What this report is about

Extreme rainfall across eastern Australia in 2021 and 2022 led to a series of major flood events in New South Wales.

This audit assessed how effectively the NSW Government provided emergency accommodation and temporary housing in response to the early 2022 Northern Rivers and late 2022 Central West flood events.

Responsible agencies included in this audit were the Department of Communities and Justice, NSW Reconstruction Authority, the former Department of Planning and Environment, the Department of Regional NSW and the Premier’s Department.

Findings

The Department of Communities and Justice rapidly provided emergency accommodation to displaced persons immediately following these flood events.

There was no plan in place to guide a temporary housing response and agencies did not have agency-level plans for implementing their responsibilities.

The NSW Government rapidly procured and constructed temporary housing villages. However, the amount of temporary housing provided did not meet the demand.

There is an extensive waitlist for temporary housing and the remaining demand in the Northern Rivers is unlikely to be met. The NSW Reconstruction Authority has not reviewed this list to confirm its accuracy.

Demobilisation plans for the temporary housing villages have been developed, but there are no long-term plans in place for the transition of tenants out of the temporary housing.

Agencies are in the process of evaluating the provision of emergency accommodation and temporary housing.

The findings from the 2022 State-wide lessons process largely relate to response activities.

Audit recommendations

The NSW Reconstruction Authority should:

  • Develop a plan for the provision of temporary housing.
  • Review the temporary housing waitlist.
  • Determine a timeline for demobilising the temporary housing villages.
  • Develop a strategy to manage the transition of people into long-term accommodation.
  • Develop a process for state-wide recovery lessons learned.

All audited agencies should:

  • Finalise evaluations of their role in the provision of emergency accommodation and temporary housing.
  • Develop internal plans for implementing their roles under state-wide plans.

Read the PDF report

Parliamentary reference - Report number #389 - released 22 February 2024

Published

Actions for Driver vehicle system

Driver vehicle system

Transport
Finance
Cyber security
Information technology
Internal controls and governance
Project management
Service delivery

What this report is about

Transport for NSW (TfNSW) uses the Driver vehicle System (DRIVES) to support its regulatory functions. The system covers over 6.2 million driver licences and over seven million vehicle registrations.

DRIVES first went live in 1991 and has been significantly extended and updated since, though is still based around the same core system. The system is at end of life but has become an important service for Service NSW and the NSW Police Force.

DRIVES now includes some services to other parts of government and non-government entities which have little or no connection to transport. There are 141 users of DRIVES in total, including commercial insurers, national regulators, and individual citizens.

This audit assessed whether TfNSW is effectively managing DRIVES and planning to transition it to a modernised system.

Audit findings

TfNSW has not effectively planned the replacement of DRIVES.

It is now working on its third business case for a replacement system but has failed to learn lessons from its past attempts.

In the meantime, TfNSW has not taken a strategic approach to managing DRIVES’ growth.

TfNSW has been slow to reduce the risk of misuse of personal information held in DRIVES. With its delivery partner Service NSW, TfNSW has also been slow to develop and implement automatic monitoring of access.

TfNSW uses recognised processes for managing most aspects of DRIVES, but has not kept the system consistently available for users. TfNSW has lacked accurate service availability information since June 2022, when it changed its technology support provider.

TfNSW needs to significantly prioritise cyber security improvements to DRIVES. TfNSW is seeking to lift DRIVES’ cyber defences, but it will not achieve its stated target safeguard level until December 2025.

Even then, one of the target safeguards will not be achieved in full until DRIVES is modernised.

Audit recommendations

TfNSW should:

  • implement a service management framework including insight into the views of DRIVES users, and ensuring users can influence the service
  • ensure it can accurately and cost effectively calculate when DRIVES is unavailable due to unplanned downtime
  • ensure implementation of a capability to automatically detect anomalous patterns of access to DRIVES
  • ensure that DRIVES has appropriate cyber security and resilience safeguards in place as a matter of priority
  • develop a clear statement of the future role in whole of government service delivery for the system
  • resolve key issues currently faced by the DRIVES replacement program including by:
    • clearly setting out a strategy and design for the replacement
    • preparing a specific business case for replacement.

Read the PDF report

Parliamentary reference - Report number #388 - released 20 February 2024

Published

Actions for Regional road safety

Regional road safety

Transport
Health
Community Services
Internal controls and governance
Management and administration
Project management
Risk

What this report is about

Around one-third of the state’s population lives in regional NSW, but deaths on regional roads make up around two-thirds of the state’s road toll.

Transport for NSW (TfNSW) is responsible for managing road safety outcomes across the NSW road network. This audit assessed the effectiveness of TfNSW’s delivery of road safety strategies, plans and policies in regional areas.

The NSW Road Safety Action Plan 2022–2026 has the stated goal of ‘no death or serious injury occurring on the road transport network’ by 2050.

What we found

There is a disproportionate amount of trauma on regional roads, but there are no specific road safety plans or trauma reduction targets for regional NSW.

TfNSW advises that the setting of state-wide road safety targets is consistent with other jurisdictions and international best practice. However, the proportion of road fatalities and serious injuries in regional NSW is almost the same as ten years ago.

There is no regional implementation plan to assist TfNSW to target the Road Safety Action Plan 2026 to regional areas.

TfNSW considers that local road safety outcomes should be managed by councils, but only 52% of regional councils participated in its Local Government Road Safety Program (LGRSP) in 2022–23. This program has not been updated since 2014, despite commitments to do so in 2021 and 2022.

TfNSW has not undertaken a systematic and integrated analysis of the combined impact of its road safety strategies and plans in regional NSW since 2012.

TfNSW reports against the Community Road Safety Fund (CRSF) annually but there is no consolidated, public reporting on total road safety funding allocated to regional NSW. The Fund underspend increased from 12% in 2019–20 to 20% in 2022–23.

What we recommended

We recommended TfNSW:

  • develop a regional implementation plan to support the NSW Road Safety Action Plan, including a framework to annually measure, analyse and publicly report on progress
  • develop a plan to measure and mitigate risks causing underspend in the CRSF
  • expedite the review of the LGRSP including recommendations to increase involvement of regional councils.

Disclosure of confidential information

Under the Government Sector Audit Act 1983 (the Act), the Auditor-General may disclose confidential information if, in the Auditor-General’s opinion, the disclosure is in the public interest, and that disclosure is necessary for the exercise of the Auditor-General’s functions.

Confidential information in the Act means Cabinet information or information subject to legal privilege. This performance audit report contained confidential information.

The NSW Premier has certified that in his opinion the disclosure of the confidential information was not in the public interest.

The confidential information has been redacted from this report.

Under section 36A(2) of the Government Sector Audit Act 1983, the Auditor-General may authorise the disclosure of confidential information if, in the Auditor-General’s opinion, the disclosure is in the public interest and necessary for the exercise of the Auditor-General’s functions. Confidential information under the Government Sector Audit Act 1983 means Cabinet information, or information that could be subject to a claim of privilege by the State or a public official in a court of law. This performance audit report contained confidential information which, in the opinion of the Auditor-General, is in the public interest to disclose and that disclosure is necessary for the exercise of the Auditor-General’s functions.

On 26 October 2023, pursuant to section 36A(2)(b) of the Government Sector Audit Act 1983, the Auditor-General notified the NSW Premier of the intention to include this information in the published report, having formed the opinion that its disclosure is in the public interest and is necessary for the exercise of the Auditor-General’s functions.

On 23 November 2023, pursuant to section 36A(2)(c) of the Government Sector Audit Act 1983, the NSW Premier certified that, in his opinion, the proposed disclosure of the confidential information contained in this report was not in the public interest. The Premier’s certificate follows. Section 36A(4) states that a certificate of the Premier that it is not in the public interest to disclose confidential information is conclusive evidence of that fact.

The issuance of the certificate by the NSW Premier prevents the publication of this information. The relevant sections of the report containing confidential information have been redacted.

One-third of the New South Wales population resides in regional areas, but two-thirds of the state’s road crash fatalities take place on regional roads.

Between 2017 and 2021, the average number of fatalities for every 100,000 of the population living in regional New South Wales was 8.33 — approximately four times higher than the equivalent measure for Greater Sydney. Similarly, the average number of serious injuries in regional New South Wales over the same period was 75.24 per 100,000 of the population, compared with 50.53 in Greater Sydney. Further, more than 70% of people who lose their lives in accidents on regional roads are residents of regional areas.

Residents of regional areas face particular transport challenges. They often need to travel longer distances for work, health care, or recreation purposes, yet their public transport options are more limited than metropolitan residents. Vehicle safety is also an issue. According to the NSW Road Safety Progress Report 2021, of the light vehicles registered in New South Wales that were manufactured in or after 2000, 48.4% of light vehicles in regional areas had a five-star Australasian New Car Assessment Program (ANCAP) rating, compared to 54.8% in metropolitan areas. Road conditions in regional areas can also be more challenging for drivers.

Regional New South Wales covers 98.5% of the total area of the state. The road network in New South Wales is vast — spanning approximately 200,000 kilometres.

The road network includes major highways, state roads and local roads. Speed limits range from 10 km/hr in high pedestrian shared zones, up to 110 km/hr on high volume and critical road corridors. Eighty per cent of the network has a 100 km/h speed limit, which is mostly applied as a default speed limit, regardless of the presence of safety features and treatments.

Speed is the primary causal factor in more crashes in New South Wales than any other factor, and car crashes in regional areas are more likely to be fatal because of the higher average speeds involved.

The responsibility for managing road safety outcomes across the entire New South Wales road network lies with Transport for NSW (TfNSW), pursuant to Schedule 1 of the Transport Administration Act 1988.

While its safety responsibilities are state-wide, TfNSW does not own or directly manage all of the road network in regional New South Wales, which spans approximately 200,000 kilometres. Approximately 80% of the roads are classified as Local Roads and are administered and managed by local councils. Local councils also maintain Regional Roads that run through their local government areas. TfNSW is responsible for managing State Roads (approximately 20% of roads), which are major arterial roads. It also provides funding for councils to manage over 18,000 km (approximately 10%) of state-significant Regional Roads.

According to TfNSW, between 2016 and 2020, there were 9,776 people killed or seriously injured on roads in regional New South Wales. Adding to the tragic loss of life, according to TfNSW, the estimated cost to the community between 2016 and 2020 resulting from regional road trauma and fatalities was around $13.7 billion.

TfNSW also noted that the ‘risk of road trauma is pervasive, and a combination of effective road safety measures is required to systematically reduce this risk’.

TfNSW released its first long-term road-safety strategy in December 2012, which introduced the goal of ‘Vision Zero’ — a long-term goal of zero deaths or serious injuries on NSW roads. The terminology was changed to ‘Towards Zero’ in the 2021 Road Safety Plan and has been retained in the NSW Road Safety Action Plan 2022–2026. Towards Zero has the stated goal of ‘no death or serious injury occurring on the road transport network’ by 2050.

The objective of this audit is to assess the effectiveness of TfNSW’s delivery of ‘Towards Zero’ in regional areas.

In making this assessment, the audit examined whether TfNSW:

  • is effectively reducing the number of fatalities and serious injuries on regional roads
  • has an effective framework, including governance arrangements, for designing and refreshing the NSW Road Safety Strategy 2012–2021 and the NSW Road Safety Action Plan 2022–2026
  • effectively makes use of whole-of-government and other relevant sources of data to support decision-making, and to evaluate progress and outcomes
  • effectively manages accountabilities, including roles and responsibilities, with respect to road safety outcomes and the use of data.

This audit focused on the policies and strategies used by TfNSW for managing road safety outcomes in regional areas. We did not evaluate individual road safety projects, programs and initiatives as part of this audit.

Whilst Regional Roads and Local Roads (as defined by the Road Network Classifications) are owned and maintained by local councils, we included these roads in this audit as TfNSW may advise and assist councils to promote and improve road safety, as well as manage grant programs that focus on improving road safety outcomes on these roads. Hereafter, unless otherwise stated, references to ‘regional roads’ refer to all classifications of roads in the state which are in regional New South Wales, irrespective of their ownership.

Local councils in regional areas are key stakeholders for the purposes of this audit, and we interviewed eight as part of the audit process (noting that this was not intended to be a representative sample). Road asset management by local councils is also out of scope for this audit as it is the focus of a subsequent performance audit by the Audit Office of New South Wales.b

The Audit Office of New South Wales has undertaken several performance audits relating to road safety since 2009 and these have been referenced while undertaking this audit. They include:

  • Condition of State Roads (August 2006)
  • Improving Road Safety: Heavy Vehicles (May 2009)
  • Improving Road Safety: School Zones (March 2010)
  • Improving Road Safety: Speed Cameras (July 2011)
  • Regional Assistance Programs (May 2018)
  • Mobile speed cameras (October 2018)
  • Rail freight and Greater Sydney (October 2021).

Conclusion

TfNSW has acknowledged that there is a disproportionate amount of road trauma on regional roads in the NSW Road Safety Strategy 2012–2021, the NSW Road Safety Plan 2021, and the NSW Road Safety Action Plan 2022–2026. However, TfNSW has not articulated or evaluated a strategy for implementing road safety policy in regional New South Wales to assist in guiding targeted activities to address regional road trauma. There is also no transparency about the total amount of funding invested in improving road safety outcomes for regional New South Wales.

People living in regional New South Wales make up one-third of the state’s population, but deaths on regional roads make up around two-thirds of the state’s total road toll. This statistic is almost the same in 2023 as it was ten years ago when TfNSW released its first long-term road safety strategy.

More than 70% of people who died on roads between 2012 and 2022 in regional New South Wales were residents of regional areas. Speed is the greatest contributing factor to road fatalities and serious injuries across the entire state. However, it is responsible for more fatalities on regional roads (43%) than in Greater Sydney (34%).

TfNSW’s road safety strategies and plans acknowledge that most road fatalities occur in regional New South Wales but none of its existing strategies or plans show evidence of tailoring measures to suit particular regional settings or ‘hot spots’. There are infrastructure initiatives (such as Saving Lives on Country Roads) and behavioural programs targeting regional areas (such as Driver Reviver). However, these activities are not aligned to a regional-specific strategy or plan that addresses issues specific to regional areas.

TfNSW has state-wide responsibility for managing road safety outcomes. TfNSW advised the audit that a regional plan and regional trauma reduction targets are not needed as the state-wide plan and targets apply equally for all areas of New South Wales, and local road safety factors are best managed by local councils. TfNSW partners with local councils. However, only 52% of councils in regional New South Wales participate in TfNSW’s Local Government Road Safety Program, compared to 84% of councils in metropolitan areas. TfNSW has not undertaken any evaluations to determine whether projects completed under the Local Government Road Safety Program have reduced road trauma at the local level.

Notwithstanding the above points, TfNSW works with local councils (who are road authorities for local roads in their respective areas under the Roads Act 1993) and other key stakeholders such as the NSW Police Force to achieve the NSW Government’s road safety policy objectives.

TfNSW advised that ‘the setting of state-wide road safety targets is consistent with other jurisdictions and international best practice. Importantly, delivery of road safety countermeasures is tailored and applied with a focus on road user groups across all geographic locations to maximise trauma reductions’. There may be legitimate reasons for the existing approach, as articulated by TfNSW. However, the proportion of road fatalities in regional New South Wales roads has not reduced since 2012 – despite a long-term reduction in the overall number of deaths on the state’s roads between 2012–2021. The audit report has recommended that a regionally focused implementation plan could address this issue. TfNSW has accepted this report’s recommendation that such a plan be developed.

Specific road safety initiatives targeted to regional areas have not been implemented or expanded

Text removed pursuant to section 36A of the Government Sector Audit Act 1983 (NSW), in compliance with the issuance of a Premier’s certificate preventing the publication of this information.

TfNSW increased the use of other forms of automated enforcement (such as tripling enforcement hours in mobile speed cameras).
However, the use of automated enforcement has a strong metropolitan focus with most red light and fixed speed cameras being in metropolitan areas. Average speed cameras are the only camera type overwhelmingly located in regional areas but these apply only to heavy vehicles and are positioned on major freight routes. 

There is no consolidated, public reporting of what proportion of total road safety funding is directed to regional New South Wales each year. The main source of funding for road safety in New South Wales, the Community Road Safety Fund, has been underspent since 2019.

Fines from camera-detected speeding, red-light and mobile phone use offences are required to be used solely for road safety purposes through the Community Road Safety Fund (CRSF), as set out in the Transport Administration Amendment (Community Road Safety Fund) Act 2012.

