Actions for CBD and South East Light Rail Project

CBD and South East Light Rail Project

Transport
Compliance
Financial reporting
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk

Transport for NSW did not effectively plan and procure the CBD and South East Light Rail (CSELR) project to achieve best value for money according to a report released today by NSW Auditor-General, Margaret Crawford. Transport for NSW is on track to deliver the project, but it will come at a higher cost with lower benefits than in the approved business case.   Parliamentary reference - Report number #278 - released 30 November 2016

Published

Actions for Implementation of the NSW Government’s program evaluation initiative

Implementation of the NSW Government’s program evaluation initiative

Industry
Justice
Planning
Premier and Cabinet
Treasury
Environment
Financial reporting
Internal controls and governance
Management and administration
Risk
Service delivery
Shared services and collaboration
Workforce and capability

The NSW Government’s ‘program evaluation initiative’, introduced to assess whether service delivery programs achieve expected outcomes and value for money, is largely ineffective according to a report released today by NSW Auditor-General, Margaret Crawford. Government services, in areas such as public order and safety, health and education, are delivered by agencies through a variety of programs. In 2016–17, the NSW Government estimates that it will sp

Published

Actions for Government Advertising 2015-16

Government Advertising 2015-16

Premier and Cabinet
Compliance
Management and administration
Workforce and capability

Overall, the peer review process provides good assurance that government advertising campaigns are necessary and cost effective, according to a report released today by the NSW Auditor-General, Margaret Crawford. In NSW, the Government Advertising Act 2011 requires government advertising campaigns with a likely expenditure over $50,000 to be independently peer reviewed before launch. The Department of Premier and Cabinet manages this process, which incl

Published

Actions for Red tape reduction

Red tape reduction

Premier and Cabinet
Finance
Financial reporting
Internal controls and governance
Management and administration
Project management
Regulation
Shared services and collaboration

Overall, NSW Government initiatives and processes to prevent and reduce red tape were not effective, according to a report released today by the NSW Auditor-General. In 2015, the Government reported that its red tape reduction initiatives, implemented between 2011 and 2015, had resulted in $896 million in savings. While these initiatives resulted in some savings, the total value of savings is unknown because estimates for some initiatives were based on

Published

Actions for Managing unsolicited proposals in New South Wales

Managing unsolicited proposals in New South Wales

Premier and Cabinet
Internal controls and governance
Management and administration
Procurement
Shared services and collaboration

Overall, the governance arrangements for unsolicited proposals are adequate. However, there needs to be greater transparency and public reporting on unsolicited proposals received by government, according to a report released today by the NSW Acting Auditor-General, Tony Whitfield. 'Unsolicited proposals warrant more disclosure as they pose a greater risk to value for money than procurements done through open, competitive and transparent processes,” sai

Published

Actions for Realising the benefits of the Service NSW initiative

Realising the benefits of the Service NSW initiative

Whole of Government
Information technology
Internal controls and governance
Management and administration
Project management
Service delivery
Shared services and collaboration

The current benefits realisation approach for Service NSW needs to improve so benefits and savings can be effectively measured, reported and realised, according to a report released today by the NSW Acting Auditor-General, Tony Whitfield. Customers are finding that Service NSW provides a convenient and practical way to access all government transaction services.   Parliamentary reference - Report number #266 - released 17 February 2016

Published

Actions for Franchising of Sydney Ferries Network services

Franchising of Sydney Ferries Network services

Transport
Procurement
Service delivery

Franchising services on the Sydney Ferries Network was justified, and Transport for NSW’s management of the franchise has been largely effective according to a report released today by the NSW Acting Auditor-General, Tony Whitfield. 'Franchising has resulted in cost savings, good service performance, and effective risk transfer from government to the private sector operator', said Mr Whitfield.   Parliamentary reference - Report number #265&

Published

Actions for Public sector management reforms

Public sector management reforms

Finance
Industry
Premier and Cabinet
Planning
Whole of Government
Environment
Management and administration
Workforce and capability

The Public Service Commission is making good progress with leading the implementation of public sector management reforms, according to a report released today by the Acting New South Wales Auditor-General, Tony Whitfield. 'The Commission developed a sound evidence base for the reforms and gained wide public sector support by engaging with agency heads and using public sector working groups to develop options', said the Acting Auditor-General. 'They dev

Published

Actions for Volume Eight 2011 Focus on Transport and Ports

Volume Eight 2011 Focus on Transport and Ports

Transport
Industry
Asset valuation
Financial reporting
Fraud
Information technology
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Workforce and capability

The report includes comments on financial audits of government agencies in the Transport and Ports sectors. The audit of corporations’ financial statements for the year ended 30 June 2011 resulted in unmodified audit opinions within the Independent Auditor’s Reports. A key recommendation from the report is that Sydney Ports Corporation should continue working with other government authorities and industry stakeholders to improve the effect

Published

Actions for Solar Bonus Scheme

Solar Bonus Scheme

Premier and Cabinet
Compliance
Infrastructure
Management and administration
Project management
Regulation
Risk
Service delivery

A NSW Auditor General’s Report has found that the NSW Government and its agencies grossly underestimated the cost and number of people that would install systems under the Solar Bonus Scheme. By October 2010, the estimated cost of the Scheme, if it continued the way it was going, would have reached $3.988 billion. More than ten times the original estimate of $362 million. In response to the increased cost, the gross tariff for new applicants was reduced