Actions for Handback of the M4 Tollway
Handback of the M4 Tollway
This audit focuses on the M4 handback. It looks at whether the road will be in good condition when the State gets it back, and whether it will cope with the extra traffic after the toll is removed. These are critical issues for taxpayers and motorists. Taxpayers don’t want to be responsible for a large repair bill and motorists don’t want to be stuck in traffic jams.
To ensure that future private sector partnerships (PPP) deal adequately with handback, we recommend that the Roads and Traffic Authority (RTA):
- ensure deeds spell out an appropriate inspection and testing program to determine repairs required to bring roads up to a satisfactory condition at handback (p.11)
- ensure deeds link condition standards and maintenance approaches to changing industry standards and approaches over the life of the PPP (p.11)
- consider including in deeds a requirement that operators provide a performance bond or similar security over the cost of handback repairs (p.11)
- review the lessons learnt from the M4 tollway handback and determine whether it should seek to negotiate changes to existing tollway deeds to better deal with handback, by June 2010 (p.11)
Parliamentary reference - Report number #193 - released 27 October 2009
Actions for Government Licensing Project
Government Licensing Project
The Government Licensing Project (GLP) is standardising and simplifying processes of agencies which issue licences. However, it is currently running over the original anticipated completion date, exceeding the original budget and expected to produce savings less than originally planned.
Parliamentary reference - Report number #192 - released 7 October 2009
Actions for Administering Domestic Waterfront Tenancies
Administering Domestic Waterfront Tenancies
The audit’s overall conclusion is that Lands and Maritime are broadly achieving outcomes consistent with the IPART report on administering domestic waterfront tenancies. But a lack of collaboration between the agencies is contributing to poor customer service. Inconsistencies with the IPART report recommendations and operational differences between the two agencies result in different rents and conditions for tenants in the two agencies. The differences are having a significant impact on customer service.
Parliamentary reference - Report number #191 - released 23 September 2009
Actions for Review of Eastern Distributor
Review of Eastern Distributor
Following a resolution of the Legislative Council, the Audit Office has undertaken a performance audit of the Eastern Distributor. For a number of reasons, The Audit Office is not in the position to determine “whether the proposed toll and concession period represents the best deal”. In part this is the result of time constraints which do not allow a careful analysis of many toll and concession options. Similarly, the audit does not answer “whether the current proposal represents the best environmental outcome”. But each of these issues (toll and concession and environmental consequences) is discussed in the audit report.
The Audit Office recommends that the Roads and Traffic Authority (RTA), for any further major project of this type, ensures that it establishes a process which allows all decision makers to have a thorough understanding of the reasonableness of the proponents’ offers and their implications for the State and for the public. The Audit Office also recommends that the RTA should at the outset consult with TCorp in respect of each major project put to tender.
Parliamentary reference - Report number #42 - released 31 July 1997
Actions for Immunisation in NSW
Immunisation in NSW
Improving immunisation levels has been a policy priority for NSW and Commonwealth governments since the early 1990s. Along with other States they are pursuing a range of initiatives aimed at reaching immunisation target levels above 95% by the year 2000. At such levels, the occurrence of vaccine preventable diseases is minimised and their spread prevented.
There is considerable support for this policy from the public, the medical profession and all levels of government. However, like much in public health, it depends for its success on effective cooperation between many participants, both nationally and locally, with competing demands on their time and resources.
Parliamentary reference - Report number #38 - released 12 June 1997