The CRSF has been underspent every year since 2019–20. The underspend has increased from 12% in 2019–20 to 20% in 2022–23 where the full year underspend was forecasted to be $104 million. Of this underspend, $13.5 million was dedicated for regional road infrastructure projects. TfNSW advised the audit that much of the underspend is the result of delays to infrastructure projects due to COVID-19, bushfires, and floods, as well as skills shortages. However, TfNSW has not provided any evidence that it had a plan to mitigate these risks – meaning the level of underspend could continue to grow. TfNSW also advised ‘there is no reason to expect budget management and controls will not return to pre-COVID circumstances’.

In total, TfNSW received $700 million in funding for road safety in 2021–22 (including federal contributions and the Community Road Safety Fund). Of this, $411 million (or ~59%) was directed to regional New South Wales. This is the most recent comprehensive financial data that was provided by TfNSW to the audit team. The 2022–23 NSW Budget allocated $880 million for road safety in 2022–23, with a forecasted total allocation for road safety of $1.6 billion in recurrent expenses and $0.8 billion in capital expenditure over the period 2022–23 to 2025–26.

Appendix one – Response from Transport for NSW

Appendix two – The Safe Systems framework and NSW road safety strategies and plans

Appendix three – About the audit

Appendix four – Performance auditing

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #386 - released 30 November 2023

Published

Actions for NSW government agencies' use of consultants

NSW government agencies' use of consultants

Treasury
Whole of Government
Compliance
Internal controls and governance
Management and administration
Procurement
Workforce and capability

What the report is about

This audit assessed how effectively NSW government agencies procure and manage consultants. It examined the role of the NSW Procurement Board and NSW Procurement (a unit within NSW Treasury) in supporting and monitoring agency procurement and management of consultants.

The audit used four sources of data that contain information about spending on consultants by NSW government agencies, including annual report disclosures and the State's financial consolidation system (Prime). It also reviewed a sample of consulting engagements from ten NSW government agencies.

What we found

Our review of a selection of consulting engagements indicates that agencies do not procure and manage consultants effectively.

We found most agencies do not use consultants strategically and do not have systems for managing or evaluating consultant performance. We also found examples of non-compliance with procurement rules, including contract variations that exceeded procurement thresholds.

NSW Procurement has made improvements to the information available about spending on consultants, including additional analysis and reporting. However, there is no single data source that accurately captures spending on consultants.

Our analysis of data on whole-of-government spending on consultants, drawn from agency annual reports, indicates that four large professional services firms accounted for about a quarter of consultancy expenditure from 2017–18 to 2021–22. This concentration increases strategic risks, including over-reliance on a limited number of providers and potential reduction in the independence of advice.

It is also highly unlikely that NSW government agencies will meet the government's 2019 policy commitment to reduce consultancy expenses by 20% each year, over four years, from 2019–20. NSW Treasury advised that to implement this commitment, agency budgets were reduced in Prime in line with the savings targets. However, actual spending on consulting in NSW Treasury's Reports on State Finances 2020–21 and 2021–22 was almost $100 million higher than the savings targets over the first three years since 2019–20.

What we recommended

The report made seven recommendations which aim to improve:

  • the quality and transparency of data on spending on consultants
  • monitoring of strategic risks and agency compliance with procurement and recordkeeping rules
  • agencies' strategic use of consultants, including evaluation and knowledge retention.

Between 2017–18 and 2021–22, NSW government agency annual reports disclosed total spending of around $1 billion on consultants across more than 10,000 engagements. More than 1,000 consulting firms provided services to NSW government agencies during this period. Consulting is a classification of professional services that is characterised by giving advice or recommendations on a specific issue. The NSW Procurement Board Direction PBD-2021-03 defines a consultant as a person or organisation that provides 'recommendations or professional advice to assist decision-making by management'. PBD-2021-03 notes that the advisory nature of the work of consultants is the main factor that distinguishes them from other providers of professional services.

The NSW Procurement Board is responsible for setting procurement policy, issuing directions to support policies, and monitoring and reporting on agency compliance with policies and directions. NSW Procurement, a division within NSW Treasury, supports agencies to comply with the NSW Procurement Board’s policies and directions. A 'devolved governance model' is used for procurement in New South Wales. This means the heads of government entities that are covered by the NSW Procurement Board’s directions are responsible for managing the entity's procurement, including managing risks, reporting and ensuring compliance, in line with procurement laws and policies.

This audit assessed how effectively NSW government agencies procure and manage consultants. It assessed the role of the NSW Procurement Board and NSW Procurement in supporting and monitoring agency procurement and management of consultants. It also reviewed a sample of consulting engagements from ten NSW government agencies to examine how agencies procured, managed and reported on their use of consultants. The ten NSW government agencies were:

  • NSW Treasury
  • Department of Communities and Justice
  • Department of Customer Service
  • Department of Education
  • Department of Planning and Environment
  • Department of Premier and Cabinet
  • Department of Regional NSW
  • Infrastructure NSW
  • Sydney Metro
  • Transport for NSW

There are four different sources of data that contain information about spending on consultants by NSW government agencies: the State's financial consolidation system (Prime), disclosures of spending on consultants in agency annual reports, and two systems operated by NSW Procurement (the Business Advisory Services (BAS) dashboard and Spend Cube). Each of these data sources serves a different purpose, and collects and categorises information differently. None of these provide a complete source of data on spending on consultants, either in their own right or collectively.

NSW Treasury considers Prime to be the 'source of truth' on consulting expenditure across the NSW public sector. An account within Prime records recurrent spending on consultants, but this account does not include capital expenditure (that is, spending on consultants that has from a financial reporting perspective been 'capitalised' to a project on the balance sheet). As the State's financial consolidation system, Prime captures all financial information. However, capitalised consulting expenditure is recorded within various capital accounts, and is not identifiable within these accounts. While this is appropriate for accounting purposes, it means that the Prime account that records recurrent consulting expenditure does not reflect total spending on consultants by NSW government agencies. We used the data in Prime to assess whether NSW government agencies met the NSW Government's policy commitment—stated before the 2019 election and costed by the Parliamentary Budget Office—to reduce recurrent expenditure on consulting by 20% each year, over four years, from 2019–20. We did this because, while the Prime account for recurrent consulting expenditure does not reflect all spending on consultants, it does capture the recurrent spending that was subject to the policy commitment.

Most NSW government agencies are required by legislation to disclose spending on consultants (as defined in PBD-2021-03) in their annual reports. These disclosures include both recurrent and capital expenditure. For consulting engagements that cost more than $50,000, the disclosures also provide itemised information, including the names of the individual projects and the consultants used. While this data is more complete than Prime because it includes capital expenditure, it also has some gaps. Some entities are excluded from public reporting requirements on consultant use. For example, NSW Local Health Districts (LHD) are not required to produce annual reports, and the Ministry of Health does not include LHD consulting expenditure in its annual report.1 We used annual report disclosure data to report on total expenditure on consultants, and the concentration of suppliers of consulting services to NSW government agencies.

The BAS dashboard and Spend Cube are systems created by NSW Procurement to collect information about spending on suppliers of professional services. This includes consultants, but also includes other professional services providers. The systems were not designed for reporting on spending on consulting as defined in PBD-2021-03. However, we have used this data to assess specific aspects of NSW Procurement's monitoring of the use of consultants by NSW government agencies.

In 2018, we conducted an audit titled 'Procurement and reporting of consultancy services'. This assessed how 12 NSW government agencies complied with procurement requirements and how NSW Procurement supported the functions of the NSW Procurement Board. The 2018 audit found that none of the 12 agencies fully complied with NSW Procurement Board Directions on the use of consultants and that the NSW Procurement Board was not fully effective in overseeing and supporting agencies’ procurement of consultants. Specific findings from the 2018 audit included: 

  • Agencies applied the definition of consultant inconsistently, which affected the accuracy of reporting on consultancy expenditure.
  • There was inadequate guidance from NSW Procurement for agencies implementing the procurement framework, with a need for additional tools, automated processes, and other internal controls to improve compliance.
  • NSW Procurement had insufficient data for effective oversight of procurement and did not publish any data on the procurement of consultancy services by NSW government agencies.

Conclusion

Our review of a selection of consulting engagements from ten NSW government agencies indicates that these agencies do not procure and manage consultants effectively. We found that most agencies do not have a strategic approach to using consultants, or systems for managing or evaluating their performance. We also found examples of non-compliance with procurement rules, including contract variations that exceeded procurement thresholds. NSW Procurement, a division within NSW Treasury, provides frameworks and some guidance to agencies for procuring consultants. However, gaps in its data collection and analysis mean monitoring of strategic risks is limited and it does not respond to agency non-compliance consistently. There are limitations in ability of various data sources to accurately record spending on consultants. These limitations include incomplete recording of all spending, and different definitions of consulting for accounting and financial reporting purposes. Notwithstanding these limitations, and based on information in the State's financial consolidation system (Prime)—which records recurrent expenditure on consultants—it is highly unlikely that NSW government agencies will meet the government's 2019 policy commitment to reduce spending on consultants, as defined in the policy commitment and costed by the Parliamentary Budget Office. 

The use of a 'devolved governance model' for procurement means NSW government agencies are responsible for developing and implementing their own systems that align with the NSW Government Procurement Policy Framework. Agency heads are responsible for demonstrating compliance. Most agencies included in this audit did not have a clear strategic approach to how and when consultants should be used (for example, to seek advice and expertise not already available within the agency) and were using consultants in an ad hoc manner.

Our analysis of whole-of-government spending on consultants, drawn from agency annual reports, indicates that four large professional services firms account for around 27% of spending on consultants in the period from 2017–18 to 2021–22. The number of firms making up the top 50% of expenditure decreased from 11 to eight during this time, with the other 50% of expenditure spread across more than 1,000 firms. Concentration of consulting engagements within a small number of firms increases strategic risks, including that advice is not sufficiently objective and impartial, and that NSW government agencies become overly reliant on selected professional services firms.

Our review of a selection of consulting engagements by NSW government agencies found several examples of non-compliance with procurement policy. This included the use of variations to contract values which exceeded allowable limits. Record keeping was inadequate in many cases we reviewed, which limits transparency about government spending. Most agencies did not proactively manage their consulting engagements. The majority of consulting engagements that we reviewed were not evaluated or assessed by the agency for quality. Very few used any processes to ensure the transfer and retention of knowledge generated through consulting engagements. This means agencies miss opportunities to increase core staff skills and knowledge and to maximise value from these engagements.

NSW Procurement oversees a detailed policy framework that provides guidance and support to NSW government agencies when they are using consultants. The policy framework provides mandatory steps and some other guidance. Our audit on the procurement and reporting of consultancy services in 2018 found that agency reporting on the use of consultants was inconsistent and recommended that NSW Procurement should improve the quality, accuracy and completeness of data collection. NSW Procurement’s guidance on how agencies should classify and report on consulting engagements remains ambiguous. This contributes to continued inconsistent reporting by and across agencies, and reduces the quality of data on the use of consultants.

NSW Procurement has made some improvements to the information available about spending on consultants since our audit in 2018, including additional analysis and reporting that is available to agencies. However, there is still no single data source that accurately captures all spending on consultants. This is despite our recommendations in 2018 that NSW Procurement improve the quality of information collected from agencies and suppliers, which NSW Procurement accepted. This makes it harder for NSW Procurement or individual agencies to track trends and identify risks or improvement opportunities in the way consultants are used. 

In early 2019, the NSW Government made a policy commitment to reduce consultancy expenses by 20% each year, over four years, from 2019–20 (excluding capital-related consultancy expenses). This commitment was set out in the Parliamentary Budget Office's '2019 Coalition Election Policy Costings (Policy Costings)'. NSW Treasury subsequently advised that to implement this commitment, agency budgets were reduced in Prime in line with the savings targets. However, actual spending on consultants recorded in Prime in the first three years after the commitment was made was almost $100 million higher than the targets. We did not see any evidence that the financial data on actual expenditure was used to inform reporting on NSW government agencies' progress toward achieving the savings set out in the policy commitment.


1 The Government Sector Finance Legislation (Repeal and Amendment) Act 2018 No 70 will amend the Health Services Act 1997 to specify that annual reporting information for any or all NSW Health entities may be included in the annual reporting information prepared by the Ministry of Health under the Government Sector Finance Act 2018. This provision is expected to commence on 1 July 2023.

This chapter outlines our findings on the role of NSW Procurement in overseeing the use of consultants by NSW government agencies.

This chapter outlines our findings on the use of consultants by the ten NSW government agencies that were included in this audit.

Appendix one – Responses from auditees

Appendix two – About the audit

Appendix three – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #378 - released 2 March 2023

Published

Actions for Government's acquisition of private property: Sydney Metro project

Government's acquisition of private property: Sydney Metro project

Transport
Planning
Whole of Government
Compliance
Infrastructure
Internal controls and governance
Project management
Risk

What the report is about

Sydney Metro is Australia’s largest public transport project. It requires the acquisition of many private properties, including residential and business properties.

This audit assessed the effectiveness of the acquisition of private properties for the Sydney Metro project. The audited agencies were Sydney Metro, the Department of Planning and Environment (Valuer General NSW) and Transport for NSW (the Centre for Property Acquisition).

The audit assessed agencies against the framework for property acquisitions in New South Wales. It did not re-perform the valuations done for individual properties that were acquired by Sydney Metro.

What we found

Acquisitions of private property for the Sydney Metro project were mostly effective in the sample of acquisitions we assessed. We found Sydney Metro:

  • complied with legislative and policy requirements for compensation and communication with people subject to property acquisitions
  • kept accurate records of its acquisitions and applied probity controls consistently
  • did not complete detailed plans or negotiation strategies for the high-risk and high-value acquisitions we reviewed
  • did not comply with legislative timelines for most compulsory acquisitions because of delays in receiving the required information from the Valuer General in these cases.

The Centre for Property Acquisition has overseen the implementation of reforms to residential acquisition processes, but its assessment of the effectiveness of these reforms has not been comprehensive.

What we recommended

The audit made four recommendations to the audited agencies to improve:

  • plans and strategies for the acquisition of high-risk and high-value properties
  • timeliness of issuing compensation determinations for compulsory acquisitions
  • data quality on the experience of people subject to property acquisitions.

The NSW Government has the power to acquire land that is owned or leased by individuals or businesses, if it is needed for a public purpose. The power arises from the Land Acquisition (Just Terms Compensation) Act 1991 (the Just Terms Act). Government agencies that have the power to compulsorily acquire private property are referred to as ‘acquiring authorities’. People who are subject to acquisitions are referred to as ‘affected parties’ and include property owners (business or residential), businesses with a commercial lease on a property, or individuals with residential tenancy leases. In recent years, the vast majority of acquisitions by the NSW Government have been for public transport or road projects.

Sydney Metro is a NSW Government agency with responsibility for building the Sydney Metro railway project. Sydney Metro is Australia’s largest public transport project. The project requires the acquisition of a large number of private properties. Sydney Metro has been one of the largest acquirers of private property in recent years, completing over 500 acquisitions between 2020 and mid-2022, with a total acquisition value of over $2 billion. Other agencies and statutory officers involved in the acquisition of property for the Sydney Metro project include:

  • the Department of Planning and Environment (DPE), which supports the minister responsible for the Just Terms Act. DPE also provides staff to the Valuer General of NSW
  • the Valuer General of NSW, an independent statutory officer that determines compensation in cases where the acquiring authority and the affected party cannot agree on compensation for property that has been acquired
  • Transport for NSW, which includes the Centre for Property Acquisition (CPA). The CPA does not have a direct role in acquiring properties, but its responsibilities include developing guidance for acquiring agencies and monitoring and reporting on their activities.

About this audit

The objective of this audit was to assess the effectiveness of acquisitions of private properties for Sydney Metro projects. The audit assessed agencies against the legislative and policy requirements in place for government acquisitions of private property in New South Wales. In line with the Audit Office's legislative mandate, the audit does not comment on the merits of the policy objectives reflected in the Just Terms Act.

The audit examined a sample of 20 property acquisitions. This was not a statistically representative sample. While our report provides comments on Sydney Metro’s overall acquisition processes, it does not provide assurance regarding the acquisitions that were not examined for this audit.

The audit did not re-perform the valuations done for individual properties that were acquired by Sydney Metro. Affected parties who disagree with the valuation of their property have the right to seek independent assessment of this via the Valuer General and the Land and Environment Court.

Conclusion

Acquisitions of property for the Sydney Metro project were mostly effective in the sample of acquisitions we assessed. Sydney Metro followed requirements for communication with affected parties. Compensation processes were conducted in compliance with legislative requirements, but compensation determinations for compulsory acquisitions were not completed within legislated time frames due to delays in receiving these from the Valuer General. Governance and probity processes were followed consistently, with some relatively minor exceptions. 

Sydney Metro has detailed guidelines for acquisitions that are based on relevant legislation and government policy. In the 20 acquisitions we assessed for this audit, these procedures were followed consistently. This included adhering to minimum timelines for negotiation periods, engaging independent valuers and other experts when needed, and complying with governance and probity processes.

