Actions for Albert 'Tibby' Cotter Walkway

Albert 'Tibby' Cotter Walkway

Transport
Internal controls and governance
Procurement
Project management

On 17 September 2015, the Acting Auditor-General of New South Wales, Tony Whitfield, released a report on the Albert ‘Tibby’ Cotter Walkway which crosses over Anzac Parade in Moore Park. The Walkway’s primary function is to cater for event patrons in the precinct. Moore Park is listed on the State Heritage Register and is an open space specifically established to cater for public recreation.
 
Roads and Maritime Services (RMS) delivered the Walkway to an extremely tight timeframe. It was operational for the 2015 Cricket World Cup at the Sydney Cricket Ground as promised by the government. However, the World Cup deadline added substantially to the total cost of the Walkway, which is projected to be $38 million.
 
Transport for NSW and RMS could not provide evidence of a compelling economic or financial argument to support the construction of the Walkway or for the tight deadline. Also, the processes they adopted to provide assurance of the project’s value for money were not adequate.

 

Parliamentary reference - Report number #260 - released 17 September 2015

Published

Actions for Sydney metropolitan bus contracts

Sydney metropolitan bus contracts

Transport
Internal controls and governance
Management and administration
Procurement
Project management
Service delivery

On 9 September 2015, the Acting Auditor-General of New South Wales, Tony Whitfield, released a report on Sydney Metropolitan Bus Service Contracts.
 
All scheduled bus services in the Sydney metropolitan area are provided under contracts with the public and private operators. The contracts allow Transport for NSW (TfNSW) to determine what bus services are provided and to whom. This audit assessed the effectiveness of TfNSW’s design and management of these contracts.
 
Bus services provided under the Sydney Metropolitan Bus Service Contracts have largely been effective and efficient. Operators are mostly meeting their key performance indicators. Customer satisfaction is better than under the previous contracts and improving, patronage is increasing, and the unit costs of providing services are now lower than under the previous contracts. 
 
However, punctuality remains a problem. Private operators are mostly starting their trips on time, but rarely meeting their mid and end-of-trip targets. State Transit Authority’s (STA) punctuality is improving but is worse than private operators, and other areas of performance are generally below private operators.
 
The current situation is a substantial improvement over what we found in our 2010 audit on the previous contracts.

 

Parliamentary reference - Report number #258 - released 9 September 2015

Published

Actions for Identifying productivity in the public sector

Identifying productivity in the public sector

Health
Education
Community Services
Transport
Justice
Treasury
Whole of Government
Internal controls and governance
Management and administration

This report examines selected areas of government activity to see if sufficient information was available to identify and assess changes in productivity. The areas examined were primary and secondary school public education, acute inpatient care in NSW public hospitals, CityRail, the NSW Police Force, and the NSW Local Court.

Productivity is commonly defined as the amount of output per unit of input.

 

Parliamentary reference - Report number #256 - released 16 July 2015

Published

Actions for Implementing performance audit recommendations

Implementing performance audit recommendations

Premier and Cabinet
Treasury
Whole of Government
Health
Education
Community Services
Transport
Justice
Compliance
Internal controls and governance
Management and administration

NSW Government agencies have sound processes for implementing performance audit recommendations in Auditor-General’s Reports to Parliament. There are many cases of good practice. For example, some agencies formed a steering committee and developed a detailed plan to implement recommendations. Another incorporated the implementation of recommendations into both its business plan and the work plans of individual officers who were managing projects. Most agencies also used their Audit and Risk Committees to monitor recommendations.
 
We found some cases where agencies can improve how they coordinate actions to address recommendations. Most agencies were not revisiting these actions to determine whether they remain appropriate.

 

Parliamentary reference - Report number #254 - released 24 June 2015

Published

Actions for Large construction projects

Large construction projects

Treasury
Transport
Health
Industry
Planning
Premier and Cabinet
Whole of Government
Compliance
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management

The independent assurance given to the NSW Government and sponsor agencies on the viability of large capital projects throughout their lifecycle is inadequate. Government policy is regularly not followed and not properly communicated to those responsible for implementing such policy.
 
This audit sought to test the effectiveness of the NSW capital project assurance system - which includes gateway reviews and reporting - but significant levels of non-compliance identified in our case studies prevented this. The NSW Commission of Audit also identified this issue in 2012. Gateway reviews are conducted by independent reviewers at key stages of a project’s life cycle and provide an independent assessment on a project’s readiness to proceed to the next stage.

