Refine search Expand filter

Reports

Published

Actions for Environmental impact assessment of major projects in NSW

Environmental impact assessment of major projects in NSW

Environment
Management and administration
Regulation
Service delivery

The Audit Office is of the opinion that the basis for environmental impact assessment of major projects in NSW is sound. The key concept of 'environmental significance' is well defined. The system is closely specified. The Department of Urban Affairs and Planning (DUAP) leads a whole-of-government approach to environmental impact assessment and its assessments are comprehensive. However, the Audit Office considers that there are opportunities for improvement by more actively managing the participants and the performance of the environmental impact assessment system. DUAP needs to strengthen its internal documentation and must ensure the public have greater involvement.

 

Parliamentary reference - Report number #92 - released 28 November 2001

Published

Actions for E-Government readiness assessment guide

E-Government readiness assessment guide

Whole of Government
Information technology
Internal controls and governance
Risk

The purpose of this document is to assist agencies in meeting the challenges of exploiting the benefits and managing the risks which e-government presents. Being 'e-ready' and managing the transition to e-government will not happen by chance. It is difficult and requires a careful and concerted effort. This guide draws from the research assembled in the performance audit, e-government - Use of the Internet and related technologies to improve public sector performance (September 2001). It addresses issues at the agency level, in a self-help guide format.

 

Parliamentary reference - Report number #88 - released 19 September 2001

Published

Actions for Use of the internet and related technologies to improve public sector performance

Use of the internet and related technologies to improve public sector performance

Whole of Government
Cyber security
Information technology
Procurement
Service delivery
Shared services and collaboration
Workforce and capability

Notwithstanding the considerable effort, it is not apparent that the Government's vision can be fully achieved without increased efforts. Based on the current position, to ensure that the Government's vision can be achieved the Audit Office is of the view that the following key issues need to be urgently addressed: 

  • more robust mechanisms are needed to monitor, review and report publicly on progress and benefits

  • a greater emphasis should be placed on central coordination to ensure that agencies act in a more uniform and integrated manner  

  • the achievement of significant reform of business processes will require a substantial strengthening of accountability mechanisms and more comprehensive, rigorous and systematic approaches to e-government project and risk management. 

  • despite an array of guidance material and support provided by central agencies, line agency needs for assistance do not seem to be being met to sufficiently advance matters across the sector at the pace and scope desired

  • the Government’s e-government aspirations and funding are not always effectively harmonised. Agencies typically have limited resources available to trial or experience new technologies, and display an aversion to the associated risks.

 

Parliamentary reference - Report number #87 - released 19 September 2001

Published

Actions for Controlling and reducing pollution from industry

Controlling and reducing pollution from industry

Planning
Environment
Compliance
Management and administration
Regulation

The regulatory framework introduced under the Protection of the Environment Operations Act 1997, along with other initiatives progressively being implemented by the Environment Protection Authority (EPA), should enhance the overall effectiveness of environment protection in NSW. The Audit Office is of the opinion that the framework is consistent with best practice and once fully implemented, should contribute to the achievement of further improvements in the environmental performance of industry.

However while the legislative framework supports best practice in regulation and enforcement, there are a number of issues which limit the effectiveness of the reforms. Some of the problems, such as the quality of licences and the effectiveness of compliance activities, have been identified by the EPA and may be addressed through recent initiatives.

 

Parliamentary reference - Report number #82 - released 18 April 2001

Published

Actions for Ambulance Service of NSW: Readiness to respond

Ambulance Service of NSW: Readiness to respond

Health
Internal controls and governance
Management and administration
Shared services and collaboration
Workforce and capability

This performance audit indicates that the Service has considerable work to do to reach its aspirations of being recognised amongst leading examples of best practice services. The commitment of the Service to serving the community and the professionalism of the Service's officers is not in question. It is, however, apparent that a number of barriers to performance will need to be overcome for the Service to perform as well as it would wish.

