Actions for Transport 2021

Transport 2021

Transport
Asset valuation
Compliance
Financial reporting
Information technology
Infrastructure
Internal controls and governance

What the report is about

The results of the Transport cluster agencies’ financial statement audits for the year ended 30 June 2021.

What we found

Unmodified financial statement audit opinions were issued for all Transport cluster agencies. Resolution of issues delayed signing the Transport Asset Holding Entity of NSW (TAHE) until 24 December 2021. Matters relating to TAHE are also reported in the report on State Finances 2021.

Emphasis of Matter - TAHE

An Emphasis of Matter paragraph was included in TAHE's audit opinion to draw attention to uncertainty associated with:

  • future access and licence fees that are subject to re-signed agreements
  • an additional $4.1 billion of funding that is outside the forward estimates period
  • a significant portion of the fair value of TAHE’s non-financial assets is reflected in the terminal value, which is outside the ten-year contract period to 30 June 2031, and the risk that TAHE will not be able to negotiate contract terms to support current projections.

TAHE's transition from RailCorp also changed its valuation of assets to an income approach, resulting in a $20.3 billion decrease to the fair value. The fair value decrease was because the cash flows were not sufficient to support the previous recorded value.

TAHE corrected a misstatement of $1.2 billion relating to the valuation of its assets. This followed significant deliberation on key judgements and assumptions, with TAHE adopting risk assumptions in its valuation that were not in line with comparable benchmarks.

Emphasis of Matter - State Transit Authority of New South Wales

An Emphasis of Matter paragraph was included in the State Transit Authority of NSW's (the Authority) audit opinion to draw attention to the financial statements not prepared on a going concern basis. This was because the NSW Government put the Authority's bus contracts out to competitive tender and accordingly, management assessed the Authority's principal activities are not expected to operate for a full 12 months after 30 June 2021.

The implementation of AASB 1059 ‘Service Concession Arrangements: Grantors’ resulted in a net increase in assets of $23.5 billion across the Transport cluster.

The 2020–21 audits identified six high-risk and 45 moderate risk issues across the cluster. Fourteen of the moderate risk issues were repeat issues, including information technology controls around management of user access for key financial systems and payroll processes.

The high-risk issues, in addition to those related to TAHE and previously reported in the report on State Finances 2021, include:

  • absence of conflict of declarations related to land acquisition processes at Transport for NSW
  • no evidence of conflict of interest declarations obtained by TAHE from consultants and contractors regarding involvement in other engagements.

What we recommended

TAHE needs to:

  • finalise revised commercial agreements to reflect fees detailed in a Heads of Agreement signed on 18 December 2021
  • prepare robust projections and business plans to support the required rate of return.

NSW Treasury and TAHE should monitor the risk that control of TAHE assets could change in the future.

Transport for NSW needs to significantly improve its processes to ensure all key information is identified and shared with the Audit Office.

Transport agencies should implement a process to ensure conflicts of interest declarations are completed for land acquisitions and applied consistently across the cluster.

Transport agencies should implement a process to capture all contracts and agreements entered to ensure:

  • agencies are aware of contractual obligations
  • financial reporting implications are assessed, particularly with respect to leases, revenue and service concession arrangements.

Fast facts

The Transport cluster plans and delivers infrastructure and integrated services across all modes of transport. This includes road, rail, bus, ferry, light rail, cycling and walking. There are 11 agencies in the cluster.

  • $128b road and maritime system infrastructure assets as at 30 June 2021
  • 100% unqualified audit opinions were issued on agencies 30 June 2021 financial statements
  • 26 monetary misstatements were reported in 2020–21
  • $24.9b rail systems infrastructure assets as at 30 June 2021
  • high-risk management letter findings were identified
  • 37% of reported issues were repeat issues

 

This report provides Parliament and other users of the transport cluster (the cluster) agencies’ financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the cluster for 2021.

Section highlights

  • Unqualified audit opinions were issued on all Transport agencies' financial statements.
  • An 'Emphasis of Matter' paragraph was included in the Transport Asset Holding Entity of New South Wales' (TAHE) Independent Auditor's Report to draw attention to significant uncertainty associated with the judgements, estimates and assumptions supporting the valuation of TAHE’s property, plant and equipment (PPE) and intangible assets.
  • In 2020–21, the former RailCorp transitioned to TAHE, a for-profit state-owned corporation. When TAHE became a for-profit entity, it was required to change its valuation approach. The value of a for-profit entity's assets cannot exceed the cash flows they might realise either through their sale or continued use. This change in the basis of valuation resulted in a decrease of $20.3 billion in the fair value of the assets. The decrease in fair value was because the cash flows, which support measurement under the income approach, were insufficient to support the previous valuation based on the current replacement cost of those assets.
  • TAHE also corrected a misstatement of $1.2 billion relating to the valuation of its assets after significant deliberation on key judgements and assumptions, with TAHE adopting higher risk assumptions in its valuation when compared to the relevant market benchmarks.
  • On 18 December 2021, a Heads of Agreement (HoA) was signed between TAHE, Transport for NSW, Sydney Trains and NSW Trains. This HoA reflected TAHE's intention to negotiate higher access and licence fees in order to meet the shareholding ministers' revised expectation of a higher rate of return. This matter resolved the treatment of a significant accounting issue in the State’s consolidated (whole-of-government) financial statements. Refer to the Report on State Finances tabled on 9 February 2022. The expectation of an additional $5.2 billion in fees added to the valuation of TAHE's PPE and intangibles, with a final value of $17.15 billion.
  • The implementation of AASB 1059 ‘Service Concession Arrangements: Grantors’ resulted in a net increase in assets of $23.5 billion across the cluster. AASB 1059 had a significant impact on Transport for NSW, Sydney Metro, Sydney Ferries and TAHE's 2020–21 financial statements.
  • TAHE corrected a misstatement of $97.2 million relating to the application of AASB 1059 'Service Concession Arrangements: Grantors' for the Airport Link Company Contract. 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from our financial statement audits of agencies in the cluster.

Section highlights

  • The number of findings reported to management increased from 56 in 2019–20 to 73 in 2020–21.
  • Thirty-seven per cent were repeat findings. Many repeat issues related to information technology controls around user access management and payroll processes. These included deficiencies in the monitoring of privileged user access to key financial systems, review of user access to key financial systems and segregation of duties between preparer and reviewer for new employee hires.
  • Six new high-risk issues were identified in 2020–21, an increase of three compared to last year.
  • One high-risk issue related to conflicts of interests not being declared by all officers involved in the land acquisition process at Transport for NSW.
  • Five high-risk issues arose from the audit of TAHE, with respect to:
    • control over TAHE assets and operations
    • asset valuations
    • access price build up
    • detailed business modelling to support returns
    • conflict of interest management.
  • Based on the access and licence agreements signed at 30 June 2021 between TAHE, Sydney Trains and NSW Trains, our review of the expected returns calculated by NSW Treasury did not support the assumption that there was a reasonable expectation that a sufficient rate of return could be achieved from the NSW Government's investment in TAHE.
  • On 14 December 2021 the shareholding ministers' increased their expectations as to TAHE's target average return from 1.5 per cent to the expected long-term inflation rate of 2.5 per cent.
  • On 18 December 2021 the revised shareholder expectations were confirmed in a signed Heads of Agreement. The Heads of Agreement will increase access fees paid by rail operators to TAHE by $5.2 billion.
  • TAHE's access and licence agreements specified fees that were well short of the IPART regulated maximum (ceiling price).
  • The finalisation of the access and licence agreements with Sydney Trains and NSW Trains resulted in a significant write-down of TAHE's asset value by $20.3 billion. The revaluation loss will need to be recovered as part of the shareholders’ rate of return of 2.5 per cent in order to sustain the whole-of-government accounting treatment of cash contributions recorded as an equity contribution and not a grant expense.
  • There was a significant adjustment to TAHE’s valuation between the financial statements originally submitted for the audit and the final, signed financial statements due to differences in risk assumptions resulting in a correction of a $1.2 billion misstatement. 

Findings reported to management

The number of findings reported to management has increased, and 37 per cent of all issues were repeat issues

Breakdowns and weaknesses in internal controls increase the risk of fraud and error. Deficiencies in internal controls, matters of governance interest and unresolved issues were reported to management and those charged with governance of agencies. The Audit Office does this through management letters, which include observations, related implications, recommendations and risk ratings.

In 2020–21, there were 73 findings raised across the cluster (56 in 2019–20) and 37 per cent of all issues were repeat issues (43 per cent in 2019–20).

In view of the recent performance audit ‘Managing Cyber Risks’ and compliance audit ‘Compliance with the NSW Cyber Security Policy’ involving the cluster, it is noted with concern that the most common repeat issues related to weaknesses in controls over information technology user access administration and password management. Moderate risk issues included completeness and accuracy of contract registers, accounting for assets and management of supplier and payroll masterfiles.

A delay in implementing audit recommendations increases the risk of intentional and accidental errors in processing information, producing management reports, and generating financial statements. This can impair decision-making, affect service delivery and expose agencies to fraud, financial loss and reputational damage. Control deficiencies may also mean agency staff are less likely to follow internal policies, inadvertently causing the agency not to comply with legislation, regulation, and central agency policies.

The table below describes the common issues identified across the cluster by category and risk rating. 

Risk rating Issue
Information technology
Moderate: 7 new, 4 repeat**

The financial audits identified opportunities for agencies to improve information technology processes and controls that support the integrity of financial data used to prepare agencies' financial statements. Of particular concern are issues associated with:

  • monitoring of privileged user access
  • user access management
  • password configuration management.
Low: 4 new, 1 repeat***
Internal control deficiencies or improvements
High: 1 new*

The financial audits identified internal control deficiencies across key business processes, including:

  • declarations of conflicts of interest over land acquisitions (see further details below)
  • management of contracts and agreement register
  • accounting for assets
  • management of payroll and supplier masterfiles
  • payroll processes.
Moderate: 15 new, 8 repeat**
Low: 2 new, 5 repeat***
Financial reporting
High: 3 new*

The financial audits identified opportunities for agencies to strengthen financial reporting, including:

  • asset valuations (see further details below)
  • detailed business modelling to support returns (see further details below)
  • access price build-up (see further details below)
  • timely capitalisation of completed assets.
Moderate: 3 new, 1 repeat**
Low: 2 new***
Governance and oversight
High: 1 new*

The financial audits identified opportunities for agencies to improve governance and oversight processes, including:

  • control over TAHE assets and operations
  • governance over Cyber Security.
Moderate: 2 new**
Non-compliance with key legislation and/or central agency policies
High: 1 new*

The financial audits identified the need for agencies to improve its compliance with key legislation and central agency policies, including:

  • conflict of interest (COI) management
  • outdated policies and procedures
  • incomplete probation procedures.
Moderate: 4 new, 1 repeat**
Low: 1 new, 7 repeat***

* High-risk from the consequence and/or likelihood of an event that has had, or may have a negative impact on the entity.
** Moderate risk from the consequence and/or likelihood of an event that has had, or may have a negative impact on the entity.
*** Low risk from the consequence and/or likelihood of an event that has had, or may have a negative impact on the entity.
Note: Management letter findings are based either on final management letters issued to agencies.

2020–21 audits identified six high-risk findings

High-risk findings were reported at the following cluster agencies.

Agency Description
2020–21 findings
Transport for NSW (new finding)

Declaration of conflicts of interest in the land acquisition process

In 2021, we conducted a performance audit over the Acquisition of 4–6 Grand Avenue, Camellia which examined:

  • whether Transport for NSW conducted an effective process to purchase 4–6 Grand Avenue, Camellia
  • whether Transport for NSW has effective processes and procedures to identify and acquire property required to deliver the NSW Government’s major infrastructure projects.

The report made several recommendations over Transport for NSW’s internal policies and procedures to guide the land acquisition process. As part of the financial audit, we obtained an understanding of key controls and processes relating to the acquisition of land, relevant to the audit of the financial statements. We found that conflicts of interests were not always declared by all officers involved in the land acquisition process. Furthermore, processes for declaring conflicts of interests are not consistently applied across cluster agencies.

Out of a sample of 19 land acquisitions tested, we identified:

  • 14 instances where there was no evidence of declarations of conflicts of interests made by the team members involved in the acquisition process
  • 2 instances where conflicts of interest declarations were completed by key members of the acquisition team only at a project level
  • 1 instance where conflicts of interest declarations were only completed by the property negotiator and the valuer, but not the other members of the acquisition team.

Management advised that the land acquisition processes, at the time of the land acquisitions, did not require formal conflicts of interests to be declared as they believe that as per Transport for NSW code of conduct, declaration is only required where the staff member considers that a potential or perceived Conflict of Interest exists. However, Transport for NSW's Procurement Policy requires the documentation of formal declarations from all staff involved in procurement activities to formally disclose any conflicts of interest or state that they do not have a conflict of interest.

This matter has been included as a high-risk finding in the management letter as absence of rigorous and consistent management of conflicts of interests, and non-compliance with established policies increases the risk that Transport for NSW may be exposed to reputational damage or financial losses in relation to land acquisitions. Furthermore, this may result in lack of probity or value-for money considerations during the land acquisition process.

Further details are elaborated below under 'Land acquisitions'.

Transport Asset Holding Entity of New South Wales (new finding)

Control over TAHE assets and operations

The State-Owned Corporations Act 1989 maintains that all decisions relating to the operation of a statutory state-owned corporation (SOC) are to be made by or under the authority of the board. However, under the Transport Administration Act 1988 (TAA), the functions of TAHE may only be exercised under one or more operating licences issued by the portfolio minister. The current Operating Licence confers terms and conditions for TAHE to carry out its functions, and imposes constraints on TAHE, including (but not limited to):

  • railway operations not permitted
  • transport services not permitted
  • TAHE must not carry out maintenance of its assets.

Such operating licences are short term in nature, and the TAA allows the transport minister (portfolio minister) to grant one or more operating licences to TAHE and may amend, substitute, or impose, amend or revoke conditions of the operating licence.

For the current year, the legal form of the arrangements established in its first year of operation imply TAHE has control over the assets based on the Implementation Deed and the agreements signed with the public operators.

However, risks remain as TAHE is in its early stages, and the actual substance of operations will need to be observed and considered.

Given the restrictions that can be placed on the entity through the Operating Licence, and the ability to make further changes to the Operating Licence and Statement of Expectations set by the portfolio minister, there is a risk there could be limitations placed on the Board of Directors to operate with sufficient independence in its decision-making with respect to the operations of TAHE. Over time, this may further impact the degree of control required by TAHE to satisfy the recognition criteria over its assets. It may also fundamentally change the presentation of TAHE’s financial statements.

Future limitations to the degree of control TAHE, and its Board, can exercise over its functions may impact the degree of control TAHE has over its assets going forward. As part of the 2021–22 audit, we will monitor and assess whether, in substance, these assets continue to be controlled by TAHE and whether, in substance, TAHE can operate as an independent SOC. We require management continue to demonstrate that TAHE continues to maintain control over its assets and has the ability to operate as an independent SOC. Further details are described below under 'Transport Asset Holding Entity'.

Transport Asset Holding Entity of New South Wales (new finding)

Asset valuation

The final updated valuation was based on cash flows that were in a signed Heads of Agreement, which stated that it set out the proposed indicative future access and licence fees which will form the basis of the negotiations between TAHE, Transport for NSW, Sydney Trains and NSW Trains, who will work together to review access fees and licence fees payable under the agreements and to make all necessary changes to the Operating Agreements by 1 July 2022.

This adds uncertainty in the cash flows. It is crucial that TAHE formalises these updated fees in legally binding signed access and licence agreements with the relevant parties as soon as possible.

Refer below for further details on the Heads of Agreement.

Transport Asset Holding Entity of New South Wales (new finding)

Conflict of interest (COI) management

For procurement transactions through direct negotiation with single quotes, there was no evidence of COI declarations obtained from the consultants and contractors regarding involvement in other engagements. Contractors and consultants are required to declare actual COI. However, there was no requirement to confirm nil conflict of interest. In addition, there is a risk that perceived COI may not be adequately assessed or managed. TAHE is expected to operate as an independent SOC and would need to ensure any perceived or actual conflict of interest is adequately addressed.

Management should implement a process to:

  • ensure conflicts of interest declarations are completed when engaging all consultants and contractors (including involvement with other engagements and confirmation of nil conflicts of interests)
  • ensure probity is undertaken to identify any actual or perceived conflicts of interest.

The declarations should consider individuals and relationships that may create, or may be perceived to create, conflicts of interest.

Transport Asset Holding Entity of New South Wales (new finding)

Detailed business modelling to support returns

On 18 December 2021, Transport for NSW, TAHE and the operators, Sydney Trains and NSW Trains entered into a Heads of Agreement (HoA). This HoA forms the basis of negotiations to revise the pricing within the existing 10-year contracts and deliver upon the shareholders' expectation of a return of 2.5 per cent per annum of contributed equity, including recovering the revaluation loss incurred in 2020–21.

TAHE needs to revise its business plan and include detailed business modelling that supports the shareholding ministers' revised expectations of return (2.5 per cent return on the State’s equity injections and recovery of the write-down of assets over the average useful life of those assets) and align the business plan and Statement of Corporate Intent. This requires more detailed projections, estimates and plans that support how TAHE expects to recover the asset write-down and expected returns to government. The current modelling for ten years needs to be enhanced with modelling over the expected recovery period of approximately 33 years.

Transport Asset Holding Entity of New South Wales (new finding)

Access price build-up

Management explained that in determining access and licence fees for the agreements with Sydney Trains and NSW Trains, assets prior to the commencement of equity injections in 2015–16 were excluded from the calculations. Management explained the premise being that these assets were previously funded by government through capital grants. The replacement and refurbishment of these assets is expected to be through government funded maintenance performed through the public rail operators and/or the equity injections from NSW Treasury rather than through access and licence fees.


The number of moderate risk findings increased from prior year

Forty-five moderate risk findings were reported in 2020–21, representing a 73.1 per cent increase from 2019–20. Of these, 14 were repeat findings, and 31 were new issues. 

Key moderate risk findings related to:

  • weaknesses in user access management to key financial systems
  • management of contracts and agreements register
  • management of supplier and payroll masterfiles
  • accounting for assets
  • control deficiencies at service organisations
  • segregation of duties relating to the hiring of employees
  • conflict of interest management
  • annual leave management
  • review of internal audit charter
  • disaster recovery planning.

Transport Asset Holding Entity of New South Wales

Background

The establishment of TAHE was originally announced by the NSW Government in the 2015–16 State Budget. On 1 July 2020, the former Rail Corporation New South Wales (RailCorp), a not-for-profit entity, transitioned to the Transport Asset Holding Entity of New South Wales (TAHE), a for-profit statutory state-owned corporation under the Transport Administration Act 1988. There was no change in the structure of TAHE as a new entity was not created. Ownership remains fully with the government. TAHE, and the former RailCorp, were both classified as Public Non-Financial Corporation (PNFC) entities within the Total State Sector Accounts.

Prior to 1 July 2015, the government paid appropriations to Transport for NSW, a General Government Sector (GGS) agency, to construct transport assets. When completed, these assets were granted to the former RailCorp, a not for-profit entity within the PNFC sector. The grants to the former RailCorp were recorded as an expense in the State’s GGS budget result.

From 1 July 2015, the government announced the creation of TAHE (a dedicated asset manager). Funding for new capital projects was to be provided through equity injections and was no longer recorded as an expense to the GGS budget, even though the business model was yet to be determined. The change, as explained in the 2015–16 State Budget, was due to the expectation that the former RailCorp will transition to TAHE, which was intended, over time to provide a commercial return. That Budget also highlighted how the change, which was largely a change in the basis of accounting, was intended to improve the GGS budget result each year. In total, the GGS has contributed approximately $11.1 billion to TAHE since 2015–16. This includes the equity injections from the GGS to TAHE made in the current year of $2.4 billion.

NSW Treasury initially set a timetable for the stand-up of TAHE of 1 July 2019, which included finalising the business model, operating model and contracts for the use of TAHE's assets. The enactment of the Transport Administration Act 1988 resulted in RailCorp transitioning to TAHE on 1 July 2020, 12 months after its originally planned operational date. Contributions paid to the former RailCorp and subsequently to TAHE by the GGS were treated as equity investments from July 2015 forward. This treatment continued, despite delays in settling the business model. In 2020, the Audit Office raised a high-risk finding due to the significance of the financial reporting impacts and business risks for NSW Treasury and TAHE.

The business model adopted and the flow of funds between transport agencies in the GGS and PNFC sectors is shown in the diagram below. For further details refer to the Report on State Finances 2021.

