Actions for Effectiveness of SafeWork NSW in exercising its compliance functions

Effectiveness of SafeWork NSW in exercising its compliance functions

Finance
Industry
Health
Compliance
Internal controls and governance
Management and administration
Procurement
Project management
Regulation
Risk

What this report is about 

This report assesses how effectively SafeWork NSW, a part of the Department of Customer Service (DCS), has performed its regulatory compliance functions for work health and safety in New South Wales. 

The report includes a case study examining SafeWork NSW's management of a project to develop a realtime monitoring device for airborne silica in workplaces. 

Findings 

There is limited transparency about SafeWork NSW's effectiveness as a regulator. The limited performance information that is available is either subsumed within DCS reporting (or other sources) and is focused on activity, not outcomes. 

As a work health and safety (WHS) regulator, SafeWork NSW lacks an effective strategic and data-driven approach to respond to emerging WHS risks. 

It was slow to respond to the risk of respirable crystalline silica in manufactured stone. 

SafeWork NSW is constrained by an information management system that is over 20 years old and has passed its effective useful life. 

While it has invested effort into ensuring consistent regulatory decisions, SafeWork NSW needs to maintain a focus on this objective, including by ensuring that there is a comprehensive approach to quality assurance. 

SafeWork NSW's engagement of a commercial partner to develop a real-time silica monitoring device did not comply with key procurement obligations. 

There was ineffective governance and process to address important concerns about the accuracy of the real-time silica monitoring device. 

As such, SafeWork NSW did not adequately manage potential WHS risks. 

Recommendations 

The report recommended that DCS should: 

  • ensure there is an independent investigation into the procurement of the research partner for the real-time silica detector 
  • embed a formal process to review and set its annual regulatory priorities 
  • publish a consolidated performance report 
  • set long-term priorities, including for workforce planning and technology uplift 
  • improve its use of data, and start work to replace its existing complaints handling system 
  • review its risk culture and its risk management framework 
  • review the quality assurance measures that support consistent regulatory decisions

 

Read the PDF report.

Parliamentary reference - Report number #390 - released 27 February 2024
 

Published

Actions for Driver vehicle system

Driver vehicle system

Transport
Finance
Cyber security
Information technology
Internal controls and governance
Project management
Service delivery

What this report is about

Transport for NSW (TfNSW) uses the Driver vehicle System (DRIVES) to support its regulatory functions. The system covers over 6.2 million driver licences and over seven million vehicle registrations.

DRIVES first went live in 1991 and has been significantly extended and updated since, though is still based around the same core system. The system is at end of life but has become an important service for Service NSW and the NSW Police Force.

DRIVES now includes some services to other parts of government and non-government entities which have little or no connection to transport. There are 141 users of DRIVES in total, including commercial insurers, national regulators, and individual citizens.

This audit assessed whether TfNSW is effectively managing DRIVES and planning to transition it to a modernised system.

Audit findings

TfNSW has not effectively planned the replacement of DRIVES.

It is now working on its third business case for a replacement system but has failed to learn lessons from its past attempts.

In the meantime, TfNSW has not taken a strategic approach to managing DRIVES’ growth.

TfNSW has been slow to reduce the risk of misuse of personal information held in DRIVES. With its delivery partner Service NSW, TfNSW has also been slow to develop and implement automatic monitoring of access.

TfNSW uses recognised processes for managing most aspects of DRIVES, but has not kept the system consistently available for users. TfNSW has lacked accurate service availability information since June 2022, when it changed its technology support provider.

TfNSW needs to significantly prioritise cyber security improvements to DRIVES. TfNSW is seeking to lift DRIVES’ cyber defences, but it will not achieve its stated target safeguard level until December 2025.

Even then, one of the target safeguards will not be achieved in full until DRIVES is modernised.

Audit recommendations

TfNSW should:

  • implement a service management framework including insight into the views of DRIVES users, and ensuring users can influence the service
  • ensure it can accurately and cost effectively calculate when DRIVES is unavailable due to unplanned downtime
  • ensure implementation of a capability to automatically detect anomalous patterns of access to DRIVES
  • ensure that DRIVES has appropriate cyber security and resilience safeguards in place as a matter of priority
  • develop a clear statement of the future role in whole of government service delivery for the system
  • resolve key issues currently faced by the DRIVES replacement program including by:
    • clearly setting out a strategy and design for the replacement
    • preparing a specific business case for replacement.

Read the PDF report

Parliamentary reference - Report number #388 - released 20 February 2024

Published

Actions for Management of the Critical Communications Enhancement Program

Management of the Critical Communications Enhancement Program

Finance
Health
Justice
Whole of Government
Cyber security
Information technology
Infrastructure
Internal controls and governance
Project management
Risk
Service delivery
Shared services and collaboration

What the report is about

Effective radio communications are crucial to NSW's emergency services organisations.

The Critical Communications Enhancement Program (CCEP) aims to deliver an enhanced public safety radio network to serve the five emergency services organisations (ESOs), as well as a range of other users.

This report assesses whether the NSW Telco Authority is effectively managing the CCEP.

What we found

Where it has already been delivered (about 50% of the state), the enhanced network meets most of the requirements of ESOs.

The CCEP will provide additional infrastructure for public safety radio coverage in existing buildings agreed to with ESOs. However, radio coverage inside buildings constructed after the CCEP concludes will be at risk because building and fire regulations do not address the need for in-building public safety radio coverage.

Around 98% of radios connected to the network can be authenticated to protect against cloning, though only 42% are.

The NSW Telco Authority has not settled with ESOs on how call encryption will be used across the network. This creates the risk that radio interoperability between ESOs will not be maximised.

When completed, the public safety radio network will be the only mission critical radio network for ESOs. It is unclear whether governance for the ongoing running of the network will allow ESOs to participate in future network operational decisions.

The current estimated capital cost for the NSW Telco Authority to complete the CCEP is $1.293 billion. This is up from an estimated cost of $400 million in 2016. The estimated capital cost was not publicly disclosed until $1.325 billion was shown in the 2021–22 NSW Budget Papers.

We estimate that the full cost to government, including costs to the ESOs, of implementing the enhanced network is likely to exceed $2 billion.

We made recommendations about

  • The governance of the enhanced Public Safety Network (PSN) to support agency relationships.
  • The need to finalise a Traffic Mitigation Plan for when the network is congested.
  • The need to provide advice to the NSW Government about the regulatory gap for ensuring adequate network reach in future buildings.
  • The need to clarify how encryption and interoperability will work on the enhanced network.
  • The need for the NSW Telco Authority to comply with its policy on Infrastructure Capacity Reservation.
  • Expediting measures to protect against the risk of cloning by unauthenticated radios.

Public safety radio networks are critical for operational communications among Emergency Services Organisations (ESOs), which in New South Wales include:

  • NSW Ambulance
  • Fire and Rescue NSW
  • NSW Police Force
  • NSW Rural Fire Service
  • NSW State Emergency Service.1

Since 1993, these five ESOs have had access to a NSW Government owned and operated radio communications network, the Public Safety Network (PSN), to support their operational communications. Around 60 to 70 other entities also have access to this network, including other NSW government entities, Commonwealth government entities, local councils, community organisations, and utility companies.

Pursuant to the Government Telecommunications Act 2018 ('the Act'), the New South Wales Government Telecommunications Authority ('NSW Telco Authority') is responsible for the establishment, control, management, maintenance and operation of the PSN.2

Separate to the PSN, all ESOs and other government entities have historically maintained their own radio communication capabilities and networks. Accordingly, the PSN has been a supplementary source of operational radio communications for these entities.

These other radio networks maintained by ESOs and other entities are of varying size and capability, with many ageing and nearing their end-of-life. There was generally little or no interoperability between networks, infrastructure was often co-located and duplicative, and there were large gaps in geographic coverage.

In 2016, the NSW Telco Authority received dedicated NSW Government funding to commence the Critical Communications Enhancement Program (CCEP).

According to NSW Telco Authority's 2021–22 annual report, the CCEP is a transformation program for operational communications for NSW government agencies. The CCEP '…aims to deliver greater access to public safety standard radio communications for the State’s first responders and essential service agencies'. The objective of CCEP is to consolidate the large number of separate radio networks that are owned and operated by various NSW government entities and to enhance the state’s existing shared PSN. The program also aims to deliver increased PSN coverage throughout New South Wales.

The former NSW Government intended that as the enhanced PSN was progressively rolled-out across NSW, ESOs would migrate their radio communications to the enhanced network, before closing and decommissioning their own networks.

About this Audit

This audit assessed whether the CCEP is being effectively managed by the NSW Telco Authority to deliver an enhanced PSN that meets ESOs' requirements for operational communications.

We addressed the audit objective by answering the following two questions:

  1. Have agreed ESO user requirements for the enhanced PSN been met under day-to-day and emergency operational conditions?
  2. Has there been adequate transparency to the NSW Government and other stakeholders regarding whole-of-government costs related to the CCEP?

In answering the first question, we also considered how the agreed user requirements were determined. This included whether they were supported by evidence, whether they were sufficient to meet the intent of the CCEP (including in considering any role for new or alternative technologies), and whether they met any relevant technical standards and compliance obligations (including for cyber security resilience).

While other NSW government agencies and entities use the PSN, we focused on the experience of the five primary ESOs because these will be the largest users of the enhanced PSN.

Both the cost and time required to complete the CCEP roll-out have increased since 2016. While it was originally intended to be completed in 2020, this is now forecast to be 2027. Infrastructure NSW has previously assessed the reasons for the increases in time and cost. A summary of the findings made by Infrastructure NSW is presented in Chapter 1 of this report. Accordingly, as these matters had already been assessed, we did not re-examine them in this performance audit.

The auditee for this performance audit is the NSW Telco Authority, which is a statutory authority within the Department of Customer Service portfolio.

In addition to being responsible for the operation of the PSN, section 5 of the Act also prescribes that the NSW Telco Authority is:

  • to identify, develop and deliver upgrades and enhancements to the government telecommunications network to improve operational communications for government sector agencies
  • to develop policies, standards and guidelines for operational communications using telecommunications networks.

The NSW Telco Authority Advisory Board is established under section 10 of the Act. The role of the board is to advise the NSW Telco Authority and the minister on any matter relating to the telecommunications requirements of government sector agencies and on any other matter relating to the functions of the Authority. As of 2 June 2023, the responsible minister is the Minister for Customer Service and Digital Government.

The five identified ESOs are critical stakeholders of the CCEP and therefore they were consulted during this audit. However, the ESOs were not auditees for this performance audit.

Conclusion

In areas of New South Wales where the enhanced Public Safety Network has been implemented under the Critical Communications Enhancement Program, the NSW Telco Authority has delivered a radio network that meets most of the agreed requirements of Emergency Services Organisations for routine and emergency operations.
In April 2023, the enhanced Public Safety Network (PSN) was approximately 50% completed. In areas where it is used by Emergency Services Organisations (ESOs), the PSN generally meets agreed user requirements. This is demonstrated through extensive performance monitoring and reporting, which shows that agreed performance standards are generally achieved. Reviews by the NSW Government and the NSW Telco Authority found that the PSN performed effectively during major flood events in 2021 and 2022.

Where it is completed, PSN coverage is generally equal to or better than each ESO's individual pre-existing coverage. The NSW Telco Authority has a dedicated work program to address localised coverage gaps (or 'blackspots') in those areas where coverage has otherwise been substantively delivered. Available call capacity on the network far exceeds demand in everyday use. Any operational issues that may occur with the PSN are transparent to ESOs in real time.

The NSW Telco Authority consulted extensively with ESOs on requirements for the enhanced PSN, with relatively few ESO requirements not being included in the specifications for the enhanced PSN. Lessons from previous events, including the 2019–20 summer bushfires, have informed the design and implementation of the enhanced PSN (such as the need to ensure adequate backup power supply to inaccessible sites). The network is based on the Project 25 technical standards for mission-critical radio communications, which is widely-accepted in the public safety radio community throughout Australia and internationally.

There is no mechanism to ensure adequate radio coverage within new building infrastructure after the CCEP concludes, but the NSW Telco Authority and ESOs have agreed an approach to prioritise existing in-building sites for coverage for the duration of the CCEP.
The extent to which the PSN works within buildings and other built structures (such as railway tunnels) is of crucial importance to ESOs, especially the NSW Police Force, NSW Ambulance, and Fire and Rescue NSW. This is because a large proportion of their operational communications occurs within buildings.

There is no mechanism to ensure the adequacy of future in-building coverage for the PSN in new or refurbished buildings after the CCEP concludes. Planning, building, and fire regulations are silent on this issue. We note there are examples in the United States of how in-building coverage for public safety radio networks can be incorporated into building or fire safety codes.

In regard to existing buildings, it is not possible to know whether a building requires its own in-building PSN infrastructure until nearby outside radio sites, including towers and antennae, have been commissioned into the network. Only then can it be determined whether their radio transmissions are capable of penetrating inside nearby buildings. Accordingly, much of this work for in-building coverage cannot be done until outside radio sites are finished and operating.