Sydney Metro staff followed requirements for communication and support for residential acquisitions by assigning ‘personal managers’ and providing additional support to affected parties when needed. The Centre for Property Acquisition (CPA) has overseen reforms to the residential property acquisition process in recent years. These reforms include the introduction of the NSW Property Acquisition Standards and the use of personal managers, in addition to the existing acquisition managers, for residential acquisitions. However, the CPA has not assessed the impact of these changes on the experiences on people affected by property acquisitions.

Sydney Metro did not comply with the legislative requirement to provide a formal compensation notice to the affected party within 45 days of a compulsory acquisition starting in any of the eight relevant acquisitions in our sample. This was because Sydney Metro must wait for the Valuer General to complete a compensation determination before Sydney Metro can send the compensation notice, and the Valuer General did not do this within 45 days. We acknowledge that Sydney Metro does not have full control over this process, and that it has taken steps to mitigate the impact of delays on affected parties. 

This chapter presents our findings on Sydney Metro's acquisition of industrial and commercial properties. Industrial properties include construction businesses and manufacturing facilities. Commercial properties were mostly properties such as shopping centres and office towers. Many of these acquisitions involve businesses and properties that are relatively complex and have high values. This means the valuation process can require multiple experts and can be lengthy and contested. Adherence to governance and probity requirements is important for these acquisitions in order to demonstrate that the acquiring authority has achieved value for money.

This chapter presents our findings on Sydney Metro's acquisition of residential properties, which include apartments and houses, and small business leases, which mostly affected businesses in small shopping centres or arcades. Most of these acquisitions were lower value compared to industrial and commercial property acquisitions and did not require as much expert advice on complex technical issues. However, residential property acquisitions can be personally distressing for the affected parties and require staff from the acquiring authority to provide support and show empathy while ensuring legislative compliance and value for money.

Appendix one – Responses from agencies

Appendix two – About the audit 

Appendix three – Performance auditing 

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #375 - released 9 February 2023

Published

Actions for Design and implementation of the Transport Asset Holding Entity

Design and implementation of the Transport Asset Holding Entity

Transport
Treasury
Asset valuation
Financial reporting
Infrastructure
Procurement
Risk
Service delivery

What the report is about

The Transport Asset Holding Entity (TAHE) is the State's custodian of rail assets. It is a state owned corporation and commenced operating on 1 July 2020.

This audit assessed the effectiveness of NSW Government agencies' design and implementation of TAHE. We audited TAHE, Transport for NSW (TfNSW) and NSW Treasury.

Separate and related audits on TAHE are reported in 'State Finances 2022', 'State Finances 2021' and 'Transport and Infrastructure 2022' reports.

What we found

The design and implementation of TAHE, which spanned seven years, was not effective.

The process was not cohesive or transparent. It delivered an outcome that is unnecessarily complex in order to support an accounting treatment to meet the NSW Government's short-term Budget objectives, while creating an obligation for future governments.

The benefits of TAHE were claimed in the 2015–16 NSW Budget before the enabling legislation was passed by Parliament in 2017. This committed the agencies to implement a solution that justified the 2015–16 Budget impacts, regardless of any challenges that arose.

Rail safety arrangements were a priority throughout TAHE's design and implementation, and risks were raised and addressed.

Agencies relied heavily on consultants on matters related to the creation of TAHE, but failed to effectively manage these engagements. Agencies failed to ensure that consultancies delivered independent advice as an input to decision-making. A small number of firms were used repeatedly to provide advice on the same topic. The final cost of TAHE-related consultancies was $22.6 million compared to the initial estimated cost of $12.9 million.

What we recommended

We recommended that the audited agencies should:

  • improve accountability and transparency for major new fiscal transformation initiatives
  • ensure entities do not reflect the financial impact of significant initiatives in the Budget when there is uncertainty, or it creates perverse incentives
  • review record keeping practices, systems and policies to ensure compliance with the State Records Act 1998, and the NSW Government Information Classification, Labelling and Handling Guidelines
  • review procurement policies to ensure that consultant use complies with all NSW Government policy requirements.

The NSW Government established the Transport Asset Holding Entity (TAHE), a statutory State Owned Corporation (SOC), on 1 July 2020 to replace the former rail infrastructure owner – RailCorp. It is the State's custodian of rail network assets, including rail tracks and other infrastructure, rolling stock, land, train stations and facilities, retail space, and signal and power systems, within metropolitan and regional New South Wales. It is responsible for $2.8 billion of major capital projects in 2022–23.

TAHE was established under Part 2 of the Transport Administration Act 1988 and is governed by a decision-making board. The Treasurer and the Minister for Finance and Employee Relations are the Shareholding Ministers of TAHE, and they annually agree performance expectations articulated in a Statement of Corporate Intent.

Whereas TAHE is the custodian of rail assets, Sydney Trains and NSW Trains operate public rail services. TAHE does not have responsibility for the operation of the heavy rail network or train services, nor does it have network control functions. TAHE, Sydney Trains and NSW Trains are in the Transport and Infrastructure cluster in the public sector (formerly the Transport cluster and renamed in April 2022), which also includes Sydney Metro and Transport for NSW (TfNSW).

TfNSW leads the Transport and Infrastructure cluster. Its role is to set the strategic direction for transport across the State. This involves the shaping of planning, policy, strategy, regulation, resource allocation and other service and non-service delivery functions for all modes of transport.

TAHE's Operating Licence is granted by the Portfolio Minister and authorises the entity to perform the functions required to acquire, develop, finance, divest and hold assets, pursuant to the Transport Administration Act 1988. The Portfolio Minister also issues a Statement of Expectations which outlines the government’s expectation for the business for the next three to five years.

TAHE's original Portfolio Minister was the Minister for Transport who approved, on 30 June 2020, the issuing of an interim 12-month Operating Licence to enable TAHE to commence operating on 1 July 2020. The Portfolio Minister then granted TAHE's current Operating Licence in 2021. After TAHE requested a 12-month extension to its current Operating Licence, its next Operating Licence is due on 1 July 2024. The current Portfolio Minister is the Minister for Infrastructure, Cities and Active Transport.

About this audit

This audit assessed the effectiveness of NSW Government agencies' design and implementation of TAHE. In making this assessment, we considered whether: 

  • the process of designing and implementing TAHE was cohesive and transparent, and delivered an effective outcome
  • agencies' roles and responsibilities were clear in the planning of TAHE
  • agencies effectively identified and managed certain risks.

Conclusion

The design and implementation of TAHE was not effective. The process was not cohesive or transparent. It delivered an outcome that is unnecessarily complex in order to meet the NSW Government's short-term Budget objectives, while creating an obligation for future governments to sustain TAHE through continuing investment, and funding of the state owned rail operators. The ineffective process to design TAHE delivered a model that entails significant uncertainty as to whether the anticipated longer-term financial improvements to the Budget position can be achieved or sustained.

NSW Treasury and TfNSW had different objectives for TAHE

Up to June 2013, RailCorp had been the owner and operator of rail services and maintainer of the metropolitan rail network for almost a decade. It had been operating as a not-for-profit Public Non-Financial Corporation (PNFC).

In 2012, NSW Treasury (hereafter Treasury) decided there was a risk that the Australian Bureau of Statistics (ABS) would reclassify RailCorp to the General Government Sector (GGS), meaning depreciation expenses of approximately $870 million would be reflected in the GGS Budget. Treasury wanted to avoid this impact on the GGS Budget, and considered the establishment of a transport asset holding entity as a means to do so. Capital grants to RailCorp were being treated as an expense to the GGS Budget.

TfNSW also wanted an asset holding entity – but one that would be a non-trading ‘shell’ company with no staff that would hold and manage all public transport assets. TfNSW's concept envisaged the entity would have a structure that would enable future public transport reforms and strategic directions while ensuring vertical integration of operations between asset owners and the rail operators to maintain rail safety.

However, Treasury pursued its objective to improve the GGS Budget result, and sought to expand on TfNSW's 'shell' asset holding entity concept. Treasury wanted an entity that could generate a return on investment, as this meant that government investment in transport assets could be treated as equity investments, rather than a Budget expense, and in turn improve the GGS Budget position. As an example of the potential impact of creating this new entity, capital grants of $2.3 billion were paid to RailCorp in 2013–14. If Treasury's objective was met, grants of this significance would then be treated as an equity investment, rather than an expense in the GGS Budget.

In 2017, Treasury's preferred option was progressed through legislation, but both agencies' central objectives for the proposed asset holding entity would continue to prove difficult to reconcile. To achieve Treasury's objective to improve the Budget result, the entity would need to generate a return on investment (this is further discussed below). However, TfNSW expressed concerns that the prioritisation of rail safety, and the effective management of governance, regulation and operations would be more complex in an entity with commercial imperatives.

Asset holding entities are a common approach to the management of transport assets in Australia and internationally, and there are a range of approaches to how they are structured and used. Such structures should be driven by the goal of improved asset management. Ultimately, TfNSW's objectives could have been delivered through a simpler entity structure. However, reconciling TfNSW's objectives with Treasury's imperative to deliver and justify a Budget improvement in the short-term resulted in an overly lengthy process and an unnecessarily complex outcome that places an obligation on future governments to sustain. There is still significant uncertainty as to whether the short-term improvements to the Budget can continue to be realised in the longer-term.

The Budget benefits of TAHE were claimed before the entity was legislated, committing the agencies to deliver, regardless of the complexities that subsequently arose

The 2015–16 GGS Budget treated the government's investment in TAHE (still known at this time as RailCorp) as an equity contribution. This had the immediate impact of improving the Budget result by $1.8 billion per annum. However, the legislation to enable the establishment of TAHE had not yet been passed by Parliament, key elements of the operating model were still under development, and imminent changes in accounting standards had the potential to impact TAHE's financial model. The decision to book the benefits in the Budget early committed the involved agencies to implement a solution that justified the 2015–16 Budget impacts, irrespective of the challenges that arose. 

TAHE's financial structure requires circular government investment to work

For the NSW Government to continue to treat its investment in TAHE as an equity contribution, rather than an expense to the Budget, there must be a reasonable expectation that TAHE will generate a sufficient rate of return as required by the Government Finance Statistics (GFS) framework. In doing so, it needs to recover a revaluation loss created by a $20.3 billion reduction in the value of its assets which was incurred in its first full year of operation. This loss occurred as a result of a revaluation of TAHE's assets when RailCorp (a not-for profit entity) became TAHE (a for-profit commercial entity) – and is discussed further in the 'Key findings' below.

TAHE generates a small portion of its income from transactions with the private sector but, as noted in our report 'State Finances 2021', TAHE receives the majority of its revenue (more than 80%) from access and licence fee agreements with Sydney Trains and NSW Trains. Both of these entities are funded by grants (a Budget expense) to TfNSW from the GGS Budget.

Based on Treasury’s correspondence with the ABS in 2015, TAHE was initially expected to pay a return on equity of 7% in 2016–17. The assumption of a 7% return persisted through to 2018, after the legislation enabling the establishment of TAHE was passed by Parliament. However, when the initial access and licence fees were agreed on 1 July 2020, this figure had been revised to an expected rate of return of 1.5% excluding the revaluation loss. This was below the long-term inflation target and did not include the recovery of the revaluation loss – risking the government's ability to treat its investment in TAHE as an equity contribution. Importantly, as TAHE is primarily reliant on fees paid by the state owned rail operators that, in turn, are funded by the GGS Budget (as an expense), the decision to change the returns model from 7% to 1.5% would in its own right have had a positive impact on the GGS Budget. However, the decision to use a 1.5% return would ultimately be problematic as it made it difficult to treat the government's contributions to TAHE as an equity investment, as discussed below.

On 14 December 2021, to avoid a qualified audit opinion, the NSW Government made the decision to increase TAHE's expected rate of return to 2.5%, equal to the Reserve Bank’s long-term inflation target.

In 2021-22, TAHE needed to start charging rail operators higher access and licence fees in order to generate a return of 2.5%, so as to support the government's treatment of its investment in TAHE as an equity contribution in the GGS Budget. This meant the government needed to provide additional grant (expense) funding to the state owned rail operators so they could pay the increased access and licence fees to TAHE. Based on current projections, TAHE is not expected to recover the revaluation loss until 2046.

There remains a risk that TAHE will not be able to generate a sufficient return on the NSW Government's investment without relying on increased funding to state owned rail operators so that they can in turn pay the higher access and licence fees. TAHE's ability to generate returns on government investment from other sources are uncertain and may not be achievable or sustainable. Current modelling highlights that TAHE remains largely reliant, through to 2046, on increasing fees (which are assumed to increase at 2.5% per annum from 2031 onwards when the current 10 year contracts with rail operators expire) paid by the state owned rail operators that remain principally reliant on GGS Budget grants.

The process of designing and implementing TAHE was not transparent to independent scrutiny

Our report 'State Finances 2021' commented that Treasury did not always provide this Office with information relating to TAHE on a timely basis. Similarly, during this performance audit, there were also multiple instances where auditees were unable to provide documentation regarding key activities in the process to deliver TAHE. Agencies also applied higher sensitivity classifications to large tranches of documents than was justified or required by policy. Of particular concern is the incorrect classification of documents as Cabinet sensitive information. The incorrect or over-classification of documentation as Cabinet sensitive delayed this Office's ability to provide scrutiny or independent assurance.

There was a lack of clarity around the roles and responsibilities of governance structures set up to oversee the design and implementation of TAHE

From 2014, multiple workstreams and advisory committees were established to progress the design and implementation of TAHE. For some of these committees and workstreams, there is limited information on what they were tasked to do and what they achieved. Most had ceased meeting by 2018, before significant work needed to deliver TAHE was completed.

The lack of clarity around the roles and responsibilities of these governance structures reduced opportunities for TfNSW and Treasury to reconcile their differing objectives for TAHE, and resolve key questions earlier in the process.

There was a heavy reliance on consulting firms throughout the process to establish TAHE, and the management of consultant engagements failed to ensure that agencies received independent advice to support objective decision-making

In 2020, Treasury and TfNSW failed to prevent, identify, or adequately manage a conflict of interest when they engaged the same 'Big 4' consulting firm to work on separate TAHE-related projects. Both agencies used the firm's work to further their respective views with regard to the financial implications of TAHE's operating model. At this time those views were still unreconciled.

Treasury engaged the firm to provide a fiscal risk management strategy and advice on the impact of changes to accounting standards. TfNSW engaged the same firm to develop operating and financial models for TAHE, which raised concerns regarding the viability of TAHE. Disputes arose around the findings of these reports. Treasury disagreed with some of the outcomes of the work commissioned by TfNSW, relating to accounting treatment and fiscal advice.

The management of this conflict (real or perceived) was left to the 'Big 4' consulting firm when it was more appropriate for it to be managed by Treasury and TfNSW. If these agencies had communicated more effectively, used available governance structures consistently, and shared information openly about their use of the firm and the nature of their respective engagements, these disputes might have been avoided. This issue, coupled with deficiencies in procurement by both agencies, reflected and further perpetuated the lack of cohesion in the design and implementation of TAHE.

More broadly, over the period 2014 – 2021, 16 separate consulting firms were employed to work on 36 contracts, valued at over $22.56 million, relating to TAHE ranging from accounting and legal advice, project management, and the provision of administrative support and secretariat services.

Consultants are legitimately used by agencies to provide advice on how to achieve the outcomes determined by government, including advising agencies on the risks and challenges in achieving those outcomes. Similarly, consultants can provide expert knowledge in the service of achieving those outcomes and managing the risks. However, the heavy reliance on consulting firms during the design and implementation of TAHE heightened the risk that agencies were not receiving value for money, were outsourcing tasks that should be performed by the public service, and did not mitigate the risk that the advice received was not objective and impartial. The risk that the role of consultants could have been blurred between providing independent advice to government on options and facilitating a pre-determined outcome was not effectively treated or mitigated. This risk was amplified because a small number of firms were used repeatedly to provide advice on one topic. The effective procurement and management of consultants is an obligation of government agencies.

Appendix one – Responses from audited agencies, and Audit Office clarification of matters raised in the TAHE formal response 

Appendix two – Classification of government entities 

Appendix three – About the audit 

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #372 - released 24 January 2023

 

Published

Actions for Coordination of the response to COVID-19 (June to November 2021)

Coordination of the response to COVID-19 (June to November 2021)

Premier and Cabinet
Community Services
Health
Justice
Whole of Government
Internal controls and governance
Risk
Service delivery
Shared services and collaboration

What the report is about

This audit assessed the effectiveness of NSW Government agencies’ coordination of the response to COVID-19, with a focus on the Delta variant outbreak in the Dubbo and Fairfield Local Government Areas (LGA) between June and November 2021. We audited five agencies - the Department of Premier and Cabinet, NSW Health, the NSW Police Force, Resilience NSW and the Department of Customer Service.