Appendix one – Misstatements in financial statements submitted for audit

Appendix two – Early close procedures

Appendix three – Financial data

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Treasury 2021

Treasury 2021

Treasury
Finance
Compliance
Financial reporting
Internal controls and governance
Management and administration

What the report is about

The results of Treasury cluster agencies' financial statement audits for the year ended 30 June 2021. The results of the audit of the NSW Government's consolidated Total State Sector Accounts (TSSA), which are prepared by NSW Treasury, are reported separately in our report on State Finances 2021.

What we found

Unmodified audit opinions were issued for all Treasury cluster agencies.

The number of identified monetary misstatements increased from 16 in 2019–20 to 24 in 2020–21.

Reported corrected monetary misstatements decreased from 15 in 2019–20 to seven with a gross value of $1.1 billion in 2020–21.

The largest corrected misstatement was in NSW Treasury's financial statements and was a $1 billion correction to administered borrowings.

Reported uncorrected monetary misstatements increased from one in 2019–20 to 17 with a gross value of $168 million in 2020–21.

Seven of the 2020–21 uncorrected misstatements related to one common decision relating to investment management funds terminated during the year by the NSW Treasury Corporation (TCorp).

All agencies submitted their 2020–21 financial statements within NSW Treasury's reporting deadlines.

What the key issues were

Significant audit findings were identified with respect to NSW Treasury's processes to prepare the NSW Government's consolidated TSSA (whole of government accounts). This included one extreme finding and several high-risk findings related to NSW Treasury processes. These are reported in our report on State Finances 2021.

Two high-risk issues raised in 2019–20 were also not addressed by NSW Treasury during the year and were repeat issues reported to management. These related to the appropriations framework and resolution of cross cluster payments, and instances where some agencies spent deemed appropriations money without an authorised delegation.

A number of previously reported audit findings and recommendations with respect to icare continue to be ongoing issues, namely:

  • The Workers Compensation Nominal Insurer continues to hold less assets than the estimated present value of its future payment obligations.
  • The Workers Compensation Nominal Insurer's four week return-to-work rate fell from 68% to 64%. This is below icare's 70% target. Contributing factors include COVID-19 lockdowns which have impacted claims handling processes, and increased barriers to claimants returning to work.
  • Instances were noted where inadequate documentation was kept on file to support claims, including pre-injury average weekly earnings (PIAWE) calculations.

The Workers Compensation (Dust Diseases) Authority increased its outstanding claims liability by $93.9 million, which included $39.3 million to remediate historical underpayments, resulting from workers not being paid the rate required by existing legislation.

The icare Board approved a new approach for remediating PIAWE underpayments on 24 September 2021, the date the Workers Compensation Nominal Insurer’s financial statements were approved for issue. The impact of the decision on the financial statements was not discussed with the Audit Office and assessed as an ‘after balance date event’.

What we recommended

Our report on State Finances 2021 made several recommendations to improve NSW Treasury processes. These included:

  • improve processes to ensure information is shared with audit on a timely basis
  • seek legislative amendments to resolve statutory inconsistencies relating to statutory reporting time frames
  • implement effective quality review processes over key accounting information
  • establish a policy to determine the minimum expected rate of return on equity injections in other public sector entities
  • prepare robust financial projections to support accounting decisions
  • re-confirm sector classifications of TAHE, Sydney Trains and NSW Trains
  • ensure sufficient oversight of its use of consultants and assess the risk of an overdependence on consultants at the cost of internal capability
  • improve disclosures of equity injections invested in other public sector entities
  • determine a state-wide policy on when borrowings are recognised in agency financial statements
  • make legislative amendments to ensure expenditure incurred across financial years does not exceed the appropriation authority and assess the financial reporting impact
  • improve the guidance provided to agencies to ensure expenditure of public money is properly supported by authorised delegations.

We also recommended icare should ensure:

  • it has sufficient controls over claim payments including an effective quality assurance program, to minimise claim payment errors
  • that documentation to support injured worker benefit calculations is appropriately maintained, and the documentation requirements are set out in a policy
  • the impact of ‘after balance date events’ on financial statements is appropriately assessed
  • its operational practices are improved to ensure the correct payment of claims in compliance with legislative requirements. icare also needs to act on a timely basis on received legal advice and amend operational practices to ensure correct payments are made.

Fast facts 

NSW Treasury notes that it is the Government's principal financial and economic adviser to guide the State’s growth for the benefit of the people who live, work and study in NSW.

  • $111b funds under management as at 30 June 2021
  • 100% unqualified audit opinions were issued on agencies’ 30 June 2021 financial statements
  • 24 monetary misstatements were reported in 2020–21
  • $17b total expenditure incurred in 2020–21
  • 12 extreme and high-risk findings were identified
  • 30% of reported issues were repeat issues

This report focuses on agencies within the Treasury cluster and provides parliament and other users of the Treasury cluster's financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

NSW Treasury also prepares the consolidated NSW whole of government financial statements (the Total State Sector Accounts), which is reported in the report on State Finances 2021.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making is enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Treasury cluster (the cluster) for 2021.

Section highlights

  • Unmodified audit opinions were issued on all the cluster agencies 2020–21 financial statements.
  • The number of identified monetary misstatements increased from 16 in 2019–20 to 24 in 2020–21.
  • Reported corrected monetary misstatements decreased from 15 in 2019–20 to seven with a gross value of $1.1 billion in 2020–21. The largest corrected misstatement was in NSW Treasury's financial statements resulting in a $1 billion correction to its administered borrowings. The correction was to address an understatement by NSW Treasury which did not recognise a liability for funds raised by NSW Treasury Corporation (TCorp) on its behalf as it applied settlement date accounting rather than trade date when recognising these borrowings. A corresponding receivable from TCorp was also recognised to reflect that funds were to be received on 1 July 2021.
  • The number of uncorrected misstatements increased from one in 2019–20 to 17 in 2020–21. Two of the misstatements above $5 million related to investment valuations within the SAS Trustee Corporation Pooled Fund, two related to premium income overstatements within the Workers Compensation Nominal Insurer, and one related to NSW Treasury administered liabilities and expenses where it recognised a provision for remediation costs when it had no present obligation. A further seven related to investment management funds that were terminated during the year by TCorp.
  • Nine agencies that were required to perform early close procedures did not complete a total of 25 mandatory procedures. The most common incomplete early close procedures include inter and intra (cluster) agency balances and transactions not confirmed with the counterparty agency and significant management judgements and assumptions made when estimating transactions and balances not documented.
  • To ensure compliance with Australian Accounting Standards, transactions and balances that were formerly reported in the Crown Entity’s financial statements are now reported by NSW Treasury as it primarily controls or administers the transactions and balances on behalf of the State.
  • icare changed the risk margin applied to measure the Workers Compensation Nominal Insurer's outstanding claims liability. If the risk margin used when valuing its 2019–20 outstanding claims liability had been retained, its net asset deficiency would have worsened compared to the prior year. The change in risk margin aligns the Nominal Insurer’s ‘probability of adequacy’ with the Australian Prudential Regulation Authority’s minimum reporting requirements for general insurers.
  • The icare Board approved a new approach for remediating pre-injury average weekly earnings underpayments (subject to legal advice, and assessment by a wage remediation expert), on 24 September 2021 and announced on 11 November 2021. The impact of the decision on the Nominal Insurer's financial statements was not assessed by icare as an ‘after balance date event’ and was not raised with the Audit Office prior to icare finalising its 2021 financial statements on 24 September 2021.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from our financial statement audits of agencies in the Treasury cluster.

Section highlights

  • The 2020–21 audits identified one new Extreme Risk and 11 High Risk findings. The extreme risk finding related to the incomplete provision and timely access to information to the Total State Sector Accounts (TSSA) audit and the accounting for the General Government Sector's investment in TAHE. Findings related to the TSSA audit are reported in the report on State Finances 2021. Of the 11 high risk findings, two were repeat findings relating to cross cluster payments and authorisation to spend deemed funds. High risk repeat findings need to be addressed with greater priority.
  • There were 21 moderate risk findings reported to management in 2020–21, ten of which were repeat findings. The most common repeat finding related to claims processing, information technology user access administration. Repeat findings, particularly those that relate to data protection, need greater prioritisation and should be implemented on a timely basis.
  • icare is in the process of implementing organisational reform in response to findings in recent external reviews. These reviews identified 151 recommendations for icare to improve in the areas of risk and governance, performance, and culture and accountability. All of the recommendations were accepted by icare and are expected to be addressed through their ‘Improvement Program’. A number of the observations referred to in this report were also identified in the external reviews.
  • The Nominal Insurer's four week return-to-work rate fell from 68% at 30 June 2020 to 64% at 30 June 2021 and was at 63% at 30 September 2021. This is below icare's target of 70%.
  • The Nominal Insurer overpaid, and underpaid claims to policyholders due to claims processing weaknesses. There was also insufficient documentation to support key inputs to weekly benefit payments, thereby further increasing the risk of claims being overpaid, and underpaid.
  • The Home Building Compensation Fund's net liability position reduced from $746 million at 30 June 2020 to $534 million at 30 June 2021 due to increases in premium rates and increased building activity from stimulus measures.
  • The Nominal Insurer's provision for errors in pre-injury average weekly earnings decreased from $21 million to 30 June 2020, to $11.6 million at 30 June 2021. The provision was not reassessed for icare’s decision to proactively remediate PIAWE underpayments.
  • The NSW Self Insurance Corporation also recognised a $12.8 million provision at 30 June 2021 to remediate past underpayments.

Findings reported to management

The number of findings reported to management has decreased, but 30% of all issues were repeat issues and these need greater focus and prioritisation

Breakdowns and weaknesses in internal controls increase the risk of fraud and error. Deficiencies in internal controls, matters of governance interest and unresolved issues were reported to management and those charged with governance of agencies. The Audit Office does this through management letters, which include observations, related implications, recommendations and risk ratings.

In 2020–21, there were 57 findings raised across the cluster (71 in 2019–20), 30% of which were repeat issues (32% in 2019–20).

The most common repeat issues related to claims processing and information technology user access administration.

A delay in implementing audit recommendations increases the risk of intentional and accidental errors in processing information, producing management reports and generating financial statements. This can impair decision-making, affect service delivery and expose agencies to fraud, financial loss and reputational damage. Poor controls may also mean agency staff are less likely to follow internal policies, inadvertently causing the agency not to comply with legislation, regulation and central agency policies.

The table below describes the common issues identified across the cluster by category and risk rating.

Risk rating Issue
Information technology

Moderate2
4 new
2 repeat

Low1
6 new
4 repeat

The financial audits identified the need for agencies to improve information technology processes and controls that support the integrity of financial data used to prepare agencies' financial statements. Of particular concern are issues associated with:
  • poor user access administration and monitoring of privileged user activities
  • lack of disaster recovery planning.
Internal control deficiencies or improvements

High3
1 repeat

Moderate2
5 new
7 repeat

Low1
9 new
 

 

The financial audits identified internal control weaknesses across key business processes, including:
  • lack of controls to ensure cluster expenditure does not exceed a minister's appropriation authority received under the annual Appropriations Act and the GSF Act
  • inadequate procurement controls including purchase orders not being used and policy documents not stipulating thresholds which require minimum quotations or tenders
  • inadequate claim processing controls leading to documentation not kept to support claims, and errors in payments.
High risk issues are discussed later in this chapter.
Financial reporting

High3
2 new

Moderate2
2 new
1 repeat

Low1
2 new 

The financial audits identified opportunities for agencies to strengthen financial reporting, including:
  • need to review significant judgements, and continue to assess whether assets are controlled
  • grants being incorrectly accounted for leading to errors
  • provisions not including costs to settle the obligation and errors in the accuracy and completeness of underlying data used in valuations.
High risk issues are discussed later in this chapter.
Governance and oversight

Extreme4
1 new

High3
7 new

Low1
1 new
 

The financial audits identified the need for agencies to improve governance and oversight processes, including:
  • documentation was inadequate and key documents were either not provided to the Audit Office, or were not provided on a timely basis, or their existence was not made known to the Audit Office
  • inconsistencies in the GSF Act and GSA Act relating to statutory timeframes
  • numerous versions of working papers were submitted all of which contained errors, omissions and/or poor logic
  • no formal policy or benchmark on expected investment returns from other government sectors
  • addressing significant uncertainty relating to access fees to be paid by rail operators raised in the Total State Sector Accounts audit opinion
  • the sector classification of certain Public Non-Financial Corporations needs to be confirmed with the Australian Bureau of Statistics
  • external consultants were used extensively to advise government agencies on matters related to TAHE
  • there is no state-wide policy about borrowings which provides guidance around performance obligations arising under trades between government agencies.
Extreme and high risk issues are discussed later in this chapter and in the report on State Finances 2021.
Non-compliance with key legislation and/or central agency policies

High3
1 repeat

Low1
1 new
1 repeat

The financial audits identified the need for agencies to improve its compliance with key legislation and central agency policies, including:
  • non-compliance with the GSA Act and expenditure of public monies not supported by authorised delegations or spent for an authorised and valid purpose
  • input tax credits were not always claimed correctly.
High risk issues are discussed later in this chapter.

 Extreme risk from the consequence and/or likelihood of an event that has had, or may have a negative impact on the entity.
3 High risk from the consequence and/or likelihood of an event that has had, or may have a negative impact on the entity.
2 Moderate risk from the consequence and/or likelihood of an event that has had, or may have a negative impact on the entity.
1 Low risk from the consequence and/or likelihood of an event that has had, or may have a negative impact on the entity.

 Note: Management letter findings are based either on final management letters issued to agencies, or draft letters where findings have been agreed with management.

The number of moderate risk findings decreased from prior year

There were 21 moderate risk findings reported in 2020–21, representing a 30% decrease from 2019–20. Of these, ten were repeat findings, and 11 were new issues.

Moderate risk repeat findings include:

  • claims processing weaknesses including claim payment errors, and inadequate documentation to support calculations and evidence claims were reviewed by someone with appropriate delegation
  • inadequate review of user access and higher risks of unintended or unauthorised system access
  • controls assurance reports from an outsourced service provider did not cover the services it provided to the government agency
  • failure to review procurement contracts register to ensure it is accurate and complete
  • ongoing control deficiencies with grant application and approval processes
  • key policies including delegations not being reviewed in a number of years and do not incorporate new requirements from more recent legislation
  • quality review processes failing to identify material classification errors associated with grant funding.

NSW Treasury related matters

Accounting for the Government's investment in Transport Asset Holding Entity

A total of seven recommendations were made with respect to NSW Treasury's processes to prepare the NSW Government's consolidated whole of government accounts (the TSSA). This included one extreme risk finding and six high risk findings. The extreme finding related to NSW Treasury needing to significantly improve its processes to ensure all key information is identified and shared with the Audit Office on a timely basis. Other high-risk findings were identified which resulted in the following recommendations for NSW Treasury:

  • establishing a policy to determine the minimum expected rate of return on the GGS equity injections in other public sectors entities and report on the performance of these GGS investments in the TSSA, including how much and what type of returns the government is obtaining from its investments compared to its targeted return
  • facilitate revised commercial agreements to reflect access and license fees that were agreed in the 18 December 2021 Heads of Agreement between Transport for NSW, TAHE and the operators Sydney Trains and NSW Trains
  • with TAHE, prepare robust projections and business plans to support GGS investment returns beyond FY2031.
  • liaising with the ABS to re-confirm the classification of TAHE, NSW Trains and Sydney Trains as entities within the PNFC sector
  • monitoring the risk that control of TAHE assets could change in future reporting periods and the implications on the TSSA
  • consider whether there is sufficient competent oversight of its use of consultants and assess the risk of an over dependence on consultants at the cost of internal capability.

More details on the recommendations to NSW Treasury relating to its accounting for the GGS investment in TAHE are included on pages 7 to 24 of the State Finances 2021 NSW Auditor-General’s Report to Parliament. 

Borrowings of $1 billion were understated by NSW Treasury

NSW Treasury, a GGS agency, made agreements to borrow $1 billion from New South Wales Treasury Corporation (TCorp), a PFC sector agency. Some of these agreements were entered as early as 17 May 2021 and all agreements for borrowings were entered into before 30 June 2021. However, NSW Treasury requested that settlement of those additional borrowings be deferred until 1 July 2021.

As TCorp raised the funds before 30 June 2021, it recognised a financial asset and liability to NSW Treasury on 30 June 2021. Despite TCorp having raised the funds by 30 June 2021 under the mutually agreed trade deal, NSW Treasury did not recognise any borrowings at year end on the basis that it requested the settlement date and receipt of cash to be deferred to past the balance sheet date. This led to an understatement of debt liabilities of $1 billion by NSW Treasury, and an inconsistent accounting treatment between the two agencies. NSW Treasury subsequently corrected the misstatement after the matter was raised by the audit, resulting in the GGS recognising $1 billion in financial assets and borrowings at 30 June 2021.

More detail on these inconsistencies is on page 37 of the State Finances 2021 NSW Auditor-General’s Report to Parliament. We recommended NSW Treasury seek develop a state-wide accounting policy for borrowings which ensure correct and consistent accounting treatment between agencies and sectors.

Inconsistencies exist in the GSF Act and GSA Act related to key statutory timeframes

There are inconsistencies between key statutory reporting timeframes imposed on the Treasurer and Auditor-General for the Consolidated State Financial Statements (the Statements) in the Government Sector Finance Act 2018 (GSF Act) and Government Sector Audit Act 1983 (GSA Act). Ambiguity in the statutory reporting timeframes could impact on the future timely provision of this information to Parliament. More detail on these inconsistencies is on page 54 of the State Finances 2021 NSW Auditor-General’s Report to Parliament. We recommended NSW Treasury seek legislative amendments in Parliament to resolve these inconsistencies.

NSW Treasury lacks a framework to monitor and provide assurance to ministers that they are in compliance with their appropriation authority

In July 2021, NSW Treasury highlighted a potential issue associated with certain cross-cluster payments which was based on advice received from the Crown Solicitor in January 2021. After being made aware of the issue, the Audit Office obtained its own advice on matters related to the appropriations framework under relevant state legislation. In the advice to the Audit Office, the Crown Solicitor advised that an agency is not subject to its own legally appropriated expenditure limit (assuming it is not subject to any annual spending limit imposed through an instrument of delegation or a budget control authority issued by the Treasurer under section 5.1 of the GSF Act). In effect, because responsible ministers are given appropriations, these legal expenditure limits, rest in aggregate, with the principal department and agencies the minister is responsible for. It is not possible for an individual agency to monitor or determine at what ‘point in time’ expenditure has been incurred in excess of the minister’s appropriation authority and there is currently no framework to monitor this.

Further detail on this matter is on pages 54 to 56 of the State Finances 2021 NSW Auditor-General’s Report to Parliament. In this report, we recommended that NSW Treasury:

  • ensure a framework exists to monitor and provide assurance to ministers that expenditure incurred across a financial year by agencies under the relevant minister's coordination does not exceed the appropriation authority conferred by the annual Appropriations Act and the GSF Act
  • assess how the requirement to prepare a Summary of Compliance under Australian Accounting Standards impacts relevant principal departments and cluster agencies financial statement disclosures.

Agencies have again spent monies without an authorised delegation

In the State Finances NSW Auditor-General's Report to Parliament for 2020 and 2021 we reported instances where agencies spent money received from an annual appropriation and/or deemed appropriation money without an authorised delegation from the relevant minister(s) as required by sections 4.6(1) and 5.5(3) of the GSF Act. Further detail on this matter is on pages 56 to 57 of the State Finances 2021 NSW Auditor-General’s Report to Parliament. In this report, we recommended NSW Treasury promptly improve the guidance it provides agencies to ensure that expenditure of public monies is properly supported by authorised delegations.

Control deficiencies at NSW Treasury's service providers

NSW Treasury's business processes and information technology services were provided by Infosys, Unisys and the Department of Customer Service during 2020–21. Together this constitutes the GovConnect environment.

The GovConnect information technology general controls (ITGC) were qualified in 2020–21. The key controls over user access, system changes and batch process failed in all ITGC reports. Most of these deviations were not mitigated or sufficiently mitigated to address the risk of unauthorised user access.

In response to the internal control qualifications, the audit teams performed data analytics over payroll and accounts payable to obtain reasonable assurance that these control deficiencies did not materially impact on relevant agencies' financial statements.

Refer to the Customer Service 2021 NSW Auditor-General’s Report to Parliament for further details.

Insurance related matters

icare is in the process of implementing organisational reform in response to findings in recent external reviews. These reviews have identified 151 recommendations for icare to improve in the areas of risk and governance, performance, and culture and accountability. The reviews include the April 2021 McDougall Review, and the February 2021 ‘Independent Review of icare governance, accountability and culture’ which was recommended by SIRA in the Dore Report.

