Actions for The Cross City Tunnel Project

The Cross City Tunnel Project

Transport
Treasury
Premier and Cabinet
Planning
Environment
Infrastructure
Management and administration
Procurement
Project management
Risk

In our opinion the Government’s ‘no net cost to government’ requirement was a legitimate (but not the only possible) basis for the tunnel bid process. The Government was entitled to decide that tunnel users meet the tunnel costs. Structuring the bid process on the basis of an upfront reimbursement of costs incurred (or to be incurred) by the Roads and Traffic Authority (RTA) was therefore appropriate.

In our opinion, however, the Government, Treasury and the RTA did not sufficiently consider the implications of an upfront payment involving more than simple project cost reimbursement (i.e. the ‘Business Consideration Fee’ component). In addition, the RTA was wrong to change the toll escalation factor late in 2002 to compensate the tunnel operator, Cross City Motorway Pty Ltd, for additional costs.

 

Parliamentary reference - Report number #152 - released 31 May 2006

Published

Actions for Fare evasion on public transport: Follow-up audit

Fare evasion on public transport: Follow-up audit

Transport
Finance
Management and administration

The overall level of fare evasion is now lower, and the revenue forgone much less, than in 2000. The estimation of fare evasion, detection of fare evasion and management of fare compliance by RailCorp, State Transit and Sydney Ferries has improved, although Sydney Ferries needs to improve further.

However, only one in four fines for fare evasion are paid within 12 months. This is worse than in 2000. And the number of frequent fare evaders has almost trebled. State Debt Recovery Office and the transport agencies need to develop new and improved strategies to reduce the level of fine default and to better manage frequent fare evaders.

 

Parliamentary reference - Report number #150 - released 26 April 2006

Published

Actions for Review of Walsh Bay

Review of Walsh Bay

Finance
Infrastructure
Management and administration
Procurement
Project management

The decision to seek development of Walsh Bay without a Master Plan and/or detailed study as to the state of the precinct presented significant problems throughout the life of the project. Now, four years later, negotiations still continue on the details of the final scheme. Based on the latest estimates, it will not provide a financial return as was originally expected. The audit found no evidence to indicate why the former Government wished to expedite Walsh Bay, but it is aware that there was an election due. Many of the problems which have been encountered could have been avoided with more careful and more extensive consideration at the start, particularly in the light of Property Services Group's recommendations.

 

Parliamentary reference - Report number #58 - released 17 December 1998