In March 2023, the NSW Telco Authority and ESOs agreed on a list of 906 mandatory and 7,086

non-mandatory sites for in-building PSN coverage. Most of these sites will likely be able to receive radio coverage via external antennae and towers, however this cannot be confirmed until those nearby external PSN sites are completed. The parties also agreed on an approach to prioritising those sites where coverage is needed but not provided by antennae and towers. Available funding will likely only extend to ensuring coverage in sites deemed mandatory, which is nonetheless expected to meet the overall benchmark of achieving 'same or better' coverage than what ESOs had previously.

There is a risk that radio interoperability between ESOs will not be maximised because the NSW Telco Authority has not settled with ESOs how encryption will be used across the enhanced PSN.
End-to-end encryption of radio transmissions is a security feature that prevents radio transmissions being intercepted or listened to by people who are not meant to. The ability of the PSN to provide end-to-end encryption of operational communications is of critical importance to the two largest prospective users of the PSN: the NSW Police Force and NSW Ambulance. Given that encryption excludes other parties that do not have the requisite encryption keys, its use creates an obstacle to achieving a key intended benefit of the CCEP, that is a more interoperable PSN, where first responders are better able to communicate with other ESOs.

Further planning and collaboration between PSN participants are necessary to consider how these dual benefits can be achieved, including in what operational circumstances encrypted interoperability is necessary or appropriate.

The capital cost to the NSW Telco Authority of the CCEP, originally estimated at $400 million in 2016, was not made public until the 2021–22 NSW Budget disclosed an estimate of $1.325 billon.
The estimated capital cost to complete all stages of the CCEP increased over time. This increasing cost was progressively disclosed to the NSW Government through Cabinet processes between 2015–16 and 2021–22.

In 2016, the full capital cost to the NSW Telco Authority of completing the CCEP was estimated to be $400 million. This estimated cost was not publicly disclosed, nor were subsequent increases, until the cost of $1.325 billion was publicly disclosed in the 2021–22 NSW Budget (revised down in the 2022–23 NSW Budget to $1.293 billion).

There has been no transparency about the whole-of-government cost of implementing the enhanced PSN through the CCEP.
In addition to the capital costs incurred directly by the NSW Telco Authority for the CCEP, ESOs have incurred costs to maintain their own networks due to the delay in implementing the CCEP. The ESOs will continue to incur these costs until they are able to fully migrate to the enhanced PSN, which is expected to be in 2027. These costs have not been tracked or reported as part of transparently accounting for the whole-of-government cost of the enhanced PSN. This is despite Infrastructure NSW in 2019 recommending to the NSW Telco Authority that it conduct a stocktake of such costs so that a whole-of-government cost impact is available to the NSW Government.

1 The definition of 'emergency services organisation' is set out in the State Emergency and Rescue Management Act 1989 (NSW). In addition to the five ESOs discussed in this report, the definition also includes: Surf Life Saving New South Wales; New South Wales Volunteer Rescue Association Inc; Volunteer Marine Rescue NSW; an agency that manages or controls an accredited rescue unit; and a non-government agency that is prescribed by the regulations for the purposes of this definition.
2 Section 15(1) of the Government Telecommunications Act 2018 (NSW).

The NSW Telco Authority established and tracked its own costs for the CCEP

Over the course of the program from 2016, the NSW Telco Authority prepared a series of business cases and program reviews that estimated its cost of implementing the program in full, including those shown in Exhibit 6 below.

Exhibit 6: Estimated costs to fully implement the CCEP
Source Capital cost ($ million) Operating cost
($ million)
Completion date
March 2016 business case 400 37.3 2020
November 2017 internal review 476.7 41.7 2022
March 2020 business case 950–1,050 -- 2025
October 2020 business case 1,263.1 56.1 2026

Source: CCEP business cases as identified.

In response to the 2016 CCEP business case, the then NSW Government approved the NSW Telco Authority implementing the CCEP in full, with funding provided in stages. The NSW Telco Authority tracked its costs against approved funding, with monthly reports provided to the multi-agency Program Steering Committee

Throughout the program, the NSW Government was informed of increasing costs being incurred by the NSW Telco Authority for the CCEP

The various business cases, program updates, and program reviews prepared by the NSW Telco Authority were provided to the NSW Government through the required Cabinet process when seeking approval for the program proceeding and requests for both capital and operational funding. These provided clear indication of the changing overall cost of the CCEP to the NSW Telco Authority, as well as the delays that were being experienced.

There was no transparency to the Parliament and community about changes in the capital cost of the CCEP until the 2021–22 NSW Budget

As the business cases for the CCEP were not publicly available, the only sources of information about capital cost were NSW Budget papers and media releases. The information provided in the annual Budget papers prior to the 2021–22 NSW Budget provided no visibility of the estimated full capital cost to complete all stages of the CCEP. As shown in Exhibit 7 below, this information was fragmented and complex.

Media releases about the progress of the CCEP did not provide the estimated total cost to the NSW Telco Authority of $1.325 billion to complete all stages of the CCEP until June 2021. Prior to this date, media releases only provided funding for the initial stages of the program or for the stages subject to a funding announcement.

Even during the September 2019 and March 2020 Parliamentary Estimate Committee hearings where the costings and delays to the CCEP were raised, the estimated full cost of the CCEP was not revealed.

Exhibit 7: CCEP funding in NSW Budget papers from 2015–16 to 2022–23
Financial year Type of major work Description of expenditure Forecast estimate to complete ($ million) Estimated duration
2015–16 New work Infrastructure Rationalisation Program: Planning and Pilot 18.3 2015–16
2016–17 Work in progress CCEP Planning and Pilot 18.3 2015–17
New work CCEP 45 2016–17
2017–18 New work CCEP 190.75 2017–21
2018–19 Work in progress CCEP North Coast and State-wide Detailed Design 190.75 2017–21
New work CCEP Greater Metropolitan Area 236 2018–22
2019–20 Work in progress CCEP 426.9 2018–22
2020–21 Work in progress CCEP 664.8 2018–22
2021–22 Work in progress CCEP 1,325 2018–26
2022–23 Work in progress CCEP 1,292.8 2018–26

Source: NSW Treasury, Annual State Budget Papers.

The original business case for the CCEP included estimated ESO costs, though these costs were not tracked throughout the program

Estimates for ESO costs for operating and maintaining their own radio networks over the four years from 2016–17 were included in the original March 2016 business case. They included $75.2 million for capital expenditure and $95 million for one-off operating costs. These costs, as well as costs incurred by ESOs due to the delay in the program, were not subsequently tracked by the NSW Telco Authority.

In January 2017, Infrastructure NSW reviewed the CCEP business case of March 2016. In this review, Infrastructure NSW recommended that the NSW Telco Authority identify combined and apportioned costs and cashflow for all ESOs over the CCEP funding period reflecting all associated costs to deliver the CCEP. These to include additional incidental capital costs accruing to ESOs, transition and migration to the new network and the cost (capital and operational) of maintaining existing networks. This recommendation was implemented in the November 2017 program review, with ESO capital costs estimated as $183 million.

In 2019, Infrastructure NSW conducted a Deep Dive Review on the progress of the CCEP. In this review, Infrastructure NSW made what it described as a 'critical recommendation' that the NSW Telco Authority:

…coordinate a stocktake of the costs of operational bridging solutions implemented by PSAs [ESOs] as a result of the 18-month delay, so that a whole-of-government cost impact is available to the NSW Government.  

It should be noted that the delay to CCEP completion now is seven years and that further ‘operational bridging solutions’ have been needed by the ESOs.

'Stay Safe and Keep Operational' costs incurred by ESOs will be significantly higher than originally estimated

Stay Safe and Keep Operational (SSKO) funding was established to provide funding to ESOs to maintain their legacy networks while the CCEP was refreshing and enhancing the PSN. This recognised that much of the network infrastructure relied on by ESOs had reached – or was reaching – obsolescence and would either require extensive maintenance or replacement before the PSN was available for ESOs to migrate to it. ESOs may apply to NSW Treasury for SSKO funding, with their specific proposals being reviewed (and endorsed, where appropriate) by the NSW Telco Authority. Accordingly, SSKO expenditure does not fall within the CCEP budget allocation.

As shown in the table below, extracted from the March 2016 CCEP business case, the total expected cost for SSKO purposes over the course of the CCEP was originally $40 million, assuming the enhanced PSN would be fully available by 2020.

Exhibit 8: Stay Safe and Keep Operational forecast costs, 2017 to 2020
Year 2017 2018 2019 2020 Total
SSKO forecast ($ million) 12.5 15 10 2.5 40

Source: March 2016 CCEP business case.

In October 2022, the expected completion date for the CCEP was re-baselined to August 2027. Accordingly, ESOs will be required to continue to maintain their radio networks using legacy equipment for seven years longer than the original 2020 forecast. This will likely become progressively more expensive and require additional SSKO funding. For example, NSW Telco Authority endorsed SSKO bids for 2022–23 exceeded $35 million for that year alone.

Compared to the original forecast made in the March 2016 CCEP business case of $40 million, we found ESOs had estimated SSKO spending to 2027 will be $292.5 million.

A refresh of paging network used by ESOs and the decommissioning of redundant sites were both removed from the original 2016 scope of the CCEP

Paging

A paging network is considered an important user requirement by the Fire and Rescue NSW, NSW Rural Fire Service, and NSW State Emergency Service. The 2016 CCEP business case included a paging network refresh within the program scope of works. This was reiterated in the November 2017 internal review of the program. These documents did not estimate a cost for this refresh. The March 2020 and October 2020 business cases excluded paging from the program scope. The audit is unable to identify when, why or by whom the decision was made to remove paging from the program scope, something that was also not well communicated to the affected ESOs.

In 2021, after representations from the affected ESOs, the NSW Telco Authority prepared a separate business case for a refresh of the paging network at an estimated capital cost of $60.31 million. This program was subsequently approved by the NSW Government and included in the 2022–23 NSW Budget.

In determining an estimated full whole-of-government cost of delivering the enhanced PSN, we have included the budgeted cost of the paging network refresh on the basis that:

  • it was expressly included in the original approved March 2016 business case
  • the capability is deemed essential to the needs of three ESOs.

Decommissioning costs

The 2016 CCEP business case included cost estimates for decommissioning surplus sites (whether ‘old’ GRN sites or sites belonging to ESOs’ own networks). These estimates were provided for both the NSW Telco Authority ($38 million) and for the ESOs ($55 million). However, while these estimates were described, they were not included as part of the NSW Telco Authority's estimated capital cost ($400 million) or (more relevantly) operating cost ($37.3 million) for the CCEP. This is despite decommissioning being included as one of eight planned activities for the rollout of the program.

In the October 2020 business case, an estimate of $201 million was included for decommissioning agency networks based on a model whereby:

  • funding would be coordinated by the NSW Telco Authority
  • scheduling and reporting through an inter-agency working group and
  • where appropriate, agencies would be appointed as the most appropriate decommissioning party.

This estimated cost is not included in the CCEP budget.

In determining an estimated full whole-of-government cost of the enhanced PSN, we have included the estimated cost of decommissioning on the basis that:

  • decommissioning was included in the 2016 CCEP business case as one of eight 'planned activities for the rollout of the program'
  • effective decommissioning of surplus sites and equipment (including as described in the business case as incorporating asset decommissioning, asset re-use, and site make-good) is an inherent part of the program management for an enhanced PSN
  • costs incurred in decommissioning are entirely a consequence of the CCEP program.

The estimated minimum cost of building an enhanced PSN consistent with the original proposal is over $2 billion

We have derived two estimated minimum whole-of-government costs for delivering an enhanced PSN. These are:

  • $2.04 billion when calculated from NSW Telco Authority data – shown as estimate A in Exhibit 9 below.
  • $2.26 billion when calculated from ESO supplied data – shown as estimate B in Exhibit 9.

Both totals include:

  • budgeted amounts for both CCEP capital expenditure ($1,292.8 million) and operating expenditure ($139 million)
  • the NSW Telco Authority's 2020 estimated cost for decommissioning ($201 million)
  • the NSW Telco Authority's approved funding for paging refresh ($60.3 million).

The two estimated totals primarily vary around the capital expenditure of ESOs (particularly SSKO funding). To determine these costs, we used ESO provided actual SSKO costs to date, as well as their estimates for maintaining their legacy radio networks through to 2027.

The equivalent cost estimates from the NSW Telco Authority were sourced from the November 2017 internal review and the October 2020 business case for CCEP. It should be noted that the amounts for both estimates are not audited, or verified, but do provide an indication of how whole-of-government costs have grown over the course of the program.

The increase in and reasons for the increase in total CCEP costs (capital and one-off operating) incurred or forecast by the NSW Telco Authority (from $437.3 million in 2016 to $1,431.8 million in 2022) have been provided to the NSW Government through various business cases and reviews prepared by the NSW Telco Authority, as well as by reviews conducted by Infrastructure NSW as part of its project assurance responsibilities.