The audit also considered relevant planning and preparation activities that occurred prior to June 2021 to examine how emergency management and public health responses learned from previous events.

What we found

Prior to Delta, agencies developed capability to respond to COVID-19 related challenges.

However, lessons learned from prior reviews of emergency management arrangements, and from other jurisdictions, had not been implemented when Delta emerged in June 2021. As a result, agencies were not as fully prepared as they could have been to respond to the additional challenges presented by Delta.

Gaps in emergency management plans affected agencies' ability to support individuals, families and businesses impacted by restrictions to movement and gathering such as stay-at-home orders. In LGAs of concern, modest delays of a few days had a significant impact on people, especially those most vulnerable.

On 23 July 2021, the NSW Government established a cross-government coordinating approach, the Delta Microstrategy, which complemented existing emergency management arrangements, improved coordination between NSW Government agencies and led to more effective local responses.

Where possible, advice provided to government was supported by cross-government consultation, up-to-date evidence and insights. Public Health Orders were updated as the response to Delta intensified or to address unintended consequences of previous orders. The frequency of changes hampered agencies' ability to effectively communicate changes to frontline staff and the community in a rapidly evolving situation.

The NSW Government could provide greater transparency and accountability over decisions to apply Public Health Orders during a pandemic.

What we recommended

The audit made seven recommendations intended to improve transparency, accountability and preparedness for future emergency events.

This audit assessed the effectiveness of NSW Government agencies’ coordination (focused on the Department of Premier and Cabinet, NSW Health, the NSW Police Force, Resilience NSW and the Department of Customer Service) of the COVID-19 response in selected Local Government Areas (Fairfield City Council and Dubbo Regional Council) between June and November 2021.

As noted in this report, Resilience NSW was responsible for the coordination of welfare services as part of the emergency management arrangements. On 16 December 2022, the NSW Government abolished Resilience NSW.

During the audited period, Resilience NSW was tasked with supporting the needs of communities subject to stay-at-home orders or stricter restrictions and it provided secretariat support to the State Emergency Management Committee (SEMC). The SEMC was, and remains, responsible for the coordination and oversight of emergency management policy and preparedness.

Our work for this performance audit was completed on 15 November 2022, when we issued the final report to the five audited agencies. While the audit report does not make specific recommendations to Resilience NSW, it does include five recommendations to the State Emergency Management Committee. On 8 December 2022, the then Commissioner of Resilience NSW provided a response to the final report, which we include as it is the formal response from the audited entity at the time the audit was conducted.

The community of New South Wales has experienced significant emergency events during the past three years. COVID-19 first emerged in New South Wales after bushfire and flooding emergencies in 2019–20. The pandemic is now into its third year, and there have been further extreme weather and flooding events during 2021 and 2022.

Lessons taken from the experience of these events are important to informing future responses and reducing future risks to the community from emergencies.

This audit focuses on the NSW Government's response to the COVID-19 pandemic, and in particular, the Delta variant (Delta) that occurred between June and November 2021. The response to the Delta represents six months of heightened challenges for the NSW Government.

Government responses to emergencies are guided by legislation. The State Emergency and Rescue Management Act 1989 (SERM Act) establishes emergency management arrangements in New South Wales and covers:

  • coordination at state, regional and local levels through emergency management committees
  • emergency management plans, supporting plans and functional areas including the State Emergency Management Plan (EMPLAN)
  • operations centres and controllers at state, regional and local levels.

This audit focuses on the activities of five agencies during the audit period:

  • The NSW Police Force led the emergency management response and was responsible for coordinating agencies across government in providing the tactical and operational elements that supported and enhanced the health response to the pandemic. The NSW Police Force also led the compliance response which enforced Public Health Orders and included household checks on those required to isolate at home after testing positive to COVID-19. In some parts of NSW, they were supported by the Australian Defence Force in this role.
  • NSW Health was responsible for leading the health response which coordinated all parts of the health system, initially to prevent, and then to manage, the pandemic.
  • Resilience NSW coordinated welfare services as part of the emergency management arrangements and provided secretariat support to the State Emergency Management Committee (SEMC). The SEMC is responsible for the coordination and oversight of emergency management policy and preparedness. Resilience NSW was also tasked with supporting the needs of communities subject to stay-at-home orders or stricter restrictions.
  • The Department of Customer Service (DCS) was responsible for the statewide strategic communications response.
  • The Department of Premier and Cabinet (DPC) held a key role in providing policy and legal services, as well as supporting the coordination of activity across a range of functional areas and decision-making by our State’s leaders.

This audit assessed the effectiveness of NSW Government agencies’ coordination (focused on the Department of Premier and Cabinet, NSW Health, the NSW Police Force, Resilience NSW and the Department of Customer Service) of the COVID-19 response in selected Local Government Areas (LGA) (Fairfield City Council and Dubbo Regional Council) after June 2021.

The audit investigated whether:

  • government decisions to apply LGA-specific Public Health Orders were supported by effective crisis management governance and planning frameworks
  • agencies effectively coordinated in the communication (and enforcement) of Public Health Orders.

While focusing on the coordination of NSW Government agencies’ response to the Delta variant in June through to November 2021, the audit also considered relevant planning and preparation activities that occurred prior to June 2021 to examine how emergency management and public health responses learned from previous events.

This audit does not assess the effectiveness of other specific COVID-19 responses such as business support. It refers to the preparedness, planning and delivery of these activities in the context of supporting communities in selected LGAs. NSW Health's contribution to the Australian COVID-19 vaccine rollout was also subject to a separate audit titled 'New South Wales COVID-19 vaccine rollout' tabled in NSW Parliament on 7 December 2022. 

This audit is part of a series of audits which have been completed, or are in progress, regarding the New South Wales COVID-19 emergency response. The Audit Office of New South Wales '2022–2025 Annual Work Program' details the ongoing focus our audits will have on providing assurance on the effectiveness of emergency responses.

In this document Aboriginal refers to the First Nations peoples of the land and waters now called Australia, and includes Aboriginal and Torres Strait Islander peoples.

Conclusion

Prior to June 2021, agencies worked effectively together to adapt and refine pre-existing emergency management arrangements to respond to COVID-19. However, lessons learned from prior reviews of emergency management arrangements, and from other jurisdictions, had not been implemented when Delta emerged in June 2021. As a result, agencies were not as fully prepared as they could have been to respond to the additional challenges presented by Delta.

In the period March 2020 to June 2021, the State's Emergency Management (EM) arrangements coordinated the New South Wales emergency response to COVID-19 with support from the Department of Premier and Cabinet (DPC) which led the cross-government COVID-19 Taskforce. NSW Government agencies enhanced the EM arrangements, which until then had typically been activated in response to natural disasters, to meet the specific circumstances of the pandemic.

However, the State Emergency Management Committee (SEMC), supported by Resilience NSW, did not address relevant recommendations arising from the 2020 Bushfires Inquiry before June 2021 and agencies did not always integrate lessons learned from other jurisdictions or scenario training exercises into emergency management plans or strategies before Delta. As a result, deficiencies in the EM arrangements, including representation of vulnerable communities on EM bodies, well-being support for multicultural communities in locked down environments and cross-agency information sharing, persisted when Delta emerged in June 2021.

It should be noted that for the purposes of this audit there is no benchmark, informed by precedent, that articulates what level of preparation would have been sufficient or proportionate. However, the steps required to address these gaps were reasonable and achievable, and the failure to do so meant that agencies were not as fully prepared as they could have been for the scale and escalation of Delta’s spread across the State.

The Delta Microstrategy complemented the EM arrangements to support greater coordination and agencies are working to improve their capability for future events

The Delta Microstrategy (the Microstrategy) led to innovations in information sharing and collaboration across the public service. Agencies involved in the response have completed, or are completing, reviews of their contribution to the response. That said, none of these reviews includes a focus on whole-of-government coordination.

On 23 July 2021, the NSW Government approved the establishment of the Microstrategy to respond to the additional challenges presented by Delta including the need to support communities most impacted by restrictions to movement and gathering in the LGAs of concern. An extensive range of government agencies were represented across eight Microstrategy workstreams, which coordinated with the existing EM arrangements to deliver targeted strategies to communities in high-risk locations and improve data and information sharing across government. This enhanced the public health, compliance, income and food support, communications and community engagement aspects of the response.

Agencies also leveraged learnings from early weeks of the Delta wave and were able to replicate those lessons in other locations. The use of pre-staging hubs in Fairfield to support food and personal hamper distribution was used a month later in Dubbo which acted as a central hub for more remote parts of the State.

Emergency management plans did not enable government to respond immediately to support vulnerable communities in high-risk LGAs or regional NSW

There are gaps in the emergency management plans relating to the support for individuals, families and businesses impacted by the stay-at-home orders and other restrictions to movement and gathering. These gaps affected agencies' ability to respond immediately when the need arose during Delta.

Emergency management plans and supporting instruments did not include provision for immediate relief for households, which meant arrangements for isolation income support and food security measures had to be designed in the early stages of Delta before it could be approved and deployed.

There were delays – sometimes only days, on occasion, weeks - in providing support to affected communities. In particular, there were delays to the provision of income support and in scaling up efforts to coordinate food and grocery hampers to households in isolation. In LGAs of concern, modest delays of a few days had a significant impact on people, especially those most vulnerable.

Although government issued stricter restrictions for workers in the Fairfield LGA on 14 July 2021, it only approved targeted income support for people in LGAs of concern on 16 August 2021.

Overall, agencies coordinated effectively to provide advice to government but there are opportunities to learn lessons to improve preparedness for future events

Agencies coordinated in providing advice to government. The advice was supported by timely public health information, although this was in the context of a pandemic, where data and information about the virus and its variants was changing regularly. However, agencies did not always consider the impact on key industries or supply chains when they provided advice to government, which meant that Public Health Orders would sometimes need to be corrected.

Public Health Orders were also updated as the response to Delta intensified or to address unintended consequences of previous orders. The frequency of changes hampered agencies' ability to effectively communicate changes to frontline staff and the community in a rapidly evolving situation.

The audit identified several occasions where there were delays, ranging from three to 21 days, between the provision of advice to government and subsequent decision-making (which we have not detailed due to the confidentiality of Cabinet deliberations). Agency officers advised of instances where they were not provided sufficient notice of changes to Public Health Orders to organise local infrastructure (such as traffic support for testing clinics) to support compliance with new requirements.

The COVID-19 pandemic arrived in Australia in late January 2020 as the bushfire and localised flooding emergencies were in their final stages. Between 2020 and mid-2021, agencies responded to the initial variants of COVID-19, managed a border closure with Victoria that lasted nearly four months and dealt with localised ‘flare-ups’ that required postcode-based restrictions on mobility in northern parts of Sydney and regional New South Wales. During this period, New South Wales had the opportunity to learn from events in Victoria which imposed strict restrictions on mobility across the State and the growing emergence of the Delta variant (Delta) across the Asia Pacific.

This section of the report assesses how emergency management and public health responses adapted to these lessons and determined preparedness for, and responses to, widespread community transmission of Delta in New South Wales.

The previous chapter discusses how agencies had refined the existing emergency management arrangements to suit the needs of a pandemic and describes some gaps that were not addressed. This chapter explores the first month of Delta (mid-June to mid-July 2021). It explores the areas where agencies were prepared and responses in place for the outbreak. It also discusses the impact of the gaps that were not addressed in the period prior to Delta and other issues that emerged.

NSW Health provided advice on the removal of restrictions based on up-to-date advice

The NSW Government discussed the gradual process for removing restrictions using the Doherty Institute modelling provided to National Cabinet on 10 August 2021. NSW Health highlighted the importance of maintaining a level of public health and safety measure bundles to further suppress case numbers. This was based on additional modelling from the Doherty Institute.

The Department of Regional NSW led discussion and planning around reopening with a range of proposal through August and September 2021. The Department of Premier and Cabinet and NSW Health jointly developed a paper to provide options on the restrictions when the State reached a level of 70% double dose vaccinations.

The roadmap to reopening was originally published on 9 September 2021. However, by 11 October 2021, the restrictions were relaxed when the 70% double dose threshold was reached to allow:

  • up to ten fully vaccinated visitors to a home (increased from five)
  • up to 30 fully vaccinated people attending outdoor gatherings (increased from 20)
  • weddings and funerals limits increased to 100 people (from 50)
  • the reopening of indoor pools for training, exercise and learning purposes only.

On the same day, the NSW Government announced further relaxation of restrictions once the 80% double dose threshold was reached. These restrictions were further relaxed on 8 November 2021. This included the removal of capacity restrictions to the number of visitors to a private residence, indoor pools to reopen for all purposes and density limits of one person for every two square metres, dancing allowed in nightclubs and 100% capacity in major stadia.

The NSW Government allowed workers in regional areas who received one vaccination dose to return to their workplace from 11 October 2021.

The Premier extended the date of easing of restrictions for unvaccinated people aged over 16 from 1 December to 15 December 2021.

Many agencies have undertaken reviews of their response to the Delta outbreak but a whole-of-government review has yet to be conducted

Various agencies and entities associated with the response to the Delta outbreak conducted after-action review processes. These processes assessed the achievements delivered, lessons learned and opportunities for improvement. However, a whole-of-government level review has not been conducted. This limits the New South Wales public service's ability to improve how it coordinates responses in future emergencies.

The agencies/entities that conducted reviews included:

  • South West Metropolitan region, Western NSW region, Fairfield Local Emergency Management Committee (LEMC), Dubbo Local Emergency Operations Controller (LEOCON), which were collated centrally by the State Emergency Operations Centre (SEOC)
  • Aboriginal Affairs NSW assessed representation and relevance of the emergency management arrangements for Aboriginal communities following the 2019 bushfires
  • Resilience NSW developed case studies to capture improved practice with regard to food security and supply chains
  • a community support and empowerment-focused after-action review undertaken by the Pillar 5 workstream of the Microstrategy.

Key lessons collated from the after-action reviews include:

  • the impact of variation in capability across agencies on the management of key aspects of the response including welfare support and logistics
  • issues with boundary differences between NSW Police Force regions, local government areas (LGA and local health districts (LHD) caused issues in delivering and coordinating services in an emergency situation 
  • the need to improve relationships between state and local Government outside of acute emergency responses to improve service delivery 
  • issues arising from impediments to information sharing between agencies and jurisdictions, such as:
    • timeliness and accuracy of data used to direct compliance activities
    • the impact of insufficient advance notice on changes to Public Health Orders
    • timely access to data across public sector agencies and other jurisdictions to inform decision-making, analysis and communications
    • gaps in data around ethnicity, geolocation of recent positive cases and infection/vaccination rates in Aboriginal communities.
  • the lack of Aboriginal community representation on many LEMCs
  • compared with the response to COVID-19 in 2020, improved coordination of communications with Culturally and Linguistically Diverse (CALD) populations with a reduction in overlapping messages and over-communication
  • improved attendance from agency representatives in LEMCs, and regional emergency operations centres (REOC) to improve interagency communications, planning, capability development and community engagement issues
  • deficiencies in succession planning and fatigue management practices
  • the potential for REOC Welfare/Well-being subgroups to be included as part of the wider efforts to community needs during emergencies.

NSW Health commenced a whole of system review of its COVID-19 response in May 2022. At the time of writing, the completion due date for the debrief is 7 November 2022. This debrief is expected to explore:

  • governance
  • engagement 
  • innovation and technology 
  • community impact 
  • workforce impact
  • system impact and performance.

NSW Health is also undertaking a parallel Intra-Action Review that is focused on the public health aspects of the response with finalisation estimated for the end of November 2022. At the time of completing this performance audit report, NSW Health had not finalised these reviews and, as a result, we cannot validate their findings against our own observations.

Recent inquiries are likely to impact the governance of emergency management in New South Wales

In March 2022, the NSW Government established an independent inquiry to examine and report on the causes of, preparedness for, response to and recovery from the 2022 floods. The Flood Inquiry report made 28 recommendations, which the NSW Government supported in full or in principle. Some of the recommendations relate directly to the governance and leadership of emergency management arrangements in New South Wales. 

The State Emergency Management Committee (SEMC) will likely be involved in, and impacted by, the recommendations arising from the Flood Inquiry with potential changes to its membership and reshaping of functional areas and agencies. At the same time, the SEMC may have a role in overseeing the changes that emerge from the SEOC consolidated after-action reviews. This can also extend to ensuring local and regional bodies have incorporated the required actions. There is a risk that the recommendations from the pandemic-based after-action reviews may not be considered due to the priority of action resulting from the Flood Inquiry.

