Refine search Expand filter

Reports

Published

Actions for Implementing Asset Management Reforms

Implementing Asset Management Reforms

Justice
Planning
Finance
Treasury
Asset valuation
Financial reporting
Infrastructure
Internal controls and governance
Management and administration
Project management

Hospitals, schools, public housing, roads, bridges, buses and trains are just some of the assets used by government in providing services to citizens.

The NSW Government’s asset base is impressive in size - with a value of around $167 billion and with government plans to spend around $8 billion acquiring or replacing assets in the current year. Another $2 billion is spent each year on maintenance.

Good asset management is very important to government; even a small efficiency gain in this area can provide significant returns. Good practice by those responsible for managing assets can improve reliability, extend asset life, save on maintenance costs and aid in identifying and disposing of unnecessary or non-performing assets.

Improving the NSW public sector’s approach to asset management has been on the reform agenda for at least a decade. Changes in practice have been accelerated more recently by integrating asset management policy with the budget process.

In this audit we examined NSW Treasury’s efforts to improve asset management practices in the public sector and the progress made by 3 agencies - the Department of Corrective Services, NSW Fire Brigades and the Powerhouse Museum - towards better managing their asset portfolios.

This report informs Parliament and the community on progress to date and what more needs to be done to ensure that agencies manage assets effectively and achieve best value.

 

Parliamentary reference - Report number #143 - released 12 October 2005

Published

Actions for In-year Monitoring of the State Budget

In-year Monitoring of the State Budget

Finance
Premier and Cabinet
Compliance
Financial reporting
Internal controls and governance
Management and administration

The annual Budget is one of the most important and visible statements about a government’s financial intentions.

Once a Budget is released, it is important to monitor variations from the projections it contains. This is done for two reasons -

  • first, to ensure that individual agencies are properly managing their budget allocations and that any genuine emerging need for additional funding is met.
  • second, to ensure that any changes to the State’s overall financial position are understood and corrective action is undertaken.

This audit dealt primarily with the second of these objectives.

Budget monitoring involves both agencies and Treasury working together to quickly identify factors that might impact the budget, to clearly understand the implications for their budget position and to take any remedial action needed.

Poor monitoring may reduce the confidence that stakeholders have in the government’s financial management. It may mean that government decisions made in- year or for the following budget (for example on tax measures or spending increases/savings) are based on an incorrect understanding of the State’s true financial position.

I hope that this Report provides some useful insights that will assist in better monitoring.

 

Parliamentary reference - Report number #141 - released 28 July 2005

Published

Actions for Planning for Sydney's Water Needs

Planning for Sydney's Water Needs

Planning
Environment
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Service delivery

Reliably supplying water to our State’s principal city, Sydney, is a major responsibility for the Government.

The community has been made keenly aware in recent years that inflows have been decreasing, and that Sydney has been using more water than is available. In April 2005 the water in Sydney’s storages dropped to 41.5 per cent of their capacity – the lowest level since the construction of Warragamba dam in 1960.

As Sydney continues to develop, it is expected that the demand for water will increase. The way that we use it will need to be sustainable, as it has a direct impact on our economy, our lifestyle and our environment.

In planning for the future the State’s water agencies face a range of uncertainties. But the task is vital.

This report informs Parliament and the community on the progress made - and what remains to be done - to ensure a reliable water supply for Sydney.

 

Parliamentary reference - Report number #135 - released 4 May 2005

Published

Actions for Follow-up of Performance Audit: Collecting Outstanding Fines and Penalties

Follow-up of Performance Audit: Collecting Outstanding Fines and Penalties

Finance
Internal controls and governance
Management and administration
Service delivery

Periodically we review the extent to which agencies have implemented the recommendations they accept from our earlier audits. This gives Parliament and the public an update on the extent of progress made.

In this follow-up audit, we examine changes following our April 2002 report on how well the State Debt Recovery Office (under the Office of State Revenue) was collecting outstanding fines and penalties.

