Refine search Expand filter

Reports

Published

Actions for Rail freight and Greater Sydney

Rail freight and Greater Sydney

Transport
Information technology
Infrastructure
Management and administration
Project management
Service delivery

What the report is about

The movement of freight contributes $66 billion annually to the NSW economy. Two thirds of all freight in NSW moves through Greater Sydney, and the volume of freight moving through Greater Sydney is expected to increase by 48 per cent by 2036.

This audit assessed the effectiveness of transport agencies in improving the use of rail freight capacity in Greater Sydney, and to meet current and future freight demand.

What we found

Transport agencies do not have strategies or targets in place to improve the efficiency or capacity of the metropolitan shared rail network for freight.

The transport agencies acknowledge that they do not have sufficient information to achieve the most efficient freight outcomes and they do not know how to use the shared rail network to maximise freight capacity without compromising passenger rail services.

The Freight and Ports Plan 2018-2023 contains one target for rail freight - to increase the use of rail at Port Botany to 28 per cent by 2021. However, Transport for NSW (TfNSW)'s data indicates this target will not be met.

Sydney Trains records data on train movements and collects some data on delays and incidents. TfNSW collects data for the construction of the Standard Working Timetable and third-party contracts.

However, a lack of clarity around what data is gathered and who has ownership of the data makes data sharing difficult and limits its analysis and reporting.

The Freight and Ports Plan 2018-2023 includes the goal of 'Reducing avoidable rail freight delays', but the transport agencies do not have any definition for an avoidable delay and, as a result, do not measure or report them.

TfNSW and Sydney Trains are appointed to manage and deliver the Transport Asset Holding Entity of New South Wales (TAHE)'s obligations to allow rail freight operators to use the shared rail network. There are no performance measures in rail freight operator contracts or inter-agency agreements. This limits transport agencies' ability to improve performance.

TfNSW’s Freight Branch is working on four freight-specific strategies; a review of the Plan, a freight rail strategy, a port efficiency strategy and a freight data strategy.

TfNSW has not yet determined the timeframes or intended outcomes of these strategies.

What we recommended

Transport agencies should:

  • commit, as part of the review of Future Transport 2056, to delivering the freight-specific strategies currently in development and develop whole-of-cluster accountability for this work including timeframes, specific targets and clear roles and responsibilities 
  • improve the collection and sharing of freight data
  • develop a plan to reduce avoidable freight delays
  • systematically collect data on the management of all delays involving and/or impacting rail-freight
  • develop and implement key performance indicators for the agreements between the transport agencies.

Fast facts    

  • 288 million tonnes of freight volume predicted to pass through Greater Sydney in 2036, up from 194 million in 2016 (an increase of 48%)

  • 54 trucks that can be replaced by one 600 m long port shuttle freight train    

  • 26,671 freight trains that passed through the metropolitan shared rail network between 1 July 2020 and 30 June 2021

The movement of freight contributes $66.0 billion annually to the New South Wales economy — or 13 per cent of the Gross State Product. Two thirds of all freight in New South Wales moves through Greater Sydney, and the volume of freight moving through Greater Sydney is expected to increase by 48 per cent by 2036. This increasing demand is driven by increasing population and economic growth.

The sequence of activities required to move goods from their point of origin to the eventual consumer (the supply chain) is what matters most to shippers and consumers. Road can provide a single-mode door-to-door service, whereas conveying goods by rail typically involves moving freight onto road at some point. In Greater Sydney, 80 per cent of all freight is moved on road. Freight often passes through intermodal terminals (IMTs) as it transitions from one mode of transport to the next.

In 2016, Transport for NSW (TfNSW) released Future Transport 2056 - the NSW Government's 40-year vision for transport in New South Wales, which is intended to guide investment over the longer term. In Future Transport 2056, TfNSW noted that New South Wales will struggle to meet increasing demand for freight movements unless rail plays a larger role in the movement of freight.

Sydney Trains manages the metropolitan shared rail network, which is made up of rail lines that are used by both passenger and freight trains. The Transport Administration Act 1988 requires that, for the purposes of network control and timetabling, NSW Government transport agencies give ‘reasonable priority’ to passenger trains on shared lines. As the Greater Sydney population and rail patronage continue to grow, so too will competition for access to the shared rail network. See Appendix two for details of the area encompassed by Greater Sydney.

Freight operators can also use dedicated rail freight lines operated by the Australian Rail Track Corporation (ARTC - an Australian Government statutory-owned corporation). As the metropolitan shared rail network connects with dedicated freight lines, freight operators often use both to complete a journey.

TfNSW, Sydney Trains and the Transport Asset Holding Entity (TAHE) work in conjunction with other rail infrastructure owners and private sector entities, including port operators, privately operated IMTs and freight-shipping companies. TfNSW and Sydney Trains are responsible for managing the movement of freight across the metropolitan shared rail network. TAHE is the owner of the rail infrastructure that makes up the metropolitan shared rail network. The NSW Government established TAHE, a NSW Government state-owned corporation, on 1 July 2020 to replace the former rail infrastructure owner - RailCorp. The Auditor-General for New South Wales has commenced a performance audit on TAHE which is expected to table in 2022.

On 1 July 2021, TAHE entered into new agreements with TfNSW and Sydney Trains to operate, manage and maintain the metropolitan shared rail network. Until 30 June 2021, and in accordance with TAHE's Implementation Deed, TAHE operated under the terms of RailCorp's existing arrangements and agreements.

This audit assessed the effectiveness of TfNSW, Sydney Trains and TAHE in improving the use of rail freight capacity in Greater Sydney, and to meet current and future freight demand.

The audit focused on:

  • the monitoring of access to shared rail lines
  • the management of avoidable delays of rail freight movements
  • steps to increase the use of rail freight capacity in Greater Sydney.

Conclusion

Transport agencies do not have clear strategies or targets in place to improve the freight efficiency or capacity of the metropolitan shared rail network. They also do not know how to make best use the rail network to achieve the efficient use of its rail freight capacity. These factors expose the risk that rail freight capacity will not meet anticipated increases in freight demand.

Future Transport 2056 notes that opportunities exist to shift more freight onto rail, and that making this change remains an important priority for the NSW Government. However, the transport agencies acknowledge that they do not have sufficient information to achieve the most efficient freight outcomes. In particular, transport agencies do not know how to use the shared rail network in a way that maximises freight capacity without compromising passenger rail services.

Neither Future Transport 2056 nor the Freight and Ports Plan 2018–2023 give any guidance on how transport agencies will improve the efficiency or capacity of the shared rail network. Other than a target for rail freight movements to and from Port Botany, which TfNSW's data indicates will not be met, there are no targets for improving rail freight capacity across the shared network. The lack of specific strategies, objectives and targets reduces accountability and makes it difficult for transport agencies to effectively improve the use of rail freight capacity in line with their commitment to do so.

Sydney Trains and Transport for NSW do not effectively use data to improve rail freight performance and capacity.

To drive performance improvement when planning for the future, transport agencies need good quality data on freight management and movements. Sydney Trains records data on train movements in real-time and collects some data on delays and incidents. TfNSW collects data for the construction of the Standard Working Timetable (SWTT) and third-party contracts. However, the different types of data gathered and the separation between the teams responsible mean that there is a lack of clarity around what data is gathered and who has ownership it. This lack of coordination prevents best use of the data to develop a single picture of how well the network is operating or how performance could be improved.

Sydney Trains' ability to evaluate the effectiveness of its incident and delay mitigation strategies is also limited by a lack of information on its management of rail-freight related delays or incidents. While Sydney Trains collects data on major incidents, it can only use this to conduct event-specific analysis on the causes of an incident, and to review the operational and management response. The use of complete and accurate incident data would assist to define, identify and reduce avoidable delays. Reducing avoidable delays is a goal of the Freight and Ports Plan 2018–2023. More complete data on all incidents would help TfNSW to have more effective performance discussions with rail freight operators to help improve performance.

TfNSW has started developing strategies to identify how it can use rail freight capacity to achieve efficient freight outcomes, but it has not committed to implementation timeframes for this work.

TfNSW’s Freight Branch has started work on four freight-specific strategies to improve freight efficiency: a review of the Plan, a freight rail strategy, a port efficiency strategy and a freight data strategy. However, none of these strategies will be fully developed before the end of 2022. TfNSW has not yet determined the implementation timeframes or intended outcomes of these strategies, although TfNSW reports that it is taking an iterative approach and some recommendations and initiatives will be developed during 2022. 

Appendix one - Response from agencies

Appendix two - The Greater Sydney region

Appendix three - TfNSW strategic projects 

Appendix four - Sydney Trains path priority principles 

Appendix five - Sydney Trains delay management

Appendix six - About the audit 

Appendix seven - Performance auditing
 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #357 - released (19 October 2021).

Published

Actions for WestConnex: changes since 2014

WestConnex: changes since 2014

Transport
Compliance
Infrastructure
Internal controls and governance
Management and administration
Project management
Risk

What the report is about

The report examined whether Transport for NSW (TfNSW) and Infrastructure NSW (INSW) effectively assessed and justified major scope changes to the WestConnex project since 2014.

What we found

NSW Government decisions to fund WestConnex-related projects outside WestConnex's $16.812 billion budget have reduced transparency and understate the full cost of WestConnex.

The NSW Government's decision to separate Sydney Gateway from WestConnex has reduced transparency over the cost of the road component of Sydney Gateway. $1.76 billion of the cost to complete Sydney Gateway is funded outside the WestConnex budget.

Network integration costs, currently estimated at $2.3 billion, are also funded outside the WestConnex budget. Many of these costs are directly attributable to WestConnex and ought to be included in the reported budget.

The Parramatta Road Urban Amenity Improvement Program, costing $198 million, should also be included as part of the WestConnex reported budget.

Decisions to exclude or remove these elements from WestConnex without justification have seen $4.26 billion of projects funded outside the $16.8 billion budget.

Positively, robust analysis was used to develop and incorporate design improvements into the 2015 WestConnex Updated Strategic Business Case.

The separate components of WestConnex underwent all required assurance reviews. However, the NSW Government's assurance framework does not require ongoing ‘whole-of-program’ assurance for large and complex projects like WestConnex. The absence of a holistic review of WestConnex allows for some costs and benefits to avoid scrutiny.

What we recommended

TfNSW should:

  • review the impact of scope changes on project objectives, costs and benefits for complex infrastructure projects
  • ensure that estimated costs and benefits of works which are reasonably required to meet consent conditions are included in business cases for complex large infrastructure projects
  • establish centralised and project specific record keeping for major infrastructure projects.

Infrastructure NSW should provide transparent whole of program assurance on total costs and benefits when complex projects are split into sub-projects.

Government should consider enhancing public transparency of existing infrastructure assurance processes by requiring that large complex infrastructure programs undergo periodic review at a whole-of-program level.

Fast facts

  • $16.812b 2015 WestConnex business case budget
  • $2.3b current estimated cost of network integration works to enable WestConnex, funded outside the WestConnex budget
  • $1.76b cost to complete Sydney Gateway to enable WestConnex and also funded outside the WestConnex budget
  • $198m Parramatta Road Urban Amenity Improvement Program, originally part of WestConnex but now funded outside the WestConnex budget

WestConnex

WestConnex is a 33 km motorway network that will link the western and south‑western suburbs with the Sydney CBD and the Airport and Port Botany precinct. It will also connect with proposed future motorway links to the north shore, northern beaches, and southern Sydney. The project is being delivered in three stages, with completion scheduled for 2023.

When first conceived by Infrastructure NSW (INSW) in 2012, WestConnex was described as a single integrated concept. In August 2013, government approved a business case for an integrated concept of WestConnex, with an estimated cost of $14.881 billion (in nominal outturn costs). Transport for NSW (TfNSW) is the government agency (sponsor agency) accountable for the delivery of WestConnex in accordance with the business case. In August 2014, the NSW Government established the Sydney Motorway Corporation to fund, deliver and operate WestConnex.

In November 2015, the NSW Government publicly released an updated WestConnex business case with greater detail and design enhancements, which increased the estimated cost to $16.812 billion.

Subsequent to this update, further changes were made to the design, including realignment of the M4 to M5 Link connection to the Western Harbour Tunnel project, an expanded interchange at Rozelle, the deletion of the Camperdown Intersection, and the addition of the Iron Cove Link. The reported budget for WestConnex was not changed as a result of these design updates.

To fund WestConnex, Sydney Motorway Corporation consolidated a concessional loan of $2 billion from the Australian Government, private sector debt and equity funding from the State. The Australian Government also provided a $1.5 billion contribution to the State to partially fund construction of WestConnex.

In August 2018, the NSW Government sold 51 per cent of its stake in Sydney Motorway Corporation for $9.26 billion. At the time of writing, the NSW Government is in the process of selling its remaining 49 per cent stake of Sydney Motorway Corporation.

About this audit

In the course of delivering a complex major infrastructure project, it is reasonable to expect changes to the original design and scope. Changes may occur as the design moves from a high‑level concept to a detailed design for project delivery, as new risks or issues are identified, as demands change, or as other interdependent projects are approved. Changes can also occur in response to potential cost or delivery overruns which arise as a result of planning deficiencies. Where design and scope changes significantly change the project costs and/or expected benefits, the justification for these changes should be robust and transparent.

Following our 2014 performance audit, 'WestConnex: Assurance to the government', the NSW Government established the Infrastructure Investor Assurance Framework (IIAF) to improve accountability and transparency over major projects that are developed, procured, or delivered by government agencies. Under the framework, TfNSW, as project sponsor, is responsible for ensuring the WestConnex project meets all IIAF requirements. These include ensuring the project remains strategically aligned and viable, and benefits are on track. INSW is responsible for coordinating the assurance review process and reporting directly to NSW Cabinet on project delivery against time, budget and risks to project delivery.

The objective of this performance audit is to assess whether TfNSW and INSW effectively assessed and justified major scope changes to the WestConnex project since 2014.

 

Conclusion

Government decisions to separate WestConnex related projects and deliver them outside WestConnex's 2015 business case budget of $16.812 billion has understated the total cost of WestConnex achieving its objectives. The rationale for separating these elements from the WestConnex project scope has not been transparent. Together, these projects represent costs of $4.26 billion funded outside the $16.812 billion WestConnex budget.

Since 2015, the NSW Government has removed several projects from the scope described in the 2015 WestConnex business case, and funded them separately:
  • In mid‑2017, the Sydney Gateway became a separate project outside WestConnex. This project, estimated in 2015 to cost $800 million, now has an estimated cost of $2.56 billion. The project remains partly funded by an $800 million contribution from the $16.812 billion WestConnex budget, with $1.76 billion funded outside the WestConnex budget.
  • In late 2018, the Parramatta Road Urban Amenity Improvement Program became a separate project outside the 2015 WestConnex budget. This project was part of the 2015 WestConnex Business Case and is intended to create urban renewal opportunities around Paramatta Road. It is estimated to cost $198 million.

Work required to integrate WestConnex with existing roads ('network integration') was funded outside the $16.812 billion budget for the November 2015 WestConnex business case. TfNSW is obliged to deliver network integration works to meet the conditions of planning approval for WestConnex. As such, these costs should be included in the WestConnex budget. The current estimated cost of these network integration works is $2.3 billion.

The rationale to exclude or remove each of these elements from the WestConnex project scope has not been transparent, nor supported by robust analysis and justification. These elements are required for WestConnex to achieve its objectives. The additional project costs will also deliver additional benefits not included in the 2015 WestConnex business case. Removing them understates the total cost of achieving the objectives set out in the 2013 and 2015 WestConnex business cases.

WestConnex's complex financing arrangements further reduce transparency on costs.

Transparency over the total cost of WestConnex – including elements funded from other project budgets – is further limited by the project's complex financing arrangements.

Prior to 2018, the Audit Office provided assurance on costs borne and levied by Sydney Motorway Corporation and its controlled entities. Since the NSW Government sold its majority stake in WestConnex in August 2018, the Auditor‑General no longer has the mandate to provide this assurance. Considering this, and the lack of transparency on the cost of projects removed from the WestConnex project scope, there is no transparent or comprehensive view of the total cost to deliver WestConnex – nor of how these cost would be offset by the sale of the government's remaining stake.