Furthermore, there is potential for the SEMC to work with NSW Health during its system-wide review. Such an approach is likely to improve preparedness for future events.

Appendix one – Response from agencies

Appendix two – Chronology 2020–2021

Appendix three – About the audit

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #371 - released 20 December 2022

Published

Actions for Integrity of grant program administration

Integrity of grant program administration

Local Government
Premier and Cabinet
Internal controls and governance
Management and administration

What the report is about

This report assessed the integrity of the assessment and approval processes for two grant programs:

  • Stronger Communities Fund Round 2 (tied grants round), which was administered by the former Office of Local Government (OLG) and provided $252 million to newly amalgamated councils and other councils that had been subject to a merger proposal during 2017–18 and 2018–19.
  • Regional Cultural Fund, which was administered by Create NSW (now within the Department of Premier and Cabinet) and awarded $100 million for cultural projects in regional NSW.

What we found

The assessment and approval process for Round 2 of the Stronger Communities Fund lacked integrity. The government decided to prioritise funds for councils that had worked constructively with the government through the 2016 merger process. 

However, this information was not included in the program guidelines. The program guidelines were not published and did not contain details of selection and assessment processes. Councils and projects were instead identified by the former Premier, Deputy Premier and Minister for Local Government and communicated to OLG with little or no information about the basis for the council or project selection. There was no merit assessment of identified projects. This process resulted in 96 per cent of funds allocated to coalition state seats.

The assessment process that Create NSW used for the Regional Cultural Fund was robust and produced transparent and defensible recommendations to the minister. However, the former Minister for the Arts, in consultation with the former Deputy Premier, did not follow the recommendations of the independent assessment panel in 22 per cent of cases. Reasons for these changes were not documented by Create NSW.

What we recommended

The Department of Premier and Cabinet should develop a model for grant administration that must be used for all grant programs administered in NSW that:

  • is based on ethical principles such as impartiality, equity and transparency 
  • ensures assessments and decisions can be made against clear eligibility criteria
  • ensures accountability for decisions and actions of all those who are involved in the program 
  • includes minimum mandatory administration and documentation standards
  • requires any ministerial override of recommendations to be documented. 

The Department of Planning and Environment should ensure that guidelines prepared for all grant programs are published and include a governance framework that includes accountabilities and key assessment steps.

Fast facts    

Stronger Communities Fund Round 2

  • $252m allocated to 24 councils    
  • 96% allocated to council projects in coalition state seats
  • 36% of the funding ($90m) was allocated to a single council
  • $8m in projects identified before the program guidelines were finalised

Regional Cultural Fund

  • 405 applications received across three funding rounds
  • $99m awarded for 147 cultural projects in regional NSW 
  • 22% panel recommendations not followed by ministers  
  • $9.3m awarded to projects not recommended by panel

Grants are frequently used by the state government to deliver funds to councils and community organisations to provide infrastructure and services important to their local communities. Grant programs are administered by NSW Government agencies in line with priorities and objectives set by the government.

Guidance for agencies administering grant programs is available in the Good Practice Guide to Grants Administration (the 'DPC Guide') which is maintained by the Department of Premier and Cabinet (DPC). In addition to this guide, some agencies maintain their own grant program policies and guidelines. More broadly, public servants are required to comply with financial legislation and the Government Sector Employment Act 2013 which include requirements to be transparent, fiscally responsible and focus on the efficient, effective and prudent use of resources.

The objective of this performance audit is to assess the integrity of the assessment and approval processes for NSW Government grant programs.

The audit focuses on two grant programs, both administered during the 2017–18 and 2018–19 financial years. The Stronger Communities Fund (round two tied grants round) was administered by the former Office of Local Government (OLG), now referred to as the Local Government Group within the Department of Planning and Environment (DPE). The fund awarded $252 million to 24 councils that had amalgamated in 2016 or which had been the subject of a merger proposal. The Regional Cultural Fund was administered by Create NSW, now within the Department of Premier and Cabinet (DPC). The fund awarded $100 million to organisations in regional New South Wales to support the development of cultural infrastructure in regional areas.

The audit comments upon the role played by the then Premier, Deputy Premier, ministers and their staff in the audited grant programs to provide context. The Audit Office of NSW cannot compel those individuals to participate in the audit or provide documents. In all cases, reference to the Premier, Deputy Premier, ministers, MPs and their staff refers to the individuals who were in those roles at the time the grant programs were administered unless otherwise noted.

Conclusion

Stronger Communities Fund

The assessment and approval processes for round two of the Stronger Communities Fund (SCF) lacked integrity. The program guidelines developed by the Office of Local Government (OLG) were deficient in a number of aspects and were not used to guide the selection of councils or projects for funding. Of the 55 councils that met the eligibility criteria in the guidelines, 24 received funding. Ninety-six per cent of available SCF funding was allocated to projects in coalition-held state government electorates. Funding for councils was determined by the then Premier, Deputy Premier and Minister for Local Government and communicated by their staff through emails to OLG with little or no information about the basis for the council or project selection. OLG administered payment of these funds without questioning or recording the basis for selection. For the 22 councils where funding allocations were determined by the former Premier and Deputy Premier, the only record of their approval is a series of emails from their staff. The exclusion of key information from the program guidelines and the lack of formality in approving 22 of the 24 funding allocations prevent accountability and transparency over the government's approach to selecting councils for funding.

In July 2017, the NSW Government established priorities for how the remaining SCF funds should be used. The funds were to be used to cover costs associated with councils' legal action relating to amalgamation, to reimburse costs incurred by councils that were unable to merge but had participated constructively in the merger process, and to fund community initiatives in council areas that had amalgamated in 2016.

OLG developed the initial grant program guidelines between July 2017 and September 2017 in consultation with the then Premier, Deputy Premier and Minister for Local Government and their staff. These were then revised in June 2018. Neither version of the guidelines made reference to the type of projects that were to be prioritised and did not set out how the funds should be administered in accordance with these priorities. The guidelines also did not include information about how councils and projects would be selected and made no provision for an assessment of identified projects against the criteria for eligible projects in the guidelines. OLG did not publish the guidelines and the process adopted by the Premier, Deputy Premier and Minister for Local Government to select projects did not reference the criteria for eligible projects in the guidelines. The selection of councils and funded projects resulted in 96 per cent of available funding being allocated to projects in coalition-held state government electorates.

The Minister for Local Government was responsible for distributing the SCF funds but only approved funding for projects at two of 24 councils, both paid in November 2017. Projects at the other 22 councils were identified by the former Premier and Deputy Premier between June 2018 and June 2019 in consultation with other coalition Members of Parliament and communicated to OLG through emails from Premier and Deputy Premier's staff. When making payments in response to email instructions from staff in the offices of the Premier, Deputy Premier and Minister for Local Government, OLG did not seek to ensure that identified projects were consistent with the guidelines and made payments to selected councils with little or no information to justify them. With the exception of the two funding allocations approved by the then Minister for Local Government, OLG also did not ensure that formal records were in place to document approval for the remaining 22 funding allocations.

Regional Cultural Fund

The assessment process that Create NSW used for the Regional Cultural Fund was robust and produced transparent and defensible recommendations to the then Minister for the Arts. However, the integrity of the approval process for funding allocations was compromised because the minister, in consultation with the then Deputy Premier, did not follow the recommendations of the independent assessment panel in multiple cases and the reasons for making changes were not documented by the minister's office or Create NSW.

All projects that received funding were assessed by Create NSW as eligible for funding under the program. An independent assessment panel assessed applications against the program objective and criteria. This process was designed in line with good practice in grants administration and was implemented consistently. The then Minister for the Arts, in consultation with the former Deputy Premier, did not follow the panel's recommendations for 22 per cent, or more than one in five, of the applications assessed for funding. Thirty-four applications that were recommended by the independent panel did not receive any funding. In the second funding round, seven of the top ten ranked applications were not funded.

The Minister for the Arts approved funding for 22 applications that were not recommended by the independent panel. This resulted in around $9.3 million being awarded to applicants that were not rated highest by the independent panel, including six applicants that received grants of $500,000 or more. Most did not meet one or more assessment criteria and received low ratings.

The then minister did not provide reasons for not approving funding in line with the recommendations of the panel. This did not breach any legislation or guidelines in New South Wales, but it compromised Create NSW's ability to demonstrate integrity and value for money in the RCF approval process. It creates a clear perception that factors other than the merits of the projects influenced funding decisions.

Create NSW's administration of the Regional Cultural Fund was based on relevant legislative requirements and good practice guidance. The objectives of the program were defined clearly and the guidelines and criteria were consistent with the program objectives. The governance and probity framework was appropriate for the size and nature of the program.

Appendix one – Response from agencies

Appendix two – List of funded projects - Stronger Communities Fund Round 2

Appendix three – List of funded projects - Regional Cultural Fund

Appendix four – About the audit

Appendix five – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #361 - released 8 February 2022.

Published

Actions for Managing cyber risks

Managing cyber risks

Whole of Government
Transport
Cyber security
Information technology
Internal controls and governance
Procurement
Risk

What the report is about

This audit assessed how effectively Transport for NSW (TfNSW) and Sydney Trains identify and manage their cyber security risks.

The NSW Cyber Security Policy (CSP) sets out 25 mandatory requirements for agencies, including implementing the Australian Cyber Security Centre’s Essential 8 strategies to mitigate cyber security incidents, and identifying the agency’s most vital systems, their ‘crown jewels’. 

The audited agencies have requested that we do not disclose detail of the significant vulnerabilities detected during the audit, as these vulnerabilities are not yet remediated. We provided a detailed report to the agencies in December 2020 outlining significant issues identified in the audit. We have conceded to the agencies' request but it is disappointing that transparency to the Parliament and the public on issues that potentially directly affect them needs to be limited in this way.

What we found

TfNSW and Sydney Trains are not effectively managing their cyber security risks.

Both agencies have assessed their cyber security risks as unacceptably high and both agencies had not identified all of the risks we detected during this audit – some of which are significant.

Both agencies have cyber security plans in place that aim to address cyber security risks. TfNSW and Sydney Trains have combined this into the Transport Cyber Defence Rolling Program, part of the Cyber Defence Portfolio (CDP). 

However, neither agency has reached its target ratings for the CSP and the Essential 8 and maturity is low in relation to significant risks and vulnerabilities exposed.

Further, neither agency is fostering a culture where cyber security risk management is an important and valued aspect of decision-making.

TfNSW is not implementing cyber security training effectively across the cluster with only 7.2% of staff having completed basic cyber security training.

What we recommended

TfNSW and Sydney Trains should:

  • develop and implement a plan to uplift the Essential 8 controls to the agency's target state
  • as a matter of priority, address the vulnerabilities identified as part of this audit and previously described in a detailed Audit Office report provided to both agencies
  • ensure cyber security risk reporting to executives and the Audit and Risk Committee
  • collect supporting information for the CSP self assessments 
  • classify all information and systems according to importance and integrate this with the crown jewels identification process
  • require more rigorous analysis to re-prioritise CDP funding 
  • increase uptake of cyber security training.

TfNSW should assess the appropriateness of its target rating for each of the CSP mandatory requirements.

Department of Customer Service should:

  • clarify the requirement for the CSP reporting to apply to all systems
  • require agencies to report the target level of maturity for each mandatory requirement.

Fast facts

  • $42m Total value of the Transport Cyber Defence Rolling Program over three years.
  • 7.2% Percentage of staff across the Transport cluster who had completed introductory cyber security training

Response to requests by audited agencies to remove information from this report

In preparing this audit report, I have considered how best to balance the need to support public accountability and transparency with the need to avoid revealing information that could pose additional risk to agencies’ systems. This has involved an assessment of the appropriate level of detail to include in the report about the cyber security vulnerabilities identified in this audit.

In making this assessment, the audit team consulted with Transport for NSW (TfNSW), Sydney Trains, and Cyber Security NSW to identify content which could potentially pose a threat to the agencies’ cyber security.

In December 2020, my office also provided TfNSW and Sydney Trains with a detailed report of many of the significant vulnerabilities identified in this audit, to enable the agencies to address the cyber security risks identified. The detailed report was produced as a result of a 'red team' exercise, which was conducted with both agencies' knowledge and consent. The scope of this exercise reflected the significant input provided by both agencies. More information on this exercise is at page 12 of this report.

TfNSW and Sydney Trains have advised that in the six months from December 2020 and at the time of tabling this audit report, they have not yet remediated all the vulnerabilities identified. As a result, they, along with Cyber Security NSW, have requested that we not disclose all information contained in this audit report to reduce the likelihood of an attack on their systems and resulting harm to the community. I have conceded to this request because the vulnerabilities identified have not yet been remediated and leave the agencies exposed to significant risk.

It should be stressed that the risks identified in the detailed report exist due to the continued presence of these previously identified vulnerabilities, rather than due to their potential publication. The audited agencies, alone, are accountable for remediating these vulnerabilities and addressing the risks they pose.

It is disappointing that transparency to the Parliament and the public on issues that potentially directly affect them needs to be limited in this way.

That said, the conclusions drawn in this report are significant in terms of risk and remain valid, and the recommendations should be acted upon with urgency.

Cyber security risk is an increasing area of concern for governments in Australia and around the world. In recent years, there have been a number of high-profile cyber security attacks on government entities in Australia, including in New South Wales. Malicious cyber activity in Australia is increasing in frequency, scale, and sophistication. The Audit Office of New South Wales is responding to these risks with a program of audits in this area, which aim to identify the effectiveness of particular agencies in managing cyber risks, as well as their compliance with relevant policy.

Cyber Security NSW, part of the Department of Customer Service (DCS) releases and manages the NSW Cyber Security Policy (CSP). The CSP sets out 25 mandatory requirements for agencies, including making it mandatory for agencies to implement the Australian Cyber Security Centre Essential 8 Strategies to Mitigate Cyber Security Incidents (the Essential 8). The Essential 8 are key controls which serve as a baseline set of protections which agencies can put in place to make it more difficult for adversaries to compromise a system. Agencies are required to self-assess their maturity against the CSP and the Essential 8, and report that assessment to Cyber Security NSW annually.

The CSP makes agencies responsible for identifying and managing their cyber security risks. The CSP sets out responsibilities and governance regarding risk identification, including making agencies responsible for identifying their 'crown jewels', the agency's most valuable and operationally vital systems. Once these risks are identified, agencies are responsible for developing a cyber security plan to mitigate those risks.

This audit focussed on two agencies: Transport for NSW (TfNSW) and Sydney Trains. TfNSW is the lead agency for the Transport cluster and provides a number of IT services to the entire cluster, including Sydney Trains. This audit focussed on the activities of TfNSW's Transport IT function, which is responsible for providing cyber security across the cluster, as well as directly overseeing four of TfNSW's crown jewels. Sydney Trains is one of the agencies in the Transport cluster. While it receives some services from TfNSW, it is also responsible for implementing its own IT controls, as well as controls to protect its Operational Technology (OT) environment. This OT environment includes systems which are necessary for the operation and safety of the train network.

To test the mitigations in place and the effectiveness of controls, this audit involved a 'red team' simulated exercise. A red team involves authorised attackers seeking to achieve certain objectives within the target's environment. The red team simulated a determined external cyber threat actor seeking to gain access to TfNSW's systems. The red team also sought to test the physical security of some Sydney Trains' sites relevant to the agency's cyber security. The red team exercise was conducted with the knowledge of TfNSW and Sydney Trains.

This audit included the Department of Customer Service as an auditee, as they have ownership of the CSP through Cyber Security NSW. This audit did not examine the management of cyber risk in the Department of Customer Service.

This audit assessed how effectively selected agencies identify and manage their cyber security risks. The audit assessed this with the following criteria:

  • Are agencies effectively identifying and planning for their cyber security risks?
  • Are agencies effectively managing their cyber security risks?

Following this in-depth portfolio assessment, the Auditor-General for NSW will also table a report on NSW agencies' compliance with the CSP in the first quarter of 2021–22.

Conclusion

Transport for NSW and Sydney Trains are not effectively managing their cyber security risks. Significant weaknesses exist in their cyber security controls, and both agencies have assessed that their cyber risks are unacceptably high. Neither agency has reached its Essential 8 or Cyber Security Policy target levels. This low Essential 8 maturity exposes both agencies to significant risk. Both agencies are implementing cyber security plans to address identified cyber security risks.
This audit identified other weaknesses, such as low numbers of staff receiving basic cyber security awareness training. Cyber security training is important for building and supporting a cyber security culture. Not all of the weaknesses identified in this audit had previously been identified by the agencies, indicating that their cyber security risk identification is only partially effective.
Agency executives do not receive regular detailed information about cyber risks and how they are being managed, such as information on mitigations in place and the effectiveness of controls for cyber risk. As a result, neither agency is fostering a culture where cyber security risk management is an important and valued aspect of executive decision-making.
TfNSW and Sydney Trains are partially effective at identifying their cyber security risks and both agencies have cyber security plans in place

Both agencies regularly carry out risk assessments and have identified key cyber security risks, including risks that impact on the agencies' crown jewels. These risks have been incorporated into the overall enterprise risk process. However, neither agency regularly reports detailed cyber risk information to agency executives to adequately inform them about cyber risk. The Cyber Security Policy (CSP) requires agencies to foster a culture where cyber security risk management is an important and valued aspect of decision-making. By not informing agency executives in this way, TfNSW and Sydney Trains are not fulfilling this requirement.

