Refine search Expand filter

Reports

Published

Actions for Transport 2020

Transport 2020

Transport
Asset valuation
Cyber security
Financial reporting
Information technology
Infrastructure
Project management

1. Financial Reporting

Audit opinion Unmodified audit opinions issued for the financial statements of all Transport cluster entities.
Quality and timeliness of financial reporting All cluster agencies met the statutory deadlines for completing the early close and submitting the financial statements.

Transport cluster agencies continued to experience some challenges with accounting for land and infrastructure assets. The former Roads and Maritime Services and Sydney Metro recorded prior period corrections to property, plant and equipment balances.
Impact of COVID-19 on passenger revenue and patronage Total patronage and revenue for public transport decreased by approximately 18 per cent in 2019–20 due to COVID-19.

The Transport cluster received additional funding from NSW Treasury during the year to support the reduced revenue and additional costs incurred such as cleaning on all modes of public transport and additional staff to manage physical distancing.
Completion of the CBD and South East Light Rail The CBD and South East Light Rail project was completed and commenced operations in this financial year. At 30 June 2020, the total cost of the project related to the CBD and South East Light Rail was $3.3 billion. Of this total cost, $2.6 billion was recorded as assets, whilst $700 million was expensed.

2. Audit Observations

Internal control While internal controls issues raised in management letters in the Transport cluster have decreased compared to the prior year, control weaknesses continue to exist in access security for financial systems. We identified 56 management letter findings across the cluster and 43 per cent of all issues were repeat issues. The majority of the repeat issues relate to information technology controls around user access management.

There were three high risk issues identified - two related to financial reporting of assets and one for implementation of TAHE (see below).
Agency responses to emergency events Transport for NSW established the COVID-19 Taskforce in March 2020 to take responsibility for the overall response of planning and coordination for the Transport cluster. It also implemented the COVIDSafe Transport Plan which incorporates guidance on physical distancing, increasing services to support social distancing and cleaning.
RailCorp transition to TAHE On 1 July 2020, RailCorp was renamed Transport Asset Holding Entity of New South Wales (TAHE) and converted to a for-profit statutory State-Owned Corporation. TAHE is a commercial for-profit Public Trading Entity with the intent to provide a commercial return to its shareholders.

A plan was established by NSW Treasury to transition RailCorp to TAHE which covered the period 1 July 2015 to 1 July 2019. A large portion of the planned arrangements were not implemented by 1 July 2020. As at the time of this report, the TAHE operating model, Statement of Corporate Intent (SCI) and other key plans and commercial agreements are not finalised. The State Owned Corporations Act 1989 generally requires finalisation of an SCI three months after the commencement of each financial year. However, under the Transport Administration Act 1988, TAHE received an extension from the voting shareholders, the Treasurer and Minister for Finance and Small Business, to submit its first SCI by 31 December 2020. In accordance with the original plan, interim commercial access arrangements were supposed to be in place with RailCorp prior to commencement of TAHE.

Under the transitional arrangements, TAHE is continuing to operate in accordance with the asset and safety management plans of RailCorp. The final operating model is expected to include considerations of safety, operational, financial and fiscal risks. This should include a consideration of the potential conflicting objectives of a commercial return, and maintenance and safety measures.

This matter has been included as a high risk finding in our management letter due to the significance of the financial reporting impacts and business risks for TAHE.

Recommendation: TAHE management should:
  • establish an operating model in line with the original intent of a commercial return
  • finalise commercial agreements with the public rail operators
  • confirm forecast financial information to assess valuation of TAHE infrastructure
  • finalise asset and safety management plans.

Resolution of the above matters are critical as they may significantly impact the financial reporting arrangements for TAHE for 2020–21, in particular, accounting policies adopted as well as measurement principles of its significant infrastructure asset base.

Completeness and accuracy of contracts registers Across the Transport cluster, contracts and agreements are maintained by the transport agencies using disparate registers.

Recommendation (repeat): Transport agencies should continue to implement a process to centrally capture all contracts and agreements entered. This will ensure:
  • agencies are fully aware of contractual and other obligations
  • appropriate assessment of financial reporting implications
  • ongoing assessments of accounting standards, in particular AASB 16 ‘Leases’, AASB 15 'Revenue from Contract with Customers', AASB 1058 'Income of Not-for-Profit Entities' and new accounting standard AASB 1059 'Service Concession Arrangements: Grantors' are accurate and complete.

 

This report provides parliament and other users of the Transport cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations
  • the impact of emergencies and the pandemic.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Transport cluster for 2020, including any financial implications from the recent emergency events.

Section highlights

  • Total patronage and revenue for public transport decreased by approximately 18 per cent in 2019–20 due to COVID-19.
  • Unqualified audit opinions were issued on all Transport agencies' financial statements.
  • Transport cluster agencies continued to experience challenges with accounting of land and infrastructure assets.

 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our:

  • observations and insights from our financial statement audits of agencies in the Transport cluster
  • assessment of how well cluster agencies adapted their systems, policies and procedures, and governance arrangements in response to recent emergencies.

Section highlights

  • While there was a decrease in findings on internal controls across the Transport cluster, 43 per cent of all issues were repeat issues. Many repeat issues related to information technology controls around user access management.
  • RailCorp transitioned to TAHE on 1 July 2020. TAHE's operating model and commercial arrangements with public rail operators has not been finalised despite government original plans to be operating from 1 July 2019. TAHE management should finalise its operating model and commercial agreements with public rail operators as they may significantly impact the financial reporting arrangements for TAHE for 2020–21.
  • Completeness and accuracy of contracts registers remains an ongoing issue for the Transport cluster.

Appendix one – List of 2020 recommendations

Appendix two – Status of 2019, 2018 and 2017 recommendations

Appendix three – Management letter findings

Appendix four – Financial data

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Education 2020

Education 2020

Education
Asset valuation
Compliance
Financial reporting
Fraud
Information technology
Internal controls and governance
Management and administration
Procurement

The Auditor-General for New South Wales, Margaret Crawford, released a report today titled Education 2020. This report focuses on key observations and findings from the most recent audits of agencies in the Education cluster.

Unqualified audit opinions were issued for all cluster agencies’ financial statements. However, internal control deficiencies were identified across the cluster agencies, including deficiencies in the management of purchasing cards and 15 internal control issues that were repeated from the previous year.

The 2019–20 natural disasters caused widespread damage in both Northern and Southern NSW. The COVID‑19 pandemic further challenged agencies, requiring social distancing and other infection control measures which disrupted the traditional means of teaching students. Agencies have adjusted their operations to respond to these emergency events.

The TAFE Commission’s revenues 2019–20 were impacted by the pandemic. Lower enrolments and an increase in fee-free short courses offered during the year contributed to the result.

Read the PDF report

This report analyses the results of our audits of financial statements of entities within the Education cluster for the year ended 30 June 2020. The table below summarises our key observations and recommendations.

1. Financial reporting 

Audit opinions Unqualified audit opinions were issued for all cluster agencies' 30 June 2020 financial statements audits.
New accounting standards

Agencies implemented three new accounting standards during the year.