However, the growth in ESO costs and other consequential costs, such as paging and decommissioning, from around $263 million in the 2016 CCEP business case to between $600 million and $800 million, has to a large degree remained invisible and unexplained to the NSW Government and other stakeholders

Exhibit 9: Estimated whole-of-government costs of the enhanced PSN
  Estimated whole-of-government cost, over time
Cost type 20161 20172 20203 2023–Estimate A4 2023–Estimate B5
$ million $ million $ million $ million $ million
CCEP capital expenditure 400a 476.7b 1,263.1c 1,292.8d 1,292.8d
CCEP operating expenditure 37.3a 41.7b 41.5e 139d 139d
CCEP total 437.3 518.4 1,304.6 1,431.8 1,431.8
ESO capital expenditure 75.2a,f 183b,e 75.4e 258.4g 292.5
ESO one-off operating expenditure 93a n.a.l 86.5e 86.5h 273
ESO total 168.2 183 161.9 344.9 565.5
Paging n.a.i n.a.i n.a.j 60.3k 60.3k
Decommissioning 93 n.a.l 201.0 201h 201
Paging and decommissioning total 93 n.a. 201 261.3 261.3
Whole-of-government total 698.5 701.4 1,667.5 2,038 2,258.6

Notes:
  1. Financial year 2016 to Financial year 2020.
  2. Financial year 2016 to Financial year 2021.
  3. Financial year 2016 to Financial year 2025.
  4. Financial year 2016 to Financial year 2026.
  5. Financial year 2022 to Financial year 2025.
  6. Stay Safe and Keep Operational (SSKO) costs plus terminals costs.
  7. November 2017 internal review and October 2020 Business case.
  8. October 2020 Business case.
  9. Included in CCEP capital expenditure at that time.
  10. By 2020, a refresh of the paging network had been removed from the CCEP scope.
  11. A separate business case for a refresh of the paging network was approved by government in 2022.
  12. Figure not included in the source document.
Sources:
  1. March 2016 CCEP business case.
  2. November 2017 Internal Review conducted by the NSW Telco Authority.
  3. October 2020 CCEP business case.
  4. Derived from business cases, with ESO costs drawn from NSW Telco Authority data.
  5. Derived from business cases, with ESO costs based on data provided to the Audit Office of New South Wales by each of the five ESOs.

Appendix one – Response from agency

Appendix two – Trunked public safety radio networks

Appendix three – About the audit

Appendix four – Performance auditing

 

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #383 - released 23 June 2023

 

Published

Actions for Regulation of public native forestry

Regulation of public native forestry

Environment
Industry
Compliance
Management and administration
Regulation
Risk

What this report is about

The Forestry Corporation of NSW (FCNSW) is a state-owned corporation that manages over two million hectares of public native forests and plantations supplying timber to sawmills across NSW.

The NSW Environment Protection Authority (EPA) is responsible for regulating the native forestry industry in NSW.

FCNSW must comply with Integrated Forestry Operations Approvals (IFOAs), which set out rules for how timber harvesting may occur.

Most harvesting is undertaken under the Coastal IFOA, which commenced in 2018.

This audit assessed how effectively Forestry Corporation of NSW manages its public native forestry activities to ensure compliance, and how effectively the Environment Protection Authority regulates these activities.

What we found

Forestry Corporation of NSW (FCNSW) clearly articulates its compliance obligations.

While FCNSW undertakes monitoring of its contractors, it does not do so consistently and does not target its monitoring activities on a risk basis.

FCNSW has largely fulfilled mandatory Coastal IFOA training requirements, but has not yet trained other staff who would also benefit from the training.

Contractor compliance appears to be improving, but there are gaps and inconsistencies in FCNSW's documentation of this.

FCNSW is not measuring its overall compliance to determine how it is tracking against its target.

The EPA undertakes proactive inspections of Coastal IFOA harvesting operations on a risk basis. However, it does not assess the risk at harvest sites covered by other IFOAs.

Most EPA compliance staff have received basic training, but few have received more advanced training required to effectively undertake forestry inspections.

Some EPA offices do not have the necessary equipment to undertake forestry inspections.

The EPA and FCNSW are not implementing all elements of a Memorandum of Understanding that aims to promote a cooperative relationship between the agencies.

What we recommended

The report made recommendations to FCNSW which aim to improve:

  • staff training
  • consistency of compliance reviews and data capture
  • targeting of compliance activities
  • measurement of performance.

The report made recommendations to the EPA which aim to improve:

  • risk-assessments
  • staff training
  • staff equipment.

The report also recommended that FCNSW and EPA should fully implement their Memorandum of Understanding.

The Forestry Corporation of NSW (FCNSW) is a state-owned corporation that supplies timber to sawmills in New South Wales, including timber harvested from public native forests. FCNSW is responsible for the management of around two million hectares of public native forests and plantations. Around half the area of native forests is permanently set aside for conservation.

Public native forestry is regulated through the Forestry Act 2012, Biodiversity Conservation Act 2016, Protection of the Environment Operations Act 1997 and associated regulations. Under the Forestry Act 2012, the objectives of FCNSW include, where its activities affect the environment, to conduct its operations in compliance with the principles of ecologically sustainable development contained in section 6(2) of the Protection of the Environment Administration Act 1991. This involves the integration of social, economic and environmental considerations in decision-making processes.

In undertaking its native forestry operations, FCNSW must comply with Integrated Forestry Operations Approvals (IFOA), issued jointly by the Minister for the Environment and the Minister for Agriculture, which set out rules to protect species and ecosystems where timber harvesting is occurring, and aim to ensure forests are managed in an ecologically sustainable way. FCNSW must also ensure that its contractors undertake forestry operations in line with IFOAs. The Coastal IFOA, developed in 2018, consolidated the four IFOAs for the Eden, Southern, Upper and Lower North East coastal regions of New South Wales into a single IFOA. The other three current IFOAs are Brigalow Nandewar, South Western Cypress and Riverina Redgum (the Western IFOAs).

The NSW Environment Protection Authority (EPA) is responsible for regulating native forestry in New South Wales. Under the Protection of the Environment Administration Act 1991, one of the objectives of the EPA is to protect, restore and enhance the quality of the environment in New South Wales, having regard to the need to maintain ecologically sustainable development. This includes monitoring FCNSW’s compliance with IFOA conditions, including by maintaining and enforcing a compliance program.

The Coastal IFOA also introduced a new structure and regulatory approach for IFOAs, establishing outcomes, conditions and protocols. The conditions set mandatory actions and controls intended to protect threatened plants, animals, habitats, soils and water. The protocols, referenced in the conditions, set out additional enforceable actions and controls intended to support the effective implementation of the conditions.

Public native forestry is the largest component of hardwood supply in New South Wales. The 2019–20 bushfires had a major impact on regional communities, and large areas of native forest. This heightened environmental risks and challenges in public native forestry. Five million hectares of New South Wales was impacted, including more than 890,000 hectares of native State Forests. This is over 40% of the coastal and tablelands native State Forests in New South Wales.

In addition to effective compliance activities, the success of the regulatory approach to public native forestry operations depends on how wood supply yields are modelled, and ensuring that harvested volumes do not exceed these yields. This is of particular importance in areas where forests have been severely damaged by fire. This audit did not consider sustainable yields. Recent reviews of this include an independent review of the FCNSW sustainable yield model and a Natural Resources Commission review in 2021.

This audit assessed how effectively Forestry Corporation of NSW manages its public native forestry activities to ensure compliance, and how effectively the Environment Protection Authority regulates these activities.

Conclusion

Forestry Corporation of NSW (FCNSW) clearly articulates its compliance obligations at the corporate level and for each harvest site. However, there are deficiencies in FCNSW’s compliance approach. While FCNSW undertakes monitoring of its contractors in a number of ways, it does not consistently monitor compliance across its contractors and does not target its monitoring activities on a risk basis. This increases the risk that non-compliant practices will not be identified, potentially leading to environmental harm.

FCNSW has a compliance strategy and program that sets out its compliance obligations and how they will be managed. FCNSW’s Compliance Policy outlines compliance requirements, actions to ensure compliance, and responsibilities for staff, supervisors, senior management and board members. FCNSW also has a compliance monitoring system manual that outlines its monitoring program, and its risk-assessment and incident reporting procedures. These corporate documents set out FCNSW’s overall approach to managing compliance.

Harvesting in State Forests is undertaken by contractors or sub-contractors. FCNSW provides training to its staff and contractors and undertakes monitoring to identify contractor compliance with relevant requirements through a variety of means, including its quality assurance assessment (QAA) program. FCNSW also communicates compliance obligations to contractors in harvest plans.

FCNSW is not undertaking its monitoring activities on a risk basis. The frequency of contractor supervision is inconsistent and is not tied to the contractor’s past performance, meaning that monitoring resources are not necessarily being targeted at the areas of highest -risk.

FCNSW also does not target its QAAs on a risk basis. FCNSW does not have procedures for how QAAs should occur outside the North Coast region. QAAs are conducted inconsistently, with some reviews occurring in only part of the harvest site while others cover the whole harvest site. In addition, some QAAs do not meet FCNSW’s minimum standards. FCNSW’s record keeping of QAAs is also inconsistent, making it difficult to determine true levels of compliance and the cause of identified potential non-compliances.

In addition, FCNSW does not collate and analyse the results of its compliance monitoring to target its compliance audits. Undertaking these audits on a risk basis would allow FCNSW to apply its resources to the highest-risk harvest sites and contractors.

The EPA identifies native forestry as a high priority regulatory activity and undertakes proactive inspections of Coastal IFOA harvest sites on a risk basis. However, the EPA does not assess the risk at Western IFOA harvest sites, leaving a significant gap in its inspection regime. This means that the EPA may not be inspecting all high-risk harvest sites to ensure compliance with regulations across those sites. The EPA has started to train more of its staff in conducting forestry inspections, but it currently has a limited number of trained and experienced staff to undertake this work.

The EPA has developed a Regulatory and Compliance Priorities Statement 2022–23 which identifies native forestry as a key risk. This statement identifies that forestry is a priority area for its compliance activities because of the increased environmental risk and sensitivity in forests following the 2019–20 bushfires. A divisional plan for its regulatory operations contains specific actions for forestry, including ensuring that the EPA has a consistent approach to recording regulatory actions undertaken and identifying priority areas for assurance over State Forests.

As part of its compliance activities, the EPA responds to complaints received, or reports of non-compliance, across all four IFOA areas and also carries out proactive inspections in the Coastal IFOA area. To guide these inspections, the EPA determines the level of risk posed by each harvest site in the Coastal IFOA area using information it gathers from FCNSW. The EPA prioritises inspections of sites rated as high and medium-risk, but the EPA has not undertaken risk-assessments for the three Western IFOAs. By not determining the risks in these areas, the EPA does not have assurance that it is checking FCNSW compliance with regulations across all high-risk sites.

Most EPA staff have basic training in forestry matters, but few staff have the more advanced training required to effectively undertake forestry inspections. In addition, not all EPA officers have access to the technology required to undertake forestry inspections, such as internet-enabled tablets and specialised tapes for measuring tree diameter. This limits the EPA’s ability to determine the level of compliance with regulations and respond effectively to instances of environmental harm in relation to public native forestry.

The Coastal IFOA does not contain provisions which allow the EPA to unilaterally restrict forestry activities in the aftermath of a catastrophic event such as the 2019–20 bushfires. Following the bushfires, FCNSW approached the EPA and asked for additional site-specific operating conditions (SSOC) at some locations to assist it in maintaining compliance. The SSOCs were issued by the EPA and FCNSW was required to carry out forestry operations in accordance with the SSOCs at relevant harvest sites. These SSOCs were in place for 12 months. After a year, FCNSW decided not to renew this approach with the EPA, but implemented its own voluntary measures during harvesting operations. Unlike the SSOCs, the EPA was unable to undertake enforcement activities for breaches of voluntary measures.

Appendix one – Responses from agencies
Appendix two – About the audit
Appendix three – Performance auditing

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #382 - released 22 June 2023

Published

Actions for Cyber Security NSW: governance, roles, and responsibilities

Cyber Security NSW: governance, roles, and responsibilities

Local Government
Whole of Government
Finance
Cyber security
Information technology
Internal controls and governance
Management and administration

What the report is about

Cyber Security NSW is part of the Department of Customer Service, and aims to provide the NSW Government with an integrated approach to preventing and responding to cyber security threats.

This audit assessed the effectiveness of Cyber Security NSW's arrangements in contributing to the NSW Government's commitments under the NSW Cyber Security Strategy, in particular, increasing the NSW Government's cyber resiliency. The audit asked:

  • Are internal planning and governance processes in place to support Cyber Security NSW meet its objectives? 
  • Are Cyber Security NSW's roles and responsibilities defined and understood across the public sector?