Agencies' cyber security risk assessment processes are not sufficiently comprehensive to identify all potential risks. Not all of the weaknesses identified in this audit had previously been identified by the agencies.

To address identified cyber security risks, both agencies have received funding approval to implement cyber security plans. TfNSW first received approval for its cyber security plan in 2017. Sydney Trains received approval for its cyber security plan in February 2020. In 2020–21 TfNSW and Sydney Trains combined their plans into the Transport Cyber Defence Rolling Program business case valued at $42.0 million over three years. This is governed as part of a broader Cyber Defence Portfolio (CDP). The CDP largely takes a risk-based approach to annual funding. The Cyber Defence Portfolio Steering Committee and Board can re-allocate funds from an approved project to a different project. This re-allocation process could be improved by making it more risk-based.

TfNSW and Sydney Trains are not effectively managing their cyber security risks

Neither agency has fully mitigated its cyber security risks. These risks are significant. Neither TfNSW nor Sydney Trains have reduced their cyber risk to levels acceptable to the agencies. Both agencies have set a risk tolerance for cyber security risks, and the identified enterprise-level cyber security risks remain above this rating. Both agencies' self-attested maturity against the Essential 8 remains low in comparison to the agencies' target levels, and in relation to the significant risks and vulnerabilities that are exposed. Little progress was made against the Essential 8 in 2020.

Neither agency has reached its target levels of maturity for the CSP mandatory requirements. Not reaching the target rating of the CSP mandatory requirements risks information and systems being managed inconsistently or not in alignment with good governance principles. The Transport Cyber Defence Rolling Program has a KPI to achieve a target rating of three for all CSP requirements where business appropriate. TfNSW considers this target rating to be its target for all the CSP requirements. However TfNSW has not undertaken analysis to determine whether this target is appropriate to its business.

The CSP makes agencies accountable for the cyber risks of their ICT service providers. While both agencies usually included their cyber security expectations in contracts with third-party suppliers, neither agency was routinely conducting audits to ensure that these expectations were being met.

The CSP requires agencies to make staff aware of cyber security risks and deliver cyber security training. TfNSW is responsible for delivering cyber security training across the Transport cluster, including in Sydney Trains. TfNSW was not effectively delivering cyber security training across the cluster because training was not mandatory for all staff at the time of the audit and completion rates among those staff assigned the training was low. As such, only 7.2 per cent of staff across the Transport cluster had completed introductory cyber security training as at January 2021.

Agencies have assessed their cyber risks as being above acceptable levels

An agency's risk tolerance is the amount of risk which the agency will accept or tolerate without developing further strategies to modify the level of risk. Risks that are within an agency's risk tolerance may not require further mitigation and may be deemed acceptable, while risks which are above the agency's risk tolerance likely require further mitigation before they become acceptable to the agency.

Both agencies have defined their risk tolerance and have identified risks which are above this level, indicating that they are unacceptable to the agency. TfNSW has defined 'very high' risks as generally intolerable and 'high' risks as undesirable. Its risk tolerance is 'medium'. Sydney Trains has four classifications of risk: A, B, C and D. A and B risks are deemed 'unacceptable' and 'undesirable' respectively, while C risks are considered 'tolerable'. This aligns with the TfNSW definition of a medium risk tolerance.

Transport IT reported five enterprise-level cyber security risks through its enterprise risk reporting tool in September 2020, all of which relate to cyber security or have causes relating to cyber security. These risks are in aggregate form, rather than relating to specific vulnerabilities. At the time of the audit, one of these risks was rated as very high and the other four rated as high. At this time, Transport IT had identified a further seven divisional-level risks which were above the agency’s risk tolerance.

Similarly, Sydney Trains has identified one main cyber security risk in its IT enterprise-level risk register and another with a potential cyber cause. Both of these IT risks are deemed to have a residual risk of ‘unacceptable’.

Similarly, two cyber-related OT risks have been determined to be above the agency's risk tolerance. One risk is rated as 'unacceptable'. Another risk, while not entirely cyber rated, is rated 'undesirable' and is deemed to have some causes which may stem from a cyber-attack.

Agencies have assessed their current cyber risk mitigations as requiring improvement

In addition to the risk ratings stated above, at the time of the audit neither agency believed that its controls were operating effectively. Transport IT had rated the control environments for its cyber security enterprise risks as 'requires improvement'. Mitigations were listed in the risk register for these risks but, in some cases, they were unlikely to reduce the risk to the target state or by the target date. For example, one risk had actions listed as 'under review' and no further treatment actions listed, but a due date of July 2021, while another risk was being treated by the CDP with a due date of July 2021. The CDP identified in May 2020 that while the average risk identified as part of that program will be reduced to a medium level by this date, ten high risks will still remain. Given the delays in the program, this number may be higher. As such, it seems unlikely that the enterprise risk will be reduced to below a 'high' level by July 2021.

Sydney Trains’ IT and OT risk registers cross-reference controls and mitigations against the causes and consequences. The IT cyber security risk identified in the register had causes with no mitigations designed for them. Further, some of these causes did not have future mitigations designed for them. This risk also had controls in place which are identified as partially effective. For the unacceptable OT risk noted above, while there was a control designed for each of the potential causes, Sydney Trains had identified all of the controls in place as either partially effective or ineffective. This indicates that Sydney Trains was not effectively mitigating the causes of its cyber risks and, even where it had designed controls or mitigations, these were not always implemented to fully mitigate the cause of the risk.

Additional information on gaps in cyber mitigations which were exposed in the course of this audit has been detailed to both agencies. The Foreword of this report provides information about why this detail is not included here.

Essential 8 maturity is low across TfNSW and Sydney Trains and little progress was made in 2020

CSP mandatory requirement 3.2 states that agencies must implement the ACSC Essential 8. Agencies must also rate themselves against each of the Essential 8 on a maturity scale from zero to three and report this to Cyber Security NSW. A full list of the Essential 8 can be found in Exhibit 1. Both agencies have a low level of maturity against the Essential 8 not just in comparison to the targets they have set, but also in relation to the risks and vulnerabilities exposed. Both agencies have set target maturity ratings for the Essential 8 but none of the Essential 8 ratings across either agency are currently implemented to this level. Having a low level of Essential 8 maturity exposes both agencies to significant risks and vulnerabilities. Little progress was made between the 2019 and 2020 attestation periods.

Transport IT has set a target rating of three across all of the Essential 8. Sydney Trains has set a target rating of three for its IT systems. Sydney Trains had an interim target of two for its OT systems in 2020 and advised that this has since increased to three. It should be noted that not all the Essential 8 are applicable to OT systems.

None of the Essential 8 ratings across either agency are currently implemented to the target levels. Given that the Essential 8 provide the controls which are most commonly able to deter cyber-attacks, having maturity at a low level potentially exposes agencies to a cyber security attack.

Some work is underway across both TfNSW and Sydney Trains to improve the Essential 8 control ratings. The CDP provided some resources to the Essential 8 over 2019–20, with uplift focusing on specific systems. The CDP work in 2019 and 2020 relevant to the Essential 8 largely focussed on determining the current state of the Essential 8 and creating a target state roadmap. As a result, there was little improvement between the 2019 and 2020 attestation periods. The CDP has a workstream for the Essential 8 in its FY 2020–21 funding allocation, however as noted above in Exhibit 6 this was delayed as resources were redeployed to Project La Brea. Regardless, work on some specific aspects of the Essential 8 remain part of the 2020–21 CDP allocation, with workstreams allocated to improving three of the Essential 8. In addition, some work from Project La Brea should lead to an improvement in the Essential 8.

Sydney Trains' Cyber Uplift Program included a workstream which had in scope the uplift in the Essential 8 in IT. There were also other workstreams which aimed to improve some of the Essential 8 for OT systems. Work is also ongoing as part of the CDP to uplift these scores in Sydney Trains.

TfNSW and Sydney Trains have not reached their target maturity across the CSP mandatory requirements and TfNSW has not evaluated its cluster-wide target to ensure it is appropriate

Cyber Security NSW allows each agency to determine its target level of maturity for the first 20 CSP mandatory requirements. Agencies can tailor their target levels to their risk profile. Not reaching the target rating of the CSP mandatory requirements risks information and systems being managed inconsistently or not in alignment with good governance principles.

Sydney Trains has set its target level of maturity for IT and OT. All of Sydney Trains' target maturity levels are at least a three (defined), with a target of four (quantitatively managed) for many of the mandatory requirements. While Cyber Security NSW does not currently mandate a minimum level of maturity, in 2019 there was a requirement for each agency to target a minimum level of three.

Sydney Trains has not met its target ratings across the mandatory requirements.

The Transport Cyber Defence Rolling Program has a program KPI to ensure that the entire cluster reaches a minimum maturity level of three against all the CSP requirements by 2023. TfNSW has not reviewed its CSP mandatory requirement targets to determine if a three is desirable for all requirements or if a higher target level may be more appropriate. It is important for senior management to set cyber security objectives as a demonstration of leadership and a commitment to cyber security.

TfNSW has not met its target ratings across the mandatory requirements for its Group IT ISMS, which was the focus of this audit.

Both agencies claimed progress in their implementation of the mandatory requirements between 2019 and 2020. The audit did not seek to verify the self-assessed results from either agency.

Both agencies operate ISMS in line with the CSP

CSP mandatory requirement 3.1 requires agencies to implement an Information Security Management System (ISMS) or Cyber Security Framework (CSF), with scope at least covering systems identified as the agency's ‘crown jewels’. The ISMS or CSF should be compliant with, or modelled on, one or more recognised IT or OT standard. As noted in the introduction, an ISMS ‘consists of the policies, procedures, guidelines, and associated resources and activities, collectively managed by an organisation, in the pursuit of protecting its information assets.’ Both agencies operate an ISMS compliant with the CSP requirement.

As noted in the introduction, TfNSW operates four ISMS. The Transport IT ISMS is certified against ISO27001, the most common standard for ISMS certification. Three of TfNSW’s six crown jewels are managed within this ISMS. The other ISMS are not certified to relevant standards, though TfNSW claims that they align with relevant controls. This is sufficient for the purposes of the CSP.

Sydney Trains operates two ISMS, one for IT and another for OT. Neither of these are certified to relevant ISMS Standards, however there have been conformance reviews of both IT and OT with relevant standards. These ISMS cover all crown jewels in the agency.

There are currently 11 ISMS in operation across the Transport cluster. TfNSW has proposed moving towards a holistic approach to these ISMS, with the CDP Board responsible for governing the available security controls and directing agency IT and OT teams to implement these.

Agencies are not routinely conducting audits of third-party suppliers to ensure compliance with contractual obligations

CSP mandatory requirement 1.5 makes agencies accountable for the cyber risks of their ICT service providers and ensuring that providers comply with the CSP and any other relevant agency security policies. The ACSC has provided advice on what organisations should do when managing third party suppliers of ICT. The ACSC advises that organisations should use contracts to define cyber security expectations and seek assurance to ensure that these contract expectations are being met. While both agencies usually include specific cyber security expectations in contracts, neither is routinely seeking assurance that these expectations are being met.

The NSW Government has mandated the use of the 'Core& One' contract template for low-value IT procurements and the Procure IT contract template for high-value IT procurements. Both of these contracts contain space for the procuring agency to include cyber security controls for the contractor to implement. The Procure IT contract template also includes a right-to-audit clause which allows agencies to receive assurance around the implementation of these controls. TfNSW and Sydney Trains used the mandated contracts for relevant contracts examined as part of this audit.

TfNSW included security controls in all the contracts examined as part of this audit. Compliance with ISO27001 was the most commonly stated security expectation. Of the contracts examined as part of this audit, only one contract did not have a right-to-audit clause. This contract was signed in October 2016. While these clauses are in place, TfNSW rarely conducted these audits on its third-party providers. Of the eight TfNSW contracts examined in detail, only two of these had been audited to confirm compliance with the stated security controls.

Sydney Trains included security controls in all but one of the contracts examined as part of this audit. Sydney Trains did not require contractors to be compliant with ISO27001, but only required compliance with whole-of-government policies. Sydney Trains does not routinely conduct audits of its third-party suppliers, however it did conduct deep-dive risk analyses of its top ten highest risk IT suppliers. This involved a detailed review of both the suppliers' security posture and also the contract underpinning the relationship with the supplier.

The CDP funding for 2020–21 includes a workstream for strategic third-party contract remediation. This funding is to conduct some foundational work which will allow the CDP to make further improvements in future years. While this funding will not address gaps in contract requirements or management across all contracts, this workstream aims to reduce the risks posed by strategic suppliers covering critical assets. Similarly, work is currently underway as part of the CDP to conduct OT risk assessments for key suppliers to Sydney Trains in a similar way to the work undertaken for IT suppliers.

Sydney Trains has risk assessed its third-party suppliers but TfNSW has not done so

It is important to conduct a risk assessment of suppliers to identify high-risk contractors. This allows agencies to identify those contractors who may require additional controls stated in the contract, those who require additional oversight, and also where auditing resources are best targeted.

Sydney Trains has risk assessed all its IT suppliers and, as noted above, has conducted a deep-dive risk analysis of its top ten highest risk suppliers. TfNSW has not undertaken similar analysis of its key suppliers, however it has identified risks attached to each of its strategic suppliers and has documented these. As a result of not risk assessing its suppliers, TfNSW cannot take a targeted approach to its contract management.

TfNSW demonstrated poor records handling relating to the contracts examined as part of this audit

TfNSW was not able to locate one of the contracts requested as part of the audit's sample. Other documentation, such as contract management plans, could not be located for many of the other contracts requested as part of this audit. These poor document handling practices limits TfNSW's ability to effectively oversee service providers and ensure that they are implementing agreed controls. It also limits public transparency on the effectiveness of these controls.

The Transport cluster is not effectively implementing cyber security awareness training

Agencies are responsible for implementing regular cyber security education for all employees and contractors under mandatory requirement 2.1 in the CSP. TfNSW is responsible for delivering this training to the whole Transport cluster, including Sydney Trains. The Transport cluster has basic cyber awareness training available for all staff. TfNSW also offers additional training provided by Cyber Security NSW targeted at executives and executive assistants. While TfNSW has training available to staff, it is not delivering this effectively. TfNSW does not make training mandatory for most staff nor does it require staff to repeat training regularly. Even among those staff who have been assigned the training, completion rates are low, meaning that delivery is not effectively monitored. Cyber security training is important for building and supporting a cyber security culture.

TfNSW is responsible for creating and rolling out all forms of training to agencies within the Transport cluster. Both TfNSW and Sydney Trains have the same mandatory cyber awareness training that is automatically assigned to new starters. At the time of the audit, this training was not mandatory for ongoing staff. TfNSW does make additional cyber security training available to staff who can choose to undertake the training themselves, or can be assigned the training by their manager. All TfNSW cyber security training is delivered via online modules and it is the responsibility of managers to ensure that it is completed.

Cyber security training completion rates for both TfNSW and Sydney Trains are low. Only 13.5 per cent of staff across the Transport cluster had been assigned the Cyber Safety for New Starters training as of January 2021. Although this course is mandatory for new starters, only 53 per cent of staff assigned the Cyber Safety for New Starters training module had completed the course by January 2021. As a result, only 7.2 per cent of staff across the entire Transport cluster had completed this training at that time. In Sydney Trains, less than one per cent of staff had completed this training as at January 2021 and a further 7.6 per cent of staff have completed the 'Cyber Security: Beyond the Basics' training. These low completion rates indicate that TfNSW is not effectively rolling out cyber security training across the cluster.

In October 2020, the Department of Customer Service released 'DCS-2020-05 Cyber Security NSW Directive - Practice Requirement for NSW Government', which made annual cyber security training mandatory for all staff from 2021. In line with this requirement, TfNSW has advised that it will be gradually implementing mandatory annual training from July 2021 for all staff.