There is no 'whole‑of‑program' assurance over the WestConnex program of works. This limits transparency and confidence that WestConnex will meet intended objectives within its budget.

After INSW conducted a gateway review of a draft of the 2015 WestConnex Business Case under the IIAF, the project was broken up into separate components to support staged delivery. Each of these projects, including the Sydney Gateway, as well as the Network Integration Program, underwent the required assurance reviews under the IIAF. INSW also provided monthly progress updates to government. These individual projects are, in themselves, significant in scale and complexity. Addressing them as discrete components for the purposes of the assurance review process is justified and there is no requirement under the IIAF to holistically review projects which together deliver final benefits of the WestConnex program. However, whole‑of‑program review would improve transparency over total costs and benefits.

In 2016, TfNSW revised the design of the M4‑M5 Link and Rozelle to address traffic and integration issues.

TfNSW identified that the concept designs used for the M4‑M5 Link and Rozelle Interchange in the 2015 WestConnex Business Case would not integrate well with surface roads, including the proposed Bays Precinct, and would result in increased traffic on Victoria Road and the ANZAC Bridge. Following a comprehensive review conducted in mid‑2016, TfNSW refined the design of the M4‑M5 Link and Rozelle Interchange to address these limitations without increasing the cost of delivery. TfNSW documented the rationale for the design changes, including how the changes improved on the original design to increase capacity, improve traffic conditions and create more open space.

1. Key findings

Government decisions to fund WestConnex related projects outside of WestConnex's $16.812 billion reported budget have reduced transparency over costs and understate the full cost of WestConnex

In 2015, the work required to integrate WestConnex with existing roads ('network integration') was funded as a separate project with an estimated cost of $1.534 billion outside the 2015 WestConnex budget of $16.812 billion. TfNSW then created the Network Integration Program to respond to the conditions of planning approval for WestConnex. The current estimated cost to deliver all network integration works is $2.3 billion.

Since the 2015 WestConnex Business Case, the NSW Government has removed several elements from the scope of WestConnex and funded them as separate projects, while keeping the published WestConnex budget at an estimated $16.812 billion. Projects removed include:

  • Sydney Gateway, currently costed at $2.56 billion (with an $800 million contribution from WestConnex)
  • Parramatta Road Urban Amenity Improvement Program, costed at $198 million in late 2018 and funded though new funding to the Greater Sydney Commission.

Together, these projects represent costs of $4.26 billion that are not included in the WestConnex budget, but are required for WestConnex to achieve the objectives of the 2013 and 2015 WestConnex Business Cases. The costs of these elements in supporting the objectives of WestConnex is not tracked centrally, and there is no single point of oversight over them. Exhibit 1 compares total WestConnex forecast costs (including related projects) between November 2015 and April 2021.

 

November 2015
($ million)

April 2021
($ million)
WestConnex
Stage 1
Stage 1A (M4 Widening) 497 517
Stage 1B (M4 East) 3,802 3,782
Total 4,299 4,299
Stage 2
King Georges Road Interchange 131 131
New M5 4,335 4,335
Sydney Gateway Contribution 800 800
Total 5,266 5,266
Stage 3
M4‑M5 Link and Rozelle Interchange 7,049 7,049
Urban renewal (Parramatta Road) 198 ‑‑
Urban renewal (Rozelle) ‑‑ 198
Total 7,247 7,247
Total reportable WestConnex 16,812 16,812

Exhibit 1: WestConnex and related projects forecast costs
  November 2015
($ million)
April 2021
($ million)
Related projects
Network integration 1,534 2,300
Urban renewal (Parramatta Road) ‑‑ 198
Sydney Gateway Road Component ‑‑ 1,760
Total 1,534 4,258

Source: AO research.

Many network integration costs are directly attributable to WestConnex and ought to be included in the reported budget for WestConnex

Prior to 2015, the scope of WestConnex included enabling works needed before or during construction, as well as funding for future works to address any adverse traffic outcomes created by WestConnex which become apparent after its opening. These works are also known as network integration works.

When government approved the 2015 WestConnex Business Case, it noted that the project would require $1.534 billion for network integration works to address the impacts of WestConnex on the road network. However, the WestConnex project budget of $16.812 billion did not include funding for network integration works. Instead, Roads and Maritime Services (RMS, now TfNSW) was to fund network integration through its normal budget allocation.

It is important to recognise these costs as part of the total WestConnex project cost because:

  • TfNSW created the Network Integration Program to respond to network traffic and transport elements of the planning conditions of approval for WestConnex granted by the then NSW Department of Planning and Environment under the Environment, Planning and Assessment Act 1979.
  • NSW Treasury guidelines for business cases note that accurate cost estimates include assessment of the financial impact of meeting the conditions of planning approval.
  • Travel time and vehicle operating cost benefits attributed to the WestConnex project in the 2015 WestConnex Business Case assume that some network integration works, then costed at $373 million, were in place.

Refer to Appendix two for more detail on network integration works.

Some of the projects in the WestConnex Network Integration Program provide community and place benefits, such as parklands and cycleways. These benefits have not been attributed to WestConnex. Additionally, some network integration works are likely to deliver additional traffic related benefits to WestConnex. As the Network Integration Program’s primary purpose is to meet the conditions of planning approval for WestConnex, TfNSW should attribute all the costs and benefits of the program to WestConnex.

To September 2021, the total funded cost of the Network Integration Program is approximately $2.077 billion. TfNSW estimates that it will need a further $222 million to complete all expected network integration works.

The NSW Government's decision to separate Sydney Gateway from WestConnex has reduced transparency and accountability for TfNSW's underestimation of the cost of the road component of Sydney Gateway

Sydney Gateway is a high‑capacity connection between the new St Peters Interchange and the Sydney Airport and Port Botany precinct. It includes a road and rail components. The road component was included in the scope of WestConnex in the 2015 WestConnex Business Case. The November 2015 design, which TfNSW costed at $800 million, involved separate roadways from the St Peters Interchange to the International terminal, and to the domestic terminals and Mascot airport precinct.

By October 2016, TfNSW was aware that the $800 million budget for Sydney Gateway was insufficient and revised the forecast cost for the road component to $1.8 billion. The original cost estimate did not sufficiently consider the cost of:

  • constructing a complex design adjacent to the airport precinct
  • obtaining access to land required for the project
  • managing environmental contamination.

On 9 August 2017, the then Minister for WestConnex announced that the Sydney Gateway project was not part of WestConnex.

The 2015 WestConnex Business Case notes that material changes to the WestConnex budget, funding, scope, or timeframe are subject to Cabinet approval processes. It states that, when seeking approval for material changes, the portfolio Minister will make a submission to the relevant Cabinet Committee. Changes in project scope required the approval of the then Cabinet Committee on Infrastructure and should have been endorsed by the WestConnex Interdepartmental Steering Committee.

TfNSW and the NSW Department of Premier and Cabinet (DPC) assert that there is no documentation to support the government’s decision to separate Sydney Gateway from the WestConnex Program, or the WestConnex Interdepartmental Steering Committee's endorsement of a submission to Cabinet seeking approval for the separation.

The established governance processes for major scope changes were not followed in this instance. The lack of transparency regarding government's decision to separate Sydney Gateway from WestConnex also reduces visibility of TfNSW's underestimation of the cost of delivering the road component of Sydney Gateway.

The November 2018 Final Business Case for Sydney Gateway, which was approved by the government, included an estimate of $2.45 billion (nominal outturn cost) for the road component. This estimate included an $800 million contribution from WestConnex. A more recent estimate (late 2020) for this project is $2.56 billion (nominal outturn cost).

The Parramatta Road Urban Amenity Improvement Program should be included as part of the WestConnex budget

A specific objective of the 2015 WestConnex Business Case was the creation of opportunities for urban renewal along and around Parramatta Road. The business case included an allocation of $198 million in the $16.812 billion WestConnex budget for the Parramatta Road Urban Amenity Improvement program, designed to implement aspects of the objective. In November 2018, the NSW Government removed the Parramatta Road Urban Amenity Improvement Program from the WestConnex program of works and reallocated the $198 million (inside the $16.812 billion WestConnex budget) for urban renewal works around the Rozelle Interchange. As part of this decision, government approved new funding of $198 million to the Greater Sydney Commission for the urban amenity program, outside the $16.812 billion WestConnex budget. This understates the cost of WestConnex meeting its objectives by $198 million.

There is no requirement for ongoing ‘whole‑of‑program’ assurance of the WestConnex program of works, including related projects

In August 2015, INSW conducted its first Gateway Review of WestConnex as a program consisting of composite projects. Following that review, TfNSW registered each of the components of WestConnex with INSW as individual projects, rather than keeping WestConnex registered as a program or mega‑project. This is not inconsistent with the IIAF and all WestConnex related projects, including Sydney Gateway and the Network Integration Program, have undergone independent assurance reviews as individual projects under the IIAF.

Once a program like WestConnex is broken down into its composite parts, there is no requirement for the sponsor agency (TfNSW) or INSW to provide independent assurance on the program as a whole until it is completed. This is then done as part of the Gateway review for benefits realisation, which examines whether project benefits are being measured and meet expectations. These individual projects are, in themselves, significant in scale and complexity. While addressing them as discrete components for the purposes of the assurance review process can be justified, the absence of strategic, holistic reviews of WestConnex allows for total costs and benefits to become opaque and avoid scrutiny. Programs of this scale require greater ongoing transparency on total costs and benefits in order to ensure confidence they will meet intended objectives within budget.

There is a lack of public transparency on the total costs and benefits of the WestConnex project

Prior to 2018, the Audit Office provided assurance on costs borne and levied by Sydney Motorway Corporation and its controlled entities. Since the NSW Government sold 51 per cent of its stake in WestConnex in August 2018, the Auditor‑General no longer has the mandate to provide this assurance. The Audit Office is also unable to provide any assurance regarding the performance of tolling concessions.

This means that the total costs of WestConnex, including those levied on road users through tolling, are not reported alongside the full cost of delivering the project. This information, and independent assurance over that information, would provide transparency and context to the outcome of government's sale of its interest in WestConnex.

To enhance the transparency of existing infrastructure assurance processes, government could consider requiring large and complex infrastructure programs to undergo periodic review at a whole‑of‑program level. This could take the form of annual reports to Parliament on the total costs and benefits of selected large and complex projects by the responsible agency. The reports could include an assessment of the cost to government and cost to the community of funding and financing. Independent assurance of the agency report would provide Parliament with greater confidence that infrastructure is delivered economically and providing value for money for the people of NSW.

The Australian National Audit Office provides similar assurance on selected Department of Defence acquisition projects as part of its annual Major Projects Report.

Design enhancements included in the 2015 WestConnex Updated Strategic Business Case were supported by robust analysis

The 2015 WestConnex Business Case contained more detail than the 2013 WestConnex business case. Design enhancements were made as a result of modelling analysis conducted over the two years since the 2013 business case. Enhancements included a full underground link between Kingsgrove and St Peters as part of the New M5 and re‑alignment of the M4‑M5 link tunnel (Stage 3) to include the Rozelle Interchange. The Rozelle Interchange will provide a direct connection to the Anzac Bridge and Victoria Road, and will enable a connection to the proposed Western Harbour Tunnel and Beaches Link. A map and description of these elements can be found at Exhibits 2 and 3 of this report.

In 2016, TfNSW revised the design of the M4‑M5 Link and Rozelle to address traffic and integration issues

As part of preparing the 2015 WestConnex Business Case, TfNSW prepared a Project Definition and Delivery Report (PDDR) for the M4‑M5 Link. This report describes the scope of the project, including a high‑level concept design. TfNSW identified limitations with the proposed design of the M4‑M5 in the PDDR, which it would need to address as the project moved to a detailed design stage. In particular, these limitations included:

  • poor integration with the Bays Precinct masterplan
  • traffic capacity constraints on Victoria Road and Anzac Bridge
  • construction complexity.

Following a comprehensive review in mid‑2016, TfNSW changed the design of the M4‑M5 Link and Rozelle Interchange to address these limitations. These changes included:

  • deletion of the Camperdown intersection to improve traffic conditions on Parramatta Road
  • a fully underground and larger Rozelle Interchange with 10‑hectare dedicated parklands
  • a toll‑free tunnel link from Iron Cove Bridge to Anzac Bridge
  • increasing the lanes in the dual tunnels from three to four each way.

TfNSW documented, but did not publish, the rationale for the design changes, including how the changes addressed the limitations of the previous design while providing increased community benefit through the creation of open space. TfNSW undertook cost comparison studies which estimated that these changes would have a neutral impact on the estimated project cost while achieving the same or improved benefits.

TfNSW's record‑keeping systems for large infrastructure investments negatively impact accountability and transparency

In response to our formal requests for relevant information, made during the conduct of this audit, TfNSW advised that complete and valid records of key decision‑making processes, analysis and advice were unavailable. Additionally, TfNSW often provided information that was incomplete or unverifiable (for instance, unsigned briefing notes). This is not consistent with accepted governance practices and does not comply with the requirements of the State Records Act 1998.

We also requested that TfNSW provide a list of relevant documents held by the Sydney Motorway Corporation (SMC). While TfNSW acknowledged that SMC may hold material relevant to the audit, TfNSW did not have a list or description of these documents. As SMC is now a majority privately held entity, both the Audit Office and TfNSW have limited power to require SMC to provide documentation.

The delivery timeframe for large and complex infrastructure projects such as WestConnex frequently exceeds five years, and some projects can take over a decade to deliver. These projects represent a significant investment of public resources and government agencies should expect independent review and assurance activities such as performance audits. The establishment of dedicated record keeping facilities for major infrastructure projects, such as data rooms, would improve transparency and accountability. This would ensure that the use of public resources is fully auditable in line with public expectations and the requirements of the Government Sector Finance Act 2018, the State Records Act 1998 and the Public Finance and Audit Act 1983.

2. Recommendations

By December 2021, TfNSW should:

1. review the impact of scope changes on project objectives, costs and benefits for complex infrastructure projects

2. when preparing business cases for complex large infrastructure projects, ensure that the estimated costs and benefits of works which are reasonably expected to meet consent conditions are included in the overall project cost and its benefits (as per Treasury guidelines)

3. establish and maintain centralised and project‑specific record keeping, including through dedicated project data rooms, to ensure major infrastructure projects can readily be subject to external oversight and assurance.

By June 2022, INSW should:

4. provide transparent whole‑of‑program assurance on total costs and benefits throughout the project life‑cycle when complex projects are split into sub‑projects.

By June 2022, NSW Government should:

5. consider enhancing the public transparency of existing infrastructure assurance processes by requiring that large complex infrastructure programs undergo periodic review at a whole‑of‑program level. This could take the form of reports to Parliament on the total costs and benefits on selected large and complex projects by the responsible agency, including cost to government and cost to community of funding and financing, as well as an accompanying independent assessment of the agency report.

Following our 2014 performance audit report 'WestConnex: Assurance to the government', the NSW Government established the Infrastructure Investor Assurance Framework (IIAF). INSW is responsible for the development, implementation and administration of the IIAF. The assurance framework involves gateway reviews, health checks, deep dive reviews, and project monitoring and reporting at various stages in the lifecycle of a project. The main aims of the IIAF are to help ensure major infrastructure projects are delivered on time and on budget, and to ensure that reports are regularly monitored by the Cabinet of the NSW Government. The IIAF gateway review process is compulsory for all significant investments and expenditure under the NSW Treasury Gateway Policy.

In accordance with the IIAF, INSW is responsible for the following:

  • providing a dedicated Assurance Team including Gateway Review Managers to coordinate Reviews
  • determining appropriate expert reviewers, and manages scheduling, commissioning and administration of Assurance Review reports. Infrastructure NSW is independent of the Expert Review Team
  • monitoring Tier 1 – High Profile/High Risk projects, Tier 2 and Tier 3 (if required) project performance through independent Assurance Reviews
  • providing independent analysis and advice on key risks and any corrective actions recommended for Tier 1 – High Profile/High Risk, Tier 2 and Tier 3 projects
  • escalating projects to Infrastructure Investor Assurance Committee (IIAC) and Cabinet where projects present ‘red flag issues’ and where corrective action is needed
  • working with delivery agencies to register all capital projects with an estimated cost greater than $10.0 million and ensures they are risk profiled and assigned a risk‑based project tier with an endorsed IIAF Project Registration report
  • preparing forward looking annual Cluster Assurance Plans
  • maintaining and continuously improves the IIAF process
  • reporting to the IIAC, Cabinet and Infrastructure NSW Board
  • regularly report to NSW Treasury on the performance of the IIAF.

