This report outlines the results of audits of the financial statements of agencies now grouped in the NSW Planning, Industry and Environment cluster.

Unqualified audit opinions were issued for 56 of the 66 cluster agencies’ 30 June 2019 financial statements. Ten audits remain incomplete. The cluster agencies need to improve the timeliness of financial reporting. 

The Audit Office continued to identify issues regarding unprocessed Aboriginal land claims and the recognition of Crown land. ‘Auditor-General’s reports to parliament have recommended action to reduce the level of unprocessed land claims since 2007. However, the number of unprocessed claims continued to increase’, Margaret Crawford said.

One in five internal control findings were repeat issues. Key themes included information technology, asset management and improvements required to expense and payroll controls.

The report makes several recommendations including:

  • Property NSW should urgently address the deficiencies in the lease data used to calculate the impact of the new leasing standard effective from 1 July 2019
  • the Department of Planning, Industry and Environment should prioritise action to reduce unprocessed Aboriginal land claims
  • the Department of Planning, Industry and Environment should ensure the Crown land database is complete and accurate so state agencies and local government councils are better informed about the Crown land they control.

This report analyses the results of our audits of financial statements of the Planning, Industry and Environment cluster agencies for the year ended 30 June 2019. The table below summarises our key observations.

1. Machinery of Government changes

Creation of the Planning, Industry and Environment cluster

The Machinery of Government (MoG) changes abolished the former Planning and Environment cluster and former Industry cluster, and created the Planning, Industry and Environment cluster on 1 July 2019.

The Department of Planning and Environment (DPE), the Department of Industry (DOI), the Office of Environment and Heritage, and the Office of Local Government were abolished and the majority of their functions were transferred to the new Department of Planning, Industry and Environment (DPIE).

The Department of Planning, Industry and Environment is still in the process of implementing changes

The MoG changes bring risks and challenges to the cluster. A MoG Steering Committee, with the support of various project control groups and working groups, identified and developed responses to key risks arising from the changes.

However, the DPIE will take some time to fully integrate the policies, systems and processes of the abolished Departments and agencies.

2. Financial reporting

Audit opinions Unqualified audit opinions were issued for 56 of the 66 cluster agencies' 30 June 2019 financial statements audits. Ten financial statements audits are still ongoing.
Timeliness of financial reporting

Fifty-five of the 57 agencies subject to statutory deadlines submitted their financial statements on time.

Due to issues identified during the audit, 13 financial statements audits were not completed and audit opinions issued by the statutory deadline.

Agencies prepared and submitted their early close procedures in accordance with the mandatory timeframe set by NSW Treasury. However, 17 of the 49 agencies where we reviewed early close procedures were assessed as either partially addressing or not addressing one or more of the mandatory requirements. The cluster agencies could benefit from an increased focus on early close procedures.

Introduction of AASB 16 'Leases'

We noted errors in the lease data used in Property NSW's AASB 16 impact calculations, which affect both Property NSW and other government agencies. These errors were significant enough to present a risk of material misstatements to the financial statements of Property NSW and other government agencies in future reporting periods.

We had similar findings in our recent performance audit on 'Property Asset Utilisation', which highlighted issues with the quality of Property NSW's records.

Recommendation: Property NSW should urgently address the deficiencies in the lease data used to calculate the impact of the new leasing standard effective from 1 July 2019.

Unprocessed Aboriginal land claims have continued to increase

Despite an increase in the number of claims resolved, the number of unprocessed Aboriginal land claims increased by 7.2 per cent from the prior year to 35,855 at 30 June 2019. Claims can be made over Crown land assets of the DPIE or other government agencies. Until claims are resolved, there is an uncertainty over who is entitled to the land and the uses and activities that can be carried out on the land. We first recommended action to address unprocessed claims in 2007.

Recommendation (repeat issue): The DPIE should prioritise action to reduce unprocessed Aboriginal land claims.

3. Audit observations

Internal controls

One in five internal control issues identified and reported to management in 2018–19 were repeat issues.

The lack of user access review was the most common IT general control issue in the cluster.

Drought relief

The NSW Government announced an emergency drought relief package of $500 million in 2018, in addition to other financial assistance measures already in place.

Limited documentation and written agreements between relevant delivery agencies resulted in a $31.0 million misstatement relating to grant revenue.

Recognition of Crown land

Crown land is an important asset of the state. Management and recognition of Crown land assets is weakened when there is confusion over who is responsible for a particular Crown land parcel. Last year we recommended the DOI should ensure the database of Crown land is complete and accurate. While the DOI has commenced actions to improve the database, this continued to be an issue in 2018–19.

Recommendation (repeat issue): The DPIE should ensure the Crown land database is complete and accurate so state agencies and local government councils are better informed about the Crown land they control.

Developer contributions The former DPE continued to accumulate more developer contributions revenues than it spent on infrastructure projects. Total unspent funds increased to $274 million at 30 June 2019.

 

This report provides parliament and other users of the Planning, Industry and Environment cluster agencies financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

This cluster was created by the Machinery of Government changes on 1 July 2019. This report is focused on agencies in the Planning, Industry and Environment cluster from 1 July 2019. However, these agencies were all in other clusters during 2018–19. Please refer to the section on Machinery of Government changes for more details.

Machinery of Government (MoG) refers to how the government organises the structures and functions of the public service. MoG changes are where the government reorganises these structures and functions that are given effect by Administrative orders.

The MoG changes, announced following the NSW State election on 23 March 2019, created the Planning, Industry and Environment (PIE) cluster. The Administrative Changes Orders issued on 2 April 2019, 1 May 2019 and 28 June 2019 gave effect to these changes. These orders became effective on 1 July 2019.

Section highlights

The 2019 MoG changes significantly impacted the former Planning and Environment, and Industry clusters and agencies.

  • The PIE cluster combines most of the functions and agencies of the former Planning and Environment and Industry clusters from 1 July 2019.
  • The Department of Planning, Industry and Environment is the principal agency in the PIE cluster.
  • The MoG changes bring risks and challenges to the PIE cluster.
  • A MoG Steering Committee was established to oversee the transitional processes.
  • The full integration of the systems and processes will not be completed in the near future.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Planning, Industry and Environment (PIE) cluster for 2019. In this chapter, the Department of Planning, Industry and Environment is referred to as DPIE, the former Department of Planning and Environment as DPE, and the former Department of Industry as DOI.

Section highlights

  • Unqualified audit opinions were issued for all completed 30 June 2019 financial statements audits. However, some cluster agencies can further enhance the quality of financial reporting.
  • Timeliness of financial reporting remains an issue for 13 agencies.
  • Deficiencies were identified in the data used to calculate the impact of AASB 16 ‘Leases’ effective from 1 July 2019. Property NSW should urgently address these deficiencies.
  • Unprocessed Aboriginal land claims continue to increase. DPIE should prioritise action to reduce unprocessed Aboriginal land claims.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our audit observations and insights from our financial statement audits of agencies in the Planning, Industry and Environment (PIE) cluster for 2019. In this chapter, the Department of Planning, Industry and Environment is referred to as DPIE, the former Department of Planning and Environment as DPE, and the former Department of Industry as DOI.

Section highlights

  • One in five issues identified and reported to management in 2018–19 were repeat issues.
  • The lack of user access review was the most common IT general control issue in the PIE cluster.
  • The PIE cluster provided significant financial assistance for drought relief.
  • There continues to be significant deficiencies in Crown land records. The DPIE should ensure the Crown land database is complete and accurate.
  • Unspent developer contributions funds continued to build up in 2018–19. 

Appendix one – List of 2019 recommendations

Appendix two – Status of 2018 recommendations

Appendix three – Cluster agencies

Appendix four – Financial data

Appendix five – Management letter findings

Appendix six – Timeliness of financial reporting

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Mental health service planning for Aboriginal people in New South Wales

Mental health service planning for Aboriginal people in New South Wales

Health
Management and administration
Project management
Service delivery
Workforce and capability

A report released by the Auditor-General for New South Wales, Margaret Crawford, has found that NSW Health is not forming effective partnerships with Aboriginal communities to plan, design and deliver appropriate mental health services. There is limited evidence that NSW Health is using the knowledge and expertise of Aboriginal communities to guide how mental health care is structured and delivered.

Mental illness (including substance use disorders) is the main contributor to lower life expectancy and increased mortality in the Aboriginal population of New South Wales. It contributes to a higher burden of disease and premature death at rates that are 40 per cent higher than the next highest chronic disease group, cardiovascular disease.1 

Aboriginal people have significantly higher rates of mental illness than non Aboriginal people in New South Wales. They are more likely to present at emergency departments in crisis or acute phases of mental illness than the rest of the population and are more likely to be admitted to hospital for mental health treatments.2 

In acknowledgement of the significant health disparities between Aboriginal and non Aboriginal people, NSW Health implemented the NSW Aboriginal Health Plan 2013 2023 (the Aboriginal Health Plan). The overarching message of the Aboriginal Health Plan is ‘to build respectful, trusting and effective partnerships with Aboriginal communities’ and to implement ‘integrated planning and service delivery’ with sector partners. Through the Plan, NSW Health commits to providing culturally appropriate and ‘holistic approaches to the health of Aboriginal people'.

