Actions for CBD South East Sydney Light Rail: follow-up performance audit

CBD South East Sydney Light Rail: follow-up performance audit

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk
Service delivery

This is a follow-up to the Auditor-General's November 2016 report on the CBD South East Sydney Light Rail project. This follow-up report assessed whether Transport for NSW has updated and consolidated information about project costs and benefits.

The audit found that Transport for NSW has not consistently and accurately updated project costs, limiting the transparency of reporting to the public.

The Auditor-General reports that the total cost of the project will exceed $3.1 billion, which is above the revised cost of $2.9 billion published in November 2019. $153.84 million of additional costs are due to omitted costs for early enabling works, the small business assistance package and financing costs attributable to project delays.

The report makes four recommendations to Transport for NSW to publicly report on the final project cost, the updated expected project benefits, the benefits achieved in the first year of operations and the average weekly journey times.

Read full report (PDF)

The CBD and South East Light Rail is a 12 km light rail network for Sydney. It extends from Circular Quay along George Street to Central Station, through Surry Hills to Moore Park, then to Kensington and Kingsford via Anzac Parade and Randwick via Alison Road and High Street.

Transport for NSW (TfNSW) is responsible for planning, procuring and delivering the Central Business District and South East Light Rail (CSELR) project. In December 2014, TfNSW entered into a public private partnership with ALTRAC Light Rail as the operating company (OpCo) responsible for delivering, operating and maintaining the CSELR. OpCo engaged Alstom and Acciona, who together form its Design and Construct Contractor (D&C).

On 14 December 2019, passenger services started on the line between Circular Quay and Randwick. Passenger services on the line between Circular Quay and Kingsford commenced on 3 April 2020.

In November 2016, the Auditor-General published a performance audit report on the CSELR project. The audit found that TfNSW would deliver the CSELR at a higher cost with lower benefits than in the approved business case, and recommended that TfNSW update and consolidate information about project costs and benefits and ensure the information is readily accessible to the public.

In November 2018, the Public Accounts Committee (PAC) examined TfNSW's actions taken in response to our 2016 performance audit report on the CSELR project. The PAC recommended that the Auditor-General consider undertaking a follow-up audit on the CSELR project. The purpose of this follow-up performance audit is to assess whether TfNSW has effectively updated and consolidated information about project costs and benefits for the CSELR project.

Conclusion

Transport for NSW has not consistently and accurately updated CSLER project costs, limiting the transparency of reporting to the public. In line with the NSW Government Benefits Realisation Management Framework, TfNSW intends to measure benefits after the project is completed and has not updated the expected project benefits since April 2015.

Between February 2015 and December 2019, Transport for NSW (TfNSW) regularly updated capital expenditure costs for the CSELR in internal monthly financial performance and risk reports. These reports did not include all the costs incurred by TfNSW to manage and commission the CSELR project.

Omitted costs of $153.84 million for early enabling works, the small business assistance package and financing costs attributable to project delays will bring the current estimated total cost of the CSELR project to $3.147 billion.

From February 2015, TfNSW did not regularly provide the financial performance and risk reports to key CSELR project governance bodies. TfNSW publishes information on project costs and benefits on the Sydney Light Rail website. However, the information on project costs has not always been accurate or current.

TfNSW is working with OpCo partners to deliver the expected journey time benefits. A key benefit defined in the business plan was that bus services would be reduced owing to transfer of demand to the light rail - entailing a saving. However, TfNSW reports that the full expected benefit of changes to bus services will not be realised due to bus patronage increasing above forecasted levels.

Appendix one – Response from agency

Appendix two – Governance and reporting arrangements for the CSELR

Appendix three – 2018 CSELR governance changes

Appendix four – About the audit

Appendix five – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #335 - released 11 June 2020

Published

Actions for Train station crowding

Train station crowding

Transport
Management and administration
Risk
Service delivery
Workforce and capability

This report focuses on how Transport for NSW and Sydney Trains manage crowding at selected metropolitan train stations.

The audit found that while Sydney Trains has identified platform crowding as a key strategic risk, it does not have an overarching strategy to manage crowding in the short to medium term. Sydney Trains 'do not have sufficient oversight to know if crowding is being effectively managed’, the Auditor-General said.

Sydney Trains' operational response to crowding involves restricting customer access to platforms or station entries before crowding reaches unsafe levels or when it impacts on-time running. Assuming rail patronage increases, it is likely that Sydney Trains will restrict more customers from accessing platforms or station entries, causing customer delay. ‘Restricting customer access to platforms or station entries is not a sustainable approach to manage station crowding’, said the Auditor-General.