Our financial statement audits of the Department of Education (the Department) and NSW Education Standards Authority (NESA) identified issues with the leasing information provided by Property NSW (PNSW). Despite the outsourcing arrangement, both the Department and NESA remain ultimately responsible for the completeness and accuracy of this information, which would have benefited from a more thorough quality assurance, validation and review process before they placed reliance upon it.

Recommendation:

We recommend the Department and NESA:

  • quality assure and validate the information provided by PNSW
  • ensure changes made by PNSW to lease data are supported and that assumptions and judgements applied are appropriate
  • document their review of the data supplied.
Changes were made to the financial reporting requirements this year to account for the impact of the pandemic

Emergency legislation was enacted during the year in response to the COVID-19 pandemic. The legislation revised the statutory reporting deadlines for agencies to submit their financial statements and allowed the Treasurer to continue authorising payments from the consolidated fund until the enactment of the 2020–21 budget.

All cluster agencies prepared their financial statements on a going concern basis and submitted their financial statements within the revised statutory deadlines.

The State provided $159.0 million in stimulus funding to support the operations of cluster agencies during emergency events. Nearly half of this funding was to support cleaning activities by the Department and the Technical and Further Education Commission (the TAFE Commission) during the COVID-19 pandemic.

Quality and timeliness of financial reporting

The number of monetary misstatements identified in agencies' financial statements decreased to 14 (23 in 2018–19).

While the number of corrections made to the financial statements after the submission date increased to eight (two in 2018–19), it is important to note these corrections provide parliament and other users of the financial statements increased confidence in the accuracy and presentation of agencies' performance and financial position.

Sustainability of cluster agencies The TAFE Commission's enrolments declined, and operating margins reduced, both being impacted by the COVID-19 pandemic.

2. Audit observations

Internal control deficiencies

We identified 33 internal control issues, including 15 findings that were repeated from previous years.

A high-risk issue was reported at the Department relating to the inadequate monitoring and follow up of privileged user activity in its enterprise resource planning system – SAP.

Repeat findings relate to ongoing deficiencies in information technology controls and management policies, practices and procedures.

Recommendation:

Cluster agencies should:

  • prioritise and action recommendations to address internal control deficiencies
  • review and confirm the appropriateness of existing privileged user access accounts
  • implement a rigorous monitoring regime to ensure that any improper use of privileged user accounts can be detected in a timely manner.
Agency responses to emergency events

The Department established a separate bushfire relief directorate and COVID-19 Taskforce to assist and support school communities in response to recent emergencies.

Other cluster agencies have established committees or response teams to oversee and address all aspects of the impact of COVID-19.

Schools review 2019 We continue to identify instances of non-compliance in relation to cash management and procurement at schools.
Use of purchasing cards at the Department of Education

Since 2015, the NSW Government has encouraged the use of purchasing cards by public sector agencies. Purchasing cards are efficient to transact low value, high volume procurement of goods and services, but the use must be effectively monitored.

Our review of the Department's purchasing cards identified weaknesses in its oversight and monitoring controls, including the issue and cancellation of purchasing cards

Opportunities exist for the Department to better monitor card use. Tools such as data analytics are an efficient and effective detective control to identify irregular activity or misuse by cardholders.

Recommendation:

The Department should:

  • improve the accuracy and completeness of exit procedures for terminated employees to ensure cards are returned and cancelled
  • perform periodic reviews to ensure active cards are held only by current employees
  • set transaction limits that do not exceed the limits of the user’s financial delegation
  • establish a data analytics regime to help analyse and identify high risk patterns and anomalies in their purchasing card usage, augmenting their existing monitoring and detective controls.

 

This report provides parliament and other users of the Education cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations
  • the impact of emergencies and the COVID-19 pandemic.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

The COVID-19 Legislation Amendment (Emergency Measures–Treasurer) Act 2020 amended legislation administered by the Treasurer to implement further emergency measures as a result of the COVID-19 pandemic. These amendments:

  • allowed the Treasurer to authorise payments from the consolidated fund until the enactment of the 2020–21 budget – supporting the going concern assessments of cluster agencies
  • revised budgetary, financial and annual reporting time frames – impacting the timeliness of financial reporting
  • exempted certain statutory bodies and departments from preparing financial statements.

This chapter outlines our audit observations related to the financial reporting of agencies in the Education cluster for 2020, including any financial implications from the recent emergency events.

Section highlights 

Unqualified audit opinions were issued on the financial statements of cluster agencies.

All cluster agencies met the revised statutory deadlines for completing early close procedures and submitting their financial statements.
 
Emergency legislation allowing the Treasurer to continue authorising payments from the consolidated fund under the existing Appropriations Act enabled cluster agencies to prepare financial statements on a going concern basis.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our:

  • observations and insights from our financial statement audits of agencies in the Education cluster. It also comments on our review of elements of the financial control framework applied by schools in NSW whose financial results form part of the Department of Education's (the Department) financial statements.
  • assessment of how well cluster agencies adapted their systems, policies and procedures, and governance arrangements in response to recent emergencies.

Section highlights

  • A high-risk issue regarding inadequate monitoring of privileged user access was identified at the Department.
  • We continue to observe issues by schools in relation to cash management and non-compliance with procurement guidelines and purchasing card use.
  • Opportunities exist for the Department and cluster agencies to enhance their monitoring and review of purchasing card activities. Tools such as data analytics procedures provide an efficient and effective detective control, particularly when used in conjunction with independent spot-checks.

Appendix one – List of 2020 recommendations

Appendix two – Status of 2019 and 2018 recommendations

Appendix three – Financial data

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for CBD South East Sydney Light Rail: follow-up performance audit

CBD South East Sydney Light Rail: follow-up performance audit

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk
Service delivery

This is a follow-up to the Auditor-General's November 2016 report on the CBD South East Sydney Light Rail project. This follow-up report assessed whether Transport for NSW has updated and consolidated information about project costs and benefits.

The audit found that Transport for NSW has not consistently and accurately updated project costs, limiting the transparency of reporting to the public.

The Auditor-General reports that the total cost of the project will exceed $3.1 billion, which is above the revised cost of $2.9 billion published in November 2019. $153.84 million of additional costs are due to omitted costs for early enabling works, the small business assistance package and financing costs attributable to project delays.

The report makes four recommendations to Transport for NSW to publicly report on the final project cost, the updated expected project benefits, the benefits achieved in the first year of operations and the average weekly journey times.

Read full report (PDF)

The CBD and South East Light Rail is a 12 km light rail network for Sydney. It extends from Circular Quay along George Street to Central Station, through Surry Hills to Moore Park, then to Kensington and Kingsford via Anzac Parade and Randwick via Alison Road and High Street.

Transport for NSW (TfNSW) is responsible for planning, procuring and delivering the Central Business District and South East Light Rail (CSELR) project. In December 2014, TfNSW entered into a public private partnership with ALTRAC Light Rail as the operating company (OpCo) responsible for delivering, operating and maintaining the CSELR. OpCo engaged Alstom and Acciona, who together form its Design and Construct Contractor (D&C).