The mental health sector is complex, involving Commonwealth, state and non government service providers. In broad terms, NSW Health has responsibility to support patients requiring higher levels of clinical support for mental illnesses, while the Commonwealth and non government organisations offer non acute care such as assessments, referrals and early intervention treatments.

The NSW Health network includes 15 Local Health Districts and the Justice Health and Forensic Mental Health Network that provide care to patients during acute and severe phases of mental illness in hospitals, prisons and community service environments. This includes care to Aboriginal patients in the community at rates that are more than four times higher than the non Aboriginal population. Community services are usually provided as follow up after acute admissions or interactions with hospital services. The environments where NSW Health delivers mental health care include:

  • hospital emergency departments, for short term assessment and referral
  • inpatient hospital care for patients in acute and sub acute phases of mental illness
  • mental health outpatient services in the community, such as support with medications
  • custodial mental health services in adult prisons and juvenile justice centres.

The NSW Government is reforming its mental health funding model to incrementally shift the balance from hospital care to enhanced community care. In 2018–19, the NSW Government committed $400 million over four years into early intervention and specialist community mental health teams.

This audit assessed the effectiveness of NSW Health’s planning and coordination of mental health services and service pathways for Aboriginal people in New South Wales. We addressed the audit objective by answering three questions: 

  1. Is NSW Health using evidence to plan and inform the availability of mental health services for Aboriginal people in New South Wales?
  2. Is NSW Health collaborating with partners to create accessible mental health service pathways for Aboriginal people?
  3. Is NSW Health collaborating with partners to ensure the appropriateness and quality of mental health services for Aboriginal people?
Conclusion

NSW Health is not meeting the objectives of the NSW Aboriginal Health Plan, to form effective partnerships with Aboriginal Community Controlled Health Services and Aboriginal communities to plan, design and deliver mental health services.

There is limited evidence that existing partnerships between NSW Health and Aboriginal communities meet its own commitment to use the ‘knowledge and expertise of the Aboriginal community (to) guide the health system at every level, including (for) the identification of key issues, the development of policy solutions, the structuring and delivery of services' 3 and the development of culturally appropriate models of mental health care.

NSW Health is planning and coordinating its resources to support Aboriginal people in acute phases of mental illness in hospital environments. However, it is not effectively planning for the supply and delivery of sufficient mental health services to assist Aboriginal patients to manage mental illness in community environments. Existing planning approaches, data and systems are insufficient to guide the $400 million investment into community mental health services announced in the 2018–19 Budget.

NSW Health is not consistently forming partnerships to ensure coordinated care for patients as they move between mental health services. There is no policy to guide this process and practices are not systematised or widespread.

In this report, the term ‘Aboriginal people’ is used to describe both Aboriginal and Torres Strait Islander peoples. The Audit Office of NSW acknowledges the diversity of traditional countries and Aboriginal language groups across the state of New South Wales.


1 Australian Burden of Disease Study: Impact and causes of illness and death in Aboriginal and Torres Strait Islander people 2011 (unaudited).
2 Australian Institute of Health and Welfare data 2016–17 (unaudited).
3 NSW Health, The Aboriginal Health Plan 2013-2023.

In May 2019, the Audit Office of New South Wales invited Aboriginal mental health clinicians and policy experts from government and non-government organisations to attend a one-day workshop. Workshop attendees advised on factors that improve the quality and appropriateness of mental health care for Aboriginal people in New South Wales. They described appropriate mental health care as:

  • culturally safe, allowing Aboriginal people to draw strength in their identity, culture and community
  • person centred and focussed on individual needs
  • delivered by culturally competent staff with no bias
  • holistic, trauma-informed and focussed on early intervention where possible
  • delivered in places that are appropriate including outreach to homes and communities
  • welcoming of the involvement of local Aboriginal community and connected to local knowledge and expertise including totems and kinship structures. 

The definition of 'appropriate' mental health care for Aboriginal people throughout this report is based on this advice.

Aboriginal people access emergency services at much higher rates than non-Aboriginal people

The choices that people make in relation to health service options provide some insight into the suitability and appropriateness of the service to their needs.

Aboriginal people have different mental health service use patterns than non-Aboriginal people. Aboriginal people are much more likely to be in a crisis situation before receiving mental health services, usually in an emergency department of a hospital.

Aboriginal people make up three per cent of the total New South Wales population, but they constitute 11 per cent of emergency department presentations for mental health treatments. In regional areas, Aboriginal people make up 20.5 per cent of presentations at emergency departments for mental health reasons. 

A number of factors help to explain Aboriginal mental health service usage patterns. According to government and non-government mental health organisations:

  • emergency department services are better known to Aboriginal people than other mental health services
  • community-based models of care are not appropriate for Aboriginal people
  • Aboriginal people are reluctant to access community-based mental health services to prevent crisis situations
  • community mental health services are not available for Aboriginal people after hours and during the weekend, so emergency services are the only option.

The statewide proportions of Aboriginal people presenting at emergency departments for mental health treatments has been increasing over time (Exhibit 6).

Appendix one – Response from agency

Appendix two – The NSW Aboriginal Health Plan

Appendix three – About the audit

Appendix four – Performance auditing

 

Parliamentary Reference: Report number #326 - released 29 August 2019

Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Government Advertising 2017-18

Government Advertising 2017-18

Premier and Cabinet
Compliance
Regulation

The State Insurance Regulatory Authority’s (SIRA) ‘green slip refund’ campaign, and the TAFE semester one 2018 student recruitment campaign, complied with most requirements of the Government Advertising Act 2011 and the Government Advertising Guidelines, according to a report released today by the Auditor-General for New South Wales, Margaret Crawford.

The Government Advertising Act 2011 (the Act) requires the Auditor-General to conduct a performance audit on the activities of one or more government agencies in relation to government advertising campaigns in each financial year. The performance audit assesses whether a government agency or agencies has carried out activities in relation to government advertising in an effective, economical and efficient manner and in compliance with the Act, the regulations, other laws and the Government Advertising Guidelines (the Guidelines).

This audit examined two campaigns conducted in 2017–18:

  • the 'Green slip refund' campaign run by the State Insurance Regulatory Authority (SIRA)
  • the semester one component of the 'TAFE NSW 2018 Student Recruitment Annual Campaign Program' run by the NSW TAFE Commission (TAFE).

Section 6 of the Act prohibits political advertising. Under this section, material that is part of a government advertising campaign must not contain the name, voice or image of a minister, member of parliament or a candidate nominated for election to parliament or the name, logo or any slogan of a political party. Further, a campaign must not be designed to influence (directly or indirectly) support for a political party.

Conclusion
Neither campaign breached the prohibition on political advertising contained in section 6 of the Act. Both campaigns also complied with most requirements of the Act, the regulations, other laws and the Guidelines. Neither agency could demonstrate that their campaigns were fully effective or economical.
SIRA did not breach section 6 of the Act, which prohibits political advertising. However, SIRA used its post-campaign evaluation to ask the public whether they believe the government was helping to reduce the cost of living by making reforms in a variety of areas, including some that were not related to the green slip campaign. SIRA advised that these additional statements were included to provide a broader context for any change in the green slip campaign survey results. This is not an appropriate use of the post-campaign evaluation because the post-campaign evaluation should measure the success of the campaign against its stated objectives.
Neither campaign met all their key objectives, limiting the overall effectiveness of the campaigns. SIRA successfully increased awareness of the availability of green slip refunds and met the target for the proportion of people claiming their refunds online. However, it did not meet its objective to inform the public about the reforms to the green slip scheme, beyond the refunds available to motorists. While 62 per cent of surveyed people were aware of the reforms, there was little knowledge about many specific aspects of the reforms, which people largely associated with lower insurance prices and refunds. TAFE was successful in achieving targets for changing the public perception of TAFE. However, it failed to achieve its semester one enrolment target.
SIRA was not able to demonstrate that its campaign was economical as it directly negotiated with a single supplier for the campaign's creative materials. This is contrary to the NSW Government's and SIRA's own procurement guidance that advise it to seek quotes from suppliers on a prequalification scheme if available. SIRA had access to the Advertising and Digital Communication Services prequalification scheme, but still continued with direct negotiations. While SIRA sought to demonstrate value for money by comparing the supplier's quote to the expenditure on creative materials in other campaigns, it did not document this evaluation to ensure that decision makers were fully informed. 
TAFE was not able to demonstrate that its campaign was economical as it did not compare the campaign with a zero-advertising scenario to demonstrate the exact benefits directly attributable to the campaign. TAFE's cost-benefit analysis also did not identify to what extent benefits could be achieved without advertising, nor did it consider alternatives to advertising which could achieve the same impact as the advertising campaign. All these elements should have been included in TAFE's cost benefit analysis.
Both agencies achieved some efficiencies in implementing their campaigns. SIRA booked all of its media placements in a cost-efficient manner. TAFE booked most of its media placements in a cost-efficient manner and achieved further efficiencies through the re-use of previous campaign material.