What we found

Cyber Security NSW has a clear purpose that is in line with wider government policy and objectives. However, it does not clearly and consistently communicate its key objectives, with too few reliable and meaningful ways of measuring progress toward those objectives.

Cyber Security NSW does not provide adequate assurance of the cyber security maturity self assessments performed by NSW Government agencies. Department heads are accountable for ensuring their agency's compliance with NSW government policy.

Cyber Security NSW has a remit to assist local government to improve cyber resilience. However, it cannot mandate action and does not have a strategic approach guiding its efforts.

What we recommended

By 30 June 2023 the Department of Customer Service should:

  1. implement an approach that provides reasonable assurance that NSW government agencies are assessing and reporting their compliance with the NSW Government Cyber Security Policy in a manner that is consistent and accurate
  2. ensure that Cyber Security NSW has a strategic plan that clearly demonstrates how the functions and services provided by Cyber Security NSW contribute to meeting its purpose and achieving NSW government outcomes
  3. ensure that Cyber Security NSW has a detailed, complete and accessible catalogue of services available to agencies and councils
  4. develop a comprehensive engagement strategy and plan for the local government sector, including councils, government bodies, and other relevant stakeholders. 

The NSW Cyber Security Strategy details a vision for ‘…NSW to become a world leader in cyber security, protecting, growing, and advancing our digital economy’. Cyber Security NSW, located within the Department of Customer Service, has lead responsibility for one of the four commitments in the strategy: to increase the NSW Government’s cyber resilience.

Cyber Security NSW ‘aims to provide the NSW Government with an integrated approach to preventing and responding to cyber security threats’. It does not provide broader consumer-focused services.

In August 2020, the NSW Government approved a business case to enhance the funding and remit of Cyber Security NSW to include a broader range of services and functions. As a result, Cyber Security NSW is receiving $60 million in funding from 2020–21 to 2022–23, an increase from its previous funding of around $5 million per year (which had been sourced from contributions from each NSW Government department).

The objective of this performance audit was to assess the effectiveness of Cyber Security NSW’s arrangements in contributing to the NSW Government’s commitments under the NSW Cyber Security Strategy, in particular, to increase the NSW Government’s cyber resilience.

We assessed this objective through two lines of inquiry:

  1. Are internal planning and governance processes in place to support Cyber Security NSW meet its objectives?
  2. Are Cyber Security NSW roles and responsibilities defined and understood across the public sector?

The Audit Office of New South Wales has reported on the topic of cyber security previously. Most recently, the Internal Controls and Governance 2022 report included findings and recommendations relating to cyber security internal controls and governance at 25 of the largest agencies in the NSW public sector. While that report is multi-agency and sought to assess the level of cyber security attained in selected agencies, this current performance audit report focuses specifically on Cyber Security NSW and how well-equipped it is to meet its whole-of-government cyber security leadership and coordination roles.

Conclusion

Cyber Security NSW has a clear purpose that is aligned with wider government policy and objectives, but it cannot effectively demonstrate its progress toward improving cyber resilience

Cyber Security NSW's high-level purpose is to support the NSW Government’s delivery of digitised services that are protected, connected, and trusted. This purpose is consistent with broader NSW Government and Australian Government policy and builds on the purpose of the previous NSW Office of the Government Chief Information Security Officer, which was itself informed by external research and previous Audit Office of New South Wales recommendations.

In delivering its purpose, Cyber Security NSW provides a wide range of services to NSW government agencies and the local government sector. The majority of agencies and councils consulted during this audit reported that the services they received contributed to improving their individual cyber security.

However, Cyber Security NSW does not clearly and consistently communicate its key objectives to ensure that its efforts are effectively and efficiently targeted, prioritised, planned, and reported. This is despite it receiving enhanced funding to expand the scope of services it provides. It currently has many sets of objectives across a range of sources, including the Cyber Security Strategy, business plans, corporate material, and public communications. It has too few reliable and meaningful ways of measuring progress toward its objectives, and no overall workplan or roadmap to show how the objectives will be achieved.

Without a clear and consistent program logic, it is difficult to determine whether the functions and services delivered by Cyber Security NSW are helping to achieve the level of cyber resilience required to meet the increasing cyber threats faced by the NSW public sector.

Cyber Security NSW does not provide assurance of the cyber security maturity self-assessments performed by individual NSW Government agencies

The NSW Government has a devolved model for cyber security assurance. Cyber Security NSW administers the whole-of-government policy settings, and agency heads are responsible for ensuring compliance with policy requirements.

Cyber Security NSW has a remit to carry out audits of agencies’ self-assessments, but it has not carried out these audits and does not seek its own assurance of the results of these self-assessments. It is not sufficiently addressing previously identified inconsistencies and inaccuracies in how those self-assessments are performed and reported.

This form of auditing would be an important assurance that self-assessment and reporting is reliable. This is important given that maturity reporting is the main source of knowledge about the cyber security maturity and resilience of NSW Government agencies to cyber threats. If these self-assessments are unreliable, then it creates the risk that knowledge of the potential resilience of the NSW public sector to cyber security incidents is similarly unreliable. There is no other body in NSW with the mandate to routinely provide this form of assurance.

Cyber Security NSW has a remit to assist local government improve cyber resilience, however it cannot mandate action, and does not have a strategic approach guiding its efforts

Consistent with the expectations that accompanied its 2020 funding enhancement, Cyber Security NSW has engaged with the local government sector, albeit with mixed results. While these mixed results are partly a consequence of it not being provided a formal mandate in the sector, it has also been impacted by the fact that Cyber Security NSW has not established an engagement plan or strategy to guide its engagement with the local government sector.

Cyber security is an evolving landscape where the nature and scale of threats are increasing. The Australian Cyber Security Centre (ACSC), the Australian Government lead agency for cyber security, reported in its in 2020–21 annual report that it received over 67,500 cybercrime reports, equating to one report of a cyber attack every eight minutes, with no sector of the economy or type of government agency immune.

Citizens of NSW are increasingly accessing online government services in this context, providing different types of sensitive personal information. This reliance and transition to digital services has increased in recent times, particularly during the COVID-19 pandemic. The NSW Legislative Council’s Portfolio Committee (the Committee) noted in the March 2021 inquiry report into cyber security in NSW that ‘a failure to get cyber security right in New South Wales represents a significant risk to the State’s economy, business and community, and will affect public trust in government’.

The Committee noted that sound cyber security practices across NSW Government agencies, which Cyber Security NSW was established to drive, will enable the State and community to leverage opportunities from the digital world. Indeed, NSW aims to become a world leader in cyber security by protecting, growing and advancing the digital economy.

Establishment of Cyber Security NSW

Prior to the establishment of Cyber Security NSW, the Office of the Government Chief Information Security Officer was responsible for cyber security across the NSW government sector. This role was announced in March 2017 and was tasked with ‘identifying areas of high risk of attack, and working across NSW agencies to share intelligence, facilitate minimum security standards, and ultimately ensure that citizens can trust in the NSW Government’s delivery of digital transformation’. At the time of this appointment, the Minister for Customer Service and Digital Government stated that ‘cyber security and risk has emerged as one of the most high-profile, borderless and rapidly evolving risks facing government’.

The Office of the Government Chief Information Security Officer was renamed on 20 May 2019 to Cyber Security NSW. Governance updates at the time note that this was undertaken to ‘better reflect the leadership and coordination role required to uplift cyber security and decision-making across NSW Government’. The establishment of Cyber Security NSW was also partly in response to the Audit Office of New South Wales 2018 performance audit report on ‘Detecting and Responding to Cyber Security Incidents’. That audit found that there was no whole-of-government capability to detect and respond effectively to cyber security incidents. Cyber Security NSW is relatively new and is established as a branch within the Department of Customer Service (DCS).

The Office of the Government Chief Information Security Officer, and subsequently Cyber Security NSW, was initially funded through a levy imposed on clusters. Funding arrangements for Cyber Security NSW changed with the announcement in August 2020 of $240 million over three years for the stated purpose of bolstering the NSW Government’s cyber security capability and creating a world leading cyber industry. This funding included direct investment of $60 million from 2020–21 to 2022–23 for Cyber Security NSW to increase its capability and capacity, with the size of the team at the time expected to grow from 25 to 100 staff. In announcing this funding, the Minister for Customer Service and Digital Government stated that ‘…this is the biggest single cyber security investment in national history and will strengthen the government's capacity to detect and respond to the fast-moving cyber threat landscape’.

Cyber Security NSW is divided into two directorates, with one directorate having a focus on operations, and the other on policy and awareness. In turn, there are seven teams within the two directorates. As at March 2022, Cyber Security NSW had 76 ongoing positions filled, five contractors and 22 vacancies.

Cyber Security NSW states that its aim ‘…is to provide the NSW Government with an integrated approach to preventing and responding to cyber security threats. By building a stronger cyber resilience across whole-of-government, Cyber Security NSW is able to support the economic growth prosperity and efficiency of NSW’.

NSW Government Cyber Security Strategy

The NSW Government Cyber Security Strategy was released in September 2018 to ‘…guide and inform the safe management of government’s growing cyber footprint’. The 2018 Cyber Security Strategy also set out an action plan with success criteria against each of the six themes of the NSW cyber security framework. Based on a framework from the US National Institute of Standards and Technology (NIST), these themes are:

  • lead
  • prepare
  • prevent
  • detect 
  • respond 
  • recover.

The Strategy was revised in 2021 and combined with the Cyber Security Industry Development Strategy. The aim of this current strategy is to ‘…outline the key strategic objectives, guiding principles, and high-level focus areas that the NSW Government will use to align existing and future programs of work’. The strategy includes four NSW Government commitments to:

  • increase NSW Government cyber resiliency
  • help NSW cyber security businesses grow
  • enhance cyber security skills and workforce 
  • support cyber security research and innovation.

Cyber Security NSW has responsibility as ‘lead agency’ on the first commitment. This role requires it to set commitment objectives and focus areas for the strategy and provide central leadership and coordination of programs and initiatives.

NSW Government Cyber Security Policy

The NSW Government’s Cyber Security Policy was released in February 2019, replacing the former Digital Information Security Policy. All NSW Government agencies must comply with the Cyber Security Policy, and it was recommended for adoption by State Owned Corporations (SOC), local councils, and universities.

The current version of the Cyber Security Policy sets out a range of mandatory requirements for agencies, including: 

  • annual reporting of their self-assessed levels of maturity against all the mandatory requirements of the Policy and the Australian Cyber Security Centre’s ‘Essential Eight’ requirements 
  • that agencies must provide a list of their ‘crown jewels’ and high and extreme risks to their cluster Chief Information Security Officer (CISO).

The Policy sets out that Cyber Security NSW:

  • may assist agencies with their implementation of the Policy with an FAQ document and guidelines on several cyber security topics
  • will summarise the maturity reports provided by agencies and provide the results to the relevant governance bodies including the Cyber Security Steering Group, Secretaries’ Board, relevant committees of Cabinet, Cyber Security Senior Officers’ Group, and the ICT and Digital Leadership Group, as well as use these reports to identify common themes and areas for improvement across NSW Government.

As discussed further in Chapter 3, a mandatory guideline issued by the Secretary of the Department of Customer Service in 2020 established that departments and agencies will be subject to audits by Cyber Security NSW. This is to test compliance with the Cyber Security Policy and report these outcomes to the Secretaries’ Board.

This chapter considers whether the Department of Customer Service has a strategic plan for Cyber Security NSW that includes a consistent hierarchy of priorities, which are then reflected in workplans, and inform decisions about specific functions and activities. It also considers whether:

  • there was a sound, evidence-based rationale for why Cyber Security NSW was established
  • the specific services and functions Cyber Security NSW provides are adequately targeted to agency and council needs
  •  there is adequate performance assessment of how the services and functions performed by Cyber Security NSW contribute to uplifting cyber maturity and increasing cyber resilience.

This chapter considers the distribution of responsibility for cyber security in the NSW public sector, as well as whether the responsibilities and roles of Cyber Security NSW are clear and understood by agencies and councils. It also considers whether Cyber Security NSW has sufficient authority and mandate to fulfill its responsibilities for both NSW Government agencies and the local government sector.

Appendix one – Response from agency

Appendix two – About the audit

Appendix three – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #374 - released 8 February 2023

Published

Actions for NSW planning portal

NSW planning portal

Planning
Industry
Environment
Local Government
Information technology
Project management
Risk

What the report is about

The ePlanning program is an initiative of the Department of Planning and Environment (the department) to deliver a digital planning service for New South Wales through the NSW planning portal (the portal).

Using the portal, relevant planning activities can be carried out online, including all stages of development applications.

The portal has been developed under three separate business cases in 2013, 2014 and 2020.

In late 2019, the government mandated the use of the portal for all development applications. This decision took effect across 2020–21.

This audit assessed the effectiveness of the department's implementation, governance and stakeholder engagement in delivering the NSW planning portal. 

