Actions for Planning, Industry and Environment 2021

Planning, Industry and Environment 2021

Environment
Industry
Local Government
Planning
Asset valuation
Financial reporting
Information technology
Internal controls and governance
Risk

This report analyses the results of our audits of the Planning, Industry and Environment cluster agencies for the year ended 30 June 2021.

Our preferred approach is to table the ‘Report on State Finances’ in Parliament before any other cluster report. This is because the 'Report on State Finances' focuses on the audit results and observations relating to the Total State Sector Accounts, in effect a consolidation of all government agencies. This year the 'Report on State Finances' has been delayed due to significant accounting issues being considered in the Total State Sector Accounts and which may impact the Treasury and Transport clusters.

As there are no outstanding matters relating to audits in the Planning, Industry and Environment cluster impacting the Total State Sector Accounts we have decided to break with normal practice and table this cluster report ahead of the ‘Report on State Finances’.

What the report is about

The results of the Planning, Industry and Environment cluster agencies' financial statements audits for the year ended 30 June 2021.

What we found

Unmodified audit opinions were issued for all completed 30 June 2021 financial statements audits of cluster agencies. Three audits are ongoing.

An 'Other Matter' paragraph was included in the Independent Planning Commission's (the IPC) audit opinion because the prior year comparative figures were not audited. Prior to 2020–21, the IPC was not required to prepare separate financial statements under the Public Finance and Audit Act 1983 (PF&A Act). The financial reporting provisions of the Government Sector Finance Act 2018 now require the IPC to prepare financial statements.

The number of identified misstatements increased from 51 in 2019–20 to 54 in 2020–21.

The 2010–11 to 2019–20 audits of the Water Administration Ministerial Corporation’s (the Corporation) financial statements are incomplete due to insufficient records and evidence to support the transactions of the Corporation, particularly for the earlier years. Management has commenced actions to improve the governance and financial management of the Corporation. These audits are currently in progress and the 2020–21 audit will commence shortly.

There are 609 State controlled Crown land managers (CLMs) across New South Wales that predominantly manage small parcels of Crown land.

Eight CLMs prepared and submitted 2019–20 financial statements by the revised deadline of 30 June 2021. A further 24 CLMs did not prepare financial statements in accordance with the PF&A Act. The remaining CLMs were not required to prepare 2019–20 financial statements as they met NSW Treasury's financial reporting exemption criteria.

The Department of Planning, Industry and Environment's (the department) preliminary assessment indicates that 60 CLMs are required to prepare financial statements in 2020–21. To date, no CLMs have prepared and submitted financial statements for audit in 2020–21.

There are also 120 common trusts that have never submitted financial statements for audit. Common trusts are responsible for the care, control and management of land that has been set aside for specific use in a certain locality, such as grazing, camping or bushwalking.

What the key issues were

The number of matters we reported to management increased from 135 in 2019–20 to 180 in 2020–21, of which 40 per cent were repeat findings.

Seven high-risk issues were identified in 2020–21:

  • system control deficiencies at the department relating to user access to HR and payroll management systems, vendor master data management and journal processing, which require manual reviews to mitigate risks
  • deficiencies related to the Centennial Park and Moore Park Trust's tree assets valuation methodology
  • the Lord Howe Island Board did not regularly review and monitor privileged user access rights to key information systems
  • the Natural Resources Access Regulator identified and adjusted three prior period errors retrospectively, which indicate deficiencies within the financial reporting processes
  • deficiencies relating to the Parramatta Park Trust's tree assets valuation methodology
  • lease arrangements have not been confirmed between the Planning Ministerial Corporation and Office of Sport regarding the Sydney International Regatta Centre
  • the Wentworth Park Sporting Complex land manager (the land manager) has a $6.5 million loan with Greyhound Racing NSW (GRNSW). GRNSW requested the land manager to repay the loan. However, the land manager subsequently requested GRNSW to convert the loan to a grant. Should this request be denied, the land manager would not be able to continue as a going concern without financial support. This matter remains unresolved for many years.

There continues to be significant deficiencies in Crown land records. The department uses the Crown Land Information Database (CLID) to record key information relating to Crown land in New South Wales that are managed and controlled by the department and land managers (including councils and land managers controlled by the state). The CLID system was not designed to facilitate financial reporting and the department is required to conduct extensive adjustments and reconciliations to produce accurate information for the financial statements.

The department is implementing a new system to record Crown land (the CrownTracker project). The department advised that the project completion date will be confirmed by June 2022.

What we recommended

The department should ensure CLMs and common trusts meet their statutory reporting obligations.

Cluster agencies should prioritise and action recommendations to address internal control deficiencies, with a focus on addressing high-risk and repeat issues.

The department should prioritise action to ensure the Crown land database is complete and accurate. This will allow the department and CLMs to be better informed about the Crown land they control.

Fast facts

The Planning, Industry and Environment cluster aims to make the lives of people in New South Wales better by developing well-connected communities, preserving the environment, supporting industries and contributing to a strong economy.

There are 54 agencies, 609 State controlled Crown land managers that predominantly manage small parcels of Crown land and 120 common trusts in the cluster.

  • 42% of the area of NSW is Crown land
  • $33.2b water and electricity infrastructure as at 30 June 2021
  • 100% unqualified audit opinions were issued for all completed 30 June 2021 financial statements audits
  • 7 high-risk management letter findings were identified
  • 54 monetary misstatements were reported in 2020–21
  • 40% of reported issues were repeat issues

This report provides parliament and other users of the Planning, Industry and Environment cluster (the cluster) agencies’ financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision-making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Planning, Industry and Environment cluster (the cluster) for 2021.

Section highlights

  • Unmodified audit opinions were issued for all completed 30 June 2021 financial statements audits of cluster agencies. Three audits are ongoing.
  • An 'Other Matter' paragraph was included in the Independent Planning Commission’s (the IPC) audit opinion because the prior year comparative figures were not audited. Prior to 2020–21, the IPC was not required to prepare separate financial statements under the Public Finance and Audit Act 1983. From 2020–21, the IPC is required to prepare financial statements under the Government Sector Finance Act 2018.
  • The 2010–11 to 2019–20 audits of the Water Administration Ministerial Corporation’s (the Corporation) financial statements were incomplete due to insufficient records and evidence to support the transactions of the Corporation, particularly for the earlier years. These audits are currently underway, and the 2020–21 audit will commence shortly.
  • The Department of Planning, Industry and Environment's (the department) preliminary assessment indicates that 60 State controlled Crown land managers (CLMs) are required to prepare financial statements in 2020–21. To date, no CLMs have prepared and submitted financial statements for audit in 2020–21. All 120 common trusts have never submitted their financial statements for audit. The department needs to do more to ensure that the CLMs and common trusts meet their statutory reporting obligations.
  • Nine agencies that were required to perform early close procedures did not complete a total of 20 mandatory procedures. The most common incomplete early close procedures include the revaluation of property, plant and equipment, documenting all significant management judgments and assumptions, and the implementation of new and updated accounting standards.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision-making.

This chapter outlines our observations and insights from our financial statements audits of agencies in the Planning, Industry and Environment cluster.

Section highlights

  • The number of findings reported to management has increased from 135 in 2019–20 to 180 in 2020–21, and 40 per cent were repeat issues.
  • Seven high-risk issues were identified in 2020–21, and three high-risk findings were repeat issues.
  • There continues to be significant deficiencies in Crown land records. The department should prioritise action to ensure the Crown land database is complete and accurate.

Appendix one - Misstatements in financial statements submitted for audit

Appendix two – Early close procedures

Appendix three – Timeliness of financial reporting

Appendix four – Financial data

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Health 2021

Health 2021

Health
Asset valuation
Compliance
Cyber security
Financial reporting
Infrastructure
Internal controls and governance
Procurement

This report analyses the results of our audits of the Health cluster agencies for the year ended 30 June 2021.

Our preferred approach is to table the ‘Report on State Finances’ in Parliament before any other cluster report. This is because the 'Report on State Finances' focuses on the audit results and observations relating to the Total State Sector Accounts, in effect a consolidation of all government agencies. This year the 'Report on State Finances' has been delayed due to significant accounting issues being considered in the Total State Sector Accounts and which may impact the Treasury and Transport clusters.

As there are no outstanding matters relating to audits in the Health cluster impacting the Total State Sector Accounts we have decided to break with normal practice and table this cluster report ahead of the ‘Report on State Finances’.

What the report is about

The results of Health cluster (the cluster) agencies' financial statements audits for the year ended 30 June 2021.

What we found

Unmodified audit opinions were issued for the financial statements of all Health cluster agencies.

The COVID-19 pandemic increased the complexity and number of accounting matters faced by the cluster. The total gross value of corrected misstatements in 2020–21 was $250.2 million, of which $226.0 million were pandemic related.

A qualified audit opinion was issued on the Annual Prudential Compliance Statement. The basis of the qualification related to 19 instances (18 in 2018–19) of non-compliance relating to three of the 20 prudential requirements across five aged care facilities.

What the key issues were

The total number of matters we reported to management across the cluster increased from 112 in 2019–20 to 116 in 2020–21. Of the 116 issues raised in 2020–21, three were high risk (one in 2019–20) and 57 were moderate risk (47 in 2019–20). Nearly one half of the issues were repeat issues.

The three new high-risk issues identified were:

Hotel Quarantine (HQ) fees

The absence of a tailored debt recovery strategy, data integrity issues and uncertainties around future HQ arrangements increased risks around the recoverability of HQ fees from travellers.

COVID-19 inventories

Data errors and anomalies in the impairment model and difficulties forecasting key factors impacting the management of Personal Protective Equipment (PPE) increased uncertainty associated with the valuation and impairment of COVID-19 inventories.