The Auditor-General made seven recommendations to improve Transport for NSW and Sydney Trains' management of station crowding. Transport for NSW have accepted these recommendations on behalf of the Transport cluster.

Public transport patronage has been impacted by COVID-19. This audit was conducted before these impacts occurred.

Read full report (PDF)

Sydney Trains patronage has increased by close to 34 per cent over the last five years, and Transport for NSW (TfNSW) expects the growth in patronage to continue over the next 30 years. As patronage increases there are more passengers entering and exiting stations, moving within stations to change services, and waiting on platforms. As a result, some Sydney metropolitan train stations are becoming increasingly crowded.

There are three main causes of station crowding:

  • patronage growth exceeding the current capacity limits of the rail network
  • service disruptions
  • special events.

Crowds can inhibit movement, cause discomfort and can lead to increased health and safety risks to customers. In the context of a train service, unmanaged crowds can affect service operation as trains spend longer at platforms waiting for customers to alight and board services which can cause service delays. Crowding can also prevent customers from accessing services.

Our 2017 performance audit, ‘Passenger Rail Punctuality’, found that rail agencies would find it hard to maintain train punctuality after 2019 unless they significantly increased the capacity of the network to carry trains and people. TfNSW and Sydney Trains have plans to improve the network to move more passengers. These plans are set out in strategies such as More Trains, More Services and in the continued implementation of new infrastructure such as the Sydney Metro. Since 2017, TfNSW and Sydney Trains have introduced 1,500 more weekly services to increase capacity. Additional network capacity improvements are in progress for delivery from 2022 onwards.

In the meantime, TfNSW and Sydney Trains need to use other ways of managing crowding at train stations until increased capacity comes on line.

This audit examined how effectively TfNSW and Sydney Trains are managing crowding at selected metropolitan train stations in the short and medium term. In doing so, the audit examined how TfNSW and Sydney Trains know whether there is a crowding problem at stations and how they manage that crowding.

TfNSW is the lead agency for transport in NSW. TfNSW is responsible for setting the standard working timetable that Sydney Trains must implement. Sydney Trains is responsible for operating and maintaining the Sydney metropolitan heavy rail passenger service. This includes operating, staffing and maintaining most metropolitan stations. Sydney Trains’ overall responsibility is to run a safe rail network to timetable.

Conclusion

Sydney Trains has identified platform crowding as a key strategic risk, but does not have an overarching strategy to manage crowding in the short to medium term. TfNSW and Sydney Trains devolve responsibility for managing crowding at stations to Customer Area Managers, but do not have sufficient oversight to know if crowding is being effectively managed. TfNSW is delivering a program to influence demand for transport in key precincts but the effectiveness of this program and its impact on station crowding is unclear as Transport for NSW has not evaluated the outcomes of the program.

TfNSW and Sydney Trains do not directly measure or collect data on station crowding. Data and observation on dwell time, which is the time a train waits at a platform for customers to get on and off trains, inform the development of operational approaches to manage crowding at stations. Sydney Trains has KPIs on reliability, punctuality and customer experience and use these to indirectly assess the impact of station crowding. TfNSW and Sydney Trains only formally assess station crowding as part of planning for major projects, developments or events.

Sydney Trains devolve responsibility for crowd management to Customer Area Managers, who rely on frontline Sydney Trains staff to understand how crowding affects individual stations. Station staff at identified key metropolitan train stations have developed customer management plans (also known as crowd management plans). However, Sydney Trains does not have policies to support the creation, monitoring and evaluation of these plans and does not systematically collect data on when station staff activate crowding interventions under these plans.

Sydney Trains stated focus is on providing a safe and reliable rail service. As such, management of station crowding is a by-product of its strategies to manage customer safety and ensure on-time running of services. Sydney Trains' operational response to crowding involves restricting customer access to platforms or stations before crowding reaches unsafe levels, or when it impacts on-time running. As rail patronage increases, it is likely that Sydney Trains will need to increase its use of interventions to manage crowding. As Sydney Trains restrict more customers from accessing platforms or station entries, it is likely these customers will experience delays caused by these interventions.