 

Parliamentary reference - Report number #80 - released 7 March 2001

Published

Actions for Sale of the TAB

Sale of the TAB

Treasury
Internal controls and governance
Procurement

The Audit Office is of the opinion that:

  • the sale was delivered with reasonable efficiency and effectiveness

  • the sale yielded a satisfactory return to the NSW Government. The possibility for a higher return was limited to about 2% to 4% on gross proceeds of $936m. It would have required setting a higher share price for all investors and adopting a more flexible approach to share allocation

  • the Government’s objective to promote community and investor support was achieved. The scale of the demand for script added to costs and was not fully translated into higher proceeds  

  • generally satisfactory accountability frameworks were put in place for the sale and no probity concerns were identified

  • the frameworks to achieve the Government’s wider reforms of the racing and wagering industries have substantially been implemented.

 

Parliamentary reference - Report number #61 - released 23 December 1998

Published

Actions for NSW Senior Executive Service: Professionalism and Integrity Volume 1 Part 1 Summary and Research Report

NSW Senior Executive Service: Professionalism and Integrity Volume 1 Part 1 Summary and Research Report

Premier and Cabinet
Internal controls and governance
Workforce and capability

The Audit Office is of the opinion that there are several features of the current Senior Executive Service (SES) model, or its application, which hinder the capacity of the SES to operate effectively in line with the Government’s stated objectives. The ultimate effect of these features is to reduce the capacity or perceived capacity of the SES to meet the Government’s objectives for the operation of the SES.

Taken overall, difficulties in the SES identified by the audit included: uncertainty caused by the way some contracts have been applied in practice, removal for reasons other than poor performance, informal strategies such as using restructuring to “terminate contracts and to move people in and out of positions regardless of their formal reported performance” (Section 5.4), inconsistently applied rules about selection/recruitment, appointment and removal of the SES, an imbalance between CES responsibility to the Minister as the employer/reviewer with their responsibility not to act in a political or partial manner, apparent lack of rigour in, value of and Ministerial accountability for CES performance review processes and failure to implement an adequate system of rewards and sanctions related to performance.

 

Parliamentary reference - Report number #59.1 - released 17 December 1998

Published

Actions for NSW Senior Executive Service: Professionalism and Integrity Volume 1 Part 2 SES Research

NSW Senior Executive Service: Professionalism and Integrity Volume 1 Part 2 SES Research

Premier and Cabinet
Internal controls and governance
Workforce and capability

This Performance Audit Report, prepared by the University of Technology, Sydney (UTS) on behalf of The Audit Office of New South Wales (NSW), is a study of the NSW Senior Executive Service (SES).

It found the dissonance between where optimal executive performance might take place on a performance spectrum, encompassing the formal SES and less formal political arenas, is canvassed. The critical point here is that this arena, between the informal political actions and the application of formal SES structures, where much of the important decision making takes place, will always be difficult to manage. Transparency in decision making processes where non partisan and partisan actions are clearly defined seems a primary essential element of performance if the integrity of the NSW SES is to be maintained.

 

Parliamentary reference - Report number #59.2 - released 17 December 1998

Published

Actions for Review of Walsh Bay

Review of Walsh Bay

Finance
Infrastructure
Management and administration
Procurement
Project management

The decision to seek development of Walsh Bay without a Master Plan and/or detailed study as to the state of the precinct presented significant problems throughout the life of the project. Now, four years later, negotiations still continue on the details of the final scheme. Based on the latest estimates, it will not provide a financial return as was originally expected. The audit found no evidence to indicate why the former Government wished to expedite Walsh Bay, but it is aware that there was an election due. Many of the problems which have been encountered could have been avoided with more careful and more extensive consideration at the start, particularly in the light of Property Services Group's recommendations.

 

Parliamentary reference - Report number #58 - released 17 December 1998

Published

Actions for The coordination of bushfire fighting activities

The coordination of bushfire fighting activities

Justice
Management and administration
Service delivery
Shared services and collaboration
Workforce and capability

The NSW model of rural fire fighting is complex, and requires an extensive amount of coordination and cooperation to function properly. This has inherent risks. In general, the model has been made to work quite well and much improvement in rural fire fighting has been achieved over the past decade. The efforts of all concerned should be recognised and applauded especially since any change must be developed cooperatively between a number of agencies and groups.

Nevertheless, past tensions and difficulties have left pockets of disagreement and resistance. The rural fire fighting culture which was developed over the course of a century has always been highly dedicated, as it is today. However, changed organisational, technical, legal, financial and environmental factors have necessitated major and continuing changes.

 

Parliamentary reference - Report number #57 - released 2 December 1998