The State Insurance Regulatory Authority (SIRA) conducted the 'Green slip refund' campaign between March and June 2018. SIRA ran this campaign to raise awareness of the Compulsory Third Party (CTP) refunds and reforms after the Motor Accidents Injuries Act 2017 commenced in December 2017. SIRA's view is that the reforms include a reduced cost for CTP insurance, benefits for at-fault drivers, reduced opportunity for fraud and attempts to lower insurance company profits. Green slip holders are also able to claim partial refunds on their 2017 green slip insurance premium. The campaign aimed to make green slip holders aware of the refunds available, encourage them to claim online and to inform people about the changes to the green slip scheme. The campaign focused on the first two of these objectives. The total cost of the campaign was $1.9 million. See Appendix two for more details on this campaign.

The 'Green slip refund' advertising campaign did not breach section 6 of the Act which prohibits political advertising. However, SIRA used its post-campaign evaluation to ask the public whether they believe the government was helping to reduce the cost of living by making reforms in a variety of areas, including some that were not related to the green slip campaign. SIRA advised that these additional statements were included to provide a broader context for any change in the green slip campaign survey results. This is not an appropriate use of the post-campaign evaluation because the post-campaign evaluation should measure the success of the campaign against its stated objectives. 
The campaign met most of its objectives, including raising awareness of the green slip refunds and encouraging people to claim online. However, the campaign was not fully effective because it did not inform the public of the green slip reforms. This was one of the objectives of the campaign. Sixty-two per cent of people in the post-campaign survey stated that they were aware of the reforms, an increase from the baseline of 20 per cent. However, these people largely associated the reforms with lower insurance prices and had a low awareness of any other elements of the reforms, such as SIRA's view that the reforms introduced better support for people injured on the road. This indicates that the campaign did little to inform people about the green slip reforms beyond the price of insurance. 
SIRA was able to ensure cost-efficient media purchases by signing its media booking authority within the timeframe advised by DPC.
SIRA could not demonstrate that the campaign was carried out economically. SIRA directly negotiated with a single supplier to procure the creative materials for this campaign. Direct negotiations make it difficult to ensure value for money due to the lack of competition. SIRA proceeded with direct negotiations despite being able to access a prequalification scheme which could increase competition. In doing so, SIRA did not follow government's or its internal procurement guidance. While SIRA sought to demonstrate value for money by comparing the supplier's quote to the expenditure on creative materials in other campaigns, it did not document this evaluation to ensure that decision makers were fully informed. 

Campaign materials we reviewed did not breach section 6 of the Act

Section 6 of the Act prohibits political advertising as part of a government advertising campaign. A government advertising campaign must not:

  • be designed to influence (directly or indirectly) support for a political party
  • contain the name, voice or image of a minister, a member of parliament or a candidate nominated for election to parliament
  • contain the name, logo, slogan or any other reference to a political party.

The audit team found no breaches of section 6 of the Act in the campaign material we reviewed.

Before the start of the campaign, SIRA conducted a survey which asked people whether they agreed ‘that the NSW Government is helping to reduce the cost of living by making positive reforms to:

  • reduce the cost of green slips
  • reduce the cost of health insurance
  • increase the number of jobs
  • increase investment in the state.'

SIRA's initial submission to peer review listed one of the campaign objectives as improving the perception of the government as a positive reformer. DPC advised SIRA that this should not be included. SIRA removed this objective.

Even though SIRA appropriately removed this objective, the post-campaign evaluation still measured agreement with the above statements, three of which did not relate to this campaign or SIRA's responsibilities. SIRA advised that these three additional statements were included to provide a broader context for any change in the green slip campaign survey results. For example, if all four measures reported an increase in positive responses of roughly the same size, then the increase may have been due to factors other than the advertising campaign.

This is not an appropriate use of the post-campaign evaluation, which should measure the success of the campaign against its stated objectives. The Guidelines list the purposes that government advertising may serve and none of these relate to improving the perception of the government. The inclusion of the above questions in SIRA's post-campaign evaluation creates a risk that the results may be used for party political purposes.

The campaign met most targets, however some were not challenging to achieve

The post-campaign evaluation demonstrated that the campaign met the targets for 12 of its 13 objectives including the targets relating to raising awareness of the refunds and the proportion of people claiming their refunds online. A fourteenth objective, the percentage of people aware that they should contact SIRA after a road accident injury, did not have a target set, meaning that it is not possible to say whether the campaign had the desired impact in this case.

In August 2017, before the campaign commenced, SIRA conducted a survey to determine the baselines for some of its objectives. This is a good practice to support an effective post campaign evaluation process. The survey found that 20 per cent of people were aware of the green slip reforms. SIRA's objective was to raise this to 25 per cent, which represents a small gain relative to the proposed campaign expenditure. The campaign aimed for 40 per cent of motorists to be aware of refunds, which is very low given that this was the primary focus of the campaign. SIRA followed the advice of its survey provider when setting these targets. 

In the survey carried out after the campaign, 66 per cent of people were aware of the availability of green slip refunds for most motorists. The campaign also aimed to get 83 per cent of motorists to claim their refunds via online channels. It met this target, with a total of 84 per cent. Finally, 62 per cent of people in the post-campaign survey were aware of the green slip reforms. This result is discussed further below.

The overall target for total number of refunds claimed is 85 per cent of eligible drivers, that is to say CTP holders. SIRA will evaluate the results of this objective after the conclusion of the refund period in June 2019.

The campaign did little to inform the public about the broader green slip reforms

One objective of the green slip refund campaign was to inform the public about the green slip reforms. The final campaign creative material focused almost entirely on the green slip refunds rather than the range of other reforms. This was because the peer review raised concerns that the creative material was attempting to deliver too many messages. 

The campaign submission stated that the advertising campaign would raise awareness of the broader reforms to the CTP scheme, citing several examples such as reduced opportunities for fraud and reduced insurer profits. SIRA also advised the Minister for Finance, Services and Property that secondary messaging in the campaign would benefit public understanding of the reforms.

Some of the television and radio advertisements referred to ‘more protection’ or ‘better protection’ for people injured on New South Wales roads, however advertisements did not refer to other elements of the reforms. Other campaign creative materials contained messages solely relating to the green slip refund and made no further reference to the broader reforms. SIRA used other communication channels, such as giving wallet cards to health service providers, to spread these messages to people, particularly those who had been injured.

Sixty two per cent of people in the post-campaign survey were aware of the green slip reforms. SIRA asked these people which benefits they associated with the reforms. The results of this survey are in Exhibit 4. Seventy-one per cent of this sample identified the reduced costs of green slips as one of the changes, but awareness of other elements of the reforms remains low. Though 29 per cent of people perceive the reforms to make the green slip scheme ‘fairer’, no more than 15 per cent of people could list a specific benefit which did not relate to insurance prices.

Exhibit 4: Perceived benefits associated with the changes to the CTP green slip scheme
Perceived benefit Percentage aware of this benefit
Reduced costs of green slips for vehicle owners 71%
A fairer scheme for all people 29%
Reduced costs of comprehensive vehicle insurance 20%
Better support for people injured on our roads 15%
Less chances of fraudulent claims 15%
Lowering insurance company profits 13%
Quicker payment of claims to injured people 10%

Source: State Insurance Regulatory Authority.

Another campaign target was to ensure that people understood that they should contact SIRA in case of an injury. None of the campaign creative materials contained this information. SIRA did some limited work to inform the public about this through its social media channels. One of the pieces of creative material directed the reader to SIRA's website for further information on the reforms, which contained this information. During the campaign period, there was an increase in the number of calls received by SIRA's CTP Assist phone line. However, in the post-campaign evaluation, only two per cent of surveyed people identified that they should contact SIRA in case of an injury.

The media plan allowed sufficient time for cost-efficient media placement

During the peer review process, DPC provides advice to agencies about the time they should allow to ensure cost-efficient media placement. For example, DPC advise that agencies book television advertising six to 12 weeks in advance and that agencies book radio advertising two to eight weeks in advance.

SIRA allowed sufficient time between the completion of the peer review process and the commencement of the first advertising. SIRA signed the agreement with the approved Media Agency Services provider eight weeks before the campaign started, meaning that it could achieve cost-efficient media placement for all types of media used in this campaign.

SIRA directly negotiated with a single supplier, making it difficult to demonstrate value for money

SIRA directly negotiated with a single supplier to procure the campaign's creative material. A direct negotiation occurs when an agency negotiates with a proponent without first undergoing a competitive process. It is difficult to demonstrate value for money using direct negotiation due to the lack of competition. 