Since 2015, TfNSW has been delivering the 'Travel Choices' program which aims to influence customer behaviour and to manage the demand for public transport services in key precincts. TfNSW is unable to provide data demonstrating the overall effectiveness of this program and the impact the program has on distributing public transport usage out of peak AM and PM times. TfNSW and Sydney Trains continue to explore initiatives to specifically address crowd management.

Conclusion

TfNSW and Sydney Trains do not directly measure or collect data on station crowding. There are no key performance indicators directly related to station crowding. Sydney Trains uses performance indicators on reliability, punctuality and customer experience to indirectly assess the impact of station crowding. Sydney Trains does not have a routine process for identifying whether crowding contributed to minor safety incidents. TfNSW and Sydney Trains formally assess station crowding as part of planning for major projects, developments or events.

 

Conclusion

Sydney Trains has identified platform crowding as a strategic risk but does not have an overarching strategy to manage station crowding. Sydney Trains' stated focus is on providing a safe and reliable rail service. As such, management of station crowding is a by-product of its strategies to manage customer safety and ensure on-time running of services.

Sydney Trains devolve responsibility for managing crowding at stations to Customer Area Managers but does not have sufficient oversight to know that station crowding is effectively managed. Sydney Trains does not have policies to support the creation, monitoring or evaluation of crowd management plans at key metropolitan train stations. The use of crowding interventions is likely to increase due to increasing patronage, causing more customers to experience delays directly caused by these activities.

TfNSW and Sydney Trains have developed interventions to influence customer behaviour and to manage the demand for public transport services but are yet to evaluate these interventions. As such, their impact on managing station crowding is unclear.

Appendix one – Response from agency

Appendix two – Sydney rail network

Appendix three – Rail services contract

Appendix four – Crowding pedestrian modelling

Appendix five – Airport Link stations case study

Appendix six – About the audit

Appendix seven – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #333 - released 30 April 2020

 

Published

Actions for Local Schools, Local Decisions: needs-based equity funding

Local Schools, Local Decisions: needs-based equity funding

Education
Internal controls and governance
Management and administration
Service delivery

The Auditor-General for New South Wales, Margaret Crawford, released a report today examining the Department of Education’s (the department’s) support and oversight of school planning and use of needs-based funding under the Local Schools, Local Decisions reform.

The report found the department has not had adequate oversight of how schools are using needs-based funding to improve student outcomes since it was introduced in 2014.

The department had not set measures or targets for needs-based equity funding. It had also not been clear enough in how it expected schools to report on the outcomes of additional funding. This means it has not been able to effectively demonstrate the impact of funding at a school, or state-wide level.

To assist with the transition to greater local decision-making, the department provided schools with guidance materials, additional resources and systems support. However, guidance material was not clear enough on the purpose of funding, school budgeting systems were not fit-for-purpose when initially introduced, and support for schools was spread across different areas of the department.

The department has recently increased executive oversight of progress to improve educational outcomes for Aboriginal students and students from a low socio-economic background. It has also developed a consistent set of school-level targets to be implemented from 2020. This may help the department more reliably monitor progress in lifting outcomes for students with additional learning needs.

The report makes eight recommendations aimed at clarifying requirements of schools, better coordinating support and strengthening oversight of the use of needs-based equity funding.

Read full report (PDF)

The Local Schools, Local Decisions reform was launched in 2012 to give public schools more authority to make local decisions about how best to meet the needs of their students. A major element of the reform was the introduction of a new needs-based school funding model. Core elements of the model address staffing and operational requirements, while needs-based elements reflect the characteristics of schools and students within them. This includes equity funding designed to support students with additional needs. The four categories of equity funding are:

  • socio-economic background
  • Aboriginal background
  • English language proficiency
  • low-level adjustment for disability. 

Around $900 million in equity funding was allocated in 2019. School principals decide how to use these funds and account for them through their school annual reports. The Department of Education (the department) supports schools in making these choices with tools and systems, guidelines, and good practice examples.

The objective of this audit was to assess the department's support and oversight of school planning and use of needs-based funding under the Local Schools, Local Decisions reform. To address this objective, the audit examined whether:

  • effective accountability arrangements have been established
  • effective support is provided to schools.  

Conclusion

The department has not had adequate oversight of how schools are using needs-based equity funding to improve student outcomes since it was introduced in 2014. While it provides guidance and resources, it has not set measures or targets to describe the outcomes expected of this funding, or explicit requirements for schools to report outcomes from how these funds were used. Consequently, there is no effective mechanism to capture the impact of funding at a school, or state-wide level. The department has recently developed a consistent set of school-level targets to be implemented from 2020. This may help it to better hold schools accountable for progress towards its strategic goal of reducing the impact of disadvantage.

