Actions for WestConnex: Assurance to the Government

WestConnex: Assurance to the Government

Transport
Treasury
Premier and Cabinet
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk

This audit assesses the assurance provided to the NSW Government for the initial stages of the WestConnex project.

The audit examined the WestConnex project from concept development to the pre-tender phase for Stage 1A – M4 (Parramatta to Homebush Bay). It did not examine the merit of the project or whether it represented value-for-money.

This audit found a number of shortcomings with the governance of the WestConnex project during its early stages and makes recommendations on how to better govern the remainder of the project to minimise the risk of failure.

 

Parliamentary reference - Report number #247 - released 18 December 2014

Published

Actions for Managing Contaminated Sites

Managing Contaminated Sites

Planning
Industry
Environment
Compliance
Internal controls and governance
Management and administration
Project management
Regulation
Risk

NSW Government agencies with large landholdings need to better manage their contaminated sites.

When contaminated sites are reported to the Environmental Protection Authority (EPA) there are long delays in assessing the extent of contamination. The EPA also lacks the management controls to ensure that all significantly contaminated sites are actively monitored and key milestones for remediation are met.

 

Parliamentary reference - Report number #245 - released 10 July 2014

Published

Actions for Environmental impact assessment of major projects in NSW

Environmental impact assessment of major projects in NSW

Environment
Management and administration
Regulation
Service delivery

The Audit Office is of the opinion that the basis for environmental impact assessment of major projects in NSW is sound. The key concept of 'environmental significance' is well defined. The system is closely specified. The Department of Urban Affairs and Planning (DUAP) leads a whole-of-government approach to environmental impact assessment and its assessments are comprehensive. However, the Audit Office considers that there are opportunities for improvement by more actively managing the participants and the performance of the environmental impact assessment system. DUAP needs to strengthen its internal documentation and must ensure the public have greater involvement.

 

Parliamentary reference - Report number #92 - released 28 November 2001

Published

Actions for Controlling and reducing pollution from industry

Controlling and reducing pollution from industry

Planning
Environment
Compliance
Management and administration
Regulation

The regulatory framework introduced under the Protection of the Environment Operations Act 1997, along with other initiatives progressively being implemented by the Environment Protection Authority (EPA), should enhance the overall effectiveness of environment protection in NSW. The Audit Office is of the opinion that the framework is consistent with best practice and once fully implemented, should contribute to the achievement of further improvements in the environmental performance of industry.

However while the legislative framework supports best practice in regulation and enforcement, there are a number of issues which limit the effectiveness of the reforms. Some of the problems, such as the quality of licences and the effectiveness of compliance activities, have been identified by the EPA and may be addressed through recent initiatives.

 

Parliamentary reference - Report number #82 - released 18 April 2001