On 14 December 2019, passenger services started on the line between Circular Quay and Randwick. Passenger services on the line between Circular Quay and Kingsford commenced on 3 April 2020.

In November 2016, the Auditor-General published a performance audit report on the CSELR project. The audit found that TfNSW would deliver the CSELR at a higher cost with lower benefits than in the approved business case, and recommended that TfNSW update and consolidate information about project costs and benefits and ensure the information is readily accessible to the public.

In November 2018, the Public Accounts Committee (PAC) examined TfNSW's actions taken in response to our 2016 performance audit report on the CSELR project. The PAC recommended that the Auditor-General consider undertaking a follow-up audit on the CSELR project. The purpose of this follow-up performance audit is to assess whether TfNSW has effectively updated and consolidated information about project costs and benefits for the CSELR project.

Conclusion

Transport for NSW has not consistently and accurately updated CSLER project costs, limiting the transparency of reporting to the public. In line with the NSW Government Benefits Realisation Management Framework, TfNSW intends to measure benefits after the project is completed and has not updated the expected project benefits since April 2015.

Between February 2015 and December 2019, Transport for NSW (TfNSW) regularly updated capital expenditure costs for the CSELR in internal monthly financial performance and risk reports. These reports did not include all the costs incurred by TfNSW to manage and commission the CSELR project.

Omitted costs of $153.84 million for early enabling works, the small business assistance package and financing costs attributable to project delays will bring the current estimated total cost of the CSELR project to $3.147 billion.

From February 2015, TfNSW did not regularly provide the financial performance and risk reports to key CSELR project governance bodies. TfNSW publishes information on project costs and benefits on the Sydney Light Rail website. However, the information on project costs has not always been accurate or current.

TfNSW is working with OpCo partners to deliver the expected journey time benefits. A key benefit defined in the business plan was that bus services would be reduced owing to transfer of demand to the light rail - entailing a saving. However, TfNSW reports that the full expected benefit of changes to bus services will not be realised due to bus patronage increasing above forecasted levels.

Appendix one – Response from agency

Appendix two – Governance and reporting arrangements for the CSELR

Appendix three – 2018 CSELR governance changes

Appendix four – About the audit

Appendix five – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #335 - released 11 June 2020

Published

Actions for Train station crowding

Train station crowding

Transport
Management and administration
Risk
Service delivery
Workforce and capability

This report focuses on how Transport for NSW and Sydney Trains manage crowding at selected metropolitan train stations.

The audit found that while Sydney Trains has identified platform crowding as a key strategic risk, it does not have an overarching strategy to manage crowding in the short to medium term. Sydney Trains 'do not have sufficient oversight to know if crowding is being effectively managed’, the Auditor-General said.

Sydney Trains' operational response to crowding involves restricting customer access to platforms or station entries before crowding reaches unsafe levels or when it impacts on-time running. Assuming rail patronage increases, it is likely that Sydney Trains will restrict more customers from accessing platforms or station entries, causing customer delay. ‘Restricting customer access to platforms or station entries is not a sustainable approach to manage station crowding’, said the Auditor-General.

The Auditor-General made seven recommendations to improve Transport for NSW and Sydney Trains' management of station crowding. Transport for NSW have accepted these recommendations on behalf of the Transport cluster.

Public transport patronage has been impacted by COVID-19. This audit was conducted before these impacts occurred.

Read full report (PDF)

Sydney Trains patronage has increased by close to 34 per cent over the last five years, and Transport for NSW (TfNSW) expects the growth in patronage to continue over the next 30 years. As patronage increases there are more passengers entering and exiting stations, moving within stations to change services, and waiting on platforms. As a result, some Sydney metropolitan train stations are becoming increasingly crowded.

There are three main causes of station crowding:

  • patronage growth exceeding the current capacity limits of the rail network
  • service disruptions
  • special events.

Crowds can inhibit movement, cause discomfort and can lead to increased health and safety risks to customers. In the context of a train service, unmanaged crowds can affect service operation as trains spend longer at platforms waiting for customers to alight and board services which can cause service delays. Crowding can also prevent customers from accessing services.

Our 2017 performance audit, ‘Passenger Rail Punctuality’, found that rail agencies would find it hard to maintain train punctuality after 2019 unless they significantly increased the capacity of the network to carry trains and people. TfNSW and Sydney Trains have plans to improve the network to move more passengers. These plans are set out in strategies such as More Trains, More Services and in the continued implementation of new infrastructure such as the Sydney Metro. Since 2017, TfNSW and Sydney Trains have introduced 1,500 more weekly services to increase capacity. Additional network capacity improvements are in progress for delivery from 2022 onwards.

In the meantime, TfNSW and Sydney Trains need to use other ways of managing crowding at train stations until increased capacity comes on line.

This audit examined how effectively TfNSW and Sydney Trains are managing crowding at selected metropolitan train stations in the short and medium term. In doing so, the audit examined how TfNSW and Sydney Trains know whether there is a crowding problem at stations and how they manage that crowding.

TfNSW is the lead agency for transport in NSW. TfNSW is responsible for setting the standard working timetable that Sydney Trains must implement. Sydney Trains is responsible for operating and maintaining the Sydney metropolitan heavy rail passenger service. This includes operating, staffing and maintaining most metropolitan stations. Sydney Trains’ overall responsibility is to run a safe rail network to timetable.

Conclusion

Sydney Trains has identified platform crowding as a key strategic risk, but does not have an overarching strategy to manage crowding in the short to medium term. TfNSW and Sydney Trains devolve responsibility for managing crowding at stations to Customer Area Managers, but do not have sufficient oversight to know if crowding is being effectively managed. TfNSW is delivering a program to influence demand for transport in key precincts but the effectiveness of this program and its impact on station crowding is unclear as Transport for NSW has not evaluated the outcomes of the program.

TfNSW and Sydney Trains do not directly measure or collect data on station crowding. Data and observation on dwell time, which is the time a train waits at a platform for customers to get on and off trains, inform the development of operational approaches to manage crowding at stations. Sydney Trains has KPIs on reliability, punctuality and customer experience and use these to indirectly assess the impact of station crowding. TfNSW and Sydney Trains only formally assess station crowding as part of planning for major projects, developments or events.

Sydney Trains devolve responsibility for crowd management to Customer Area Managers, who rely on frontline Sydney Trains staff to understand how crowding affects individual stations. Station staff at identified key metropolitan train stations have developed customer management plans (also known as crowd management plans). However, Sydney Trains does not have policies to support the creation, monitoring and evaluation of these plans and does not systematically collect data on when station staff activate crowding interventions under these plans.

