Reports
Actions for Newcastle Urban Transformation and Transport Program
Newcastle Urban Transformation and Transport Program
The urban renewal projects on former railway land in the Newcastle city centre are well targeted to support the objectives of the Newcastle Urban Transformation and Transport Program (the Program), according to a report released today by the Auditor-General for New South Wales, Margaret Crawford. The planned uses of the former railway land achieve a balance between the economic and social objectives of the Program at a reasonable cost to the government.
Actions for Mobile speed cameras
Mobile speed cameras
Key aspects of the state’s mobile speed camera program need to be improved to maximise road safety benefits, according to a report released today by the Auditor-General for New South Wales, Margaret Crawford. Mobile speed cameras are deployed in a limited number of locations with a small number of these being used frequently. This, along with decisions to limit the hours that mobile speed cameras operate, and to use multiple warning signs, have reduced
Actions for Detecting and responding to cyber security incidents
Detecting and responding to cyber security incidents
A report released today by the Auditor-General for New South Wales, Margaret Crawford, found there is no whole-of-government capability to detect and respond effectively to cyber security incidents. There is very limited sharing of information on incidents amongst agencies, and some agencies have poor detection and response practices and procedures. The NSW Government relies on digital techno
Actions for Managing IT Services Contracts
Managing IT Services Contracts
Neither agency (NSW Ministry of Health and NSW Police Force) demonstrated that they continued to get value for money over the life of these long term contracts or that they had effectively managed all critical elements of the three contracts we reviewed post award. This is because both agencies treated contract extensions or renewals as simply continuing previous contractual arrangements, rather than as establishing a new contract and financial comm
Actions for Review of Walsh Bay
Review of Walsh Bay
The decision to seek development of Walsh Bay without a Master Plan and/or detailed study as to the state of the precinct presented significant problems throughout the life of the project. Now, four years later, negotiations still continue on the details of the final scheme. Based on the latest estimates, it will not provide a financial return as was originally expected. The audit found no evidence to indicate why the former Government wished to expedite
Actions for Police response to fraud
Police response to fraud
This audit was initiated following concerns expressed by the Department of Agriculture about the Police’s handling of a suspected fraud that it had first reported in 1996. The Department’s main concern related to the long delays before a full Police investigation took place. Nevertheless, the current review highlighted a number of areas that, in the opinion of The Audit Office, require closer examination and resolution by the Police Service in implement
Actions for Redevelopment proposal for East Fairfield (Villawood) Estate
Redevelopment proposal for East Fairfield (Villawood) Estate
This audit examines the processes which led to the Government’s decision to demolish and sell the East Fairfield (Villawood) housing estate at a cost of nearly $32m gross ($17m net). In doing so, the audit focuses on whether the decision process demonstrates that it is an efficient and effective use of government funds. The audit raises a number of concerns about the decision-making process. Although demolition and redevelopment may have been the most e