Refine search Expand filter

Reports

Published

Actions for Attracting, retaining and managing Nurses in hospitals

Attracting, retaining and managing Nurses in hospitals

Health
Internal controls and governance
Management and administration
Service delivery
Workforce and capability

The department has done well to attract and retain nurses. Between 2001-02 and 2005-06 the average number of nurses employed increased to 39,804 with the annual resignation rate falling from 16 to 14 per cent. Overall, the public health sector gained 5,588 nurses, representing an average annual increase of four per cent. Despite the gains, there are indicators that there may still not be enough nurses.

 

Parliamentary reference - Report number #162 - released 12 December 2006

Published

Actions for Helping older people access a residential aged care facility

Helping older people access a residential aged care facility

Health
Community Services
Compliance
Internal controls and governance
Management and administration
Risk
Service delivery
Shared services and collaboration
Workforce and capability

Assessment processes for older people needing to go to an Residential Aged Care Facility (RACF) vary depending on the processes of the Aged Care Assessement Teams (ACAT) they see and whether or not they are in hospital. The data collected on ACAT performance was significantly revised during 2004 making comparisons with subsequent years problematic. ACATs have more responsibilities than assessing older people for residential care. It is not clear whether they have sufficient resources for this additional workload.

 

Parliamentary reference - Report number #160 - released 5 December 2006

Published

Actions for Major infectious disease outbreaks: Readiness to response

Major infectious disease outbreaks: Readiness to response

Health
Internal controls and governance
Management and administration
Risk
Service delivery
Shared services and collaboration
Workforce and capability

NSW Health is working to increase its preparedness to respond to a major infectious disease outbreak. It is also contributing to the development of national policies, strategies and capabilities, which affect its level of preparedness. We found however little evidence that other jurisdictions were significantly further advanced than NSW in preparation and testing of plans for a pandemic. In our view NSW Health needs to balance the costs of over-preparedness and additional capacity that may never be used, against the very significant consequences of under-preparation. It needs to identify the desired level of preparedness for its Area Health Services, set measurable goals and identify key gaps between those goals and current capabilities. It needs to set clear plans for closing those gaps and then sustaining desired levels of preparedness.

 

Parliamentary reference - Report number #159 - released 22 November 2006

Published

Actions for Condition of State Roads

Condition of State Roads

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Service delivery

The Roads and Traffic Authority (RTA) has improved the overall surface condition of State Roads in the last decade. Country road surfaces are now generally much better. Ride quality has improved and cracking has been reduced. The RTA has also achieved a substantial reduction in the number of structurally deficient bridges over the same period. 

Despite a significant increase in the State’s contribution to maintenance since 1999-2000, the RTA has deferred road rebuilding projects. The RTA is rebuilding at less than half its long term target, and has not met this target at any time this decade. The RTA has not identified how it will address deferred rebuilding, although it advises it is developing a new road network management plan which will address this.

 

Parliamentary reference - Report number #157 - released 16 August 2006

Published

Actions for The Cross City Tunnel Project

The Cross City Tunnel Project

Transport
Treasury
Premier and Cabinet
Planning
Environment
Infrastructure
Management and administration
Procurement
Project management
Risk

In our opinion the Government’s ‘no net cost to government’ requirement was a legitimate (but not the only possible) basis for the tunnel bid process. The Government was entitled to decide that tunnel users meet the tunnel costs. Structuring the bid process on the basis of an upfront reimbursement of costs incurred (or to be incurred) by the Roads and Traffic Authority (RTA) was therefore appropriate.

In our opinion, however, the Government, Treasury and the RTA did not sufficiently consider the implications of an upfront payment involving more than simple project cost reimbursement (i.e. the ‘Business Consideration Fee’ component). In addition, the RTA was wrong to change the toll escalation factor late in 2002 to compensate the tunnel operator, Cross City Motorway Pty Ltd, for additional costs.

 

Parliamentary reference - Report number #152 - released 31 May 2006

Published

Actions for Fare evasion on public transport: Follow-up audit

Fare evasion on public transport: Follow-up audit

Transport
Finance
Management and administration

The overall level of fare evasion is now lower, and the revenue forgone much less, than in 2000. The estimation of fare evasion, detection of fare evasion and management of fare compliance by RailCorp, State Transit and Sydney Ferries has improved, although Sydney Ferries needs to improve further.

However, only one in four fines for fare evasion are paid within 12 months. This is worse than in 2000. And the number of frequent fare evaders has almost trebled. State Debt Recovery Office and the transport agencies need to develop new and improved strategies to reduce the level of fine default and to better manage frequent fare evaders.

 

Parliamentary reference - Report number #150 - released 26 April 2006

Published

Actions for Follow-up audits: Police response to calls for assistance, The levying and collection of Land Tax and Coordination of bushfire fighting activities

Follow-up audits: Police response to calls for assistance, The levying and collection of Land Tax and Coordination of bushfire fighting activities

Justice
Finance
Management and administration
Service delivery

The acceptance of audit recommendations by agencies in the current review was high and represented 96 per cent of the recommendations made. In addition, half of the recommendations in the 1998 audits have been adequately addressed and for over 70 per cent of recommendations there has been some measurable change in practices or performance.

But overall, most of these improvements have been incremental. And, for nearly one third of the recommendations, changes have not yet taken effect and there is a risk that the issue or problem contained in the original reports may persist. There is also a danger that current reporting arrangements may not provide Parliament sufficient assurance as to the extent accepted recommendations have been implemented and improvements have been achieved. 

To provide greater transparency and accountability, agencies, following a performance audit, should establish arrangements, such as an audit committee, to follow up on the progress of implementation of the recommendations and report on the progress of the implementation of recommendations in their annual report to Parliament.

 

Parliamentary reference - Report number #84 - released 21 June 2001

Published

Actions for Ambulance Service of NSW: Readiness to respond

Ambulance Service of NSW: Readiness to respond

Health
Internal controls and governance
Management and administration
Shared services and collaboration
Workforce and capability

This performance audit indicates that the Service has considerable work to do to reach its aspirations of being recognised amongst leading examples of best practice services. The commitment of the Service to serving the community and the professionalism of the Service's officers is not in question. It is, however, apparent that a number of barriers to performance will need to be overcome for the Service to perform as well as it would wish.

 

Parliamentary reference - Report number #80 - released 7 March 2001