A significant amount of extra funding has been provided to schools over recent years in recognition of the additional learning needs of certain groups of students facing disadvantage. Under the Local Schools, Local Decisions reform, schools were given the ability to make decisions about how best to use the equity funding in combination with their overall school resources to meet their students’ needs. However, multiple guidelines provided to schools contain inconsistent advice on how the community should be consulted, how funding could be used, and how impact should be reported. Because of this, it is not clear how schools have used equity funding for the benefit of identified groups. School annual reports we reviewed did not fully account for the equity funding received, nor adequately describe the impact of funding on student outcomes.

To help in the transition to greater local decision-making, the department provided extra support by; establishing peer support for new principals, increasing the number of directors, developing data analysis and financial planning systems, targeted training and showcasing good practice. Multiple roles and areas of the department provide advice to schools in similar areas and this support could be better co-ordinated.

Financial planning systems designed to help schools budget for equity and other funding sources were not fit-for-purpose when originally introduced. Schools reported a lack of trust in their budget figures and so were not fully spending their allocated funding. Since then, the department developed and improved a budgeting tool in consultation with stakeholder and user groups. It provided extra funding for administrative support and one-to-one training to help schools develop their capabilities. Despite this, schools we spoke to reported they were not yet fully confident in using the system and needed ongoing training and support. 

Appendix one – Response from agency

Appendix two – About the audit

Appendix three – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #331 - released 8 April 2020.

Published

Actions for Education 2018

Education 2018

Education
Asset valuation
Financial reporting
Information technology
Infrastructure
Service delivery
Shared services and collaboration
Workforce and capability

The Auditor-General for New South Wales, Margaret Crawford, released her report today on the results of the financial audits of agencies in the Education cluster. The report focuses on key observations and findings from the most recent financial audits of these agencies. 'I am pleased to report that unqualified audit opinions were issued on the financial statements of both agencies in the Education cluster', the Auditor-General said. Statements were submitted and audited within statutory deadlines.

This report analyses the results of our audits of financial statements of the Education cluster for the year ended 30 June 2018. The table below summarises our key observations.

This report provides parliament and other users of the Education cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations
  • service delivery.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Education cluster for 2017–18.

Observation Conclusions and recommendations
2.1 Quality of financial reporting
Unqualified audit opinions were issued on the financial statements of both cluster agencies. Sufficient audit evidence was obtained to conclude the financial statements were free of material misstatement.
2.2 Timeliness of financial reporting
Both cluster agencies met the statutory deadlines for completing early close procedures and submitting financial statements. Early close procedures continue to facilitate the timely preparation of cluster agencies’ financial statements and completion of audits, but scope exists to improve outcomes by resolving issues and supplying supporting documentation earlier.
2.3 Key issues from financial audits
Inconsistencies in the Department’s annual leave and long service leave data, identified over the past three audits, remain unresolved. This issue impacts the Department’s liability estimates for annual leave and long service leave, including associated on-costs. It also on-flows to the Crown Entity, which assumes the Department's liability for long service leave. Recommendation: The Department should confirm leave data and review assumptions following deployment of the new HR/Payroll system to better estimate the liability for employee benefits and the amount to be assumed by the Crown Entity.
2.4 Key financial information
Cluster agencies recorded net deficits in 2017–18.

The Department recorded a net deficit of $30.7 million in 2017–18 against a budgeted surplus of $122 million.

The NSW Education Standards Authority recorded a net deficit of $4.1 million against a budgeted deficit of $4.7 million.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from:

  • our financial statement audits of agencies in the Education cluster for 2018
  • the areas of focus identified in the Audit Office work program.

The Audit Office Annual Work Program provides a summary of all audits to be conducted within the proposed time period as well as detailed information on the areas of focus for each of the NSW Government clusters.

Observation Conclusions and recommendations
3.1  Internal controls
Twenty internal control deficiencies were identified during our audits of cluster agencies. We assessed one as a high risk finding.  
Eight internal control weaknesses were repeat issues from previous financial audits that had not been fully addressed by management. Recommendation: Management should prioritise and action recommendations to address internal control weaknesses.
3.2 Information technology
Delivery of the Learning Management and Business Reform (LMBR) program is complete.

