus on the quality of business cases is reflected in internal performance monitoring and reporting which focuses mainly on tracking the delivery of projects against internal benchmarks, often revised from the baselines in the business case, and expenditure against cashflow targets. There is no evident internal monitoring and/or reporting to the Chief Executive and Board on defined quality metrics linked to business case development and staff capability.

Performance reporting on balanced scorecard metrics has similarly focused mainly on process rather than quality and has been inconsistent in recent years.

Appendix one – Response from agency

Appendix two – About the audit

Appendix three – Performance auditing

Appendix four – Ministry of Health planning tools and guidelines

Appendix five – Streamlined investment decision process for Health Capital Projects

Appendix six – Timeline of business cases and relevant policy guidelines

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #338 - released 12 August 2020

Published

Actions for Their Futures Matter

Their Futures Matter

Justice
Community Services
Education
Health
Whole of Government
Cross-agency collaboration
Internal controls and governance
Management and administration
Project management

The Auditor-General for New South Wales, Margaret Crawford, released a report today examining whether the Department of Communities and Justice had effective governance and partnership arrangements in place to deliver ‘Their Futures Matter’.

Their Futures Matter was intended to place vulnerable children and families at the heart of services, and direct investment to where funding and programs deliver the greatest social and economic benefits. It was a four-year whole-of-government reform in response to the 2015 Tune Review of out-of-home care.

The Auditor-General found that while important foundations were put in place, and new programs trialled, the key objective to establish an evidence-based whole-of-government early intervention approach for vulnerable children and families in NSW was not achieved.

Governance and cross-agency partnership arrangements to deliver Their Futures Matter were found to be ineffective. 'Their Futures Matter lacked mechanisms to secure cross portfolio buy‑in and did not have authority to drive reprioritisation of government investment', the Auditor-General said.

At the reform’s close, the majority of around $380 million in investment funding remains tied to existing agency programs, with limited evidence of their comparative effectiveness or alignment with Their Futures Matter policy objectives. The reform concluded on 30 June 2020 without a strategy or plan in place to achieve its intent.

The Auditor-General made four recommendations to the Department of Communities and Justice, aimed at improving implementation of outstanding objectives, revising governance arrangements, and utilising the new human services data set to address the intent of the reform. However, these recommendations respond only in part to the findings of the audit.

According to the Auditor-General, ‘Cross-portfolio leadership and action is required to ensure a whole-of-government response to delivering the objectives of Their Futures Matter to improve outcomes for vulnerable children, young people and their families in New South Wales.’

Read full report (PDF)

In 2016, the NSW Government launched 'Their Futures Matter' (TFM) - a whole-of-government reform aimed at delivering improved outcomes for vulnerable children, young people and their families. TFM was the government's key response to the 2015 Independent Review of Out of Home Care in New South Wales (known as 'the Tune Review').

The Tune Review found that, despite previous child protection reforms, the out of home care system was ineffective and unsustainable. It highlighted that the system was not client-centred and was failing to improve the long-term outcomes for vulnerable children and families. The review found that the greatest proportion of relevant expenditure was made in out of home care service delivery rather than in evidence-based early intervention strategies to support children and families when vulnerabilities first become evident to government services (such as missed school days or presentations to health services).

The then Department of Family and Community Services (FACS) designed the TFM reform initiatives, in consultation with central and human services agencies. A cross-agency board, senior officers group, and a new unit in the FACS cluster were established to drive the implementation of TFM. In the 2016–17 Budget, the government allocated $190 million over four years (2016–17 to 2019–20) to the reform. This resourced the design and commissioning of evidence-based pilots, data analytics work, staffing for the implementation unit and secretariat support for the board and cross-agency collaboration.

As part of the TFM reform, the Department of Premier and Cabinet, NSW Treasury and partnering agencies (NSW Health, Department of Education and Department of Justice) identified various existing programs that targeted vulnerable children and families (such as the preceding whole-of-government ‘Keep Them Safe’ reform coming to an end in June 2020). Funding for these programs, totalling $381 million in 2019–20, was combined to form a nominal ‘investment pool’. The government intended that the TFM Implementation Board would use this pool to direct and prioritise resource allocation to evidence-based interventions for vulnerable children and families in NSW.