What we found

Since implementation commenced in 2013, the NSW planning portal has progressively achieved its objectives to provide citizens with access to consolidated planning information, and allow them to prepare and submit development applications online.

Shortcomings in the department's initial planning and management of the program led to a significant time overrun. It has taken the department longer and cost significantly more to implement the portal than first anticipated. 

In recent years the department has improved the planning, implementation and governance of the ePlanning program, resulting in improved delivery of the portal’s core functions.

The department now has a clear view of the scope necessary to finalise the program, but has not yet published the services it plans to implement in 2022 and 2023.

Mandating the use of the portal for all development applications changed the program's strategic risk environment and required the department to work more closely with a cohort of stakeholders, many of whom did not want to adopt the portal.

Despite this change, the department kept its overall delivery approach the same.

While implementation of the portal has delivered financial benefits, the department has overestimated their value.

The Department has only reported benefits since 2019 and has not independently assured the calculation of benefits.

What we recommended

By December 2022, the department should:

  • publish a roadmap of the services it expects to release on the portal across 2022 and 2023
  • update its ePlanning program assumptions, benefits targets and change management approach to reflect the government's decision to mandate the use of the portal for all stages of a development application
  • independently assure and report publicly the correct calculation of ePlanning program benefits.

Fast facts

  • 10 years taken to implement the portal when completed
  • 3 years longer than initially planned to implement the portal
  • $146m capital expenditure on the portal when completed
  • $38.5m more spent than planned in the business cases.

The ePlanning program is an initiative of the Department of Planning and Environment (the department) to deliver a digital planning service for New South Wales through the NSW planning portal (the portal, or the planning portal). The department defines the portal as an online environment where community, industry and government can work together to better understand and meet their obligations under the Environmental Planning and Assessment Act 1979 (NSW). Using the portal, relevant planning activities can be carried out online throughout New South Wales. This includes, but is not limited to:

  • applying for and gaining planning approval
  • applying for and gaining approval for building works, sub-dividing land and similar activities
  • issuing occupancy and other certificates.

The portal has been developed under three separate business cases. The first business case in 2013 led to the creation of a central portal, which made planning information available to view by planning applicants and allowed some planning applications to be lodged and tracked online.

Under a second business case prepared in 2014, the department set out to improve and widen the functions available via the portal. The department prepared a third business case in 2020 to fund further improvements to the portal over the period July 2020 to June 2023. The third business case also extended the portal's functions to support the building and occupation stages of the planning cycle.

In late 2019, the government mandated the use of the portal for all stages of development applications. This decision took effect across 2020–21 and applied to all councils as well as certifiers and others involved in the planning process.

The objective of this performance audit was to assess the effectiveness of the department's implementation, governance and stakeholder engagement in delivering the NSW planning portal. We investigated whether:

  • delivery of the NSW planning portal was planned effectively
  • sound governance arrangements are in place to ensure effective implementation of the program
  • users of the NSW planning portal are supported effectively to adopt and use the system.
Conclusion

Since implementation commenced in 2013, the NSW planning portal has progressively achieved its objectives to provide citizens with access to consolidated planning information and allow them to prepare and submit development applications online. Implementation was initially hindered by deficiencies in planning and it has taken the department significantly longer and cost significantly more to implement the portal than first anticipated. While the portal's implementation has delivered financial benefits, the department has overestimated their value. As a result, the department cannot yet demonstrate that the portal has achieved overall financial benefits, relative to its costs.

In the first two years of the ePlanning program, the department delivered a portal that allowed planners, developers, certifiers and the public to view important planning information. However, the department found the delivery of a second, transactional version of the portal in 2017 to be much more challenging. This version was intended to offer more integrated information and allow development applications to be submitted and managed online. The department did not rollout this version after a pilot showed significant weaknesses with the portal's performance. A subsequent review found that this was partly because the department did not have a clear view of the portal’s role or the best way to implement it. In recent years the department has improved the planning, implementation and governance of the ePlanning program resulting in improved delivery of the portal’s core functions.

By the time the program reaches its scheduled completion in 2023, it will have taken the department ten years and around $146 million in capital expenditure to implement the portal. This will be significantly longer and more expensive than the department originally expected. This overrun is partly due to an increased scope of services delivered through the portal and an initial under-appreciation of what is involved in creating a standard, central resource such as the portal. The department also experienced some significant implementation difficulties – which saw the transactional portal discontinued after it was found to be not fit for purpose. Following this, the department re-set the program in 2017–18 and re-planned much of the portal's subsequent development.

In November 2019, the New South Wales Government decided to mandate the use of the portal for all stages of development applications by the end of 2020–21. The department had previously planned that the portal would be progressively adopted by all councils and other stakeholders over the five years to 2025. The decision to mandate the portal's use for all development applications brought forward many of the portal's benefits as well as the challenges of its implementation. The department did not change its overall delivery approach in response to the changed risks associated with the government's decision to mandate use of the portal.

The current version of the portal has given the department more timely and comprehensive planning information and has helped New South Wales to provide continuous planning services during COVID-19 lockdowns, which interrupted many other public functions. The portal has also delivered financial benefits, however the department has not independently assured benefits calculations carried out by its consultant, and the reported benefits are overstated. In addition, some stakeholders report that the portal is a net cost to their organisation. This has included some certifiers and some councils which had implemented or had started to implement their own ePlanning reforms when use of the portal was mandated in 2019. The department now needs to address the issues faced by these stakeholders while continuing to deliver the remaining improvements and enhancements to the portal. Over the remaining year of the program, it will be critical that the department focuses on the agreed program scope and carefully evaluates any opportunities to further develop the portal to support future planning reforms.

This part of the report sets out how:

  • the ePlanning program has been planned and delivered
  • users of the portal have been supported
  • the program has been governed.

This part of the report sets out the ePlanning program's:

  • expected and reported financial benefits
  • calculation of financial benefits.

In 2019, the department increased its expectations for net financial benefits

The department's three ePlanning business cases each forecast substantial financial benefits from the implementation of the planning portal. The department expected that most financial benefits would flow to planning applicants due to a quicker and more consistent planning process. It also expected that government agencies and councils would benefit from the portal.

Exhibit 6: Summary of the financial benefits originally expected
  Business case 1
($ million)
Business case 2
($ million)
Business case 3
($ million)
Total
($ million)
Benefits 90.0 44.3 270.9 405.2
Costs 43.3 29.4 89.8 162.5
Net benefits 46.7 15.0 181.1 242.7

Note: Benefits and costs are incremental. All amounts are calculated over ten years. Amounts for business case 1, 2 and 3 amounts are expressed in 2013, 2015 and 2019 dollars respectively. All amounts are discounted at seven per cent to show their value at the time when they were calculated. Amounts may not add due to rounding.
Source: Audit Office analysis of data provided by the Department of Planning and Environment.

In 2019 the department commissioned a review to explore opportunities to better identify, monitor and realise the benefits of the ePlanning program. Using this work, the department updated the expected benefits for business cases 1 and 2 to take account of:

  • errors and miscalculations in the original benefits calculations
  • slower delivery of the portal and changes to the take-up of portal services by councils
  • changes to the services supported by the portal.
Exhibit 7: Summary of the financial benefits expected for business case 1 and 2 after the 2019 update
  Original business case 1 and 2 (combined)
($ million)
New business case 1 and 2 (combined)
($ million)
Benefits 134.3 210.6
Costs 72.7 96.3
Net benefits 61.7 114.3

Note: Benefits and costs are incremental. All amounts are calculated over ten years. Amounts for the original business case 1 and 2 are expressed in 2013 and 2015 dollars respectively. The new combined amount is expressed in 2019 dollars. All amounts are discounted or inflated at seven per cent to show their value at the time when they were calculated. Amounts may not add due to rounding.
Source: Audit Office analysis of data provided by the Department of Planning and Environment.

Reported benefits significantly exceed the current targets

In September 2021, the department reported that the program had achieved $334 million of benefits over the three financial years up to June 2021 plus the first two months of 2021–22. These reported benefits were significantly higher than expected. 

Exhibit 8: Reported financial benefits from the ePlanning program
  2018–19
($ million)
2019–20
($ million)
2020–21
($ million)
July to August 2021
($ million)
Total
($ million)
Benefits 5.2 68.8 214.7 45.1 333.8
Target 2.5 14.4 56.7 19.2 92.8
Amount and per cent above target 2.7
108%
54.4
378%
158
279%
25.9
135%
241
260%

Source: Audit Office analysis of data provided by the Department of Planning and Environment.

The department attributes the higher-than-expected financial benefits to the following:

  • benefit targets have not been updated to reflect the impact of the 2019 decision to mandate the use of the portal for all development applications. This decision brought forward the expected benefits as well as potential costs of the program. However, the department did not update its third business case which was draft at the time. The business case was subsequently approved in July 2020
  • one-off cost savings for agencies not having to develop their own systems
  • public exhibitions of planning proposals continuing to be available online during 2020 when some newspapers stopping printing due to COVID-19.

The calculation of benefits is overstated

The department reported $334 million of benefits in September 2021 due to the ePlanning program. This calculation is overstated because:

  • a proportion of reported benefits is likely to be due to other planning reforms
  • the calculation of the largest single benefit is incorrect
  • the reported benefits may not fully account for dis-benefits reported by some stakeholders.

The program’s benefits are calculated primarily from changes in planning performance data, such as the time it takes to determine a planning development application. The department currently attributes the benefits from shorter planning cycles entirely to the effect of the ePlanning program. However, planning cycles are impacted by many other factors such as the complexity of planning regulations and the availability of planning professionals. Planning cycles may also be impacted by other departmental initiatives which are designed to improve the time that it takes for a planning application to be evaluated. The Introduction describes some of these initiatives.

The largest contribution to the department’s September 2021 benefit report was an estimated saving of $151 million for developers due to lower costs associated with holding their investment for a shorter time. However, the department’s calculation of this benefit assumes a high baseline for the time to determine a development application. It also assumes that all development applications except for additions or alterations to existing properties will incur financing costs. However, a small but material number of these applications will be self-financed. The calculation also includes several data errors in spreadsheets.

The calculation of some benefits relies upon an extrapolation of the benefits experienced by a small number of early-adopter councils, including lower printing and scanning costs, fewer forms and quicker processing times. However, some councils report that their costs have increased following the introduction of the portal, primarily because aspects of the portal duplicate work that they carry out in their own systems. The portal has also required some councils to re-engineer aspects of their own systems, such as the integration of their planning systems with other council systems such as finance or property and rating systems. It has also required councils to create new ways of integrating council information systems with the planning portal.

The department has published information to help councils and certifiers to automatically integrate their systems with the planning portal. This approach uses application programming interfaces (or APIs) which are an industry-standard way for systems to share information. In April and May 2021, the government granted $4.8 million to 96 regional councils to assist with the cost of developing, implementing and maintaining APIs. The maximum amount of funding for each council was $50,000. The department is closely monitoring the implementation of APIs by councils and other portal users. Once they are fully implemented the department expects APIs to reduce costs incurred by stakeholders.

The department has not yet measured stakeholder costs. It was beyond the scope of this audit to validate these costs.

The department has not independently assured the calculation of reported benefits

In 2020 the department appointed an external provider to calculate the benefits achieved by the ePlanning program. The department advised that it chose to outsource the calculation of benefits because the provider had the required expertise and because it wanted an independent calculation of the benefits. The process involves:

  • extraction and verification of planning performance data by the department
  • population of data input sheets by the department
  • calculation of benefits by the external provider using the data input
  • confirmation by the department that the calculation includes all expected benefit sources.

The department does not have access to the benefits calculation model which is owned and operated by the external provider. The department trusts that the provider correctly calculates the benefits and does not verify the reported benefit numbers. However, as the benefits model involves many linked spreadsheets and approximately 300 individual data points, there is a risk that the calculation model contains errors beyond those discussed in this audit.

The reported benefits have only been calculated since 2019

The department originally intended to track benefits from October 2014. However, it only started to track benefits in 2019 when it appointed an external provider to calculate the benefits achieved by the portal. Any benefits or dis-benefits between the introduction of the portal and 2019 are unknown and not included in the department’s calculation of benefits.

Appendix one – Response from agency

Appendix two – About the audit

Appendix three – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #366 - released 21 June 2022

Published

Actions for Building regulation: combustible external cladding

Building regulation: combustible external cladding

Finance
Local Government
Planning
Compliance
Infrastructure
Regulation
Risk

What the report is about

The report focuses on how effectively the Department of Customer Service (DCS) and Department of Planning and Environment (DPE) led reforms addressing the unsafe use of combustible external cladding on existing residential and public buildings.

Nine local councils were included in the audit because they have responsibilities and powers needed to implement the NSW Government’s reforms.

What we found

After the June 2017 Grenfell Tower fire in London, the NSW Government committed to a ten-point action plan, which included establishing the NSW Cladding Taskforce, chaired by DCS, and with DPE as a key member. The Taskforce co-ordinates and oversees the implementation of the plan.