In relation to WestConnex, TfNSW is the sponsor agency responsible for meeting relevant IIAF requirements, including:

  • registering and risk profiling projects
  • IIAF gateway, health check, and deep dive assurance reviews
  • regular reporting.

Under the IIAF, it is mandatory for all capital projects valued over $10.0 million to be registered with INSW. Capital projects can be registered either as a program (comprising of a group of related projects or activities) or as a project (which may or may not be part of a program).

According to the IIAF, programs tend to have a lifespan of several years and aim to deliver outcomes and benefits related to an organisation's strategic objectives. Projects tend to have a shorter lifespan, and deal with outputs. Projects can, however, be grouped under a single program if they are similar in nature or if they are aimed at collectively achieving a strategic objective. Complex projects can be delivered in multiple stages, under different contracts, and across different time periods.

The last assurance review of the entire WestConnex program of works as a whole was in 2015

INSW conducted the first IIAF gateway review of WestConnex in August 2015. TfNSW developed a draft WestConnex Updated Strategic Business Case to consolidate the latest analysis on WestConnex, and to confirm that the project remained fit for purpose, economically viable, and financially deliverable. The review followed a recommendation in our 2014 performance audit report that business cases be thoroughly revisited.

During September 2015, INSW conducted additional informal reviews to identify strategic risks associated with public release of the WestConnex business case. Subsequently, INSW gave the Premier of NSW its views on the draft business case, including the following points:

  • The $398 million budget for Sydney Gateway was insufficient to meet the benefits claimed in the business case for a ‘functional’ connection to Sydney Airport and Port Botany. INSW studies indicate a future‑proof solution would require a minimum spend of $755 million.
  • Enabling works for WestConnex estimated at $1.534 billion were excluded from the cost of WestConnex. Significant work remained for RMS to identify mitigation measures to address planning approvals and network performance issues.
  • Enabling works (a Southern Connector), an access ramp and surface road improvements within St Peters were excluded from the draft 2015 business case despite their inclusion in the WestConnex scope in the 2014–15 State Budget.
  • The overall cost of works not funded within the WestConnex budget ranged from $2.011 billion to $2.196 billion. This included the enabling works, access ramp and surface road improvements and the shortfall for Sydney Gateway.

All WestConnex related projects, including Sydney Gateway have undergone independent assurance reviews under the IIAF

Since INSW submitted the first WestConnex progress update report to Cabinet in June 2015, INSW has been reporting monthly on the different stages of the WestConnex Program, including Sydney Gateway, as the projects were registered with INSW as High‑Profile, High‑Risk projects. Separate reporting enabled INSW to report and review each stage with more detailed scrutiny, compared to the reporting and reviewing at a program level.

WestConnex Stage 2 (New M5) underwent both mandatory and non‑mandatory reviews at key points in the project lifecycle. Three mandatory gateway reviews – at Gate 2 (Final business case), Gate 3 (Readiness for market), and Gate 4 (Tender evaluation) – were conducted by TfNSW before the introduction of IIAF. Four non‑mandatory health check reviews and one non‑mandatory deep dive review were conducted after the introduction of the IIAF managed by INSW.

Similarly, WestConnex Stage 3 projects – M4‑M5 link, M4‑M5 Tunnels, and Rozelle Interchange – also underwent mandatory and non‑mandatory reviews at key points in their lifecycle under IIAF.

The M4‑M5 Link had two mandatory gateway reviews and one non‑mandatory health check review under IIAF. These reviews were conducted before Stage 3 was split into two stages, due to major design changes to the Rozelle Interchange and the M4‑M5 tunnels.

The M4‑M5 tunnels had two mandatory gateway reviews (at Gates 3 and 4), one non‑mandatory health check review, and one non‑mandatory deep dive review under IIAF.

Rozelle Interchange also underwent three mandatory gateway reviews at Gate 3 (part 1), Gate 3 (part 2), and Gate 4, two non‑mandatory health check reviews, and one non‑mandatory deep dive review under IIAF.

Since mid‑2017, the Sydney Gateway project has undergone required independent assurance reviews, as well as a number of optional assurance reviews

In November 2016, INSW conducted a mandatory Gate 1 gateway review on a strategic business case for the Sydney Gateway Project. TfNSW did not proceed with this business case. Following the separation of Sydney Gateway from WestConnex in mid‑2017, TfNSW developed a new business case for Sydney Gateway. It has undergone the required Gate 1, Gate 2, and Gate 3 gateway reviews, as well as two non‑mandatory health check reviews, and three non‑mandatory deep dive reviews under IIAF.

Network integration works have undergone all IIAF required assurance reviews

TfNSW completed a strategic business case for the Network Integration Program in August 2020, and INSW completed a gateway review in November 2020. This is despite network integration projects starting as early as 2015, with $645 million having been spent by June 2020. The strategic business case included a prioritisation process for completing remaining works in the program. Prior to November 2020, TfNSW registered individual network integration projects with INSW, and these projects have undergone gateway reviews where required.

The Network Integration Program strategic business case does not include Rozelle interchange network integration works ($353 million) and additional network integration works to settle a contractor claim adjacent to St Peters Interchange ($190 million). These were excluded from the business case on the basis they had already been approved by government, and as such were not subject to the prioritisation elements of the business case. TfNSW has not developed separate business cases for these works, although the scope of the St Peters Interchange works was developed through a negotiated process.

TfNSW did not prepare business cases for some network integration works which have commenced, including the $323 million Campbell Road/Euston Road works

Prior to its development of the August 2020 strategic business case, TfNSW did not prepare business cases for many network integration works that have commenced, and in some instances were completed, before 2019. Significantly, TfNSW did not prepare a business case for the Campbell Road/Euston Road works, which cost $323 million and have been completed.

In 2016, TfNSW’s Business Case Policy requires the creation of business cases for capital projects costing over $1.0 million. At the time of writing this report, TfNSW’s draft policy requires full business cases for capital projects costing $10.0 million or more.

There is no requirement for ongoing ‘whole‑of‑program’ assurance of the WestConnex program of works, including related projects

INSW conducted its first gateway review of WestConnex (as a program, which consisted of composite projects) in August 2015. Following that review, TfNSW registered each of the components of WestConnex with INSW as individual projects, rather than keeping WestConnex registered as a program or complex project. The IIAF allows this to occur.

Separate registration enabled INSW to report and review each stage with more scrutiny compared to whole‑of‑program level review.

Such an approach has merit, considering the individual stages (and components of these stages) are multi‑million dollar works in their own right. Each project has its own timing for gateway reviews at stages such as 'Readiness for Market' and 'Tender Evaluation'.

Once a program such as WestConnex is broken down into its composite parts, there is no requirement for the sponsor agency (TfNSW) or INSW to conduct independent assurance on the program of works as a whole until the whole program is completed as part of the Benefits Realisation (Gate 6) gateway review. The absence of strategic, holistic reviews of projects of the scale and complexity such as WestConnex during their delivery allows for total costs and benefits to become opaque and avoid scrutiny. Projects of this scale require greater ongoing transparency on total costs and benefits in order to ensure confidence they will meet intended objectives within budget.

INSW has advised us that it has prepared a proposal to expand its assurance function to include whole‑of‑program review of inter‑related infrastructure projects.

Appendix one – Responses from agencies

Appendix two – Network integration works

Appendix three – About the audit

Appendix four – Performance auditing

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #351 - released (17 June 2021).

Published

Actions for Acquisition of 4–6 Grand Avenue, Camellia

Acquisition of 4–6 Grand Avenue, Camellia

Transport
Asset valuation
Compliance
Fraud
Infrastructure
Internal controls and governance
Management and administration
Procurement
Risk

The Auditor-General for New South Wales, Margaret Crawford, has today released a report on Transport for NSW’s (TfNSW) acquisition of 4–6 Grand Avenue in Camellia.

This audit, which was requested on 17 November 2020 by the Hon. Andrew Constance MP, the Minister for Transport and Roads, examined:

  • whether TfNSW conducted an effective process to purchase 4–6 Grand Avenue, Camellia
  • whether TfNSW has effective processes and procedures to identify and acquire property required to deliver the NSW Government’s major infrastructure projects.

The audit found that TfNSW conducted an ineffective process when it purchased 4–6 Grand Avenue, Camellia. The audit also found that TfNSW’s internal policies and procedures to guide the transaction were, and continue to be, insufficient.

The Auditor-General has made seven recommendations to address the issues identified in the report.

On 17 November 2020, the Hon. Andrew Constance MP, the Minister for Transport and Roads, requested this audit under section 27B(3)(c) of the Public Finance and Audit Act 1983.

On 15 June 2016, Transport for New South Wales (TfNSW) acquired 6.3 hectares of land at 4–6 Grand Avenue, Camellia, by agreement from Grand 4 Investments Pty Ltd. Grand 4 Investments was a business entity established by the owners of Billbergia Pty Ltd, a property development and investment company.

TfNSW paid Grand 4 Investments $53.5 million and assumed liability for addressing environmental issues and contamination associated with the site. This took place seven months after the vendor acquired the land as part of a competitive Expression of Interest process, in which TfNSW also participated, for $38.15 million.

TfNSW is the NSW Government agency responsible for most major transport infrastructure projects in New South Wales. TfNSW acquired the Camellia site for use as a stabling and maintenance depot to support the Parramatta Light Rail (PLR) project.

Consistent with the minister’s request, this audit assessed:

  • whether TfNSW conducted an effective process to purchase 4–6 Grand Avenue, Camellia
  • whether TfNSW has effective processes and procedures to identify and acquire property required to deliver the NSW Government’s major infrastructure projects.

In considering the effectiveness of the processes for this purchase, the audit considered:

  • the requirements of the Land Acquisition (Just Terms Compensation) Act 1991 (the Act)
  • the application of sound processes to manage risk to the NSW Government and to achieve value for money
  • the application of disciplines associated with complex procurement, such as probity, in a NSW Government context.
The acquisition of the 4–6 Grand Avenue site in Camellia was consistent with a 2014 feasibility study for the PLR, but occurred before the completion of detailed project planning or an acquisition strategy.

TfNSW made two attempts to acquire the 4–6 Grand Avenue site in Camellia, and was successful on the second attempt. TfNSW recognised the risks associated with early acquisition and had high-level strategies in place should the site not be required.

The specific site had been identified in a feasibility study for the PLR commissioned by TfNSW in 2014 as one of several options in Camellia for a stabling and maintenance depot. However, TfNSW had not done any substantive analysis of the various options to identify a preferred location before the two opportunities to acquire 4–6 Grand Avenue were brought to TfNSW’s attention by the landowners (or their agents). On both occasions, TfNSW chose to actively pursue acquisition in advance of any such analysis.

The acquisition was also not informed by a Property Acquisition Strategy, which TfNSW policy recommends in order to guide the process and manage acquisition specific risks.

In 2015, TfNSW identified that it would require a stabling and maintenance depot in the Camellia area for the Parramatta Light Rail

In 2014, TfNSW commissioned an external engineering consultancy to undertake a feasibility design study for the Parramatta Light Rail - the Parramatta Transport Corridor Strategy Feasibility Design study (herein referred to as ‘the feasibility study’). In early 2015, TfNSW received the feasibility study, which was one of several key sources that informed the development of business cases for the PLR.

The feasibility study recommended that TfNSW should consolidate the maintenance and cleaning operations with overnight stabling facilities on one site. The study noted that the optimal location for any such site would be in close proximity to the proposed network, and noted that the site must have access to road connections to accommodate access for cars and trucks.

The study found that a centrally located stabling and maintenance facility would be required for all routes serving the Parramatta CBD, and that the Camellia industrial area was a preferred location for such a facility. The study noted that the Camellia area was contaminated.

The feasibility study notes that its conclusions were based on assumptions about the light rail system adopted and decisions made by the future operator of the system, who had not yet been selected or appointed.

TfNSW's decision to progress a potential acquisition in 2015 considered the risk that the site may not be required

TfNSW's FIC was responsible for making decisions on funding allocations at a whole of program level within TfNSW. FIC was also responsible for approving ‘high-risk/high-value’ variations to program budgets. Members of the FIC included:

  • Secretary of Transport for NSW
  • Deputy Secretary, Infrastructure and Services
  • Deputy Secretary, Freight, Strategy and Planning
  • Deputy Secretary, Customer Services
  • Deputy Secretary Finance and Investment
  • Deputy Secretary People and Corporate Services.

An April 2015 submission, from the then Deputy Director-General to the agency’s FIC, sought authorisation and funding approval to participate in an Expression of Interest sale process. It noted the risk that the project may not go ahead. The submission advised that:

By acquiring a strategic site now, it reduces the risk of having to pay an improved value or a value that may be subject to rapidly improving land values due to changes in land use and rezoning.

The property can be acquired for the project, held strategically and income generated by leasing the site as hardstand 1 space until the project requires the land for the Parramatta Light Rail project.

If the project does not proceed in the medium to longer term, the property can be sold at a premium to what has been paid today as property fundamentals improve.

This submission acknowledged the risks associated with environmental contamination and proposed that these risks would be managed by negotiating a contract where the remediation and associated expenses would be at the landowner’s cost. 

TfNSW assessed the 4–6 Grand Avenue site as one of several sites in Camellia that was a feasible location for a stabling and maintenance facility

The Departmental feasibility study assessed six potential sites for a stabling and maintenance facility, including 4–6 Grand Avenue, noting strengths and weaknesses of each site. A different site on Grand Avenue was assessed as the ‘base case’ option (1 Grand Avenue). The study’s comments on the 4–6 Grand Avenue site included the following:

With an area of approximately 63,000m2, this site has sufficient space for a depot with the required stabling yard and maintenance facilities. The location allows for good road access and LRT [light rail transit] access would be from Grand Avenue, which may require a road crossing or signalised intersection. The site has been used for general industrial uses; however the land has been cleared and is currently undergoing remediation 2. The site is not affected by flooding based on one in 100-year flood data.

In early 2015, once the opportunity to acquire 4–6 Grand Avenue emerged, TfNSW commissioned a specific feasibility study of the 4–6 Grand Avenue site. The feasibility studies clearly documented the existence of environmental contamination. In April 2015, the report concluded:

Given the limitations of this report and within the parameters that have been set it is concluded that from a spatial and geographic perspective the site at 6 Grand Avenue would be suitable as a stabling and maintenance depot for the Parramatta light rail project. There are few engineering and environmental constraints that would affect the feasibility level analysis of this site and all issues identified, within this desk study, are considered to be resolvable. However this being said there is a significant amount of work necessary to reach the final layout and definition of the stabling and maintenance depot. There are numerous items which require further consideration and conformation; planning approvals could impose restrictions on building heights, noise mitigation measures, light and visual impact requirements all of which can have significant impacts on the spatial requirements of any stabling and maintenance depot. 

The acquisition of 4–6 Grand Avenue was not informed by a Property Acquisition Strategy

For major projects, TfNSW typically requires the project team to complete a Property Acquisition Strategy, which is intended to guide both process as well as specific acquisition issues expected to be faced during the project. The Property Acquisition Strategy is not a mandated document but is a recommended tool to support property acquisition as part of major projects.

TfNSW did not have a Property Acquisition Strategy in place to guide the 2015 Expression of Interest process. On 6 November 2015, the then Project Director for the PLR project emailed the property team, noting a need to develop a Property Acquisition Strategy to close off the scoping design and preliminary business case.

In January 2016, TfNSW developed a draft Property Acquisition Strategy for the Parramatta Light Rail Project, although it was silent on the potential sites for the stabling and maintenance facility.

TfNSW focussed on 4–6 Grand Avenue because it was available and aligned to TfNSW's strategic interests

In early 2015, officials commenced monitoring the market for industrial real estate in the Camellia area and surrounds for possible sites for a stabling and maintenance facility.

In March 2015, then owner of the site, Akzo Nobel Pty Limited released the 4–6 Grand Avenue site through an Expression of Interest process managed by CBRE.

