Reports
Actions for WestConnex: Assurance to the Government
WestConnex: Assurance to the Government
This audit assesses the assurance provided to the NSW Government for the initial stages of the WestConnex project. The audit examined the WestConnex project from concept development to the pre-tender phase for Stage 1A – M4 (Parramatta to Homebush Bay). It did not examine the merit of the project or whether it represented value-for-money. This audit found a number of shortcomings with the governance of the WestConnex project during its early stages and
Actions for Managing Contaminated Sites
Managing Contaminated Sites
NSW Government agencies with large landholdings need to better manage their contaminated sites. When contaminated sites are reported to the Environmental Protection Authority (EPA) there are long delays in assessing the extent of contamination. The EPA also lacks the management controls to ensure that all significantly contaminated sites are actively monitored and key milestones for remediation are met. Parliamentary reference - Report number #
Actions for Volume Eight 2013 focusing on Transport and Ports
Volume Eight 2013 focusing on Transport and Ports
Unqualified audit opinions were issued on the above corporations’ 30 June 2013 financial statements. During the year, Treasury issued TC 13/01 ‘Mandatory early close procedures for 2013’. This Circular aimed to improve the quality and timeliness of agencies’ annual financial statements. In 2012-13, application of the circular was made mandatory for State owned corporations. As a result, the port corporations were required to perform the early close proce
Actions for Volume Four 2013 focusing on Electricity
Volume Four 2013 focusing on Electricity
During the year, Treasury issued TC 13/01 ‘Mandatory early close procedures for 2013’. This circular aimed to improve the quality and timeliness of agencies’ annual financial statements. In 2012-13, application of the circular was made mandatory for State owned corporations. As a result, the NSW Generators, Distributors and Transgrid were required to perform the early close procedures. All the electricity entities were broadly successful in performing th
Actions for Management of Historic Heritage in National Parks and Reserves
Management of Historic Heritage in National Parks and Reserves
The National Parks and Wildlife Service is spreading its resources too thinly, running the risk that the heritage significance of important assets will eventually be lost. Parliamentary reference - Report number #230 - released 29 May 2013
Actions for Management of the ClubGRANTS Scheme
Management of the ClubGRANTS Scheme
The ClubGRANTS scheme gives tax rebates to clubs for supporting their local community. Since 2002, $417 million of ClubGRANTS tax rebates have been given to clubs. The scheme recognises the valuable role played by registered clubs in their local communities. However, the public must have confidence that the scheme is delivering genuine services to the community. Parliamentary reference - Report number #229 - released 2 May 2013
Actions for Volume Eight 2012 focusing on Transport and Ports
Volume Eight 2012 focusing on Transport and Ports
We issued unqualified audit opinions on the transport entities’ 30 June 2012 financial statements. Some of the findings of the report include: government funding to the public transport operators totalled $4.4 billion in 2011-12 ($3.7 billion in 2010-11) passenger services revenue only covered 20 per cent of RailCorp's operating costs Transport for NSW has formalised a protocol to mitigate the risk of potential conflicts of interests
Actions for Volume Four 2012 focusing on Electricity
Volume Four 2012 focusing on Electricity
The audits of the seven State owned electricity corporations resulted in unqualified audit opinions. The electricity corporations’ end-of-year financial reporting is sound and well established, he added. After tax profits rose to $1.2 billion, up from $1.1 billion in 2010-11 and contributions to Government rose to $1.4 billion, up from $1.2 billion in 2010-11. These figures exclude profits and special dividends from the 2010-11 electricity sale
Actions for Volume One 2012 focusing on themes from 2011
Volume One 2012 focusing on themes from 2011
The following overview of audits from 2011 found agency restructures significantly impacted agency financial reporting processes, agencies are having difficulty establishing and enforcing compliance with their own policies and procedures, agencies experienced problems complying with regulations and providing adequate documentation to support their financial statements, the poor quality of some financial statements with 1,256 misstatements identified
Actions for Volume Eight 2011 Focus on Transport and Ports
Volume Eight 2011 Focus on Transport and Ports
The report includes comments on financial audits of government agencies in the Transport and Ports sectors. The audit of corporations’ financial statements for the year ended 30 June 2011 resulted in unmodified audit opinions within the Independent Auditor’s Reports. A key recommendation from the report is that Sydney Ports Corporation should continue working with other government authorities and industry stakeholders to improve the effect