Reports
Actions for Volume Nine 2015 Planning and Environment
Volume Nine 2015 Planning and Environment
The NSW Environment Protection Authority has reduced the average time to assess contaminated sites from 203 days in 2013-14 to 73 days in 2014-15. It is also improving transparency by making more information on its performance publicly available.
In 2014-15, the Department of Planning and Environment increased new housing approvals across New South Wales by 12 per cent to 58,252, exceeding the State priority target of 50,000. It also reduced the time taken to assess major projects from about three years in 2013-14 to four months in 2014-15.
Actions for Volume Seven 2015 Part One Law and Order
Volume Seven 2015 Part One Law and Order
Many factors are contributing to the overcrowding of the NSW prison system. This is in turn putting pressure on operations in the courts, and could ultimately impact rates of reoffending.
The lack of capacity is impacting more than just the NSW prison system. Over the weekend of 31 October 2015 some inmates held by the NSW Police Force could not be brought before a court because of capacity shortages.
This was one of the findings reported in Volume Seven 2015 of the Auditor-General’s Report to Parliament, which covers law and order services provided by the NSW Police Force, Department of Justice, and NSW Trustee and Guardian.
Actions for Volume Seven 2015 Part Two Emergency Services
Volume Seven 2015 Part Two Emergency Services
Demand for emergency services increased by eight per cent, in response to 187,282 incidents during 2014-15. Total volunteer numbers have risen over the last three years by 2.4 per cent to 98,536, improving capacity to deal with such incidents. NSW Rural Fire Service had only five emergency declarations in 2014-15 compared to 48 the year before, resulting in natural disaster expenditure falling by $89.0 million.
Fire and Rescue NSW response time to incidents and NSW Rural Fire Service fire containment continue to improve.
These are some of the matters highlighted in Part 2 of Volume Seven 2015 of the Auditor-General’s Report to Parliament, which covers emergency services agencies.
Actions for Volume Five 2015 Premier and Cabinet
Volume Five 2015 Premier and Cabinet
Volume Five 2015 covered Premier and Cabinet agencies such as the Department of Premier and Cabinet, Office of Sport, Venues NSW, Barangaroo Delivery Authority and Infrastructure NSW.
Actions for Government advertising 2015
Government advertising 2015
The Government Advertising Act 2011 requires the Auditor-General to conduct an annual performance audit to check NSW Government agency compliance with the Act.
This audit focused on the Department of Premier and Cabinet’s (DPC) role in monitoring government agencies compliance with government advertising requirements, and examined advertising campaigns run by Destination NSW and the Sydney Opera House.
Parliamentary reference - Report number #253 - released 22 June 2015
Actions for Large construction projects
Large construction projects
The independent assurance given to the NSW Government and sponsor agencies on the viability of large capital projects throughout their lifecycle is inadequate. Government policy is regularly not followed and not properly communicated to those responsible for implementing such policy.
This audit sought to test the effectiveness of the NSW capital project assurance system - which includes gateway reviews and reporting - but significant levels of non-compliance identified in our case studies prevented this. The NSW Commission of Audit also identified this issue in 2012. Gateway reviews are conducted by independent reviewers at key stages of a project’s life cycle and provide an independent assessment on a project’s readiness to proceed to the next stage.
Parliamentary reference - Report number #252 - released 7 May 2015
Actions for Country towns water supply and sewerage program
Country towns water supply and sewerage program
The Country Towns Water Supply and Sewerage Program has effectively promoted adoption of better management practices by local water utilities, but will not achieve its objective of eliminating the water supply and sewerage infrastructure backlog in urban areas of country NSW.
The $1.2 billion Program aims to help local water utilities provide appropriate, affordable, cost effective and well-managed water supply and sewerage services in the urban areas of country NSW. It has two broad elements:
- promoting adoption of better practices
- providing financial assistance towards the capital cost of infrastructure backlog works.
Parliamentary reference - Report number #251 - released 4 May 2015
Actions for Areas of focus from 2014
Areas of focus from 2014
Actions for WestConnex: Assurance to the Government
WestConnex: Assurance to the Government
This audit assesses the assurance provided to the NSW Government for the initial stages of the WestConnex project.
The audit examined the WestConnex project from concept development to the pre-tender phase for Stage 1A – M4 (Parramatta to Homebush Bay). It did not examine the merit of the project or whether it represented value-for-money.
This audit found a number of shortcomings with the governance of the WestConnex project during its early stages and makes recommendations on how to better govern the remainder of the project to minimise the risk of failure.
Parliamentary reference - Report number #247 - released 18 December 2014
Actions for Volume Eight 2014 Focusing on Police and Justice (Law, Order and Emergency Services)
Volume Eight 2014 Focusing on Police and Justice (Law, Order and Emergency Services)
The quality of financial reporting in the cluster continues to improve with the number of reported misstatements identified during audit decreasing over the past five years. The audits resulted in unqualified audit opinions on the financial statements of all cluster agencies for the year ended 30 June 2014, with the exception of the State Emergency Service.