TfNSW’s then Deputy Director-General, Planning, sought approval from FIC to lodge an Expression of Interest up to $30.0 million. Approval was sought on the basis that it would ‘provide certainty for the Parramatta Light Rail project by allowing for a depot site in a suitable location and potentially avoid higher costs or longer timeframes associated with compulsory acquisition following completion of the project’s business case’. FIC approved the request at its meeting on 9 April 2015.

At this time, TfNSW had not conducted any analysis of financial or operational benefits and costs of the potential sites identified in earlier feasibility studies. TfNSW staff advised us that the decision to participate in the Expression of Interest process for 4–6 Grand Avenue was because it was available. There is no documentation substantiating this statement, which TfNSW staff provided verbally as part of this audit.

In November 2015, TfNSW was advised that it was unsuccessful in the Expression of Interest process and that Grand 4 Investments (a related entity of Billbergia) had purchased 4–6 Grand Avenue. TfNSW did not conduct any further analysis of alternative potential sites in Camellia between this date and commencing discussions with Grand 4 Investments in April 2016. In that time there had been some movement on other properties that were included in the feasibility study, including 37–39a Grand Avenue being under offer in September 2015.

In March 2016, TfNSW approached CBRE to organise a meeting with Grand 4 Investments. On 1 April 2016, TfNSW met with Grand 4 Investments.

TfNSW advises that a perceived benefit of the 4–6 Grand Avenue site was that it was not subject to other uses or leaseholds that would increase the cost of compulsory acquisition. Officers involved in the acquisition advised that other nominated sites in the feasibility study were subject to other uses or leaseholds. 


1  A hardstand space is a large, paved area to store cars, heavy vehicles and machinery.
2  Officers familiar with the acquisition could not confirm the nature of remediation being undertaken, but noted that the previous landowner had cleared buildings from the site, which may have been considered part of remediation.
TfNSW's independent valuation, which it commissioned and received after the acquisition, specifically excluded consideration of environmental contamination risk. As a result, TfNSW is exposed to the risk that the acquisition was not fully compliant with the Land Acquisition (Just Terms Compensation) Act 1991 (the Act) because it did not use an accurate estimate of market value during negotiations. That said, the acquisition of 4–6 Grand Avenue by agreement was consistent with preferred processes described in the Act.

TfNSW acquired the site from the landowner by agreement, and this is consistent with provisions in the Act. Obtaining approval for compulsory acquisition should negotiations for agreement break down is also consistent with the Act. That said, TfNSW did not at any time assess whether a compulsory acquisition could have resulted in acquisition at a lower cost than what was negotiated by agreement.

Despite the high risks associated with the acquisition, TfNSW did not commission a formal valuation in time to inform the negotiation and purchase. Instead, TfNSW relied on internal advice to estimate market value, but did not obtain a formal valuation from those advisors. For high-risk transactions, the greater expertise and arm's-length independence of an external specialist valuer should be preferred over an agency's own staff.

On 15 June 2016, the settlement date for the acquisition, TfNSW commissioned a formal independent valuation of the site. On 23 November 2016, TfNSW received the final formal valuation report. By not obtaining a formal independent valuation of the property in advance of acquisition to inform the acquisition value, TfNSW exposed itself to non-compliance with the Act by not establishing the market value as the basis for the acquisition price. TfNSW also breached its own internal policies.

TfNSW instructed the valuer to conduct its valuation within the following parameters:

  • Market valuation on an ‘as is’ basis – market value based on the methodology described in the Act. This approach valued the site at $25.0 million.
  • Market valuation on a speculative development basis – market value based on the financial value of the vendor's intended use of the site which, in this case, involved leasing the site for industrial use. This approach valued the site at $52.0 million, and TfNSW advised us this valuation supported the purchase price.
  • Disregard the impact of environmental contamination – TfNSW specifically instructed the independent valuer to disregard any known (or unknown) site contamination. As TfNSW knew of the significant environmental contamination affecting the site, this parameter resulted in a valuation that overstated the value of the site as it did not consider the cost of environmental remediation. The valuer applied this assumption for both market valuation approaches.

Additionally, as the independent valuer completed the valuation after the purchase was finalised, there is a risk that the valuation may have been influenced by the known purchase price.

TfNSW's failure to acquire a formal valuation and an assessment of the financial impact of environmental remediation before it purchased 4–6 Grand Avenue represents ineffective administration and governance.
TfNSW acquired the site at a time when there was demand and increasing prices for industrial property in the area. However, TfNSW did not effectively assess and manage the risks associated with the acquisition, and gaps in process led to increased risk. Briefings to decision-makers did not contain important information, and we found no evidence that gaps in advice were queried or explored by decision-makers.

TfNSW did not have plans or advice in place to assist in managing risk, such as:

  • a property acquisition plan
  • a comprehensive and up-to-date risk management plan
  • a negotiation strategy, or any authorisation limit or minimal acceptable position
  • an independent professional evaluation
  • external expert advice (with the exception of legal advice relating to the contract of sale).

TfNSW was aware of contamination issues affecting the land and had access to considerable information about the environmental conditions, such as site environmental audit reports and information on the NSW Environment Protection Authority's contaminated land register. However, TfNSW had not analysed specific technical information about the contamination and therefore was not aware of the risk implications and cost for remediation. Despite this, TfNSW changed its position from not accepting the risks and costs of contamination, to acquiring the site unconditionally. The basis for this decision is unclear and undocumented.

Briefing to senior leaders on the acquisition was silent on a number of important matters that would have been important for approvers to consider, including:

  • an explanation of the 40 per cent increase in purchase price between November 2015 and May 2016, and a 165 per cent increase from TfNSW’s offer in April 2015
  • the contamination risks associated with the site and an evidence-based estimate of potential costs to remediate the site
  • advice that an independent valuation had not been obtained, inconsistent with TfNSW policy.

Consideration of the acquisition by FIC was based on a summary business paper and was managed out-of-session, thereby removing the ability for comprehensive consideration of the acquisition proposal and its risks.

The probity management controls and assurances in place for the acquisition of the 4–6 Grand Avenue site were insufficient. These insufficiencies were exacerbated by the probity risk profile of the transaction.

The 4–6 Grand Avenue acquisition was a high-risk/high-value transaction, undertaken in a volatile property market in a short timeframe under pressure from Grand 4 Investments. TfNSW was engaging in a direct negotiation in advance of detailed planning for the acquisition, or the PLR as a whole. These circumstances contribute to heightened probity risk.

TfNSW did not establish a probity plan and sought no probity support throughout the acquisition. Also, with one exception, the staff involved in the acquisition did not complete conflict of interest declarations.

TfNSW was aware of the potential for probity or integrity issues with the transaction when it commissioned an internal audit in connection with the transaction in 2019. Internal discussions considered whether a misconduct investigation may be more appropriate, however no such investigation was undertaken.

TfNSW's insufficient probity practices, in addition to its failure to keep complete or comprehensive records of negotiations or decisions, reduce transparency of the process and its outcome and expose TfNSW to a greater risk of misconduct, corruption and maladministration.

At the time of the transaction, the TfNSW policy framework was not sufficiently risk-focussed and did not provide clarity on when officers ought to apply specific guidance or procedures. TfNSW's policies and procedures are more focussed on acquiring land to meet project needs and timeframes, and less on assuring value for money and managing risks.

At the time of its acquisition of 4–6 Grand Avenue, TfNSW had property acquisitions policies and procedures in place. Each of these were broadly sound in their content and intent. However, they lacked specificity on how or when to apply guidance, and when risk levels should elevate the importance of recommended guidance.

TfNSW's key guidance was principles based and relied on agency staff using their experience and expertise to apply guidance according to the circumstances of an individual transaction. This guidance was not duly applied in the acquisition of 4–6 Grand Avenue, Camellia. In addition, TfNSW does not have quality or control assurance to identify when TfNSW officers did not apply important policies or processes.

The primary focus of the TfNSW’s property acquisition guidance is to achieve vacant possession of land in a timeframe that meets the need of the relevant transport project. There is less specific focus on the need to meet the requirements of the NSW Government financial management framework.

Appendix one – Response from agency 

Appendix two – About the audit 

Appendix three – Performance auditing

 

Copyright Notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #349 - released (18 May 2021).

Published

Actions for Health 2020

Health 2020

Health
Compliance
Financial reporting
Infrastructure
Internal controls and governance
Service delivery

This report analyses the results of our audits of financial statements of the Health cluster for the year ended 30 June 2020. The table below summarises our key observations.

1. Financial reporting

Financial reporting

Unqualified financial audit opinions

The financial statements of NSW Health and its 25 controlled entities received unqualified opinions.

The number of corrected and uncorrected misstatements increased from the prior year. Misstatements related predominantly to the implementation of new accounting standards, asset revaluations and accounting for new revenue streams to cover the cost of HSW Health’s response to the COVID-19 pandemic.

Qualified compliance audit opinion

We issued a qualified audit opinion for the Ministry of Health’s Annual Prudential Compliance Statement for aged care facilities operated by NSW Health. We identified 18 instances of material non-compliance with the Fees and Payments Principles 2014 (No. 2) (the Principles) in 2019–20 (30 in 2018–19).

Financial performance

NSW Health received an additional $3.3 billion in funding to cover costs associated with its response to the COVID-19 pandemic.

The impacts of the COVID-19 pandemic on the cluster were significant for health entities and included changes to operations, increased revenues, expenditure, assets and liabilities. Cancellation of elective surgery and decreased emergency department presentations meant that despite the pandemic, activity levels at many health entities decreased. Health Pathology and HealthShare were notable exceptions.

In the period to the 30 June 2020, NSW Health reported that over 900,000 COVID-19 tests were conducted. Health Pathology conducted over 500,000 of these tests. Health Pathology's surge requirements were enhanced through arrangements with 13 private sector providers. HealthShare purchased $864.2 million of personal protective equipment.

Overall, NSW Health recorded an operating surplus of $3.1 billion in 2019–20, an increase of $2.0 billion from 2018–19. As in previous years, the surplus largely resulted from additional revenue received to fund capital projects including the construction of new facilities, upgrades and redevelopments. In 2019–20 additional Commonwealth and State funding for the purchase and stockpiling of personal protective equipment also contributed to the operating surplus.

Overtime payments The Ambulance Service of NSW’s (NSW Ambulance) reduced their overtime payments to $79.7 million in 2019–20 ($83.1 million in 2018–19). Overtime payments in 2019–20 included $6.8 million related to the response to the 2019–20 bushfire season. NSW Ambulance overtime payments represent 16.8 per cent of total overtime payments in the cluster.

2. Audit observations

Internal control deficiencies

We identified more internal control deficiencies in 2019–20. The number of repeat issues from prior years also remains high.

NSW Health addressed 18 out of the 25 information system control deficiencies during the year.

Several key agreements lacked formal documentation. This included agreements between the Ministry and health entities, between health entities and agencies in other clusters and between the Ministry and health departments in other jurisdictions.

Infrastructure delivery NSW Health had 44 ongoing major capital projects at 30 June 2020 with a total revised budget of $12.3 billion. The revised total budget of $12.3 billion is $2.0 billion more than the original budget. NSW Health revises budgets when it combines project stages.

This report provides parliament and other users of the Health cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

The impacts of the COVID-19 pandemic on the cluster were significant and included changes to the operations of the health entities and increased revenue, expenditure, assets and liabilities.

As a part of this year's audits of health entities, we have considered:

  • financial implications of the COVID-19 emergency at both health entity and cluster levels
  • changes to agencies' operating models
  • agencies' access to technology and the maturity of systems and controls to prevent unauthorised and fraudulent access to data.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

The response to the COVID-19 pandemic primarily impacted the financial reporting of NSW Health through:

  • additional revenue from the State government in the form of grants and stimulus payments
  • additional revenue from the Commonwealth government under the National Partnership Agreement for COVID-19 to cover part of the cost of responding to the COVID-19 pandemic
  • increased expenses, largely due to increased payments to private health operators to maintain their viability during the COVID-19 pandemic and later to assist with public patient elective surgery waitlists and increased cleaning costs
  • increased purchases of personal protective equipment.

Chapter one outlines the impacts of NSW Health’s response to the COVID-19 pandemic. This chapter outlines our other audit observations related to the financial reporting of agencies in the Health cluster for 2020.

Section highlights

  • Unqualified audit opinions were issued for all health entities’ financial statements, although more misstatements were identified than last year.
  • NSW Health recorded an operating surplus of $3.1 billion, an increase of $2.0 billion from 2018–19. This is largely due to additional capital grants for new facilities, upgrades and redevelopments and additional Commonwealth and State funding for the purchase of personal protective equipment.
  • NSW Health’s expenses increased by 5.5 per cent in 2019–20 (7.0 per cent in 2018–19) despite the impact of the COVID-19 pandemic. The primary causes for the growth in expenses are increases in:
    • employee related expenses due to higher employee numbers, increased overtime and a 2.5 per cent award increase
    • payments to private health operators to maintain their viability during the COVID-19 pandemic and later to assist with public patient elective surgery waitlists
    • payments to private health operators due to the first full year of operation of the Northern Beaches hospital.
  • The Ambulance Service of NSW (NSW Ambulance) continued to report higher overtime payments than other health entities. However, despite the response to the 2019–20 bushfire season, their overtime payments were lower than last year. NSW Ambulance paid $79.7 million in overtime payments in 2019–20 ($83.1 million in 2018–19).
  • A qualified audit opinion was issued for the Ministry of Health’s Annual Prudential Compliance Statement for aged care facilities operated by NSW Health. There were 18 instances of material non-compliance with the Fees and Payments Principles 2014 (No. 2) (the Principles) in 2019–20 (30 in 2018–19)

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

The primary impact of the COVID-19 pandemic on the effectiveness of the internal controls of NSW Health and health entities relates to the effectiveness of controls implemented by HealthShare relating to the stocktake of personal protective equipment inventories. Inventory managed by HealthShare increased by 2,746 per cent during 2019–20. HealthShare’s inventory controls did not maintain pace with the sudden, significant increase.

The impacts of NSW Health’s response to the COVID-19 pandemic are outlined in chapter one. This chapter outlines other observations and insights from our financial statement audits of agencies in the Health cluster.

Section highlights

  • The number of internal control deficiencies has increased since 2018–19. More than a third of control deficiencies are repeat issues.
  • Control deficiencies that relate to managing employees’ leave and employee’s time recording continue to be difficult for entities to resolve, particularly during the ongoing response to the COVID-19 pandemic.
  • Several key agreements were undocumented. These included agreements between the Ministry and the health entities, between health entities, and between the Ministry and entities in other clusters and jurisdictions. These related to:
    • a loan arrangement between the Ministry and HealthShare for $319 million.
    • Northern Sydney Local Health District's use of land and buildings owned by the Graythwaite Charitable Trust
    • agreements for the treatment of New South Wales residents while they are interstate, and interstate residents receiving treatment while they are in New South Wales from Queensland, Victoria, South Australia and the ACT for both 2019–20 and 2018–19.
  • NSW Health reported that they completed nine major capital projects during 2019–20. As at 30 June 2020 there were 44 ongoing major capital health projects in NSW. The revised capital budget for these projects in total was $2.0 billion more than the original budget of $10.3 billion. NSW Health reported the budget revisions are largely the result of combining project stages.

Appendix one – List of 2020 recommendations 

Appendix two – Status of 2019 recommendations 

Appendix three – Financial data

Appendix four – Analysis of financial indicators 

Appendix five – Analysis of performance against budget

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Auditor-General’s Report to Parliament

Health 2020

11 December 2020

This corrigendum has been prepared to amend the following text within the Auditor-General’s Report to Parliament on Health 2020, dated 10 December 2020.

NSW Health emergency department treatment times

On page five the original text was as follows:

NSW Health also measures the percentage of patients whose clinical care in emergency departments is completed within four hours. The measure is used as an indicator of accessibility to public hospital services.

NSW Health aims to complete clinical care in the emergency department for 81 per cent of patients within four hours. In 2019–20 NSW Health reports it completed clinical care within four hours for 72.1 per cent of patients (a 7.3 per cent decrease from 2018–19).