 

Parliamentary reference - Report number #252 - released 7 May 2015

Published

Actions for Vocational education and training reform

Vocational education and training reform

Education
Industry
Management and administration
Procurement
Project management
Service delivery
Workforce and capability

The Department’s framework for VET reform has the potential to effectively achieve the government’s immediate objectives for the reform, which are associated with meeting its commitments under the National Partnership Agreement for Skills Reform without spending more. We found that the government is addressing VET reform objectives in the following order of priority: no extra cost (budget neutrality), TAFE viability, quality VET, access to VET for regions and equity groups, more contestability, student choice. Overall, we conclude that a more balanced approach, by putting more emphasis on increased contestability and student choice, is more likely to maximise the public value for the government’s investment in VET.

 

Parliamentary reference - Report number #249 - released 29 January 2015

Published

Actions for Security of critical IT infrastructure

Security of critical IT infrastructure

Transport
Planning
Compliance
Information technology
Internal controls and governance
Management and administration
Risk

Roads and Maritime Services and Transport for NSW have deployed many controls to protect traffic management systems but these would have been only partially effective in detecting and preventing incidents and unlikely to support a timely response. There was a potential for unauthorised access to sensitive information and systems that could have disrupted traffic.
 
Until Roads and Maritime Services’ IT disaster recovery site is fully commissioned, a disaster involving the main data centre is likely to lead to higher congestion in the short-term as traffic controllers would be operating on a regional basis without the benefit of the Traffic Management Centre.

 

Parliamentary reference - Report number #248 - released 21 January 2015

Published

Actions for Government office accommodation

Government office accommodation

Treasury
Finance
Asset valuation
Management and administration
Procurement

The Audit Office has undertaken an audit on Government Office Accommodation. The audit examined the cost effectiveness of long-term leasing versus ownership and the housing of agencies involved with the delivery of core government activities.  Core activities are those intrinsically linked to basic and ongoing functions of Government and Parliament.

It recommends that:

  • the Government consider owning office accommodation, as opposed to leasing, for its long-term core needs, subject to a case by case analysis of the relevant financial and nonfinancial factors

  • the Government undertake an analysis of the costs/savings from proposed asset sales of office accommodation in light of the demonstrated need for long-term office accommodation (for core needs) New, Expired and Expiring Leases

  • given the findings of the own versus lease case studies presented in this report, it is recommended that the Government require agencies to undertake, in collaboration with the Department of Public Works and Services (DPWS) a cost/benefit analysis of available accommodation options prior to committing to any proposed major new leases

  • the Government direct the DPWS, in collaboration with all agencies, to negotiate the renewal of all major expired/expiring leases (where continued occupancy is warranted) in order to reduce the financial risk of above-market rent increases and the risk of cancellation of leases (Major leases are defined, for the purposes of these recommendations, to be those over $500,000 rental per annum or a net lettable area over 1,000 square metres) Management of Property Information

  •  in order to improve the integrity of the Government Office Accommodation Database, agencies be required to respond to the annual data request from DPWS by a predetermined date

  • a senior officer within each agency be required to certify to the accuracy of information provided by an agency as input to the database maintained by DPWS

  • DPWS verify, on a sample basis, information provided by agencies as input to the Government Office Accommodation Database Premier’s Memorandum No 97-2

  • the compliance by agencies with Premier’s Memorandum No 97-2 Government Office Accommodation and Property Disposal be established by DPWS.

 

Parliamentary reference - Report number #45 - released 11 December 1997

Published

Actions for Review of Eastern Distributor

Review of Eastern Distributor

Transport
Infrastructure
Procurement
Project management

Following a resolution of the Legislative Council, the Audit Office has undertaken a performance audit of the Eastern Distributor. For a number of reasons, The Audit Office is not in the position to determine “whether the proposed toll and concession period represents the best deal”. In part this is the result of time constraints which do not allow a careful analysis of many toll and concession options. Similarly, the audit does not answer “whether the current proposal represents the best environmental outcome”. But each of these issues (toll and concession and environmental consequences) is discussed in the audit report.

The Audit Office recommends that the Roads and Traffic Authority (RTA), for any further major project of this type, ensures that it establishes a process which allows all decision makers to have a thorough understanding of the reasonableness of the proponents’ offers and their implications for the State and for the public. The Audit Office also recommends that the RTA should at the outset consult with TCorp in respect of each major project put to tender.

 

Parliamentary reference - Report number #42 - released 31 July 1997