Reports
Actions for Volume Twelve 2015 Part One Trade & Investment and TAFE
Volume Twelve 2015 Part One Trade & Investment and TAFE
Serious system limitations prevented TAFE NSW from providing sufficient and appropriate evidence to support recorded student revenue of $477 million, student receivables and accrued income of $47.6 million and unearned revenue of $398 million.
These limitations resulted in:
- a qualified audit opinion being issued for TAFE NSW;
- delays in enrolling students;
- inability to fully reconcile cash balances;
- difficulties in reconciling student enrolments with revenues recorded in the financial statements;
- large volumes of manual processing.
Actions for Volume Twelve 2015 Part Two Water
Volume Twelve 2015 Part Two Water
The distributions to the NSW Government increased from $690 million in 2013-14 to $1.0 billion in 2014-15. The increase was largely due to a higher dividend from Sydney Water Corporation.
Actions for Volume Four 2015 Treasury and State Finances
Volume Four 2015 Treasury and State Finances
For the third consecutive year, the General Government and Total State Sector Accounts received an unqualified auditor’s opinion following more than a decade of qualifications.
Errors in agencies’ financial statements and the Total State Sector Accounts were corrected as necessary to ensure compliance with Australian Accounting Standards and the requirements of the Public Finance and Audit Act 1983.
Improvements to year-end financial reporting processes have enabled the Audit Office to issue 229 audit opinions by 2 October 2015, compared to only 67 by the same time in 2011.
Actions for Large construction projects
Large construction projects
The independent assurance given to the NSW Government and sponsor agencies on the viability of large capital projects throughout their lifecycle is inadequate. Government policy is regularly not followed and not properly communicated to those responsible for implementing such policy.
This audit sought to test the effectiveness of the NSW capital project assurance system - which includes gateway reviews and reporting - but significant levels of non-compliance identified in our case studies prevented this. The NSW Commission of Audit also identified this issue in 2012. Gateway reviews are conducted by independent reviewers at key stages of a project’s life cycle and provide an independent assessment on a project’s readiness to proceed to the next stage.
Parliamentary reference - Report number #252 - released 7 May 2015
Actions for Areas of focus from 2014
Areas of focus from 2014