At Western Sydney Local Health District, 59 per cent of patients were treated within the targeted timeframe. NSW Health attribute this to the profile of patients presenting in emergency departments and additional time taken processing COVID-19 patients to ensure staff safety.

The original text has now been changed to:

NSW Health also measures the percentage of patients with total time in the emergency department of four hours or less for each local health district. The measure is used as an indicator of accessibility to public hospital services.

Local Health Districts Target % (2019–20) Actual % (2019–20)
Central Coast 77.0 59.9
Far West 90.2 86.6
Hunter New England 81.0 72.5
Illawarra Shoalhaven 79.0 60.2
Mid North Coast 82.0 76.7
Murrumbidgee 85.3 81.9
Nepean Blue Mountains 79.0 65.5
Northern NSW 81.0 78.2
Northern Sydney 79.0 73.9
South Eastern Sydney 78.0 70.3
South Western Sydney 78.0 61.2
Southern NSW 85.0 83.0
Sydney 76.0 70.9
Sydney Children’s Hospitals Network 80.0 72.1
Western NSW 85.9 81.0
Western Sydney 78.0 59.0
St Vincent's Health Network* 75.0 65.4
* St Vincent’s Health Network Sydney (SVHNS) comprises of St Vincent’s Hospital Sydney Limited as the affiliated health organisation in respect of four recognised establishments under the Health Services Act 1997 (NSW) (Health Services Act). Under the Health Services Act, St Vincent’s Hospital Sydney Limited, is treated as a Network for the purposes of the National Health Reform Agreement in respect of the three recognised establishments: St Vincent’s Hospital, Darlinghurst; Sacred Heart Health Service, Darlinghurst; St Joseph’s Hospital, Auburn; and St Vincent's Correctional Health, Parklea.
Source: NSW Health (unaudited)

The above changes will be reflected in the version of the report published on the Audit Office website and should be considered the true and accurate version.

Published

Actions for Transport 2020

Transport 2020

Transport
Asset valuation
Cyber security
Financial reporting
Information technology
Infrastructure
Project management

1. Financial Reporting

Audit opinion Unmodified audit opinions issued for the financial statements of all Transport cluster entities.
Quality and timeliness of financial reporting All cluster agencies met the statutory deadlines for completing the early close and submitting the financial statements.

Transport cluster agencies continued to experience some challenges with accounting for land and infrastructure assets. The former Roads and Maritime Services and Sydney Metro recorded prior period corrections to property, plant and equipment balances.
Impact of COVID-19 on passenger revenue and patronage Total patronage and revenue for public transport decreased by approximately 18 per cent in 2019–20 due to COVID-19.

The Transport cluster received additional funding from NSW Treasury during the year to support the reduced revenue and additional costs incurred such as cleaning on all modes of public transport and additional staff to manage physical distancing.
Completion of the CBD and South East Light Rail The CBD and South East Light Rail project was completed and commenced operations in this financial year. At 30 June 2020, the total cost of the project related to the CBD and South East Light Rail was $3.3 billion. Of this total cost, $2.6 billion was recorded as assets, whilst $700 million was expensed.

2. Audit Observations

Internal control While internal controls issues raised in management letters in the Transport cluster have decreased compared to the prior year, control weaknesses continue to exist in access security for financial systems. We identified 56 management letter findings across the cluster and 43 per cent of all issues were repeat issues. The majority of the repeat issues relate to information technology controls around user access management.

There were three high risk issues identified - two related to financial reporting of assets and one for implementation of TAHE (see below).
Agency responses to emergency events Transport for NSW established the COVID-19 Taskforce in March 2020 to take responsibility for the overall response of planning and coordination for the Transport cluster. It also implemented the COVIDSafe Transport Plan which incorporates guidance on physical distancing, increasing services to support social distancing and cleaning.
RailCorp transition to TAHE On 1 July 2020, RailCorp was renamed Transport Asset Holding Entity of New South Wales (TAHE) and converted to a for-profit statutory State-Owned Corporation. TAHE is a commercial for-profit Public Trading Entity with the intent to provide a commercial return to its shareholders.

A plan was established by NSW Treasury to transition RailCorp to TAHE which covered the period 1 July 2015 to 1 July 2019. A large portion of the planned arrangements were not implemented by 1 July 2020. As at the time of this report, the TAHE operating model, Statement of Corporate Intent (SCI) and other key plans and commercial agreements are not finalised. The State Owned Corporations Act 1989 generally requires finalisation of an SCI three months after the commencement of each financial year. However, under the Transport Administration Act 1988, TAHE received an extension from the voting shareholders, the Treasurer and Minister for Finance and Small Business, to submit its first SCI by 31 December 2020. In accordance with the original plan, interim commercial access arrangements were supposed to be in place with RailCorp prior to commencement of TAHE.

Under the transitional arrangements, TAHE is continuing to operate in accordance with the asset and safety management plans of RailCorp. The final operating model is expected to include considerations of safety, operational, financial and fiscal risks. This should include a consideration of the potential conflicting objectives of a commercial return, and maintenance and safety measures.

This matter has been included as a high risk finding in our management letter due to the significance of the financial reporting impacts and business risks for TAHE.

Recommendation: TAHE management should:
  • establish an operating model in line with the original intent of a commercial return
  • finalise commercial agreements with the public rail operators
  • confirm forecast financial information to assess valuation of TAHE infrastructure
  • finalise asset and safety management plans.

Resolution of the above matters are critical as they may significantly impact the financial reporting arrangements for TAHE for 2020–21, in particular, accounting policies adopted as well as measurement principles of its significant infrastructure asset base.

Completeness and accuracy of contracts registers Across the Transport cluster, contracts and agreements are maintained by the transport agencies using disparate registers.

Recommendation (repeat): Transport agencies should continue to implement a process to centrally capture all contracts and agreements entered. This will ensure:
  • agencies are fully aware of contractual and other obligations
  • appropriate assessment of financial reporting implications
  • ongoing assessments of accounting standards, in particular AASB 16 ‘Leases’, AASB 15 'Revenue from Contract with Customers', AASB 1058 'Income of Not-for-Profit Entities' and new accounting standard AASB 1059 'Service Concession Arrangements: Grantors' are accurate and complete.

 

This report provides parliament and other users of the Transport cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations
  • the impact of emergencies and the pandemic.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Transport cluster for 2020, including any financial implications from the recent emergency events.

Section highlights

  • Total patronage and revenue for public transport decreased by approximately 18 per cent in 2019–20 due to COVID-19.
  • Unqualified audit opinions were issued on all Transport agencies' financial statements.
  • Transport cluster agencies continued to experience challenges with accounting of land and infrastructure assets.

 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our:

  • observations and insights from our financial statement audits of agencies in the Transport cluster
  • assessment of how well cluster agencies adapted their systems, policies and procedures, and governance arrangements in response to recent emergencies.

Section highlights

  • While there was a decrease in findings on internal controls across the Transport cluster, 43 per cent of all issues were repeat issues. Many repeat issues related to information technology controls around user access management.
  • RailCorp transitioned to TAHE on 1 July 2020. TAHE's operating model and commercial arrangements with public rail operators has not been finalised despite government original plans to be operating from 1 July 2019. TAHE management should finalise its operating model and commercial agreements with public rail operators as they may significantly impact the financial reporting arrangements for TAHE for 2020–21.
  • Completeness and accuracy of contracts registers remains an ongoing issue for the Transport cluster.

Appendix one – List of 2020 recommendations

Appendix two – Status of 2019, 2018 and 2017 recommendations

Appendix three – Management letter findings

Appendix four – Financial data

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for State Finances 2020

State Finances 2020

Education
Finance
Community Services
Health
Justice
Industry
Planning
Environment
Premier and Cabinet
Transport
Treasury
Whole of Government
Financial reporting

The Auditor-General for New South Wales, Margaret Crawford, released her report today on State Finances for the year ended 30 June 2020.

‘I am pleased to once again report that I issued an unmodified audit opinion on the State’s consolidated financial statements,’ the Auditor-General said.

The report acknowledges this has been a challenging year, with New South Wales impacted by natural disasters and the COVID-19 pandemic.

The State’s Budget Result, reported in the financial statements, was a deficit of $6.9 billion. This is different to the 2019-20 budget forecast surplus of $1.0 billion and is an outcome of the government’s significant response to bushfires and COVID-19.

The report summarises a number of audit and accounting matters arising from the audit of the Total State Sector Accounts, a sector that comprises 291 entities controlled by the NSW Government with total assets of $495 billion and total liabilities of $256 billion.

Read full report (PDF)

Our audit opinion on the State’s 2019–20 financial statements was unmodified

An unmodified audit opinion was issued on the State’s 2019–20 consolidated financial statements.

The State extended signing its financial statements by six weeks.

Natural disasters, the COVID-19 pandemic and other factors impacted the State’s 2019–20 reporting timetable. The State extended signing its financial statements by six weeks, compared with 2018–19.

All agencies were also given a two-week extension to prepare their financial statements compared with 2018–19. Further extensions beyond two weeks were subsequently approved for the following 11 agencies (7 in 2018–19) to submit completed financial statements for audit:

  • Department of Communities and Justice
  • Department of Customer Service
  • Department of Planning, Industry and Environment
  • Department of Regional NSW
  • Department of Transport
  • Environment Protection Authority
  • Infrastructure NSW
  • Lord Howe Island Board
  • NSW Crown Holiday Parks Land Manager
  • Service NSW
  • Water Administration Ministerial Corporation.

The extensions reflected that the COVID-19 pandemic impacted agencies’ work environments during the first six months of 2020. This was at a time when many were still implementing machinery of government changes and preparing to implement three significant new accounting standards:

  • AASB 15 Revenue from Contracts with Customers (issued December 2014, effective 1 July 2019)
  • AASB 16 Leases (issued February 2016, effective 1 July 2019)
  • AASB 1058 Income of Not-for-profit entities (issued December 2016, effective 1 July 2019).

These new accounting standards were issued some years before they became effective, to allow reporting entities sufficient time to prepare for implementation. Notwithstanding this, some agencies had not fully implemented the new accounting standards in time for early close procedures, and the unforeseen impact of COVID-19 further complicated the year-end financial reporting processes for the State and its agencies.

The graph below shows the number of reported errors exceeding $20 million over the past five years in agencies’ financial statements presented for audit.

In 2019–20, agency financial statements presented for audit contained 19 errors exceeding $20 million (six in 2018–19). The total value of these errors increased to $1.4 billion ($927 million in 2018–19).

The errors resulted from:

  • incorrectly applying Australian Accounting Standards and Treasury Policies
  • incorrect judgements and assumptions when valuing noncurrent physical assets and liabilities
  • incorrectly interpreting the accounting treatment for unspent stimulus funding.

Errors in agency financial statements exceeding $20m (2016–2020)

$4.1 billion in stimulus funding was allocated in 2019–20

The government implemented an economic stimulus package primarily to mitigate the impacts of the COVID-19 pandemic on New South Wales.

The COVID-19 pandemic and bushfires had a significant impact on the State’s finances, reducing its revenue and increasing its expenses especially in sectors directly responsible for responding to the COVID-19 pandemic, such as Health.

The government announced a $4.1 billion health and economic stimulus package in 2019–20. This primarily included:

  • $2.2 billion in health measures including purchases of essential medical equipment and increasing clinical health capacity (like intensive care spaces)
  • $1.0 billion in small business and land tax relief
  • $355 million in extra cleaning services and quarantine costs.

Cluster agencies had spent $3.0 billion (just under 75 per cent) of the COVID-19 stimulus package by 30 June 2020.

The Health cluster incurred most of this expenditure.

Total spend relating to bushfires was $1.3 billion in 2019–20.

The graph below shows the total allocation and spend by cluster to 30 June 2020.

Economic stimulus allocation and spend by cluster to 30 June 2020

Deficit of $6.9 billion compared with a budgeted surplus of $1.0 billion

An outcome of the government’s overall activity and policies is its net operating balance (Budget Result). This is the difference between the cost of general government service delivery and the revenue earned to fund these sectors.

The General Government Sector, which comprises 199 entities, generally provides goods and services funded centrally by the State.

The Non-General Government Sector, which comprises 92 government businesses, generally provides goods and services, such as water, electricity and financial services that consumers pay for directly.

The Budget Result for the 2019–20 financial year was a deficit of $6.9 billion. The original budget forecast, set before the COVID-19 pandemic and bushfires, was a $1.0 billion surplus. The main driver of the change in result was:

  • $1.3 billion of higher employee costs, mainly due to:
    • increased workers compensation claims
    • additional personnel required (mainly in the Health sector) to respond to the COVID-19 pandemic
  • $2.3 billion of higher operating expenses, mainly due to:
    • $828 million from first time recognition of a child abuse claim liability
    • $507 million from additional insurance claims from the NSW bushfires
    • $343 million from COVID-19 claims by agencies for loss of revenue.
  • $1.8 billion in higher grants and subsidy expenses, mainly due to:
    • small business grants
    • COVID-19 quarantine compliance measures
    • costs incurred in response to the 2019–20 bushfires, drought and disaster relief payments
    • third party-controlled assets that were subsequently transferred to councils and utility providers, mainly arising from construction of the CBD and South East Light Rail.

The deficit was further driven by:

  • $1.9 billion less taxation revenue, mainly resulting from:
    • $1.3 billion less in payroll tax due to relief measures introduced by the government as part of its COVID-19 economic stimulus
    • $424 million less in gambling and betting taxes, due to venue closures required by COVID-19 public health orders
  • $523 million less in dividends and income tax revenue from the Non-General Government Sector, due to lower dividends received from NSW Treasury Corporation and from the State’s other commercial government businesses
  • lower fines, regulatory fees and other revenue, due to a $305 million decrease in mining royalties, largely driven by lower coal prices.

Main drivers of the 2019–20 actual vs. budget variance

Revenues increased $209 million to $86.3 billion

In 2019–20, the State’s total revenues increased by $209 million to $86.3 billion, 0.2 per cent higher than in 2018–19. COVID-19 impacted taxation revenue, which fell by $1.1 billion and revenue from the sale of goods and services, which fell by $1.1 billion. These falls were offset by a $2.5 billion (7.7 per cent) increase in grants and subsidies from the Australian Government, mainly in the form of additional stimulus funding.

Taxation revenue fell 3.5 per cent

Taxation revenue fell by $1.1 billion, mainly due to a:

  • $861 million fall in payroll tax as a result of COVID-19 relief (reduced payroll tax payments for eligible small businesses)
  • $430 million fall in stamp duty collections, driven by lower than expected growth in the property market
  • $427 million decline in gambling and betting taxes, mainly due to venue closures driven by COVID-19 public health orders.

Stamp duties of $8.8 billion were the largest source of taxation revenue, $473 million higher than payroll tax, the second-largest source of taxation revenue.

Australian Government grants and subsidies

The State received $34.2 billion in grants and subsides which are mainly from the Australian Government, $2.4 billion more than in 2018–19.

The increase was driven by a $1.1 billion increase in Commonwealth Specific Purpose Payments to support the Health cluster respond to the COVID-19 pandemic. Commonwealth National Partnership Payments increased by a similar amount to provide the State with Natural Disaster relief.

Sales of goods and services

In 2019–20, sales of goods and services fell $1.1 billion. This was due to the COVID-19 pandemic reducing:

  • patronage and related transport passenger revenue
  • health billing activities with elective surgery being put on hold
Fines, regulatory fees and other revenues

Fines, regulatory fees and other revenues fell $505 million. This was mainly due to a $409 million decrease in mining royalties attributed to a drop in thermal coal prices during 2019–20.

Other dividends and distributions

Other dividends and distributions rose by $616 million due to higher distributions received from the State’s investments. This was due to an additional $1.3 billion held in the State’s investment portfolio compared with last year.

Expenses increased $8.2 billion to $96.0 billion

The State’s expenses increased 9.3 per cent compared with 2018–19. Most of the increase was due to higher employee expenses, other operating costs and grants and subsidies.

Employee expenses, including superannuation, increased 5.7 per cent to $42.6 billion.

Salaries and wages increased to $42.6 billion from $40.3 billion in 2018–19. This was mainly due to increases in staff numbers and a 2.5 per cent increase in pay rates across the sector. Salaries and wages for the Education and Health sectors increased by $659 million and $732 million in each sector respectively.

