Actions for Signal failures on the metropolitan rail network

Signal failures on the metropolitan rail network

Transport
Information technology
Infrastructure
Internal controls and governance
Project management
Risk
Service delivery

Between 2004 and 2006, the number of signalling failures, signalling downtime and the number of trains delayed as a result of signal failures all fell. RailCorp’s on-time running performance improved over the same period. The fall in failures is a clear indication of improved performance. Changes in the definition of on-time and to the timetable during 2005 and 2006 however make it difficult to determine whether improvements in response downtime and signalling delays are due to a true performance improvement. To build upon this strong base, RailCorp needs to determine with more confidence the number and duration of signalling failures the network can tolerate without impacting on service levels.

 

Parliamentary reference - Report number #170 - released 15 August 2007

Published

Actions for Connecting with public transport

Connecting with public transport

Transport
Information technology
Infrastructure
Internal controls and governance
Management and administration
Project management
Service delivery
Workforce and capability

We see considerable potential for the Ministry of Transport to plan and manage interchanges more effectively, so as to make better use of our public transport network. We believe that the Ministry now needs to focus more on multi-modal transport planning and interchange performance. It needs to assign responsibility for the coordination and oversight of inter-modal operations to an entity resourced for the purpose. Without this it will continue to be very difficult to identify and address unmet needs, seek and secure stakeholder funding, and monitor and evaluate system performance.

 

Parliamentary reference - Report number #168 - released 6 June 2007

Published

Actions for Readiness to respond: Follow-up audit

Readiness to respond: Follow-up audit

Health
Information technology
Internal controls and governance
Management and administration
Service delivery
Shared services and collaboration
Workforce and capability

The Ambulance Service of New South Wales has substantially implemented the 28 recommendations of the 2001 audit report that it accepted. It has also introduced significant new initiatives to improve performance that were not part of the 2001 recommendations. It has made substantial changes to its organisation and operations to implement these changes. Many of the changes are still proceeding. The Service has addressed a key finding of the 2001 audit report - that it did not have adequate, relevant or credible management data for decision making. The Service now has five years of operational data from the Computer Aided Dispatch (CAD) system.

 

Parliamentary reference - Report number #167 - released 6 June 2007

Published

Actions for Responding to homelessness

Responding to homelessness

Health
Community Services
Internal controls and governance
Management and administration
Project management
Service delivery
Shared services and collaboration

Many projects, both Partnership Against Homelessness and by individual agencies, have shown good results or led to improvements. One example is helping mental health patients maintain stable housing. Another is providing street outreach services to homeless people in inner Sydney. Despite these efforts, we were unable to determine how well the government is responding to homelessness statewide. This is because there are no statewide performance measures or targets on homelessness. Also there is limited benchmarking, and no formal means of spreading information on homelessness initiatives and projects.

 

Parliamentary reference - Report number #165 - released 2 May 2007

Published

Actions for Management of research - NSW Health: Infrastructure Grants Program

Management of research - NSW Health: Infrastructure Grants Program

Health
Internal controls and governance
Management and administration
Shared services and collaboration

NSW Health has progressed in identifying and addressing key R&D issues in a complex and difficult environment. The Infrastructure Grants Program (IGP) is an innovative program and reflects a commitment by Government to support research infrastructure. The IGP has as its aims the provision of significant funding accompanied by clear research objectives and criteria for accountability and introduces a rational basis for the allocation of infrastructure grants.

While NSW Health has progressed, there is an opportunity to make the IGP more efficient and effective. These opportunities are in the areas of addressing longer term planning issues in health, streamlining and clarifying eligibility and selection criteria, improving decision-making structures and processes and improving accountability.

 

Parliamentary reference - Report number #56 - released 25 November 1998

Published

Actions for On board: Guide to better practice for Public Sector governing and advisory boards

On board: Guide to better practice for Public Sector governing and advisory boards

Whole of Government
Internal controls and governance

In most organisations with a board or committee, there was confusion about the respective roles, powers, responsibilities and accountabilities of the Minister/s, the board and the Chief Executive Officer (CEO). There are a wide variety of governance arrangements in operation across the spectrum of boards and committees. This is partly due to differing arrangements set out in relevant legislation and gaps in legislative detail which have been addressed in a variety of ways.

Under current arrangements, governing boards of SOCs have accountabilities to Shareholding Ministers and Portfolio Ministers, as well as to Ministers who are responsible for industry-wide regulation. Non-corporatised Government businesses have different accountability and control arrangements. The large number of statutory and nonstatutory bodies and authorities have a wide array of governance arrangements. As a result of uncertainty and confusion on governance aspects, The Audit Office observed that many governing boards operate as high level advisory management committees. The audit also found that board and committee practices fell short of standards expected in a professional boardroom culture.

 