All of these recommendations were accepted by icare and are expected to be addressed through their ‘Improvement Program’. As at February 2022, icare report that 21 have been addressed, 139 are in progress, and 15 still to commence.

A number of the observations referred to in this report were also identified in the above reviews and are expected to be actioned as part of the improvement program.

Workers Compensation Nominal Insurer (the Nominal Insurer)

The Nominal Insurer’s net asset deficiency at 30 June 2021

Last year's Central Agencies Report to Parliament reported that the Workers Compensation Nominal Insurer (the Nominal Insurer), the NSW Self Insurance Corporation and the Lifetime Care and Support Authority of New South Wales all had negative net assets at 30 June 2020. After strong investment returns in 2020–21, only the Nominal Insurer continued to have negative net assets at 30 June 2021.

The Nominal Insurer's negative net assets of $252.9 million at 30 June 2021 ($316.2 million at 30 June 2020) means that it still does not hold sufficient capital to meet the estimated present value of its future payment obligations, when measured in accordance with the accounting framework. The financial statements continued to be prepared on a going concern basis because the future payment obligations are not all due for settlement within the next 12 months.

As noted in section 2.4 ‘Key accounting issues’, icare changed from an 'Accounting Ratio', to an 'Insurance Ratio', to assess the Nominal Insurer’s capital position from 2020–21. The insurance ratio uses a (higher) discount rate based on the expected earnings rate on the Nominal Insurer’s assets, rather the ‘risk free’ rate which is used for financial reporting.

Last year's Report to Parliament also noted that the deterioration in the value of the Nominal Insurer’s net assets has resulted in its funding ratio at 30 June 2020 being outside of the ‘target operating zone’ set by the Board of icare. The Insurance Ratio at 30 June 2021 is 122%, which is less than icare's target operating zone of over 130%.

icare is assessing how it can increase the Nominal Insurer’s funding ratio, and advises that actions taken to date include the execution of the Nominal Insurer Improvement Program (the Improvement Program) and an increase in premium rates.

icare were given approval by the State Insurance Regulatory Authority (SIRA) to increase workers compensation premium rates from 1.4% to 1.44%  of wages (2.9%) for the 2021–22 policy year. icare advises that their pricing strategy for workers compensation premiums is for ‘modest increases over the medium term’.

Return-to-work rates have worsened

Last year's Central Agencies Report to Parliament noted that the Nominal Insurer has experienced deteriorating return-to-work rates since late 2017. According to data published by SIRA, the Nominal Insurer’s monthly four week return-to-work rate has continued to decline, falling from 68% at 30 June 2020 to 64% at 30 June 2021, and down to 63% at 30 September 2021.

A key assumption when measuring the Nominal Insurer’s outstanding claims liability, is the amount of time that injured workers will remain on benefits (i.e. continuance rates). This assumption is significantly aligned with return-to-work rate measures. At 30 June 2021, the liability was increased by $296 million due to changes in continuance rate assumptions, with workers expected to remain on benefits longer. This change is consistent with the fall in four week return-to-work rates.

The four week return-to-work rate trend since August 2017 is shown in the graph below.

Appendix one - Misstatements in financial statements submitted for audit

Appendix two – Early close procedures

Appendix three – Timeliness of financial reporting

Appendix four – Financial data

Appendix five – Acquittals and other opinions

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Published

Actions for State Finances 2021

State Finances 2021

Whole of Government
Finance
Asset valuation
Compliance
Financial reporting
Internal controls and governance
Management and administration

What the report is about

The results of the consolidated General Government Sector (GGS) and Total State Sector (TSS) financial statements audits for the year ended 30 June 2021.

What we found

The Independent Auditor’s Report on the 2020–21 GGS and TSS financial statements was unqualified but contained an emphasis of matter. The resolution of significant issues delayed signing until 24 December 2021.

The emphasis of matter draws attention to significant uncertainties associated with key assumptions related to the recognition by the GGS of a $2.4 billion investment in the Transport Asset Holding Entity (TAHE).

The Audit Office advised NSW Treasury that it intended to issue a qualified audit opinion, but actions by the NSW Government avoided this outcome. All evidence provided prior to 14 December indicated that the GGS’s return on the $2.4 billion cash contributed to TAHE was insufficient to support accounting for it as an investment. Projected returns were below the long term inflation rate and were insufficient to recover:

  • TAHE's revaluation loss of $20.3 billion in 2020–21
  • an average rate of return of at least 2.5 per cent of equity invested in TAHE.

In these circumstances, the $2.4 billion contributed to TAHE should have been expensed. This could have impacted the GGS’s budget result.

The NSW Government’s actions to avoid a qualified audit opinion included:

  • a government decision made on 14 December approving TAHE’s shareholding ministers communicating that their expectation of a return had increased to 2.5 per cent
  • reflecting the revised shareholding ministers’ expectations in the 2021–22 ‘NSW Half-Yearly Review’ on 16 December. The NSW Government provided an additional $1.1 billion to fund increased access and license fees to TAHE from the public sector operators (Sydney Trains and NSW Trains)
  • signing a Heads of Agreement (HoA) on 18 December between Transport for NSW (TfNSW),TAHE and the public sector operators. The HoA reflected the parties’ intent to renegotiate contracts to increase TAHE’s licence and access fees by $5.2 billion.

The uncertainty raised in our emphasis of matter relates to:

  • TAHE’s future estimated access and licence fees, which remain subject to re-negotiation and must meet or exceed the indicative future access and licence fees set out in the HoA
  • continued funding for TAHE's key customers (Sydney Trains and NSW Trains) to meet the price increases outlined in the HoA
  • the 2021–22 'NSW Budget Half Yearly Review', which provides for $1.1 billion of the additional funding over the forward estimates period to 2024–25. A further $4.1 billion is required over the following six years (2026–31), which are outside the forward estimates period
  • further significant cash flows required to support the funding model are outside the 10-year contract period. That is, beyond 30 June 2031.

There remains a risk that:

  • TAHE will not be able to re-contract with the rail operators for access and licence fees at a level that is consistent with current projections
  • future government's funding to TAHE’s key customers, the rail operators, may not be consistent with the current shareholding ministers’ expectations
  • TAHE will be unable to grow its non-government revenues.

The audit found a risk of undue reliance on consultants, a need to improve quality controls on materials submitted to audit and an extreme risk finding raised with respect to providing key information on a timely basis.

The GGS Budget Result for the 2020–21 financial year was a deficit of $7.1 billion compared to an original forecast budget deficit of $16 billion.

The State did not achieve its fiscal target of maintaining annual expenditure growth below the long-term revenue growth target of 5.6 per cent. In 2020–21, the GGS expenditure grew by 6.9 per cent mainly due to grants and subsidies paid from the COVID-19 stimulus packages received from the Commonwealth.

What we recommended

Significant matters concerning TAHE

We recommend NSW Treasury:

  • implement effective quality review processes over key accounting information
  • establish a policy to determine the minimum expected rate of return on its equity injections into public sector entities
  • report on the performance of investments in TAHE and all other public sector entities
  • ensure the revised commercial agreements between TAHE and NSW rail operators reflect access and licence fees set out in the Heads of Agreement
  • with TAHE, prepare robust projections and business plans to support returns beyond FY2031
  • liaise with the Australian Bureau of Statistics (ABS) and reconfirm the sector classifications of TAHE, NSW Trains and Sydney Trains
  • with TAHE, monitor the risk that control of TAHE assets could change in future reporting periods
  • significantly improve its processes to ensure all key information is identified and shared on a timely basis
  • consider whether there is sufficient competent oversight of its use of consultants and assess the risk of an overdependence on consultants at the cost of internal capability.

A number of other non-TAHE related recommendations have been raised in Section 6 ‘Key Audit Findings’.

Fast facts 

The Total State Sector comprises the General Government Sector, the Public Non-Financial Corporation (PNFC) Sector and the Public Financial Corporation (PFC) Sector.

The 2020–21 consolidated financial statements of the General Government and Total State Sectors provide the financial performance and position of the NSW Government.

  • $391b government property, plant and equipment in the Total State Sector as at 30 June 2021
  • $3.3b government net contributions to other public sectors in 2020–21. $2.4 billion was contributed to TAHE
  • $19.3b net holding losses from the GGS's investment in other public sector entities recognised outside of the 2020–21 budget result
  • $7.1b budget deficit of the General Government Sector in 2021
  • 7 - six high risk and one extreme risk management letter findings related to the General Government Sector's investment into TAHE
  • 24 monetary misstatements exceeding $20 million were identified in agencies financial statements in 2020–21
Image
Margaret Crawford, Auditor-General for New South Wales

Pursuant to the Government Sector Audit Act 1983 I present my report on State Finances 2021. My independent auditor’s opinion on the State’s consolidated financial statements, albeit delayed, is unqualified. My independent auditor’s report however, does include an emphasis of matter drawing attention to significant uncertainties remaining in relation to the State’s equity investment in the Transport Asset Holding Entity (TAHE).

The 2020–21 year was challenging from many perspectives, not least being the continuing impact of and response to the COVID-19 pandemic. Once again, NSW Treasury provided government agencies extensions of time to submit financial statements for audit. Finance staff and management right across government must be congratulated for their responsiveness in meeting their financial reporting obligations in such challenging circumstances.

The General Government’s 2020–21 budget result, reflected within the Total State Sector Accounts, was a deficit of $7.1 billion. This compares with the original budgeted deficit of $16 billion. The factors that contributed to this outcome are presented in this Report to Parliament along with other significant matters related to the audit of the Total State Sector Accounts.

One section of my report is dedicated to issues related to the accounting for TAHE. This year’s audit was significantly delayed by protracted disagreement over the treatment of the government’s cash contribution to TAHE. This matter was further frustrated by the fact that information was withheld and not shared with my Office on a timely basis. This has warranted an extreme risk finding for NSW Treasury to significantly improve governance processes to ensure complete and timely sharing of information. This is key to preserving trust, which is one of the foundations that underpins my Office’s engagement with agencies in the conduct of their audits.

The challenges encountered in completing this year’s audit were extraordinary and tested the constructive partnership between the Audit Office and NSW Treasury. I want to acknowledge the enormous efforts of staff of both agencies to correct material errors and ultimately achieve my unmodified audit opinion. I saw first-hand the professionalism, resilience and dedication of my staff. A commitment to accurate and transparent financial reporting is a key basis upon which confidence in the financial management of New South Wales’ resources can be assured.

Margaret Crawford

Auditor-General for New South Wales

9 February 2022

The Independent Auditor's Report, which includes an emphasis of matter was issued on 24 December 2021

While the audit opinion on the State's 2020–21 financial statements was ultimately unmodified, NSW Treasury delayed signing the NSW Total State Sector Accounts (TSSA) in order to resolve significant accounting issues that were material to the TSSA, in particular the treatment of the General Government Sector's (GGS) investment in the Transport Asset Holding Entity (TAHE) during 2020–21.

The Treasurer and NSW Treasury signed the consolidated financial statements on 24 December 2021, eleven weeks later than the 2018–19 pre-pandemic timetable.

The Audit Office advised NSW Treasury that the 2020–21 TSSA would be qualified with respect to TAHE

Our review of all evidence received prior to 14 December indicated the GGS's expected returns were below the long-term inflation rate and that there was no expectation it should recover a significant asset revaluation loss. The levels of projected returns did not support the accounting treatment of the GGS's cash contribution of $2.4 billion to TAHE as an equity injection.

The TSSA are prepared in accordance with Australian Accounting Standards and particularly AASB 1049 ‘Whole-of-Government and General Government Sector Financial Reporting’. This standard requires contributions from owners to comply with the Australian Bureau of Statistics (ABS) Government Finance Statistics Manual 20151 (GFSM) where it would not conflict with Australian Accounting Standards.

The ABS GFSM states that an equity contribution is recognised unless there is no reasonable expectation that a sufficient rate of return can be generated by that investment, in which case the transfer is expensed. A realistic rate of return is defined in the ABS GFSM as the intention to earn a rate of return that is sufficient to generate dividends (including income tax equivalents) and holding gains or losses at a later date. Holding losses include the final asset revaluation decrement of $20.3 billion, which TAHE incurred on its property plant and equipment assets when it became a for-profit entity and was required to value its assets on the basis of the cash flows they are expected to generate. The lower the commercial returns (cashflows), the greater the potential valuation losses of a for-profit entity's assets. This $20.3 billion valuation loss is disclosed within notes 1 'Significant Accounting policies - TAHE Reform in 2020–21', Note 11 'Equity Investments in Other Public Sector Entities' and Note 14 'Property, Plant & Equipment of the Total State Sector and GGS' financial statements.

Multiple versions of models estimating the GGS's expected rate of return were submitted to the Audit Office by NSW Treasury attempting to demonstrate the commerciality of the GGS's investment in TAHE. Until 14 December 2021, our review of all calculations indicated the existing access and licence fees set up under commercial arrangements effective 1 July 2021 did not support a reasonable expectation that a sufficient rate of return would be earned on the equity injections to TAHE. The existing revenue arrangements reflected a shareholders' expected rate of return of only 1.5 per cent per annum of contributed equity and did not include recovery of the revaluation loss of $20.3 billion incurred in 2020–21.

Having reviewed all evidence provided, the Audit Office communicated to NSW Treasury that unless corrected, the State's accounts would be qualified as the $2.4 billion transfer made by the GGS to TAHE should have been reported as a grant expense instead of an investment. The GGS's estimated rate of return was not sufficient to cover:

  • TAHE's final revaluation loss of $20.3 billion in 2020–21
  • a dollar value equal to, or exceeding a 2.5 per cent rate of return on the equity invested in TAHE (ie: at least equal to the long term inflation rate).

Action was required by the NSW Government to avoid a qualified audit opinion

NSW Government actions avoided a qualified audit opinion related to the GGS’s cash contribution of $2.4 billion to TAHE. To support the TAHE structure as a commercial arrangement earning a sufficient rate of return, the NSW Government agreed to provide additional future funding to TAHE's key government customers (Sydney Trains and NSW Trains) to support increases in access and licence fees to be paid to TAHE.

Shareholding ministers increased their expectations as to TAHE's target average return to the expected long-term inflation rate of 2.5 per cent

On 14 December 2021, a government decision was made resulting in the TAHE shareholding ministers requesting that TAHE re-negotiate the access fees and license fees payable under the Operating Agreements between TAHE and the public operators (Sydney Trains and NSW Trains). The renegotiation was to target an average return to the GGS of 2.5 per cent on the equity contributed. TAHE's existing ten year agreements with the operators provide a mechanism by which the parties meet annually and consult in order to determine the amount of the access fees and licence fees that will be payable in the following financial year.

The revised shareholder expectations for TAHE were published in the 2021–22 'NSW Budget Half Yearly Review' on 16 December 2021. The revised expectations changed the basis of the expected returns on equity from the 10-year Commonwealth bond rate of only 1.5 per cent, to the expected long-term inflation rate of 2.5 per cent. This is consistent with the Reserve Bank's target band and the Commonwealth's Department of Finance's expected return on government investments in other sectors.

The revised shareholder expectations were confirmed in a signed Heads of Agreement

On 18 December 2021, Transport for NSW (TfNSW), TAHE and the operators, Sydney Trains and NSW Trains entered into a Heads of Agreement (HoA). This HoA forms the basis of negotiations to revise the pricing within the existing 10-year contracts and deliver upon the shareholders' expectation of a return of 2.5 per cent per annum of contributed equity. This revised return includes:

  • income earned over the estimated weighted average remaining useful lives of TAHE’s assets
  • recovery of the revaluation losses in 2020–21 on TAHE’s property, plant and equipment assets incurred when TAHE commenced operations as a for-profit entity, albeit the recovery of the revaluation loss is projected to take up to 2052.

The HoA reflects an intention between all parties to revise the contractual agreements to increase future access and license fees by $5.2 billion. This included $1.1 billion for the period FY2023–25, which is reflected in the 2021–22 'NSW Budget Half Yearly Review'. Further detail on the HoA is reported in Section 3 of this report ‘Investment in the Transport Asset Holding Entity’.

NSW Treasury revised its calculations to reflect the increased future returns

Following these changes, NSW Treasury revised its calculations of estimated returns to reflect a cumulative return equivalent to the expected long-term inflation rate, and recovery of the 2021 valuation loss by 2052. The rate of return period is consistent with the weighted average remaining useful life of TAHE's assets. The changes supported the financial reporting treatment of the $2.4 billion transfer from the GGS to TAHE as an investment rather than an expense, even though TAHE is currently heavily reliant on revenues from the public rail operators, Sydney Trains and NSW Trains. If the cash contribution had to be treated as a capital grant expense, it would have reduced the GGS's budget result by $2.4 billion.

The Independent Auditor’s Report includes an emphasis of matter drawing attention to uncertainty relating to the General Government Sector's investment in the Transport Asset Holding Entity (TAHE)

Despite the investment in TAHE being better supported, and the independent auditor's opinion being unqualified, the Independent Auditor’s Report includes an emphasis of matter, which draws attention to the significant uncertainties remaining in relation to the GGS’s equity investment in TAHE. The significant uncertainty is associated with key assumptions that support the recognition by the GGS of its $2.4 billion investment in TAHE during 2020–21.

As at the time of signing the Independent Auditor's Report, there was significant uncertainty with regards to judgements around the commerciality of TAHE's operations because:

  • TAHE’s future estimated access and licence fees, which are critical to its ability to earn a realistic rate of return, remain subject to re-negotiation and re-signing of the current access agreements. The proposed indicative future access and licence fees, which are set out in the HoA are intended to form the basis of the re-negotiation.
  • $1.1 billion in additional funding for TAHE's key customers, Sydney Trains and NSW Trains, was provided in the 2021–22 'NSW Budget Half Yearly Review' consistent with the terms in the HoA. However, this funding only extends to the end of the forward estimates period in 2024–25. There is an additional $4.1 billion required over the following six years, which falls outside of the forward estimates period (up to the end of the 10-year contract period). While this has been communicated to the government's Expenditure Review Committee, it is yet to be provided for in government's budget figures. As TAHE's projections are currently highly dependent on its government customers, it is critical that the government continue to provide sufficient funding to the GGS to support increases in the prices government customers will pay for access to TAHE's assets.
  • A further significant portion of the required returns is earned outside of the 10-year contract period (terminating 30 June 2031). NSW Treasury has estimated $37.9 billion in returns from its investment in TAHE over the period from 1 July 2022 to 30 June 2052, but has not identified the source or means of these returns beyond 2031. Currently, TAHE derives the majority of its revenue from access and licence fee agreements with Sydney Trains and NSW trains, who in turn are both funded by grants to Transport for NSW from the GGS. The projected returns calculated by NSW Treasury beyond 2031 are calculated by assuming a 2.5 per cent growth rate. About 87 per cent of these estimated returns are being earned beyond the ten years, with $32.9 billion estimated over the period 2032–52. There remains risk that:
    • TAHE will not be able to re-contract for access and licence fees at a level that is consistent with current projections
    • future governments' funding to TAHE's key customers will not be sufficient to fund payment of access and licence fees at a level that is consistent with current projections
    • TAHE will be unable to grow its non-government revenues.

Significant accounting issues relating to TAHE are detailed in Section 3 to this report titled ‘Investment in the Transport Asset Holding Entity’. Other significant matters related to the TSSA audit are covered in section 6 to this report titled ‘Key Audit findings’.

Other financial reporting matters

The State extended the date for submission of agency financial statements for audit to provide relief to agencies impacted by the New South Wales' COVID-19 lockdowns

All agencies were given a one-week extension (two weeks in 2019–20) to prepare their financial statements and submit them for audit by 2 August 2021. Further extensions were subsequently approved for the following ten agencies and funds (11 in 2019–20) to submit completed financial statements for audit:

  • Department of Communities and Justice (9 August 2021 for disclosures related to cloud computing costs)
  • Investment NSW (13 August 2021)
  • Jobs for NSW (13 August 2021)
  • TCorp IM Funds (19 August 2021)
  • Lord Howe Island Board (22 October 2021)
  • Department of Customer Service (31 August 2021 for disclosures related to AASB 1059 'Service Concession Arrangements: Grantors')
  • Department of Transport (20 August 2021)
  • Sydney Olympic Park Authority (12 August 2021)
  • Planning Ministerial Corporation (12 August 2021)
  • Transport Asset Holding Entity (16 August 2021).

Additional extensions provided agencies with more time to resolve accounting issues relating to:

  • asset valuations
  • first time implementation of AASB 1059
  • asset transfers and treatment of software as service costs.

The extensions outlined above resulted in a two-week delay submitting the State’s draft consolidated financial statements for audit.