The Transport cluster undertakes activities to build a cyber-aware culture in accordance with the CSP, but awareness remains low

Increasing staff awareness of cyber security risks and maintaining a cyber secure culture are both mandatory requirements of the CSP. While TfNSW does undertake some activities to build a cyber aware culture, awareness of cyber security risks remains low. This can be demonstrated by the low training rates outlined above, and the 'Spot the Scammer' exercise, described in Exhibit 7. TfNSW is responsible for delivering these awareness raising activities across the cluster.

TfNSW frequently communicates with staff across the Transport cluster about various cyber security risks through multiple avenues. Both agencies use the intranet, emails and other awareness raising activities to highlight the importance for staff to be aware of the seriousness of cyber risks. Advice given on the intranet includes tips for spotting scammers on mobile phones, promoting the cluster-wide training courses, as well as various advice that staff could use when dealing with cyber risks in the workplace.

In addition to these awareness raising activities, TfNSW has also undertaken a cluster-wide phishing email exercise called 'Spot the Scammer'. This is outlined in Exhibit 7. This exercise was carried out in 2019 and 2020 and allowed the Transport cluster to measure the degree to which staff were able to identify phishing emails. As can be seen in Exhibit 7, the results of this exercise indicate that staff awareness of phishing emails remains low.

Exhibit 7 - Spot the Scammer exercise
In both 2019 and 2020, TfNSW performed a ‘Spot the Scammer’ exercise in which they sent out over 25,000 emails to staff based on a real phishing attack in order to measure awareness and response. The exercise tested staff 'click through rate', the percentage of staff who clicked on the fake phishing link. In 2019, these results were then compared to industry benchmarks, with over a 20 per cent click through rate being considered 'very high'. Both TfNSW and Sydney Trains were considered to have a ‘very high’ click through rate in comparison to these benchmarks in both 2019 and 2020. This indicates that staff awareness of phishing emails was low. The click through rate for TfNSW was 24 per cent in 2020, an increase from 22 per cent in 2019. For Sydney Trains, the click through rate in 2020 was 32 per cent, which was a decrease from 40 per cent in 2019.
Source: Audit Office analysis of TfNSW documents.

Appendix one – Response from agencies

Appendix two – Cyber Security Policy mandatory requirements

Appendix three – About the audit

Appendix four – Performance auditing

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #353 - released (13 July 2021).

Published

Actions for WestConnex: changes since 2014

WestConnex: changes since 2014

Transport
Compliance
Infrastructure
Internal controls and governance
Management and administration
Project management
Risk

What the report is about

The report examined whether Transport for NSW (TfNSW) and Infrastructure NSW (INSW) effectively assessed and justified major scope changes to the WestConnex project since 2014.

What we found

NSW Government decisions to fund WestConnex-related projects outside WestConnex's $16.812 billion budget have reduced transparency and understate the full cost of WestConnex.

The NSW Government's decision to separate Sydney Gateway from WestConnex has reduced transparency over the cost of the road component of Sydney Gateway. $1.76 billion of the cost to complete Sydney Gateway is funded outside the WestConnex budget.

Network integration costs, currently estimated at $2.3 billion, are also funded outside the WestConnex budget. Many of these costs are directly attributable to WestConnex and ought to be included in the reported budget.

The Parramatta Road Urban Amenity Improvement Program, costing $198 million, should also be included as part of the WestConnex reported budget.

Decisions to exclude or remove these elements from WestConnex without justification have seen $4.26 billion of projects funded outside the $16.8 billion budget.

Positively, robust analysis was used to develop and incorporate design improvements into the 2015 WestConnex Updated Strategic Business Case.

The separate components of WestConnex underwent all required assurance reviews. However, the NSW Government's assurance framework does not require ongoing ‘whole-of-program’ assurance for large and complex projects like WestConnex. The absence of a holistic review of WestConnex allows for some costs and benefits to avoid scrutiny.

What we recommended

TfNSW should:

  • review the impact of scope changes on project objectives, costs and benefits for complex infrastructure projects
  • ensure that estimated costs and benefits of works which are reasonably required to meet consent conditions are included in business cases for complex large infrastructure projects
  • establish centralised and project specific record keeping for major infrastructure projects.

Infrastructure NSW should provide transparent whole of program assurance on total costs and benefits when complex projects are split into sub-projects.

Government should consider enhancing public transparency of existing infrastructure assurance processes by requiring that large complex infrastructure programs undergo periodic review at a whole-of-program level.

Fast facts

  • $16.812b 2015 WestConnex business case budget
  • $2.3b current estimated cost of network integration works to enable WestConnex, funded outside the WestConnex budget
  • $1.76b cost to complete Sydney Gateway to enable WestConnex and also funded outside the WestConnex budget
  • $198m Parramatta Road Urban Amenity Improvement Program, originally part of WestConnex but now funded outside the WestConnex budget

WestConnex

WestConnex is a 33 km motorway network that will link the western and south‑western suburbs with the Sydney CBD and the Airport and Port Botany precinct. It will also connect with proposed future motorway links to the north shore, northern beaches, and southern Sydney. The project is being delivered in three stages, with completion scheduled for 2023.

When first conceived by Infrastructure NSW (INSW) in 2012, WestConnex was described as a single integrated concept. In August 2013, government approved a business case for an integrated concept of WestConnex, with an estimated cost of $14.881 billion (in nominal outturn costs). Transport for NSW (TfNSW) is the government agency (sponsor agency) accountable for the delivery of WestConnex in accordance with the business case. In August 2014, the NSW Government established the Sydney Motorway Corporation to fund, deliver and operate WestConnex.

In November 2015, the NSW Government publicly released an updated WestConnex business case with greater detail and design enhancements, which increased the estimated cost to $16.812 billion.

Subsequent to this update, further changes were made to the design, including realignment of the M4 to M5 Link connection to the Western Harbour Tunnel project, an expanded interchange at Rozelle, the deletion of the Camperdown Intersection, and the addition of the Iron Cove Link. The reported budget for WestConnex was not changed as a result of these design updates.

To fund WestConnex, Sydney Motorway Corporation consolidated a concessional loan of $2 billion from the Australian Government, private sector debt and equity funding from the State. The Australian Government also provided a $1.5 billion contribution to the State to partially fund construction of WestConnex.

In August 2018, the NSW Government sold 51 per cent of its stake in Sydney Motorway Corporation for $9.26 billion. At the time of writing, the NSW Government is in the process of selling its remaining 49 per cent stake of Sydney Motorway Corporation.

About this audit

In the course of delivering a complex major infrastructure project, it is reasonable to expect changes to the original design and scope. Changes may occur as the design moves from a high‑level concept to a detailed design for project delivery, as new risks or issues are identified, as demands change, or as other interdependent projects are approved. Changes can also occur in response to potential cost or delivery overruns which arise as a result of planning deficiencies. Where design and scope changes significantly change the project costs and/or expected benefits, the justification for these changes should be robust and transparent.

Following our 2014 performance audit, 'WestConnex: Assurance to the government', the NSW Government established the Infrastructure Investor Assurance Framework (IIAF) to improve accountability and transparency over major projects that are developed, procured, or delivered by government agencies. Under the framework, TfNSW, as project sponsor, is responsible for ensuring the WestConnex project meets all IIAF requirements. These include ensuring the project remains strategically aligned and viable, and benefits are on track. INSW is responsible for coordinating the assurance review process and reporting directly to NSW Cabinet on project delivery against time, budget and risks to project delivery.

The objective of this performance audit is to assess whether TfNSW and INSW effectively assessed and justified major scope changes to the WestConnex project since 2014.

 

Conclusion

Government decisions to separate WestConnex related projects and deliver them outside WestConnex's 2015 business case budget of $16.812 billion has understated the total cost of WestConnex achieving its objectives. The rationale for separating these elements from the WestConnex project scope has not been transparent. Together, these projects represent costs of $4.26 billion funded outside the $16.812 billion WestConnex budget.

Since 2015, the NSW Government has removed several projects from the scope described in the 2015 WestConnex business case, and funded them separately:
  • In mid‑2017, the Sydney Gateway became a separate project outside WestConnex. This project, estimated in 2015 to cost $800 million, now has an estimated cost of $2.56 billion. The project remains partly funded by an $800 million contribution from the $16.812 billion WestConnex budget, with $1.76 billion funded outside the WestConnex budget.
  • In late 2018, the Parramatta Road Urban Amenity Improvement Program became a separate project outside the 2015 WestConnex budget. This project was part of the 2015 WestConnex Business Case and is intended to create urban renewal opportunities around Paramatta Road. It is estimated to cost $198 million.

Work required to integrate WestConnex with existing roads ('network integration') was funded outside the $16.812 billion budget for the November 2015 WestConnex business case. TfNSW is obliged to deliver network integration works to meet the conditions of planning approval for WestConnex. As such, these costs should be included in the WestConnex budget. The current estimated cost of these network integration works is $2.3 billion.

The rationale to exclude or remove each of these elements from the WestConnex project scope has not been transparent, nor supported by robust analysis and justification. These elements are required for WestConnex to achieve its objectives. The additional project costs will also deliver additional benefits not included in the 2015 WestConnex business case. Removing them understates the total cost of achieving the objectives set out in the 2013 and 2015 WestConnex business cases.

WestConnex's complex financing arrangements further reduce transparency on costs.

Transparency over the total cost of WestConnex – including elements funded from other project budgets – is further limited by the project's complex financing arrangements.

Prior to 2018, the Audit Office provided assurance on costs borne and levied by Sydney Motorway Corporation and its controlled entities. Since the NSW Government sold its majority stake in WestConnex in August 2018, the Auditor‑General no longer has the mandate to provide this assurance. Considering this, and the lack of transparency on the cost of projects removed from the WestConnex project scope, there is no transparent or comprehensive view of the total cost to deliver WestConnex – nor of how these cost would be offset by the sale of the government's remaining stake.

There is no 'whole‑of‑program' assurance over the WestConnex program of works. This limits transparency and confidence that WestConnex will meet intended objectives within its budget.

After INSW conducted a gateway review of a draft of the 2015 WestConnex Business Case under the IIAF, the project was broken up into separate components to support staged delivery. Each of these projects, including the Sydney Gateway, as well as the Network Integration Program, underwent the required assurance reviews under the IIAF. INSW also provided monthly progress updates to government. These individual projects are, in themselves, significant in scale and complexity. Addressing them as discrete components for the purposes of the assurance review process is justified and there is no requirement under the IIAF to holistically review projects which together deliver final benefits of the WestConnex program. However, whole‑of‑program review would improve transparency over total costs and benefits.

In 2016, TfNSW revised the design of the M4‑M5 Link and Rozelle to address traffic and integration issues.

TfNSW identified that the concept designs used for the M4‑M5 Link and Rozelle Interchange in the 2015 WestConnex Business Case would not integrate well with surface roads, including the proposed Bays Precinct, and would result in increased traffic on Victoria Road and the ANZAC Bridge. Following a comprehensive review conducted in mid‑2016, TfNSW refined the design of the M4‑M5 Link and Rozelle Interchange to address these limitations without increasing the cost of delivery. TfNSW documented the rationale for the design changes, including how the changes improved on the original design to increase capacity, improve traffic conditions and create more open space.

1. Key findings

Government decisions to fund WestConnex related projects outside of WestConnex's $16.812 billion reported budget have reduced transparency over costs and understate the full cost of WestConnex

In 2015, the work required to integrate WestConnex with existing roads ('network integration') was funded as a separate project with an estimated cost of $1.534 billion outside the 2015 WestConnex budget of $16.812 billion. TfNSW then created the Network Integration Program to respond to the conditions of planning approval for WestConnex. The current estimated cost to deliver all network integration works is $2.3 billion.

Since the 2015 WestConnex Business Case, the NSW Government has removed several elements from the scope of WestConnex and funded them as separate projects, while keeping the published WestConnex budget at an estimated $16.812 billion. Projects removed include:

  • Sydney Gateway, currently costed at $2.56 billion (with an $800 million contribution from WestConnex)
  • Parramatta Road Urban Amenity Improvement Program, costed at $198 million in late 2018 and funded though new funding to the Greater Sydney Commission.

Together, these projects represent costs of $4.26 billion that are not included in the WestConnex budget, but are required for WestConnex to achieve the objectives of the 2013 and 2015 WestConnex Business Cases. The costs of these elements in supporting the objectives of WestConnex is not tracked centrally, and there is no single point of oversight over them. Exhibit 1 compares total WestConnex forecast costs (including related projects) between November 2015 and April 2021.

 

November 2015
($ million)

April 2021
($ million)
WestConnex
Stage 1
Stage 1A (M4 Widening) 497 517
Stage 1B (M4 East) 3,802 3,782
Total 4,299 4,299
Stage 2
King Georges Road Interchange 131 131
New M5 4,335 4,335
Sydney Gateway Contribution 800 800
Total 5,266 5,266
Stage 3
M4‑M5 Link and Rozelle Interchange 7,049 7,049
Urban renewal (Parramatta Road) 198 ‑‑
Urban renewal (Rozelle) ‑‑ 198
Total 7,247 7,247
Total reportable WestConnex 16,812 16,812

Exhibit 1: WestConnex and related projects forecast costs
  November 2015
($ million)
April 2021
($ million)
Related projects
Network integration 1,534 2,300
Urban renewal (Parramatta Road) ‑‑ 198
Sydney Gateway Road Component ‑‑ 1,760
Total 1,534 4,258

Source: AO research.

Many network integration costs are directly attributable to WestConnex and ought to be included in the reported budget for WestConnex

Prior to 2015, the scope of WestConnex included enabling works needed before or during construction, as well as funding for future works to address any adverse traffic outcomes created by WestConnex which become apparent after its opening. These works are also known as network integration works.

When government approved the 2015 WestConnex Business Case, it noted that the project would require $1.534 billion for network integration works to address the impacts of WestConnex on the road network. However, the WestConnex project budget of $16.812 billion did not include funding for network integration works. Instead, Roads and Maritime Services (RMS, now TfNSW) was to fund network integration through its normal budget allocation.

It is important to recognise these costs as part of the total WestConnex project cost because:

  • TfNSW created the Network Integration Program to respond to network traffic and transport elements of the planning conditions of approval for WestConnex granted by the then NSW Department of Planning and Environment under the Environment, Planning and Assessment Act 1979.
  • NSW Treasury guidelines for business cases note that accurate cost estimates include assessment of the financial impact of meeting the conditions of planning approval.
  • Travel time and vehicle operating cost benefits attributed to the WestConnex project in the 2015 WestConnex Business Case assume that some network integration works, then costed at $373 million, were in place.

Refer to Appendix two for more detail on network integration works.

Some of the projects in the WestConnex Network Integration Program provide community and place benefits, such as parklands and cycleways. These benefits have not been attributed to WestConnex. Additionally, some network integration works are likely to deliver additional traffic related benefits to WestConnex. As the Network Integration Program’s primary purpose is to meet the conditions of planning approval for WestConnex, TfNSW should attribute all the costs and benefits of the program to WestConnex.

To September 2021, the total funded cost of the Network Integration Program is approximately $2.077 billion. TfNSW estimates that it will need a further $222 million to complete all expected network integration works.

The NSW Government's decision to separate Sydney Gateway from WestConnex has reduced transparency and accountability for TfNSW's underestimation of the cost of the road component of Sydney Gateway

Sydney Gateway is a high‑capacity connection between the new St Peters Interchange and the Sydney Airport and Port Botany precinct. It includes a road and rail components. The road component was included in the scope of WestConnex in the 2015 WestConnex Business Case. The November 2015 design, which TfNSW costed at $800 million, involved separate roadways from the St Peters Interchange to the International terminal, and to the domestic terminals and Mascot airport precinct.

By October 2016, TfNSW was aware that the $800 million budget for Sydney Gateway was insufficient and revised the forecast cost for the road component to $1.8 billion. The original cost estimate did not sufficiently consider the cost of:

  • constructing a complex design adjacent to the airport precinct
  • obtaining access to land required for the project
  • managing environmental contamination.

On 9 August 2017, the then Minister for WestConnex announced that the Sydney Gateway project was not part of WestConnex.

The 2015 WestConnex Business Case notes that material changes to the WestConnex budget, funding, scope, or timeframe are subject to Cabinet approval processes. It states that, when seeking approval for material changes, the portfolio Minister will make a submission to the relevant Cabinet Committee. Changes in project scope required the approval of the then Cabinet Committee on Infrastructure and should have been endorsed by the WestConnex Interdepartmental Steering Committee.

TfNSW and the NSW Department of Premier and Cabinet (DPC) assert that there is no documentation to support the government’s decision to separate Sydney Gateway from the WestConnex Program, or the WestConnex Interdepartmental Steering Committee's endorsement of a submission to Cabinet seeking approval for the separation.

The established governance processes for major scope changes were not followed in this instance. The lack of transparency regarding government's decision to separate Sydney Gateway from WestConnex also reduces visibility of TfNSW's underestimation of the cost of delivering the road component of Sydney Gateway.