The Health sector employed an additional 2,763 full time staff in 2019–20. It also incurred more overtime in response to COVID-19. Education increased staff numbers by 4,866 full time equivalents and paid a one off 11 per cent pay rise to school administration staff in 2019–20. Historically, the government wages policy aims to limit growth in employee remuneration and other employee related costs to no more than 2.5 per cent per annum.

Operating expenses increased 8.7 per cent to $27.0 billion.

Operating expenses increased to $27.0 billion in 2019–20 ($24.8 billion in 2018–19) due to higher operating activities in Health. The higher level of activities and related costs is attributed to a full year of operations at the Northern Beaches Hospital (opened November 2018), and responding to COVID-19. The response to COVID-19 involved the State providing viability payments to private hospitals, higher visiting medical officer costs due to additional overtime hours and spending more on equipment to set up COVID-19 testing clinics.

Insurance claims increased by $2.0 billion. This was mainly due to NSW Self Insurance Corporation (SiCorp) recognising a liability for child abuse claims incurred but not reported for the first time, and claims for the 2019–20 bushfires, floods and COVID-19.

Health costs remain the State’s highest expense.

Total expenses of the State were $96 billion ($87.8 billion in 2018–19). Traditionally, the following clusters have the highest expenses as a percentage of total government expenses:

  • Health – 24.3 per cent (25.8 per cent in 2018–19)
  • Education – 17.6 per cent (19.3 per cent in 2018–19)
  • Transport - 12.8 per cent (12.6 per cent in 2018–19).

General public service expenses as a percentage of total State expenses is higher due to a $2.0 billion increase in SiCorp’s accrued claim expenses.

Other expenses increased due to additional grant funding by the State for drought relief and COVID-19 stimulus spend.

Health expenses increased by $632 million compared with 2018–19 but fell as a proportion of total State expenses.

Education expenses remained stable compared with last year due to savings in student transportation costs primarily driven by COVID-19. This led to a decrease in the proportion of the State’s costs relating to education activities.

Grants and subsidies increased $2.5 billion to $14.1 billion.

The increase in grants and subsidies was due to payments the State made to support businesses and local communities in the face of COVID-19 and bushfires. In addition, the State transferred CBD and South East Light Rail assets to councils and utility providers during 2019–20 as it no longer controlled these.

Depreciation expense increased $1.0 billion to $9.2 billion.

Depreciation increased to $9.2 billion from $8.0 billion in 2018–19. At 1 July 2019, the State implemented the new leases standard recognising a right of use (ROU) asset and related lease liability in its financial statements. The value of ROU assets are amortised over the term of the lease. This contributed to $980 million of the increase in 2019–20 depreciation expense. Last year, these costs were previously reported within other operating expenses.

Assets grew by $28.0 billion to $495 billion

The State’s assets primarily include physical assets such as land, buildings and infrastructure, and financial assets such as cash, and other financial instruments and equity investments. The value of total assets increased by $28.0 billion to $495 billion. This was a six per cent increase compared with 2018–19, mostly due to changes in asset carrying values.

Of the State’s $28.0 billion increase in asset values, $9.3 billion was due to a new accounting standard requirement for operating leases to be valued and recorded on balance sheet for the first time.

AASB 16 Leases requires entities recognise values for right-ofuse assets (ROU) for the first time. An ROU asset is a lessee’s right to use an asset, the value of which is amortised over the term of the lease. This standard came into effect from 1 July 2019.

Valuing the State’s physical assets

State’s physical assets valued at $365 billion.

The value of the State’s physical assets increased by $14.1 billion to $365 billion in 2019–20. The assets include land and buildings ($168 billion), infrastructure ($180 billion) and plant and equipment ($16.7 billion). A prior period error relating to the valuation of RMS infrastructure assets reduced the reported values by $1.0 billion from $352 billion to $351 billion at 30 June 2019.

The movement in physical asset values between years includes additions, disposals, depreciation and valuation adjustments. Other movements include reclassification of physical assets leased under finance leases to right of use assets upon adoption of AASB 16 Leases on 1 July 2019.

Movements in physical asset values

Liabilities increased $38.4 billion to $256 billion

The State borrowed additional funds in response to natural disasters and COVID-19.

The State’s borrowings rose by $33.9 billion to $113.8 billion at 30 June 2020. This accounted for most of the increase in the State’s total liabilities.

The value of TCorp bonds on issue increased by $25.2 billion to $97.0 billion to largely fund capital expenditure and costs associated with the bushfires, drought and COVID-19.

TCorp bonds are actively traded in financial markets and are guaranteed by the NSW Government.

Over 2019–20, TCorp continued to take advantage of lower interest rates, buying back short-term bonds and replacing them with longer dated debt. This lengthens the portfolio matching liabilities with the funding requirements for infrastructure assets.

With effect from 1 July 2019, AASB 16 Leases required the State to recognise liabilities for operating leases for the first time. This increased total lease liabilities from $5.3 billion at 30 June 2019 to $11.8 billion at 30 June 2020.

More than a third of the State’s liabilities relate to its employees. They include unfunded superannuation and employee benefits, such as long service and recreation leave.

Valuing these obligations involves complex estimation techniques and significant judgements. Small changes in assumptions and other variables, such as a lower discount rate, can materially impact the valuation of liability balances in the financial statements.

The State’s unfunded superannuation liability rose $300 million from $70.7 billion to $71.0 billion at 30 June 2020. This was mainly due to a lower discount rate of 0.87 per cent (1.32 per cent in 2018–19). The State’s unfunded superannuation liability represents the value of its obligations to past and present employees less the value of assets set aside to fund those obligations.

 

The State maintained its AAA credit rating

The object of the Fiscal Responsibility Act 2012 is to maintain the State’s AAA credit rating.

The government manages New South Wales’ finances in accordance with the Fiscal Responsibility Act 2012 (the Act).

The Act establishes the framework for fiscal responsibility and the strategy to maintain the State’s AAA credit rating and service delivery to the people of New South Wales.

The legislation sets out targets and principles for financial management to achieve this.

This year, the State’s credit rating from Standard & Poor’s changed from AAA/Stable to AAA/Negative. Moody’s Investors Service credit rating of Aaa/Stable did not change from the previous year.

The fiscal target for achieving this objective is that General Government annual expenditure growth should be lower than long term average revenue growth.

The State did not achieve its fiscal target of maintaining annual expenditure growth below the long-term revenue growth rate target of 5.6 per cent.

In 2019–20, General Government expenditure grew by 9.7 per cent (5.5 per cent in 2018–19).

Expenditure items that contributed most to the growth rate include:

  • recurrent grants and subsidies (20.4 per cent)
  • other operating expenses (9.5 per cent)
  • employee costs (including superannuation) (5.6 per cent)

Recurrent grant and subsidy expenses increased by $2.8 billion in 2019–20 mainly due to the COVID-19 and natural disaster payments. Other operating expenses increased mainly due to a $2.0 billion increase in SiCorp insurance claims. This included the $828 million provision for child abuse claims incurred but not reported. The bushfires and COVID-19 pandemic also increased the number and cost of claims in 2019–20.

Superannuation funding position since inception of the Act - AASB 1056 Valuation

Published

Actions for Health capital works

Health capital works

Health
Compliance
Infrastructure
Procurement
Project management

This report examines whether NSW Health effectively planned and delivered major capital works to meet the demand for health services in New South Wales.

The report found that NSW Health has substantially expanded health infrastructure across New South Wales since 2015. However, the program was driven by Local Health District priorities without assessment of the State’s broader and future‑focussed health requirements.

The report found that unclear decision making roles and responsibilities between Health Infrastructure and the Ministry of Health limited the ability of NSW Health to effectively test and analyse investment options.

Project delays and budget overruns on some major projects indicate that Health Infrastructure's project governance, risk assessment and management systems could be improved.

The Auditor‑General recommends that NSW Health ensure its capital projects offer the greatest value to New South Wales by establishing effective policy guidance and enhancing project governance and management systems.

Read full report (PDF)

Since 2011–12, NSW Health has aimed to improve its facilities and build 'future focused' infrastructure. The NSW Government’s 2015–16 election commitments established a four-year $5.0 billion capital program for NSW Health to build and upgrade more than 60 hospitals and health services. The 2019–20 State Budget committed a further $10.1 billion over four years for another 29 projects. This is the largest investment to date on health capital works in New South Wales.

Recent reviews of infrastructure have recognised that population and demographic growth will require a change in the delivery and composition of health infrastructure, including considering greater use of non-traditional, non-capital health service options and assets.

To ensure that expenditure on capital works represents the best value for money, NSW Health's business cases need to be robust and supported by evidence that demonstrates they are worthy investments. The NSW Process of Facility Planning has been the main framework guiding the detailed planning and development of NSW Health's capital works proposals. This framework was developed by the then NSW Department of Health in 2010. Its aim is to ensure investment proposals are supported by rigorous planning processes that address health service needs and provide value for money.

Infrastructure projects of the complexity and scale being delivered by NSW Health carry inherent risks. For example, unplanned cost escalations can potentially impact on the State’s finances. Unforeseen delays can also reduce the intended benefits. The growth in the State’s health capital spend and project profile, means its exposure to such risks has increased over time.

The objective of this audit was to assess the effectiveness of planning and delivery of major capital works to meet demand for health services in New South Wales. To address this objective, the audit examined whether:

  • the Ministry of Health has effective procedures for planning and prioritising investments in major health capital works
  • Health Infrastructure develops robust business cases for initiated major capital works that reliably inform government decision making
  • Health Infrastructure has effective project governance and management systems that support delivering projects on-time, within budget and achievement of intended benefits.

The audit focused on the Ministry of Health and Health Infrastructure – being the lead agencies within NSW Health responsible for prioritising, planning and delivering major health capital works across the State. The audit examined 13 business cases for eight discrete projects over a ten-year period.

Conclusion

NSW Health has substantially expanded health infrastructure across New South Wales since 2015. However, its planning and prioritisation processes were not assessed against a long-term statewide health infrastructure plan and lacked rigorous assessment against non-capital options creating a risk that they do not maximise value for New South Wales.

The scale of NSW Health's capital investment is significant and has grown substantially in recent years. The NSW Government’s election commitments in 2015–16 and 2019–20 collectively set out a $15.0 billion capital program to build and upgrade 89 hospitals and health services. NSW Health developed this infrastructure program in the absence of a statewide health infrastructure strategy and investment framework to focus its planning and decisions on the types of capital investments required to meet the long-term needs of the NSW health system.

Consequently, locally focused priorities of the State’s 17 Local Health Districts have been the primary drivers of NSW Health’s capital investments since 2015–16. Local Health District investment proposals for hospitals were developed without consideration of alternative health options such as community health service models, technology-driven eHealth care, or private sector options. Without rigorous assessment against a range of potential health service options, there is a risk that selected projects do not maximise value for New South Wales.

In recognition of the need for a statewide approach to infrastructure planning, the Ministry of Health recently developed a 20-year Health Infrastructure Strategy and prioritisation framework in 2019. The strategy was approved by the NSW Government in April 2020.

NSW Health's ability to effectively test and analyse its capital investment options has been compromised by unclear decision-making roles and responsibilities between its Health Infrastructure and the Ministry of Health agencies.

While both Health Infrastructure and the Ministry of Health have responsibilities for the assessment of business cases for proposed infrastructure projects, confusion about the roles of each agency at key steps compromised the efficacy of the process. Health Infrastructure and the Ministry of Health have differing views about which agency is responsible for testing business case inputs and conducting comprehensive options appraisals.

As a result of this confusion, Health Infrastructure and the Ministry of Health did not rigorously test Local Health District capital investment proposals against defined statewide health infrastructure investment priorities. The NSW Process of Facility Planning does not clarify the responsibilities of all parties in validating and prioritising Local Health District's Clinical Service Plans and progressing them to business cases.

NSW Health's infrastructure priorities are not sufficiently supported by transparent documentation of selection methodology and the rationale for decisions. Consequently, there is a risk that recommended options, whilst having some economic and health service merit, do not represent the greatest value.

Substantial delays and budget overruns on some major projects indicate that Health Infrastructure's project governance, risk assessment and management systems could be improved.

Health Infrastructure did not fully comply with NSW Government guidelines for developing business cases and making economic appraisals for proposed capital investments. These weaknesses, along with delays and budget overruns on some projects, demonstrate a need for Health Infrastructure to strengthen its project governance, management and quality control systems.

 

Over the period of review, NSW Government policies for business case development and submission have emphasised that effective governance arrangements are critical to a proposal's successful implementation.

NSW Health's Process of Facility Planning similarly highlights the importance of effective governance and project management for achieving good outcomes. It prescribes a general governance structure managed by Health Infrastructure that can be tailored to the planning and delivery of health infrastructure projects greater than $10.0 million.

Project challenges indicate opportunities for strengthening governance and project management

The three major hospital redevelopments examined in metropolitan, regional and rural areas had a combined Estimated Total Cost of more than $1.2 billion and comprised eight discrete projects and 13 separate business cases.

Almost all these projects experienced delivery challenges which impacted achievement of their original objectives and intended benefits. This is expected in complex and large-scale health infrastructure programs. However, in some projects the impacts were significant and resulted in substantial delays, unforeseen costs, and diversion of resources from other priority areas.

Our review of the selected case studies highlighted opportunities for enhancing governance and project management. Specifically, it indicates a need for improving transparency in the management of contingencies, risk management and assessments particularly relating to adverse site conditions and the selection of contractors. There is also a need to strengthen forward planning for options to address unfunded priorities within business cases that risk complicating the delivery of future project stages resulting in unforeseen costs and potentially avoidable budget overruns.

Need for increased transparency and accountability in the management of contingency funds

In February 2017, the Ministry's Capital Strategy Group approved the use of surplus funds of $13.76 million from Stage 1 of the Hornsby Ku-ring-gai Hospital Redevelopment for new works deemed needed to support Stage 2. Following this decision, Health Infrastructure finalised and submitted a business case addendum for Stage 1 to the Ministry in March 2017, addressing the new works comprising a two-storey building for medical imaging and paediatric floors. The business case addendum also addressed options to fit out and procure major medical imaging equipment. The Ministry approved the Stage 1 business case in July 2017, noting the Ministry's Capital Strategy Group had already approved the use of remaining Stage 1 funds to deliver the new works.

Stage 1 was completed in 2015, almost two years before the Stage 1 business case addendum was prepared in February 2017.

The Ministry's decision to approve the new works using $13.76 million of surplus Stage 1 funds did not comply with the NSW Treasury Circular TC 12/20. This policy establishes the Treasurer's approval must be sought and received before a new capital project with an Estimated Total Cost of $5.0 million or more can be approved by NSW Health. The Ministry therefore exceeded its delegated authority in making this decision, as it was not evident it had sought and received the Treasurer's approval prior to doing so.

Consequently, the surplus Stage 1 funds should not have been used by the Ministry to deliver new works in the circumstances. Instead, they should have been released from the Stage 1 project in accordance with established NSW Health procedures, and the Stage 1 Estimated Total Cost revised down accordingly. This did not occur, and NSW Health ultimately directed $11.0 million in surplus Stage 1 funds to the new works.

These circumstances indicate a need to strengthen transparency and accountability within NSW Health for the approval of new projects, and how contingency funds are used in the management of major health capital works. They also demonstrate the impact of weaknesses with options appraisal as the initial Stage 1 business case did not consider alternative options for addressing the initially unfunded works later covered by the Stage 1 business case addendum and ultimately funded from the Stage 1 contingency provision.

Weaknesses in service delivery planning resulted in unaccounted-for costs

In addition to proposing the above-noted new works, the 2017 Stage 1 Business Case Addendum for the Hornsby-Ku-ring-gai development sought to retrospectively address the estimated funding gap of around $14.0 million for the internal fit out, supply of major medical imaging equipment, and cost to operate the medical imaging service at Hornsby Ku-ring-gai Hospital also not addressed in the originally Stage 1 business case.

The Stage 1 business case addendum considered various procurement options to purchase and run the medical imaging services ranging from State operation purchase options to private operation purchase options.