Sydney Trains stated focus is on providing a safe and reliable rail service. As such, management of station crowding is a by-product of its strategies to manage customer safety and ensure on-time running of services. Sydney Trains' operational response to crowding involves restricting customer access to platforms or stations before crowding reaches unsafe levels, or when it impacts on-time running. As rail patronage increases, it is likely that Sydney Trains will need to increase its use of interventions to manage crowding. As Sydney Trains restrict more customers from accessing platforms or station entries, it is likely these customers will experience delays caused by these interventions.

Since 2015, TfNSW has been delivering the 'Travel Choices' program which aims to influence customer behaviour and to manage the demand for public transport services in key precincts. TfNSW is unable to provide data demonstrating the overall effectiveness of this program and the impact the program has on distributing public transport usage out of peak AM and PM times. TfNSW and Sydney Trains continue to explore initiatives to specifically address crowd management.

Conclusion

TfNSW and Sydney Trains do not directly measure or collect data on station crowding. There are no key performance indicators directly related to station crowding. Sydney Trains uses performance indicators on reliability, punctuality and customer experience to indirectly assess the impact of station crowding. Sydney Trains does not have a routine process for identifying whether crowding contributed to minor safety incidents. TfNSW and Sydney Trains formally assess station crowding as part of planning for major projects, developments or events.

 

Conclusion

Sydney Trains has identified platform crowding as a strategic risk but does not have an overarching strategy to manage station crowding. Sydney Trains' stated focus is on providing a safe and reliable rail service. As such, management of station crowding is a by-product of its strategies to manage customer safety and ensure on-time running of services.

Sydney Trains devolve responsibility for managing crowding at stations to Customer Area Managers but does not have sufficient oversight to know that station crowding is effectively managed. Sydney Trains does not have policies to support the creation, monitoring or evaluation of crowd management plans at key metropolitan train stations. The use of crowding interventions is likely to increase due to increasing patronage, causing more customers to experience delays directly caused by these activities.

TfNSW and Sydney Trains have developed interventions to influence customer behaviour and to manage the demand for public transport services but are yet to evaluate these interventions. As such, their impact on managing station crowding is unclear.

Appendix one – Response from agency

Appendix two – Sydney rail network

Appendix three – Rail services contract

Appendix four – Crowding pedestrian modelling

Appendix five – Airport Link stations case study

Appendix six – About the audit

Appendix seven – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #333 - released 30 April 2020

 

Published

Actions for Local Schools, Local Decisions: needs-based equity funding

Local Schools, Local Decisions: needs-based equity funding

Education
Internal controls and governance
Management and administration
Service delivery

The Auditor-General for New South Wales, Margaret Crawford, released a report today examining the Department of Education’s (the department’s) support and oversight of school planning and use of needs-based funding under the Local Schools, Local Decisions reform.

The report found the department has not had adequate oversight of how schools are using needs-based funding to improve student outcomes since it was introduced in 2014.

The department had not set measures or targets for needs-based equity funding. It had also not been clear enough in how it expected schools to report on the outcomes of additional funding. This means it has not been able to effectively demonstrate the impact of funding at a school, or state-wide level.

To assist with the transition to greater local decision-making, the department provided schools with guidance materials, additional resources and systems support. However, guidance material was not clear enough on the purpose of funding, school budgeting systems were not fit-for-purpose when initially introduced, and support for schools was spread across different areas of the department.

The department has recently increased executive oversight of progress to improve educational outcomes for Aboriginal students and students from a low socio-economic background. It has also developed a consistent set of school-level targets to be implemented from 2020. This may help the department more reliably monitor progress in lifting outcomes for students with additional learning needs.

The report makes eight recommendations aimed at clarifying requirements of schools, better coordinating support and strengthening oversight of the use of needs-based equity funding.

Read full report (PDF)

The Local Schools, Local Decisions reform was launched in 2012 to give public schools more authority to make local decisions about how best to meet the needs of their students. A major element of the reform was the introduction of a new needs-based school funding model. Core elements of the model address staffing and operational requirements, while needs-based elements reflect the characteristics of schools and students within them. This includes equity funding designed to support students with additional needs. The four categories of equity funding are:

  • socio-economic background
  • Aboriginal background
  • English language proficiency
  • low-level adjustment for disability. 

Around $900 million in equity funding was allocated in 2019. School principals decide how to use these funds and account for them through their school annual reports. The Department of Education (the department) supports schools in making these choices with tools and systems, guidelines, and good practice examples.

The objective of this audit was to assess the department's support and oversight of school planning and use of needs-based funding under the Local Schools, Local Decisions reform. To address this objective, the audit examined whether:

  • effective accountability arrangements have been established
  • effective support is provided to schools.  

Conclusion

The department has not had adequate oversight of how schools are using needs-based equity funding to improve student outcomes since it was introduced in 2014. While it provides guidance and resources, it has not set measures or targets to describe the outcomes expected of this funding, or explicit requirements for schools to report outcomes from how these funds were used. Consequently, there is no effective mechanism to capture the impact of funding at a school, or state-wide level. The department has recently developed a consistent set of school-level targets to be implemented from 2020. This may help it to better hold schools accountable for progress towards its strategic goal of reducing the impact of disadvantage.

A significant amount of extra funding has been provided to schools over recent years in recognition of the additional learning needs of certain groups of students facing disadvantage. Under the Local Schools, Local Decisions reform, schools were given the ability to make decisions about how best to use the equity funding in combination with their overall school resources to meet their students’ needs. However, multiple guidelines provided to schools contain inconsistent advice on how the community should be consulted, how funding could be used, and how impact should be reported. Because of this, it is not clear how schools have used equity funding for the benefit of identified groups. School annual reports we reviewed did not fully account for the equity funding received, nor adequately describe the impact of funding on student outcomes.

To help in the transition to greater local decision-making, the department provided extra support by; establishing peer support for new principals, increasing the number of directors, developing data analysis and financial planning systems, targeted training and showcasing good practice. Multiple roles and areas of the department provide advice to schools in similar areas and this support could be better co-ordinated.

Financial planning systems designed to help schools budget for equity and other funding sources were not fit-for-purpose when originally introduced. Schools reported a lack of trust in their budget figures and so were not fully spending their allocated funding. Since then, the department developed and improved a budgeting tool in consultation with stakeholder and user groups. It provided extra funding for administrative support and one-to-one training to help schools develop their capabilities. Despite this, schools we spoke to reported they were not yet fully confident in using the system and needed ongoing training and support. 

Appendix one – Response from agency

Appendix two – About the audit

Appendix three – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #331 - released 8 April 2020.

Published

Actions for Education 2018

Education 2018

Education
Asset valuation
Financial reporting
Information technology
Infrastructure
Service delivery
Shared services and collaboration
Workforce and capability

The Auditor-General for New South Wales, Margaret Crawford, released her report today on the results of the financial audits of agencies in the Education cluster. The report focuses on key observations and findings from the most recent financial audits of these agencies. 'I am pleased to report that unqualified audit opinions were issued on the financial statements of both agencies in the Education cluster', the Auditor-General said. Statements were submitted and audited within statutory deadlines.

This report analyses the results of our audits of financial statements of the Education cluster for the year ended 30 June 2018. The table below summarises our key observations.