ICAC's 'Guidelines for managing risks in direct negotiations' (ICAC Guidelines) provide guidance on how to undertake direct negotiations. SIRA has a direct negotiation checklist that aligns to the ICAC Guidelines. The SIRA checklist advises that staff should confirm that existing New South Wales prequalification schemes cannot provide the procurement before undertaking a direct negotiation. SIRA did not do this.

To procure creative materials, agencies can access the Advertising and Digital Communication Services prequalification scheme (the prequalification scheme). Using the prequalification scheme allows agencies to quickly seek quotes from suppliers who have a demonstrated track record and expertise. While agencies are not required to use the prequalification scheme, the NSW Procurement Board advises that agencies should use prequalification schemes where they are available to promote competition. 

By using direct negotiation when the prequalification scheme was available, and by not seeking quotes from other suppliers, SIRA was acting in a way that reduced competition. This increases the risk that SIRA did not achieve value for money in its procurement of creative materials.

SIRA advised that it sought to ensure value for money by comparing the quote from its selected supplier with the amount spent on creative materials in other campaigns of similar size. SIRA did not document this analysis at the time or include it as part of the briefing note staff used to seek approval for undertaking direct negotiation. As a result, decision-makers were not fully informed when approving this engagement. 

SIRA reported in a briefing note that it engaged in direct negotiations because:

  • it believed that the original timeframe did not allow for a competitive tender process
  • the supplier had done previous work on a related campaign for SIRA
  • the supplier provided sample work which received positive feedback from focus groups.

In July 2017, when peer review commenced, SIRA planned to launch the campaign in November 2017 to coincide with the beginning of the green slip reforms. SIRA believed that this timeframe was narrow enough to warrant entering direct negotiations. The ICAC Guidelines advise that a narrow timeframe is not a valid reason to enter into a direct negotiation. In late October 2017, the campaign launch was delayed until March 2018 to stagger the demand on the resources of Service NSW, which is administering the refund. 

The ICAC Guidelines also advise against re-appointing a supplier because it has performed previous work. Instead, agencies could consider previous experience as one of several factors when deciding between quotes. In cases where an agency asks a supplier to provide sample work, the ICAC Guidelines advise that agencies should request sample work from multiple potential suppliers to promote competition.

The campaign's cost benefit analysis complied with the Act and Guidelines 

The Act requires a cost benefit analysis (CBA) for any government advertising campaign likely to exceed $1.0 million in value. Section six of the Guidelines set out the requirements for a government advertising CBA. The campaign's CBA complied with the requirements of the Act and the Guidelines.

The campaign CBA could have demonstrated further cost effectiveness if it considered alternative media mixes as outlined in NSW Treasury's 'Cost Benefit Analysis Framework for Government Advertising and Information Campaigns'. This would also have been consistent with the Handbook.

The cluster Secretary signed the compliance certificate instead of the head of SIRA

The Act requires the head of the agency running the campaign to sign a compliance certificate. 

The Secretary of the Department of Finance, Services and Innovation, the cluster to which SIRA belongs, signed the campaign's compliance certificate. However, section 17(2) of the State Insurance and Care Governance Act 2015 states that SIRA is ‘for the purposes of any Act, a NSW Government agency.’ Given this, the Chief Executive of SIRA was responsible for signing the compliance certificate for this campaign.

This is a minor non-compliance with the Act because the Chief Executive had reviewed the campaign and recommended that the Secretary sign the compliance certificate.  

The NSW TAFE Commission (TAFE) ran the 'TAFE NSW 2018 Student Recruitment Annual Campaign Program' from November 2017 to September 2018. The aim of the campaign was to assist TAFE in achieving its 2018 student enrolment target by improving the perception of TAFE's brand and generating student enquiries. This is the first state-wide campaign run by TAFE operating under the One TAFE model. Previously, each TAFE Institute ran its own campaigns. The total budget of the campaign was $19.5 million. This audit examined only the semester one 2018 component of the campaign, which ran from November 2017 to April 2018 at a total cost of $9.5 million. See Appendix two for more details on this campaign.

The semester one component of the 'TAFE NSW 2018 Student Recruitment Annual Campaign Program' did not breach the specific provisions of section 6 of the Act which prohibits political advertising.
The campaign was not fully effective because it did not achieve its objective of reaching TAFE's semester one enrolment target.
The campaign was successful at achieving the campaign's targets which related to changing the public perception of TAFE.
TAFE was able to place most of its campaign media within cost-efficient timeframes. TAFE also achieved efficiencies by re-using many creative materials from a previous campaign.
TAFE could not demonstrate this campaign was carried out economically. TAFE's cost benefit analysis (CBA) for this campaign did not comply with three requirements of the Guidelines. For example, TAFE did not compare the campaign to a baseline case of not advertising. 
The Guidelines require government advertising to be accurate in all statements. TAFE breached this requirement. The campaign material included one statement that was inaccurate and one that was overstated.
The revision of the Brand Guidelines in August 2017 impacted this campaign. TAFE re-used many creative materials that were created when TAFE was not required to include the NSW Government logo on its advertising material. DPC appears to have directed agencies that were launching advertising campaigns to immediately comply with the Brand Guidelines, however we could not find evidence that this advice was given to TAFE. As such, 59 per cent of TAFE's materials were not compliant with the Brand Guidelines at the launch of the campaign in November 2017. TAFE had made most of this campaign's creative materials compliant by June 2018.

The campaign materials we reviewed did not breach section 6 of the Act

Section 6 of the Act prohibits political advertising as part of a government advertising campaign. A government advertising campaign must not:

  • be designed to influence (directly or indirectly) support for a political party
  • contain the name, voice or image of a minister, a member of parliament or a candidate nominated for election to parliament
  • contain the name, logo, slogan or any other reference to a political party.

The audit team found no breaches of section 6 of the Act in the campaign material we reviewed.

The campaign achieved 16 of 24 objectives, but did not reach its enrolment target

The campaign had 24 objectives which had a target for semester one. TAFE set these targets using a combination of previous experience, corporate objectives and brand surveys.

The overall objective of the combined semester one and two campaigns was to support TAFE achieving its 2018 total enrolment target of 549,636. TAFE's semester one target was 361,350, which it did not achieve. This indicates that the campaign was not fully effective.

The campaign achieved 11 of its 16 output objectives. The output targets related to TAFE's media placements and ability to reach an audience efficiently. TAFE tracked progress against many of the campaign's output objectives daily. TAFE altered its media channels throughout the campaign meaning that some of the output objectives were not met because TAFE decided to focus on alternative media channels. The campaign also achieved all seven of its outcome objectives. The outcome objectives related to changing the public perception of TAFE.

TAFE's initial media plan allowed for efficient media placement

During the peer review process, DPC provides advice to agencies about the time they should allow to ensure cost-efficient media placement. For example, DPC advise that agencies book television advertising six to 12 weeks in advance and that agencies book radio advertising two to eight weeks in advance. 

While TAFE's initial media plan allowed sufficient time between the approval of the campaign and its launch, a delay in receiving final approval for the campaign meant TAFE could not purchase media placements until two months later than planned. Most purchases still remained within DPC's recommended timeframes, but Indigenous television advertisements and metropolitan out of home advertisements both fell outside DPC's recommended time periods by one week. These delays did not impact on TAFE's efficiency.

TAFE re-used many creative materials, achieving some cost-savings

Rather than commissioning new creative materials, TAFE re-used many creative materials from the previous campaign and supplemented these with a selection of new creative materials. TAFE advised that this led to a cost saving of approximately $130,000.
TAFE sought quotes from suppliers on the government's Advertising and Digital Communication Services prequalification scheme for two creative material contracts. These contracts covered updates to existing materials and a selection of new materials.

The campaign's cost-benefit analysis did not comply with three requirements of the Guidelines

The Act requires an agency to conduct a cost-benefit analysis (CBA) if the cost of an advertising campaign is likely to exceed $1.0 million. The Guidelines set out the requirements of this CBA. TAFE did not comply with three of these requirements, outlined in Exhibit 5.

Exhibit 5: Guideline requirements for CBAs with which TAFE did not comply
6.2 The cost benefit analysis must isolate the additional costs and benefits attributable to the advertising campaign itself compared to the base-case of not-advertising.
6.3 The cost benefit analysis must specify the extent to which the expected benefits could be achieved without advertising.
6.4 The cost benefit analysis must outline what options other than advertising could be used to successfully implement the program and achieve the program benefits and a comparison of their costs.
Source: NSW Government Advertising Guidelines (2012).

In this circumstance, section 6.2 of the Guidelines required the CBA to identify the number of enrolments TAFE would expect if it did not advertise. TAFE advised us that it is not possible to say what this scenario would look like because there had always been some degree of advertising, however, this argument is not reflected in the CBA. 

TAFE used 2017 as the baseline in the CBA. In 2017, TAFE spent $13.2 million on advertising. As such, the CBA was only able to isolate the impact of the increased expenditure rather than the impact of the campaign's entire $19.5 million expenditure. TAFE advised that 2017 had the most reliable state-wide data and this contributed to the decision to use it as the baseline.