Depending on the original source of development approval, either individual local councils or DPE are responsible for ensuring that buildings are identified, assessed, and remediated. NSW Government-owned buildings are the responsibility of each department.

Identifying buildings potentially at risk was complex and resource intensive. However, on balance, it is likely that most affected buildings have now been identified.

By October 2021, around 40 per cent of assessed high-risk buildings that are the responsibility of local councils had either been remediated or found not to pose an unacceptable fire risk.

By February 2022, almost 50 per cent of affected NSW Government-owned buildings, and 90 per cent of buildings that are the responsibility of DPE, have either been cleared or are in the process of being remediated.

Earlier guidance on some key issues could have been provided by DCS and DPE in the two years after the Grenfell Tower fire. This may have reduced confusion and inconsistency across local councils we audited, and in some NSW Government departments. This especially relates to the application of the Fair Trading Commissioner's product use ban.

Given the inherent risks posed by combustible external cladding, buildings initially assessed as low-risk may also still warrant further action.

While most high-risk buildings have likely been identified, poor information handling makes it difficult to keep track of all buildings from identification, through to risk assessment and remediation.

What we recommended

DCS and DPE should:

  1. address the confusion surrounding the application of the Commissioner for Fair Trading's product use ban for aluminium composite panels with polyethylene content greater than 30 per cent
  2. develop an action plan to address buildings assessed as low-risk
  3. improve information systems to track all buildings from identification through to remediation.

Fast facts

Authority responsible for
ensuring that owners make
their buildings safe
Approximate number of
buildings referred for further
investigation*
Approximate percentage of
buildings remediated or
assessed to be safe
Local councils 1,200 40%
NSW Government owned 66 50%
DPE under delegation from
the Minister for Planning
137 90%
*After initial inspection by Fire and Rescue NSW, and/or preliminary inquiries by the consent authority, it was identified that the building may be at high-risk of
fire from combustible external cladding.

 

NSW Government's response to the risks posed by combustible external cladding

The NSW Government first became aware of the potential heightened risks posed by combustible external cladding on building exteriors after the 2014 Lacrosse Tower fire in Melbourne. However, it was the tragic loss of life from the Grenfell Tower fire in London, in June 2017, that gave added urgency to the need to address these risks.

Within six weeks of the London fire, the NSW Government committed to a ten-point plan of action for NSW to:

  • identify and remediate any buildings with combustible external cladding
  • ensure that regulation prevented the unsafe use of such cladding
  • ensure that experts involved in providing advice and certifying fire safety measures had the necessary skills and experience.

One of the actions in the ten-point plan was the creation of the NSW Government's Fire Safety and External Wall Cladding Taskforce (the Cladding Taskforce) chaired by the Department of Customer Service (DCS) and with the Department of Planning and Environment (DPE) as a key member.

The ten-point plan also specified that NSW Government departments would be responsible, in regard to buildings they owned to '…audit their buildings and determine if they have aluminium cladding'.

Local councils play a key role in implementing the Government's reforms, given their responsibilities and powers under the Environmental Planning and Assessment Act 1979 (EPA Act) and Local Government Act 1993 (Local Government Act) to approve building works (as 'consent authorities'), as well as to ensure fire safety standards are met. DPE plays an equivalent role for a smaller number of 'State Significant Developments' for which it is the consent authority under delegation from the Minister for Planning.

Commissioner for Fair Trading's building product use ban

On 18 December 2017, the Building Products (Safety) Act 2017 (BPS Act) came into effect in NSW, introducing new laws to prevent the use of unsafe building products. Notably, the BPS Act gave the Secretary of DCS and the Commissioner for Fair Trading the power to ban unsafe uses of building products.

After an extensive consultative process, the Commissioner for Fair Trading used these powers to issue a product use ban on 15 August 2018. This banned the use of external wall cladding of aluminium composite panels with a core comprised of more than 30 per cent polyethylene by mass on new buildings, unless the proposed use was subject to independent fire propagation testing of the specific product and method of application to a building in accordance with relevant Australian Standards.

Buildings occupied before the product use ban came into force are not automatically required to have the banned product removed. Under the BPS Act, consent authorities may determine necessary actions to eliminate or minimise the risk posed by the banned material on existing buildings.

Project Remediate

Project Remediate is a three-year NSW Government program announced in November 2020. The program was designed by the NSW Government to assist building owners of multi-storey apartments (two storeys or more) with high-risk combustible cladding to remediate their building to a high standard and for a fair price.

The scheme is voluntary and includes government paying for the interest on ten-year loans, as well as incorporating assurance and project management services to provide technical and practical support to owners’ corporations and strata managing agents. Building remediations under the program are expected to commence in 2022.

About this audit

This audit assessed whether DCS and DPE effectively led reforms to manage the fire safety risk of combustible external cladding on existing residential and public buildings.

In making this assessment, we considered whether the expressed policy intent of the NSW Government's ten-point plan for fire safety reform had been achieved by asking:

  • are the fire safety risks of combustible external cladding on existing buildings identified and remediated?
  • is there a comprehensive building product safety scheme that prevents the dangerous use of combustible external cladding products on existing buildings?
  • is fire safety certification for combustible external cladding on existing buildings carried out impartially, ethically and in the public interest by qualified experts?

Consistent with the focus of the Cladding Taskforce on multi-storey residential buildings and public buildings, the scope of our audit is limited to buildings categorised under the Building Code of Australia (BCA) as class 2, 3 and 9. These classes are defined in detail in section 1.2, but include: multi-unit residential apartments, hotels, motels, hostels, back-packers, and buildings of a public nature, including health care buildings, schools, and aged care buildings. The scope was also limited to existing buildings, which is defined as buildings occupied by 22 October 2018.

Auditees

The Department of Customer Service chairs the NSW Government's Cladding Taskforce, which is responsible for coordinating the combustible external cladding reforms. The Commissioner of Fair Trading sits within DCS and DCS regulates the industry accreditation scheme for fire safety practitioners, as well as administering the BPS Act.

The Department of Planning and Environment administers the EPA Act and the Environmental Planning and Assessment Regulation 2000 (EPA Regulation), which regulate the building development process. As well as being the delegated consent authority for State Significant Developments, DPE is also responsible for maintaining the mandatory cladding register requiring building owners of multi-storey (BCA class 2, 3 or 9) buildings to register buildings with combustible external cladding on an online portal.

Functions and responsibilities between DCS and DPE varied over time. For example, in October 2019, the DPE building policy team responsible for co-ordinating the DPE response to the combustible cladding issue was transferred to DCS, following changes to agency responsibilities resulting from machinery of government changes. DPE advised this resulted in a lessening of DPE's subsequent policy work on combustible cladding and its involvement in the Cladding Taskforce.

While the focus of the audit was on the oversight and coordination provided by DCS and DPE, nine councils were also auditees for this performance audit. Councils play an essential part as consent authorities for building development approvals in NSW, as well as having responsibilities and powers to ensure fire safety standards. To fully understand how well their activities were overseen and coordinated, a sample of councils was included as auditees.

Nine councils were selected to represent both metropolitan and regional areas, noting that there are very few in-scope buildings in rural areas. The audited councils were:

  • Bayside Council
  • City of Canterbury Bankstown Council
  • Cumberland City Council
  • Liverpool City Council
  • City of Newcastle Council
  • City of Parramatta Council
  • City of Ryde Council
  • City of Sydney Council
  • Wollongong City Council.

Terminology

The two NSW Government department auditees have, over time, been subject to machinery of government changes, which have changed some of their functions and what the departments are called.

Relevant to this audit, the effect of these changes has been:

  • the Department of Finance, Services, and Innovation (DFSI) became the Department of Customer Services (DCS) on 1 July 2019
  • on 1 July 2019, the Department of Planning and Environment became the Department of Planning, Industry, and Environment (DPIE)
  • on 21 December 2021, DPIE became the Department of Planning and Environment (DPE).

To avoid confusion, we use the titles by which these departments are known at the date of this report: the Department of Customer Service and the Department of Planning and Environment.

Conclusion

At July 2017, immediately after the Grenfell Tower fire, there was no reliable source to identify buildings that may have had combustible external cladding. However, it is now likely that most high-risk buildings have been identified.

Following the 2014 Lacrosse Tower fire in Melbourne, the NSW Government recognised that there was a need to be able to identify buildings in NSW that could have combustible external cladding.

The process of identifying buildings that could have combustible external cladding has been complex, resource-intensive, and inefficient principally due to the lack of centralised and coordinated building records in NSW. In total, approximately 1,200 BCA class 2, 3 and 9 buildings have been brought to the attention of councils by either Fire and Rescue NSW (FRNSW), the Cladding Taskforce, or through councils' own inspection for possible further action. In addition, approximately 2,000 more buildings were inspected by FRNSW but not referred to local councils because they either had no combustible external cladding or had combustible external cladding not assessed as being high-risk.

A multi-pronged approach to identifying buildings has been used by the DCS and DPE, through the Cladding Taskforce. While it is impossible to know the full scope of potentially affected buildings, the approach appears thorough in having identified most relevant buildings.

The process of clearing buildings with combustible external cladding has been inconsistent.

In the more than four years since the NSW Government's ten-point plan was announced, around 40 per cent of the buildings brought to the attention of councils have been cleared by either rectification or being found not to pose an unacceptable fire risk. Also, around 50 per cent of NSW Government-owned buildings identified with combustible external cladding and almost 90 per cent of identified buildings for which DPE is consent authority have been cleared or remediation is underway.

While DCS and DPE did seek to work cooperatively with councils and provided high-level guidance on the NSW Government’s fire safety reforms, it took until September 2019 before a model process and other detailed advice was provided to councils to encourage consistent processes. DCS and DPE advice to councils and NSW Government-building owners should have been more timely on two key issues:

  • the use of experts in the process of assessing and remediating existing buildings, and
  • the implementation of the product use ban on aluminium composite panels with polyethylene content 30 per cent or greater.

Clarifying the application of the product use ban may require consent authorities and building owners to revisit how some buildings have been cleared.

The management of buildings assessed as low-risk by FRNSW, estimated to be over 500, has not been a priority of the Cladding Taskforce to date, despite those buildings potentially posing unacceptable fire risks.

Information management by the Cladding Taskforce is inadequate to provide a high-level of assurance that all known affected buildings have been given proper attention.

While most high-risk buildings have likely been identified, information management is not sufficiently robust to reliably track all buildings through the process from identification, through to risk assessment and, where necessary, remediation.

Reforms to certifier registration schemes are limited to new buildings and do not apply to the existing buildings covered by this audit.

While reforms are limited in application to new buildings, some consent authorities took steps to obtain greater assurance on the quality of the work done by fire safety experts regarding combustible external cladding on existing buildings. For example, by requiring fire safety experts to be appropriately qualified and requiring peer review of cladding risk assessments and proposed remediation plans.

 

This chapter considers the part played by DCS and DPE as key members of the Cladding Taskforce in ensuring that buildings with combustible external cladding were effectively identified and remediated through processes implemented by:

  • local councils or DPE, where those bodies were consent authorities under the EPA Act for the relevant buildings
  • in the case of NSW Government buildings, the departments that owned those buildings.

This chapter considers what has been done to deliver a comprehensive building product safety scheme that prevents the dangerous use of combustible external cladding products.

 

This chapter considers whether reforms have ensured that only people with the necessary skills and experience are certifying buildings and signing off on fire-safety.

Inspections of existing buildings and development of any subsequent action plans to address combustible external cladding are not activities covered by accreditation or registration schemes for building certifiers

Almost all the risk assessment and remediation work done on buildings in the scope of this audit have been undertaken under fire safety orders issued by consent authorities using their powers under the EPA Act. This has been the recommended approach by DPE and DCS since at least 2016 (that is, before the Grenfell Tower fire in London).

While there have been reforms to certifier registrations scheme, these were not intended to ensure that combustible cladding-remediation on existing buildings is supported by people with the necessary skills and experience in fire safety under the fire safety order process. Instead, they are focused on offering better assurance for work done in respect to new building projects where accredited experts certify that building work is carried out in accordance with BCA under the DCS managed certifier registration schemes.

No steps have been taken to ensure the quality of the work done by experts inspecting, assessing the fire risk and developing action plans to address combustible external cladding on existing buildings, other than where consent authorities have chosen to exercise their discretion. This includes requiring fire safety experts to be appropriately qualified and requiring peer review of some cladding risk assessments and remediation plans.

Consent authorities determine whether individuals with accreditation are required for combustible cladding inspection, risk assessments and remediation on existing buildings

Whether an individual with certifier accreditation participates in a cladding inspection, risk assessment, or remediation for an existing building will be determined by what councils as consent authorities specify in their fire safety orders unless building owners opt to use such experts without being directed to do so by the consent authority.