COVID-19 vaccines

The Commonwealth did not provide information about the cost of vaccines provided to NSW free of charge, which required the performance of internal valuations to reflect the consumption of vaccines in the financial statements.

What we recommended

Hotel Quarantine (HQ) fees

Develop a tailored assessment methodology to estimate recoverability of HQ fees and work with Revenue NSW to develop a tailored debt recovery strategy.

COVID-19 inventories

Review the current stocktaking and impairment methodology to incorporate validation of data key to the management of COVID-19 related PPE.

COVID-19 vaccines

Work with the Commonwealth to obtain primary price information on COVID-19 vaccines.

Fast facts

The Health cluster, comprising 15 local health districts, five pillars agencies, two specialty health networks and six shared state-wise services agencies, deliver health services to the people of New South Wales.

  • 100% unqualified audit opinions were issued on agencies' 30 June 2021 financial statements
  • 24 monetary misstatements were reported in 2020–21
  • high risk management letter findings were identified
  • 47.4% of reported issues were repeat issues
  • $23.5b property, plant and equipment as at 30 June 2021
  • $26.8b total expenditure incurred in 2020–21

This report provides Parliament and other users of the Health cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision-making are enhanced when financial reporting is accurate and timely. This chapter outlines our audit observations related to the financial reporting of agencies in the Health cluster (the cluster) for 2021.

Section highlights

  • Unqualified audit opinions were issued for all cluster agencies required to prepare general-purpose financial statements.

  • The total gross value of all corrected monetary misstatements for 2020–21 was $250.2 million, of which $226.0 million were related to complexities arising from the COVID-19 pandemic.

  • A qualified audit opinion was issued on the Ministry's Annual Prudential Compliance Statement.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision-making. This chapter outlines our observations and insights from our financial statement audits of agencies in the Health cluster.

Section highlights

  • The total number of internal control deficiencies has increased from 112 issues in 2019–20 to 116 in 2020–21. Of the 116 issues raised in 2020–21, three were high (one in 2019–20) and 57 were moderate (47 in 2019–20); with nearly one half of all control deficiencies reported in 2020–21 being repeat issues.
  • The complexities arising from accounting for agreements between governments to respond to the COVID-19 pandemic presented three new high risk audit findings with respect to the:
    • expected rate of recoverability of outstanding Hotel Quarantine fees
    • procurement, stocktaking and impairment of COVID-19 inventories
    • valuation and recognition of COVID-19 vaccines received from the Commonwealth Government.
  • Management of excessive leave balances and poor quality or lack of documentation supporting key agreements were amongst the repeat issues observed again in the 2020–21 financial reporting period.

Findings reported to management

The number of findings reported to management has increased, with 47.4 per cent of all issues being repeat issues

Breakdowns and weaknesses in internal controls increase the risk of fraud and error. Deficiencies in internal controls, matters of governance interest and unresolved issues were reported to management and those charged with governance of cluster agencies. The Audit Office does this through our management letters, which include observations, implications, recommendations and risk ratings.

In 2020–21, there were 116 findings raised across the cluster (112 in 2019–20). 47.4 per cent of all issues were repeat issues (38.4 per cent in 2019–20).

A delay in implementing audit recommendations increases the risk of intentional and accidental errors in processing information, producing management reports and generating financial statements. This can impair decision-making, affect service delivery and expose agencies to fraud, financial loss and reputational damage. Poor controls may also mean agency staff are less likely to follow internal policies, inadvertently causing the agency not to comply with legislation, regulation and central agency policies.

The table below describes the common issues identified across the cluster by category and risk rating.

Risk rating Issue
Information technology

Moderate2
7 new,
3 repeat

We identified the need for agencies to improve information technology processes and controls that support the integrity of financial data used to prepare agencies' financial statements. Of particular concern are issues associated with:

  • lack of reviews of user access and privileged user access for
  • HealthRoster
  • Assets and Facilities Management Online
  • vMoney Powerhouse
  • Patient Billing and Revenue Collection system.

Repeat issues included:

  • deficient password controls
  • no independent review for data integrity of any changes made to HealthRoster
  • incomplete reviews of StaffLink User Access.

Low1
4 new,
5 repeat

Internal control deficiencies or improvements

High3

1 new, 

0 repeat

We identified internal control weaknesses across key business processes, including new issues relating to:

  • procurement, stocktaking and impairment of COVID-19 inventories (personal protective equipment)
  • instances where employees' timesheets were approved in advance
  •  monthly reconciliations not reviewed in a timely manner
  • asset revaluation processes at Illawarra Shoalhaven Local Health District.
     

Repeat issues included:

  • forced finalisation of rosters in order to finalise processing of payroll
  • partial repeat issue relating to HealthShare NSW's stocktake process, refer to details in the following section of this report.

Moderate2
6 new,
12 repeat

 Low1
10 new,
4 repeat

Financial reporting

High3

2 new, 
0 repeat

We identified weaknesses with respect to financial reporting in relation to the:

  • expected rate of recoverability of outstanding Hotel Quarantine fees
  • valuation and recognition of COVID-19 vaccines received from the Commonwealth Government
  • application of AASB 16 'Leases'
  • improvement in health agencies' grant register to better support management's accounting treatment under the applicable revenue accounting standards.

Moderate2
6 new,
1 repeat

Low1
8 new,
3 repeat

Governance and oversight
Moderate2
9 new,
5 repeat

We identified opportunities for agencies to improve governance and oversight processes, including:

  • ensure better documentation around governance arrangements for major health capital works delivered by Health Infrastructure
  • absence of documented practices at health agencies level relating to Visiting Medical Officer claims.
     

Repeat issues include:

  • delegations manual for Health Infrastructure remains in draft and has done so since 2017.
Low1
2 new,
2 repeat
Non-compliance with key legislation and/or central agency policies
Moderate2
1 new,
7 repeat

We identified the need for agencies to improve compliance with key legislation and central agency policies, with new findings including:

  • bank signatories list not updated to remove terminated employees
  • subsequent changes made to Junior Medical Officers' approved rosters not approved by an authorised delegate.
     

Repeat issues include:

  • management of excessive annual leave
  • non-compliance with the Government Information (Public Access) Act 2009 (GIPA Act) by Ambulance NSW.
Low1
5 new,
13 repeat

4Extreme risk from the consequence and/or likelihood of an event that has had, or may have a negative impact on the entity.
3 High risk from the consequence and/or likelihood of an event that has had, or may have a negative impact on the entity.
2 Moderate risk from the consequence and/or likelihood of an event that has had, or may have a negative impact on the entity.
1 Low risk from the consequence and/or likelihood of an event that has had, or may have a negative impact on the entity.

Note: Management letter findings are based either on final management letters issued to agencies, or draft letters where findings have been agreed with management.

Complexities arising from the COVID-19 response

The 2020–21 audit identified three new high-risk findings

COVID-19 has presented the cluster with several new accounting challenges. New and evolving matters arose from changes to operating conditions, which characterised the 2020–21 financial reporting period. Issues with a high degree of estimation uncertainty will require ongoing attention as the strategies employed to deal with the COVID-19 pandemic evolve.

Expected rate of recovery of outstanding Hotel Quarantine invoices

The estimation of the amount likely to be recovered is complicated not only by the uncertainties that exist regarding the assumptions those estimations rely upon, but also the debt collection processes and strategies put into place to manage the accumulated debtors' balance. Debt collection is not administered by the cluster, but rather Revenue NSW. We observed an absence of a methodology to assess the likelihood of recovery. Instead, Sydney Local Health District was relying on Revenue NSW to develop and execute on a collection strategy. Sydney Local Health District was using the same approach to hotel quarantine debts as it did to other Health receivables. As the approach to managing international borders evolves over time, so too will the cluster's need to develop robust estimation models to assess the likely collectability of debtors. 

Procurement, management and impairment of COVID-19 inventories

$656.2 million of COVID-19 inventories were procured in 2020–21, with $220.2 million consumed; $558.7 million impaired and a further $217.1 million written off. Estimates of the degree to which inventories are expired, not fit for purpose or are faulty is often based on management judgement at all stages in the procurement cycle.

With respect to the stocktaking methodology applied, the following issues were identified:

  • discrepancies noted in the stock bin listing provided for audit
  • discrepancies in the recount sheet generated
  • inconsistent application of the stocktake methodology
  • inconsistent labelling of quarantined stock
  • a lack of an approach for validating stock expiry dates, which is a key input to the impairment calculations.

Although management had developed processes and a methodology to count as well as to assess the level of inventory that was not fit for purpose, ongoing attention to the operating environment that emerges post pandemic will be important in assessing the degree to which existing COVID-19 inventories can be integrated into a ‘business as usual’ model going forward. Further refinement of the key elements of the stocktaking methodology will also be required to ensure that key inputs upon which management relies to calculate the year-end inventory impairment provision can be appropriately validated.

Valuation and recognition of COVID-19 vaccines received from the Commonwealth Government

The 2020–21 financial reporting period saw the Commonwealth acquire COVID-19 vaccines and provide these to state jurisdictions to dispense to their communities. The vaccines, although provided free of charge require recognition. However, Health entities were not responsible for acquiring the vaccines and data on the vaccines' cost was not shared by the Commonwealth. Management undertook a valuation using publicly available data to estimate the value to attribute to the vaccine inventory; developed new systems and leveraged existing pharmacy systems to track physical quantities received from the Commonwealth and ultimately distributed to NSW citizens. As the response to the pandemic evolves, larger quantities, and new lines of vaccine stock will be dealt with, and policy settings will need to adapt when patterns of distribution of those vaccines (e.g., timing of third booster shots) emerge. The Ministry of Health will need to ensure that the valuations applied to the prices of inventory distributed and held in stock are as accurate as possible. This can be done through further refinement of the existing valuation methodology, obtaining price information from the Commonwealth and engaging specialist pharmaceutical valuers.

