Refine search Expand filter

Reports

Search filters applied: industry, planning, premier and cabinet AND 2003 AND published .

Published

Actions for Complaints and Review Processes, and Provision of Industry Assistance

Complaints and Review Processes, and Provision of Industry Assistance

Justice
Industry
Management and administration

In response to the 1999 audit, both Offices focussed on improving the transparency and consistency of decisions. Both introduced client service standards and implemented systems to improve their management of complaints. In addition, the Office of the Protective Commissioner (OPC) introduced six monthly financial statements which are sent to clients or their carers. However, there are three recommendations from the 1999 audit that are not fully implement

Published

Actions for Freedom of Information

Freedom of Information

Transport
Premier and Cabinet
Education
Management and administration
Regulation
Service delivery

Freedom of Information (FOI) Coordinators and their staff were supportive of the legislation. However, the agencies examined can do considerably more to fully achieve the intentions of the Act. On the positive side, all three agencies had processes in place to handle requests and had made a number of changes to improve the effectiveness of the FOI process. Fees and charges had also been kept to a minimum. No processing fees were requested in the majority

Published

Actions for Northside Storage Tunnel Project

Northside Storage Tunnel Project

Planning
Environment
Infrastructure
Internal controls and governance
Procurement
Project management
Service delivery

The Northside Storage Tunnel was the first major public sector construction project using an alliance approach. In our opinion, the outcome of the project suggests that an alliance approach, when applied to a suitable project and managed appropriately, can support positive project outcomes. And in many respects the Alliance worked well. There are, however, a number of issues that we believe need to be addressed for future alliances.   Parliamentary ref

Published

Actions for Implementing the Ovine Johne's Disease Program

Implementing the Ovine Johne's Disease Program

Industry
Internal controls and governance
Regulation
Service delivery
Shared services and collaboration

The implementation of the Ovine Johne's Disease (OJD) program in New South Wales has been prolonged and difficult. In our view, the OJD Program in New South Wales has experienced two major difficulties with its implementation: the lack of a strategic approach to program management, and an ill-defined governance structure. Both the NSW Government and industry need to be better organised and improve the planning, direction and co-ordination of the OJD Prog