This report provides parliament and other users of the Education cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations
  • service delivery.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Education cluster for 2017–18.

Observation Conclusions and recommendations
2.1 Quality of financial reporting
Unqualified audit opinions were issued on the financial statements of both cluster agencies. Sufficient audit evidence was obtained to conclude the financial statements were free of material misstatement.
2.2 Timeliness of financial reporting
Both cluster agencies met the statutory deadlines for completing early close procedures and submitting financial statements. Early close procedures continue to facilitate the timely preparation of cluster agencies’ financial statements and completion of audits, but scope exists to improve outcomes by resolving issues and supplying supporting documentation earlier.
2.3 Key issues from financial audits
Inconsistencies in the Department’s annual leave and long service leave data, identified over the past three audits, remain unresolved. This issue impacts the Department’s liability estimates for annual leave and long service leave, including associated on-costs. It also on-flows to the Crown Entity, which assumes the Department's liability for long service leave. Recommendation: The Department should confirm leave data and review assumptions following deployment of the new HR/Payroll system to better estimate the liability for employee benefits and the amount to be assumed by the Crown Entity.
2.4 Key financial information
Cluster agencies recorded net deficits in 2017–18.

The Department recorded a net deficit of $30.7 million in 2017–18 against a budgeted surplus of $122 million.

The NSW Education Standards Authority recorded a net deficit of $4.1 million against a budgeted deficit of $4.7 million.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from:

  • our financial statement audits of agencies in the Education cluster for 2018
  • the areas of focus identified in the Audit Office work program.

The Audit Office Annual Work Program provides a summary of all audits to be conducted within the proposed time period as well as detailed information on the areas of focus for each of the NSW Government clusters.

Observation Conclusions and recommendations
3.1  Internal controls
Twenty internal control deficiencies were identified during our audits of cluster agencies. We assessed one as a high risk finding.  
Eight internal control weaknesses were repeat issues from previous financial audits that had not been fully addressed by management. Recommendation: Management should prioritise and action recommendations to address internal control weaknesses.
3.2 Information technology
Delivery of the Learning Management and Business Reform (LMBR) program is complete.

The LMBR program has been a major project for the Department since it was established in 2006.

A staged approach was adopted for implementing the Department’s new HR/Payroll system to manage the risks associated with this large-scale roll-out.

3.3 Valuation of the Department’s land and buildings
The Department completed a revaluation of land and building assets during 2017–18.

A market approach was used to revalue the Department’s land, resulting in a revaluation increment of $2.3 billion.

A current replacement cost approach was used to revalue the Department’s school buildings, resulting in an increment of $6.2 billion.

3.4 Maintenance of school facilities
The Department regularly assesses the condition of school buildings and uses Life Cycle Costing to predict maintenance and capital renewal, and to prioritise maintenance activities. The Life Cycle Costing assessment conducted by the Department in 2017–18 rated 70 per cent of school buildings as being in either as new or good condition. No school buildings were rated as being in end-of-life condition.
3.4 School asset delivery
The Department’s School Assets Strategic Plan is designed to ensure that there are sufficient fit-for-purpose places for students up to 2031. The Department created a new division, School Infrastructure NSW, to oversee the planning, supply and maintenance of schools and implement major school infrastructure projects.

This chapter provides service delivery outcomes for the Education cluster for 2017–18. It provides important contextual information about the cluster's operation, but the data on achievement of these outcomes is not audited. The Audit Office does not have a specific mandate to audit performance information.

Published

Actions for Newcastle Urban Transformation and Transport Program

Newcastle Urban Transformation and Transport Program

Transport
Planning
Compliance
Infrastructure
Management and administration
Procurement
Project management

The urban renewal projects on former railway land in the Newcastle city centre are well targeted to support the objectives of the Newcastle Urban Transformation and Transport Program (the Program), according to a report released today by the Auditor-General for New South Wales, Margaret Crawford. The planned uses of the former railway land achieve a balance between the economic and social objectives of the Program at a reasonable cost to the government. However, the evidence that the cost of the light rail will be justified by its contribution to the Program is not convincing.

The Newcastle Urban Transformation and Transport Program (the Program) is an urban renewal and transport program in the Newcastle city centre. The Hunter and Central Coast Development Corporation (HCCDC) has led the Program since 2017. UrbanGrowth NSW led the Program from 2014 until 2017. Transport for NSW has been responsible for delivering the transport parts of the Program since the Program commenced. All references to HCCDC in this report relate to both HCCDC and its predecessor, the Hunter Development Corporation. All references to UrbanGrowth NSW in this report relate only to its Newcastle office from 2014 to 2017.

This audit had two objectives:

  1. To assess the economy of the approach chosen to achieve the objectives of the Program.
  2. To assess the effectiveness of the consultation and oversight of the Program.

We addressed the audit objectives by answering the following questions:

a) Was the decision to build light rail an economical option for achieving Program objectives?
b) Has the best value been obtained for the use of the former railway land?
c) Was good practice used in consultation on key Program decisions?
d) Did governance arrangements support delivery of the program?

Conclusion
1. The urban renewal projects on the former railway land are well targeted to support the objectives of the Program. However, there is insufficient evidence that the cost of the light rail will be justified by its contribution to Program objectives.

The planned uses of the former railway land achieve a balance between the economic and social objectives of the Program at a reasonable cost to the Government. HCCDC, and previously UrbanGrowth NSW, identified and considered options for land use that would best meet Program objectives. Required probity processes were followed for developments that involved financial transactions. Our audit did not assess the achievement of these objectives because none of the projects have been completed yet.

Analysis presented in the Program business case and other planning documents showed that the light rail would have small transport benefits and was expected to make a modest contribution to broader Program objectives. Analysis in the Program business case argued that despite this, the light rail was justified because it would attract investment and promote economic development around the route. The Program business case referred to several international examples to support this argument, but did not make a convincing case that these examples were comparable to the proposed light rail in Newcastle.

The audited agencies argue that the contribution of light rail cannot be assessed separately because it is a part of a broader Program. The cost of the light rail makes up around 53 per cent of the total Program funding. Given the cost of the light rail, agencies need to be able to demonstrate that this investment provides value for money by making a measurable contribution to the Program objectives.

2. Consultation and oversight were mostly effective during the implementation stages of the Program. There were weaknesses in both areas in the planning stages.

Consultations about the urban renewal activities from around 2015 onward followed good practice standards. These consultations were based on an internationally accepted framework and met their stated objectives. Community consultations on the decision to close the train line were held in 2006 and 2009. However, the final decision in 2012 was made without a specific community consultation. There was no community consultation on the decision to build a light rail.

