Reports
Actions for WestConnex: Assurance to the Government
WestConnex: Assurance to the Government
This audit assesses the assurance provided to the NSW Government for the initial stages of the WestConnex project.
The audit examined the WestConnex project from concept development to the pre-tender phase for Stage 1A – M4 (Parramatta to Homebush Bay). It did not examine the merit of the project or whether it represented value-for-money.
This audit found a number of shortcomings with the governance of the WestConnex project during its early stages and makes recommendations on how to better govern the remainder of the project to minimise the risk of failure.
Parliamentary reference - Report number #247 - released 18 December 2014
Actions for Regional Road Funding - Block Grant and REPAIR Programs
Regional Road Funding - Block Grant and REPAIR Programs
In 2013–14, Roads and Maritime Services (RMS) provided over $170 million to local councils through the Block Grant and REPAIR programs to spend on Regional Roads. Regional Roads are the link between State Roads and Local Roads.
Parliamentary reference - Report number #241 - released 8 May 2014
Actions for Follow-up audits: Police response to calls for assistance, The levying and collection of Land Tax and Coordination of bushfire fighting activities
Follow-up audits: Police response to calls for assistance, The levying and collection of Land Tax and Coordination of bushfire fighting activities
The acceptance of audit recommendations by agencies in the current review was high and represented 96 per cent of the recommendations made. In addition, half of the recommendations in the 1998 audits have been adequately addressed and for over 70 per cent of recommendations there has been some measurable change in practices or performance.
But overall, most of these improvements have been incremental. And, for nearly one third of the recommendations, changes have not yet taken effect and there is a risk that the issue or problem contained in the original reports may persist. There is also a danger that current reporting arrangements may not provide Parliament sufficient assurance as to the extent accepted recommendations have been implemented and improvements have been achieved.
To provide greater transparency and accountability, agencies, following a performance audit, should establish arrangements, such as an audit committee, to follow up on the progress of implementation of the recommendations and report on the progress of the implementation of recommendations in their annual report to Parliament.
Parliamentary reference - Report number #84 - released 21 June 2001