During the audit, TAFE sought advice from NSW Treasury regarding whether a 2017 baseline was appropriate and NSW Treasury advised that it was. Regardless, TAFE did not receive this advice prior to writing the CBA and did not put commentary around this in the CBA. This would also not be sufficient for fulfilling the requirements of the Guidelines.

The CBA did not comply with sections 6.3 and 6.4 of the Guidelines. The CBA briefly considered the impact of spending the campaign budget directly on new training courses, however there was no sustained analysis of this option. TAFE staff advised that there are no realistic alternatives to advertising for achieving the campaign's objectives. However we did not see analysis to support this conclusion in documents provided to us. 

The campaign CBA could have better demonstrated cost effectiveness if it considered alternative media mixes as outlined in NSW Treasury's 'Cost Benefit Analysis Framework for Government Advertising and Information Campaigns'. This would also have been consistent with the Handbook.

TAFE made one inaccurate claim in its advertising and overstated a second

The Guidelines set out rules regarding the content of a government advertising campaign. Exhibit 6 sets out one of the principles with which agencies must comply.

Exhibit 6: Guidelines' requirement for accuracy
The following principles apply to the style and content of government advertising campaigns:
  • Accuracy in the presentation of all facts, statistics, comparisons and other arguments. All statements and claims of fact included in government advertising campaigns must be able to be substantiated.
Source: NSW Government Advertising Guidelines (2012).

TAFE made one inaccurate claim in its advertising and overstated a second.

In some campaign creative material, TAFE claimed that 78 per cent of its own graduates are employed after training (Exhibit 15 in Appendix 2). According to the National Centre for Vocational Education Research, 78 per cent of New South Wales Vocational Education and Training (VET) graduates (i.e. from all training providers) are employed after training. The result for TAFE graduates is 70.4 per cent.

One of the campaign's television advertisements refers to TAFE as ‘Australia's most reputable education provider’. This statement referred to a survey of current TAFE students who were asked where they would consider studying in future: TAFE, University or a private college. The current TAFE students selected TAFE by a large margin. The limited scope of TAFE's student survey and its results do not support the claim that it is ‘Australia's most reputable education provider’.

DPC did not consistently communicate the transitional arrangements for the Brand Guidelines and as such much of TAFE's creative material did not comply at campaign launch

On 7 August 2017, the government released the NSW Government Brand Guidelines (Brand Guidelines), setting out how agencies use the NSW Government logo. The Brand Guidelines replaced the Branding Style Guide which had been in place since September 2015. Some agencies were exempt from using the Branding Style Guide and the introduction of the new Brand Guidelines required these agencies to apply for a new exemption.

TAFE had recently commenced the peer review process for this campaign when the Brand Guidelines were released. TAFE was exempt from the requirements of the Branding Style Guide and as such the material which TAFE was planning to re-use in the new campaign did not contain the NSW Government logo.

Communication about how long agencies had to make themselves compliant with the Brand Guidelines was unclear. On 11 August 2017, the Chair of the Cabinet Standing Committee on Communication and Government Advertising (the Committee) sent a letter to the Secretary of the Department of Industry informing him that the Department must update all its material to be compliant with the Brand Guidelines ‘as soon as practicable within an 18-month transition period’. The Department of Industry advised TAFE that new advertising would need to be immediately compliant, however it was not clear if this included materials which agencies were re-using from previous campaigns. DPC advised the audit team that it expected re-used materials to be compliant when agencies launched new campaigns. DPC provided this advice to some agencies but did not communicate it more broadly. We could not source evidence that DPC provided this advice to TAFE.

DPC ran workshops to explain the transitional arrangements in September 2017 for the changes in the Brand Guidelines, however these did not specifically address the transitional timeframes for new advertising campaigns.

The Department of Industry, on behalf of TAFE, applied to the Committee for approval to co-brand the TAFE logo with the NSW Government logo. This was approved in October 2017. The requirements for co-branding are in Exhibit 7.

Exhibit 7: Co-branding in the NSW Government Brand Guidelines

Co-branding partners the agency logo with the NSW Government logo. The NSW Government logo must always be presented as the dominant or lead brand. The Brand Guidelines provide the following template shown below the exhibit box.

The NSW Government logo is on the left and the agency logo is placed on the right, with a dividing line between them.

Published

Actions for Unsolicited proposal process for the lease of Ausgrid

Unsolicited proposal process for the lease of Ausgrid

Premier and Cabinet
Asset valuation
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Service delivery
Shared services and collaboration

In October 2016, the NSW Government accepted an unsolicited proposal from IFM Investors and AustralianSuper to lease 50.4 per cent of Ausgrid for 99 years. The deal followed the Federal Government’s rejection of two bids from foreign investors, for national security reasons.

A performance audit of the lease of Ausgrid has found shortcomings in the unsolicited proposal process. Releasing the audit findings today, the Auditor-General for New South Wales, Margaret Crawford said ‘this transaction involved a $20 billion asset owned by the people of New South Wales. As such, it warranted strict adherence to established guidelines’.

Ausgrid is a distributor of electricity to eastern parts of Sydney, the Central Coast, Newcastle and the Hunter Region.

In June 2014, the then government announced its commitment to lease components of the state's electricity network as part of the Rebuilding NSW plan. Implementation of the policy began after the government was re-elected in 2015. Between November 2015 and August 2016, the NSW Government held a competitive tender process to lease 50.4 per cent of Ausgrid for 99 years. The NSW Government abandoned the process on 19 August 2016 after the Australian Treasurer rejected two bids from foreign investors, for national security reasons. That day, the Premier and Treasurer released a media statement clarifying the government's objective to complete the transaction via a competitive process in time to include the proceeds in the 2017–18 budget.

On 31 August 2016, the state received an unsolicited proposal from IFM Investors and AustralianSuper to acquire an interest in Ausgrid under the same terms proposed by the state during the tender process. In October 2016, the government accepted the unsolicited proposal. 

This audit examined whether the unsolicited proposal process for the partial long-term lease of Ausgrid was effectively conducted and in compliance with the government’s 2014 Unsolicited Proposals: Guide for Submission and Assessment (Unsolicited Proposals Guide or the Guide). 

The audit focused on how the government-appointed Assessment Panel and Proposal Specific Steering Committee assessed key requirements in the Guide that unsolicited proposals must be demonstrably unique and represent value for money. 

Conclusion

The evidence available does not conclusively demonstrate the unsolicited proposal was unique, and there were some shortcomings in the negotiation process, documentation and segregation of duties. That said, before the final commitment to proceed with the lease, the state obtained assurance that the proposal delivered value for money. 

It is particularly important to demonstrate unsolicited proposals are unique, in order to justify the departure from other transaction processes that offer greater competition, transparency and certainty about value for money.

The Assessment Panel and the Proposal Specific Steering Committee determined the Ausgrid unsolicited proposal was unique, primarily on the basis that the proponent did not require foreign investment approval from the Australian Treasurer, and the lease transaction could be concluded earlier than through a second tender process. However, the evidence that persuaded the Panel and Committee did not demonstrate that no other proponent could conclude the transaction in time to meet the government’s deadline. 

It is not appropriate to determine an unsolicited proposal is unique because it delivers an earlier outcome than possible through a tender process. The Panel and Committee did not contend, and it is not evident, that the unsolicited proposal was the only way to meet the government’s transaction deadline.

The evidence does not demonstrate that the proponent was the only party that would not have needed foreign investment approval to participate in the transaction. It also does not demonstrate that the requirement for foreign investment approval would have reduced the pool of foreign buyers to the degree that it would be reasonable to assume none would emerge. 

The Panel, Committee and financial advisers determined that the final price represented value for money, and that retendering offered a material risk of a worse financial outcome. However, an acceptable price was revealed early in the negotiation process, and doing so made it highly unlikely that the proponent would offer a higher price than that disclosed. The Department of Premier and Cabinet (DPC) and NSW Treasury were not able to provide a documented reserve price, bargaining strategy or similar which put the negotiations in context. It is not evident that the Panel or Committee authorised, justified or endorsed negotiations in advance. 

Key aspects of governance recommended by the Guide were in place. Some shortcomings relating to role segregation, record keeping and probity assurance weakened the effectiveness of the unsolicited proposal process adopted for Ausgrid.

The reasons for accepting that the proposal and proponent were unique are not compelling.

The Unsolicited Proposals Guide says the 'unique benefits of the proposal and the unique ability of the proponent to deliver the proposal' must be demonstrated. 

The conclusion reached by the Panel and Committee that the proposal offered a ‘unique ability to deliver (a) strategic outcome’ was primarily based on the proponent not requiring foreign investment approval from the Australian Treasurer, and allowing the government to complete the lease transaction earlier than by going through a second tender process. 

It is not appropriate to determine an unsolicited proposal is unique because it delivers an earlier outcome than possible through a tender process. The Panel and Committee did not contend, and it is not evident, that the unsolicited proposal was the only way to meet the government’s transaction deadline.

