Refine search Expand filter

Reports

Published

Actions for Newcastle Urban Transformation and Transport Program

Newcastle Urban Transformation and Transport Program

Transport
Planning
Compliance
Infrastructure
Management and administration
Procurement
Project management

The urban renewal projects on former railway land in the Newcastle city centre are well targeted to support the objectives of the Newcastle Urban Transformation and Transport Program (the Program), according to a report released today by the Auditor-General for New South Wales, Margaret Crawford. The planned uses of the former railway land achieve a balance between the economic and social objectives of the Program at a reasonable cost to the government. However, the evidence that the cost of the light rail will be justified by its contribution to the Program is not convincing.

The Newcastle Urban Transformation and Transport Program (the Program) is an urban renewal and transport program in the Newcastle city centre. The Hunter and Central Coast Development Corporation (HCCDC) has led the Program since 2017. UrbanGrowth NSW led the Program from 2014 until 2017. Transport for NSW has been responsible for delivering the transport parts of the Program since the Program commenced. All references to HCCDC in this report relate to both HCCDC and its predecessor, the Hunter Development Corporation. All references to UrbanGrowth NSW in this report relate only to its Newcastle office from 2014 to 2017.

This audit had two objectives:

  1. To assess the economy of the approach chosen to achieve the objectives of the Program.
  2. To assess the effectiveness of the consultation and oversight of the Program.

We addressed the audit objectives by answering the following questions:

a) Was the decision to build light rail an economical option for achieving Program objectives?
b) Has the best value been obtained for the use of the former railway land?
c) Was good practice used in consultation on key Program decisions?
d) Did governance arrangements support delivery of the program?

Conclusion
1. The urban renewal projects on the former railway land are well targeted to support the objectives of the Program. However, there is insufficient evidence that the cost of the light rail will be justified by its contribution to Program objectives.

The planned uses of the former railway land achieve a balance between the economic and social objectives of the Program at a reasonable cost to the Government. HCCDC, and previously UrbanGrowth NSW, identified and considered options for land use that would best meet Program objectives. Required probity processes were followed for developments that involved financial transactions. Our audit did not assess the achievement of these objectives because none of the projects have been completed yet.

Analysis presented in the Program business case and other planning documents showed that the light rail would have small transport benefits and was expected to make a modest contribution to broader Program objectives. Analysis in the Program business case argued that despite this, the light rail was justified because it would attract investment and promote economic development around the route. The Program business case referred to several international examples to support this argument, but did not make a convincing case that these examples were comparable to the proposed light rail in Newcastle.

The audited agencies argue that the contribution of light rail cannot be assessed separately because it is a part of a broader Program. The cost of the light rail makes up around 53 per cent of the total Program funding. Given the cost of the light rail, agencies need to be able to demonstrate that this investment provides value for money by making a measurable contribution to the Program objectives.

2. Consultation and oversight were mostly effective during the implementation stages of the Program. There were weaknesses in both areas in the planning stages.

Consultations about the urban renewal activities from around 2015 onward followed good practice standards. These consultations were based on an internationally accepted framework and met their stated objectives. Community consultations on the decision to close the train line were held in 2006 and 2009. However, the final decision in 2012 was made without a specific community consultation. There was no community consultation on the decision to build a light rail.

The governance arrangements that were in place during the planning stages of the Program did not provide effective oversight. This meant there was not a single agreed set of Program objectives until 2016 and roles and responsibilities for the Program were not clear. Leadership and oversight improved during the implementation phase of the Program. Roles and responsibilities were clarified and a multi-agency steering committee was established to resolve issues that needed multi-agency coordination.
The light rail is not justified by conventional cost-benefit analysis and there is insufficient evidence that the indirect contribution of light rail to achieving the economic development objectives of the Program will justify the cost.
Analysis presented in Program business cases and other planning documents showed that the light rail would have small transport benefits and was expected to make a modest contribution to broader Program objectives. Analysis in the Program business case argued that despite this, the light rail was justified because it would attract investment and promote economic development around the route. The Program business case referred to several international examples to support this argument, but did not make a convincing case that these examples were comparable to the proposed light rail in Newcastle.
The business case analysis of the benefits and costs of light rail was prepared after the decision to build light rail had been made and announced. Our previous reports, and recent reports by others, have emphasised the importance of completing thorough analysis before announcing infrastructure projects. Some advice provided after the initial light rail decision was announced was overly optimistic. It included benefits that cannot reasonably be attributed to light rail and underestimated the scope and cost of the project.
The audited agencies argue that the contribution of light rail cannot be assessed separately because it is part of a broader Program. The cost of the light rail makes up around 53 per cent of the total Program funding. Given the high cost of the light rail, we believe agencies need to be able to demonstrate that this investment provides value for money by making a measurable contribution to the Program objectives.

