Published

Actions for Complaints and Review Processes, and Provision of Industry Assistance

Complaints and Review Processes, and Provision of Industry Assistance

Justice
Industry
Management and administration

In response to the 1999 audit, both Offices focussed on improving the transparency and consistency of decisions. Both introduced client service standards and implemented systems to improve their management of complaints. In addition, the Office of the Protective Commissioner (OPC) introduced six monthly financial statements which are sent to clients or their carers. However, there are three recommendations from the 1999 audit that are not fully implemented although progress has been made in addressing the issues. These matters relate to establishing external appeal mechanisms and the review of OPC client fees.

 

Parliamentary reference - Report number #117 - released 24 September 2003

Published

Actions for Freedom of Information

Freedom of Information

Transport
Premier and Cabinet
Education
Management and administration
Regulation
Service delivery

Freedom of Information (FOI) Coordinators and their staff were supportive of the legislation. However, the agencies examined can do considerably more to fully achieve the intentions of the Act. On the positive side, all three agencies had processes in place to handle requests and had made a number of changes to improve the effectiveness of the FOI process. Fees and charges had also been kept to a minimum. No processing fees were requested in the majority of cases, and if charged, were not unreasonable.

 

Parliamentary reference - Report number #114 - released 28 August 2003

Published

Actions for Northside Storage Tunnel Project

Northside Storage Tunnel Project

Planning
Environment
Infrastructure
Internal controls and governance
Procurement
Project management
Service delivery

The Northside Storage Tunnel was the first major public sector construction project using an alliance approach. In our opinion, the outcome of the project suggests that an alliance approach, when applied to a suitable project and managed appropriately, can support positive project outcomes. And in many respects the Alliance worked well. There are, however, a number of issues that we believe need to be addressed for future alliances.

 

Parliamentary reference - Report number #113 - released 24 July 2003

Published

Actions for Implementing the Ovine Johne's Disease Program

Implementing the Ovine Johne's Disease Program

Industry
Internal controls and governance
Regulation
Service delivery
Shared services and collaboration

The implementation of the Ovine Johne's Disease (OJD) program in New South Wales has been prolonged and difficult. In our view, the OJD Program in New South Wales has experienced two major difficulties with its implementation: the lack of a strategic approach to program management, and an ill-defined governance structure. Both the NSW Government and industry need to be better organised and improve the planning, direction and co-ordination of the OJD Program and future programs.

 

Parliamentary reference - Report number #107 - released 26 February 2003

Published

Actions for Lease to Fox Studios Australia

Lease to Fox Studios Australia

Premier and Cabinet
Asset valuation
Infrastructure
Management and administration
Procurement
Project management

The audit found that the process for the lease and development of the Showground site commenced on the basis that no Government moneys would be provided and no theme park activities would be allowed. However despite this a State Government subsidy of between $84.8m and $106.8m (in net present value terms) is to be provided for the development and the area of the Showground to be leased to Fox was extended to comprise 24.3 hectares of the 28.8 hectare site to allow Fox also to develop a family entertainment park.

The audit also found that the process commenced under the former Government were intended to ensure that no one party was placed above another however, the actual processes employed up to the General Election in March 1995 were so flawed as not to be relied upon to select a preferred proponent or to justify dispensing with a tender process.

 

Parliamentary reference - Report number #44 - released 8 December 1997

Published

Actions for Redundancy arrangements

Redundancy arrangements

Industry
Planning
Compliance
Management and administration
Workforce and capability

The audit identified that overall the agencies had carried out the redundancy process satisfactorily and the process, with some exceptions, complied with Government and internal policies. Government policy states that performance problems should be dealt with by managing the performance of the employee rather than restructuring/redundancy processes. In a limited number of instances certain employees, whose performance had been questioned, had been offered and accepted voluntary redundancy.

The audit also indicates that the process of redundancies has resulted in lower salary costs, in real dollar terms, without undue increase in either overtime or consultancy costs nor any detrimental effect on service quality. However, it is noted that the decrease in staffing levels occurred exclusively in the non-budget sector. Budget sector staffing levels increased by 1.4 per cent during 1989-95. There are also signs that the need for and the benefits arising out of redundancies are not well planned or measured. The need for redundancies often arises from a desire to reduce staff related costs while there is no comparison of the costs of redundancy compared to benefits.

 

Parliamentary reference - Report number #37 - released 17 April 1997

Published

Actions for Review of NSW Agriculture

Review of NSW Agriculture

Industry
Asset valuation
Infrastructure
Internal controls and governance
Management and administration
Workforce and capability

Following a request from the NSW Legislative Council in September 1996, a performance audit into various matters affecting the operation of the New South Wales Department of Agriculture was undertaken by The Audit Office.

Among the recommendations from this report, the Audit Office found that:

  • An economic appraisal should be undertaken before all major developments, including rationalisation plans, are implemented. It should include details of anticipated benefits from the changes planned, so that their achievement can be evaluated after implementation.

  • Government policies should be made explicit or else established by directives in writing. Planning Infrastructure and human resources should be planned to maximise efficiency and effectiveness. If Government chooses alternatives that have higher costs or lower benefits for the Department, then these should be explicitly funded.

  • The Department should strengthen its system of internal control by strengthening the role of the Board of Management as a means of management control, directing an overhaul of the Charter of the Internal Audit Committee and using it to drive the Department’s internal audit function and ensuring implementation of an effective financial management information system.

 

Parliamentary reference - Report number #36 - released 27 March 1997