This audit assessed whether TFM had effective governance and partnership arrangements in place to enable an evidence-based early intervention investment approach for vulnerable children and families in NSW. We addressed the audit objective with the following audit questions:

  • Was the TFM reform driven by effective governance arrangements?
  • Was the TFM reform supported by effective cross-agency collaboration?
  • Has the TFM reform generated an evidence base to inform a cross-agency investment approach in the future?

The audit did not seek to assess the outcomes for children, young people and families achieved by TFM programs and projects.

Conclusion

The governance and cross-agency partnership arrangements used to deliver the Their Futures Matter reform were ineffective. Important foundations were put in place, and new programs trialled over the reform's four years. However, an evidence-based whole-of-government early intervention approach for vulnerable children and families in NSW − the key objective of the reform − was not established. The reform concluded in June 2020 without a strategy or plan in place to achieve its intent.

The governance arrangements established for the Their Futures Matter (TFM) reform did not provide sufficient independence, authority and cross-agency clout to deliver on the reform’s intent. This hindered delivery of the reform's key elements, particularly the redirection of funding to evidence-based earlier intervention supports, and limited the impact that TFM could have on driving system change.

TFM increased focus on the contribution that other agencies outside of the former Family and Community Services portfolio could make in responding to the needs of vulnerable children and families, and in reducing the demand costs of related government service delivery. Despite being a whole-of-government reform, TFM lacked mechanisms to secure cross-portfolio buy-in and lacked the powers to drive reprioritisation of government investment in evidence-based and earlier intervention supports across agencies. At the reform’s close, the majority of the reform's investment pool funding remained tied to existing agency programs, with limited evidence of their comparative effectiveness or alignment with Their Futures Matter policy objectives.

TFM began building an evidence base about ‘what works’, including piloting programs and creating a new dataset to identify risk factors for vulnerability and future costs to government. However, this evidence base does not yet comprehensively map how existing services meet needs, identify system duplications or gaps, nor demonstrate which government funded supports and interventions are most effective to make a difference to life outcomes for vulnerable children and families in NSW.
Despite these issues, the need, intent and vision for Their Futures Matter remains relevant and urgent, as issues identified in the Tune Review remain pertinent.

Their Futures Matter (TFM) is a whole-of-government reform to deliver improved outcomes for vulnerable children, young people and their families.

Supported by a cross-agency TFM Board, and the TFM Unit in the then Department of Family and Community Services (FACS), the reform aimed to develop whole-of-government evidence-based early intervention investment approaches for vulnerable children and families in NSW.

Governance refers to the structures, systems and practices that an organisation has in place to:

  • assign decision-making authorities and establish the organisation's strategic direction
  • oversee the delivery of its services, the implementation of its policies, and the monitoring and mitigation of its key risks
  • report on its performance in achieving intended results, and drive ongoing improvements.

We examined whether the TFM reform was driven by effective governance arrangements and cross-agency collaboration.

The reform agenda and timeframe set down for Their Futures Matter (TFM) were ambitious. This chapter assesses whether the TFM Board and TFM Unit had the capability, capacity and clout within government to deliver the reform agenda.

Creating a robust evidence base was important for Their Futures Matter, in order to:

  • identify effective intervention strategies to improve supports and outcomes for vulnerable children and families
  • make efficient use of taxpayer money to assist the maximum number of vulnerable children and families
  • inform the investment-based approach for future funding allocation.

This chapter assesses whether the TFM reform has developed an evidence base to inform cross-agency investment decisions.

Appendix one – Response from agency

Appendix two – TFM governance entities

Appendix three – TFM Human Services Data Set

Appendix four – TFM pilot programs

Appendix five – About the audit

Appendix six – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #337 - released 24 July 2020

Published

Actions for CBD South East Sydney Light Rail: follow-up performance audit

CBD South East Sydney Light Rail: follow-up performance audit

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk
Service delivery

This is a follow-up to the Auditor-General's November 2016 report on the CBD South East Sydney Light Rail project. This follow-up report assessed whether Transport for NSW has updated and consolidated information about project costs and benefits.

The audit found that Transport for NSW has not consistently and accurately updated project costs, limiting the transparency of reporting to the public.

The Auditor-General reports that the total cost of the project will exceed $3.1 billion, which is above the revised cost of $2.9 billion published in November 2019. $153.84 million of additional costs are due to omitted costs for early enabling works, the small business assistance package and financing costs attributable to project delays.