Emerging trends

Recognition of provisions without sufficient support

Several NSW Health entities raised accruals and provisions in 2020–21, which did not have an appropriate basis for recognition. Liabilities can only be recognised where there is a present obligation to make a payment arising from a past event. A number of these errors remain uncorrected in the financial statements of those entities as they are not material, individually or in aggregate to the financial statements as a whole. Increased training and guidance are required to ensure that treatment within the cluster is consistent and reflects events that have occurred and give rise to obligations.

Treatment of Commonwealth funding

In the 2020–21 and 2019–20 financial reporting periods, we observed prior period errors arising from the treatment of Commonwealth funding. These errors related to recognising revenue under funding agreements entered into with the Commonwealth in the incorrect period. The conditions of these funding arrangements, the transactional information requiring validation and the circumstances when revenue should be recognised are not always clear and can be complex. Early and continuous engagement with the Commonwealth is required to ensure that revenue recognition principles are consistently applied across the cluster.

Key repeat issues

Management of excessive annual leave

NSW Treasury guidelines stipulate annual leave balances exceeding 30 days are considered excess annual leave balances. Managing excess annual leave balances has been reported as an issue for the cluster for more than five years, with the average percentage of employees with excessive leave balances over the last five years being 36.1 per cent (35.5 per cent over five years covering 2015–16 to 2019–20).

The operational demands required to manage the COVID-19 pandemic have presented new challenges for the cluster in trying to manage its excessive leave balances. 39.2 per cent of employees now have excess leave balances at 30 June 2021 (35.4 per cent at 30 June 2020).

The state's leave policy C2020-12 Managing Accrued Recreation Leave Balances requires agencies to manage excessive leave balances to 30 days or less to maintain their workforces physical and mental health.

Accurate time recording

Forced-finalisation of time records by system administrators within HealthRoster remains an issue and we continue to observe time records forced-finalised by system administrators so pay runs can be finalised on a timely basis. During 2020–21, a total of two million (2.2 million in 2019–20) time records were force approved, which represents 5.7 per cent of total time records (6.9 per cent in 2019–20).

Existence, completeness and accuracy of key agreements

Delivery of major capital projects

Health Infrastructure (a division of the Health Administration Corporation) is responsible for the delivery of major capital projects with a budgeted spend of more than $10.0 million. Health Infrastructure oversee the planning, design, procurement, and construction phases. Capital works in progress are recognised in the financial statements of the health entity that intends to use those assets upon completion. The health entities recognise both the capital work in progress and the revenue associated with the capital funding from the Ministry for the construction of the assets. Capital funding is currently agreed with health entities as part of the annual Service Agreement. The assumption that the health entities control the assets during their construction is consistent with Health Infrastructure's role as an agent for the health entity and the Ministry's policy directive PD2020-033 'Management and control of Health Administration Corporation owned Real Property'.

We continued to observe a lack of clarity regarding agreements between Health Infrastructure, the Ministry and the cluster agency that will eventually receive the completed asset. This can lead to confusion and uncertainty around the rights and obligations of each party to the transaction.

Cross border patient funding arrangements

When patients require medical care in a jurisdiction where they are not generally domiciled, there are arrangements in place to provide funding to support cross border patient treatments. We have previously observed that agreements between NSW and other jurisdictions have not been finalised, and this continues to be the case. In the case of Victoria, no agreement has been finalised for the past seven years.

We continue to note that the cluster has long outstanding receivables and payables with other states. The absence of formal agreements between the states hampers the settlement of the debts relating to the treatment of cross border patients. The following table shows the status of Cross Border Agreements between NSW and other jurisdictions:

States 2014–15 2015–16 2016–17 2017–18 2018–19 2019–20 2020–21
Queensland Signed Signed Signed Signed Signed Not finalised Not finalised
Victoria Not finalised Not finalised Not finalised Not finalised Not finalised Not finalised Not finalised
Australian Capital Territory Signed Signed Signed Signed Signed Signed Not finalised
South Australia Signed Signed Signed Signed Signed Signed Not finalised
Tasmania Signed Signed Signed Signed Signed Signed Not finalised
Northern Territory Signed Signed Signed Signed Signed Signed Not finalised
Western Australia Signed Signed Signed Signed Signed Signed Not finalised

Albury Base Hospital

Albury Base hospital is located on the border of NSW and Victoria and services residents of both states. Documentation supporting the extension of the expired Intergovernmental Agreement 2009–2017 between NSW and Victoria in relation to the integration of health services in Wodonga and Albury could not be located.

Appendix one – Misstatements in financial statements submitted for audit

Appendix two – Early close procedures

Appendix three – Timeliness of financial reporting

Appendix four – Financial data

 

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Premier and Cabinet 2021

Premier and Cabinet 2021

Premier and Cabinet
Whole of Government
Asset valuation
Financial reporting
Infrastructure
Internal controls and governance
Shared services and collaboration

This report analyses the results of our audits of the Premier and Cabinet cluster agencies for the year ended 30 June 2021.

Our preferred approach is to table the ‘Report on State Finances’ in Parliament before any other cluster report. This is because the 'Report on State Finances' focuses on the audit results and observations relating to the Total State Sector Accounts, in effect a consolidation of all government agencies. This year the 'Report on State Finances' has been delayed due to significant accounting issues being considered in the Total State Sector Accounts and which may impact the Treasury and Transport clusters.

As there are no outstanding matters relating to audits in the Premier and Cabinet cluster impacting the Total State Sector Accounts we have decided to break with normal practice and table this cluster report ahead of the ‘Report on State Finances’.

What the report is about

The results of the Premier and Cabinet cluster (the cluster) agencies' financial statement audits for the year ended 30 June 2021.

What we found

Unmodified audit opinions were issued for all Premier and Cabinet cluster agencies.

The number of monetary misstatements decreased from 49 in 2019–20 to 38 in 2020–21.

The Library Council of New South Wales corrected a prior period error of $325 million. In 2017, the council split its collection assets into six asset classes, but not the related asset revaluation reserves. To correct this error, some revaluation decrements previously recognised in asset revaluation reserves were reclassified to accumulated funds.

Eight agencies did not complete all of the mandatory early close procedures.

What the key issues were

The Premier and Cabinet cluster was impacted by three Machinery of Government (MoG) changes during 2020–21.

The changes resulted in the transfer of activities and functions in and out of the cluster and the creation of a new entity - Investment NSW.

The transferor entities continued to provide services to Investment NSW subsequent to 30 June 2021. There were no formal service level agreements in place for the provision of these services.

The New South Wales Electoral Commission (the Commission) and Sydney Opera House Trust obtained letters of financial support from their relevant Minister and/or NSW Treasury in 2020–21. The postponement of local government elections impacted the Commission's operations due to increased planned expenditure to support a COVID-safe election. Sydney Opera House Trust's ability to generate revenue was impacted due to the closure of the Concert Hall partly due to COVID-19 and planned renovations.

The number of repeated audit issues raised with management and those charged with governance increased from 22 in 2019–20 to 24 in 2020–21.

There were 47 moderate risk and 28 low risk findings identified. Of the total findings there were 24 repeat issues.

What we recommended

Investment NSW should ensure services received from other agencies are governed by service level agreements.

Fast facts

The Department of Premier and Cabinet supports the Premier and Cabinet to deliver the government's objectives, infrastructure, preparedness for disaster, incident recovery, arts and culture.

  • $11.9b of property, plant and equipment as at 30 June 2021
  • $4.4b total expenditure incurred in 2020-21
  • 100% unqualified audit opinions were issued on agencies' 30 June 2021 financial statements
  • 47 moderate risk findings were reported to management 
  • 38 monetary misstatements were reported in 2020-21
  • 32% of all reported issues were repeat issues.

This report provides Parliament and other users of the Premier and Cabinet’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Premier and Cabinet cluster (the cluster) for 2021.

Section highlights

  • Unqualified audit opinions were issued on all completed cluster agencies' 2020–21 financial statements.
  • Monetary misstatements decreased from 49 in 2019–20 to 38 in 2020–21.
  • Thirteen agencies were exempt from financial reporting in 2020–21. 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from our financial statement audits of agencies in the Premier and Cabinet cluster.

Section highlights

  • The 2020–21 audits identified 47 moderate risk issues across the cluster. Sixteen of the moderate risk issues were repeat issues. Many repeat issues related to governance and oversight and information technology.
  • The number of moderate risk findings increased by 42 per cent in 2020–21.
  • The moderate risk issues included information technology improvements, lack of service level agreements, risk management, contract and procurement and asset management improvements.

Appendix one – Misstatements in financial statements submitted for audit

Appendix two – Early close procedures

Appendix three – Timeliness of financial reporting

Appendix four – Financial data

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Regional NSW 2021

Regional NSW 2021

Environment
Industry
Asset valuation
Compliance
Financial reporting
Infrastructure
Internal controls and governance
Management and administration
Service delivery

This report analyses the results of our audits of the Regional NSW cluster agencies for the year ended 30 June 2021.

Our preferred approach is to table the ‘Report on State Finances’ in Parliament before any other cluster report. This is because the 'Report on State Finances' focuses on the audit results and observations relating to the Total State Sector Accounts, in effect a consolidation of all government agencies. This year the 'Report on State Finances' has been delayed due to significant accounting issues being considered in the Total State Sector Accounts and which may impact the Treasury and Transport clusters.

As there are no outstanding matters relating to audits in the Regional NSW cluster impacting the Total State Sector Accounts we have decided to break with normal practice and table this cluster report ahead of the ‘Report on State Finances’.

What the report is about

The results of the Regional NSW cluster (the cluster) agencies’ financial statement audits for the year ended 30 June 2021.

What we found

Unmodified audit opinions were issued for all completed 30 June 2021 financial statement audits of cluster agencies. Four audits are ongoing.