As discussed earlier, councils acting as consent authorities vary in whether they require building owners to engage individuals with certifier accreditation. In most of the councils we audited, A1 or C10 accredited experts were either required, or recommended, to perform functions such as auditing suspected combustible cladding, or conducting fire safety risk assessments and developing plans to rectify combustible cladding.

However, these types of work are not functions covered by the accreditation or registration schemes that apply to building and development certifiers.

Certifier accreditation schemes do not cover cladding remediation work done under fire safety orders

While councils may require or recommend that independent accredited A1 or C10 certifiers be engaged by building owners for cladding risk assessment and remediation, they are not performing those functions as certifiers — they are, in effect, more akin to expert consultants. Accordingly, how they perform their functions and duties is not covered by the legislation supporting the accreditation scheme for certifiers that was operated until July 2020 by the Building Professional Board.

Instead, their use in this process is a convenient and practical way for consent authorities to ensure that building owners use appropriate experts who have the qualifications, skills and experience needed to investigate and identify combustible cladding, and then to formulate appropriate action to deal with such cladding. However, these individuals are not performing regulated or accredited work, are not subject to regulatory oversight, and are not accountable to any accreditation body for the quality of the work they perform.

While councils could (and sometimes do) choose to decline poor quality or incomplete cladding-related work prepared by A1 or C10 certifiers, the burden of resolving poor quality would fall on the building owner, who would have to seek amended or additional risk assessments or rectification plans.

In the absence of regulatory oversight, disincentives for poor quality cladding-related work, may include litigation being commenced by the property owner, harm to the expert's reputation in a small and competitive market, and the potential impact on whether the individual could retain their professional indemnity insurance at a reasonable cost (especially in an environment when many insurance providers withdrew coverage for cladding related work).

Reforms impact on regulated experts doing work on new buildings

The reforms that commenced on 1 July 2020, replaced categories of accreditation with classes of registration, and varied the classes such that:

  • accredited building surveyor category A1 became registered building surveyor-unrestricted
  • accredited certifier—fire safety engineer category C10 became registered certifiers-fire safety.

The legislation that introduced these reforms, the Building and Development Certifiers Act 2018, also repealed the pre-existing Building Professionals Act 2005 and abolished the Building Professionals Board. The new Act was accompanied by the Building and Development Certifiers Regulation 2020.

While the scope of this audit is limited to existing buildings, we note that there are buildings with combustible external cladding that are yet to be remediated. Just as these processes previously drew on the expertise of A1 and C10 category certifiers, it seems inevitable that the remediation of existing buildings will continue to draw on the expertise of the equivalent new classes of registered building surveyor-unrestricted and registered certifier-fire safety.

 

Appendix one – Response from agencies

Appendix two – About the audit

Appendix three – Performance auditing

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #364 - released 13 April 2022.

Published

Actions for Managing climate risks to assets and services

Managing climate risks to assets and services

Planning
Environment
Treasury
Industry
Infrastructure
Management and administration
Risk
Service delivery

What the report is about

This report assessed how effectively the Department of Planning, Industry and Environment (DPIE) and NSW Treasury have supported state agencies to manage climate risks to their assets and services.

Climate risks that can impact on state agencies' assets and services include flooding, bushfires, and extreme temperatures. Impacts can include damage to transport, communications and energy infrastructure, increases in hospital admissions, and making social housing or school buildings unsuitable.

NSW Treasury estimates these risks could have significant costs.

What we found

DPIE and NSW Treasury’s support to agencies to manage climate risks to their assets and services has been insufficient.

In 2021, key agencies with critical assets and services have not conducted climate risk assessments, and most lack adaptation plans.

DPIE has not delivered on the NSW Government commitment to develop a state-wide climate change adaptation action plan. This was to be complete in 2017.

There is also no adaptation strategy for the state. These have been released in all other Australian jurisdictions. The NSW Government’s draft strategic plan for its Climate Change Fund was also never finalised.

DPIE’s approach to developing climate projections is robust, but it hasn’t effectively educated agencies in how to use this information to assess climate risk.

NSW Treasury did not consistently apply dedicated resourcing to support agencies' climate risk management until late 2019.

In March 2021, DPIE and NSW Treasury released the Climate Risk Ready NSW Guide and Course. These are designed to improve support to agencies.

What we recommended

DPIE and NSW Treasury should, in partnership:

  • enhance the coordination of climate risk management across agencies
  • implement climate risk management across their clusters.

DPIE should:

  • update information and strengthen education to agencies, and monitor progress
  • review relevant land-use planning, development and building guidance
  • deliver a climate change adaptation action plan for the state.

NSW Treasury should:

  • strengthen climate risk-related guidance to agencies
  • coordinate guidance on resilience in infrastructure planning
  • review how climate risks have been assured in agencies’ asset management plans.

Fast facts

4 years

between commitments in the NSW Climate Change Policy Framework, and DPIE and NSW Treasury producing key supports to agencies for climate risk management.

$120bn

Value of physical assets held by nine NSW Government entities we examined that have not completed climate risk assessments.

Low capability to do climate risk assessment has been found across state agencies. The total value of NSW Government physical assets is $365 billion, as at 30 June 2020.

x3

NSW Treasury’s estimates of the annual fiscal and economic costs associated with natural disasters will triple by 2060–61.

According to the Intergovernmental Panel on Climate Change in 2021, each of the last four decades has been successively warmer and surface temperatures will continue to increase until at least the mid-century. The Commonwealth Scientific and Industrial Research Organisation (CSIRO) and the Bureau of Meteorology (BoM) have reported that extreme weather across Australia is more frequent and intense, and there have been longer-term changes to weather patterns. They also report sea levels are rising around Australia increasing the risk of inundation and damage to coastal infrastructure and communities.

According to the Department of Planning, Industry and Environment (the department), in New South Wales the impacts of a changing climate, and the risks associated with it, will be felt differently across regions, populations and economic sectors. The department's climate projections indicate the number of hot days will increase, rainfall will vary across the state, and the number of severe fire days will increase.

The NSW Government is a provider of essential services, such as health care, education and public transport. It also owns and manages around $365 billion in physical assets (as at June 2020). More than $180 billion of its assets are in major infrastructure such as roads and railway lines.

In NSW, climate risks that could directly impact on state agencies' assets and services include flooding, bushfires, and extreme temperatures. In recent years, natural hazards exacerbated by climate change have damaged and disrupted government transport, communications and energy infrastructure. As climate risks eventuate, they can also increase hospital admissions when people are affected by poorer air quality, and make social housing dwellings or schools unsafe and unusable during heatwaves. The physical impacts of a changing climate also have significant financial costs. Taking into account projected economic growth, NSW Treasury has estimated that the fiscal and economic costs associated with natural disasters due to climate change will more than triple per year by 2061.

The department and NSW Treasury advise that leading practice in climate risk management includes a process that explicitly identifies climate risks and integrates these into existing risk management, monitoring and reporting systems. This is in line with international risk management and climate adaptation standards. For agencies to manage the physical risks of climate change to their assets and services, leading practice identified by the department means that they need to:

  • use robust climate projection information to understand the potential climate impacts
  • undertake sound climate risk assessments, within an enterprise risk management framework
  • implement adaptation plans that reduce these risks, and harness opportunities.

Adaptation responses that could be planned for include: controlling development in flood-prone locations; ensuring demand for health services can be met during heatwaves; improving thermal comfort in schools to support student engagement; proactive asset maintenance to reduce disruption of essential services, and safeguarding infrastructure from more frequent and intense natural disasters.

According to NSW Treasury policy, agencies are individually responsible for risk management systems appropriate to their context. The department and NSW Treasury have key roles in ensuring that agencies are supported with robust information and timely, relevant guidance to help manage risks to assets and services effectively, especially for emerging risks that require coordinated responses, such as those posed by climate change.

This audit assessed whether the department and NSW Treasury are effectively supporting NSW Government agencies to manage climate risks to their assets and services. It focused on the management of physical risks to assets and services associated with climate change.

Conclusion

The Department of Planning, Industry and Environment (the department) has made climate projections available to agencies since 2014, but provided limited guidance to assist agencies to identify and manage climate risks. NSW Treasury first noted climate change as a contextual factor in its 2012 guidance on risk management. NSW Treasury only clarified requirements for agencies to integrate climate considerations into their risk management processes in December 2020.
The department has not delivered on a NSW Government commitment for a state-wide climate change adaptation action plan, which was meant to be completed in 2017. Currently many state agencies that own or manage assets and provide services do not have climate risk management in place.
Since 2019, the department and NSW Treasury have worked in partnership to develop a coordinated approach to supporting agencies to manage these risks. This includes guidance to agencies on climate risk assessment and adaptation planning published in 2021.
More work is needed to embed, sustain and lead effective climate risk management across the NSW public sector, especially for the state's critical infrastructure and essential services that may be exposed to climate change impacts.

The NSW Government set directions in the 2016 NSW Climate Change Policy Framework to 'manage the impact of climate change on its assets and services by embedding climate change considerations into asset and risk management’ and more broadly into 'government decision-making'.

The department released climate projections and has made information on projected climate change impacts available since 2014, but this has not been effectively communicated to agencies. The absence of a state-wide climate change adaptation action plan has limited the department's implementation of a coordinated, well-communicated program of support to agencies for their climate risk management.

NSW Treasury is responsible for managing the state's finances and providing stewardship to the public sector on financial and risk management, but it did not consistently apply dedicated resourcing to support agencies' climate risk management until late 2019. NSW Treasury estimates the financial costs of climate-related physical risks are significant and will continue to grow.

The partnership between the department and NSW Treasury has produced the 2021 Climate Risk Ready NSW Guide and Course, which aim to help agencies understand their exposure to climate risks and develop adaptation responses. The Guide maps out a process for climate risk assessment and adaptation planning and is referenced in NSW Treasury policy on internal audit and risk management. It is also referenced in NSW Treasury guidance to agencies on how to reflect the effects of climate-related matters in financial statements.

There is more work to be done by the department on maintaining robust, accessible climate information and educating agencies in its use. NSW Treasury will need to continue to update its policies, guidance and economic analyses with relevant climate considerations to support an informed, coordinated approach to managing physical climate risks to agencies' assets and services, and to the state's finances more broadly.

The effectiveness of the department and NSW Treasury's support involves the proactive and sustained take-up of climate risk management by state agencies. There is a key role for the department and NSW Treasury in monitoring this progress and its results.

Prior to 2021, support provided by the Department of Planning, Industry and Environment (the department) to agencies for managing physical climate risks to their assets and services has been limited. NSW Treasury has a stewardship role in public sector performance, including risk management, but has not had a defined role in working with the department on climate risk matters until mid-2019. The low capacity of agencies to undertake this work has been known to NSW Government through agency surveys by the department in 2015 and by the department and NSW Treasury in 2018.

The support delivered to agencies around climate risk management, including risk assessment and adaptation planning, has been slow to start and of limited impact. The department's capacity to implement a coordinated approach to supporting agencies has also been limited by the absence of a state-wide adaptation strategy and related action plan.

In 2021, products were released by the department and NSW Treasury with potential to improve support to agencies on climate risk assessment and adaption planning (that this, Climate Risk Ready NSW Guide and Course, which provides links to key NSW Treasury polices). The department and NSW Treasury are now leading work to develop a more coordinated approach to climate risk management for agencies' assets and services, and building the resilience of the state to climate risk more broadly.

Climate projections are a key means of understanding the potential impacts of climate change, which is an important step in the climate risk assessment process. The Department of Planning, Industry and Environment (the department) used a robust approach to develop its climate projections (NARCliM). The full version of NARCliM (v1.0) is based on 2007 models11 and while still relevant, this has limited its perceived usefulness and uptake. The process of updating these projections requires significant resourcing. The department has made recent updates to enhance the currency and usefulness of its climate projections. NARCliM (v2.0) should be available in 2022.

While climate projections have been available to agencies and the community more broadly since 2013–14, the department has not been effective in educating the relevant data users within agencies in how to use the information for climate risk assessments and adaptation planning.

The absence of a strategy focused on this is significant and has contributed to the current low levels of climate risk assessment uptake across agencies (see section 2). Agencies are required to use the climate projections developed by the department when developing long term plans and strategies as part of the NSW Government Common Planning Assumptions.


11 The department advises the 2007 global climate models were released to users by the Intergovernmental Panel on Climate Change in 2010.
It is too soon to determine the impact of the 2021 Climate Risk Ready NSW (CRR) Guide and Course, produced by the Department of Planning, Industry and Environment (the department) and NSW Treasury. But there are opportunities for these agencies to progress these developments in partnership: especially with the establishment of senior executive steering and oversight committees related to climate risk.

For the department, key opportunities to embed climate risk management include leveraging land use planning policies and guidance to drive adaptation, which has potential to better protect the state's assets and services. NSW Treasury has a role in continuing to update its policies, guidance and economic analyses with relevant climate change considerations to support an informed, coordinated approach to addressing physical climate risks to agencies' assets and services, and to the state's finances more broadly.

