Actions for Signal failures on the metropolitan rail network

Signal failures on the metropolitan rail network

Transport
Information technology
Infrastructure
Internal controls and governance
Project management
Risk
Service delivery

Between 2004 and 2006, the number of signalling failures, signalling downtime and the number of trains delayed as a result of signal failures all fell. RailCorp’s on-time running performance improved over the same period. The fall in failures is a clear indication of improved performance. Changes in the definition of on-time and to the timetable during 2005 and 2006 however make it difficult to determine whether improvements in response downtime and signalling delays are due to a true performance improvement. To build upon this strong base, RailCorp needs to determine with more confidence the number and duration of signalling failures the network can tolerate without impacting on service levels.

 

Parliamentary reference - Report number #170 - released 15 August 2007

Published

Actions for Connecting with public transport

Connecting with public transport

Transport
Information technology
Infrastructure
Internal controls and governance
Management and administration
Project management
Service delivery
Workforce and capability

We see considerable potential for the Ministry of Transport to plan and manage interchanges more effectively, so as to make better use of our public transport network. We believe that the Ministry now needs to focus more on multi-modal transport planning and interchange performance. It needs to assign responsibility for the coordination and oversight of inter-modal operations to an entity resourced for the purpose. Without this it will continue to be very difficult to identify and address unmet needs, seek and secure stakeholder funding, and monitor and evaluate system performance.

 

Parliamentary reference - Report number #168 - released 6 June 2007

Published

Actions for Using computers in schools for teaching and learning: Follow-up audit

Using computers in schools for teaching and learning: Follow-up audit

Education
Information technology
Management and administration
Service delivery
Workforce and capability

We consider that students and teachers have significantly better access to computers than was the case when we did our 2000 audit. Teachers and students are also increasingly using computers for teaching and learning. The Department of Education and Training has been proactive in advancing Information Communication Technology (ICT) into schools. However we found that teachers and students are less likely to use computers if there are problems with infrastructure or technical support.

 

Parliamentary reference - Report number #166 - released 9 May 2007

Published

Actions for Educating primary school students with disabilities

Educating primary school students with disabilities

Education
Internal controls and governance
Management and administration
Service delivery
Workforce and capability

Special education programs so far have been able to support schools to accommodate these students and as a result, we have an inclusive education system. Our concern is that as the number of students with disabilities increases, pressure will be placed on both funding and the capacity of schools to provide quality services.

The Government’s special education initiative is a positive step towards addressing these problems. Nevertheless, other changes need to be made to improve services to meet the needs of individual students. For example, the department needs to develop a common assessment tool to capture the additional support needs of students with disabilities on enrolment and improve accountability for services and results after enrolment.

 

Parliamentary reference - Report number #158 - released 6 September 2006

Published

Actions for Condition of State Roads

Condition of State Roads

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Service delivery

The Roads and Traffic Authority (RTA) has improved the overall surface condition of State Roads in the last decade. Country road surfaces are now generally much better. Ride quality has improved and cracking has been reduced. The RTA has also achieved a substantial reduction in the number of structurally deficient bridges over the same period. 

Despite a significant increase in the State’s contribution to maintenance since 1999-2000, the RTA has deferred road rebuilding projects. The RTA is rebuilding at less than half its long term target, and has not met this target at any time this decade. The RTA has not identified how it will address deferred rebuilding, although it advises it is developing a new road network management plan which will address this.

 

Parliamentary reference - Report number #157 - released 16 August 2006

Published

Actions for The Cross City Tunnel Project

The Cross City Tunnel Project

Transport
Treasury
Premier and Cabinet
Planning
Environment
Infrastructure
Management and administration
Procurement
Project management
Risk

In our opinion the Government’s ‘no net cost to government’ requirement was a legitimate (but not the only possible) basis for the tunnel bid process. The Government was entitled to decide that tunnel users meet the tunnel costs. Structuring the bid process on the basis of an upfront reimbursement of costs incurred (or to be incurred) by the Roads and Traffic Authority (RTA) was therefore appropriate.

In our opinion, however, the Government, Treasury and the RTA did not sufficiently consider the implications of an upfront payment involving more than simple project cost reimbursement (i.e. the ‘Business Consideration Fee’ component). In addition, the RTA was wrong to change the toll escalation factor late in 2002 to compensate the tunnel operator, Cross City Motorway Pty Ltd, for additional costs.

 

Parliamentary reference - Report number #152 - released 31 May 2006

Published

Actions for Agencies working together to improve services

Agencies working together to improve services

Premier and Cabinet
Treasury
Justice
Transport
Education
Internal controls and governance
Service delivery
Shared services and collaboration

In the cases we examined, we found that agencies working together can improve services or results. However, the changes were not always as great as anticipated or had not reached maximum potential. Establishing the right governance framework and accountability requirements between partners at the start of the project is critical to success. And joint responsibility requires new funding and reporting arrangements to be developed.

 

Parliamentary reference - Report number #149 - released 22 March 2006