The governance arrangements that were in place during the planning stages of the Program did not provide effective oversight. This meant there was not a single agreed set of Program objectives until 2016 and roles and responsibilities for the Program were not clear. Leadership and oversight improved during the implementation phase of the Program. Roles and responsibilities were clarified and a multi-agency steering committee was established to resolve issues that needed multi-agency coordination.
The light rail is not justified by conventional cost-benefit analysis and there is insufficient evidence that the indirect contribution of light rail to achieving the economic development objectives of the Program will justify the cost.
Analysis presented in Program business cases and other planning documents showed that the light rail would have small transport benefits and was expected to make a modest contribution to broader Program objectives. Analysis in the Program business case argued that despite this, the light rail was justified because it would attract investment and promote economic development around the route. The Program business case referred to several international examples to support this argument, but did not make a convincing case that these examples were comparable to the proposed light rail in Newcastle.
The business case analysis of the benefits and costs of light rail was prepared after the decision to build light rail had been made and announced. Our previous reports, and recent reports by others, have emphasised the importance of completing thorough analysis before announcing infrastructure projects. Some advice provided after the initial light rail decision was announced was overly optimistic. It included benefits that cannot reasonably be attributed to light rail and underestimated the scope and cost of the project.
The audited agencies argue that the contribution of light rail cannot be assessed separately because it is part of a broader Program. The cost of the light rail makes up around 53 per cent of the total Program funding. Given the high cost of the light rail, we believe agencies need to be able to demonstrate that this investment provides value for money by making a measurable contribution to the Program objectives.

Recommendations
For future infrastructure programs, NSW Government agencies should support economical decision-making on infrastructure projects by:
  • providing balanced advice to decision makers on the benefits and risks of large infrastructure investments at all stages of the decision-making process
  • providing scope and cost estimates that are as accurate and complete as possible when initial funding decisions are being made
  • making business cases available to the public.​​​​​​
The planned uses of the former railway land achieve a balance between the economic and social objectives of the Program at a reasonable cost to the government.

The planned uses of the former railway land align with the objectives of encouraging people to visit and live in the city centre, creating attractive public spaces, and supporting growth in employment in the city. The transport benefits of the activities are less clear, because the light rail is the major transport project and this will not make significant improvements to transport in Newcastle.

The processes used for selling and leasing parts of the former railway land followed industry standards. Options for the former railway land were identified and assessed systematically. Competitive processes were used for most transactions and the required assessment and approval processes were followed. The sale of land to the University of Newcastle did not use a competitive process, but required processes for direct negotiations were followed.

Recommendation
By March 2019, the Hunter and Central Coast Development Corporation should:
  • work with relevant stakeholders to explore options for increasing the focus on the heritage objective of the Program in projects on the former railway land. This could include projects that recognise the cultural and industrial heritage of Newcastle.
Consultations about the urban renewal activities followed good practice standards, but consultation on transport decisions for the Program did not.

Consultations focusing on urban renewal options for the Program included a range of stakeholders and provided opportunities for input into decisions about the use of the former railway land. These consultations received mostly positive feedback from participants. Changes and additions were made to the objectives of the Program and specific projects in response to feedback received. 

There had been several decades of debate about the potential closure of the train line, including community consultations in 2006 and 2009. However, the final decision to close the train line was made and announced in 2012 without a specific community consultation. HCCDC states that consultation with industry and business representatives constitutes community consultation because industry representatives are also members of the community. This does not meet good practice standards because it is not a representative sample of the community.

There was no community consultation on the decision to build a light rail. There were subsequent opportunities for members of the community to comment on the implementation options, but the decision to build it had already been made. A community and industry consultation was held on which route the light rail should use, but the results of this were not made public. 

Recommendation
For future infrastructure programs, NSW Government agencies should consult with a wide range of stakeholders before major decisions are made and announced, and report publicly on the results and outcomes of consultations. 

The governance arrangements that were in place during the planning stages of the Program did not provide effective oversight. Project leadership and oversight improved during the implementation phase of the Program.

Multi-agency coordination and oversight were ineffective during the planning stages of the Program. Examples include: multiple versions of Program objectives being in circulation; unclear reporting lines for project management groups; and poor role definition for the initial advisory board. Program ownership was clarified in mid-2016 with the appointment of a new Program Director with clear accountability for the delivery of the Program. This was supported by the creation of a multi-agency steering committee that was more effective than previous oversight bodies.

The limitations that existed in multi-agency coordination and oversight had some negative consequences in important aspects of project management for the Program. This included whole-of-government benefits management and the coordination of work to mitigate impacts of the Program on small businesses.

Recommendations
For future infrastructure programs, NSW Government agencies should: 

  • develop and implement a benefits management approach from the beginning of a program to ensure responsibility for defining benefits and measuring their achievement is clear
  • establish whole-of-government oversight early in the program to guide major decisions. This should include:
    • agreeing on objectives and ensuring all agencies understand these
    • clearly defining roles and responsibilities for all agencies
    • establishing whole-of-government coordination for the assessment and mitigation of the impact of major construction projects on businesses and the community.

By March 2019, the Hunter and Central Coast Development Corporation should update and implement the Program Benefits Realisation Plan. This should include:

  • setting measurable targets for the desired benefits
  • clearly allocating ownership for achieving the desired benefits
  • monitoring progress toward achieving the desired benefits and reporting publicly on the results.

Appendix one - Response from agencies    

Appendix two - About the audit

Appendix three - Performance auditing

 

Parliamentary reference - Report number #310 - released 12 December 2018

Published

Actions for Transport 2018

Transport 2018

Transport
Asset valuation
Compliance
Financial reporting
Infrastructure
Management and administration
Procurement
Risk
Service delivery
Workforce and capability

The Auditor-General for New South Wales, Margaret Crawford released her report today on key observations and findings from the 30 June 2018 financial statement audits of agencies in the Transport cluster. Unqualified audit opinions were issued for all agencies' financial statements. However, assessing the fair value of the broad range of transport related assets creates challenges.

This report analyses the results of our audits of financial statements of the Transport cluster for the year ended 30 June 2018. The table below summarises our key observations.

This report provides Parliament and other users of the Transport cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Transport cluster for 2018.

Observation Conclusions and recommendations
2.1 Quality of financial reporting
Unqualified audit opinions were issued for all agencies' financial statements Sufficient audit evidence was obtained to conclude the financial statements were free of material misstatement.
2.2 Key accounting issues
Valuation of assets continues to create challenges. Although agencies complied with the requirements of the accounting standards and Treasury policies on valuations, we identified some opportunities for improvements at RMS.

RMS incorporated data from its asset condition assessments for the first time in the valuation methodology which improved the valuation outcome. Overall, we were satisfied with the valuation methodology and key assumptions, but we noted some deficiencies in the asset data in relation to asset component unit rates and old condition data for some components of assets. 

Also, a bypass and tunnel were incorrectly excluded from RMS records and valuation process since 2013. This resulted in an increase for these assets’ value by $133 million.

The valuation inputs for Wetlands and Moorings were revised this year to better reflect the assets' characteristics resulting in a $98.0 million increase.