Recommendations
For future infrastructure programs, NSW Government agencies should support economical decision-making on infrastructure projects by:
  • providing balanced advice to decision makers on the benefits and risks of large infrastructure investments at all stages of the decision-making process
  • providing scope and cost estimates that are as accurate and complete as possible when initial funding decisions are being made
  • making business cases available to the public.​​​​​​
The planned uses of the former railway land achieve a balance between the economic and social objectives of the Program at a reasonable cost to the government.

The planned uses of the former railway land align with the objectives of encouraging people to visit and live in the city centre, creating attractive public spaces, and supporting growth in employment in the city. The transport benefits of the activities are less clear, because the light rail is the major transport project and this will not make significant improvements to transport in Newcastle.

The processes used for selling and leasing parts of the former railway land followed industry standards. Options for the former railway land were identified and assessed systematically. Competitive processes were used for most transactions and the required assessment and approval processes were followed. The sale of land to the University of Newcastle did not use a competitive process, but required processes for direct negotiations were followed.

Recommendation
By March 2019, the Hunter and Central Coast Development Corporation should:
  • work with relevant stakeholders to explore options for increasing the focus on the heritage objective of the Program in projects on the former railway land. This could include projects that recognise the cultural and industrial heritage of Newcastle.
Consultations about the urban renewal activities followed good practice standards, but consultation on transport decisions for the Program did not.

Consultations focusing on urban renewal options for the Program included a range of stakeholders and provided opportunities for input into decisions about the use of the former railway land. These consultations received mostly positive feedback from participants. Changes and additions were made to the objectives of the Program and specific projects in response to feedback received. 

There had been several decades of debate about the potential closure of the train line, including community consultations in 2006 and 2009. However, the final decision to close the train line was made and announced in 2012 without a specific community consultation. HCCDC states that consultation with industry and business representatives constitutes community consultation because industry representatives are also members of the community. This does not meet good practice standards because it is not a representative sample of the community.

There was no community consultation on the decision to build a light rail. There were subsequent opportunities for members of the community to comment on the implementation options, but the decision to build it had already been made. A community and industry consultation was held on which route the light rail should use, but the results of this were not made public. 

Recommendation
For future infrastructure programs, NSW Government agencies should consult with a wide range of stakeholders before major decisions are made and announced, and report publicly on the results and outcomes of consultations. 

The governance arrangements that were in place during the planning stages of the Program did not provide effective oversight. Project leadership and oversight improved during the implementation phase of the Program.

Multi-agency coordination and oversight were ineffective during the planning stages of the Program. Examples include: multiple versions of Program objectives being in circulation; unclear reporting lines for project management groups; and poor role definition for the initial advisory board. Program ownership was clarified in mid-2016 with the appointment of a new Program Director with clear accountability for the delivery of the Program. This was supported by the creation of a multi-agency steering committee that was more effective than previous oversight bodies.

The limitations that existed in multi-agency coordination and oversight had some negative consequences in important aspects of project management for the Program. This included whole-of-government benefits management and the coordination of work to mitigate impacts of the Program on small businesses.

Recommendations
For future infrastructure programs, NSW Government agencies should: 

  • develop and implement a benefits management approach from the beginning of a program to ensure responsibility for defining benefits and measuring their achievement is clear
  • establish whole-of-government oversight early in the program to guide major decisions. This should include:
    • agreeing on objectives and ensuring all agencies understand these
    • clearly defining roles and responsibilities for all agencies
    • establishing whole-of-government coordination for the assessment and mitigation of the impact of major construction projects on businesses and the community.

By March 2019, the Hunter and Central Coast Development Corporation should update and implement the Program Benefits Realisation Plan. This should include:

  • setting measurable targets for the desired benefits
  • clearly allocating ownership for achieving the desired benefits
  • monitoring progress toward achieving the desired benefits and reporting publicly on the results.

Appendix one - Response from agencies    

Appendix two - About the audit

Appendix three - Performance auditing

 

Parliamentary reference - Report number #310 - released 12 December 2018

Published

Actions for Fraud controls in local councils

Fraud controls in local councils

Local Government
Fraud
Internal controls and governance
Management and administration
Risk

Many local councils need to improve their fraud control systems, according to a report released today by the Auditor-General for New South Wales, Margaret Crawford. The report highlights that councils often have fraud control procedures and systems in place, but are not ensuring people understand them and how they work. There is also significant variation between councils in the quality of their fraud controls.

Fraud can directly influence councils’ ability to deliver services, and undermine community confidence and trust. ICAC investigations, such as the recent Operation Ricco into the former City of Botany Bay Council, show the financial and reputational damage that major fraud can cause. Good fraud control practices are critical for councils and the community. 

The Audit Office of New South Wales 2015 Fraud Control Improvement Kit (the Kit) aligns with the Fraud and Corruption Control Standard AS8001-2008 and identifies ten attributes of an effective fraud control system. This audit used the Kit to assess how councils manage the risk of fraud. It identifies areas where fraud control can improve. 

Fraud can disrupt the delivery and quality of services and threaten the financial stability of councils.