The number of misstatements identified in the financial statements of cluster agencies decreased from 27 in 2019–20 to seven in 2020–21.

The Department corrected an understatement of $82.2 million in prepaid income related to the Bushfire Clean-up Program.

What the key issues were

Local Land Services (LLS) undertook a comprehensive revaluation of asset improvements on land reserves used for moving stock (travelling stock reserves).

The revaluation process identified that improvements on land reserves, with a value of $93.0 million, had not been previously recognised in the financial statements. LLS corrected this error by restating the 2019–20 comparative balances in its 2020–21 financial statements.

The Forestry Corporation of NSW revalued its biological assets that comprise approximately 225,000 hectares of softwood plantations and 34,000 hectares of hardwood forests. The current year valuation resulted in $71.4 million decrement in the total biological assets from $824.9 million in 2019–20 to $753.5 million in 2020–21.

The number of matters reported to management decreased from 36 in 2019–20 to 19 in 2020–21. Twelve moderate risk issues were identified and 47 per cent of reported issues were repeat issues.

What we recommended

Cluster agencies should prioritise and action recommendations to address internal control deficiencies.

 

Fast facts

The Regional NSW cluster plans and delivers regional programs and infrastructure to respond to regional issues, creating and preserving regional jobs, driving regional economy, growing existing and supporting emerging industries. There are 31 agencies in the cluster.

  • $2.3b of regional land and buildings as at 30 June 2021.

  • 100% unqualified audit opinions were issued for all completed 30 June 2021 financial statements audits.

  • monetary misstatements were reported in 2020–21.

  • $603m of grants and subsidies administered to the regional community in 2020–21.

  • 12 moderate risk management letter findings were identified and reported to management.

  • 47% of reported issues were repeat issues. 

This report provides Parliament and other users of the Regional NSW cluster agencies’ financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Regional NSW cluster for 2021.

Section highlights

  • Unqualified audit opinions were issued for all completed 30 June 2021 financial statements audits of cluster agencies. Four audits are ongoing.
  • The number of monetary misstatements identified during the audit decreased from 27 in 2019–20 to seven in 2020–21.
  • Three cluster agencies could improve their early close process by completing all required procedures.
  • Local Land Services disclosed a prior period error relating to the completeness of asset improvements on travelling stock reserves.

 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from our financial statement audits of agencies in the Regional NSW cluster.

Section highlights

  • The number of findings reported to management decreased from 36 in 2019–20 to 19 in 2020–21, and 47 per cent were repeat findings.
  • The 2020–21 audits identified 12 moderate risk and seven low risk issues across the cluster.
  • Four moderate risk issues and five low risk issues were repeat findings from
    2019–20.

 

Appendix one - Misstatements in financial statements submitted for audit

Appendix two - Early close procedures

Appendix three - Financial data

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Grants administration for disaster relief

Grants administration for disaster relief

Treasury
Finance
Compliance
Fraud
Management and administration
Project management

What the report is about

The report examined whether NSW Treasury, Service NSW and the Department of Customer Service effectively administered grants programs funded under the $750 million Small Business Support Fund, including:

  • $10,000 Small Business Support Grant
  • $3,000 Small Business Recovery Grant.

What we found

The agencies effectively implemented the grants within required timeframes, reflecting the NSW Government’s decision to deliver urgent financial support to small businesses impacted by the COVID-19 pandemic.

NSW Treasury met urgent timeframes to design the grants and Service NSW made timely payments in line with the grants' objectives and eligibility criteria.

Service NSW and the Department of Customer Service strengthened processes to detect and minimise fraud in response to identified external fraud risks, and to investigate suspected fraudulent applications.

Fraud security checks and investigations are ongoing, and the agencies will not know the full extent of fraud across the grants until these processes have been completed.

The agencies regularly monitored and reported on the timeliness of payments to small business applicants but have not yet measured all benefits of the grants programs.

The $10,000 Support Grant and the $3,000 Recovery Grant have provided around $630 million in one off grant payments to eligible small businesses.

What we recommended

NSW Treasury should finalise and implement an evaluation of both grants programs, including obtaining feedback from businesses.

Service NSW should develop a framework that documents expected controls for how it administers grants, including business processes, fraud control and governance and probity requirements.

Service NSW should publish information on all grants programs, including grants distribution and uptake.

The Department of Customer Service should ensure its processes for managing conflicts of interest meets its policy requirements.

Upcoming performance audit

The Audit Office is conducting a further performance audit into grants administration for disaster relief focussing on bushfire grants. This is planned to complete in 2021-22.

Fast facts

Small Business Support Fund
  • $630m Grant payments made to small businesses under two grants administered
  • Over 52,500 Applications received a $10,000 Grant payment
  • Over 23,000 Businesses paid both $10,000 Support Grant and $3,000 Recovery Grant
  • 36,700 Applications received a $3,000 grant payment
Grant program administration
  • 11 Days taken to deliver the $10,000 Small Business Support Grant application website
  • 26 Days taken to deliver the $3,000 Small Business Recovery Grant application website

Further information

Please contact Ian Goodwin, Deputy Auditor-General on 9275 7347 or by email.

The NSW Government responded to the partial shutdown of the NSW economy caused by the COVID-19 pandemic in 2020 by, among other measures, announcing on 3 April 2020 that it would place $750 million into the Small Business Support Fund (the Fund).

Under the Fund, the NSW Government would pay one-off grants of up to $10,000 to small business impacted by the shutdown. The objectives of the $10,000 Small Business Support Grant ($10,000 Support Grant) were to:

  • ease the pressure on small businesses that have been affected by the COVID-19 pandemic
  • support the ongoing operations of small businesses highly impacted by the COVID-19 restrictions
  • deliver cash-flow into small businesses as soon as possible so that small businesses could meet pressing financial needs.

Grant applications were assessed against eligibility criteria that were determined by the NSW Government. The eligibility criteria for the $10,000 Support Grant required an employing small business to demonstrate it was significantly impacted by the COVID-19 pandemic by self-declaring or demonstrating a significant decline of 75 per cent or more in turnover compared to 2019. Documentation requirements were relaxed for small businesses within highly impacted industries.

In June 2020, the NSW Government announced a second round of one-off grants of up to $3,000 to small businesses that were highly impacted by the COVID-19 pandemic ($3,000 Recovery Grant). The objective of the $3,000 Recovery Grant was to help small businesses in 'highly impacted industries' — those directly impacted by the restrictions and closures put in place under the Public Health Orders — to meet the costs of safely reopening or scaling up operations.

The eligibility criteria for the $3,000 Recovery Grant required that a small business be in a highly impacted industry, demonstrate that it was significantly impacted by the COVID-19 pandemic by declaring a significant decline in turnover, and had costs associated with reopening under the 'COVID-Safe' requirements.

NSW Treasury and Service NSW implemented both grants on behalf of the NSW Government. The process of applying for a grant was intended to be quick and easy, with Service NSW using automated assessments and simple online application forms to process applications. Applicants applied for the $10,000 Support Grant through the Service NSW website between 14 April 2020 to 30 June 2020 and applied for the $3,000 Small Business Recovery Grant between 1 July 2020 and 31 August 2020.

At May 2021, around $520 million has been paid to over 52,500 grant applicants under the $10,000 Support Grant and around $109 million had been paid to around 36,700 grant applicants under the $3,000 Recovery Grant.

The Audit Office plans to undertake a performance audit into grants administration for disaster relief focussing on bushfire grants in 2021–22.

This audit assessed whether the grants funded under the $750 million Small Business Support Fund were effectively administered and implemented to provide disaster relief. It addressed the following questions:

  • Were funded grants programs planned, designed and targeted effectively?
  • Were funded grants programs implemented in line with the objectives and criteria and delivery requirements?
  • Have agencies established measures to monitor intended benefits and outcomes?

This audit did not seek to assess the effectiveness of any other grant programs or stimulus measures. It also did not seek to assess the impact of the funding on applicants, or the future prospects of small businesses that received support.

Conclusion

NSW Treasury and Service NSW effectively implemented two grants within required timeframes reflecting the NSW Government's decision to deliver urgent financial support to small businesses impacted by the COVID-19 pandemic in 2020. The $10,000 Support Grant and the $3,000 Recovery Grant have provided around $630 million in one-off grant payments to eligible small businesses.
NSW Treasury met urgent timeframes to design the grants and Service NSW made timely payments in line with the grants' objectives and eligibility criteria.

NSW Treasury met urgent timeframes to provide advice to the NSW Government on the grant design, proposed delivery partner, expected numbers of eligible businesses and the suitability of the proposed grant payment amount within the required timeframes. This was achieved within one day for the $10,000 Support Grant and within four days for the $3,000 Support Grant. In the context of the complex and changing pandemic and economic conditions between March and July 2020, NSW Treasury's advice to government outlined the risk, feasibility, expected demand estimates and assumptions for the grants.

NSW Treasury's demand projections were limited by uncertainty as to the pandemic's economic impact. Estimated demand for the grants was not met, resulting in around $120 million from the Small Business Support Fund remaining unspent.

Service NSW met urgent timeframes to stand-up both grants: 11 days for the $10,000 Support Grant and 26 days for the $3,000 Recovery Grant. It met agreed delivery requirements and made timely payments to small businesses in line with the grants' objectives and eligibility criteria. Over 65,000 businesses have received a payment under either grant, and over 23,000 businesses received both grants.

Gaps in project and risk management processes were expected given the tight timeframe to implement the grants.

The tight timeframe in which the agencies had to implement the grants contributed to gaps in project and risk management. The agencies advised that compromises were understood by both parties and were a necessary trade-off to ensure payments were made quickly.

Service NSW and the Department of Customer Service have acted to strengthen their processes to detect and minimise fraud in response to identified external fraud risks and to investigate suspected fraudulent applications since the grants commenced. Service NSW intends to further enhance fraud controls for grants applications and payments for future grants by implementing a fraud control framework by December 2021.

