Actions for Handback of the M4 Tollway

Handback of the M4 Tollway

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management

This audit focuses on the M4 handback. It looks at whether the road will be in good condition when the State gets it back, and whether it will cope with the extra traffic after the toll is removed. These are critical issues for taxpayers and motorists. Taxpayers don’t want to be responsible for a large repair bill and motorists don’t want to be stuck in traffic jams.

To ensure that future private sector partnerships (PPP) deal adequately with handback, we recommend that the Roads and Traffic Authority (RTA):

  • ensure deeds spell out an appropriate inspection and testing program to determine repairs required to bring roads up to a satisfactory condition at handback (p.11)
  • ensure deeds link condition standards and maintenance approaches to changing industry standards and approaches over the life of the PPP (p.11)
  • consider including in deeds a requirement that operators provide a performance bond or similar security over the cost of handback repairs (p.11)
  • review the lessons learnt from the M4 tollway handback and determine whether it should seek to negotiate changes to existing tollway deeds to better deal with handback, by June 2010 (p.11)

 

Parliamentary reference - Report number #193 - released 27 October 2009

Published

Actions for Administering Domestic Waterfront Tenancies

Administering Domestic Waterfront Tenancies

Planning
Transport
Management and administration
Service delivery
Shared services and collaboration

The audit’s overall conclusion is that Lands and Maritime are broadly achieving outcomes consistent with the IPART report on administering domestic waterfront tenancies. But a lack of collaboration between the agencies is contributing to poor customer service. Inconsistencies with the IPART report recommendations and operational differences between the two agencies result in different rents and conditions for tenants in the two agencies. The differences are having a significant impact on customer service.

 

Parliamentary reference - Report number #191 - released 23 September 2009

Published

Actions for Tackling Cancer with Radiotherapy

Tackling Cancer with Radiotherapy

Health
Internal controls and governance
Management and administration
Procurement
Service delivery
Workforce and capability

Overall radiotherapy services are managed in a reasonably efficient and effective manner. Much is being done to further improve efficiency and effectiveness, and more can be done. While New South Wales has a number of well-established radiotherapy treatment centres, the high capital cost limits their availability in all hospitals. Some patients need to travel long distances and be away from their homes for up to seven weeks. The projected growth in demand for radiotherapy services will further challenge NSW Health and it needs to more clearly demonstrate how it will have the right facilities in the right place at the right time.

 

Parliamentary reference - Report number #188 - released 23 June 2009

Published

Actions for Grants Administration

Grants Administration

Premier and Cabinet
Treasury
Health
Community Services
Planning
Compliance
Internal controls and governance
Management and administration
Procurement
Risk

We found no significant difference in the funding of government and opposition electorates. However, more money was given to electorates that were safely held by the major parties. These seats received $1.29 for every dollar given to marginal and independent seats with government marginals getting the least. Electorates also receive different levels of funding according to which region they are in. Such variations may reflect valid agency objectives such as meeting State Plan targets or addressing socio-economic disadvantage.

But while agencies publish who gets what, they do not adequately evaluate or explain what grant programs have achieved. As a result, there is a risk that New South Wales may not get the best value for its spending. We recommend that agencies regularly evaluate their grant programs and publish the results.

 

Parliamentary reference - Report number #186 - released 6 May 2009

Published

Actions for Signal failures on the metropolitan rail network

Signal failures on the metropolitan rail network

Transport
Information technology
Infrastructure
Internal controls and governance
Project management
Risk
Service delivery

Between 2004 and 2006, the number of signalling failures, signalling downtime and the number of trains delayed as a result of signal failures all fell. RailCorp’s on-time running performance improved over the same period. The fall in failures is a clear indication of improved performance. Changes in the definition of on-time and to the timetable during 2005 and 2006 however make it difficult to determine whether improvements in response downtime and signalling delays are due to a true performance improvement. To build upon this strong base, RailCorp needs to determine with more confidence the number and duration of signalling failures the network can tolerate without impacting on service levels.

 

Parliamentary reference - Report number #170 - released 15 August 2007

Published

Actions for Connecting with public transport

Connecting with public transport

Transport
Information technology
Infrastructure
Internal controls and governance
Management and administration
Project management
Service delivery
Workforce and capability

We see considerable potential for the Ministry of Transport to plan and manage interchanges more effectively, so as to make better use of our public transport network. We believe that the Ministry now needs to focus more on multi-modal transport planning and interchange performance. It needs to assign responsibility for the coordination and oversight of inter-modal operations to an entity resourced for the purpose. Without this it will continue to be very difficult to identify and address unmet needs, seek and secure stakeholder funding, and monitor and evaluate system performance.

 

Parliamentary reference - Report number #168 - released 6 June 2007

Published

Actions for Readiness to respond: Follow-up audit

Readiness to respond: Follow-up audit

Health
Information technology
Internal controls and governance
Management and administration
Service delivery
Shared services and collaboration
Workforce and capability

The Ambulance Service of New South Wales has substantially implemented the 28 recommendations of the 2001 audit report that it accepted. It has also introduced significant new initiatives to improve performance that were not part of the 2001 recommendations. It has made substantial changes to its organisation and operations to implement these changes. Many of the changes are still proceeding. The Service has addressed a key finding of the 2001 audit report - that it did not have adequate, relevant or credible management data for decision making. The Service now has five years of operational data from the Computer Aided Dispatch (CAD) system.

 

Parliamentary reference - Report number #167 - released 6 June 2007

Published

Actions for Responding to homelessness

Responding to homelessness

Health
Community Services
Internal controls and governance
Management and administration
Project management
Service delivery
Shared services and collaboration

Many projects, both Partnership Against Homelessness and by individual agencies, have shown good results or led to improvements. One example is helping mental health patients maintain stable housing. Another is providing street outreach services to homeless people in inner Sydney. Despite these efforts, we were unable to determine how well the government is responding to homelessness statewide. This is because there are no statewide performance measures or targets on homelessness. Also there is limited benchmarking, and no formal means of spreading information on homelessness initiatives and projects.

 

Parliamentary reference - Report number #165 - released 2 May 2007

Published

Actions for Review of Eastern Distributor

Review of Eastern Distributor

Transport
Infrastructure
Procurement
Project management

Following a resolution of the Legislative Council, the Audit Office has undertaken a performance audit of the Eastern Distributor. For a number of reasons, The Audit Office is not in the position to determine “whether the proposed toll and concession period represents the best deal”. In part this is the result of time constraints which do not allow a careful analysis of many toll and concession options. Similarly, the audit does not answer “whether the current proposal represents the best environmental outcome”. But each of these issues (toll and concession and environmental consequences) is discussed in the audit report.

The Audit Office recommends that the Roads and Traffic Authority (RTA), for any further major project of this type, ensures that it establishes a process which allows all decision makers to have a thorough understanding of the reasonableness of the proponents’ offers and their implications for the State and for the public. The Audit Office also recommends that the RTA should at the outset consult with TCorp in respect of each major project put to tender.

 

Parliamentary reference - Report number #42 - released 31 July 1997

Published

Actions for Immunisation in NSW

Immunisation in NSW

Health
Service delivery
Shared services and collaboration

Improving immunisation levels has been a policy priority for NSW and Commonwealth governments since the early 1990s. Along with other States they are pursuing a range of initiatives aimed at reaching immunisation target levels above 95% by the year 2000. At such levels, the occurrence of vaccine preventable diseases is minimised and their spread prevented.

There is considerable support for this policy from the public, the medical profession and all levels of government. However, like much in public health, it depends for its success on effective cooperation between many participants, both nationally and locally, with competing demands on their time and resources.

 