It recommended outsourcing the operation and provision of equipment to the private sector based on estimated savings to the public sector initially of around $650,000 per annum reducing over time to $270,000. The Ministry endorsed this option in June 2017, but it did not ultimately proceed.

A July 2018 report to the Executive Steering Committee on the project shows NSW Health later decided to deliver operation of the medical imaging unit 'traditionally' with an updated estimate of the cost at approximately $16.4 million. The report also shows the Ministry supported the costs now being met by the Northern Sydney Local Health District.

This means the funding gap previously identified in the Stage 1 business case addendum for fitting out the medical imaging building and supply of major medical equipment would need to be met fully by the State, representing a $16.4 million cost overrun for the project.

Examined reports to the Executive Steering Committee show this was largely funded by the Northern Sydney Local Health District via the disposal of land realising approximately $15.0 million in proceeds.

This initially unforeseen cost, along with the additional $11.0 million for the new works approved under the Stage 1 business case addendum, were ultimately merged with the Stage 2 project initially approved in 2017–18 with an Estimated Total Cost of $200 million.

The extent of budget variation on the Hornsby Kur-ring-gai development has not been transparent

The 2019–20 State Budget provided an additional $65.0 million for a further Stage 2A to deliver additional built capacity to support outpatient services, enhanced allied health services, re-housed community health services and the delivery of prioritised clinical services unfunded as part of Stage 2. The funds were approved based on an Investment Decision Template (IDT) that examined two options in addition to the base case representing scoping alternatives to the preferred master planned capital solution.

However, we found the IDT showed around 23 per cent of the $65.0 million sought (i.e. $15.0 million) was to be allocated to fund the deficit in Stage 2, which had arisen as a result of project delays due to adverse site conditions. This was not discussed in the IDT.

The February 2020 report to the Executive Steering Committee shows a combined Stage 2 and 2A final forecast cost of $292.6 million against a potential budget of $290.7 million representing an overall deficit for the project of around 0.6 per cent.

However, this favourable final budget position does not transparently show the funding challenges experienced over the project's implementation to-date. The three major budget issues include:

  • inappropriate use of around $11.0 million in Stage 1 contingency for originally unfunded works contrary to Treasury policy
  • the additional $16.4 million cost unforeseen in the Stage 1 business case for delivering medical imaging services mostly funded through the sale of land
  • an additional $15.0 million from Stage 2A to cover the budget overrun in Stage 2 due to adverse site conditions.

The cumulative impact of these events is that Stages 1 and 2 of the Hornsby project cost approximately $42.4 million than it should have in the circumstances around 14 per cent more than what the revised combined Estimated Total Cost for both stages should have been after releasing the $11.0 million in surplus Stage 1 funds, with Stage 2 delayed by around 14 months.

Opportunity for strengthening risk management for adverse site conditions

Major construction projects often experience adverse site conditions which can be difficult to fully detect in advance. However, we found this was a common occurrence in the projects we examined sometimes with significant time and/or budget impacts indicating scope to enhance related risk and cost assessments. Specifically:

  • Hornsby Ku-ring-gai Hospital Redevelopment Stage 2: adverse site conditions during demolition works resulted in an 11-month delay for delivering the medical imaging unit and 14-month delay completing Stage 2 main works including need for additional $15.0 million in funds to cover the resultant budget deficit for the project.
  • Blacktown Mt Druitt Hospital Redevelopment Stage 2: adverse site conditions combined with project complexity delayed completion of the early works by approximately five months. This contributed to the delay in completing the main construction works which occurred around nine months later than planned in the business case.
  • Dubbo Health Service Redevelopment Stages 3 and 4: Health Infrastructure advised adverse site conditions including asbestos containing materials and ground conditions delayed works for the main building with completion forecast for March 2021, around 21 months later than planned in the final business case. This resulted in the need for additional $13.5 million to cover increased construction costs and risks, increasing the Stage 3 and 4 forecast final cost from $150 million to $163.5 million as at February 2020.

These examples indicate a risk the cumulative impact of adverse site conditions may be substantial when measured across both time and Health Infrastructure's full delivery program. They also point to potential for Health Infrastructure to achieve efficiencies and improved outcomes from strengthening its approach to assessing and mitigating the risks from adverse site conditions.

Limited due diligence with prospective contractors risks avoidable delays and costs

Main construction works on Stage 1 of the Dubbo Health Service Redevelopment were completed in October 2015, approximately 13 months later than planned in the final business case. Delays were mainly due to insolvency of the early works contractor resulting in their departure from the project. The ensuing 11-month delay in completing the early works significantly impacted the overall schedule and delivery of main construction works.

The insolvency event was significant as it affected nine separate Health Infrastructure projects – three of which had yet to reach practical completion. It also affected state-funded projects in other sectors. It resulted in the need for additional funding of $11.5 million that was provided in the 2014–15 State Budget increasing the total Stage 1 and 2 budget from $79.8 million to $91.3 million.

Health Infrastructure’s analysis of lessons learned shows it worked actively to mitigate the impacts of the insolvency event across all affected projects. However, it also indicates a risk the lessons were mainly focused on mitigating the impacts after an insolvency event occurred rather than on prevention.

Although Health Infrastructure initially commissioned a financial assessment of the now insolvent early works contractor before engagement, it did not detect any risks of the impending insolvency and instead concluded the contractor was in a strong financial position. However, the contractor became insolvent shortly after commencement approximately seven months later. This indicates a risk of weaknesses in the assessment performed that was not explicitly addressed by the lessons learned.

Delivery of the main construction works were further impacted by disputes with the main works contractor over the scope of works for the renal unit resulting in Health Infrastructure terminating the contract in November 2016 following lengthy negotiations over several months.

The scope of works relating to the renal unit were ultimately transferred to Stages 3 and 4 and were delivered in December 2019, around five years later than originally planned in the business case.

Health Infrastructure advised the delay was ultimately beneficial to the project because the refurbishment works for the renal unit, initially scheduled for Stages 1 and 2, would have been demolished to accommodate the new Western Cancer Centre proposed after Stages 1 and 2 and currently being delivered in parallel with Stages 3 and 4.

Health Infrastructure advised the actual cost of Stages 1 and 2 was $84.7 million against the budget of $91.3 million. The residual $6.6 million relates to the renal works not delivered during Stage 1 and 2 and transferred to Stage 3 and 4.

Health Infrastructure advised the contractual provisions for mitigating insolvency events 'in-flight' are limited highlighting the importance of proactive and effective due diligence prior to engaging contractors for significant construction projects.

Need for a quality framework linked to staff training and capability development

Health Infrastructure's 2017-20 Corporate Plan identifies the development of a quality framework to support delivery of future-focused outcomes as a key organisational priority. Related initiatives within the Corporate Plan describe a framework underpinned by a Quality Committee providing advice on:

  • records management, to meet the requirements of the State Records Act 1998
  • project assurance, to ensure future focused outcomes and enhance Health Infrastructure's Standards, Policies, Procedures and Guidelines, Templates and Design Guidance Notes
  • knowledge management and library services, to promote and leverage from project learnings.

Although Health Infrastructure has some elements of a quality framework it is not yet fully in place. Health Infrastructure advised it had yet to establish the quality framework and related committee described in its Corporate Plan due in part to its focus on responding to the growth of its capital program.

Health Infrastructure's Development and Innovation team has been active in supporting continuous improvement in knowledge and project management including development of business cases. Although useful, these initiatives have relied heavily on leveraging and disseminating insights from Gateway reviews and have not formed part of a systematic quality and continuous improvement framework.

The limited focus on the quality of business cases is reflected in internal performance monitoring and reporting which focuses mainly on tracking the delivery of projects against internal benchmarks, often revised from the baselines in the business case, and expenditure against cashflow targets. There is no evident internal monitoring and/or reporting to the Chief Executive and Board on defined quality metrics linked to business case development and staff capability.

Performance reporting on balanced scorecard metrics has similarly focused mainly on process rather than quality and has been inconsistent in recent years.

Appendix one – Response from agency

Appendix two – About the audit

Appendix three – Performance auditing

Appendix four – Ministry of Health planning tools and guidelines

Appendix five – Streamlined investment decision process for Health Capital Projects

Appendix six – Timeline of business cases and relevant policy guidelines

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #338 - released 12 August 2020

Published

Actions for CBD South East Sydney Light Rail: follow-up performance audit

CBD South East Sydney Light Rail: follow-up performance audit

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk
Service delivery

This is a follow-up to the Auditor-General's November 2016 report on the CBD South East Sydney Light Rail project. This follow-up report assessed whether Transport for NSW has updated and consolidated information about project costs and benefits.

The audit found that Transport for NSW has not consistently and accurately updated project costs, limiting the transparency of reporting to the public.

The Auditor-General reports that the total cost of the project will exceed $3.1 billion, which is above the revised cost of $2.9 billion published in November 2019. $153.84 million of additional costs are due to omitted costs for early enabling works, the small business assistance package and financing costs attributable to project delays.

The report makes four recommendations to Transport for NSW to publicly report on the final project cost, the updated expected project benefits, the benefits achieved in the first year of operations and the average weekly journey times.

Read full report (PDF)

The CBD and South East Light Rail is a 12 km light rail network for Sydney. It extends from Circular Quay along George Street to Central Station, through Surry Hills to Moore Park, then to Kensington and Kingsford via Anzac Parade and Randwick via Alison Road and High Street.

Transport for NSW (TfNSW) is responsible for planning, procuring and delivering the Central Business District and South East Light Rail (CSELR) project. In December 2014, TfNSW entered into a public private partnership with ALTRAC Light Rail as the operating company (OpCo) responsible for delivering, operating and maintaining the CSELR. OpCo engaged Alstom and Acciona, who together form its Design and Construct Contractor (D&C).

On 14 December 2019, passenger services started on the line between Circular Quay and Randwick. Passenger services on the line between Circular Quay and Kingsford commenced on 3 April 2020.

In November 2016, the Auditor-General published a performance audit report on the CSELR project. The audit found that TfNSW would deliver the CSELR at a higher cost with lower benefits than in the approved business case, and recommended that TfNSW update and consolidate information about project costs and benefits and ensure the information is readily accessible to the public.

In November 2018, the Public Accounts Committee (PAC) examined TfNSW's actions taken in response to our 2016 performance audit report on the CSELR project. The PAC recommended that the Auditor-General consider undertaking a follow-up audit on the CSELR project. The purpose of this follow-up performance audit is to assess whether TfNSW has effectively updated and consolidated information about project costs and benefits for the CSELR project.

Conclusion

Transport for NSW has not consistently and accurately updated CSLER project costs, limiting the transparency of reporting to the public. In line with the NSW Government Benefits Realisation Management Framework, TfNSW intends to measure benefits after the project is completed and has not updated the expected project benefits since April 2015.

Between February 2015 and December 2019, Transport for NSW (TfNSW) regularly updated capital expenditure costs for the CSELR in internal monthly financial performance and risk reports. These reports did not include all the costs incurred by TfNSW to manage and commission the CSELR project.

Omitted costs of $153.84 million for early enabling works, the small business assistance package and financing costs attributable to project delays will bring the current estimated total cost of the CSELR project to $3.147 billion.

From February 2015, TfNSW did not regularly provide the financial performance and risk reports to key CSELR project governance bodies. TfNSW publishes information on project costs and benefits on the Sydney Light Rail website. However, the information on project costs has not always been accurate or current.

TfNSW is working with OpCo partners to deliver the expected journey time benefits. A key benefit defined in the business plan was that bus services would be reduced owing to transfer of demand to the light rail - entailing a saving. However, TfNSW reports that the full expected benefit of changes to bus services will not be realised due to bus patronage increasing above forecasted levels.

Appendix one – Response from agency

Appendix two – Governance and reporting arrangements for the CSELR

Appendix three – 2018 CSELR governance changes

Appendix four – About the audit

Appendix five – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #335 - released 11 June 2020

Published

Actions for Transport 2019

Transport 2019

Transport
Asset valuation
Financial reporting
Infrastructure
Internal controls and governance
Management and administration
Service delivery
Workforce and capability

This report details the results of the financial audits of NSW Government's Transport cluster for the financial year ended 30 June 2019. The report focuses on key observations and findings from the most recent financial statement audits of agencies in the Transport cluster.

Unqualified audit opinions were issued for all agencies' financial statements. However, valuations of assets continue to create challenges across the cluster. The Audit Office identified some deficiencies in relation to asset valuations at Transport for NSW, Roads and Maritime Services, Rail Corporation New South Wales and Sydney Metro.

The Audit Office noted an increase in findings on internal controls across the Transport cluster. Key themes related to information technology, asset management and employee leave entitlements. The report also highlights the status of significant infrastructure projects across the Transport cluster.

The report makes several recommendations including:

  • agency finance teams need to be consulted on major business decisions and commercial transactions at the time of their execution to assess the financial reporting impacts
  • the Department of Transport should ensure consistent accounting policies are applied across its controlled entities.

Download the Transport 2019 report (PDF)

This report analyses the results of our audits of financial statements of the Transport cluster for the year ended 30 June 2019. The table below summarises our key observations.

1. Machinery of Government changes
Transport for NSW, as the
lead agency, will absorb the
functions of Roads and
Maritime Services

The NSW Government announced its intention to integrate Roads and Maritime Services (RMS) into Transport for NSW (TfNSW) as part of the Machinery of Government changes.

This change was not included in the Administrative Orders as the Transport Administration Act 1988 No. 109 governs the composition of the Transport cluster. The Transport Administration Amendment (RMS Dissolution) Act 2019 (the Act) received assent on 22 November 2019. The Act dissolves RMS and transfers the assets, rights and liabilities of RMS to TfNSW. As at the date of this Report, the Act is not yet in force.

Transport is considering the impact of the changes on its operating model and financial reporting.

2. Financial reporting
Audit opinions

Unqualified audit opinions were issued on the 2018–19 financial statements of all agencies in the Transport cluster.

TfNSW and Sydney Metro obtained a three-week extension from NSW Treasury to submit their financial statements for audit to resolve accounting issues surrounding the valuation of property, plant and equipment.

The Department of Transport reported total consolidated property, plant and equipment of $158 billion at 30 June 2019. In 2018–19, there were issues with asset valuations at TfNSW, RMS, Sydney Metro and Rail Corporation New South Wales (RailCorp), resulting in adjustments after the submission of financial statements for audit and the correction of a prior period error.

There was also a prior period error resulting from an agreement between TfNSW and the former UrbanGrowth Development Corporation due to a lack of assessment of the financial reporting implications at the time of signing the agreement.

Recommendation: Agency finance teams need to be consulted on major business decisions and commercial transactions to assess their accounting impacts at the time of their execution, rather than at the end of a financial year. Agencies also need to resolve all key accounting issues such as valuations as part of the early close procedures.

This would improve the quality of financial reporting and avoid the need for extensions for agencies to submit their financial statements for audit.

Preparedness for new
accounting standards
Agencies across the cluster are progressing in their implementation of the new accounting standards.

Transport cluster agencies need to improve their contracts registers to ensure they have a complete list of contracts and agreements to assess the impact of the new accounting standards.
Valuation of assets remains
a challenge in the
Transport cluster

Whilst agencies complied with the requirements of the accounting standards and NSW Treasury policies on valuations, the Audit Office identified some deficiencies in relation to asset valuations across the cluster.

TfNSW reported a retrospective correction of a prior period error at 1 July 2017 which resulted in a reduction in the valuation of its Country Rail Network earthworks by $2.1 billion. This was due to survey results which identified the earthworks were flatter and lower than estimated in the valuation at 30 June 2017.

RMS made several adjustments during the year to correct asset values due to changes to valuation assumptions or data improvements. This included:

  • reduction of $318 million in the value of land under roads
  • decrease of $84.9 million to the value of land and buildings
  • changes to the value of traffic control and traffic signal network assets, due to data improvements.

Sydney Metro North West officially opened in May 2019 and reported total assets of $9.1 billion. Sydney Metro derecognised $322 million in assets constructed to facilitate its operation but transferred to councils and utilities.

Inconsistent accounting
policies across the
Transport cluster

There was an inconsistency identified in the cluster relating to the valuation of substratum land. In 2018–19, RailCorp derecognised $109 million of substratum land to ensure consistency in its approach with other Transport agencies.