The LMBR program has been a major project for the Department since it was established in 2006.

A staged approach was adopted for implementing the Department’s new HR/Payroll system to manage the risks associated with this large-scale roll-out.

3.3 Valuation of the Department’s land and buildings
The Department completed a revaluation of land and building assets during 2017–18.

A market approach was used to revalue the Department’s land, resulting in a revaluation increment of $2.3 billion.

A current replacement cost approach was used to revalue the Department’s school buildings, resulting in an increment of $6.2 billion.

3.4 Maintenance of school facilities
The Department regularly assesses the condition of school buildings and uses Life Cycle Costing to predict maintenance and capital renewal, and to prioritise maintenance activities. The Life Cycle Costing assessment conducted by the Department in 2017–18 rated 70 per cent of school buildings as being in either as new or good condition. No school buildings were rated as being in end-of-life condition.
3.4 School asset delivery
The Department’s School Assets Strategic Plan is designed to ensure that there are sufficient fit-for-purpose places for students up to 2031. The Department created a new division, School Infrastructure NSW, to oversee the planning, supply and maintenance of schools and implement major school infrastructure projects.

This chapter provides service delivery outcomes for the Education cluster for 2017–18. It provides important contextual information about the cluster's operation, but the data on achievement of these outcomes is not audited. The Audit Office does not have a specific mandate to audit performance information.

Published

Actions for Transport 2018

Transport 2018

Transport
Asset valuation
Compliance
Financial reporting
Infrastructure
Management and administration
Procurement
Risk
Service delivery
Workforce and capability

The Auditor-General for New South Wales, Margaret Crawford released her report today on key observations and findings from the 30 June 2018 financial statement audits of agencies in the Transport cluster. Unqualified audit opinions were issued for all agencies' financial statements. However, assessing the fair value of the broad range of transport related assets creates challenges.

This report analyses the results of our audits of financial statements of the Transport cluster for the year ended 30 June 2018. The table below summarises our key observations.

This report provides Parliament and other users of the Transport cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Transport cluster for 2018.

Observation Conclusions and recommendations
2.1 Quality of financial reporting
Unqualified audit opinions were issued for all agencies' financial statements Sufficient audit evidence was obtained to conclude the financial statements were free of material misstatement.
2.2 Key accounting issues
Valuation of assets continues to create challenges. Although agencies complied with the requirements of the accounting standards and Treasury policies on valuations, we identified some opportunities for improvements at RMS.

RMS incorporated data from its asset condition assessments for the first time in the valuation methodology which improved the valuation outcome. Overall, we were satisfied with the valuation methodology and key assumptions, but we noted some deficiencies in the asset data in relation to asset component unit rates and old condition data for some components of assets. 

Also, a bypass and tunnel were incorrectly excluded from RMS records and valuation process since 2013. This resulted in an increase for these assets’ value by $133 million.

The valuation inputs for Wetlands and Moorings were revised this year to better reflect the assets' characteristics resulting in a $98.0 million increase.

2.3 Timeliness of financial reporting
Residual Transport Corporation did not submit its financial statements by the statutory reporting deadline. Residual Transport Corporation remained a dormant entity with no transactions for the year ended 30 June 2018.
With the exception of Residual Transport Corporation, all agencies completed early close procedures and submitted financial statements within statutory timeframes. Early close procedures allow financial reporting issues and risks to be addressed early in the reporting and audit process.
2.4 Financial sustainability
NSW Trains and the Chief Investigator of the Office of Transport Safety Investigations reported negative net assets of $75.7 million and $89,000 respectively at 30 June 2018.  NSW Trains and the Chief Investigator of the Office of Transport Safety Investigations continue to require letters of financial support to confirm their ability to pay liabilities as they fall due. 
2.5 Passenger revenue and patronage
Transport agencies revenue growth increased at a higher rate than patronage. Public transport passenger revenue increased by $114 million (8.3 per cent) in 2017–18, and patronage increased by 37.1 million (5.1 per cent) across all modes of transport based on data provided by TfNSW. 
Negative balance Opal Cards resulted in $3.8 million in revenue not collected in 2017–18 and $7.8 million since the introduction of Opal. A total of 1.1 million Opal cards issued since its introduction have negative balances. Transport for NSW advised it is liaising with the ticketing vendor to implement system changes and are investigating other ways to reduce the occurrences.
2.6 Cost recovery from public transport users
Overall cost recovery from users has decreased. Overall cost recovery from public transport users (on rail and bus services by STA) decreased from 23.2 per cent to 22.4 per cent between 2016–17 and 2017–18. The main reason for the decrease is due to expenditure increasing at a faster rate than revenue in 2017–18.