In 2020–21, agency financial statements presented for audit contained 24 errors exceeding $20 million (19 in 2019–20). The total value of these errors was $6.6 billion, a significant increase from the previous year ($1.4 billion in 2019–20)

The graph below shows the number of reported errors exceeding $20 million over the past five years in agencies’ financial statements presented for audit.

The errors resulted from:

  • incorrect application of Australian Accounting Standards and NSW Treasury Policies
  • incorrect judgements and assumptions when valuing non-current physical assets and liabilities
  • human error or lack of oversight.

The completion of the 2020–21 Total State Sector Accounts was significantly delayed as material accounting issues were resolved. These issues related to how the General Government Sector’s (GGS)2 investment in the Transport Asset Holding Entity was accounted for. The key areas of audit concern, which required considerable effort to satisfactorily resolve, included our assessment of:

  • the accounting treatment of funds transferred to TAHE from the GGS, specifically:
    • whether funds transferred to TAHE from the GGS should be considered an equity investment or capital grant expense, with the latter having implication to the presentation of the NSW Government Budget positions. Funds are expensed unless, as an investment, there is a reasonable expectation to generate a sufficient rate of return
    • forming a view as to what a ‘reasonable expectation of a sufficient rate of return on investment3’ should be with respect to the Australian Bureau of Statistics' Government Finance Statistics Manual 2015 (GFSM)
    • the valuation of TAHE’s property, plant and equipment at 30 June 2021
  • whether TAHE was correctly classified as a Public Non-Financial Corporation (PNFC) entity
  • whether, under the agreements in place for the use and price of TAHE's assets, TAHE controlled its property, plant and equipment.

Our assessments were hindered by errors and omissions in information and models provided by NSW Treasury to demonstrate expected returns from TAHE, as well as a lack of timeliness and completeness in their responses to requests for documentation to support NSW Treasury's proposed accounting of government's contributions to TAHE.

Up until 13 December 2021, evidence provided by NSW Treasury to support the treatment of a $2.4 billion equity transfer from the GGS to TAHE did not demonstrate a sufficient rate of return on the State's investment. Instead, the evidence suggested the transfer was of the nature of a capital grant expense, which would impact the GGS budget result. Unless corrected, by either reversing the equity investment to a capital grant expense (impacting the GGS budget result) or providing additional resources to the rail operators to support additional TAHE access and licence fees (adding additional expenses to future GGS budget results), this matter would have caused the State's accounts to have been qualified.

After the Audit Office communicated the likely audit outcome to NSW Treasury, significant changes were made by government from 14 December 2021. Government decisions that avoided qualification of the TSSA included:

  • On 14 December, a government decision approved communicating revised shareholders' expectations of rate of return of 2.5 per cent being the long-term inflation rate, and increased grants to Transport for NSW for the rail operators to pay increased access and licence fees to TAHE to support of the new rate of return (previously 1.5 per cent).
  • On 16 December, the 2021–22 'NSW Budget Half Yearly Review' included an increase in expected returns to be derived through higher access and license fees charged by TAHE. To facilitate these returns, an increased allocation of funds of $1.1 billion was made to Transport for NSW (TfNSW) from 1 July 2022 as part of the forward estimates for the period 2022–25. This was to pay for the proposed increased access and licence fees the operators would be required to pay TAHE.
  • On 18 December, TfNSW, TAHE and the operators Sydney Trains and NSW Trains signed a Heads of Agreement (HoA) forming the basis of negotiations to revise annual operating agreements to facilitate the shareholders’ expected returns of 2.5 per cent of contributed equity. The HoA included indicative access and licence charges to be used as a basis of renegotiation, increasing access fees and licence fees to be paid by Sydney Trains and NSW Trains over the 10-year period from 2022–2031 by a further $5.2 billion. Most of this increase occurs outside the forward estimates. The majority of the additional funding may need to be funded by future governments.

NSW Treasury has projected returns to be earned to 2052 (a period covering the weighted average remaining useful lives of TAHE's assets) as sufficient to recover the revaluation loss of $20.3 billion which arose when TAHE revalued its assets under the income approach. These assets were valued on a discounted cash flow basis as at 30 June 2021.

These key decisions and the circumstances leading up to these changes are detailed later in this section.

Background

On 1 July 2020, the former Rail Corporation of New South Wales (RailCorp), a not-for-profit entity, was renamed the Transport Asset Holding Entity of New South Wales (TAHE) transitioning to a for-profit statutory State-Owned Corporation under the Transport Administration Act 1988. There was no change in the structure of TAHE as a new entity was not created. Ownership remains fully with the government. TAHE, and the former RailCorp, were both classified as Public Non-Financial Corporation (PNFC) entities within the Total State Sector Accounts. TAHE was not a newly created entity, nor was it the result of a change in administrative re-arrangements (such as Machinery of Government change).

Prior to 1 July 2015, the government paid appropriations to TfNSW, a GGS agency, to construct transport assets. When completed, these assets were granted to RailCorp, a not for-profit entity within the PNFC sector. The grants to RailCorp were recorded as an expense in the State’s GGS budget result and in the NSW Total State Sector Accounts (TSSA).

From 1 July 2015, the government announced the creation of TAHE (a dedicated asset manager). Funding for new capital projects was to be provided through equity injections, even though the business model was yet to be determined. NSW Treasury initially set a timetable for finalising the business model, operating model and contracts for the use of TAHE's assets of 1 July 2019.

Contributions paid to TAHE by the GGS were treated as equity investments from July 2015 forward. This treatment continued, despite delays in settling the business model. In 2020, the Audit Office raised a high risk finding due to the significance of the financial reporting impacts and business risks for NSW Treasury and TAHE.

The business model eventually adopted was one whereby:

  • The GGS invests in TAHE with an expectation of a sufficient rate of return.
  • TAHE charges the operators (predominantly Sydney Trains and NSW Trains) to use network and rolling stock to deliver services. The operators remain responsible for both the delivery of the services and the maintenance and safe operation of the assets. The operators are primarily funded by TfNSW through grants.
  • The GGS grants funds to operators, which allows them to pay access fees to TAHE. The amount of these grants impacts the budget result.
  • TAHE pays a return back to GGS by way of dividends and tax equivalents. The return may also include holding gains and losses on the fair value of the net assets of TAHE.

TAHE earns relatively small amounts of income from transactions with the private sector. While the TAHE Board envisages that, over time, they will enhance the commerciality of TAHE’s operations, it is currently highly dependent on revenues from government contracts (over 80 per cent). The circularity in flow of funds between transport agencies in the GGS and PNFC sectors is shown in the diagram below:

The government continues to respond to the impacts of the COVID-19 pandemic on New South Wales through its economic stimulus measures

The COVID-19 pandemic continues to significantly impact the State’s finances, reducing revenue and increasing expenses especially in sectors directly responsible for responding to the COVID-19 pandemic, such as Health. Over 2020–21, the government allocated an additional $5.6 billion to agencies as part of its economic stimulus and pandemic response. Measures included:

  • $1.8 billion in health measures including essential medical equipment purchases, vaccine distribution, quarantine, contract tracing and maintaining clinical health capacity (such as intensive care units)
  • $508 million in additional cleaning services primarily to the Department of Education and Transport for NSW
  • $500 million as part of the ‘Dine & Discovery NSW’ voucher program to the Department of Customer Service
  • $350 million in combined land tax relief and small business recovery grants to Department of Customer Service and NSW Treasury respectively.

Around $4.5 billion of this package was spent in 2020–21, leaving $1.1 billion unspent and carried forward into 2021–22. The graph below shows the total allocation and spend by cluster for 2021 compared to their target spend.

Deficit of $7.1 billion compared with a budgeted deficit of $16 billion

The outcomes of the government’s overall activity and policies are reflected its net operating balance (Budget Result). This is the difference between the cost of general government service delivery and the revenue earned to fund these sectors.

The General Government Sector, which comprises 204 entities, generally provides goods and services funded centrally by the State.

In addition to the 204 entities within the General Government Sector, a further 98 government controlled businesses are included within the consolidated Total State Sector financial statements. These businesses generally provide goods and services, such as water, electricity and financial services for which consumers pay for directly.

The Budget Result for the 2020–21 financial year was a deficit of $7.1 billion compared to an original forecast of a budget deficit of $16 billion.

Revenues increased $5.6 billion to $91.8 billion

In 2020–21, the State’s total revenues increased by $5.6 billion to $91.8 billion, 6.5 per cent higher than previous year. A decrease of 0.3 per cent was recorded in 2019–20. The main contributors to the increase in the State's revenues were an increase in taxation revenue of $4.6 billion and an increase in grants and subsidies of $1.4 billion when compared to the prior financial year.

Taxation revenue increased by 15.3 per cent

Taxation revenue increased by $4.6 billion, mainly due to:

  • $2.9 billion higher stamp duties collected from property sales driven by:
    • $2.7 billion increase in contracts and conveyance duties (transfer duties) from both higher transaction volumes and strong property price growth during 2020–21
    • $200 million increase in motor vehicle registration duty driven by increases in new vehicle sales
  • $520 million higher Gambling and Betting Taxes was earned as 2019–20. The previous year's revenues were impacted by club and hotel closures due to COVID-19. The operation of these venues in 2020–21 returned to normal for most of the year resulting in higher club gaming tax revenue of $216 million and hotel gaming taxes of $265 million
  • $439 million higher collections of payroll taxes. The previous year's revenues were impacted by tax relief measures implemented by the government in response to COVID-19. Lower payroll tax was collected in 2019–20 as employment levels dropped during the State’s first lock down
  • $416 million higher land tax revenues, driven by an average 3.2 per cent increase in valuer general land values, which are the basis for determining land tax values.

Stamp duties of $11.7 billion remains the largest source of taxation revenue, $2.9 billion higher than payroll tax of $8.8 billion, the second-largest source of taxation revenue.

Expenses increased $4.1 billion to $101 billion

The State’s expenses increased 4.3 per cent compared with 2019–20. Most of the increase was due to higher employee expenses, depreciation and amortisation, other operating costs and grants and subsidies expense.

Employee expenses, including superannuation, increased 3.6 per cent to $44.1 billion

Salaries and wages increased to $36.3 billion ($34.8 billion in 2019–20). This was mainly due to increases in staff numbers and an average increase of approximately three per cent in the cost of NSW's employees across the sector. Salaries and wages for the Education and Health sectors increased by $511 million and $619 million respectively.

The Health sector employed an additional 4,893 full time staff in 2020–21 (2,763 in 2019–20) and incurred an extra $28 million in overtime mainly in response to COVID-19. Education increased staff numbers by 2,418 full time equivalents in 2020–21 (4,866 in 2019–20). This year, the health and education sectors received a 0.3 per cent award increase in pay rates.

The Public Service Commission (PSC) noted in the ‘State of the NSW Public Sector Report, 2021’ that the government sector senior executive headcount increased by 347 to 3,680 (3,333 in 2019–20). The Transport cluster represented the majority of the increase in the government sector's senior executive headcount, with an increase of 182. The PSC report noted the increase was due to the growing portfolio of major transport infrastructure projects.

Historically, the government wages policy aims to limit growth in employee remuneration and other employee related costs to no more than 2.5 per cent per annum.

Depreciation and amortisation expense increased 7.6 per cent to $10.3 billion

Depreciation and amortisation increased to $10.3 billion in 2020–21 ($9.6 billion in 2019–20). This increase was mainly driven by the depreciation of completed infrastructure projects including the State’s WestConnex M8 and M5 East Motorways, and other road projects such as Woolgoolga to Ballina project. This year also includes twelve months of depreciation relating to the CBD and South-East Light Rail versus six months in the previous financial year.

Furthermore, the first time adoption of AASB 1059 ‘Service Concession Arrangements’ resulted in the State recognising $45.4 billion of service concession assets in its capacity as grantor under arrangements with operators. More than 87 per cent of this balance was recognised by the Transport cluster. These assets are valued at current replacement cost and are depreciated on an annual basis. A service concession arrangement is an arrangement whereby the government as grantor, contracts with an operator to develop (or upgrade), operate and maintain the grantor's public service assets such as roads, bridges or hospitals. The grantor controls or regulates what services the operator must provide using the assets, to whom, and at what price. The grantor also retains any significant residual interest in the assets at the end of the arrangement. Further details about AASB 1059 are included in the ‘Implementation of new accounting standards’ section of this report.

Grants and subsidies increased $1.5 billion to $15.6 billion

The increase in grants and subsidies is due to payments made by the State in supporting businesses and local communities in response to COVID-19. These mainly included $240 million in Dine & Discover voucher payments, $156 million in land tax relief assistance, $160 million increase in grants to non-government schools (including $31 million to support Covid intensive learning support programs), and $109 million relating to small business grant payments.

The State also transferred $592 million in newly constructed assets to local councils. These mainly related to $378 million in assets transferred following completion of WestConnex stage 2 and $180 million from Northern Roads.

Other operating expenses increased two per cent to $27.5 billion

Operating expenses increased to $27.5 billion in 2020–21 ($26.9 billion in 2019–20) due to higher operating activities as agencies responded to the pandemic.

Supplies and Other Services increased by $1.7 billion. This was mainly due to funding of $533 million in hotel quarantine and associated services, and $495 million in medical equipment for the health sector.

Inventories consumed increased by $266 million. This included $217 million in COVID-19 medical equipment that was written off because it had expired or did not meet the TGA regulatory standards. Contractor expenses increased by $306 million because of increased capital works activity, primarily in the Transport sector.

The increase was offset by $1.6 billion in lower insurance claims expense. In 2019–20 financial year, higher claims were made in respect to natural disaster events, including bush fires.

Health costs remain the State’s highest expense

Total expenses of the State were $101 billion ($96.4 billion in 2019–20). In 2020–21, Health remains the highest contributor of expenses for the State with $25.7 billion ($24.2 billion in 2019–20). Education remains the second highest contributor of expenses reporting $18.4 billion in 2020–21 ($17.5 billion in 2019–20).

The following sectors have the highest expenses as a percentage of total State expenses:

  • Health – 25.6 per cent (25.1 per cent in 2019–20)
  • Education – 18.3 per cent (18.2 per cent in 2019–20)
  • Transport – 14.5 per cent (13.3 per cent in 2019–20).

Assets grew by $12.3 billion to $526 billion

The State’s assets include physical assets such as land, buildings and infrastructure, and financial assets such as cash, and other financial instruments and equity investments. The value of total assets increased by $12.3 billion to $526 billion. This was a 2.4 per cent increase compared with 2019–20, mostly due to changes in asset carrying values.

Valuing the State’s physical assets

State’s physical assets valued at $391 billion

The value of the State’s physical assets increased by $1.7 billion to $391 billion in 2020–21 ($37.9 billion increase in 2019–20). The State’s physical assets include land and buildings ($172 billion), infrastructure systems ($202 billion) and plant and equipment ($16.7 billion).

The movement in physical asset values between years includes additions, disposals, depreciation and valuation adjustments. Other movements include assets reclassified to held for sale and other opening balance adjustments.

Liabilities increased $16.4 billion to $291 billion

The State borrowed additional funds in response to COVID-19

The State’s borrowings rose by $15.8 billion to $134 billion at 30 June 2021. This accounted for most of the increase in the State’s total liabilities.

The value of TCorp bonds on issue increased by $16.8 billion to $114 billion, which largely funded the State's capital expenditure and response to the COVID-19 pandemic.

TCorp bonds are traded in financial markets and are guaranteed by the NSW Government.

Over 2020–21, TCorp continued to take advantage of lower interest rates, buying back short-term bonds and replacing them with longer dated debt. This lengthens the portfolio matching liabilities with the funding requirements for infrastructure assets.

The State’s fiscal objective published in the 2021–22 Budget Papers is to repair the operating position by returning the budget to surplus by 2024–25 and rebuilding balance sheet capacity by bringing net debt down towards seven per cent of Gross State Product (GSP) over the medium-term. The State measures net debt as the sum of deposits held, government securities, loans payable and other borrowings, less the sum of cash and deposits, advances paid and investments, loans receivable and placements.

The chart below shows the actual net debt to GSP for NSW compared to the Commonwealth net debt to Gross Domestic Product (GDP) over the past six years. The trend shows an increase in net debt, particularly in the past two years, which is mainly driven by additional borrowings needed to fund stimulus measures when responding to COVID-19 and natural disaster relief.

GSF Act and GSF Regulation

Financial reporting provisions in the Government Sector Finance Act 2018 (GSF Act) have now commenced

From 1 July 2021, the Public Finance and Audit Act 1983 (PF&A Act) financial reporting provisions were repealed. Agencies prepared their 2020–21 financial statements under Part 7 of the GSF Act. They were audited under the Government Sector Audit Act (GSA Act). The GSF Act requires the timeframe for annual financial statement submission be specified in the Treasurer’s Directions.

Under the GSF Act, all reporting GSF agencies are required to prepare annual financial statements, unless exempt from the definition of a reporting agency under the Government Sector Finance Regulation 2018 (GSF Regulation). Those agencies exempt from preparing financial statements include certain small agencies, Crown Land Managers, special purpose staff agencies and retained State interests. These agencies must meet prescribed requirements or thresholds and self-assess each year to determine whether they remain exempt against the criteria in the GSF Regulation.

Most of the financial reporting provisions of the GSF Act have now commenced except for requirements concerning special deposit accounts (SDA) and special purpose financial reports, which are scheduled to commence on 1 July 2023, subject to approval from the Governor.

The GSF Act now includes most of the provisions applicable to GSF agencies, as requirements for appropriations, expenditure, financial services, and other matters were enacted on 1 December 2018 and 1 July 2019.

Once fully commenced, the GSF Act will consolidate and replace reporting provisions of four Acts:

  • PF&A Act
  • Public Authorities (Financial Arrangements) Act 1987
  • Annual Reports (Departments) Act 1985
  • Annual Reports (Statutory Bodies) Act 1984.

GSA Act and GSA Regulation

The PF&A Act was renamed the GSA Act on 1 July 2021 and now only contains provisions relating to the Auditor-General and the Audit Office, the audit of government sector finances and governance of the Public Accounts Committee.

Of note in the renamed GSA Act is that:

  • a new principal object was added that specifically provides the Auditor-General is an independent and accountable statutory officer
  • the previous financial reporting provisions in the PF&A Act were repealed as the financial reporting provisions are contained in Part 7 of the GSF Act. As a result, there are no longer financial reporting provisions in the GSA Act
  • a new section 34 was added, which contains the requirements for the audit of State sector agencies’ financial statements. These were previously contained in two separate sections.

The GSA Regulation commenced on 1 July 2021, replacing the Public Finance and Audit Regulation 2015 (PF & A Regulation). The GSA Regulation contains the list of entities, funds and accounts prescribed for the purpose of audits under the GSA Act.

Inconsistencies exist in the GSF Act and GSA Act related to key statutory timeframes

There are inconsistencies between key statutory timeframes imposed on the Treasurer and Auditor-General in the GSF Act and GSA Act which has been brought to the attention of NSW Treasury. The inconsistencies identified include:

  • Section 34(3)(a) of the GSA Act defines the audit period for the Statements be as soon as practicable after the Auditor-General is given the Statements. This appears to be inconsistent with section 49(3) of the GSA Act, which requires that the Auditor-General, on or before 22 October transmit the Statements and audit report to the Treasurer. Neither provision is a paramount provision.
  • Section 49(3) of the GSA Act also appears to be inconsistent with section 52(1) of the GSA Act which provides that the Statements are to be given to the Auditor-General in accordance with section 7.17 of the GSF Act. Section 7.17 of the GSF Act requires that the Statements are to be prepared and given to the Auditor-General by an agreed date to enable the audit of the Statements. Part 7 of the GSF Act is a paramount provision under section 1.8 of the GSF Act, which means the requirements in section 7.17 of the GSF Act prevail.

There are also inconsistencies in key statutory reporting timeframes imposed on the Treasurer under the GSF Act.

The audited Statements are a key accountability mechanism that provides information on the State’s financial performance and position. Ambiguity in the statutory reporting timeframes could impact on the future timely provision of this information to Parliament. As noted at the beginning of this report, the delay in issuing the audit report for the 30 June 2021 Statements was due to NSW Treasury’s resolution of accounting issues that were material to the Statements, in particular the treatment of the General Government Sectors investment in TAHE during 2020–21. NSW Treasury's management letter will include a high risk finding with regards to the inconsistencies between the GSF Act and GSA Act.

Recommendation

NSW Treasury should seek legislative amendments in Parliament to resolve the inconsistencies in the GSF Act and GSA Act relating to key statutory reporting time frames.

Appropriations framework

NSW Treasury lacks a framework to monitor and provide assurance to ministers that they are in compliance with their appropriation authority

The GSF Act requires that money not be paid out of the Consolidated Fund except under the authority of an Act, such as the annual Appropriation Act or GSF Act. This means a minister is only authorised to spend out of the Consolidated Fund the amount they have been appropriated by the relevant Act(s).

