Actions for Code Red: Hospital Emergency Departments

Code Red: Hospital Emergency Departments

Health
Service delivery
Shared services and collaboration

All three hospitals followed the Department of Health’s guidelines for judging capacity and had systems in place to notify hospital staff and ambulance crews of changes in status. We found discrepancies in the records kept by all three hospitals when compared to the records maintained by the Department of Health. Our view however, is that these records do not need to be a perfect match for the intended purpose, which is to guide ambulance crews to the sh

Published

Actions for Waiting Times for Elective Surgery in Public Hospitals

Waiting Times for Elective Surgery in Public Hospitals

Health
Information technology
Internal controls and governance
Management and administration
Service delivery

We recognise that managing waiting times is a difficult and complex task. Waiting times are influenced by many factors, some of which are outside the control of NSW Health. There are, however, steps which NSW Health could, and should, take to ensure that the processes to manage waiting times are efficient and effective. By all measures used by NSW Health, patients are waiting longer for elective treatment today than six or seven years ago. In March 2003

Published

Actions for Dealing with Unlicensed and Unregistered Driving

Dealing with Unlicensed and Unregistered Driving

Justice
Transport
Information technology
Regulation
Shared services and collaboration

In our opinion there are inadequacies in the current arrangements for detecting unauthorised driving. For example better information is needed on the extent of unlicensed driving. This may require giving the NSW Police power to conduct random licence and registration checks. In addition, there are technological and legal constraints to the efficient and effective detection of unauthorised driving.   Parliamentary reference - Report number #115&nbs

Published

Actions for The Millennium Train Project

The Millennium Train Project

Transport
Infrastructure
Procurement
Project management
Service delivery

State Rail has made significant improvements since the purchase of the Tangara. It improved measures necessary for handling contracts dealing with technically complex and innovative projects, although some other problems have been encountered, with new lessons to learn. The design and manufacture of new trains requires a significant investment in both time and cost. The Millennium Train has come at a considerably higher price than originally expected. An

Published

Actions for Delivering Services Online

Delivering Services Online

Transport
Information technology
Internal controls and governance
Service delivery
Shared services and collaboration

A staged, systematic and careful approach and extensive business re-engineering effort underpinned the Roads and Traffic Authority's (RTA) steady progress in providing customers with a range of reliable and secure online registration services. The RTA’s consistent and disciplined pursuit of new and challenging e-business opportunities is commendable.   Parliamentary reference - Report number #111 - released 11 June 2003

Published

Actions for Implementing the Ovine Johne's Disease Program

Implementing the Ovine Johne's Disease Program

Industry
Internal controls and governance
Regulation
Service delivery
Shared services and collaboration

The implementation of the Ovine Johne's Disease (OJD) program in New South Wales has been prolonged and difficult. In our view, the OJD Program in New South Wales has experienced two major difficulties with its implementation: the lack of a strategic approach to program management, and an ill-defined governance structure. Both the NSW Government and industry need to be better organised and improve the planning, direction and co-ordination of th

Published

Actions for CityRail Passenger Security

CityRail Passenger Security

Transport
Service delivery
Shared services and collaboration

StateRail has invested significantly over the last five years in passenger safety and security. Security guards on trains from 7.00 pm were introduced in 1998. More recently, additional lighting, 5,700 closed circuit television cameras (CCTV) and emergency help points have been installed on CityRail stations. In addition, CityRail has employed some 100 transit officers to patrol its network and intends to employ another 200 transit officers in 2003. Whil