The report makes four recommendations to Transport for NSW to publicly report on the final project cost, the updated expected project benefits, the benefits achieved in the first year of operations and the average weekly journey times.

Read full report (PDF)

The CBD and South East Light Rail is a 12 km light rail network for Sydney. It extends from Circular Quay along George Street to Central Station, through Surry Hills to Moore Park, then to Kensington and Kingsford via Anzac Parade and Randwick via Alison Road and High Street.

Transport for NSW (TfNSW) is responsible for planning, procuring and delivering the Central Business District and South East Light Rail (CSELR) project. In December 2014, TfNSW entered into a public private partnership with ALTRAC Light Rail as the operating company (OpCo) responsible for delivering, operating and maintaining the CSELR. OpCo engaged Alstom and Acciona, who together form its Design and Construct Contractor (D&C).

On 14 December 2019, passenger services started on the line between Circular Quay and Randwick. Passenger services on the line between Circular Quay and Kingsford commenced on 3 April 2020.

In November 2016, the Auditor-General published a performance audit report on the CSELR project. The audit found that TfNSW would deliver the CSELR at a higher cost with lower benefits than in the approved business case, and recommended that TfNSW update and consolidate information about project costs and benefits and ensure the information is readily accessible to the public.

In November 2018, the Public Accounts Committee (PAC) examined TfNSW's actions taken in response to our 2016 performance audit report on the CSELR project. The PAC recommended that the Auditor-General consider undertaking a follow-up audit on the CSELR project. The purpose of this follow-up performance audit is to assess whether TfNSW has effectively updated and consolidated information about project costs and benefits for the CSELR project.

Conclusion

Transport for NSW has not consistently and accurately updated CSLER project costs, limiting the transparency of reporting to the public. In line with the NSW Government Benefits Realisation Management Framework, TfNSW intends to measure benefits after the project is completed and has not updated the expected project benefits since April 2015.

Between February 2015 and December 2019, Transport for NSW (TfNSW) regularly updated capital expenditure costs for the CSELR in internal monthly financial performance and risk reports. These reports did not include all the costs incurred by TfNSW to manage and commission the CSELR project.

Omitted costs of $153.84 million for early enabling works, the small business assistance package and financing costs attributable to project delays will bring the current estimated total cost of the CSELR project to $3.147 billion.

From February 2015, TfNSW did not regularly provide the financial performance and risk reports to key CSELR project governance bodies. TfNSW publishes information on project costs and benefits on the Sydney Light Rail website. However, the information on project costs has not always been accurate or current.

TfNSW is working with OpCo partners to deliver the expected journey time benefits. A key benefit defined in the business plan was that bus services would be reduced owing to transfer of demand to the light rail - entailing a saving. However, TfNSW reports that the full expected benefit of changes to bus services will not be realised due to bus patronage increasing above forecasted levels.

Appendix one – Response from agency

Appendix two – Governance and reporting arrangements for the CSELR

Appendix three – 2018 CSELR governance changes

Appendix four – About the audit

Appendix five – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #335 - released 11 June 2020

Published

Actions for Funding enhancements for police technology

Funding enhancements for police technology

Justice
Community Services
Information technology
Management and administration
Procurement
Project management

This report focuses on how the NSW Police Force managed a $100 million program to acquire new technology. The program invested in technologies intended to make police work safer and quicker. These included body-worn video (BWV) cameras, smart phone devices, mobile fingerprint scanners and hand-held drug testing devices.

The audit found that while the NSW Police Force mostly managed the ‘Policing for Tomorrow’ program effectively, investment decision making could be improved in the future. The NSW Police Force missed an opportunity to take a whole-of-organisation approach to identify capability gaps and target the acquired technologies to plug these.

The NSW Police Force has processes in place to monitor the benefits of some of the larger technology, but it does not do this consistently for all procured technology. It could not demonstrate that smaller projects are improving the efficiency or effectiveness of policing.

The audit also found that the NSW Police Force does not routinely engage with external stakeholders on the use or impacts of new technology that changes how officers interact with the public, noting that this will not always be possible for particularly sensitive procurements that involve covert technologies or methodologies.

The Auditor-General made three recommendations to guide improvement of NSW Police Force ICT procurement, benefits management and stakeholder engagement processes.