Generally, money is authorised to be paid out of the Consolidated Fund either through:

  • The Annual Appropriation Act - this is an act to appropriate out of the Consolidated Fund sums for the services of the government for the relevant financial year. These appropriations are made to the responsible ministers of principal departments, Special Offices and certain SDAs.
  • The GSF Act - this act allows the responsible minister of a GSF agency to be given an appropriation out of the Consolidated Fund, at the time the agency receives or recovers any deemed appropriation money. Deemed appropriation money is defined in section 4.7(3) of the GSF Act.

Ministers can delegate and sub-delegate appropriation expenditure functions to accountable authorities and officers of GSF agencies. Any spending by accountable authorities and officers of GSF agencies in excess of the amount appropriated to their relevant minister would be made contrary to section 4.6(1) of the GSF Act.

The Budget Papers are an additional mechanism by which the government controls the level of expenditure by agencies both at the individual and departmental administrative cluster level. The Budget Papers set an administrative limit imposed by the government. Separately, the Treasurer can issue a Budget control authority under section 5.1 of the GSF Act. A Budget control authority can regulate expenditure of money by GSF agencies in a variety of ways, as set out in section 5.1(2) of the GSF Act.

In July 2021, NSW Treasury advised the Audit Office that it had received advice from the Crown Solicitor's Office, in January 2021, that payments between agencies in different administrative clusters would not meet the definition of a 'deemed appropriation' under the GSF Act by the receiving agency. This applies to money paid and received by two agencies across different administrative clusters that continue to hold the money in the Consolidated Fund. These intra-government receipts increase the amount an agency has available to spend, without there being a corresponding increase in the responsible minister’s appropriated expenditure limits, thus increasing the risk an agency’s expenditure could cause a minister to exceed their appropriated expenditure authority.

After being made aware of the issue, the Audit Office worked with NSW Treasury officers to clarify potential implications. The Audit Office also obtained further advice from the Crown Solicitor’s Office to clarify certain aspects of the appropriations framework more broadly. In the advice to the Audit Office, the Crown Solicitor advised that an agency is not subject to its own legally appropriated expenditure limit (assuming it is not subject to any annual spending limit imposed through an instrument of delegation or a budget control authority issued by the Treasurer under section 5.1 of the GSF Act). In effect, because responsible ministers are given appropriations, these legal expenditure limits, rest in aggregate, with the principal department and agencies the minister is responsible for. The advice also confirmed:

  • a deemed appropriation for the services of an agency would ordinarily be available for the services of other agencies, if the officers of the other agencies had a delegation from the minister(s) to expend the deemed appropriation and funds remained available under those deemed appropriations
  • that the ‘exhaustion’ of a minister’s appropriation may be precipitated by one agency’s level of expenditure in the financial year, but the effect is that the relevant appropriation is exhausted for all agencies (and their officers) that may otherwise rely on it
  • whether expenditure by an agency occurred beyond the scope of its authority would require a progressive examination of the total amounts expended from the minister’s appropriation
  • amounts expended from the Consolidated Fund without the authority of an appropriation are spent contrary to section 4.6(1) of the GSF Act
  • a minister is responsible to Parliament for (i) the manner in which appropriations are expended, and (ii) any ‘overspends’ (that is, expenditure without authority) by agencies for which they are responsible.

Determining whether expenditure has occurred without the authority of an appropriation is complex and it is not possible for an individual agency to monitor or determine at what ‘point in time’ expenditure has been incurred in excess of the minister’s appropriation authority. As noted earlier, there are mechanisms in place to manage agencies' administrative expenditure limits set by the Budget Papers, but there is no mechanism in place to ensure expenditure by agencies does not exceed a minister’s appropriation authority received under the annual Appropriations Act and GSF Act.

Recommendation

NSW Treasury should ensure a framework exists to monitor and provide assurance to ministers that expenditure incurred across a financial year by agencies under the relevant minister’s coordination does not exceed the appropriation authority conferred by the annual Appropriation Act and the GSF Act.

In addition, principal departments and agencies that hold money in the Consolidated Fund are required by Australian Accounting Standard AASB 1058 'Income of Not-for-Profit Entities' and NSW Treasury Circular TC20/08 'Mandates of options and major policy decisions under Australian Accounting Standards' to prepare a Summary of Compliance in their financial statements. The Summary of Compliance applies to agencies that obtain part or all of their spending authority from a Parliamentary appropriation. It is intended to provide information on the amounts appropriated or authorised for an agency’s use and whether those expenditures were authorised. There remains uncertainty around how the Crown Solicitor’s Office advice received by the Audit Office impacts these disclosures, as the total spending authority given by Parliamentary appropriations and expenditure against these appropriations cannot generally be attributed to an individual agency. Such a scenario is not contemplated by the relevant Australian Accounting Standard. NSW Treasury's management letter will include high risk findings about improving mechanisms in place to manage agencies administrative expenditure limits, uncertainties related to appropriation spending authority on agencies summary of compliance disclosures.

Recommendation

NSW Treasury should assess how the requirement to prepare a Summary of Compliance under Australian Accounting Standards impacts relevant principal departments and agencies' financial statement disclosures.

Delegations to incur expenditure

Further to last year's reporting, some agencies have again spent monies without an authorised delegation

The delegation to incur expenditure is an important accountability mechanism of responsible government.

Last year’s Report on State Finances reported instances where government agencies did not understand or correctly apply the requirements of the GSF Act for deemed appropriations, resulting in some agencies spending deemed appropriations money without an authorised delegation from the relevant minister(s) as required by sections 4.6(1) and 5.5(3) of the GSF Act.

This year’s financial audits identified that further agencies: TAFE Commission, Multicultural NSW and the Office of the Ageing and Disability Commissioner spent money received from an annual Appropriation and/or deemed appropriation money without an authorised delegation from the relevant minister(s), as required by sections 4.6(1) and 5.5(3) of the GSF Act. NSW Treasury's management letter will include high risk issues about improving mechanisms in place to ensure agencies have appropriate delegations in place to spend Appropriation and/or deemed appropriation money.

In addition, the audit of the Jobs for NSW Fund (the Fund) special purpose statements identified that five payments from the Fund were authorised by an officer without the necessary delegation from the minister as required by section 14 of the Jobs for NSW Act 2015 and sections 5.5(2) and 5.5(3) of the GSF Act.

Recommendation

Given the continued instances of non-compliance, NSW Treasury needs to promptly improve the guidance it provides agencies to ensure that expenditure of public monies is properly supported by authorised delegations.

Implementation of new accounting standards

This year, the State implemented the requirements of AASB 1059

AASB 1059 ‘Service Concession Arrangements: Grantors’

AASB 1059 is an Australian Accounting Standard that requires public sector entities (grantors) that enter service concession arrangements with private sector operators for the delivery of public services recognise service concession assets and liabilities in their financial statements. The standard was effective from 1 July 2020.

AASB 1059 requires a grantor to:

  • recognise an asset provided by the operator as a service concession asset if the grantor controls the asset
  • initially measure the service concession asset at current replacement cost (CRC) in accordance with AASB 13 ‘Fair Value Measurement’
  • recognise a corresponding liability measured initially at the fair value (CRC) of the service concession asset, adjusted for any consideration between the grantor and the operator
  • make sufficient disclosure in the financial statements so that users can understand the nature, amount and timing of assets, liabilities, revenue and cash flows arising from these.

The adoption of AASB 1059 increased the State’s total assets and liabilities by $19.5 billion and $19.6 billion respectively, with net worth reducing by $131 million at 1 July 2019

The State adopted a modified retrospective approach when adopting AASB 1059 and recognised and measured service concession assets and liabilities at the date of initial application of 1 July 2019, with any net adjustments recognised in accumulated funds at that date. This means comparatives were restated to reflect the impact of AASB 1059.

Most of the service concession assets recognised by the State related to Property, Plant & Equipment, in particular infrastructure assets.

Agencies had to devote significant effort to implement AASB 1059 and ensure their 2020–21 financial statements materially complied with the standard's requirements. Last year, the Audit Office highlighted advance preparation was key to ensuring agencies effectively transitioning to this new standard. Despite the new standard being issued well in advance of its commencement date, Sydney Water Corporation, Department of Customer Service, Transport for NSW (TfNSW) and TAHE did not prepare sufficiently for their respective implementations.

Whilst most agencies in 2019–20 had commenced assessing their existing commercial arrangements to determine whether they were within the scope of AASB 1059, calculating and posting the accounting entries to support the implementation of this standard was delayed for TfNSW. TfNSW had not finalised its opening balance adjustments in time for the Audit Office’s early close review. Critical assessments of AASB 1059 to identify the accounting implications for the Transport sector, in particular TfNSW and TAHE were still being considered as late as 30 September 2021.

Restart NSW

Restart NSW was established in 2011 to fund the State’s major infrastructure projects

Restart NSW funds Rebuilding NSW, the government’s 10-year plan to invest $23 billion in new infrastructure. Its infrastructure projects, including Sydney Metro West and Parramatta Light Rail, are primarily funded by proceeds from the government’s asset recycling program. The Restart Fund had a balance of $12.4 billion at 30 June 2021 ($15 billion in 2019–20).

The Fund paid $3.8 billion for infrastructure projects in 2020–21 ($4.3 billion in 2020–21). The largest payments were for transport projects, including Sydney Metro West, Parramatta Light Rail, and contributed $319 million of the $2.4 billion equity contribution to the Transport Asset Holding Entity (TAHE).

The funds are invested in the NSW Infrastructure Future Fund (NIFF), which is allowed under the Restart NSW Fund Act 2011 (Restart Act). The NIFF is an investment vehicle for the fund to help the NSW Government meet its infrastructure objectives and this fund is managed by TCorp. In 2020–21, the fund earned a net return of 7.9 per cent, higher than its annual benchmark return of 4.2 per cent, benefiting from improved returns in financial markets over 2020–21.

The fund directed 30.1 per cent of its payments towards rural and regional infrastructure projects in 2020–21

The Restart Act requires the fund to report on the percentage of payments directed to rural and regional infrastructure projects and whether this represents at least 30 per cent of the total payments from the fund. The Restart NSW Fund Amendment (Rural and Regional Infrastructure Funding) Bill 2020 introduced in Parliament in 2020 would amend the Restart Act by requiring at least 30 per cent of the total payments each financial year and for the life of the Restart NSW Fund be made on infrastructure projects in rural and regional areas.

This year the fund exceeded its target of directing at least 30 per cent of funding towards rural and regional infrastructure projects. However, since the funds’ commencement, only 23 per cent of total payments went towards rural and regional infrastructure projects. Current projections for the life of the fund indicate only 27.5 per cent of funding will be spent on rural and regional projects, which is below the funds target of 30 per cent target for the life of the fund.

Audit Office’s work plan for 2021–22

The Audit Office’s 2021–22 work plan focuses on the State’s response, recovery and impact from the COVID-19 pandemic and natural disaster emergencies

The COVID-19 pandemic continues to have a significant impact on the people and the public sector of New South Wales. Government continues to assist communities in their recovery from the 2019–20 bushfires and subsequent flooding. The scale of government responses to these events has been significant and has required a wide-ranging response involving emergency response coordination, service delivery, governance and policy.

Significant resources have been directed toward these responses, and in assisting rebuilding and economic recovery. Some systems and processes have changed to reflect the need for quick responses to immediate needs. The increasing and changing risk environment presented by these events has meant that we have recalibrated and focused our efforts on providing assurance on how effectively aspects of these emergency responses have been delivered. This includes financial and governance risks arising from the scale and complexity of government responses to these events.

While these emergencies are having a significant impact today, they are also likely to continue to have an impact into the future. We will take a phased approach to ensuring that our work addresses the following elements of the emergencies and government responses:

Appendix one – Prescribed entities

Appendix two – Legal opinions

Appendix three – TSS sectors and entities
 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Customer Service 2021

Customer Service 2021

Finance
Asset valuation
Cyber security
Financial reporting
Information technology
Internal controls and governance
Shared services and collaboration

This report analyses the results of our audits of the Customer Service cluster agencies for the year ended 30 June 2021.

Our preferred approach is to table the ‘Report on State Finances’ in Parliament before any other cluster report. This is because the ‘Report on State Finances’ focuses on the audit results and observations relating to the Total State Sector Accounts, in effect a consolidation of all government agencies. This year the ‘Report on State Finances’ has been delayed due to significant accounting issues being considered in the Total State Sector Accounts and which may impact the Treasury and Transport clusters.

As there are no outstanding matters relating to audits in the Customer Service cluster impacting the Total State Sector Accounts we have decided to break with normal practice and table this cluster report ahead of the ‘Report on State Finances’.

What the report is about

The results of Customer Service cluster agencies' financial statement audits for the year ended 30 June 2021.

What we found

Unmodified audit opinions were issued for all Customer Service cluster agencies.

The number of monetary misstatements decreased from 48 in 2019–20 to 46 in 2020–21.

Seven out of eight agencies did not complete all mandatory early close procedures.

What the key issues were

Upon the implementation of AASB 1059 'Service Concession Arrangements: Grantors', the Department of Customer Service (the department) recognised a service concession asset, the land titling database, totalling $845 million for the first time at 1 July 2019.

The department reported several retrospective corrections of prior period errors.

The 2020–21 audits identified three high-risk and 59 moderate risk issues across the cluster. The high-risk issues were related to:

  • the Department of Customer Service – internal control qualifications and control deviations in GovConnect service providers
  • the Department of Customer Service – significant control deficiencies in information technology change management controls
  • Rental Bond Board – uncertainties in the accounting treatment of rental bonds.

The percentage of repeat issues we report to management and those charged with governance in management letters increased from 29 per cent in prior year to 42 per cent in 2020–21 while the number of items decreased from 94 to 93.

The magnitude and number of internal control exceptions in GovConnect service providers increased resulting in additional audit procedures to address the risks of fraud and errors in the financial statements.

What we recommended

The department should improve the validation process of key valuation assumptions and inputs provided by the private operator NSW Land Registry Services. It should revisit its accounting treatment of new land titling records.

The department should ensure GovConnect service providers prioritise the remediation of control deficiencies in information technology services.

The department should continue to improve controls in cyber security management.

Cyber Security NSW and NSW Government agencies need to prioritise improvements to their cyber security resilience as a matter of urgency.

The New South Wales Government Telecommunications Authority should improve its fixed assets management and financial reporting process to accommodate its growing fixed assets profile.

Fast facts

The Customer Service cluster aims to plan, prioritise, fund and drive digital transformation and customer service across every cluster in the NSW Government.

  • $3.9b total expenditure incurred in 2020–21 
  • $34.1b total administered income managed on behalf of the NSW Government in 2020–21
  • 100% unqualified audit opinions were issued on agencies' 30 June 2021 financial statements 
  • 3 high-risk management letter findings were identified
  • 46 monetary misstatements were reported in 2020–21
  • 42% of reported issues were repeat issues.

This report provides Parliament and other users of the Customer Service cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision-making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Customer Service cluster (the cluster) for 2021.

Section highlights

  • Unqualified audit opinions were issued on the financial statements of cluster agencies.
  • The number of reported misstatements has decreased from 48 in 2019–20 to 46 in 2020–21.
  • Agencies could do more work to improve the quality and timeliness of completing mandatory early close procedures.
  • The Department of Customer Service implemented the new accounting standard AASB 1059 'Service Concession Arrangements: Grantors', which resulted in recognition of a service concession asset of $845 million at 1 July 2019. The valuation of land titling database requires significant judgements and estimations.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision-making.

This chapter outlines our observations and insights from our financial statement audits of agencies in the Customer Service.

Section highlights

  • The 2020–21 audits identified three high-risk and 59 moderate risk issues across the cluster. Twenty-six moderate risk issues were repeat issues. The most common repeat issues related to information technology controls around user access management.
  • The magnitude and number of internal control qualification issues from GovConnect service providers have increased. Ineffective controls at service providers increase the risk of fraud, error and security to data. Urgent attention is required to remediate the internal control exceptions in information and technology services.
  • The NSW Public Sector's cyber security resilience needs urgent attention. Cyber Security NSW and NSW Government agencies need to prioritise improvements to their cyber security resilience as a matter of urgency.

Findings reported to management

Forty-two per cent of findings reported to management were repeat issues

Breakdowns and weaknesses in internal controls increase the risk of fraud and error. Deficiencies in internal controls, matters of governance interest and unresolved issues were reported to management and those charged with governance of agencies. The Audit Office does this through management letters, which include observations, related implications, recommendations and risk ratings.

In 2020–21, there were 93 findings raised across the cluster (94 in 2019–20). Forty-two per cent of all issues were repeat issues (29 per cent in 2019–20).

The most common repeat issues related to weaknesses in controls over information technology user access administration.

A delay in implementing audit recommendations increases the risk of intentional and accidental errors in processing information, producing management reports and generating financial statements. This can impair decision-making, affect service delivery and expose agencies to fraud, financial loss and reputational damage. Poor controls may also mean agency staff are less likely to follow internal policies, inadvertently causing the agency not to comply with legislation, regulation and central agency policies.

The table below describes the common issues identified across the cluster by category and risk rating. 

Risk rating Issue
Information technology
High3
1 new,
1 repeat

The financial audits identified the need for agencies to improve information technology processes and controls that support the integrity of financial data used to prepare agencies' financial statements. Of particular concern are issues associated with:

  • internal control exceptions in information and technology services provided by GovConnect service providers
  • inadequate change management controls
  • poor user access administration and no monitoring of privileged user activities
  • insufficient cybersecurity controls and processes.

High-risk issues are discussed later in the chapter.

Moderate2
5 new,
8 repeat

Low1
7 new,
5 repeat

Internal control deficiencies or improvements

Moderate2
5 new,
3 repeat

The financial audits identified internal control weaknesses across key business processes, including:

  • lack of documentation support for payroll transactions
  • untimely removal of unused transaction negotiation authority facility and old bank signatories
  • inadequate fixed asset management controls including timely capitalisation of project overhead costs.

 Low1
3 new,
2 repeat

Financial reporting

High3
1 new

The financial audits identified opportunities for agencies to strengthen financial reporting, including:

  • uncertainties in legislation to support accounting of rental bonds as funds held in trust
  • improvements required in lease accounting including the review of extension options, assessing indicators of impairment and reviewing the lease reports for completeness and accuracy 
  • the removal of fully depreciated assets in the fixed asset register was not timely
  • the quality and timeliness of completing early close procedures required improvement.

High-risk issues are discussed later in the chapter.

Moderate2
9 new,
8 repeat

Low1
7 new,
3 repeat

Governance and oversight
Moderate2
10 new,
3 repeat

The financial audits identified opportunities for agencies to improve governance and oversight processes, including:

  • renewing or finalising service arrangement agreements between agencies were required 
  • lack of formalised documentation regarding arrangements with external providers for leasing and use of assets.
Low1
3 new
Non-compliance with key legislation and/or central agency policies
Moderate2
4 new,
4 repeat

The financial audits identified the need for agencies to improve its compliance with key legislation and central agency policies, including:

  • non-compliance with contract and procurement management policy, including the use of purchasing cards
  • non-compliance with TC 21-02 'Statutory Act of Grace Payments'
  • annual leave in excess of 30 days where Circular 2020-12 requires agency heads to reduce employee recreation leave balances to 30 days or less.
Low1
1 repeat

4 Extreme risk from the consequence and/or likelihood of an event that has had, or may have a negative impact on the entity.
3 High-risk from the consequence and/or likelihood of an event that has had, or may have a negative impact on the entity.
2 Moderate risk from the consequence and/or likelihood of an event that has had, or may have a negative impact on the entity.
1 Low risk from the consequence and/or likelihood of an event that has had, or may have a negative impact on the entity.
Note: Management letter findings are based on management letters issued to agencies.

2020–21 audits identified three high-risk findings

High-risk findings, including repeat findings, were reported at the following cluster agencies. One of the 2019–20 high-risk findings were not resolved.

Agency Description
2020–21 findings  
Department of Customer Service
Repeat finding:
Qualifications and control deviations in GovConnect NSW controls assurance reports

The GovConnect information technology general controls (ITGC) provided by the department, Infosys and Unisys were qualified in 2020–21. The key controls over user access, system changes and batch process failed in all ITGC reports. Most of these deviations were not mitigated or sufficiently mitigated to address the risk of unauthorised user access.

The control deficiencies in ITGC increase:

  • the risk of unauthorised transactions, system and configuration changes (workflow approvals, three-way match etc.) and modifications to the system reports
  • incomplete, invalid and inappropriate system access, segregation of duties controls and system reports for the customers using the SAPConnect.