The agencies regularly monitored and reported on the timeliness of payments to small business applicants but have not yet measured all benefits of the grants programs.

Service NSW and NSW Treasury established processes to monitor and report on the timeliness of payments to grant applicants.

NSW Treasury has not yet measured all intended impacts of the grants, nor undertaken processes to obtain detailed feedback from grant recipients. Without these measures, there is limited insight into the extent to which the grants helped to support small businesses or ability to capture lessons which could be applied in future grants programs. NSW Treasury advises that an evaluation will commence from mid-2021.

1. Key findings

Around $630 million in timely one-off grant payments have been made to small businesses

Service NSW and NSW Treasury have paid around $630 million in one-off grant payments to small businesses via two grants administered under the $750 million Small Business Support Fund. At May 2021:

  • around $520 million has been paid to over 52,500 grant applications received for the $10,000 Small Business Support Grant ($10,000 Support Grant)
  • around $109 million has been paid to 36,700 grant applications received for the $3,000 Small Business Recovery Grant ($3,000 Recovery Grant).

Across both grants, over 65,000 small businesses received a payment across either grant, and over 23,000 businesses received payments under both grants.

NSW Treasury advise that, while no data was collected on the time to pay applicants for the $10,000 Support Grant, from its monitoring of the grants' outputs it was satisfied that payment timeframes met its expectations. Service NSW met its targeted time to pay applicants with payments made within ten days for the $3,000 Recovery Grant.

Funds for both grants were not fully spent due to limitations in data and uncertainty of the COVID-19 pandemic's impact. At May 2021, the final demand for the $10,000 Support Grant was around 30 per cent less than initially anticipated and the final demand for the $3,000 Recovery Grant was around 40 per cent less than initially anticipated.

NSW Treasury developed proposals establishing high level design and delivery expectations within rapid timeframes

NSW Treasury put forward proposals to the NSW Government for the two grants administered under the $750 million Small Business Support Fund. It met rapid timeframes for producing this advice: within one day for the $10,000 Support Grant and within four days for the $3,000 Recovery Grant. NSW Treasury's advice to the NSW Government on how to best target the total funding, eligibility criteria and the feasibility of delivering the grants through Service NSW was based on comparable grants programs – including the $10,000 Small Business Bushfire Support Grant – which at that time were ongoing.

The proposals established, at a high-level, the rationale for the grants, expected financial costs, risks and analysis on budget impacts, and confirmation that Service NSW could deliver the grants applications platform. NSW Treasury's demand projections were uncertain due to limited data in the early stages of the pandemic regarding potential economic impact.

Given the tight timeframes, the proposals did not fully consider all planning and design aspects for both grants. For example, there was minimal identification of the costs and benefits of the programs, and a lack of detailed design and delivery requirements. The proposals outlined that arrangements to finalise the risk management, controls, and auditing plan would be agreed by Service NSW and NSW Treasury before implementation.

In future circumstances where urgent advice on program design is required, NSW Treasury could set clearer expectations for the delivery agency, including fully considering costs, benefits and delivery requirements that could be carried through to project governance and implementation.

Service NSW implemented both grants in line with delivery expectations

Service NSW met urgent timeframes to stand-up both grants: 11 days for the $10,000 Support Grant and 26 days for the $3,000 Recovery Grant. Delivery expectations for each grant were established under a grant project agreement (grant agreement). Service NSW delivered the online application platform, assessment of applications, payments and reporting of the grants' uptake as per the grant agreements.

The urgent timeframes to deliver the grants contributed to gaps in Service NSW's project and risk management processes throughout the lifecycle of both grants. For example, the requirement to meet pressing timeframes for the $10,000 Support Grant launch meant agencies had reduced time to achieve sign-off on key documentation. As a result, important documents and processes – including the grant agreement, risk documentation and key business process and quality assurance processes – were not finalised ahead of launch.

Quality assurance and compliance processes for detecting fraud were not settled until after the conclusion of the applications for the $10,000 Support Grant, and were not completed until late 2020. Some project documents, including risk registers, communication plans and project briefs are still not finalised.

The longer timeframe to develop the $3,000 Recovery Grant meant that agencies were able to build on their understanding of the implementation requirements from the $10,000 Support Grant, and better document these expectations and understanding while ensuring that key documents and sign-offs were in place prior to launch.

Service NSW tightened its risk management and controls in response to evidence of fraudulent applications

In May 2020, Service NSW and the Department of Customer Service (DCS) were alerted to suspected fraudulent activity within grants administered by Service NSW. Initially, Service NSW anticipated that up to $8.8 million of the $10,000 Support Grant was at risk of exposure to fraudulent applications. However, Service NSW reported that, at April 2021, $1.9 million for the $10,000 Support Grant and $254,000 for the $3,000 Recovery Grant from paid applications were at risk of fraud exposure.

Following an internal review of the potential exposure to fraudulent or ineligible applications, Service NSW implemented additional automated security checks on applications, increased manual assessments of grant applications, established a dedicated taskforce for grants administration and engaged a unit within DCS to manage high-risk investigations.

Service NSW and DCS's increased governance and oversight has resulted in an established case management function, increased referrals to law enforcement, prioritised investigations of suspicious applications and the development of a 'Fraud Control Framework' aimed at addressing external fraud risks. Given Service NSW had limited experience in these processes in context of administering grant payments, such actions were an appropriate response.

Security checks and investigations of suspicious applications are ongoing. Service NSW will not know the full extent of fraud across the grants until these processes have been fully completed.

Service NSW and Department of Customer Service can improve how conflicts of interest are managed for future programs

Compliance with agency policies and processes to manage conflicts of interest and financial subdelegations demonstrates that investment decisions are being made by appropriately skilled and experienced staff, allowing agencies to operate efficiently, and reducing the risk of internal fraud.

DCS was unable to produce employee conflicts of interest declarations for the $10,000 Support Grant. Therefore, it is not known how many employees had completed conflicts of interest declarations for this round.

DCS provided information on conflicts of interest declarations for the $3,000 Recovery Grant. Twenty-nine per cent of declarations provided for employees undertaking grant assessments for the $3,000 Recovery Grant were incomplete at March 2021, and a further nine per cent were not finalised even though they indicated a real, potential or perceived conflict.

For future grants programs, ensuring compliance with conflicts of interest policies would help DCS and Service NSW to have greater confidence that conflicts of interest are appropriately identified and managed.

NSW Treasury has not yet measured all benefits or outcomes of the grants

In April 2021, NSW Treasury updated its evaluation plan for the $10,000 Support Grant and $3,000 Recovery Grant in support of an economic evaluation to commence from mid-2021. The updated evaluation plan outlines inputs, activities, and outputs as well as immediate, short term and medium term outcomes for both grants.

The evaluation will consider the extent to which both grants achieved their intended outcomes, and whether the economic benefits exceeded the costs to help inform decisions about the nature and design of any future small business support programs. This will complement, and feed into a broader review of all NSW Government COVID-19 stimulus measures.

Service NSW rapidly developed an approach to administer the grants

Over recent disasters, such as the 2019–20 bushfires and the COVID-19 pandemic, Service NSW has been responsible for administering grant programs on behalf of other government agencies.

Service NSW implemented both grants under its Project Management Framework and under each grant agreement with NSW Treasury as it does not have its own grants administration framework. To address the risks that emerged during delivery, Service NSW developed an approach to standardise and monitor the administration of the grants while they were being implemented.

Service NSW now has an opportunity to establish a grants administration framework, based on the processes, lessons and outcomes captured under the grants administration taskforce and in developing its fraud control framework. Embedding these processes into business as usual for grants administration will enable Service NSW to have a consistent set of expectations for controls, business processes and governance and probity requirements for future grants it implements.

2. Recommendations

By December 2021, NSW Treasury should:

1. finalise and implement an evaluation of the $10,000 Support Grant and $3,000 Recovery Grant, including obtaining direct feedback from businesses on how grant funds achieved the grant objectives.

By December 2021, Service NSW should:

2. develop a grants administration framework, which documents expected controls – including fraud controls – business processes and governance and probity requirements

3. publish information on all grants programs, including grants distribution and uptake.

By December 2021, the Department of Customer Service should:

4. ensure its process for managing conflicts of interest meets policy requirements by:

  • ensuring employees promptly declare any real, potential or perceived conflicts of interest
  • annually producing a list of conflicts of interest for records retention purposes
  • requiring a separate register of conflicts of interest declarations where a grant program is deemed as high risk.

3. Lessons for grants administered within urgent timeframes

The two grants this audit examined were administered within a context of urgent timeframes, and increased complexity and uncertainty about the impact of the COVID-19 pandemic. The following lessons are shared to assist sponsor and delivery agencies in administering future grants where rapid implementation is required.

Sponsor agencies should consider the following lessons:

1. develop an approach to define and measure benefits for rapidly developed programs and projects where a full business case and cost-benefit analysis is not feasible

2. establish common processes and expectations for co-administered grants:

  • periodically assure agencies' capability to deliver grants programs
  • agree and establish risk appetite statements with administering agencies
  • clearly establish expected performance levels and targets under any agreement

3. review the processes and outcomes of rapidly developed programs, capture lessons learned, and apply these in planning and delivering future programs.

Delivery agencies should consider the following lessons:

1. risk management and risk appetite:

  • perform robust assessment procedures to ensure risks associated with delivery of the project are identified
  • ensure the controls implemented adequately address identified risks
  • agree and document the acceptable risk appetite at the outset
  • review risk management processes after the grants are issued when unable to finalise risk management processes ahead of launch

2. grant agreements between NSW public sector agencies:

  • ensure agreements are finalised in a timely manner
  • ensure agreements clearly outline:
    • roles and responsibilities of both parties,
    • changes in scope of services provided
    • fees and charges applicable

3. frameworks for grants administration:

  • ensure that there is a common set of expectations in place to guide grants administration including standard controls and processes for managing risk, capturing lessons learned and reporting on outcomes.