The evidence does not demonstrate that the proponent was the only party that would not have needed foreign investment approval to participate in the transaction. Nor does it demonstrate that the requirement for foreign investment approval would have reduced the pool of foreign buyers to the degree that it would be reasonable to assume none would emerge. 

That said, the Australian Treasurer’s decision to reject the two bids from the previous tender process created uncertainty about the conditions under which he would approve international bids. The financial advisers engaged for the Ausgrid transaction informed the Panel and Committee that:

  • it was not likely another viable proponent would emerge soon enough to meet the government’s transaction deadline
  • the market would be unlikely to deliver a better result than offered by the proponent
  • going to tender presented a material risk of a worse financial result. 

The Unsolicited Proposals Guide says that a proposal to directly purchase or acquire a government-owned entity or property will generally not be unique. The Ausgrid unsolicited proposal fell into this category. 

Recommendations:
DPC should ensure future Assessment Panels and Steering Committees considering a proposal to acquire a government business or asset:

  • recognise that when considering uniqueness they should: 
    • require very strong evidence to decide that both the proponent and proposal are the only ones of their kind that could meet the government’s objectives 
    • give thorough consideration to any reasonable counter-arguments against uniqueness.
  • rigorously consider all elements of the Unsolicited Proposals Guide when determining whether a proposal should be dealt with as an unsolicited proposal, and document these deliberations and all relevant evidence
  • do not use speed of transaction compared to a market process as justification for uniqueness.
The process to obtain assurance that the final price represented value for money was adequate. However, the negotiation approach reduced assurance that the bid price was maximised. 

The Panel and Committee concluded the price represented value for money, based on peer-reviewed advice from their financial advisers and knowledge acquired from previous tenders. The financial advisers also told the Panel and Committee that there was a material risk the state would receive a lower price than offered by the unsolicited proposal if it immediately proceeded with a second market transaction. 

The state commenced negotiations on price earlier than the Guide says they should have. Early disclosure of a price that the state would accept reduced the likelihood of achieving a price greater than this. DPC says the intent of this meeting was to quickly establish whether the proponents could meet the state’s benchmark rather than spending more time and resources on a proposal which had no prospect of proceeding.

DPC and NSW Treasury were not able to provide a documented reserve price, negotiation strategy or similar which put the negotiations and price achieved in context. It was not evident that the Panel or Committee authorised, justified or endorsed negotiations in advance. However, the Panel and Committee endorsed the outcomes of the negotiations. 

The negotiations were informed by the range of prices achieved for similar assets and the specific bids for Ausgrid from the earlier market process.

Recommendations:
DPC should ensure any future Assessment Panels and Steering Committees considering a proposal to acquire a government business or asset:

  • document a minimum acceptable price, and a negotiating strategy designed to maximise price, before commencing negotiations
  • do not communicate an acceptable price to the proponent, before the negotiation stage of the process, and then only as part of a documented bargaining strategy.
Key aspects of governance recommended by the Guide were in place, but there were some shortcomings around role segregation, record keeping and probity assurance.

The state established a governance structure in accordance with the Unsolicited Proposals Guide, including an Assessment Panel and Proposal Specific Steering Committee. The members of the Panel and Steering Committee were senior and experienced officers, as befitted the size and nature of the unsolicited proposal. 

The separation of negotiation, assessment and review envisaged by the Guide was not maintained fully. The Chair of the Assessment Panel and a member of the Steering Committee were involved in negotiations with the proponent. 

DPC could not provide comprehensive records of some key interactions with the proponent or a documented negotiation strategy. The absence of such records means the Department cannot demonstrate engagement and negotiation processes were authorised and rigorous. 

The probity adviser reported there were no material probity issues with the transaction. The probity adviser also provided audit services. This is not good practice. The same party should not provide both advisory and audit services on the same transaction.

Recommendations:
DPC should ensure any future Assessment Panels and Steering Committees considering a proposal to acquire a government entity or asset:
•    maintain separation between negotiation, assessment and review in line with the Unsolicited Proposals Guide
•    keep an auditable trail of documentation relating to the negotiation process
•    maintain separation between any probity audit services engaged and the probity advisory and reporting services recommended in the current Guide.

Published

Actions for Industry 2018

Industry 2018

Industry
Asset valuation
Cyber security
Financial reporting
Information technology
Internal controls and governance
Service delivery

The Auditor-General for New South Wales, Margaret Crawford, released her report today on the Industry cluster. The report focuses on key observations and findings from the most recent financial audits of agencies in the cluster. Cluster agencies received unqualified audit opinions for 41 out of the 47 financial statements presented for audit for 30 June 2018. Six audits remain incomplete. 'While it is pleasing to note that unqualified audit opinions have been issued, the timeliness of financial reporting needs to be improved through better oversight, prompt resolution of issues, and an increased focus on early close procedures', the Auditor-General said.

This report analyses the results of our audits of financial statements of the Industry cluster for the year ended 30 June 2018. The table below summarises our key observations.

This report provides parliament and other users of the Industry cluster agencies' financial statements with the results of our audits, including our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations
  • service delivery.

The Department of Industry (the Department) is the lead agency in a cluster of 50 agencies. Other significant agencies in the cluster include Local Land Services, New South Wales Rural Assistance Authority, Technical and Further Education Commission (TAFE NSW), various sporting agencies, Forestry Corporation NSW and Water NSW.

The cluster:

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Industry cluster for 2018.
 

Observation Conclusions and recommendations
2.1 Quality of financial reporting
Unqualified audit opinions were issued for 41 out of 47 financial statement audits. Six audits are continuing.

The number of misstatements identified in financial statements submitted for audit increased from 73 in 2016–17 to 92 in 2017–18.
Conclusion: Agencies continue to address financial reporting issues and ensure significant matters that may impact the audit opinion are appropriately dealt with. The increase in the number of misstatements indicates a renewed focus on quality is required.
2.2 Timeliness of financial reporting
Nineteen out of 37 audit opinions were issued within the statutory deadline. Delays occurred due to the time required to resolve issues identified during the audit, or to obtain appropriate evidence to support balances or disclosures in the financial statements. There were also delays in receiving the signed certification from the agency, required before we can issue an audit opinion.

We reviewed the conduct of early close procedures at 17 agencies. Fifteen of these agencies were assessed as not fully addressing mandatory early close procedures.
Recommendation: Timeliness of financial reporting should be improved through better oversight of the preparation of financial statements, prompt resolution of issues, and an increased focus on early close procedures.
2.3 Key financial reporting issues
Information system limitations continue at TAFE NSW. TAFE NSW implemented additional processes to verify the accuracy and completeness of revenue from student fees. Conclusion: Procedures to address system limitations are costly, causing delays in financial reporting and increased resource commitments for staff, contractors and audit.
Misstatements and internal control issues continue to be identified in accounting for Crown land. The information system used to record Crown land was not designed to facilitate efficient financial reporting. These limitations and other control weaknesses impacted the completeness and accuracy of the Department's financial statements.
Recommendation: The Department should address system limitations and control weaknesses to ensure complete and accurate reporting for Crown land.
Unprocessed Aboriginal land claims continue to increase. Recommendation (repeat issue): The Department should reduce unprocessed Aboriginal land claims.
2.4 Financial information and sustainability
Cluster agencies recorded a combined surplus of $58.0 million compared to a combined deficit of $86.0 million in the previous year.

 

We identified five agencies with potential sustainability issues such as low liquidity or negative net assets. Conclusion: Adequate arrangements are in place to mitigate potential sustainability issues. These arrangements include a commitment from the Department to provide financial support if required. 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from:

  • our financial statement audits of agencies in the Industry cluster for 2018
  • the areas of focus identified in the Audit Office work program.

The Audit Office Annual Work Program provides a summary of all audits to be conducted within the proposed time period as well as detailed information on the areas of focus for each of the NSW Government clusters.

Observation Conclusions and recommendations
3.1 Internal control
Almost one in three internal control issues identified in 2017–18 were repeat issues. Recommendation (repeat issue): Recommendations to management to address internal control issues from prior years should be addressed promptly to reduce risks and improve processes.
3.2 Information technology controls
User access administration over financial systems remains an area of weakness. Two high risk and 18 moderate risk issues related to user access administration across nine agencies were identified. Recommendation (repeat issue): Agencies' controls over administration of user access to critical systems should:
  • retain documentation of approvals to create, modify and deactivate user access
  • allocate appropriate access rights
  • perform and document regular user access reviews
  • log and monitor privileged/super user account activity
  • deactivate terminated user access on a timely basis.
3.3 Annual work program
Errors continue to be identified in the Crown land database.