The role of the department has changed significantly from a coordinating agency on behalf of GovConnect customers to a GovConnect IT service provider. It is leading a new IT operating model called ‘Service Integration and Application Management’ (SIAM) to strengthen governance and improve performance of GovConnect service providers. The Department is responsible for the remediation of control deficiencies and continuous improvement in the GovConnect environment.

This matter was assessed as high-risk, if not adequately addressed, it had the potential to result in material fraud and error in the department's financial statements and reputation damages.

This issue is further discussed later in this chapter.

2020–21 findings  
Department of Customer Service
New finding:
Change management significant control deficiencies

Revenue NSW, a division of the department has a key role in managing the State’s finances. It administers State taxes, manages fines, recovers State debt and administers grants and subsidies.

The audit team found significant control deficiencies in change management controls:

  •  appropriate system controls were not in place to restrict developers from releasing changes to the live business systems
  • 8 developers had direct access to the business application servers used for calculating and administering State taxes.

We have included this matter as a high-risk management letter finding, as the audit team could not identify mitigating controls. The system activity of these developers was also not being independently logged and monitored. This increases the risk of unauthorised system change. This can significantly affect the integrity of tax calculation, business process approvals, invalid changes to bank accounts, unauthorised refunds and write-offs. The audit team conducted a risk analysis over the relevant business processes affected by this issue and performed additional audit procedures to address the audit risk.

Rental Bond Board
Repeat finding: Accounting treatment of rental bonds held in trust

The Rental Bond Board (the Board) holds rental bonds totalling $1.7 billion at 30 June 2021. The Board treated the rental bonds off-balance sheet and disclosed the rental bonds as ‘trust funds’. This treatment is based on management’s judgement that the Board does not have control of these funds.

Previously the Board obtained advices from the Crown Solicitors who stated that in their view the rental bond funds held in the rental bond account were not moneys held in trust and the Residential Tenancies Act 2010 (the Act) should be reviewed and amended to better support its accounting treatment of rental bonds. The Board has initiated the need to amend the Act, however the implementation of the legislative amendments is still pending.

This matter was assessed as high-risk, if not adequately supported, it had the potential to result in material misstatements in the Board's financial statements.


The number of moderate risk findings increased from prior year

Fifty-nine moderate risk findings were reported in 2020–21, which was a 11.3 per cent increase from 2019–20. Of these, 26 were repeat findings, and 33 were new issues.

Moderate risk findings include:

  • weaknesses in user access management, such as untimely access removal for terminated staff, and a lack of periodic user access review
  • accounting for leases such as the review of extension options, assessing indicators of impairment and reviewing the lease reports for completeness and accuracy
  • formalising arrangements between agencies including corporate service arrangements, funding arrangements, leases, use of SAP system and computer assets
  • use of purchasing cards where our data analytics performed indicated potential gaps and controls and non-compliance with government policies.

The magnitude and number of internal control exceptions in GovConnect service providers have increased

In 2015, the NSW Government selected Unisys Australia Pty Limited’s (Unisys) as an information technology (IT) outsourced service provider and Infosys Limited (Infosys) as a business process outsourced service provider. The outsourced services arrangement was branded GovConnect NSW (GovConnect). The Department of Customer Service (the department) is the contract authority for the NSW Government. In 2019, the NSW Government transitioned a number of Unisys’ IT services progressively to the department and ceased all Unisys's IT services in May 2021. In 2020-21, Infosys, Unisys and the Department were co-providers of business processes and information technology services that constitute the GovConnect environment.

The role of the department has changed significantly from a coordinating agency on behalf of GovConnect customers to a GovConnect IT service provider. The department is responsible for the remediation of control deficiencies and continuous improvement in GovConnect internal control environment.

The department leads the project management of GovConnect services, including the arrangement to provide internal control assurance reports to customers in 2020–21. It engages an independent service auditor (service auditor) from the private sector to perform annual assurance reviews of controls at GovConnect service providers in accordance with Australian Standard on Assurance Engagements 3402 'Assurance Reports on Controls at a Service Organisation' (ASAE 3402). The service auditor reports on the internal controls at a service organisation, which are relevant to a user entity's internal control environment.

The service auditor issued eight ASAE 3402 reports covering business processes controls and information technology general controls (ITGC) provided by the service providers. Four out of eight reports were qualified, a significant increase from previous years.

The table below shows the service auditor's ASAE 3402 opinions issued in various business processes and information technology services provided by service providers for the last five years.

ASAE 3402 controls report# 2015–16^ 2016–17 2017–18 2018–19 2019–20 2020–21
Infosys Accounts receivable Qualified Unqualified Unqualified Unqualified Unqualified Qualified
Infosys Accounts payable Qualified Qualified Unqualified Unqualified Unqualified Unqualified
Infosys Fixed assets Qualified Unqualified Unqualified Unqualified Unqualified Unqualified
Infosys General ledger Qualified Qualified Unqualified Unqualified Unqualified Unqualified
Infosys Payroll Adverse Qualified Unqualified Unqualified Unqualified Unqualified
Infosys ITGC Qualified Qualified Unqualified Unqualified Unqualified Qualified
Unisys ITGC Qualified Unqualified Qualified Qualified Unqualified Qualified
The department ITGC* -- -- -- -- Qualified Qualified
ServiceFirst** Disclaimer -- -- -- -- --

# The ASAE 3402 controls reports were issued by an independent private sector service auditor appointed by the Department of Customer Service.
* Information technology services were transitioned from Unisys to the department in phases from 2019–20 to 2020–21.
** ServiceFirst was the shared service centre and its last reporting period was from 1 July 2015 to 13 December 2015.
^ GovConnect first reporting period from 14 December 2015 to 30 June 2016.

In 2020–21, the information technology services controls reports issued to the department, Infosys and Unisys were qualified. Infosys' accounts receivable business process controls report was also qualified. The audit qualifications were because:

  • the service auditor did not get access to the complete set of records processed during the financial year for several ITGC controls. The system that stored these records was hosted at Unisys. From December 2019 to 28 May 2021, the services at Unisys were progressively migrated to the department's IT environment but this system could not be migrated to the department in the required format, resulting in audit scope limitation for service auditors
  • of the deviations identified during sample testing of ITGC controls
  • the monthly follow up of outstanding receivables was not performed regularly, which was the only key control to address the timely collection of accounts receivable.

Internal control exceptions in GovConnect information and technology services require urgent remediations

The relevant controls over user access, system changes and password controls failed in all three ASAE 3402 GovConnect ITGC reports. These control failures can lead to unauthorised system access, system and configuration changes (workflow approvals, three-way match, etc.) and modifications to key reports. It increases the risk of:

  • fraud and error in the financial statements
  • ineffective segregation of duties controls
  • accuracy and completeness of system generated reports for the agencies using the SAPConnect system.

The table shows the number of ITGC control deviations compared to prior year:

Year ended 30 June 2021 2020
  Total controls tested Total number of control deviations and findings Total controls tested Total number of control deviations and findings
Infosys ITGC 41 16 35 8
Unisys ITGC 25 11 33 4
DCS ITGC 31 9 10 5

Most of these deviations were not mitigated or sufficiently mitigated to address the risk of unauthorised user access.

The service auditor identified significant areas for remediation:

  • governance arrangement of the IT services
  • user access management controls
  • SAP database controls
  • logical access
  • incident management.

In response to the internal control qualifications, the audit teams performed data analytics over payroll and accounts payable. The data analytics identified several terminated employees that were paid long after their termination dates which resulted in salary overpayments during 2020–21. While management had put processes in place to recover these overpayments, the payroll processing controls need to be improved to prevent such overpayments.

The Department of Customer Service advised that it established a ‘Control Reframe Project’ (the project) to address the internal control exceptions at GovConnect service providers. The objective of the project is to ensure the GovConnect assurance model is aligned with clear lines of responsibility and remediation actions are in place to support the delivery of services and achieve an improved outcome for future years.

Recommendation

We recommend the Department of Customer Service:

  • improve governance and internal control environment over the information technology services
  • ensure GovConnect service providers prioritise remediation actions to address internal control exceptions
  • perform a post-implementation review of the transition of the Unisys arrangement to identify lessons learnt and continuous improvement
  • develop data analytics to help analyse and identify high-risk patterns and anomalies in GovConnect key transaction systems, augmenting their existing monitoring and detective controls.

The NSW Public Sector's cyber security resilience needs urgent attention

The 2020 'Central Agencies' Report to Parliament highlighted the need for Cyber Security NSW, a business unit within the Department of Customer Service, and NSW Government agencies to prioritise improvements to their cyber security resilience as a matter of urgency. A status update of the 2020 recommendation is included in Appendix five of this report.

The Audit Office's Annual Work Program identifies cyber security as a focus area for the Audit Office in 2021–24. It outlines a three-pronged approach to auditing cyber security in this period:

  • considering how agencies are responding to the risks associated with cyber security across our financial audits across the NSW public sector
  • examining the effectiveness of cyber security planning and governance arrangements for large NSW state government agencies for our Internal Controls and Governance report
  • conducting deep-dive performance audits of the effectiveness of specific agency activities in preparing for, and responding to cyber security risks.

A performance audit 'Managing cyber risks' was tabled in Parliament in July 2021. The audit made several recommendations to audited agencies to uplift their cyber security management. It also recommended the Department of Customer Service to:

  • clarify the requirement of the NSW Cyber Security Policy (CSP) reporting to all systems
  • require agencies to report the target level of maturity for each mandatory requirement.

A compliance audit 'Compliance with the NSW Cyber Security Policy' was tabled in October 2021. The audit examined whether agencies are complying with the NSW Cyber Security Policy to ensure all NSW Government departments and public service agencies are managing cyber security risks to their information and systems.

The report found that key elements to strengthen cyber security governance, controls and culture are not sufficiently robust and not consistently applied. There has been insufficient progress to improve cyber security safeguards across NSW Government agencies. The poor levels of cyber security maturity are a significant concern. Improvement requires dedicated leadership and resourcing. To comply with some elements of the government’s policy agencies will have to invest in technical uplift and some measures may take time to implement. However, other elements of the policy do not require any investment in technology. They simply require leadership and management commitment to improve cyber literacy and culture. And they require accountability and transparency. Transparent reporting of performance is a key means to improve performance.

The report noted that the CSP was not achieving the objective of improved cyber governance, controls and culture. The compliance audit made several recommendations to Cyber Security NSW and other NSW Government agencies.

The 2021 maturity self-assessment results against the Australian Cyber Security Centre Essential 8 for the 25 largest NSW State Government agencies are reported in the 2021 'Internal Control and Governance' Report to Parliament.

Repeat recommendation

Cyber Security NSW and NSW Government agencies need to prioritise improvements to their cyber security resilience as a matter of urgency.

Management of cyber security risk

Our 2020-21 financial audit assessed whether cyber security risks represent a risk of material misstatement to the department's own financial statements. A request performance audit 'Service NSW's handling of personal information' was tabled on 18 December 2020. The audit followed two cyber security incidents that resulted in data breaches of customer information. As part of our audit procedures, we obtained an understanding of the controls the department has in place to address the risk of cyber security incidents and respond to any incidences which may have occurred during the year, including its impact on the audit.

Our assessment of the department’s own cyber risk management shows that:

  • an approved security incident response plan was not in place during the reporting period. There was a lack of testing over incident detection and monitoring process
  • a formal process over patch management that includes assessment, determining relevance and priority, timely rollout and escalation and reporting of long outstanding patches to senior management is being established.

The department provides information security services including cyber security management to cluster agencies. We found that there were insufficient communications within the Customer Service cluster over the controls and assurance over cyber security risk management. Some cluster agencies had put in place limited controls over cyber security risk management.

Recommendation

We recommend the Department of Customer Service:

  • establish an approved security incident response plan and formal process over patch management
  • improve communications with cluster agencies over the controls and assurance in cyber security management.

Appendix one – Misstatements in financial statements submitted for audit

Appendix two – Early close procedures

Appendix three – Timeliness of financial reporting

Appendix four – Financial data

Appendix five – Status of 2020 recommendations

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Health 2021

Health 2021

Health
Asset valuation
Compliance
Cyber security
Financial reporting
Infrastructure
Internal controls and governance
Procurement

This report analyses the results of our audits of the Health cluster agencies for the year ended 30 June 2021.

Our preferred approach is to table the ‘Report on State Finances’ in Parliament before any other cluster report. This is because the 'Report on State Finances' focuses on the audit results and observations relating to the Total State Sector Accounts, in effect a consolidation of all government agencies. This year the 'Report on State Finances' has been delayed due to significant accounting issues being considered in the Total State Sector Accounts and which may impact the Treasury and Transport clusters.

As there are no outstanding matters relating to audits in the Health cluster impacting the Total State Sector Accounts we have decided to break with normal practice and table this cluster report ahead of the ‘Report on State Finances’.

What the report is about

The results of Health cluster (the cluster) agencies' financial statements audits for the year ended 30 June 2021.

What we found

Unmodified audit opinions were issued for the financial statements of all Health cluster agencies.

The COVID-19 pandemic increased the complexity and number of accounting matters faced by the cluster. The total gross value of corrected misstatements in 2020–21 was $250.2 million, of which $226.0 million were pandemic related.

A qualified audit opinion was issued on the Annual Prudential Compliance Statement. The basis of the qualification related to 19 instances (18 in 2018–19) of non-compliance relating to three of the 20 prudential requirements across five aged care facilities.

What the key issues were

The total number of matters we reported to management across the cluster increased from 112 in 2019–20 to 116 in 2020–21. Of the 116 issues raised in 2020–21, three were high risk (one in 2019–20) and 57 were moderate risk (47 in 2019–20). Nearly one half of the issues were repeat issues.

The three new high-risk issues identified were:

Hotel Quarantine (HQ) fees

The absence of a tailored debt recovery strategy, data integrity issues and uncertainties around future HQ arrangements increased risks around the recoverability of HQ fees from travellers.

COVID-19 inventories

Data errors and anomalies in the impairment model and difficulties forecasting key factors impacting the management of Personal Protective Equipment (PPE) increased uncertainty associated with the valuation and impairment of COVID-19 inventories.

COVID-19 vaccines

The Commonwealth did not provide information about the cost of vaccines provided to NSW free of charge, which required the performance of internal valuations to reflect the consumption of vaccines in the financial statements.

What we recommended

Hotel Quarantine (HQ) fees

Develop a tailored assessment methodology to estimate recoverability of HQ fees and work with Revenue NSW to develop a tailored debt recovery strategy.

COVID-19 inventories

Review the current stocktaking and impairment methodology to incorporate validation of data key to the management of COVID-19 related PPE.

COVID-19 vaccines

Work with the Commonwealth to obtain primary price information on COVID-19 vaccines.

Fast facts

The Health cluster, comprising 15 local health districts, five pillars agencies, two specialty health networks and six shared state-wise services agencies, deliver health services to the people of New South Wales.

  • 100% unqualified audit opinions were issued on agencies' 30 June 2021 financial statements
  • 24 monetary misstatements were reported in 2020–21
  • high risk management letter findings were identified
  • 47.4% of reported issues were repeat issues
  • $23.5b property, plant and equipment as at 30 June 2021
  • $26.8b total expenditure incurred in 2020–21

This report provides Parliament and other users of the Health cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision-making are enhanced when financial reporting is accurate and timely. This chapter outlines our audit observations related to the financial reporting of agencies in the Health cluster (the cluster) for 2021.

Section highlights

  • Unqualified audit opinions were issued for all cluster agencies required to prepare general-purpose financial statements.

  • The total gross value of all corrected monetary misstatements for 2020–21 was $250.2 million, of which $226.0 million were related to complexities arising from the COVID-19 pandemic.

  • A qualified audit opinion was issued on the Ministry's Annual Prudential Compliance Statement.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision-making. This chapter outlines our observations and insights from our financial statement audits of agencies in the Health cluster.

Section highlights

  • The total number of internal control deficiencies has increased from 112 issues in 2019–20 to 116 in 2020–21. Of the 116 issues raised in 2020–21, three were high (one in 2019–20) and 57 were moderate (47 in 2019–20); with nearly one half of all control deficiencies reported in 2020–21 being repeat issues.
  • The complexities arising from accounting for agreements between governments to respond to the COVID-19 pandemic presented three new high risk audit findings with respect to the:
    • expected rate of recoverability of outstanding Hotel Quarantine fees
    • procurement, stocktaking and impairment of COVID-19 inventories
    • valuation and recognition of COVID-19 vaccines received from the Commonwealth Government.
  • Management of excessive leave balances and poor quality or lack of documentation supporting key agreements were amongst the repeat issues observed again in the 2020–21 financial reporting period.

Findings reported to management

The number of findings reported to management has increased, with 47.4 per cent of all issues being repeat issues

Breakdowns and weaknesses in internal controls increase the risk of fraud and error. Deficiencies in internal controls, matters of governance interest and unresolved issues were reported to management and those charged with governance of cluster agencies. The Audit Office does this through our management letters, which include observations, implications, recommendations and risk ratings.

In 2020–21, there were 116 findings raised across the cluster (112 in 2019–20). 47.4 per cent of all issues were repeat issues (38.4 per cent in 2019–20).

A delay in implementing audit recommendations increases the risk of intentional and accidental errors in processing information, producing management reports and generating financial statements. This can impair decision-making, affect service delivery and expose agencies to fraud, financial loss and reputational damage. Poor controls may also mean agency staff are less likely to follow internal policies, inadvertently causing the agency not to comply with legislation, regulation and central agency policies.

The table below describes the common issues identified across the cluster by category and risk rating.

Risk rating Issue
Information technology

Moderate2
7 new,
3 repeat

We identified the need for agencies to improve information technology processes and controls that support the integrity of financial data used to prepare agencies' financial statements. Of particular concern are issues associated with:

  • lack of reviews of user access and privileged user access for
  • HealthRoster
  • Assets and Facilities Management Online
  • vMoney Powerhouse
  • Patient Billing and Revenue Collection system.

Repeat issues included:

  • deficient password controls
  • no independent review for data integrity of any changes made to HealthRoster
  • incomplete reviews of StaffLink User Access.

Low1
4 new,
5 repeat

Internal control deficiencies or improvements

High3

1 new, 

0 repeat

We identified internal control weaknesses across key business processes, including new issues relating to:

  • procurement, stocktaking and impairment of COVID-19 inventories (personal protective equipment)
  • instances where employees' timesheets were approved in advance
  •  monthly reconciliations not reviewed in a timely manner
  • asset revaluation processes at Illawarra Shoalhaven Local Health District.
     

Repeat issues included:

  • forced finalisation of rosters in order to finalise processing of payroll
  • partial repeat issue relating to HealthShare NSW's stocktake process, refer to details in the following section of this report.

Moderate2
6 new,
12 repeat

 Low1
10 new,
4 repeat

Financial reporting

High3

2 new, 
0 repeat

We identified weaknesses with respect to financial reporting in relation to the:

  • expected rate of recoverability of outstanding Hotel Quarantine fees
  • valuation and recognition of COVID-19 vaccines received from the Commonwealth Government
  • application of AASB 16 'Leases'
  • improvement in health agencies' grant register to better support management's accounting treatment under the applicable revenue accounting standards.

Moderate2
6 new,
1 repeat

Low1
8 new,
3 repeat

Governance and oversight
Moderate2
9 new,
5 repeat

We identified opportunities for agencies to improve governance and oversight processes, including:

  • ensure better documentation around governance arrangements for major health capital works delivered by Health Infrastructure
  • absence of documented practices at health agencies level relating to Visiting Medical Officer claims.
     

Repeat issues include:

  • delegations manual for Health Infrastructure remains in draft and has done so since 2017.
Low1
2 new,
2 repeat
Non-compliance with key legislation and/or central agency policies
Moderate2
1 new,
7 repeat

We identified the need for agencies to improve compliance with key legislation and central agency policies, with new findings including:

  • bank signatories list not updated to remove terminated employees
  • subsequent changes made to Junior Medical Officers' approved rosters not approved by an authorised delegate.
     

Repeat issues include:

  • management of excessive annual leave
  • non-compliance with the Government Information (Public Access) Act 2009 (GIPA Act) by Ambulance NSW.
Low1
5 new,
13 repeat

4Extreme risk from the consequence and/or likelihood of an event that has had, or may have a negative impact on the entity.
3 High risk from the consequence and/or likelihood of an event that has had, or may have a negative impact on the entity.
2 Moderate risk from the consequence and/or likelihood of an event that has had, or may have a negative impact on the entity.
1 Low risk from the consequence and/or likelihood of an event that has had, or may have a negative impact on the entity.

Note: Management letter findings are based either on final management letters issued to agencies, or draft letters where findings have been agreed with management.