There is currently no plan on how the department and NSW Treasury intend to routinely monitor the progress of agencies with implementing the CRR Guide or developing climate risk 'maturity' more broadly. As agencies are responsible for implementing risk management systems that meet NSW Treasury standards, which now clearly includes consideration of climate risk (TPP20-08), establishing effective monitoring, reporting and accountability around this progress should be a priority for the department and NSW Treasury.

Appendix one – Response from agencies

Appendix two – Timeline of key activities 

Appendix three – About the audit 

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #355 - released (7 September 2021).

Published

Actions for Support for regional town water infrastructure

Support for regional town water infrastructure

Industry
Environment
Local Government
Infrastructure
Management and administration
Regulation
Risk

The Auditor-General for New South Wales, Margaret Crawford, released a report today examining whether the Department of Planning, Industry and Environment has effectively supported the planning for, and funding of, town water infrastructure in regional NSW.

The audit found that the department has not effectively supported or overseen town water infrastructure planning since at least 2014. It does not have a clear regulatory approach and lacks internal procedures and data to guide its support for local water utilities that service around 1.85 million people in regional NSW.

The audit also found that the department has not had a strategy in place to target investments in town water infrastructure to the areas of greatest priority. A state-wide plan is now in development.

The Auditor-General made seven recommendations to the department, aimed at improving the administration and transparency of its oversight, support and funding for town water infrastructure, and at strengthening its sector engagement and interagency coordination on town water planning issues and investments.

According to the Auditor-General, ‘A continued focus on coordinating town water planning, investments and sector engagement is needed for the department to more effectively support, plan for and fund town water infrastructure, and to work with local water utilities to help avoid future shortages of safe water in regional towns and cities.’ 

This report is part of a multi-volume series on the theme of water. Refer to ‘Water conservation in Greater Sydney’ and ‘Water management and regulation – undertaking in 2020-21’.

Read full report (PDF)

Safe and reliable water and sewer services are essential for community health and wellbeing, environmental protection, and economic productivity. In 2019, during intense drought, around ten regional New South Wales (NSW) cities or towns were close to ‘zero’ water and others had six to 12 months of supply. In some towns, water quality was declared unsafe.

Ensuring the right water and sewer infrastructure in regional NSW to deliver these services (known as 'town water infrastructure') involves a strategic, integrated approach to water management. The NSW Government committed to ‘secure long-term potable water supplies for towns and cities’ in 2011. In 2019, it reiterated a commitment to invest in water security by funding town water infrastructure projects.

The New South Wales’ Water Management Act 2000 (WM Act) aims to promote the sustainable, integrated and best practice management of the State’s water resources, and establishes the priority of town water for meeting critical human needs.

The Department of Planning, Industry and Environment (the department) is the lead agency for water resource policy, regulation and planning in NSW. It is also responsible for ensuring water management is consistent with the shared commitments of the Australian, State and Territory Governments under the National Water Initiative. This includes the provision of healthy, safe and reliable water supplies, and reporting on the performance of water utilities.

Ninety-two Local Water Utilities (LWUs) plan for, price and deliver town water services in regional NSW. Eighty-nine are operated by local councils under the New South Wales’ Local Government Act 1993, and other LWUs exercise their functions under the WM Act. The Minister for Water, Property and Housing is the responsible minister for water supply functions under both acts.

The department is the primary regulator of LWUs. NSW Health, the NSW Environment Protection Authority (EPA) and the Natural Access Resource Regulator (NRAR) also regulate aspects of LWUs' operations. The department’s legislative powers with respect to LWUs cover approving infrastructure developments and intervening where there are town water risks, or in emergencies. In this context, the department administers the Best Practice Management of Water Supply and Sewerage Guidelines (BPM Guidelines) to support its regulation and to assist LWUs to strategically plan and price their services, including their planning for town water infrastructure.

Under the BPM Guidelines, the department supports LWU’s town water infrastructure planning with the Integrated Water Cycle Management (IWCM) Checklist. The Checklist outlines steps for LWUs to prepare an IWCM strategy: a long-term planning document that sets out town water priorities, including infrastructure and non-infrastructure investments, water conservation and drought measures. The department's objective is to review and approve (i.e. give ‘concurrence to’) an IWCM strategy before the LWU implements it. In turn, these documents should provide the department with evidence of town water risks, issues and infrastructure priorities.

The department also assesses and co-funds LWU's town water infrastructure projects. In 2017, the department launched the $1 billion Safe and Secure Water Program to ensure town water infrastructure in regional NSW is secure and meets current health and environmental standards. The program was initially established under the Restart NSW Fund.

This audit examined whether the department has effectively supported the planning for and funding of town water infrastructure in regional NSW. It focused on the department’s activities since 2014. This audit follows a previous Audit Office of NSW report which found that the department had helped to promote better management practices in the LWU sector, up to 2012–13.

Conclusion

The Department of Planning, Industry and Environment has not effectively supported or overseen town water infrastructure planning in regional NSW since at least 2014. It has also lacked a strategic, evidence-based approach to target investments in town water infrastructure.

A continued focus on coordinating town water planning, investments and sector engagement is needed for the department to more effectively support, plan for and fund town water infrastructure, and work with Local Water Utilities to help avoid future shortages of safe water in regional towns and cities.

The department has had limited impact on facilitating Local Water Utilities’ (LWU) strategic town water planning. Its lack of internal procedures, records and data mean that the department cannot demonstrate it has effectively engaged, guided or supported the LWU sector in Integrated Water Cycle Management (IWCM) planning over the past six years. Today, less than ten per cent of the 92 LWUs have an IWCM strategy approved by the department.

The department did not design or implement a strategic approach for targeting town water infrastructure investment through its $1 billion Safe and Secure Water Program (SSWP). Most projects in the program were reviewed by a technical panel but there was limited evidence available about regional and local priorities to inform strategic project assessments. About a third of funded SSWP projects were recommended via various alternative processes that were not transparent. The department also lacks systems for integrated project monitoring and program evaluation to determine the contribution of its investments to improved town water outcomes for communities. The department has recently developed a risk-based framework to inform future town water infrastructure funding priorities.

The department does not have strategic water plans in place at state and regional levels: a key objective of these is to improve town water for regional communities. The department started a program of regional water planning in 2018, following the NSW Government’s commitment to this in 2014. It also started developing a state water strategy in 2020, as part of an integrated water planning framework to align local, regional and state priorities. One of 12 regional water strategies has been completed and the remaining strategies are being developed to an accelerated timeframe: this has limited the department’s engagement with some LWUs on town water risks and priorities.

Regional New South Wales (NSW) is home to about a third of the state's population. Infrastructure that provides safe and reliable water and sewer services (also known simply as 'town water infrastructure') is essential for community health and wellbeing, environmental protection, and economic productivity. Planning for and meeting these infrastructure needs, as well as identifying when non-infrastructure options may be a better solution, involves a strategic and integrated approach to water resource management in regional NSW.

We examined whether the department has effectively supported planning for town water infrastructure since 2014. This assessment was made in the context of its current approach to LWU sector regulation. The findings below focus on whether the department has an effective framework including governance arrangements for town water issues to inform state-wide strategic water planning, and whether (at the local level) the department has effectively overseen and facilitated town water infrastructure planning through its Integrated Water Cycle Management (IWCM) planning guidance to LWUs.

We examined whether the department has effectively targeted town water infrastructure funding to policy objectives, with a focus on the design and implementation of the Safe and Secure Water Program (SSWP) since its commencement in 2017. The program’s aim was to fund town water infrastructure projects that would deliver health, social and environmental benefits, and support economic growth and productivity. We also assessed the department’s capacity to demonstrate the outcomes of the SSWP funding and the contributions of its town water infrastructure investments more broadly. Finally, we identified risks to the effectiveness of the department’s work underway since 2018–19, which is intended to enhance its strategic water planning and approach to prioritising investments in reducing town water risks.

Appendix one – Response from agency

Appendix two – Key terms

Appendix three – About the audit

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #341 - released 24 September 2020

Published

Actions for Water conservation in Greater Sydney

Water conservation in Greater Sydney

Environment
Industry
Infrastructure
Internal controls and governance
Management and administration
Regulation
Risk

This report examines whether the Department of Planning, Industry and Environment, and Sydney Water have effectively progressed water conservation initiatives in Greater Sydney.

The report found that the department and Sydney Water have not effectively investigated, implemented or supported water conservation initiatives in Greater Sydney. The agencies have not met key requirements of the current Metropolitan Water Plan and Sydney Water has not met all its operating licence requirements for water conservation. There has been little policy or regulatory reform, little focus on identifying new options and investments, and limited planning and implementation of water conservation initiatives.

As a result, Greater Sydney's water supply may be less resilient to population growth and climate variability, including drought.

The Metropolitan Water Plan states that water conservation, including recycling water, makes the drinking water supply go further. The plan also states that increasing water conservation efforts may be cheaper than building new large-scale supply options and can delay the timing of investment in new supply infrastructure.

The Auditor-General recommends the department develop a clear policy and regulatory position on water conservation options, improve governance and funding for water conservation, and work with Sydney Water to assess the viability of water conservation initiatives. The report also recommends improvements to Sydney Water’s planning for and reporting on water conservation, including the transparency of this information.

This report is part of a multi-volume series on the theme of water. Refer to ‘Support for regional town water infrastructure’ and ‘Water management and regulation – undertaking in 2020-21’.

Read full report (PDF)

The current, 2017 Metropolitan Water Plan states that water conservation, including recycling water, makes the drinking water supply go further. The plan also states that increasing water conservation efforts may be cheaper than building new large-scale supply options and can delay the timing of investment in new supply infrastructure.

Water conservation refers to water recycling, leakage management and programs to enhance water efficiency. Water recycling refers to both harvesting stormwater for beneficial use and reusing wastewater.

This audit examined whether water conservation initiatives for the Greater Sydney Metropolitan area are effectively investigated, implemented and supported. We audited the Department of Planning, Industry and Environment (the Department) and the Sydney Water Corporation (Sydney Water), with a focus on activities since 2016.

The Department is responsible for the integrated and sustainable management of the state’s water resources under the Water Management Act 2000, which includes encouraging ‘best practice in the management and use of water’ as an objective. The Department is also responsible for strategic water policy and planning for Greater Sydney, including implementing the Metropolitan Water Plan.

Sydney Water is a state-owned corporation and the supplier of water, wastewater, recycled water and some stormwater services to more than five million people in Greater Sydney. It is regulated by an operating licence that is issued by the Governor on the recommendation of the Independent Pricing and Regulatory Tribunal (IPART). The Tribunal determines Sydney Water’s maximum prices, reviews its operating licence and monitors compliance. Sydney Water's operating licence and reporting manual set out requirements for its planning, implementing and reporting of water conservation.

From 2007 to 2012, the Climate Change Fund was a source of funds for water conservation activities to be undertaken by the Department and Sydney Water. The Climate Change Fund was established under the Energy and Utilities Administration Act 1987. Four of its six objectives relate to water savings. Water distributors such as Sydney Water can be issued with orders to contribute funds for water-related programs. The Fund is administered by the Department.

In 2016, Sydney Water developed a method for determining whether and how much to invest in water conservation. Known as the ‘Economic Level of Water Conservation’ (ELWC), the method identifies whether it costs less to implement a water conservation initiative than the value of the water saved, in which case the initiative should be implemented.

Conclusion

The Department and Sydney Water have not effectively investigated, implemented or supported water conservation initiatives in Greater Sydney.

The agencies have not met key requirements of the Metropolitan Water Plan and Sydney Water has not met all its operating licence requirements for water conservation. There has been little policy or regulatory reform, little focus on identifying new options and investments, and limited planning and implementation of water conservation initiatives.

As a result, Greater Sydney's water supply may be less resilient to population growth and climate variability, including drought.

The Department has not undertaken an annual assessment of Sydney Water’s level of investment in water conservation against water security risks and the capacity to respond when drought conditions return, as required by the Metropolitan Water Plan. It did not complete identified research and planning activities to support the plan, such as developing and using a framework for assessing the potential for water conservation initiatives for Greater Sydney, and developing a long-term strategy for water conservation and water recycling. It also did not finalise a monitoring, evaluation, reporting and improvement strategy to support the plan.

Sydney Water has been ineffective in driving water conservation initiatives, delivering detailed planning and resourcing for ongoing initiatives, and in increasing its investment in water conservation during drought. These were requirements of the Metropolitan Water Plan. Sydney Water's reporting on water conservation has not met all its operating licence requirements and lacked transparency with limited information on key aspects such as planning for leakage management, how the viability of potential initiatives were assessed, and how adopted initiatives are tracking.

The Department and Sydney Water did not put in place sufficient governance arrangements, including clarifying and agreeing responsibilities for key water conservation planning, delivery and reporting activities. There has also been limited collaboration, capacity building and community engagement to support water conservation, particularly outside times of drought.

Appendix one – Responses from agencies

Appendix two – About the audit

Appendix three – Glossary

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 