Instances were identified where Crown land was not recognised by the appropriate entity, or was recognised by more than one entity.
Recommendation: The Department should ensure the Crown land database is complete and accurate so state agencies and local government councils are better informed about the Crown land they control.
Approximately 700 managers of Crown land do not submit financial statements required by the Public Finance and Audit Act 1983. NSW Treasury and the Department are continuing work to clarify reporting arrangements for these entities.
3.4 Managing maintenance
Some cluster agencies do not monitor their backlog maintenance. Consequently, the total backlog maintenance in the Industry cluster is unknown. This impacts the reliability and consistency of information about assets and their condition. When backlog maintenance is unknown, it is difficult for agencies to develop an accurate and effective maintenance plan that focuses on areas of highest need. It also means agencies' maintenance plans are reactive rather than preventative.
Effective maintenance planning helps agencies to:
  • quantify and budget asset maintenance costs
  • support service delivery at the lowest possible long-term cost
  • reduce service disruptions and losses due to asset failure
  • identify and respond to risks posed by the age and condition of assets.
Recommendation: Cluster agencies should develop an asset maintenance plan and complete an assessment of the condition of their assets to identify any maintenance backlogs. 
Maintenance budgets in some cluster agencies are not set based on actual maintenance needs. Recommendation: Cluster agencies should set their maintenance budgets based on identified maintenance needs to more accurately budget and prioritise expenditure.

Agencies in the Industry cluster provide services across a wide variety of areas. This chapter outlines certain service delivery outcomes for 2017–18 for the Industry cluster. It provides important contextual information about the cluster's operation, but the data on activity levels and performance is provided by Cluster agencies. The Audit Office does not have a specific mandate to audit performance information. Accordingly, the information in this chapter is unaudited. 

In our recent performance audit, Progress and measurement of Premier's Priorities, we identified 12 limitations of performance measurement and performance data. We recommended that the Department of Premier and Cabinet ensure that processes to check and verify data are in place for all agency data sources.

Published

Actions for Members' Additional Entitlements 2017

Members' Additional Entitlements 2017

Premier and Cabinet
Compliance
Internal controls and governance
Management and administration
Regulation
Service delivery

In a report released today, the Auditor-General for New South Wales, Margaret Crawford, identified two instances where Members of Parliament did not materially comply with the Parliamentary Remuneration Tribunal’s Determination relating to additional entitlements. The Department of Parliamentary Services has subsequently requested that the two Members concerned repay amounts that were incorrectly claimed. One claim was made under the Electorate to Sydney Travel allowance and the other from the Communication allowance.

Published

Actions for Progress and measurement of the Premier's Priorities

Progress and measurement of the Premier's Priorities

Premier and Cabinet
Compliance
Internal controls and governance
Management and administration
Project management
Risk
Service delivery
Shared services and collaboration
Workforce and capability

The Premier’s Implementation Unit uses a systematic approach to measuring and reporting progress towards the Premier’s Priorities performance targets, but public reporting needed to improve, according to a report released today by the Auditor-General of NSW, Margaret Crawford.

The Premier of New South Wales has established 12 Premier’s Priorities. These are key performance targets for government.

The 12 Premier's Priorities
  • 150,000 new jobs by 2019

  • Reduce the volume of litter by 40 per cent by 2020

  • 10 key projects in metro and regional areas to be delivered on time and on budget, and nearly 90 local infrastructure projects to be delivered on time

  • Increase the proportion of NSW students in the top two NAPLAN bands by eight per cent by 2019

  • Increase the proportion of women in senior leadership roles in the NSW Government sector from 33 to 50 per cent by 2025 and double the number of Aboriginal and Torres Strait Islander people in senior leadership roles in the NSW Government sector, from 57 to 114

  • Increase the proportion of young people who successfully move from Specialist Homelessness Services to long-term accommodation to more than 34 per cent by 2019

  • 61,000 housing completions on average per year to 2021

  • Reduce the proportion of domestic violence perpetrators reoffending by 25 per cent by 2021

  • Improve customer satisfaction with key government services every year, this term of government to 2019

  • Decrease the percentage of children and young people re-reported at risk of significant harm by 15 per cent by 2020

  • 81 per cent of patients through emergency departments within four hours by 2019

  • Reduce overweight and obesity rates of children by five percentage points by 2025


Source: Department of Premier and Cabinet, Premier’s Priorities website.

Each Premier’s Priority has a lead agency and minister responsible for achieving the performance target.

The Premier’s Implementation Unit (PIU) was established within the Department of Premier and Cabinet (DPC) in 2015. The PIU is a delivery unit that supports agencies to measure and monitor performance, make progress toward the Premier’s Priorities targets, and report progress to the Premier, key ministers and the public.

This audit assessed how effectively the NSW Government is progressing and reporting on the Premier's Priorities.

 


The Premier’s Implementation Unit (PIU) is effective in assisting agencies to make progress against the Premier’s Priorities targets. Progress reporting is regular but transparency to the public is weakened by the lack of information about specific measurement limitations and lack of clarity about the relationship of the targets to broader government objectives.The PIU promotes a systematic approach to measuring performance and reporting progress towards the Premier’s Priorities’ performance targets. Public reporting would be improved with additional information about the rationale for choosing specific targets to report on broader government objectives.

The PIU provides a systematic approach to measuring performance and reporting progress towards the Premier's Priorities performance targets. Public reporting would be improved with additional information about the rationale for choosing specific targets to report on broader government objectives. The data used to measure the Premier’s Priorities comes from a variety of government and external datasets, some of which have known limitations. These limitations are not revealed in public reporting, and only some are revealed in progress reported to the Premier and ministers. This limits the transparency of reporting.

The PIU assists agencies to avoid unintended outcomes that can arise from prioritising particular performance measures over other areas of activity. The PIU has adopted a collaborative approach to assisting agencies to analyse performance using data, and helping them work across organisational silos to achieve the Premier’s Priorities targets.


 


Data used to measure progress for some of the Premier’s Priorities has limitations which are not made clear when progress is reported. This reduces transparency about the reported progress. Public reporting would also be improved with additional information about the relationship between specific performance measures and broader government objectives.

The PIU is responsible for reporting progress to the Premier, key ministers and the public. Agencies provide performance data and some play a role in preparing progress reports for the Premier and ministers. For 11 of the Premier's Priorities, progress is reported against measurable and time-related performance targets. For the infrastructure priority, progress is reported against project milestones.

Progress of some Priorities is measured using data that has known limitations, which should be noted wherever progress is reported. For example, the data used to report on housing completions does not take housing demolitions into account, and is therefore overstating the contribution of this performance measure to housing supply. This known limitation is not explained in progress reports or on the public website.

Data used to measure progress is sourced from a mix of government and external datasets. Updated progress data for most Premier’s Priorities is published on the Premier’s Priorities website annually, although reported to the Premier and key ministers more frequently. The PIU reviews the data and validates it through fieldwork with front line agencies. The PIU also assists agencies to avoid unintended outcomes that can arise from prioritising single performance measures. Most, but not all, agencies use additional indicators to check for misuse of data or perverse outcomes.

We examined the reporting processes and controls for five of the Premier’s Priorities. We found that there is insufficient assurance over the accuracy of the data on housing approvals.

The relationships between performance measures and broader government objectives is not always clearly explained on the Premier’s Priority website, which is the key source of public information about the Premier’s Priorities. For example, the Premier’s Priority to reduce litter volumes is communicated as “Keeping our Environment Clean.” While the website explains why reducing litter is important, it does not clearly explain why that particular target has been chosen to measure progress in keeping the environment clean.

By December 2018, the Department of Premier and Cabinet should:

  1. improve transparency of public reporting by:
    • providing information about limitations of reported data and associated performance
    • clarifying the relationship between the Premier’s Priorities performance targets and broader government objectives.
  2. ensure that processes to check and verify data are in place for all agency data sources
  3. encourage agencies to develop and implement additional supporting indicators for all Premier’s Priority performance measures to prevent and detect unintended consequences or misuse of data.

 


The Premier's Implementation Unit is effective in supporting agencies to deliver progress towards the Premier’s Priority targets.

The PIU promotes a systematic approach to monitoring and reporting progress against a target, based on a methodology used in delivery units elsewhere in the world. The PIU undertakes internal self-evaluation, and commissions regular reviews of methodology implementation from the consultancy that owns the methodology and helped to establish the PIU. However, the unit lacks periodic independent reviews of their overall effectiveness. The PIU has adopted a collaborative approach and assists agencies to analyse performance using data, and work across organisational silos to achieve the Premier’s Priorities targets.

Agency representatives recognise the benefits of being responsible for a Premier's Priority and speak of the value of being held to account and having the attention of the Premier and senior ministers.

By June 2019, the Department of Premier and Cabinet should:

  1. establish routine collection of feedback about PIU performance including:
    • independent assurance of PIU performance
    • opportunity for agencies to provide confidential feedback.

 

 

Published

Actions for Matching skills training with market needs

Matching skills training with market needs

Industry
Compliance
Internal controls and governance
Management and administration
Risk
Service delivery
Workforce and capability

The NSW Department of Industry targets subsidies towards training programs delivering skills most needed in New South Wales. However, the Department still provides subsidies to qualifications that the market may no longer need, according to a report released by Margaret Crawford, Auditor-General for New South Wales. 