2.3 Timeliness of financial reporting
Residual Transport Corporation did not submit its financial statements by the statutory reporting deadline. Residual Transport Corporation remained a dormant entity with no transactions for the year ended 30 June 2018.
With the exception of Residual Transport Corporation, all agencies completed early close procedures and submitted financial statements within statutory timeframes. Early close procedures allow financial reporting issues and risks to be addressed early in the reporting and audit process.
2.4 Financial sustainability
NSW Trains and the Chief Investigator of the Office of Transport Safety Investigations reported negative net assets of $75.7 million and $89,000 respectively at 30 June 2018.  NSW Trains and the Chief Investigator of the Office of Transport Safety Investigations continue to require letters of financial support to confirm their ability to pay liabilities as they fall due. 
2.5 Passenger revenue and patronage
Transport agencies revenue growth increased at a higher rate than patronage. Public transport passenger revenue increased by $114 million (8.3 per cent) in 2017–18, and patronage increased by 37.1 million (5.1 per cent) across all modes of transport based on data provided by TfNSW. 
Negative balance Opal Cards resulted in $3.8 million in revenue not collected in 2017–18 and $7.8 million since the introduction of Opal. A total of 1.1 million Opal cards issued since its introduction have negative balances. Transport for NSW advised it is liaising with the ticketing vendor to implement system changes and are investigating other ways to reduce the occurrences.
2.6 Cost recovery from public transport users
Overall cost recovery from users has decreased. Overall cost recovery from public transport users (on rail and bus services by STA) decreased from 23.2 per cent to 22.4 per cent between 2016–17 and 2017–18. The main reason for the decrease is due to expenditure increasing at a faster rate than revenue in 2017–18.


 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from:

  • our financial statement audits of agencies in the Transport cluster for 2018
  • the areas of focus identified in the Audit Office annual work program.

The Audit Office Annual Work Program provides a summary of all audits to be conducted within the proposed time period as well as detailed information on the areas of focus for each of the NSW Government clusters. 

Observation Conclusions and recommendations
3.1 Internal controls 
There was an increase in findings on internal controls across the Transport cluster. Key themes related to information technology, employee leave entitlements and asset management. Eighteen per cent of all issues were repeat issues.
3.2 Audit Office Annual work program
The Transport cluster wrote-off over $200 million of assets which were replaced by new assets or technology.

Majority of this write-off was recognised by RMS, with $199 million relating to the write-off of existing assets which have been replaced during the year. 

RailCorp is expected to convert to TAHE from 1 July 2019. Several working groups are considering different aspects of the TAHE transition including its status as a for-profit Public Trading Enterprise and which assets to transfer to TAHE. We will continue to monitor developments on TAHE for any impact to the financial statements.
RMS' estimated maintenance backlog at 30 June 2018 of $3.4 billion is lower than last year. Sydney Trains' estimated maintenance backlog at 30 June 2018 increased by 20.6 per cent to $434 million. TfNSW does not quantify its backlog maintenance. TfNSW advised it is liaising with Infrastructure NSW to develop a consistent definition of maintenance backlog across all transport service providers. 
Not all agencies monitor unplanned maintenance across the Transport cluster. Unplanned maintenance can be more expensive than planned maintenance. TfNSW should develop a consistent approach to define, monitor and track unplanned maintenance across the cluster.

This chapter outlines certain service delivery outcomes for 2017–18. The data on activity levels and performance is provided by Cluster agencies. The Audit Office does not have a specific mandate to audit performance information. Accordingly, the information in this chapter is unaudited. 

We report this information on service delivery to provide additional context to understand the operations of the Transport cluster and to collate and present service information for different modes of transport in one report. 

In our recent performance audit, Progress and measurement of Premier's Priorities, we identified 12 limitations of performance measurement and performance data. We recommended that the Department of Premier and Cabinet ensure that processes to check and verify data are in place for all agency data sources.

Published

Actions for Mobile speed cameras

Mobile speed cameras

Transport
Compliance
Financial reporting
Information technology
Internal controls and governance
Management and administration
Regulation
Service delivery

Key aspects of the state’s mobile speed camera program need to be improved to maximise road safety benefits, according to a report released today by the Auditor-General for New South Wales, Margaret Crawford. Mobile speed cameras are deployed in a limited number of locations with a small number of these being used frequently. This, along with decisions to limit the hours that mobile speed cameras operate, and to use multiple warning signs, have reduced the broad deterrence of speeding across the general network - the main policy objective of the mobile speed camera program.

The primary goal of speed cameras is to reduce speeding and make the roads safer. Our 2011 performance audit on speed cameras found that, in general, speed cameras change driver behaviour and have a positive impact on road safety.

Transport for NSW published the NSW Speed Camera Strategy in June 2012 in response to our audit. According to the Strategy, the main purpose of mobile speed cameras is to reduce speeding across the road network by providing a general deterrence through anywhere, anytime enforcement and by creating a perceived risk of detection across the road network. Fixed and red-light speed cameras aim to reduce speeding at specific locations.

Roads and Maritime Services and Transport for NSW deploy mobile speed cameras (MSCs) in consultation with NSW Police. The cameras are operated by contractors authorised by Roads and Maritime Services. MSC locations are stretches of road that can be more than 20 kilometres long. MSC sites are specific places within these locations that meet the requirements for a MSC vehicle to be able to operate there.

This audit assessed whether the mobile speed camera program is effectively managed to maximise road safety benefits across the NSW road network.

Conclusion

The mobile speed camera program requires improvements to key aspects of its management to maximise road safety benefits. While camera locations have been selected based on crash history, the limited number of locations restricts network coverage. It also makes enforcement more predictable, reducing the ability to provide a general deterrence. Implementation of the program has been consistent with government decisions to limit its hours of operation and use multiple warning signs. These factors limit the ability of the mobile speed camera program to effectively deliver a broad general network deterrence from speeding.

Many locations are needed to enable network-wide coverage and ensure MSC sessions are randomised and not predictable. However, there are insufficient locations available to operate MSCs that meet strict criteria for crash history, operator safety, signage and technical requirements. MSC performance would be improved if there were more locations.

A scheduling system is meant to randomise MSC location visits to ensure they are not predictable. However, a relatively small number of locations have been visited many times making their deployment more predictable in these places. The allocation of MSCs across the time of day, day of week and across regions is prioritised based on crash history but the frequency of location visits does not correspond with the crash risk for each location.

There is evidence of a reduction in fatal and serious crashes at the 30 best-performing MSC locations. However, there is limited evidence that the current MSC program in NSW has led to a behavioural change in drivers by creating a general network deterrence. While the overall reduction in serious injuries on roads has continued, fatalities have started to climb again. Compliance with speed limits has improved at the sites and locations that MSCs operate, but the results of overall network speed surveys vary, with recent improvements in some speed zones but not others.
There is no supporting justification for the number of hours of operation for the program. The rate of MSC enforcement (hours per capita) in NSW is less than Queensland and Victoria. The government decision to use multiple warning signs has made it harder to identify and maintain suitable MSC locations, and impeded their use for enforcement in both traffic directions and in school zones. 