The November 2018 Final Business Case for Sydney Gateway, which was approved by the government, included an estimate of $2.45 billion (nominal outturn cost) for the road component. This estimate included an $800 million contribution from WestConnex. A more recent estimate (late 2020) for this project is $2.56 billion (nominal outturn cost).

The Parramatta Road Urban Amenity Improvement Program should be included as part of the WestConnex budget

A specific objective of the 2015 WestConnex Business Case was the creation of opportunities for urban renewal along and around Parramatta Road. The business case included an allocation of $198 million in the $16.812 billion WestConnex budget for the Parramatta Road Urban Amenity Improvement program, designed to implement aspects of the objective. In November 2018, the NSW Government removed the Parramatta Road Urban Amenity Improvement Program from the WestConnex program of works and reallocated the $198 million (inside the $16.812 billion WestConnex budget) for urban renewal works around the Rozelle Interchange. As part of this decision, government approved new funding of $198 million to the Greater Sydney Commission for the urban amenity program, outside the $16.812 billion WestConnex budget. This understates the cost of WestConnex meeting its objectives by $198 million.

There is no requirement for ongoing ‘whole‑of‑program’ assurance of the WestConnex program of works, including related projects

In August 2015, INSW conducted its first Gateway Review of WestConnex as a program consisting of composite projects. Following that review, TfNSW registered each of the components of WestConnex with INSW as individual projects, rather than keeping WestConnex registered as a program or mega‑project. This is not inconsistent with the IIAF and all WestConnex related projects, including Sydney Gateway and the Network Integration Program, have undergone independent assurance reviews as individual projects under the IIAF.

Once a program like WestConnex is broken down into its composite parts, there is no requirement for the sponsor agency (TfNSW) or INSW to provide independent assurance on the program as a whole until it is completed. This is then done as part of the Gateway review for benefits realisation, which examines whether project benefits are being measured and meet expectations. These individual projects are, in themselves, significant in scale and complexity. While addressing them as discrete components for the purposes of the assurance review process can be justified, the absence of strategic, holistic reviews of WestConnex allows for total costs and benefits to become opaque and avoid scrutiny. Programs of this scale require greater ongoing transparency on total costs and benefits in order to ensure confidence they will meet intended objectives within budget.

There is a lack of public transparency on the total costs and benefits of the WestConnex project

Prior to 2018, the Audit Office provided assurance on costs borne and levied by Sydney Motorway Corporation and its controlled entities. Since the NSW Government sold 51 per cent of its stake in WestConnex in August 2018, the Auditor‑General no longer has the mandate to provide this assurance. The Audit Office is also unable to provide any assurance regarding the performance of tolling concessions.

This means that the total costs of WestConnex, including those levied on road users through tolling, are not reported alongside the full cost of delivering the project. This information, and independent assurance over that information, would provide transparency and context to the outcome of government's sale of its interest in WestConnex.

To enhance the transparency of existing infrastructure assurance processes, government could consider requiring large and complex infrastructure programs to undergo periodic review at a whole‑of‑program level. This could take the form of annual reports to Parliament on the total costs and benefits of selected large and complex projects by the responsible agency. The reports could include an assessment of the cost to government and cost to the community of funding and financing. Independent assurance of the agency report would provide Parliament with greater confidence that infrastructure is delivered economically and providing value for money for the people of NSW.

The Australian National Audit Office provides similar assurance on selected Department of Defence acquisition projects as part of its annual Major Projects Report.

Design enhancements included in the 2015 WestConnex Updated Strategic Business Case were supported by robust analysis

The 2015 WestConnex Business Case contained more detail than the 2013 WestConnex business case. Design enhancements were made as a result of modelling analysis conducted over the two years since the 2013 business case. Enhancements included a full underground link between Kingsgrove and St Peters as part of the New M5 and re‑alignment of the M4‑M5 link tunnel (Stage 3) to include the Rozelle Interchange. The Rozelle Interchange will provide a direct connection to the Anzac Bridge and Victoria Road, and will enable a connection to the proposed Western Harbour Tunnel and Beaches Link. A map and description of these elements can be found at Exhibits 2 and 3 of this report.

In 2016, TfNSW revised the design of the M4‑M5 Link and Rozelle to address traffic and integration issues

As part of preparing the 2015 WestConnex Business Case, TfNSW prepared a Project Definition and Delivery Report (PDDR) for the M4‑M5 Link. This report describes the scope of the project, including a high‑level concept design. TfNSW identified limitations with the proposed design of the M4‑M5 in the PDDR, which it would need to address as the project moved to a detailed design stage. In particular, these limitations included:

  • poor integration with the Bays Precinct masterplan
  • traffic capacity constraints on Victoria Road and Anzac Bridge
  • construction complexity.

Following a comprehensive review in mid‑2016, TfNSW changed the design of the M4‑M5 Link and Rozelle Interchange to address these limitations. These changes included:

  • deletion of the Camperdown intersection to improve traffic conditions on Parramatta Road
  • a fully underground and larger Rozelle Interchange with 10‑hectare dedicated parklands
  • a toll‑free tunnel link from Iron Cove Bridge to Anzac Bridge
  • increasing the lanes in the dual tunnels from three to four each way.

TfNSW documented, but did not publish, the rationale for the design changes, including how the changes addressed the limitations of the previous design while providing increased community benefit through the creation of open space. TfNSW undertook cost comparison studies which estimated that these changes would have a neutral impact on the estimated project cost while achieving the same or improved benefits.

TfNSW's record‑keeping systems for large infrastructure investments negatively impact accountability and transparency

In response to our formal requests for relevant information, made during the conduct of this audit, TfNSW advised that complete and valid records of key decision‑making processes, analysis and advice were unavailable. Additionally, TfNSW often provided information that was incomplete or unverifiable (for instance, unsigned briefing notes). This is not consistent with accepted governance practices and does not comply with the requirements of the State Records Act 1998.

We also requested that TfNSW provide a list of relevant documents held by the Sydney Motorway Corporation (SMC). While TfNSW acknowledged that SMC may hold material relevant to the audit, TfNSW did not have a list or description of these documents. As SMC is now a majority privately held entity, both the Audit Office and TfNSW have limited power to require SMC to provide documentation.

The delivery timeframe for large and complex infrastructure projects such as WestConnex frequently exceeds five years, and some projects can take over a decade to deliver. These projects represent a significant investment of public resources and government agencies should expect independent review and assurance activities such as performance audits. The establishment of dedicated record keeping facilities for major infrastructure projects, such as data rooms, would improve transparency and accountability. This would ensure that the use of public resources is fully auditable in line with public expectations and the requirements of the Government Sector Finance Act 2018, the State Records Act 1998 and the Public Finance and Audit Act 1983.

2. Recommendations

By December 2021, TfNSW should:

1. review the impact of scope changes on project objectives, costs and benefits for complex infrastructure projects

2. when preparing business cases for complex large infrastructure projects, ensure that the estimated costs and benefits of works which are reasonably expected to meet consent conditions are included in the overall project cost and its benefits (as per Treasury guidelines)

3. establish and maintain centralised and project‑specific record keeping, including through dedicated project data rooms, to ensure major infrastructure projects can readily be subject to external oversight and assurance.

By June 2022, INSW should:

4. provide transparent whole‑of‑program assurance on total costs and benefits throughout the project life‑cycle when complex projects are split into sub‑projects.

By June 2022, NSW Government should:

5. consider enhancing the public transparency of existing infrastructure assurance processes by requiring that large complex infrastructure programs undergo periodic review at a whole‑of‑program level. This could take the form of reports to Parliament on the total costs and benefits on selected large and complex projects by the responsible agency, including cost to government and cost to community of funding and financing, as well as an accompanying independent assessment of the agency report.

Following our 2014 performance audit report 'WestConnex: Assurance to the government', the NSW Government established the Infrastructure Investor Assurance Framework (IIAF). INSW is responsible for the development, implementation and administration of the IIAF. The assurance framework involves gateway reviews, health checks, deep dive reviews, and project monitoring and reporting at various stages in the lifecycle of a project. The main aims of the IIAF are to help ensure major infrastructure projects are delivered on time and on budget, and to ensure that reports are regularly monitored by the Cabinet of the NSW Government. The IIAF gateway review process is compulsory for all significant investments and expenditure under the NSW Treasury Gateway Policy.

In accordance with the IIAF, INSW is responsible for the following:

  • providing a dedicated Assurance Team including Gateway Review Managers to coordinate Reviews
  • determining appropriate expert reviewers, and manages scheduling, commissioning and administration of Assurance Review reports. Infrastructure NSW is independent of the Expert Review Team
  • monitoring Tier 1 – High Profile/High Risk projects, Tier 2 and Tier 3 (if required) project performance through independent Assurance Reviews
  • providing independent analysis and advice on key risks and any corrective actions recommended for Tier 1 – High Profile/High Risk, Tier 2 and Tier 3 projects
  • escalating projects to Infrastructure Investor Assurance Committee (IIAC) and Cabinet where projects present ‘red flag issues’ and where corrective action is needed
  • working with delivery agencies to register all capital projects with an estimated cost greater than $10.0 million and ensures they are risk profiled and assigned a risk‑based project tier with an endorsed IIAF Project Registration report
  • preparing forward looking annual Cluster Assurance Plans
  • maintaining and continuously improves the IIAF process
  • reporting to the IIAC, Cabinet and Infrastructure NSW Board
  • regularly report to NSW Treasury on the performance of the IIAF.

In relation to WestConnex, TfNSW is the sponsor agency responsible for meeting relevant IIAF requirements, including:

  • registering and risk profiling projects
  • IIAF gateway, health check, and deep dive assurance reviews
  • regular reporting.

Under the IIAF, it is mandatory for all capital projects valued over $10.0 million to be registered with INSW. Capital projects can be registered either as a program (comprising of a group of related projects or activities) or as a project (which may or may not be part of a program).

According to the IIAF, programs tend to have a lifespan of several years and aim to deliver outcomes and benefits related to an organisation's strategic objectives. Projects tend to have a shorter lifespan, and deal with outputs. Projects can, however, be grouped under a single program if they are similar in nature or if they are aimed at collectively achieving a strategic objective. Complex projects can be delivered in multiple stages, under different contracts, and across different time periods.

The last assurance review of the entire WestConnex program of works as a whole was in 2015

INSW conducted the first IIAF gateway review of WestConnex in August 2015. TfNSW developed a draft WestConnex Updated Strategic Business Case to consolidate the latest analysis on WestConnex, and to confirm that the project remained fit for purpose, economically viable, and financially deliverable. The review followed a recommendation in our 2014 performance audit report that business cases be thoroughly revisited.

During September 2015, INSW conducted additional informal reviews to identify strategic risks associated with public release of the WestConnex business case. Subsequently, INSW gave the Premier of NSW its views on the draft business case, including the following points:

  • The $398 million budget for Sydney Gateway was insufficient to meet the benefits claimed in the business case for a ‘functional’ connection to Sydney Airport and Port Botany. INSW studies indicate a future‑proof solution would require a minimum spend of $755 million.
  • Enabling works for WestConnex estimated at $1.534 billion were excluded from the cost of WestConnex. Significant work remained for RMS to identify mitigation measures to address planning approvals and network performance issues.
  • Enabling works (a Southern Connector), an access ramp and surface road improvements within St Peters were excluded from the draft 2015 business case despite their inclusion in the WestConnex scope in the 2014–15 State Budget.
  • The overall cost of works not funded within the WestConnex budget ranged from $2.011 billion to $2.196 billion. This included the enabling works, access ramp and surface road improvements and the shortfall for Sydney Gateway.

All WestConnex related projects, including Sydney Gateway have undergone independent assurance reviews under the IIAF

Since INSW submitted the first WestConnex progress update report to Cabinet in June 2015, INSW has been reporting monthly on the different stages of the WestConnex Program, including Sydney Gateway, as the projects were registered with INSW as High‑Profile, High‑Risk projects. Separate reporting enabled INSW to report and review each stage with more detailed scrutiny, compared to the reporting and reviewing at a program level.

WestConnex Stage 2 (New M5) underwent both mandatory and non‑mandatory reviews at key points in the project lifecycle. Three mandatory gateway reviews – at Gate 2 (Final business case), Gate 3 (Readiness for market), and Gate 4 (Tender evaluation) – were conducted by TfNSW before the introduction of IIAF. Four non‑mandatory health check reviews and one non‑mandatory deep dive review were conducted after the introduction of the IIAF managed by INSW.

Similarly, WestConnex Stage 3 projects – M4‑M5 link, M4‑M5 Tunnels, and Rozelle Interchange – also underwent mandatory and non‑mandatory reviews at key points in their lifecycle under IIAF.

The M4‑M5 Link had two mandatory gateway reviews and one non‑mandatory health check review under IIAF. These reviews were conducted before Stage 3 was split into two stages, due to major design changes to the Rozelle Interchange and the M4‑M5 tunnels.

The M4‑M5 tunnels had two mandatory gateway reviews (at Gates 3 and 4), one non‑mandatory health check review, and one non‑mandatory deep dive review under IIAF.

Rozelle Interchange also underwent three mandatory gateway reviews at Gate 3 (part 1), Gate 3 (part 2), and Gate 4, two non‑mandatory health check reviews, and one non‑mandatory deep dive review under IIAF.

Since mid‑2017, the Sydney Gateway project has undergone required independent assurance reviews, as well as a number of optional assurance reviews

In November 2016, INSW conducted a mandatory Gate 1 gateway review on a strategic business case for the Sydney Gateway Project. TfNSW did not proceed with this business case. Following the separation of Sydney Gateway from WestConnex in mid‑2017, TfNSW developed a new business case for Sydney Gateway. It has undergone the required Gate 1, Gate 2, and Gate 3 gateway reviews, as well as two non‑mandatory health check reviews, and three non‑mandatory deep dive reviews under IIAF.

Network integration works have undergone all IIAF required assurance reviews

TfNSW completed a strategic business case for the Network Integration Program in August 2020, and INSW completed a gateway review in November 2020. This is despite network integration projects starting as early as 2015, with $645 million having been spent by June 2020. The strategic business case included a prioritisation process for completing remaining works in the program. Prior to November 2020, TfNSW registered individual network integration projects with INSW, and these projects have undergone gateway reviews where required.

The Network Integration Program strategic business case does not include Rozelle interchange network integration works ($353 million) and additional network integration works to settle a contractor claim adjacent to St Peters Interchange ($190 million). These were excluded from the business case on the basis they had already been approved by government, and as such were not subject to the prioritisation elements of the business case. TfNSW has not developed separate business cases for these works, although the scope of the St Peters Interchange works was developed through a negotiated process.

TfNSW did not prepare business cases for some network integration works which have commenced, including the $323 million Campbell Road/Euston Road works

Prior to its development of the August 2020 strategic business case, TfNSW did not prepare business cases for many network integration works that have commenced, and in some instances were completed, before 2019. Significantly, TfNSW did not prepare a business case for the Campbell Road/Euston Road works, which cost $323 million and have been completed.

In 2016, TfNSW’s Business Case Policy requires the creation of business cases for capital projects costing over $1.0 million. At the time of writing this report, TfNSW’s draft policy requires full business cases for capital projects costing $10.0 million or more.

There is no requirement for ongoing ‘whole‑of‑program’ assurance of the WestConnex program of works, including related projects

INSW conducted its first gateway review of WestConnex (as a program, which consisted of composite projects) in August 2015. Following that review, TfNSW registered each of the components of WestConnex with INSW as individual projects, rather than keeping WestConnex registered as a program or complex project. The IIAF allows this to occur.

Separate registration enabled INSW to report and review each stage with more scrutiny compared to whole‑of‑program level review.

Such an approach has merit, considering the individual stages (and components of these stages) are multi‑million dollar works in their own right. Each project has its own timing for gateway reviews at stages such as 'Readiness for Market' and 'Tender Evaluation'.

Once a program such as WestConnex is broken down into its composite parts, there is no requirement for the sponsor agency (TfNSW) or INSW to conduct independent assurance on the program of works as a whole until the whole program is completed as part of the Benefits Realisation (Gate 6) gateway review. The absence of strategic, holistic reviews of projects of the scale and complexity such as WestConnex during their delivery allows for total costs and benefits to become opaque and avoid scrutiny. Projects of this scale require greater ongoing transparency on total costs and benefits in order to ensure confidence they will meet intended objectives within budget.

INSW has advised us that it has prepared a proposal to expand its assurance function to include whole‑of‑program review of inter‑related infrastructure projects.

Appendix one – Responses from agencies

Appendix two – Network integration works

Appendix three – About the audit

Appendix four – Performance auditing

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.