Read full report (PDF)

Ahead of the March 2015 election, the NSW Government announced a $100 million Policing for Tomorrow fund for the NSW Police Force to acquire technology intended to make police work safer and quicker. The announcement committed the NSW Police Force to several investment priorities, including body-worn video (BWV) cameras, smart phone devices (MobiPOL), mobile fingerprint scanners and hand-held drug testing devices. Otherwise, the NSW Police Force was allowed flexibility in identifying and resourcing suitable projects.

This audit assessed whether the Policing for Tomorrow fund was effectively managed to improve policing in New South Wales. We addressed the audit objective with the following audit questions:

  • Did the NSW Police Force efficiently and effectively identify, acquire, implement and maintain technology resourced by the fund?
  • Did the NSW Police Force establish effective governance arrangements for administering the fund, and for monitoring expected benefits and unintended consequences?
  • Did technology implemented under the fund improve the efficiency and effectiveness of policing in New South Wales?

Conclusion

The NSW Police Force's management of the Policing for Tomorrow fund was mostly effective. There are measures in place to assess the impact of the technologies on the efficiency and effectiveness of policing in NSW. However, these measures are not in place for all technologies funded by Policing for Tomorrow. A strategic whole-of-organisation approach to identifying and filling technology capability gaps may have assisted in better targeting funds and managing expected benefits.

The NSW Police Force identified, acquired, implemented and maintained a range of technologies resourced by the fund in an efficient and effective way. The election announcement committed the NSW Police Force to four specific projects which made up over three quarters of the fund value. Investment decisions for remaining funds were driven by the availability of funding and individual technology requirements rather than targeting improved policing outcomes and the capability necessary to achieve these.

The NSW Police Force missed an opportunity to take a whole-of-organisation approach to selecting technology projects for the remainder of the funds where it had discretion. This may have included considering less obvious back office technology or making different investment decisions driven by gaps in the agency's technology capabilities.

The NSW Police Force used effective governance arrangements for administering the Policing for Tomorrow fund, including using its existing ICT Executive Board. The NSW Police Force has adequate processes in place to drive benefits and monitor the impact of technology on the efficiency and effectiveness of policing for the larger projects funded by Policing for Tomorrow. Further work is required to ensure this for smaller projects.

The NSW Police Force tends to consider only impacts on the organisation in managing benefits and identifying unintended consequences. It does not routinely engage proactively with stakeholders, including partner criminal justice agencies and members of the community, on new technology that changes how police interact with the public.

We examined how effectively the NSW Police Force governed the Policing for Tomorrow fund, to ensure that key accountability and decision-making arrangements were in place to direct the $100 million spend to appropriate technologies. We also assessed how the NSW Police Force acquired, implemented and maintained technology funded by Policing for Tomorrow to determine the effectiveness of the relevant asset management.

The Policing for Tomorrow election commitment aimed to invest in technology to ‘make police work safer and quicker – meaning more time on the street combatting crime’. We assessed whether the NSW Police Force ensured that funded technologies have improved policing efficiency and effectiveness. We did not seek to independently assure the benefits or outcomes resulting from the technologies.

Appendix one – Response from agency

Appendix two – Policing for Tomorrow projects and expenditure

Appendix three – About the audit

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #334 - released 2 June 2020

Published

Actions for Volume Ten 2011 Focusing on Health

Volume Ten 2011 Focusing on Health

Health
Financial reporting
Information technology
Internal controls and governance
Management and administration
Project management
Workforce and capability

This report includes comments on financial audits of government agencies in the Health sector. In 2010-11, Ambulance Officers spent an extra 77,200 hours waiting at emergency departments for patients to transfer to hospital care. In 2010-11, only 66 per cent of patients were moved from the emergency department to an inpatient bed within eight hours of their arrival. This is significantly down on last year’s 73 per cent and well below the 80 per cent target.

Published

Actions for Volume Nine 2011 focus on Education and Communities

Volume Nine 2011 focus on Education and Communities

Education
Community Services
Asset valuation
Internal controls and governance
Management and administration
Project management
Workforce and capability

The report includes comments on financial audits of government agencies in the Education and Communities sectors. The audits of the above entities’ financial statements for the year ended 30 June 2011 resulted in unmodified audit opinions within the Independent Auditor’s Reports. A key finding was that Treasury should consider issuing further guidance to arts and cultural bodies on collection valuation methodologies due to the significance of these assets to the State’s asset base.