Appendix one - Response from agency

Appendix two - About the audit

Appendix three - Performance auditing

 

Parliamentary reference - Report number #308 - released 18 October 2018

Published

Actions for Regional Assistance Programs

Regional Assistance Programs

Premier and Cabinet
Planning
Transport
Compliance
Infrastructure
Management and administration
Project management

Infrastructure NSW effectively manages how grant applications for regional assistance programs are assessed and recommended for funding. Its contract management processes are also effective. However, we are unable to conclude whether the objectives of these programs have been achieved as the relevant agencies have not yet measured their benefits, according to a report released today by the Auditor-General for New South Wales, Margaret Crawford. 

In 2011, the NSW Government established Restart NSW to fund new infrastructure with the proceeds from the sale and lease of government assets. From 2011 to 2017, the NSW Government allocated $1.7 billion from the fund for infrastructure in regional areas, with an additional commitment of $1.3 billion to be allocated by 2021. The NSW Government allocates these funds through regional assistance programs such as Resources for Regions and Fixing Country Roads. NSW councils are the primary recipients of funding provided under these programs.

The NSW Government announced the Resources for Regions program in 2012 with the aim of addressing infrastructure constraints in mining affected communities. Infrastructure NSW administers the program, with support from the Department of Premier and Cabinet.

The NSW Government announced the Fixing Country Roads program in 2014 with the aim of building more efficient road freight networks. Transport for NSW and Infrastructure NSW jointly administer this program, which funds local councils to deliver projects that help connect local and regional roads to state highways and freight hubs.

This audit assessed whether these two programs (Resources for Regions and Fixing Country Roads) were being effectively managed and achieved their objectives. In making this assessment, we answered the following questions:

  • How well are the relevant agencies managing the assessment and recommendation process?
  • How do the relevant agencies ensure that funded projects are being delivered?
  • Do the funded projects meet program and project objectives?

The audit focussed on four rounds of Resources for Regions funding between 2013–14 to 2015–16, as well as the first two rounds of Fixing Country Roads funding in 2014–15 and 2015–16.

Conclusion
Infrastructure NSW effectively manages how grant applications are assessed and recommended for funding. Infrastructure NSW’s contract management processes are also effective. However, we are unable to conclude on whether program objectives are being achieved as Infrastructure NSW has not yet measured program benefits.
While Infrastructure NSW and Transport for NSW managed the assessment processes effectively overall, they have not fully maintained all required documentation, such as conflict of interest registers. Keeping accurate records is important to support transparency and accountability to the public about funding allocation. The relevant agencies have taken steps to address this in the current funding rounds for both programs.
For both programs assessed, the relevant agencies have developed good strategies over time to support councils through the application process. These strategies include workshops, briefings and feedback for unsuccessful applicants. Transport for NSW and the Department of Premier and Cabinet have implemented effective tools to assist applicants in demonstrating the economic impact of their projects.
Infrastructure NSW is effective in identifying projects that are 'at‑risk' and assists in bringing them back on track. Infrastructure NSW has a risk‑based methodology to verify payment claims, which includes elements of good practice in grants administration. For example, it requires grant recipients to provide photos and engages Public Works Advisory to review progress claims and visit project sites.
Infrastructure NSW collects project completion reports for all Resources for Regions and Fixing Country Roads funded projects. Infrastructure NSW intends to assess benefits for both programs once each project in a funding round is completed. To date, no funding round has been completed. As a result, no benefits assessment has been done for any completed project funded in either program.
 

The project selection criteria are consistent with the program objectives set by the NSW Government, and the RIAP applied the criteria consistently. Probity and record keeping practices did not fully comply with the probity plans.

The assessment methodology designed by Infrastructure NSW is consistent with2 the program objectives and criteria. In the rounds that we reviewed, all funded projects met the assessment criteria.

Infrastructure NSW developed probity plans for both programs which provided guidance on the record keeping required to maintain an audit trail, including the use of conflict of interest registers. Infrastructure NSW and Transport for NSW did not fully comply with these requirements. The relevant agencies have taken steps to address this in the current funding rounds for both programs.

NSW Procurement Board Directions require agencies to ensure that they do not engage a probity advisor that is engaged elsewhere in the agency. Infrastructure NSW has not fully complied with this requirement. A conflict of interest arose when Infrastructure NSW engaged the same consultancy to act as its internal auditor and probity advisor.

While these infringements of probity arrangements are unlikely to have had a major impact on the assessment process, they weaken the transparency and accountability of the process.

Some councils have identified resourcing and capability issues which impact on their ability to participate in the application process. For both programs, the relevant agencies conducted briefings and webinars with applicants to provide advice on the objectives of the programs and how to improve the quality of their applications. Additionally, Transport for NSW and the Department of Premier and Cabinet have developed tools to assist councils to demonstrate the economic impact of their applications.

The relevant agencies provided feedback on unsuccessful applications to councils. Councils reported that the quality of this feedback has improved over time.

Recommendations

  1. By June 2018, Infrastructure NSW should:
    • ensure probity reports address whether all elements of the probity plan have been effectively implemented.
  1. By June 2018, Infrastructure NSW and Transport for NSW should:
    • maintain and store all documentation regarding assessment and probity matters according to the State Records Act 1998, the NSW Standard on Records Management and the relevant probity plans

Infrastructure NSW is responsible for overseeing and monitoring projects funded under Resources for Regions and Fixing Country Roads. Infrastructure NSW effectively manages projects to keep them on track, however it could do more to assure itself that all recipients have complied with funding deeds. Benefits and outcomes should also start to be measured and reported as soon as practicable after projects are completed to inform assessment of future projects.

Infrastructure NSW identifies projects experiencing unreasonable delays or higher than expected expenses as 'at‑risk'. After Infrastructure NSW identifies a project as 'at‑risk', it puts in place processes to resolve issues to bring them back on track. Infrastructure NSW, working with Public Works Advisory regional offices, employs a risk‑based approach to validate payment claims, however this process should be strengthened. Infrastructure NSW would get better assurance by also conducting annual audits of compliance with the funding deed for a random sample of projects.

Infrastructure NSW collects project completion reports for all Resources for Regions and Fixing Country Roads funded projects. It applies the Infrastructure Investor Assurance Framework to Resources for Regions and Fixing Country Roads at a program level. This means that each round of funding (under both programs) is treated as a distinct program for the purposes of benefits realisation. It plans to assess whether benefits have been realised once each project in a funding round is completed. As a result, no benefits realisation assessment has been done for any project funded under either Resources for Regions or Fixing Country Roads. Without project‑level benefits realisation, future decisions are not informed by the lessons from previous investments.

Recommendations

  1. By December 2018, Infrastructure NSW should:
    • conduct annual audits of compliance with the funding deed for a random sample of projects funded under Resources for Regions and Fixing Country Roads
    • publish the circumstances under which unspent funds can be allocated to changes in project scope
    • measure benefits delivered by projects that were completed before December 2017
    • implement an annual process to measure benefits for projects completed after December 2017
  1. By December 2018, Transport for NSW and Infrastructure NSW should:
    • incorporate a benefits realisation framework as part of the detailed application.