As the parent entity, the Department of Transport needs to ensure accounting policies are consistently applied across all controlled entities for consolidation purposes. Inconsistencies in the application of accounting standards across agencies will impact comparability of financial reporting and decision making across the Transport cluster.

Recommendation: The Department of Transport should ensure consistent accounting policies are applied across its controlled entities.

Revenue growth

Public transport passenger revenue increased by $89.0 million (5.9 per cent) in 2018–19, and patronage increased by 37.8 million (4.9 per cent) across all modes of transport based on data provided by TfNSW.

The increase in revenue is mainly due to an increase in patronage as well as the annual increase in fares.

Negative Opal cards

Negative balance Opal cards resulted in $2.9 million in revenue not collected in 2018–19 ($10.4 million since the introduction of Opal).

In January 2019, Transport made a change to the Sydney Airport stations to prevent customers with high negative balances exiting the station. In addition, in late 2018, Transport increased the minimum top up values for new cards at the airport stations.

Recommendation (repeat): TfNSW should implement further measures to prevent the loss of revenue from passengers tapping off with negative balance Opal cards.

3. Audit observations
Internal controls There was an increase in findings on internal controls across the Transport cluster. Key themes relate to information technology, employee leave entitlements and asset management.

Twenty-nine per cent of all issues were repeat issues. The majority of the repeat issues related to information technology controls.
Write-off of assets In addition to a $322 million derecognition of assets transferred to councils and utilities by Sydney Metro and a $109 million derecognition of substratum land at RailCorp, the Transport cluster wrote-off $278 million of assets related to roads, bridges, maritime assets, traffic signals and controls network.

These mainly related to roads, bridges, maritime assets, traffic signals and the control network where new infrastructure assets substantially replaced an existing asset as part of construction activities.
Transport Asset Holding
Entity (TAHE)
TAHE was established to be a dedicated asset manager for the delivery of public transport asset management. The Transport Administration Amendment (Transport Entities) Act 2017 will transition RailCorp into TAHE. RailCorp is now expected to transition to TAHE from 1 July 2020 (previously 1 July 2019). Several working groups have been considering various aspects of the TAHE transition including its status as a for profit Public Trading Enterprise, the operating model and the impact of the new accounting standards AASB 16 'Leases' and AASB 1059 'Service Concession Arrangements: Grantors'. The considerations of these aspects identified several challenges in the implementation of TAHE which has led to the revised transition date. Given the delays in implementation, it is important to clarify the intent of the TAHE model.
Excess annual leave

Twenty-six per cent of Transport employees have annual leave balances exceeding 30 days. Of the employees with excess leave balances, 732 (10.3 per cent) did not take any annual leave in 2018–19.

Recommendation (repeat): Transport entities should further review the approach to managing excess annual leave in 2019–20. They should:

  • monitor current and projected leave balances to the end of the financial year each month
  • agree formal leave plans with employees to reduce leave balances over an acceptable timeframe
  • ensure leave plans are actioned appropriately
  • encourage all staff with excess leave balances take a minimum two-week period of leave per year.
Completeness and
accuracy of contracts
registers

There are no centralised processes to record all significant contracts and agreements in a register across the Transport cluster.

Across the Transport cluster, contracts and agreements are maintained by the individual agencies using disparate registers. Agencies must perform detailed assessments of their existing contracts and agreements to quantify the impact of the new accounting standards (AASB 16 ‘Leases’, AASB 15 ‘Revenue from Contracts with Customers’, AASB 1058 ‘Income of Not-for-Profit Entities’ and AASB 1059 'Service Concession Arrangements: Grantors').

In 2018–19, there was also a prior period error resulting from an agreement between TfNSW and another government agency due to a lack of assessment of the financial reporting implications at the time of signing the agreement.

A lack of a complete register of all contracts and agreements increases the risk that agencies may not be able to assess the full impact of the new accounting standards, as well as perform a complete assessment of the financial reporting implications of contracts and agreements.

Recommendation: Transport agencies should implement a process to centrally capture all significant contracts and agreements entered. This will ensure:

  • agencies are fully aware of contractual and other obligations
  • appropriate assessment of financial reporting implications
  • assessment of new accounting standards, in particular AASB 16 ‘Leases’, AASB 15 'Revenue from Contract with Customers', AASB 1058 'Income of Not-for-Profit Entities ' and AASB 1059 'Service Concession Arrangements: Grantors' are accurate and complete.

 

This report provides parliament and other users of the Transport cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

This cluster was impacted by the Machinery of Government changes on 1 July 2019. The NSW Government announced its intention to integrate Roads and Maritime Services (RMS) into Transport for NSW (TfNSW). This report is focused on the Transport cluster prior to these changes. Please refer to the section on Machinery of Government changes for more details.

Machinery of Government refers to how the government organises the structures and functions of the public service. Machinery of Government changes are where the government reorganises these structures and functions, and are given effect by Administrative orders.

The Transport cluster was impacted by recent Machinery of Government changes. These changes were announced by the Department of Premier and Cabinet but were not included in the Administrative Orders as the Transport Administration Act 1988 No. 109 governs the composition of the Transport cluster. It was the intention of government to transfer the functions of the RMS into TfNSW. This requires legislative changes to the Transport Administration Act 1988 No. 109.

Section highlights

Under the Machinery of Government changes, the NSW Government will transfer the functions of RMS into TfNSW.

  • The Transport Administration Amendment (RMS Dissolution) Act 2019 (the Act) received assent on 22 November 2019.
  • The Act will dissolve RMS and transfer its functions, assets, rights and liabilities to TfNSW.
  • As at the date of this report, the Act is not yet in force.
  • There are risks and challenges for asset and liability transfers, governance and retention of knowledge.
  • As of 1 July 2019, administrative arrangements (delegations and reporting line changes) were put in place to enable TfNSW and RMS to operate within a single management structure, while still remaining as separate legal entities.
  • Transport is working on a number of options as to how to implement the changes. 

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Transport cluster for 2019.

Section highlights

  • Unqualified audit opinions were issued on all agencies' financial statements.
  • RMS required an extension from NSW Treasury for their early close procedures.
  • TfNSW and Sydney Metro required extensions to submit their year-end financial statements.
  • Valuation of assets remains a challenge across the cluster.
  • There remains Opal cards with negative balances.
  • Sydney Metro derecognised assets of $322 million in relation to assets constructed for third parties.
  • Inconsistencies in the application of accounting policies across cluster agencies impact comparability of financial reporting across the Transport cluster.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from our financial statement audits of agencies in the Transport cluster.

Section highlights

  • There was an increase in findings on internal controls across the Transport cluster. Twenty-nine per cent of all issues were repeat issues.
  • Transport entities wrote-off over $278 million of assets which were replaced by new assets or technology.
  • Twenty-six per cent of Transport employees have excess annual leave.
  • There are no processes to ensure all significant contracts and agreements are captured by agencies in a centralised register.

Appendix one – Timeliness of financial reporting by agency 

Appendix two – Management letter findings by agency 

Appendix three – List of 2019 recommendations 

Appendix four – Status of 2017 and 2018 recommendations 

Appendix five – Cluster agencies 

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Health 2019

Health 2019

Health
Asset valuation
Compliance
Financial reporting
Fraud
Information technology
Internal controls and governance
Management and administration
Procurement
Project management

This report focuses on key observations and findings from the most recent financial audits of the Ministry of Health, local health districts, specialty health networks, health corporations and independent health agencies in New South Wales. The report also summarises self-reported performance measures across the network.

The number and value of adjustments to financial statements of entities in the Health Cluster decreased from the prior year. And unqualified audit opinions were issued for all heath entities’ financial statements.

Audit findings relating to internal controls deficiencies increased across health entities. Contributing to this increase were deficiencies in information system controls, which accounted for nearly a quarter of all control deficiencies. Repeat audit findings also accounted for more than a quarter of all control deficiencies.

The report notes health entities continued to experience challenges with managing employees’ excessive annual leave and time recording practices. The Ambulance Service of New South Wales continued to report high overtime payments to its employees. 

Download Health 2019 report (PDF).

This report analyses the results of our audits of financial statements of the agencies comprising the Health cluster for the year ended 30 June 2019. The table below summarises our key observations.

1. Machinery of Government changes

Cluster changes Machinery of Government (MoG) changes refer to how the government reorganises agency structures and functions and realigns ministerial responsibilities. The Health cluster was not impacted by the MoG changes.

2. Financial reporting

Financial reporting

The financial statements of NSW Health and its controlled entities received unqualified audit opinions before the legislative deadline.

The number of corrected and uncorrected misstatements decreased from the prior year.

Management implemented more robust processes for its oversight of complex asset revaluations in 2018–19. We found no significant errors in 2018–19.

Financial performance Overall, NSW Health recorded an operating surplus of $1.1 billion in 2018–19, an increase of $699 million from 2017–18. This was the result of additional funding received for capital expenditure on the construction of new facilities, upgrades and redevelopments.

Budgeted expense for the 15 local health districts and two speciality networks increased from $18.3 billion to $19.4 billion in 2018–19. The 15 health entities recorded unfavourable variances between actual and budgeted expenses.
Excess annual leave

Managing excess annual leave remains a challenge for NSW Health, 36.9 per cent of the workforce have excess annual leave balances.

Recommendation: Health entities should further review their approach to managing excess annual leave in 2019–20, and:

  • monitor current and projected leave balances to the end of the financial year on a monthly basis
  • agree formal leave plans with employees to reduce leave balances over an acceptable timeframe
  • encourage staff who perform key control functions to take at least two consecutive weeks’ leave a year to mitigate fraud risks.
Overtime payments NSW Health entities generally manage overtime well. The Ambulance Service of NSW’s overtime payments of $83.1 million (9.8 per cent of total salaries and wages), remain significantly higher than other health entities.

Recommendation: The Ambulance Service of NSW should further review the effectiveness of its rostering practices to identify strategies to reduce overtime payments.

3. Audit observations

Internal control deficiencies We identified more internal control deficiencies in 2018–19. The number of repeat issues from prior years also remains high with more than one quarter of issues having been previously reported. More than a quarter of deficiencies related to information system controls.
Infrastructure delivery NSW Health defines projects with a budgeted cost greater than $50.0 million as 'major projects'. There were significant revisions to planned financial completion dates and budgeted costs of these projects. The revised total budgets for the 30 ongoing major capital projects at 30 June 2019 is $10.2 billion, $2.2 billion more than the original budget.
Health Infrastructure completed three major capital projects during 2018–19.
Asset maintenance The total cost of maintaining the health entities’ $19.8 billion of assets was $635 million for 2018–19. Health entities' approaches to setting maintenance budgets vary. Most entities are addressing their backlog maintenance, although many were not able to quantify the full extent of their backlog maintenance. Although health entities continue to use fully depreciated assets, the replacement cost of these assets is decreasing.

 

 

This report provides parliament and other users of the financial statements of agencies within the Health cluster with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas for the year ended 30 June 2019:

  • financial reporting
  • audit observations. 

 The Health cluster was not impacted by the Machinery of Government changes on 1 July 2019. 

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the health cluster for 2019.

Section highlights

  • We issued unqualified audit opinions for all health entities’ financial statements and identified fewer misstatement than last year. Health entities continue to meet statutory deadlines.
  • The Ministry of Health sets significant accounting policies centrally and provides a template for the preparation of health entities’ financial statements. These processes promote consistent quality in the financial reports of health entities and reduce the number of misstatements we identify.
  • NSW Health recorded an operating surplus of $1.1 billion, an increase of $699 million from 2017–18. This is because of additional capital grants for new facilities, upgrades and redevelopments. The capital replacement ratio (investment in new assets divided by depreciation) for NSW Health is 2.6.
  • NSW Health’s expenses increased by 7.0 per cent in 2018–19 (5.5 per cent in 2017–18). This is one percentage point higher than the projected long-term annual expense growth rate of six per cent. The primary causes for the growth in expenses are increased:
    • employee related expenses because provisions for employee benefits increased when the discount rate decreased
    • operating expenses associated with the opening of Northern Beaches Hospital.
  • Excess annual leave balances continue to increase for the NSW Health workforce, with excess annual leave balances impacting 37 per cent of employees (34 per cent in 2017–18).
  • Health entities should further review their approach to managing excess annual leave in 2019–20 by monitoring current and projected leave balances on a regular basis, agreeing formal leave plans with employees and encouraging staff that perform key control functions to take a minimum of two consecutive weeks’ leave a year as a fraud mitigation strategy.
  • The Ambulance Services continued to report overtime payments higher than other health entities. The Ambulance Service paid its employees $83.1 million in overtime payments in 2018–19 ($74.8 million in 2017–18).
  • We issued a qualified audit opinion for the Ministry of Health's Annual Prudential Compliance Statement for aged care facilities operated by NSW Health. We identified 40 instances of material non-compliance with the Fees and Payments Principles 2014 (No. 2) (the Principles) in 2018–19 (17 in 2017–18).

Audit opinions 

We issued unqualified audit opinions for all health entities and quality of financial reporting continues to improve

We identified fewer misstatements this year, and the errors were less significant. In 2018–19 no errors exceeded $5.0 million (eight errors recorded in 2017–18). Ten health entities conducted a full revaluation of their land, buildings and infrastructure systems in 2018–19, but more robust processes avoided the errors identified in the previous year.

Number of misstatements
Year ended 30 June 2019 2018 2017
  green circle with white tick red circle with white exclamation mark green circle with white tick red circle with white exclamation mark green circle with white tick red circle with white exclamation mark
Less than $50,000 -- -- -- 6 3 3
$50,000 to $249,999 -- 1 -- -- 2 3
$250,000 to $999,999 1 -- -- -- 1 3
$1 million to $4,999,999 -- 2 -- 2 1 5
$5 million and greater -- -- 6 2 1 2
Total number of misstatements 1 3 6 10 8 16

green circle white tick Corrected mistatements. red circle white exclamation mark Uncorrected statements.
Source: Statutory Audit Reports issued by the Audit Office.

We issued a qualified audit opinion for our compliance audit of the Ministry of Health's Annual Prudential Compliance Statement

The Ministry of Health operates eight aged care facilities in NSW and is required to comply with the Fees and Payments Principles 2014 (No. 2) (the Principles) when entering into agreements with and managing payments to and from care recipients. The Principles are set by the Commonwealth Assistant Minister for Social Services. We identified 40 instances of material non-compliance in 2018–19, including:

  • not agreeing maximum accommodation amounts payable with aged care recipients before they entered the residential care services
  • not entering into accommodation agreements with care recipients within the specified period
  • charging incorrect fees for activities or services to one care recipient
  • not refunding two bond balances within the statutory framework
  • not paying the correct amount of interest for 14 care recipients’ bonds refunded during the year.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from our financial statement audits of agencies in the health cluster.

Section highlights

  • The number of internal control deficiencies has increased since 2017–18. More than a quarter of control deficiencies are repeat issues and almost a quarter relate to information system controls. Both employee time recording and leave management remain as repeat issues in 2018–19.
  • Control deficiencies that relate to managing employees' leave, employees’ time recording or information system limitations can be difficult for entities to resolve in a timely manner.
  • Agreements for the treatment of New South Wales residents while they are interstate, and interstate residents while they are in New South Wales, are unsigned for Queensland, Victoria and the Australian Capital Territory for 2016–17, 2017–18 and 2018–19.
  • NSW Health recorded $113.6 million in revenue from fees charged to Medicare ineligible patients during 2018–19 but has received payment for less than half of this.
  • NSW Health reported that they completed three major capital projects during 2018–19.
  • As at 30 June 2019 there were 30 ongoing major capital health projects in NSW. The revised capital budget for these projects in total was $2.2 billion more than the original budget of $8.0 billion.
  • Health entities spent $635 million maintaining assets with a fair value of $19.8 billion of assets. Almost all entities were working through backlog maintenance during 2018–19, although several were unable to quantify the backlog.
  • While entities are now regularly reassessing the useful lives of their assets, entities are still using a high volume of assets that are fully depreciated. Due to the age and nature of these assets the impact was not material.

Appendix one – List of 2019 recommendations

Appendix two – Status of 2018 recommendations

Appendix three – Financial data 

Appendix four – Analysis of financial indicators

Appendix five – Analysis of performance against budget

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.