Appendix one – Response from agencies

Appendix two – Summary of other COVID‑19 Stimulus and Support for small businesses in NSW in April 2020

Appendix three – Public Health Orders

Appendix four – Highly impacted industries

Appendix five – About the audit

Appendix six – Performance auditing

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #352 - released (24 June 2021).

 

Published

Actions for Report on Local Government 2020

Report on Local Government 2020

Local Government
Asset valuation
Compliance
Cyber security
Financial reporting
Fraud
Information technology
Infrastructure
Internal controls and governance
Procurement

What the report is about

Results of the local government sector council financial statement audits for the year ended 30 June 2020.

What we found

Unqualified audit opinions were issued for 127 councils, 9 county councils and 13 joint organisation audits in 2019–20. A qualified audit opinion was issued for Central Coast Council.

Councils were impacted by recent emergency events, including bushfires and the COVID-19 pandemic. The financial implications from these events varied across councils. Councils adapted systems, processes and controls to enable staff to work flexibly.

What the key issues were

There were 1,435 findings reported to councils in audit management letters.

One extreme risk finding was identified related to Central Coast Council’s use of restricted funds for general purposes.

Fifty-three high risk matters were identified across the sector:

  • 21 high risk matters relating to asset management
  • 14 high risk matters relating to information technology
  • 7 high risk matters relating to financial reporting
  • 4 high risk matters to council governance procedures
  • 3 high risk matters relating to financial accounting
  • 3 high risk matters relating to purchasing and payables
  • 1 high risk matter relating to cash and banking.

More can be done to reduce the number of errors identified in financial reports. 61 councils required material adjustments to correct errors in previous audited financial statements.

Fast facts

  • 150 councils and joint organisations in the sector
  • 99% unqualified audit opinions issued for the 30 June 2020 financial statements
  • 490 monetary misstatements were reported in 2019-20
  • 61 prior period errors reported
  • 53 high risk management letters findings identified
  • 49% of reported issues were repeat issues

Rural fire fighting equipment

Sixty-eight councils did not record rural fire fighting equipment worth $119 million in their financial statements.

The NSW Government has confirmed these assets are not controlled by the NSW Rural Fire Service and are not recognised in the financial records of the NSW Government.

What we recommended

The Office of Local Government should communicate the State's view that rural firefighting equipment is controlled by councils in the local government sector, and therefore this equipment should be properly recorded in their financial statements.

Central Coast Council

A qualified opinion was issued for Central Coast Council (the Council) relating to two matters.

Council did not conduct the required revaluation to support the valuation of roads.

Council also disclosed a prior period error relating to restrictions of monies collected for their water, sewer, and drainage operations, which, based on the NSW Crown Solicitor’s advice, should be considered a change in accounting policy.

What we recommended

The Office of Local Government should clarify the legal framework relating to restrictions of water, sewerage and drainage funds (restricted reserves) by either seeking an amendment to the relevant legislation or by issuing a policy instrument to remove ambiguity from the current framework.

Key financial information

In 2019-20, councils:

  • collected $7.3 billion rates and annual charges
  • received $4.7 billion grants and contributions 
  • incurred $4.8 billion of employee benefits and on-costs
  • held $14.2 billion of cash and investments
  • managed $160.0 billion of infrastructure, property, plant and equipment
  • entered into $3.3 billion of borrowings.

Further information

Please contact Ian Goodwin, Deputy Auditor-General on 9275 7347 or by email.

 

Financial reporting is an important element of good governance. Confidence in and transparency of public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines audit observations related to the financial reporting of councils and joint organisations.

Highlights

  • The Office of Local Government within the Department of Planning, Industry and Environment (OLG) extended the statutory deadline for councils and joint organisations to lodge their audited financial statements by an additional month to 30 November 2020 due to the COVID-19 pandemic.
  • One hundred and thirty-three councils and joint organisations (2019: 117) lodged audited financial statements with the OLG by the revised statutory deadline of 30 November (2019: 30 October). Sixteen (2019: 30) councils received extensions to submit audited financial statements to OLG. Canberra Region Joint Organisation did not submit their audited financial statements by the statutory deadline and did not formally apply for extension before the deadline lapsed.
  • Unqualified audit opinions were issued for 127 councils, nine county councils and 13 joint organisation audits in 2019–20. A qualified audit opinion was issued for Central Coast Council.
  • Unqualified audit opinions were issued for the 2018–19 financial audits of Hilltops, MidCoast and Murrumbidgee Councils, which were not completed at the time of tabling the 'Local Government 2019' report in Parliament.
  • The total number and dollar value of corrected and uncorrected financial statement errors increased compared with the prior year.
  • Sixty-eight councils did not record rural fire fighting equipment in their financial statements worth $119 million. The NSW Government has confirmed these assets are not controlled by the NSW Rural Fire Service and are not recognised in the financial records of the NSW Government.
  • The total number of prior period financial statement errors increased from 59 in the prior year to 61, but the total dollar value of the errors decreased from $1,272 million to $813 million.
  • Councils implemented three new accounting standards in 2019–20 relating to revenue and leases.

 

Recent emergency events, including drought, bushfires, floods and the COVID-19 pandemic have impacted councils.

This chapter will provide insights into how these events have impacted councils, including:

  • financial implications of the emergency events
  • changes to councils' operating models, processes and controls
  • accessibility to technology and the maturity of councils' systems and controls to prevent unauthorised and fraudulent access to data
  • receipt and delivery of stimulus packages or programs at short notice.

Highlights

  • All councils were impacted by the recent emergency events.
  • Councils changed governance, policies, systems and processes to respond to the recent emergency events.
  • Challenges were experienced adapting Information Technology (IT) infrastructure and controls to enable staff to work from home.
  • Sixty-five per cent of councils updated business continuity plans and 42 per cent updated disaster recovery plans as a response to recent emergency events.
  • Councils received various forms of assistance from government relating to the recent emergencies, which was used to provide support to local communities.

Recent emergency events significantly impacted councils

Recent emergencies, including drought, bushfires, floods and the COVID-19 pandemic have brought particular challenges for councils and their communities.

 

A strong system of internal controls enables councils to operate effectively and efficiently, produce reliable financial reports, comply with laws and regulations and support ethical government.

This chapter outlines the overall trends in governance and internal control findings across councils, county councils and joint organisations in 2019–20. It also includes the findings reported in the 2018–19 audits of Hilltops, MidCoast and Murrumbidgee councils as these audits were finalised after the Report on Local Government 2019 was published.

Financial audits focus on key governance matters and internal controls supporting the preparation of councils' financial statements. Audit findings are reported to management and those charged with governance through audit management letters.

Highlights

  • Total number of findings reported in audit management letters decreased from 1,985 in 2018–19 to 1,435 in 2019–20.
  • One extreme risk finding was identified in 2019–20 (2018–19: nil).
  • Total number of high-risk findings decreased from 82 in 2018–19 to 53 in 2019–20. Thirty per cent of the high-risk findings identified in 2018–19 were reported as high-risk findings in 2019–20.
  • Forty-nine per cent of findings reported in audit management letters were repeat or partial repeat findings.
  • Governance, asset management and information technology (IT) comprise over 61 per cent of findings and continue to be key areas requiring improvement.
  • Fifty-six councils could strengthen their policies, processes and controls around fraud prevention and legislative compliance.
  • Sixty-eight councils had deficiencies in their processes to revalue infrastructure assets.
  • Fifty-eight councils have yet to implement basic governance and internal controls to manage cybersecurity.
  • Sixty-four councils should formalise and periodically review their IT policies and procedures.

Total number of findings reported in audit management letters decreased

In 2019–20, 1,435 findings were reported in audit management letters (2018–19: 1,985 findings). An extreme risk finding was also identified this year related to Central Coast Council's use of restricted funds. The total number of high-risk findings decreased to 53 (2018–19: 82 high-risk findings).

Findings are classified as new, repeat or ongoing findings, based on:

  • new findings were first reported in 2019–20 audits
  • repeat findings were first reported in prior year audits, but remain unresolved in 2019–20
  • ongoing findings were first reported in prior year audits, but the action due dates to address the findings are after 2019–20.

Findings are categorised as governance, financial reporting, financial accounting, asset management, purchases and payables, payroll, cash and banking, revenue and receivables, or information technology. The high-risk and common findings across these areas are explored further in this chapter.

Audit Office’s work plan for 2020–21 onwards

Focus on local council's response and recovery from recent emergencies

Local councils and their communities will continue to experience the effects of recent emergency events, including the bushfires, floods and the COVID 19 pandemic for some time. The full extent of some of these events remain unclear and will continue to have an impact into the future. The recovery is likely to take many years.

The Office of Local Government (OLG) within the Department of Planning, Industry and Environment is working with other state agencies to assist local councils and their communities to recover from these unprecedented events.

These events have created additional risks and challenges, and changed the way that councils deliver their services.

We will take a phased approach to ensure our financial and performance audits address the following elements of the emergencies and the Local Government's responses:

  • local councils' preparedness for emergencies
  • its initial responses to support people and communities impacted by the 2019–20 bushfires and floods, and COVID-19
  • the governance and oversight risks that arise from the need for quick decision making and responsiveness to emergencies
  • the effectiveness and robustness of processes to direct resources toward recovery efforts and ensure good governance and transparency in doing so
  • the mid to long-term impact of government responses to the natural disasters and COVID-19
  • whether government investment has achieved desired outcomes.