 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from:

  • our financial statement audits of agencies in the Transport cluster for 2018
  • the areas of focus identified in the Audit Office annual work program.

The Audit Office Annual Work Program provides a summary of all audits to be conducted within the proposed time period as well as detailed information on the areas of focus for each of the NSW Government clusters. 

Observation Conclusions and recommendations
3.1 Internal controls 
There was an increase in findings on internal controls across the Transport cluster. Key themes related to information technology, employee leave entitlements and asset management. Eighteen per cent of all issues were repeat issues.
3.2 Audit Office Annual work program
The Transport cluster wrote-off over $200 million of assets which were replaced by new assets or technology.

Majority of this write-off was recognised by RMS, with $199 million relating to the write-off of existing assets which have been replaced during the year. 

RailCorp is expected to convert to TAHE from 1 July 2019. Several working groups are considering different aspects of the TAHE transition including its status as a for-profit Public Trading Enterprise and which assets to transfer to TAHE. We will continue to monitor developments on TAHE for any impact to the financial statements.
RMS' estimated maintenance backlog at 30 June 2018 of $3.4 billion is lower than last year. Sydney Trains' estimated maintenance backlog at 30 June 2018 increased by 20.6 per cent to $434 million. TfNSW does not quantify its backlog maintenance. TfNSW advised it is liaising with Infrastructure NSW to develop a consistent definition of maintenance backlog across all transport service providers. 
Not all agencies monitor unplanned maintenance across the Transport cluster. Unplanned maintenance can be more expensive than planned maintenance. TfNSW should develop a consistent approach to define, monitor and track unplanned maintenance across the cluster.

This chapter outlines certain service delivery outcomes for 2017–18. The data on activity levels and performance is provided by Cluster agencies. The Audit Office does not have a specific mandate to audit performance information. Accordingly, the information in this chapter is unaudited. 

We report this information on service delivery to provide additional context to understand the operations of the Transport cluster and to collate and present service information for different modes of transport in one report. 

In our recent performance audit, Progress and measurement of Premier's Priorities, we identified 12 limitations of performance measurement and performance data. We recommended that the Department of Premier and Cabinet ensure that processes to check and verify data are in place for all agency data sources.

Published

Actions for Mobile speed cameras

Mobile speed cameras

Transport
Compliance
Financial reporting
Information technology
Internal controls and governance
Management and administration
Regulation
Service delivery

Key aspects of the state’s mobile speed camera program need to be improved to maximise road safety benefits, according to a report released today by the Auditor-General for New South Wales, Margaret Crawford. Mobile speed cameras are deployed in a limited number of locations with a small number of these being used frequently. This, along with decisions to limit the hours that mobile speed cameras operate, and to use multiple warning signs, have reduced the broad deterrence of speeding across the general network - the main policy objective of the mobile speed camera program.

The primary goal of speed cameras is to reduce speeding and make the roads safer. Our 2011 performance audit on speed cameras found that, in general, speed cameras change driver behaviour and have a positive impact on road safety.

Transport for NSW published the NSW Speed Camera Strategy in June 2012 in response to our audit. According to the Strategy, the main purpose of mobile speed cameras is to reduce speeding across the road network by providing a general deterrence through anywhere, anytime enforcement and by creating a perceived risk of detection across the road network. Fixed and red-light speed cameras aim to reduce speeding at specific locations.

Roads and Maritime Services and Transport for NSW deploy mobile speed cameras (MSCs) in consultation with NSW Police. The cameras are operated by contractors authorised by Roads and Maritime Services. MSC locations are stretches of road that can be more than 20 kilometres long. MSC sites are specific places within these locations that meet the requirements for a MSC vehicle to be able to operate there.

This audit assessed whether the mobile speed camera program is effectively managed to maximise road safety benefits across the NSW road network.

Conclusion

The mobile speed camera program requires improvements to key aspects of its management to maximise road safety benefits. While camera locations have been selected based on crash history, the limited number of locations restricts network coverage. It also makes enforcement more predictable, reducing the ability to provide a general deterrence. Implementation of the program has been consistent with government decisions to limit its hours of operation and use multiple warning signs. These factors limit the ability of the mobile speed camera program to effectively deliver a broad general network deterrence from speeding.