Recent reviews of local government in Queensland and Victoria identify that councils are at risk of fraud because they purchase large quantities of goods and services using devolved decision making arrangements. The Queensland Audit Office in its 2014–15 report 'Fraud Management in Local Government' found that ‘Councils are exposed to high-risks of fraud and corruption because of the high volume of goods and services they procure, often from local suppliers; and because of the high degree of decision making vested in councils'. They also highlight some common problems faced by councils including the absence of fraud control plans and failure to conduct regular reviews of their internal controls. Also, in 2008 and 2012 the Victorian Auditor-General identified the importance of up-to-date fraud control planning, clearly documented related policies, training staff to identify fraud risks and the importance of controls such as third party management. 

Investigations into councils by the NSW Independent Commission Against Corruption (ICAC), such as the recent Operation Ricco, show the impact that fraud can have on councils. These impacts include significant financial loss, and negative public perceptions about how well councils manage fraud. The findings of these investigations also show the importance of good fraud controls for councils.

Operation Ricco

In its report on Operation Ricco, the ICAC found that the Chief Financial Officer (CFO) of the City of Botany Bay Council and others dishonestly exercised official functions to obtain financial benefits for themselves and others by causing fraudulent payments from the Council for their benefit. It also identified the CFO received inducements for favourable treatment of contractors.

The report noted that there were overwhelming failures in the council’s procedures and governance framework that created significant opportunities for corruption, of which the CFO and others took advantage.

It found weaknesses across a wide variety of governance processes and functions, including those involving the general manager, the internal audit function, external audit, and the operation of the audit committee.

Source: Published reports of ICAC investigations July 2017.

The strength of fraud control systems varies significantly across New South Wales local councils, and many councils we surveyed need to improve significantly. 

Most surveyed councils do not have fraud control plans that direct resources to mitigating the specific fraud risks they face. Few councils reported that they conduct regular risk assessments or health checks to ensure they respond effectively to the risks they identify. 

There are sector wide weaknesses that impact on the strength of councils' fraud control practice. Less than one-third of councils that responded to the survey:

  • communicate their expectations about ethical conduct and responsibility for fraud control to staff 
  • regularly train staff to identify and respond to suspected fraud
  • inform staff or the wider community how to report suspected fraud and how reports made will be investigated.

The audit also identified a pattern of councils developing policies, procedures or systems without ensuring people understand them, or assessing that they work. This reduces the likelihood that staff will actually use them. 

In general, metropolitan and regional councils surveyed have stronger fraud control systems than rural councils. 

Newly amalgamated councils are operating with systems inherited from two or more pre-amalgamated councils. These councils are developing new systems for their changed circumstances.

Five councils surveyed reported that they did not comply with the Public Interest Disclosure Act 1994

Observations for the sector:
Councils should improve their fraud controls by:

  • tailoring fraud control plans to their circumstances and specific risks
  • systematically and regularly reviewing their fraud risks and fraud control systems to keep their plans up to-date
  • effectively communicating fraud risks, and how staff and the community can report suspected fraud 
  • ensuring that they comply with the Public Interest Disclosure Act 1994.

Recommendation:
That the Office of Local Government: 

  • work with councils to ensure they comply with the Public Interest Disclosure Act 1994.
     
Despite several New South Wales state entities collecting data on suspected fraud, the cost, extent, and nature of fraud in local councils is not clear. 
There are weaknesses in data collection and categorisation. Several state entities receive complaints about councils. These entities often do not separate complaints about fraud from other complaint data, do not separate local council data from other public-sector data, and do not separate complaints about council decisions or councillors from complaints about council staff conduct. Complaints about one incidence of suspected fraud can also be reported multiple times. 
Collaboration between state entities and councils to address these weaknesses in data collection could provide a clearer picture to the public and councils on the incidence of suspected fraud. Better information may also help councils decide where to focus fraud control efforts and apply resources more effectively.
Including measures for fraud control strength and maturity in the OLG performance framework may also improve practice in councils. Further, OLG may want to consider how a revised Model Code could better drive fraud control practice in councils.
Recommendations
That the Office of Local Government:
  •  work with state entities and councils to develop a common approach to how fraud complaints and incidences are defined and categorised so that they can:
    • better use data to provide a clearer picture of the level of fraud within councils
    • measure the effectiveness of, and drive improvement in councils' fraud controls systems

Published

Actions for Signal failures on the metropolitan rail network

Signal failures on the metropolitan rail network

Transport
Information technology
Infrastructure
Internal controls and governance
Project management
Risk
Service delivery

Between 2004 and 2006, the number of signalling failures, signalling downtime and the number of trains delayed as a result of signal failures all fell. RailCorp’s on-time running performance improved over the same period. The fall in failures is a clear indication of improved performance. Changes in the definition of on-time and to the timetable during 2005 and 2006 however make it difficult to determine whether improvements in response downtime and signalling delays are due to a true performance improvement. To build upon this strong base, RailCorp needs to determine with more confidence the number and duration of signalling failures the network can tolerate without impacting on service levels.

 

Parliamentary reference - Report number #170 - released 15 August 2007