 

Parliamentary reference - Report number #132 - released 17 March 2005

Published

Actions for Disposal of Sydney Harbour Foreshore Land

Disposal of Sydney Harbour Foreshore Land

Finance
Environment
Internal controls and governance
Management and administration

Our view is that decisions need to be made on a more strategic basis, if the Government’s aspirations for Sydney Harbour’s foreshores are to be met. At present there are high-level ‘aspirations’, but there is no overarching strategy or plan for Sydney Harbour that can guide individual decisions. Decision-making appears to be triggered when a proposal is made to dispose of a particular property. Decisions to dispose of, retain, or change the use of individual properties should be made in the context of a broader strategy, rather than on a case-by-case basis.

 

Parliamentary reference - Report number #119 - released 26 November 2003

Published

Actions for Complaints and Review Processes, and Provision of Industry Assistance

Complaints and Review Processes, and Provision of Industry Assistance

Justice
Industry
Management and administration

In response to the 1999 audit, both Offices focussed on improving the transparency and consistency of decisions. Both introduced client service standards and implemented systems to improve their management of complaints. In addition, the Office of the Protective Commissioner (OPC) introduced six monthly financial statements which are sent to clients or their carers. However, there are three recommendations from the 1999 audit that are not fully implemented although progress has been made in addressing the issues. These matters relate to establishing external appeal mechanisms and the review of OPC client fees.

 

Parliamentary reference - Report number #117 - released 24 September 2003

Published

Actions for Northside Storage Tunnel Project

Northside Storage Tunnel Project

Planning
Environment
Infrastructure
Internal controls and governance
Procurement
Project management
Service delivery

The Northside Storage Tunnel was the first major public sector construction project using an alliance approach. In our opinion, the outcome of the project suggests that an alliance approach, when applied to a suitable project and managed appropriately, can support positive project outcomes. And in many respects the Alliance worked well. There are, however, a number of issues that we believe need to be addressed for future alliances.

 

Parliamentary reference - Report number #113 - released 24 July 2003

Published

Actions for Implementing the Ovine Johne's Disease Program

Implementing the Ovine Johne's Disease Program

Industry
Internal controls and governance
Regulation
Service delivery
Shared services and collaboration

The implementation of the Ovine Johne's Disease (OJD) program in New South Wales has been prolonged and difficult. In our view, the OJD Program in New South Wales has experienced two major difficulties with its implementation: the lack of a strategic approach to program management, and an ill-defined governance structure. Both the NSW Government and industry need to be better organised and improve the planning, direction and co-ordination of the OJD Program and future programs.

 

Parliamentary reference - Report number #107 - released 26 February 2003

Published

Actions for Follow-up audits: Police response to calls for assistance, The levying and collection of Land Tax and Coordination of bushfire fighting activities

Follow-up audits: Police response to calls for assistance, The levying and collection of Land Tax and Coordination of bushfire fighting activities

Justice
Finance
Management and administration
Service delivery

The acceptance of audit recommendations by agencies in the current review was high and represented 96 per cent of the recommendations made. In addition, half of the recommendations in the 1998 audits have been adequately addressed and for over 70 per cent of recommendations there has been some measurable change in practices or performance.

But overall, most of these improvements have been incremental. And, for nearly one third of the recommendations, changes have not yet taken effect and there is a risk that the issue or problem contained in the original reports may persist. There is also a danger that current reporting arrangements may not provide Parliament sufficient assurance as to the extent accepted recommendations have been implemented and improvements have been achieved. 

To provide greater transparency and accountability, agencies, following a performance audit, should establish arrangements, such as an audit committee, to follow up on the progress of implementation of the recommendations and report on the progress of the implementation of recommendations in their annual report to Parliament.

 

Parliamentary reference - Report number #84 - released 21 June 2001

Published

Actions for Controlling and reducing pollution from industry

Controlling and reducing pollution from industry

Planning
Environment
Compliance
Management and administration
Regulation

The regulatory framework introduced under the Protection of the Environment Operations Act 1997, along with other initiatives progressively being implemented by the Environment Protection Authority (EPA), should enhance the overall effectiveness of environment protection in NSW. The Audit Office is of the opinion that the framework is consistent with best practice and once fully implemented, should contribute to the achievement of further improvements in the environmental performance of industry.

However while the legislative framework supports best practice in regulation and enforcement, there are a number of issues which limit the effectiveness of the reforms. Some of the problems, such as the quality of licences and the effectiveness of compliance activities, have been identified by the EPA and may be addressed through recent initiatives.

 