Complexities arising from the COVID-19 response

The 2020–21 audit identified three new high-risk findings

COVID-19 has presented the cluster with several new accounting challenges. New and evolving matters arose from changes to operating conditions, which characterised the 2020–21 financial reporting period. Issues with a high degree of estimation uncertainty will require ongoing attention as the strategies employed to deal with the COVID-19 pandemic evolve.

Expected rate of recovery of outstanding Hotel Quarantine invoices

The estimation of the amount likely to be recovered is complicated not only by the uncertainties that exist regarding the assumptions those estimations rely upon, but also the debt collection processes and strategies put into place to manage the accumulated debtors' balance. Debt collection is not administered by the cluster, but rather Revenue NSW. We observed an absence of a methodology to assess the likelihood of recovery. Instead, Sydney Local Health District was relying on Revenue NSW to develop and execute on a collection strategy. Sydney Local Health District was using the same approach to hotel quarantine debts as it did to other Health receivables. As the approach to managing international borders evolves over time, so too will the cluster's need to develop robust estimation models to assess the likely collectability of debtors. 

Procurement, management and impairment of COVID-19 inventories

$656.2 million of COVID-19 inventories were procured in 2020–21, with $220.2 million consumed; $558.7 million impaired and a further $217.1 million written off. Estimates of the degree to which inventories are expired, not fit for purpose or are faulty is often based on management judgement at all stages in the procurement cycle.

With respect to the stocktaking methodology applied, the following issues were identified:

  • discrepancies noted in the stock bin listing provided for audit
  • discrepancies in the recount sheet generated
  • inconsistent application of the stocktake methodology
  • inconsistent labelling of quarantined stock
  • a lack of an approach for validating stock expiry dates, which is a key input to the impairment calculations.

Although management had developed processes and a methodology to count as well as to assess the level of inventory that was not fit for purpose, ongoing attention to the operating environment that emerges post pandemic will be important in assessing the degree to which existing COVID-19 inventories can be integrated into a ‘business as usual’ model going forward. Further refinement of the key elements of the stocktaking methodology will also be required to ensure that key inputs upon which management relies to calculate the year-end inventory impairment provision can be appropriately validated.

Valuation and recognition of COVID-19 vaccines received from the Commonwealth Government

The 2020–21 financial reporting period saw the Commonwealth acquire COVID-19 vaccines and provide these to state jurisdictions to dispense to their communities. The vaccines, although provided free of charge require recognition. However, Health entities were not responsible for acquiring the vaccines and data on the vaccines' cost was not shared by the Commonwealth. Management undertook a valuation using publicly available data to estimate the value to attribute to the vaccine inventory; developed new systems and leveraged existing pharmacy systems to track physical quantities received from the Commonwealth and ultimately distributed to NSW citizens. As the response to the pandemic evolves, larger quantities, and new lines of vaccine stock will be dealt with, and policy settings will need to adapt when patterns of distribution of those vaccines (e.g., timing of third booster shots) emerge. The Ministry of Health will need to ensure that the valuations applied to the prices of inventory distributed and held in stock are as accurate as possible. This can be done through further refinement of the existing valuation methodology, obtaining price information from the Commonwealth and engaging specialist pharmaceutical valuers.

Emerging trends

Recognition of provisions without sufficient support

Several NSW Health entities raised accruals and provisions in 2020–21, which did not have an appropriate basis for recognition. Liabilities can only be recognised where there is a present obligation to make a payment arising from a past event. A number of these errors remain uncorrected in the financial statements of those entities as they are not material, individually or in aggregate to the financial statements as a whole. Increased training and guidance are required to ensure that treatment within the cluster is consistent and reflects events that have occurred and give rise to obligations.

Treatment of Commonwealth funding

In the 2020–21 and 2019–20 financial reporting periods, we observed prior period errors arising from the treatment of Commonwealth funding. These errors related to recognising revenue under funding agreements entered into with the Commonwealth in the incorrect period. The conditions of these funding arrangements, the transactional information requiring validation and the circumstances when revenue should be recognised are not always clear and can be complex. Early and continuous engagement with the Commonwealth is required to ensure that revenue recognition principles are consistently applied across the cluster.

Key repeat issues

Management of excessive annual leave

NSW Treasury guidelines stipulate annual leave balances exceeding 30 days are considered excess annual leave balances. Managing excess annual leave balances has been reported as an issue for the cluster for more than five years, with the average percentage of employees with excessive leave balances over the last five years being 36.1 per cent (35.5 per cent over five years covering 2015–16 to 2019–20).

The operational demands required to manage the COVID-19 pandemic have presented new challenges for the cluster in trying to manage its excessive leave balances. 39.2 per cent of employees now have excess leave balances at 30 June 2021 (35.4 per cent at 30 June 2020).

The state's leave policy C2020-12 Managing Accrued Recreation Leave Balances requires agencies to manage excessive leave balances to 30 days or less to maintain their workforces physical and mental health.

Accurate time recording

Forced-finalisation of time records by system administrators within HealthRoster remains an issue and we continue to observe time records forced-finalised by system administrators so pay runs can be finalised on a timely basis. During 2020–21, a total of two million (2.2 million in 2019–20) time records were force approved, which represents 5.7 per cent of total time records (6.9 per cent in 2019–20).

Existence, completeness and accuracy of key agreements

Delivery of major capital projects

Health Infrastructure (a division of the Health Administration Corporation) is responsible for the delivery of major capital projects with a budgeted spend of more than $10.0 million. Health Infrastructure oversee the planning, design, procurement, and construction phases. Capital works in progress are recognised in the financial statements of the health entity that intends to use those assets upon completion. The health entities recognise both the capital work in progress and the revenue associated with the capital funding from the Ministry for the construction of the assets. Capital funding is currently agreed with health entities as part of the annual Service Agreement. The assumption that the health entities control the assets during their construction is consistent with Health Infrastructure's role as an agent for the health entity and the Ministry's policy directive PD2020-033 'Management and control of Health Administration Corporation owned Real Property'.

We continued to observe a lack of clarity regarding agreements between Health Infrastructure, the Ministry and the cluster agency that will eventually receive the completed asset. This can lead to confusion and uncertainty around the rights and obligations of each party to the transaction.

Cross border patient funding arrangements

When patients require medical care in a jurisdiction where they are not generally domiciled, there are arrangements in place to provide funding to support cross border patient treatments. We have previously observed that agreements between NSW and other jurisdictions have not been finalised, and this continues to be the case. In the case of Victoria, no agreement has been finalised for the past seven years.

We continue to note that the cluster has long outstanding receivables and payables with other states. The absence of formal agreements between the states hampers the settlement of the debts relating to the treatment of cross border patients. The following table shows the status of Cross Border Agreements between NSW and other jurisdictions:

States 2014–15 2015–16 2016–17 2017–18 2018–19 2019–20 2020–21
Queensland Signed Signed Signed Signed Signed Not finalised Not finalised
Victoria Not finalised Not finalised Not finalised Not finalised Not finalised Not finalised Not finalised
Australian Capital Territory Signed Signed Signed Signed Signed Signed Not finalised
South Australia Signed Signed Signed Signed Signed Signed Not finalised
Tasmania Signed Signed Signed Signed Signed Signed Not finalised
Northern Territory Signed Signed Signed Signed Signed Signed Not finalised
Western Australia Signed Signed Signed Signed Signed Signed Not finalised

Albury Base Hospital

Albury Base hospital is located on the border of NSW and Victoria and services residents of both states. Documentation supporting the extension of the expired Intergovernmental Agreement 2009–2017 between NSW and Victoria in relation to the integration of health services in Wodonga and Albury could not be located.

Appendix one – Misstatements in financial statements submitted for audit

Appendix two – Early close procedures

Appendix three – Timeliness of financial reporting

Appendix four – Financial data

 

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Rail freight and Greater Sydney

Rail freight and Greater Sydney

Transport
Information technology
Infrastructure
Management and administration
Project management
Service delivery

What the report is about

The movement of freight contributes $66 billion annually to the NSW economy. Two thirds of all freight in NSW moves through Greater Sydney, and the volume of freight moving through Greater Sydney is expected to increase by 48 per cent by 2036.

This audit assessed the effectiveness of transport agencies in improving the use of rail freight capacity in Greater Sydney, and to meet current and future freight demand.

What we found

Transport agencies do not have strategies or targets in place to improve the efficiency or capacity of the metropolitan shared rail network for freight.

The transport agencies acknowledge that they do not have sufficient information to achieve the most efficient freight outcomes and they do not know how to use the shared rail network to maximise freight capacity without compromising passenger rail services.

The Freight and Ports Plan 2018-2023 contains one target for rail freight - to increase the use of rail at Port Botany to 28 per cent by 2021. However, Transport for NSW (TfNSW)'s data indicates this target will not be met.

Sydney Trains records data on train movements and collects some data on delays and incidents. TfNSW collects data for the construction of the Standard Working Timetable and third-party contracts.

However, a lack of clarity around what data is gathered and who has ownership of the data makes data sharing difficult and limits its analysis and reporting.

The Freight and Ports Plan 2018-2023 includes the goal of 'Reducing avoidable rail freight delays', but the transport agencies do not have any definition for an avoidable delay and, as a result, do not measure or report them.

TfNSW and Sydney Trains are appointed to manage and deliver the Transport Asset Holding Entity of New South Wales (TAHE)'s obligations to allow rail freight operators to use the shared rail network. There are no performance measures in rail freight operator contracts or inter-agency agreements. This limits transport agencies' ability to improve performance.

TfNSW’s Freight Branch is working on four freight-specific strategies; a review of the Plan, a freight rail strategy, a port efficiency strategy and a freight data strategy.

TfNSW has not yet determined the timeframes or intended outcomes of these strategies.

What we recommended

Transport agencies should:

  • commit, as part of the review of Future Transport 2056, to delivering the freight-specific strategies currently in development and develop whole-of-cluster accountability for this work including timeframes, specific targets and clear roles and responsibilities 
  • improve the collection and sharing of freight data
  • develop a plan to reduce avoidable freight delays
  • systematically collect data on the management of all delays involving and/or impacting rail-freight
  • develop and implement key performance indicators for the agreements between the transport agencies.

Fast facts    

  • 288 million tonnes of freight volume predicted to pass through Greater Sydney in 2036, up from 194 million in 2016 (an increase of 48%)

  • 54 trucks that can be replaced by one 600 m long port shuttle freight train    

  • 26,671 freight trains that passed through the metropolitan shared rail network between 1 July 2020 and 30 June 2021

The movement of freight contributes $66.0 billion annually to the New South Wales economy — or 13 per cent of the Gross State Product. Two thirds of all freight in New South Wales moves through Greater Sydney, and the volume of freight moving through Greater Sydney is expected to increase by 48 per cent by 2036. This increasing demand is driven by increasing population and economic growth.

The sequence of activities required to move goods from their point of origin to the eventual consumer (the supply chain) is what matters most to shippers and consumers. Road can provide a single-mode door-to-door service, whereas conveying goods by rail typically involves moving freight onto road at some point. In Greater Sydney, 80 per cent of all freight is moved on road. Freight often passes through intermodal terminals (IMTs) as it transitions from one mode of transport to the next.

In 2016, Transport for NSW (TfNSW) released Future Transport 2056 - the NSW Government's 40-year vision for transport in New South Wales, which is intended to guide investment over the longer term. In Future Transport 2056, TfNSW noted that New South Wales will struggle to meet increasing demand for freight movements unless rail plays a larger role in the movement of freight.

Sydney Trains manages the metropolitan shared rail network, which is made up of rail lines that are used by both passenger and freight trains. The Transport Administration Act 1988 requires that, for the purposes of network control and timetabling, NSW Government transport agencies give ‘reasonable priority’ to passenger trains on shared lines. As the Greater Sydney population and rail patronage continue to grow, so too will competition for access to the shared rail network. See Appendix two for details of the area encompassed by Greater Sydney.

Freight operators can also use dedicated rail freight lines operated by the Australian Rail Track Corporation (ARTC - an Australian Government statutory-owned corporation). As the metropolitan shared rail network connects with dedicated freight lines, freight operators often use both to complete a journey.

TfNSW, Sydney Trains and the Transport Asset Holding Entity (TAHE) work in conjunction with other rail infrastructure owners and private sector entities, including port operators, privately operated IMTs and freight-shipping companies. TfNSW and Sydney Trains are responsible for managing the movement of freight across the metropolitan shared rail network. TAHE is the owner of the rail infrastructure that makes up the metropolitan shared rail network. The NSW Government established TAHE, a NSW Government state-owned corporation, on 1 July 2020 to replace the former rail infrastructure owner - RailCorp. The Auditor-General for New South Wales has commenced a performance audit on TAHE which is expected to table in 2022.

On 1 July 2021, TAHE entered into new agreements with TfNSW and Sydney Trains to operate, manage and maintain the metropolitan shared rail network. Until 30 June 2021, and in accordance with TAHE's Implementation Deed, TAHE operated under the terms of RailCorp's existing arrangements and agreements.

This audit assessed the effectiveness of TfNSW, Sydney Trains and TAHE in improving the use of rail freight capacity in Greater Sydney, and to meet current and future freight demand.

The audit focused on:

  • the monitoring of access to shared rail lines
  • the management of avoidable delays of rail freight movements
  • steps to increase the use of rail freight capacity in Greater Sydney.

Conclusion

Transport agencies do not have clear strategies or targets in place to improve the freight efficiency or capacity of the metropolitan shared rail network. They also do not know how to make best use the rail network to achieve the efficient use of its rail freight capacity. These factors expose the risk that rail freight capacity will not meet anticipated increases in freight demand.

Future Transport 2056 notes that opportunities exist to shift more freight onto rail, and that making this change remains an important priority for the NSW Government. However, the transport agencies acknowledge that they do not have sufficient information to achieve the most efficient freight outcomes. In particular, transport agencies do not know how to use the shared rail network in a way that maximises freight capacity without compromising passenger rail services.

Neither Future Transport 2056 nor the Freight and Ports Plan 2018–2023 give any guidance on how transport agencies will improve the efficiency or capacity of the shared rail network. Other than a target for rail freight movements to and from Port Botany, which TfNSW's data indicates will not be met, there are no targets for improving rail freight capacity across the shared network. The lack of specific strategies, objectives and targets reduces accountability and makes it difficult for transport agencies to effectively improve the use of rail freight capacity in line with their commitment to do so.

Sydney Trains and Transport for NSW do not effectively use data to improve rail freight performance and capacity.

To drive performance improvement when planning for the future, transport agencies need good quality data on freight management and movements. Sydney Trains records data on train movements in real-time and collects some data on delays and incidents. TfNSW collects data for the construction of the Standard Working Timetable (SWTT) and third-party contracts. However, the different types of data gathered and the separation between the teams responsible mean that there is a lack of clarity around what data is gathered and who has ownership it. This lack of coordination prevents best use of the data to develop a single picture of how well the network is operating or how performance could be improved.

Sydney Trains' ability to evaluate the effectiveness of its incident and delay mitigation strategies is also limited by a lack of information on its management of rail-freight related delays or incidents. While Sydney Trains collects data on major incidents, it can only use this to conduct event-specific analysis on the causes of an incident, and to review the operational and management response. The use of complete and accurate incident data would assist to define, identify and reduce avoidable delays. Reducing avoidable delays is a goal of the Freight and Ports Plan 2018–2023. More complete data on all incidents would help TfNSW to have more effective performance discussions with rail freight operators to help improve performance.

TfNSW has started developing strategies to identify how it can use rail freight capacity to achieve efficient freight outcomes, but it has not committed to implementation timeframes for this work.

TfNSW’s Freight Branch has started work on four freight-specific strategies to improve freight efficiency: a review of the Plan, a freight rail strategy, a port efficiency strategy and a freight data strategy. However, none of these strategies will be fully developed before the end of 2022. TfNSW has not yet determined the implementation timeframes or intended outcomes of these strategies, although TfNSW reports that it is taking an iterative approach and some recommendations and initiatives will be developed during 2022. 

Appendix one - Response from agencies

Appendix two - The Greater Sydney region

Appendix three - TfNSW strategic projects 

Appendix four - Sydney Trains path priority principles 

Appendix five - Sydney Trains delay management

Appendix six - About the audit 

Appendix seven - Performance auditing
 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #357 - released (19 October 2021).

Published

Actions for Grants administration for disaster relief

Grants administration for disaster relief

Treasury
Finance
Compliance
Fraud
Management and administration
Project management

What the report is about

The report examined whether NSW Treasury, Service NSW and the Department of Customer Service effectively administered grants programs funded under the $750 million Small Business Support Fund, including:

  • $10,000 Small Business Support Grant
  • $3,000 Small Business Recovery Grant.

What we found

The agencies effectively implemented the grants within required timeframes, reflecting the NSW Government’s decision to deliver urgent financial support to small businesses impacted by the COVID-19 pandemic.

NSW Treasury met urgent timeframes to design the grants and Service NSW made timely payments in line with the grants' objectives and eligibility criteria.

Service NSW and the Department of Customer Service strengthened processes to detect and minimise fraud in response to identified external fraud risks, and to investigate suspected fraudulent applications.

Fraud security checks and investigations are ongoing, and the agencies will not know the full extent of fraud across the grants until these processes have been completed.

The agencies regularly monitored and reported on the timeliness of payments to small business applicants but have not yet measured all benefits of the grants programs.

The $10,000 Support Grant and the $3,000 Recovery Grant have provided around $630 million in one off grant payments to eligible small businesses.

What we recommended

NSW Treasury should finalise and implement an evaluation of both grants programs, including obtaining feedback from businesses.

Service NSW should develop a framework that documents expected controls for how it administers grants, including business processes, fraud control and governance and probity requirements.

Service NSW should publish information on all grants programs, including grants distribution and uptake.

The Department of Customer Service should ensure its processes for managing conflicts of interest meets its policy requirements.

Upcoming performance audit

The Audit Office is conducting a further performance audit into grants administration for disaster relief focussing on bushfire grants. This is planned to complete in 2021-22.

Fast facts

Small Business Support Fund
  • $630m Grant payments made to small businesses under two grants administered
  • Over 52,500 Applications received a $10,000 Grant payment
  • Over 23,000 Businesses paid both $10,000 Support Grant and $3,000 Recovery Grant
  • 36,700 Applications received a $3,000 grant payment
Grant program administration
  • 11 Days taken to deliver the $10,000 Small Business Support Grant application website
  • 26 Days taken to deliver the $3,000 Small Business Recovery Grant application website

Further information

Please contact Ian Goodwin, Deputy Auditor-General on 9275 7347 or by email.

The NSW Government responded to the partial shutdown of the NSW economy caused by the COVID-19 pandemic in 2020 by, among other measures, announcing on 3 April 2020 that it would place $750 million into the Small Business Support Fund (the Fund).

Under the Fund, the NSW Government would pay one-off grants of up to $10,000 to small business impacted by the shutdown. The objectives of the $10,000 Small Business Support Grant ($10,000 Support Grant) were to:

  • ease the pressure on small businesses that have been affected by the COVID-19 pandemic
  • support the ongoing operations of small businesses highly impacted by the COVID-19 restrictions
  • deliver cash-flow into small businesses as soon as possible so that small businesses could meet pressing financial needs.

Grant applications were assessed against eligibility criteria that were determined by the NSW Government. The eligibility criteria for the $10,000 Support Grant required an employing small business to demonstrate it was significantly impacted by the COVID-19 pandemic by self-declaring or demonstrating a significant decline of 75 per cent or more in turnover compared to 2019. Documentation requirements were relaxed for small businesses within highly impacted industries.

In June 2020, the NSW Government announced a second round of one-off grants of up to $3,000 to small businesses that were highly impacted by the COVID-19 pandemic ($3,000 Recovery Grant). The objective of the $3,000 Recovery Grant was to help small businesses in 'highly impacted industries' — those directly impacted by the restrictions and closures put in place under the Public Health Orders — to meet the costs of safely reopening or scaling up operations.

The eligibility criteria for the $3,000 Recovery Grant required that a small business be in a highly impacted industry, demonstrate that it was significantly impacted by the COVID-19 pandemic by declaring a significant decline in turnover, and had costs associated with reopening under the 'COVID-Safe' requirements.

NSW Treasury and Service NSW implemented both grants on behalf of the NSW Government. The process of applying for a grant was intended to be quick and easy, with Service NSW using automated assessments and simple online application forms to process applications. Applicants applied for the $10,000 Support Grant through the Service NSW website between 14 April 2020 to 30 June 2020 and applied for the $3,000 Small Business Recovery Grant between 1 July 2020 and 31 August 2020.