Many locations are needed to enable network-wide coverage and ensure MSC sessions are randomised and not predictable. However, there are insufficient locations available to operate MSCs that meet strict criteria for crash history, operator safety, signage and technical requirements. MSC performance would be improved if there were more locations.

A scheduling system is meant to randomise MSC location visits to ensure they are not predictable. However, a relatively small number of locations have been visited many times making their deployment more predictable in these places. The allocation of MSCs across the time of day, day of week and across regions is prioritised based on crash history but the frequency of location visits does not correspond with the crash risk for each location.

There is evidence of a reduction in fatal and serious crashes at the 30 best-performing MSC locations. However, there is limited evidence that the current MSC program in NSW has led to a behavioural change in drivers by creating a general network deterrence. While the overall reduction in serious injuries on roads has continued, fatalities have started to climb again. Compliance with speed limits has improved at the sites and locations that MSCs operate, but the results of overall network speed surveys vary, with recent improvements in some speed zones but not others.
There is no supporting justification for the number of hours of operation for the program. The rate of MSC enforcement (hours per capita) in NSW is less than Queensland and Victoria. The government decision to use multiple warning signs has made it harder to identify and maintain suitable MSC locations, and impeded their use for enforcement in both traffic directions and in school zones. 

Appendix one - Response from agency

Appendix two - About the audit

Appendix three - Performance auditing

 

Parliamentary reference - Report number #308 - released 18 October 2018

Published

Actions for Improving road safety: Young drivers

Improving road safety: Young drivers

Transport
Finance
Project management
Regulation
Service delivery

The audit concluded that the RTA’s licence testing and regulation has been generally effective in ensuring the safety of young drivers. There has been a significant reduction in crash and fatality rates involving young drivers over the last decade, more so than for drivers 26 years and older. This has coincided with the introduction by the RTA of an enhanced GLS. International and national research has demonstrated graduated licensing systems to be effective in reducing crashes and saving lives. Despite these improvements, young drivers are more likely to be involved in fatal crashes than other drivers.

 

Parliamentary reference - Report number #217 - released 19 October 2011

Published

Actions for Government expenditure and transport planning in relation to implementing Barangaroo

Government expenditure and transport planning in relation to implementing Barangaroo

Industry
Treasury
Transport
Compliance
Internal controls and governance
Management and administration
Project management
Service delivery

Barangaroo is an ambitious and significant development on Government-owned Sydney Harbour foreshore. Construction on the 22 hectare CBD site is expected to take 12 years to 2023. Developer contributions to Government of $1 billion are to provide for public domain and other Government development costs, including a six hectare Headland Park. When completed the precinct is to service an anticipated 26,000 workers and residents and up to 33,000 visitors a day. The Auditor-General concluded that while there was extensive transport planning and extensive documentation supporting Government financial forecasts, considerable risks remain for the implementation of the Barangaroo project. 

 

Parliamentary reference - Report number #214 - released 15 June 2011

Published

Actions for Signal failures on the metropolitan rail network

Signal failures on the metropolitan rail network

Transport
Information technology
Infrastructure
Internal controls and governance
Project management
Risk
Service delivery

Between 2004 and 2006, the number of signalling failures, signalling downtime and the number of trains delayed as a result of signal failures all fell. RailCorp’s on-time running performance improved over the same period. The fall in failures is a clear indication of improved performance. Changes in the definition of on-time and to the timetable during 2005 and 2006 however make it difficult to determine whether improvements in response downtime and signalling delays are due to a true performance improvement. To build upon this strong base, RailCorp needs to determine with more confidence the number and duration of signalling failures the network can tolerate without impacting on service levels.

 

Parliamentary reference - Report number #170 - released 15 August 2007

Published

Actions for Connecting with public transport

Connecting with public transport

Transport
Information technology
Infrastructure
Internal controls and governance
Management and administration
Project management
Service delivery
Workforce and capability

We see considerable potential for the Ministry of Transport to plan and manage interchanges more effectively, so as to make better use of our public transport network. We believe that the Ministry now needs to focus more on multi-modal transport planning and interchange performance. It needs to assign responsibility for the coordination and oversight of inter-modal operations to an entity resourced for the purpose. Without this it will continue to be very difficult to identify and address unmet needs, seek and secure stakeholder funding, and monitor and evaluate system performance.

 

Parliamentary reference - Report number #168 - released 6 June 2007