Planned financial audit focus areas in Local Government

During 2020–21, the financial audits will focus on the following key areas:

  • cybersecurity, including:
    • cybersecurity framework, policies and procedures
    • assessing the controls management has to address the risk of cybersecurity incidents
    • whether cybersecurity risks represent a risk of material misstatement to council's financial statements
  • budget management
  • financial sustainability
  • quality and timeliness of financial reporting
  • infrastructure, property, plant and equipment
  • information technology general controls.

Audit, risk and improvement committees

All councils are required to have an audit, risk and improvement committee by March 2022

The requirement for all councils to establish an audit, risk and improvement committee was deferred by 12 months to March 2022 due to the COVID 19 pandemic.

Audit, risk and improvement committees are an important contributor to good governance. They help councils to understand strategic risks and how they can mitigate them. An effective committee helps councils to build community confidence, meet legislative and other requirements and meet standards of probity, accountability and transparency.

Local Government elections

Local Government elections were postponed for one year due to the COVID 19 pandemic

The Local Government elections were deferred for one year due to the COVID 19 pandemic and will now be held on 4 September 2021. As the statutory deadline for the 2020–21 financial statements is 30 October 2021, some of the newly elected councillors will be required to endorse them.

Implementation of AASB 1059

Accounting standards implementation continue next year

AASB 1059 is effective for councils for the 2020–21 financial year.

A service concession arrangement typically involves a private sector operator that is involved with designing, constructing or upgrading assets used to provide public services. They then operate and maintain those assets for a specified period of time and is compensated by the public sector entity in return. Examples of potential service concession arrangements impacting councils include roads, community housing, childcare services and nursing homes.

AASB 1059 may result in councils recognising more service concession assets and liabilities in their financial statements.

 

Appendix one – Response from the Department of Planning, Industry and Environment

Appendix two – NSW Crown Solicitor’s advice

Appendix three – Status of 2019 recommendations

Appendix four – Status of audits

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Acquisition of 4–6 Grand Avenue, Camellia

Acquisition of 4–6 Grand Avenue, Camellia

Transport
Asset valuation
Compliance
Fraud
Infrastructure
Internal controls and governance
Management and administration
Procurement
Risk

The Auditor-General for New South Wales, Margaret Crawford, has today released a report on Transport for NSW’s (TfNSW) acquisition of 4–6 Grand Avenue in Camellia.

This audit, which was requested on 17 November 2020 by the Hon. Andrew Constance MP, the Minister for Transport and Roads, examined:

  • whether TfNSW conducted an effective process to purchase 4–6 Grand Avenue, Camellia
  • whether TfNSW has effective processes and procedures to identify and acquire property required to deliver the NSW Government’s major infrastructure projects.

The audit found that TfNSW conducted an ineffective process when it purchased 4–6 Grand Avenue, Camellia. The audit also found that TfNSW’s internal policies and procedures to guide the transaction were, and continue to be, insufficient.

The Auditor-General has made seven recommendations to address the issues identified in the report.

On 17 November 2020, the Hon. Andrew Constance MP, the Minister for Transport and Roads, requested this audit under section 27B(3)(c) of the Public Finance and Audit Act 1983.

On 15 June 2016, Transport for New South Wales (TfNSW) acquired 6.3 hectares of land at 4–6 Grand Avenue, Camellia, by agreement from Grand 4 Investments Pty Ltd. Grand 4 Investments was a business entity established by the owners of Billbergia Pty Ltd, a property development and investment company.

TfNSW paid Grand 4 Investments $53.5 million and assumed liability for addressing environmental issues and contamination associated with the site. This took place seven months after the vendor acquired the land as part of a competitive Expression of Interest process, in which TfNSW also participated, for $38.15 million.

TfNSW is the NSW Government agency responsible for most major transport infrastructure projects in New South Wales. TfNSW acquired the Camellia site for use as a stabling and maintenance depot to support the Parramatta Light Rail (PLR) project.

Consistent with the minister’s request, this audit assessed:

  • whether TfNSW conducted an effective process to purchase 4–6 Grand Avenue, Camellia
  • whether TfNSW has effective processes and procedures to identify and acquire property required to deliver the NSW Government’s major infrastructure projects.

In considering the effectiveness of the processes for this purchase, the audit considered:

  • the requirements of the Land Acquisition (Just Terms Compensation) Act 1991 (the Act)
  • the application of sound processes to manage risk to the NSW Government and to achieve value for money
  • the application of disciplines associated with complex procurement, such as probity, in a NSW Government context.
The acquisition of the 4–6 Grand Avenue site in Camellia was consistent with a 2014 feasibility study for the PLR, but occurred before the completion of detailed project planning or an acquisition strategy.

TfNSW made two attempts to acquire the 4–6 Grand Avenue site in Camellia, and was successful on the second attempt. TfNSW recognised the risks associated with early acquisition and had high-level strategies in place should the site not be required.

The specific site had been identified in a feasibility study for the PLR commissioned by TfNSW in 2014 as one of several options in Camellia for a stabling and maintenance depot. However, TfNSW had not done any substantive analysis of the various options to identify a preferred location before the two opportunities to acquire 4–6 Grand Avenue were brought to TfNSW’s attention by the landowners (or their agents). On both occasions, TfNSW chose to actively pursue acquisition in advance of any such analysis.

The acquisition was also not informed by a Property Acquisition Strategy, which TfNSW policy recommends in order to guide the process and manage acquisition specific risks.

In 2015, TfNSW identified that it would require a stabling and maintenance depot in the Camellia area for the Parramatta Light Rail

In 2014, TfNSW commissioned an external engineering consultancy to undertake a feasibility design study for the Parramatta Light Rail - the Parramatta Transport Corridor Strategy Feasibility Design study (herein referred to as ‘the feasibility study’). In early 2015, TfNSW received the feasibility study, which was one of several key sources that informed the development of business cases for the PLR.

The feasibility study recommended that TfNSW should consolidate the maintenance and cleaning operations with overnight stabling facilities on one site. The study noted that the optimal location for any such site would be in close proximity to the proposed network, and noted that the site must have access to road connections to accommodate access for cars and trucks.

The study found that a centrally located stabling and maintenance facility would be required for all routes serving the Parramatta CBD, and that the Camellia industrial area was a preferred location for such a facility. The study noted that the Camellia area was contaminated.

The feasibility study notes that its conclusions were based on assumptions about the light rail system adopted and decisions made by the future operator of the system, who had not yet been selected or appointed.

TfNSW's decision to progress a potential acquisition in 2015 considered the risk that the site may not be required

TfNSW's FIC was responsible for making decisions on funding allocations at a whole of program level within TfNSW. FIC was also responsible for approving ‘high-risk/high-value’ variations to program budgets. Members of the FIC included:

  • Secretary of Transport for NSW
  • Deputy Secretary, Infrastructure and Services
  • Deputy Secretary, Freight, Strategy and Planning
  • Deputy Secretary, Customer Services
  • Deputy Secretary Finance and Investment
  • Deputy Secretary People and Corporate Services.

An April 2015 submission, from the then Deputy Director-General to the agency’s FIC, sought authorisation and funding approval to participate in an Expression of Interest sale process. It noted the risk that the project may not go ahead. The submission advised that:

By acquiring a strategic site now, it reduces the risk of having to pay an improved value or a value that may be subject to rapidly improving land values due to changes in land use and rezoning.

The property can be acquired for the project, held strategically and income generated by leasing the site as hardstand 1 space until the project requires the land for the Parramatta Light Rail project.

If the project does not proceed in the medium to longer term, the property can be sold at a premium to what has been paid today as property fundamentals improve.

This submission acknowledged the risks associated with environmental contamination and proposed that these risks would be managed by negotiating a contract where the remediation and associated expenses would be at the landowner’s cost. 

TfNSW assessed the 4–6 Grand Avenue site as one of several sites in Camellia that was a feasible location for a stabling and maintenance facility

The Departmental feasibility study assessed six potential sites for a stabling and maintenance facility, including 4–6 Grand Avenue, noting strengths and weaknesses of each site. A different site on Grand Avenue was assessed as the ‘base case’ option (1 Grand Avenue). The study’s comments on the 4–6 Grand Avenue site included the following:

With an area of approximately 63,000m2, this site has sufficient space for a depot with the required stabling yard and maintenance facilities. The location allows for good road access and LRT [light rail transit] access would be from Grand Avenue, which may require a road crossing or signalised intersection. The site has been used for general industrial uses; however the land has been cleared and is currently undergoing remediation 2. The site is not affected by flooding based on one in 100-year flood data.

In early 2015, once the opportunity to acquire 4–6 Grand Avenue emerged, TfNSW commissioned a specific feasibility study of the 4–6 Grand Avenue site. The feasibility studies clearly documented the existence of environmental contamination. In April 2015, the report concluded:

Given the limitations of this report and within the parameters that have been set it is concluded that from a spatial and geographic perspective the site at 6 Grand Avenue would be suitable as a stabling and maintenance depot for the Parramatta light rail project. There are few engineering and environmental constraints that would affect the feasibility level analysis of this site and all issues identified, within this desk study, are considered to be resolvable. However this being said there is a significant amount of work necessary to reach the final layout and definition of the stabling and maintenance depot. There are numerous items which require further consideration and conformation; planning approvals could impose restrictions on building heights, noise mitigation measures, light and visual impact requirements all of which can have significant impacts on the spatial requirements of any stabling and maintenance depot. 

The acquisition of 4–6 Grand Avenue was not informed by a Property Acquisition Strategy

For major projects, TfNSW typically requires the project team to complete a Property Acquisition Strategy, which is intended to guide both process as well as specific acquisition issues expected to be faced during the project. The Property Acquisition Strategy is not a mandated document but is a recommended tool to support property acquisition as part of major projects.

TfNSW did not have a Property Acquisition Strategy in place to guide the 2015 Expression of Interest process. On 6 November 2015, the then Project Director for the PLR project emailed the property team, noting a need to develop a Property Acquisition Strategy to close off the scoping design and preliminary business case.