In 2012, governments across Australia entered into the National Partnership Agreement on Skills Reform. Under the National Partnership Agreement, the Australian Government provided incentive payments to States and Territories to move towards a more contestable Vocational Education and Training (VET) market. The aim of the National Partnership Agreement was to foster a more accessible, transparent, efficient and high quality training sector that is responsive to the needs of students and industry. 

The New South Wales Government introduced the Smart and Skilled program in response to the National Partnership Agreement. Through Smart and Skilled, students can choose a vocational course from a list of approved qualifications and training providers. Students pay the same fee for their chosen qualification regardless of the selected training provider and the government covers the gap between the student fee and the fixed price of the qualification through a subsidy paid to their training provider. 

Smart and Skilled commenced in January 2015, with the then Department of Education and Communities having primary responsibility for its implementation. Since July 2015, the NSW Department of Industry (the Department) has been responsible for VET in New South Wales and the implementation of Smart and Skilled. 

The NSW Skills Board, comprising nine part-time members appointed by the Minister for Skills, provides independent strategic advice on VET reform and funding. In line with most other States and Territories, the Department maintains a 'Skills List' which contains government subsidised qualifications to address identified priority skill needs in New South Wales.

This audit assessed the effectiveness of the Department in identifying, prioritising, and aligning course subsidies to the skill needs of NSW. To do this we examined whether:

  • the Department effectively identifies and prioritises present and future skill needs 
  • Smart and Skilled funding is aligned with the priority skill areas
  • skill needs and available VET courses are effectively communicated to potential participants and training providers.

Smart and Skilled is a relatively new and complex program, and is being delivered in the context of significant reform to VET nationally and in New South Wales. A large scale government funded contestable market was not present in the VET sector in New South Wales before the introduction of Smart and Skilled. This audit's findings should be considered in that context.
 

Conclusion
The Department effectively consults with industry, training providers and government departments to identify skill needs, and targets subsidies to meet those needs. However, the Department does not have a robust, data driven process to remove subsidies from qualifications which are no longer a priority. There is a risk that some qualifications are being subsidised which do not reflect the skill needs of New South Wales. 
The Department needs to better use the data it has, and collect additional data, to support its analysis of priority skill needs in New South Wales, and direct funding accordingly.
In addition to subsidising priority qualifications, the Department promotes engagement in skills training by:
  • funding scholarships and support for disadvantaged students
  • funding training in regional and remote areas
  • providing additional support to deliver some qualifications that the market is not providing.

The Department needs to evaluate these funding strategies to ensure they are achieving their goals. It should also explore why training providers are not delivering some priority qualifications through Smart and Skilled.

Training providers compete for funding allocations based on their capacity to deliver. The Department successfully manages the budget by capping funding allocated to each Smart and Skilled training provider. However, training providers have only one year of funding certainty at present. Training providers that are performing well are not rewarded with greater certainty.

The Department needs to improve its communication with prospective students to ensure they can make informed decisions in the VET market.

The Department also needs to communicate more transparently to training providers about its funding allocations and decisions about changes to the NSW Skills List. 

The NSW Skills List is unlikely to be missing high priority qualifications, but may include lower priority qualifications because the Department does not have a robust process to identify and remove these qualifications from the list. The Department needs to better use available data, and collect further data, to support decisions about which qualifications should be on the NSW Skills List.

The Department relies on stakeholder proposals to update the NSW Skills List. Stakeholders include industry, training providers and government departments. These stakeholders, particularly industry, are likely to be aware of skill needs, and have a strong incentive to propose qualifications that address these needs. The Department’s process of collecting stakeholder proposals helps to ensure that it can identify qualifications needed to address material skill needs. 

It is also important that the Department ensures the NSW Skills List only includes priority qualifications that need to be subsidised by government. The Department does not have robust processes in place to remove qualifications from the NSW Skills List. As a result, there is a risk that the list may include lower priority skill areas. Since the NSW Skills List was first created, new additions to the list have outnumbered those removed by five to one.

The Department does not always validate information gathered from stakeholder proposals, even when it has data to do so. Further, its decision making about what to include on, or delete from, the NSW Skills List is not transparent because the rationale for decisions is not adequately documented. 

The Department is undertaking projects to better use data to support its decisions about what should be on the NSW Skills List. Some of these projects should deliver useful data soon, but some can only provide useful information when sufficient trend data is available. 

Recommendation

The Department should: 

  • by June 2019, increase transparency of decisions about proposed changes to the NSW Skills List and improve record-keeping of deliberations regarding these changes
  • by December 2019, use data more effectively and consistently to ensure that the NSW Skills List only includes high priority qualifications
The Department funds training providers that deliver qualifications on the NSW Skills List. Alignment of funding to skill needs relies on the accuracy of the NSW Skills List, which may include some lower priority qualifications.

Only qualifications on the NSW Skills List are eligible for subsidies under Smart and Skilled. As the Department does not have a robust process for removing low priority qualifications from the NSW Skills list, some low priority qualifications may be subsidised. 

The Department allocates the Smart and Skilled budget through contracts with Smart and Skilled training providers. Training providers that meet contractual obligations and perform well in terms of enrolments and completion rates are rewarded with renewed contracts and more funding for increased enrolments, but these decisions are not based on student outcomes. The Department reduces or removes funding from training providers that do not meet quality standards, breach contract conditions or that are unable to spend their allocated funding effectively. Contracts are for only one year, offering training providers little funding certainty. 

Smart and Skilled provides additional funding for scholarships and for training providers in locations where the cost of delivery is high or to those that cater to students with disabilities. The Department has not yet evaluated whether this additional funding is achieving its intended outcomes. 

Eight per cent of the qualifications that have been on the NSW Skills List since 2015 are not delivered under Smart and Skilled anywhere in New South Wales. A further 14 per cent of the qualifications that are offered by training providers have had no student commencements. The Department is yet to identify the reasons that these high priority qualifications are either not offered or not taken up by students.

Recommendation

The Department should:

  • by June 2019, investigate why training providers do not offer, and prospective students do not enrol in, some Smart and Skilled subsidised qualifications 
  • by December 2019, evaluate the effectiveness of Smart and Skilled funding which supplements standard subsidies for qualifications on the NSW Skills List, to determine whether it is achieving its objectives
  • by December 2019, provide longer term funding certainty to high performing training providers, while retaining incentives for them to continue to perform well.
The Department needs to improve its communication, particularly with prospective students.

In a contestable market, it is important for consumers to have sufficient information to make informed decisions. The Department does not provide some key information to prospective VET students to support their decisions, such as measures of provider quality and examples of employment and further education outcomes of students completing particular courses. Existing information is spread across numerous channels and is not presented in a user friendly manner. This is a potential barrier to participation in VET for those less engaged with the system or less ICT literate.

The Department conveys relevant information about the program to training providers through its websites and its regional offices. However, it could better communicate some specific information directly to individual Smart and Skilled training providers, such as reasons their proposals to include new qualifications on the NSW Skills List are accepted or rejected. 

While the Department is implementing a communication strategy for VET in New South Wales, it does not have a specific communications strategy for Smart and Skilled which comprehensively identifies the needs of different stakeholders and how these can be addressed. 

Recommendation

By December 2019, the Department should develop and implement a specific communications strategy for Smart and Skilled to:

  • support prospective student engagement and informed decision making
  • meet the information needs of training providers 

Appendix one - Response from agency

Appendix two - About the audit

Appendix three - Performance auditing

 

Parliamentary reference - Report number #305 - released 26 July 2018

Published

Actions for Implementation of the NSW Government’s program evaluation initiative

Implementation of the NSW Government’s program evaluation initiative

Industry
Justice
Planning
Premier and Cabinet
Treasury
Environment
Financial reporting
Internal controls and governance
Management and administration
Risk
Service delivery
Shared services and collaboration
Workforce and capability

The NSW Government’s ‘program evaluation initiative’, introduced to assess whether service delivery programs achieve expected outcomes and value for money, is largely ineffective according to a report released today by NSW Auditor-General, Margaret Crawford.

Government services, in areas such as public order and safety, health and education, are delivered by agencies through a variety of programs. In 2016–17, the NSW Government estimates that it will spend over $73 billion on programs to deliver services.

 

Parliamentary reference - Report number #277 - released 3 November 2016

Published

Actions for Red tape reduction

Red tape reduction

Premier and Cabinet
Finance
Financial reporting
Internal controls and governance
Management and administration
Project management
Regulation
Shared services and collaboration

Overall, NSW Government initiatives and processes to prevent and reduce red tape were not effective, according to a report released today by the NSW Auditor-General.

In 2015, the Government reported that its red tape reduction initiatives, implemented between 2011 and 2015, had resulted in $896 million in savings. While these initiatives resulted in some savings, the total value of savings is unknown because estimates for some initiatives were based on unverified assumptions, cost transfers or unrealised projections.

 

Parliamentary reference - Report number #272 - released 25 August 2016