In January 2016, TfNSW developed a draft Property Acquisition Strategy for the Parramatta Light Rail Project, although it was silent on the potential sites for the stabling and maintenance facility.

TfNSW focussed on 4–6 Grand Avenue because it was available and aligned to TfNSW's strategic interests

In early 2015, officials commenced monitoring the market for industrial real estate in the Camellia area and surrounds for possible sites for a stabling and maintenance facility.

In March 2015, then owner of the site, Akzo Nobel Pty Limited released the 4–6 Grand Avenue site through an Expression of Interest process managed by CBRE.

TfNSW’s then Deputy Director-General, Planning, sought approval from FIC to lodge an Expression of Interest up to $30.0 million. Approval was sought on the basis that it would ‘provide certainty for the Parramatta Light Rail project by allowing for a depot site in a suitable location and potentially avoid higher costs or longer timeframes associated with compulsory acquisition following completion of the project’s business case’. FIC approved the request at its meeting on 9 April 2015.

At this time, TfNSW had not conducted any analysis of financial or operational benefits and costs of the potential sites identified in earlier feasibility studies. TfNSW staff advised us that the decision to participate in the Expression of Interest process for 4–6 Grand Avenue was because it was available. There is no documentation substantiating this statement, which TfNSW staff provided verbally as part of this audit.

In November 2015, TfNSW was advised that it was unsuccessful in the Expression of Interest process and that Grand 4 Investments (a related entity of Billbergia) had purchased 4–6 Grand Avenue. TfNSW did not conduct any further analysis of alternative potential sites in Camellia between this date and commencing discussions with Grand 4 Investments in April 2016. In that time there had been some movement on other properties that were included in the feasibility study, including 37–39a Grand Avenue being under offer in September 2015.

In March 2016, TfNSW approached CBRE to organise a meeting with Grand 4 Investments. On 1 April 2016, TfNSW met with Grand 4 Investments.

TfNSW advises that a perceived benefit of the 4–6 Grand Avenue site was that it was not subject to other uses or leaseholds that would increase the cost of compulsory acquisition. Officers involved in the acquisition advised that other nominated sites in the feasibility study were subject to other uses or leaseholds. 


1  A hardstand space is a large, paved area to store cars, heavy vehicles and machinery.
2  Officers familiar with the acquisition could not confirm the nature of remediation being undertaken, but noted that the previous landowner had cleared buildings from the site, which may have been considered part of remediation.
TfNSW's independent valuation, which it commissioned and received after the acquisition, specifically excluded consideration of environmental contamination risk. As a result, TfNSW is exposed to the risk that the acquisition was not fully compliant with the Land Acquisition (Just Terms Compensation) Act 1991 (the Act) because it did not use an accurate estimate of market value during negotiations. That said, the acquisition of 4–6 Grand Avenue by agreement was consistent with preferred processes described in the Act.

TfNSW acquired the site from the landowner by agreement, and this is consistent with provisions in the Act. Obtaining approval for compulsory acquisition should negotiations for agreement break down is also consistent with the Act. That said, TfNSW did not at any time assess whether a compulsory acquisition could have resulted in acquisition at a lower cost than what was negotiated by agreement.

Despite the high risks associated with the acquisition, TfNSW did not commission a formal valuation in time to inform the negotiation and purchase. Instead, TfNSW relied on internal advice to estimate market value, but did not obtain a formal valuation from those advisors. For high-risk transactions, the greater expertise and arm's-length independence of an external specialist valuer should be preferred over an agency's own staff.

On 15 June 2016, the settlement date for the acquisition, TfNSW commissioned a formal independent valuation of the site. On 23 November 2016, TfNSW received the final formal valuation report. By not obtaining a formal independent valuation of the property in advance of acquisition to inform the acquisition value, TfNSW exposed itself to non-compliance with the Act by not establishing the market value as the basis for the acquisition price. TfNSW also breached its own internal policies.

TfNSW instructed the valuer to conduct its valuation within the following parameters:

  • Market valuation on an ‘as is’ basis – market value based on the methodology described in the Act. This approach valued the site at $25.0 million.
  • Market valuation on a speculative development basis – market value based on the financial value of the vendor's intended use of the site which, in this case, involved leasing the site for industrial use. This approach valued the site at $52.0 million, and TfNSW advised us this valuation supported the purchase price.
  • Disregard the impact of environmental contamination – TfNSW specifically instructed the independent valuer to disregard any known (or unknown) site contamination. As TfNSW knew of the significant environmental contamination affecting the site, this parameter resulted in a valuation that overstated the value of the site as it did not consider the cost of environmental remediation. The valuer applied this assumption for both market valuation approaches.

Additionally, as the independent valuer completed the valuation after the purchase was finalised, there is a risk that the valuation may have been influenced by the known purchase price.

TfNSW's failure to acquire a formal valuation and an assessment of the financial impact of environmental remediation before it purchased 4–6 Grand Avenue represents ineffective administration and governance.
TfNSW acquired the site at a time when there was demand and increasing prices for industrial property in the area. However, TfNSW did not effectively assess and manage the risks associated with the acquisition, and gaps in process led to increased risk. Briefings to decision-makers did not contain important information, and we found no evidence that gaps in advice were queried or explored by decision-makers.

TfNSW did not have plans or advice in place to assist in managing risk, such as:

  • a property acquisition plan
  • a comprehensive and up-to-date risk management plan
  • a negotiation strategy, or any authorisation limit or minimal acceptable position
  • an independent professional evaluation
  • external expert advice (with the exception of legal advice relating to the contract of sale).

TfNSW was aware of contamination issues affecting the land and had access to considerable information about the environmental conditions, such as site environmental audit reports and information on the NSW Environment Protection Authority's contaminated land register. However, TfNSW had not analysed specific technical information about the contamination and therefore was not aware of the risk implications and cost for remediation. Despite this, TfNSW changed its position from not accepting the risks and costs of contamination, to acquiring the site unconditionally. The basis for this decision is unclear and undocumented.

Briefing to senior leaders on the acquisition was silent on a number of important matters that would have been important for approvers to consider, including:

  • an explanation of the 40 per cent increase in purchase price between November 2015 and May 2016, and a 165 per cent increase from TfNSW’s offer in April 2015
  • the contamination risks associated with the site and an evidence-based estimate of potential costs to remediate the site
  • advice that an independent valuation had not been obtained, inconsistent with TfNSW policy.

Consideration of the acquisition by FIC was based on a summary business paper and was managed out-of-session, thereby removing the ability for comprehensive consideration of the acquisition proposal and its risks.

The probity management controls and assurances in place for the acquisition of the 4–6 Grand Avenue site were insufficient. These insufficiencies were exacerbated by the probity risk profile of the transaction.

The 4–6 Grand Avenue acquisition was a high-risk/high-value transaction, undertaken in a volatile property market in a short timeframe under pressure from Grand 4 Investments. TfNSW was engaging in a direct negotiation in advance of detailed planning for the acquisition, or the PLR as a whole. These circumstances contribute to heightened probity risk.

TfNSW did not establish a probity plan and sought no probity support throughout the acquisition. Also, with one exception, the staff involved in the acquisition did not complete conflict of interest declarations.

TfNSW was aware of the potential for probity or integrity issues with the transaction when it commissioned an internal audit in connection with the transaction in 2019. Internal discussions considered whether a misconduct investigation may be more appropriate, however no such investigation was undertaken.

TfNSW's insufficient probity practices, in addition to its failure to keep complete or comprehensive records of negotiations or decisions, reduce transparency of the process and its outcome and expose TfNSW to a greater risk of misconduct, corruption and maladministration.

At the time of the transaction, the TfNSW policy framework was not sufficiently risk-focussed and did not provide clarity on when officers ought to apply specific guidance or procedures. TfNSW's policies and procedures are more focussed on acquiring land to meet project needs and timeframes, and less on assuring value for money and managing risks.

At the time of its acquisition of 4–6 Grand Avenue, TfNSW had property acquisitions policies and procedures in place. Each of these were broadly sound in their content and intent. However, they lacked specificity on how or when to apply guidance, and when risk levels should elevate the importance of recommended guidance.

TfNSW's key guidance was principles based and relied on agency staff using their experience and expertise to apply guidance according to the circumstances of an individual transaction. This guidance was not duly applied in the acquisition of 4–6 Grand Avenue, Camellia. In addition, TfNSW does not have quality or control assurance to identify when TfNSW officers did not apply important policies or processes.

The primary focus of the TfNSW’s property acquisition guidance is to achieve vacant possession of land in a timeframe that meets the need of the relevant transport project. There is less specific focus on the need to meet the requirements of the NSW Government financial management framework.

Appendix one – Response from agency 

Appendix two – About the audit 

Appendix three – Performance auditing

 

Copyright Notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #349 - released (18 May 2021).

Published

Actions for Planning and Environment 2016

Planning and Environment 2016

Planning
Environment
Asset valuation
Compliance
Financial reporting
Fraud
Information technology
Internal controls and governance
Project management

Auditor-General, Margaret Crawford released a report on the planning and environment cluster today, concluding that the quality of financial reporting is improving. However, the cluster can improve its financial controls and governance framework.

Published

Actions for Health 2016

Health 2016

Health
Asset valuation
Compliance
Cyber security
Financial reporting
Fraud
Information technology
Internal controls and governance
Project management

This report analyses the results of the financial statement audits of the Health cluster agencies for 2015–16.

Published

Actions for Transport 2016

Transport 2016

Transport
Asset valuation
Compliance
Financial reporting
Fraud
Information technology
Internal controls and governance
Procurement
Project management

Financial reporting within the Transport Cluster continues to improve with reported misstatements down 96 per cent since 2011-12 to just three in 2015-16, according to a report released today by the NSW Auditor-General, Margaret Crawford.