At May 2021, around $520 million has been paid to over 52,500 grant applicants under the $10,000 Support Grant and around $109 million had been paid to around 36,700 grant applicants under the $3,000 Recovery Grant.

The Audit Office plans to undertake a performance audit into grants administration for disaster relief focussing on bushfire grants in 2021–22.

This audit assessed whether the grants funded under the $750 million Small Business Support Fund were effectively administered and implemented to provide disaster relief. It addressed the following questions:

  • Were funded grants programs planned, designed and targeted effectively?
  • Were funded grants programs implemented in line with the objectives and criteria and delivery requirements?
  • Have agencies established measures to monitor intended benefits and outcomes?

This audit did not seek to assess the effectiveness of any other grant programs or stimulus measures. It also did not seek to assess the impact of the funding on applicants, or the future prospects of small businesses that received support.

Conclusion

NSW Treasury and Service NSW effectively implemented two grants within required timeframes reflecting the NSW Government's decision to deliver urgent financial support to small businesses impacted by the COVID-19 pandemic in 2020. The $10,000 Support Grant and the $3,000 Recovery Grant have provided around $630 million in one-off grant payments to eligible small businesses.
NSW Treasury met urgent timeframes to design the grants and Service NSW made timely payments in line with the grants' objectives and eligibility criteria.

NSW Treasury met urgent timeframes to provide advice to the NSW Government on the grant design, proposed delivery partner, expected numbers of eligible businesses and the suitability of the proposed grant payment amount within the required timeframes. This was achieved within one day for the $10,000 Support Grant and within four days for the $3,000 Support Grant. In the context of the complex and changing pandemic and economic conditions between March and July 2020, NSW Treasury's advice to government outlined the risk, feasibility, expected demand estimates and assumptions for the grants.

NSW Treasury's demand projections were limited by uncertainty as to the pandemic's economic impact. Estimated demand for the grants was not met, resulting in around $120 million from the Small Business Support Fund remaining unspent.

Service NSW met urgent timeframes to stand-up both grants: 11 days for the $10,000 Support Grant and 26 days for the $3,000 Recovery Grant. It met agreed delivery requirements and made timely payments to small businesses in line with the grants' objectives and eligibility criteria. Over 65,000 businesses have received a payment under either grant, and over 23,000 businesses received both grants.

Gaps in project and risk management processes were expected given the tight timeframe to implement the grants.

The tight timeframe in which the agencies had to implement the grants contributed to gaps in project and risk management. The agencies advised that compromises were understood by both parties and were a necessary trade-off to ensure payments were made quickly.

Service NSW and the Department of Customer Service have acted to strengthen their processes to detect and minimise fraud in response to identified external fraud risks and to investigate suspected fraudulent applications since the grants commenced. Service NSW intends to further enhance fraud controls for grants applications and payments for future grants by implementing a fraud control framework by December 2021.

The agencies regularly monitored and reported on the timeliness of payments to small business applicants but have not yet measured all benefits of the grants programs.

Service NSW and NSW Treasury established processes to monitor and report on the timeliness of payments to grant applicants.

NSW Treasury has not yet measured all intended impacts of the grants, nor undertaken processes to obtain detailed feedback from grant recipients. Without these measures, there is limited insight into the extent to which the grants helped to support small businesses or ability to capture lessons which could be applied in future grants programs. NSW Treasury advises that an evaluation will commence from mid-2021.

1. Key findings

Around $630 million in timely one-off grant payments have been made to small businesses

Service NSW and NSW Treasury have paid around $630 million in one-off grant payments to small businesses via two grants administered under the $750 million Small Business Support Fund. At May 2021:

  • around $520 million has been paid to over 52,500 grant applications received for the $10,000 Small Business Support Grant ($10,000 Support Grant)
  • around $109 million has been paid to 36,700 grant applications received for the $3,000 Small Business Recovery Grant ($3,000 Recovery Grant).

Across both grants, over 65,000 small businesses received a payment across either grant, and over 23,000 businesses received payments under both grants.

NSW Treasury advise that, while no data was collected on the time to pay applicants for the $10,000 Support Grant, from its monitoring of the grants' outputs it was satisfied that payment timeframes met its expectations. Service NSW met its targeted time to pay applicants with payments made within ten days for the $3,000 Recovery Grant.

Funds for both grants were not fully spent due to limitations in data and uncertainty of the COVID-19 pandemic's impact. At May 2021, the final demand for the $10,000 Support Grant was around 30 per cent less than initially anticipated and the final demand for the $3,000 Recovery Grant was around 40 per cent less than initially anticipated.

NSW Treasury developed proposals establishing high level design and delivery expectations within rapid timeframes

NSW Treasury put forward proposals to the NSW Government for the two grants administered under the $750 million Small Business Support Fund. It met rapid timeframes for producing this advice: within one day for the $10,000 Support Grant and within four days for the $3,000 Recovery Grant. NSW Treasury's advice to the NSW Government on how to best target the total funding, eligibility criteria and the feasibility of delivering the grants through Service NSW was based on comparable grants programs – including the $10,000 Small Business Bushfire Support Grant – which at that time were ongoing.

The proposals established, at a high-level, the rationale for the grants, expected financial costs, risks and analysis on budget impacts, and confirmation that Service NSW could deliver the grants applications platform. NSW Treasury's demand projections were uncertain due to limited data in the early stages of the pandemic regarding potential economic impact.

Given the tight timeframes, the proposals did not fully consider all planning and design aspects for both grants. For example, there was minimal identification of the costs and benefits of the programs, and a lack of detailed design and delivery requirements. The proposals outlined that arrangements to finalise the risk management, controls, and auditing plan would be agreed by Service NSW and NSW Treasury before implementation.

In future circumstances where urgent advice on program design is required, NSW Treasury could set clearer expectations for the delivery agency, including fully considering costs, benefits and delivery requirements that could be carried through to project governance and implementation.

Service NSW implemented both grants in line with delivery expectations

Service NSW met urgent timeframes to stand-up both grants: 11 days for the $10,000 Support Grant and 26 days for the $3,000 Recovery Grant. Delivery expectations for each grant were established under a grant project agreement (grant agreement). Service NSW delivered the online application platform, assessment of applications, payments and reporting of the grants' uptake as per the grant agreements.

The urgent timeframes to deliver the grants contributed to gaps in Service NSW's project and risk management processes throughout the lifecycle of both grants. For example, the requirement to meet pressing timeframes for the $10,000 Support Grant launch meant agencies had reduced time to achieve sign-off on key documentation. As a result, important documents and processes – including the grant agreement, risk documentation and key business process and quality assurance processes – were not finalised ahead of launch.

Quality assurance and compliance processes for detecting fraud were not settled until after the conclusion of the applications for the $10,000 Support Grant, and were not completed until late 2020. Some project documents, including risk registers, communication plans and project briefs are still not finalised.

The longer timeframe to develop the $3,000 Recovery Grant meant that agencies were able to build on their understanding of the implementation requirements from the $10,000 Support Grant, and better document these expectations and understanding while ensuring that key documents and sign-offs were in place prior to launch.

Service NSW tightened its risk management and controls in response to evidence of fraudulent applications

In May 2020, Service NSW and the Department of Customer Service (DCS) were alerted to suspected fraudulent activity within grants administered by Service NSW. Initially, Service NSW anticipated that up to $8.8 million of the $10,000 Support Grant was at risk of exposure to fraudulent applications. However, Service NSW reported that, at April 2021, $1.9 million for the $10,000 Support Grant and $254,000 for the $3,000 Recovery Grant from paid applications were at risk of fraud exposure.

Following an internal review of the potential exposure to fraudulent or ineligible applications, Service NSW implemented additional automated security checks on applications, increased manual assessments of grant applications, established a dedicated taskforce for grants administration and engaged a unit within DCS to manage high-risk investigations.

Service NSW and DCS's increased governance and oversight has resulted in an established case management function, increased referrals to law enforcement, prioritised investigations of suspicious applications and the development of a 'Fraud Control Framework' aimed at addressing external fraud risks. Given Service NSW had limited experience in these processes in context of administering grant payments, such actions were an appropriate response.

Security checks and investigations of suspicious applications are ongoing. Service NSW will not know the full extent of fraud across the grants until these processes have been fully completed.

Service NSW and Department of Customer Service can improve how conflicts of interest are managed for future programs

Compliance with agency policies and processes to manage conflicts of interest and financial subdelegations demonstrates that investment decisions are being made by appropriately skilled and experienced staff, allowing agencies to operate efficiently, and reducing the risk of internal fraud.

DCS was unable to produce employee conflicts of interest declarations for the $10,000 Support Grant. Therefore, it is not known how many employees had completed conflicts of interest declarations for this round.

DCS provided information on conflicts of interest declarations for the $3,000 Recovery Grant. Twenty-nine per cent of declarations provided for employees undertaking grant assessments for the $3,000 Recovery Grant were incomplete at March 2021, and a further nine per cent were not finalised even though they indicated a real, potential or perceived conflict.

For future grants programs, ensuring compliance with conflicts of interest policies would help DCS and Service NSW to have greater confidence that conflicts of interest are appropriately identified and managed.

NSW Treasury has not yet measured all benefits or outcomes of the grants

In April 2021, NSW Treasury updated its evaluation plan for the $10,000 Support Grant and $3,000 Recovery Grant in support of an economic evaluation to commence from mid-2021. The updated evaluation plan outlines inputs, activities, and outputs as well as immediate, short term and medium term outcomes for both grants.

The evaluation will consider the extent to which both grants achieved their intended outcomes, and whether the economic benefits exceeded the costs to help inform decisions about the nature and design of any future small business support programs. This will complement, and feed into a broader review of all NSW Government COVID-19 stimulus measures.

Service NSW rapidly developed an approach to administer the grants

Over recent disasters, such as the 2019–20 bushfires and the COVID-19 pandemic, Service NSW has been responsible for administering grant programs on behalf of other government agencies.

Service NSW implemented both grants under its Project Management Framework and under each grant agreement with NSW Treasury as it does not have its own grants administration framework. To address the risks that emerged during delivery, Service NSW developed an approach to standardise and monitor the administration of the grants while they were being implemented.

Service NSW now has an opportunity to establish a grants administration framework, based on the processes, lessons and outcomes captured under the grants administration taskforce and in developing its fraud control framework. Embedding these processes into business as usual for grants administration will enable Service NSW to have a consistent set of expectations for controls, business processes and governance and probity requirements for future grants it implements.

2. Recommendations

By December 2021, NSW Treasury should:

1. finalise and implement an evaluation of the $10,000 Support Grant and $3,000 Recovery Grant, including obtaining direct feedback from businesses on how grant funds achieved the grant objectives.

By December 2021, Service NSW should:

2. develop a grants administration framework, which documents expected controls – including fraud controls – business processes and governance and probity requirements

3. publish information on all grants programs, including grants distribution and uptake.

By December 2021, the Department of Customer Service should:

4. ensure its process for managing conflicts of interest meets policy requirements by:

  • ensuring employees promptly declare any real, potential or perceived conflicts of interest
  • annually producing a list of conflicts of interest for records retention purposes
  • requiring a separate register of conflicts of interest declarations where a grant program is deemed as high risk.

3. Lessons for grants administered within urgent timeframes

The two grants this audit examined were administered within a context of urgent timeframes, and increased complexity and uncertainty about the impact of the COVID-19 pandemic. The following lessons are shared to assist sponsor and delivery agencies in administering future grants where rapid implementation is required.

Sponsor agencies should consider the following lessons:

1. develop an approach to define and measure benefits for rapidly developed programs and projects where a full business case and cost-benefit analysis is not feasible

2. establish common processes and expectations for co-administered grants:

  • periodically assure agencies' capability to deliver grants programs
  • agree and establish risk appetite statements with administering agencies
  • clearly establish expected performance levels and targets under any agreement

3. review the processes and outcomes of rapidly developed programs, capture lessons learned, and apply these in planning and delivering future programs.

Delivery agencies should consider the following lessons:

1. risk management and risk appetite:

  • perform robust assessment procedures to ensure risks associated with delivery of the project are identified
  • ensure the controls implemented adequately address identified risks
  • agree and document the acceptable risk appetite at the outset
  • review risk management processes after the grants are issued when unable to finalise risk management processes ahead of launch

2. grant agreements between NSW public sector agencies:

  • ensure agreements are finalised in a timely manner
  • ensure agreements clearly outline:
    • roles and responsibilities of both parties,
    • changes in scope of services provided
    • fees and charges applicable

3. frameworks for grants administration:

  • ensure that there is a common set of expectations in place to guide grants administration including standard controls and processes for managing risk, capturing lessons learned and reporting on outcomes.

Appendix one – Response from agencies

Appendix two – Summary of other COVID‑19 Stimulus and Support for small businesses in NSW in April 2020

Appendix three – Public Health Orders

Appendix four – Highly impacted industries

Appendix five – About the audit

Appendix six – Performance auditing

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #352 - released (24 June 2021).

 

Published

Actions for WestConnex: changes since 2014

WestConnex: changes since 2014

Transport
Compliance
Infrastructure
Internal controls and governance
Management and administration
Project management
Risk

What the report is about

The report examined whether Transport for NSW (TfNSW) and Infrastructure NSW (INSW) effectively assessed and justified major scope changes to the WestConnex project since 2014.

What we found

NSW Government decisions to fund WestConnex-related projects outside WestConnex's $16.812 billion budget have reduced transparency and understate the full cost of WestConnex.

The NSW Government's decision to separate Sydney Gateway from WestConnex has reduced transparency over the cost of the road component of Sydney Gateway. $1.76 billion of the cost to complete Sydney Gateway is funded outside the WestConnex budget.

Network integration costs, currently estimated at $2.3 billion, are also funded outside the WestConnex budget. Many of these costs are directly attributable to WestConnex and ought to be included in the reported budget.

The Parramatta Road Urban Amenity Improvement Program, costing $198 million, should also be included as part of the WestConnex reported budget.

Decisions to exclude or remove these elements from WestConnex without justification have seen $4.26 billion of projects funded outside the $16.8 billion budget.

Positively, robust analysis was used to develop and incorporate design improvements into the 2015 WestConnex Updated Strategic Business Case.

The separate components of WestConnex underwent all required assurance reviews. However, the NSW Government's assurance framework does not require ongoing ‘whole-of-program’ assurance for large and complex projects like WestConnex. The absence of a holistic review of WestConnex allows for some costs and benefits to avoid scrutiny.

What we recommended

TfNSW should:

  • review the impact of scope changes on project objectives, costs and benefits for complex infrastructure projects
  • ensure that estimated costs and benefits of works which are reasonably required to meet consent conditions are included in business cases for complex large infrastructure projects
  • establish centralised and project specific record keeping for major infrastructure projects.

Infrastructure NSW should provide transparent whole of program assurance on total costs and benefits when complex projects are split into sub-projects.

Government should consider enhancing public transparency of existing infrastructure assurance processes by requiring that large complex infrastructure programs undergo periodic review at a whole-of-program level.

Fast facts

  • $16.812b 2015 WestConnex business case budget
  • $2.3b current estimated cost of network integration works to enable WestConnex, funded outside the WestConnex budget
  • $1.76b cost to complete Sydney Gateway to enable WestConnex and also funded outside the WestConnex budget
  • $198m Parramatta Road Urban Amenity Improvement Program, originally part of WestConnex but now funded outside the WestConnex budget

WestConnex

WestConnex is a 33 km motorway network that will link the western and south‑western suburbs with the Sydney CBD and the Airport and Port Botany precinct. It will also connect with proposed future motorway links to the north shore, northern beaches, and southern Sydney. The project is being delivered in three stages, with completion scheduled for 2023.

When first conceived by Infrastructure NSW (INSW) in 2012, WestConnex was described as a single integrated concept. In August 2013, government approved a business case for an integrated concept of WestConnex, with an estimated cost of $14.881 billion (in nominal outturn costs). Transport for NSW (TfNSW) is the government agency (sponsor agency) accountable for the delivery of WestConnex in accordance with the business case. In August 2014, the NSW Government established the Sydney Motorway Corporation to fund, deliver and operate WestConnex.

In November 2015, the NSW Government publicly released an updated WestConnex business case with greater detail and design enhancements, which increased the estimated cost to $16.812 billion.

Subsequent to this update, further changes were made to the design, including realignment of the M4 to M5 Link connection to the Western Harbour Tunnel project, an expanded interchange at Rozelle, the deletion of the Camperdown Intersection, and the addition of the Iron Cove Link. The reported budget for WestConnex was not changed as a result of these design updates.

To fund WestConnex, Sydney Motorway Corporation consolidated a concessional loan of $2 billion from the Australian Government, private sector debt and equity funding from the State. The Australian Government also provided a $1.5 billion contribution to the State to partially fund construction of WestConnex.

In August 2018, the NSW Government sold 51 per cent of its stake in Sydney Motorway Corporation for $9.26 billion. At the time of writing, the NSW Government is in the process of selling its remaining 49 per cent stake of Sydney Motorway Corporation.

About this audit

In the course of delivering a complex major infrastructure project, it is reasonable to expect changes to the original design and scope. Changes may occur as the design moves from a high‑level concept to a detailed design for project delivery, as new risks or issues are identified, as demands change, or as other interdependent projects are approved. Changes can also occur in response to potential cost or delivery overruns which arise as a result of planning deficiencies. Where design and scope changes significantly change the project costs and/or expected benefits, the justification for these changes should be robust and transparent.

Following our 2014 performance audit, 'WestConnex: Assurance to the government', the NSW Government established the Infrastructure Investor Assurance Framework (IIAF) to improve accountability and transparency over major projects that are developed, procured, or delivered by government agencies. Under the framework, TfNSW, as project sponsor, is responsible for ensuring the WestConnex project meets all IIAF requirements. These include ensuring the project remains strategically aligned and viable, and benefits are on track. INSW is responsible for coordinating the assurance review process and reporting directly to NSW Cabinet on project delivery against time, budget and risks to project delivery.

The objective of this performance audit is to assess whether TfNSW and INSW effectively assessed and justified major scope changes to the WestConnex project since 2014.

 

Conclusion

Government decisions to separate WestConnex related projects and deliver them outside WestConnex's 2015 business case budget of $16.812 billion has understated the total cost of WestConnex achieving its objectives. The rationale for separating these elements from the WestConnex project scope has not been transparent. Together, these projects represent costs of $4.26 billion funded outside the $16.812 billion WestConnex budget.

Since 2015, the NSW Government has removed several projects from the scope described in the 2015 WestConnex business case, and funded them separately:
  • In mid‑2017, the Sydney Gateway became a separate project outside WestConnex. This project, estimated in 2015 to cost $800 million, now has an estimated cost of $2.56 billion. The project remains partly funded by an $800 million contribution from the $16.812 billion WestConnex budget, with $1.76 billion funded outside the WestConnex budget.
  • In late 2018, the Parramatta Road Urban Amenity Improvement Program became a separate project outside the 2015 WestConnex budget. This project was part of the 2015 WestConnex Business Case and is intended to create urban renewal opportunities around Paramatta Road. It is estimated to cost $198 million.

Work required to integrate WestConnex with existing roads ('network integration') was funded outside the $16.812 billion budget for the November 2015 WestConnex business case. TfNSW is obliged to deliver network integration works to meet the conditions of planning approval for WestConnex. As such, these costs should be included in the WestConnex budget. The current estimated cost of these network integration works is $2.3 billion.

The rationale to exclude or remove each of these elements from the WestConnex project scope has not been transparent, nor supported by robust analysis and justification. These elements are required for WestConnex to achieve its objectives. The additional project costs will also deliver additional benefits not included in the 2015 WestConnex business case. Removing them understates the total cost of achieving the objectives set out in the 2013 and 2015 WestConnex business cases.

WestConnex's complex financing arrangements further reduce transparency on costs.

Transparency over the total cost of WestConnex – including elements funded from other project budgets – is further limited by the project's complex financing arrangements.

Prior to 2018, the Audit Office provided assurance on costs borne and levied by Sydney Motorway Corporation and its controlled entities. Since the NSW Government sold its majority stake in WestConnex in August 2018, the Auditor‑General no longer has the mandate to provide this assurance. Considering this, and the lack of transparency on the cost of projects removed from the WestConnex project scope, there is no transparent or comprehensive view of the total cost to deliver WestConnex – nor of how these cost would be offset by the sale of the government's remaining stake.

There is no 'whole‑of‑program' assurance over the WestConnex program of works. This limits transparency and confidence that WestConnex will meet intended objectives within its budget.

After INSW conducted a gateway review of a draft of the 2015 WestConnex Business Case under the IIAF, the project was broken up into separate components to support staged delivery. Each of these projects, including the Sydney Gateway, as well as the Network Integration Program, underwent the required assurance reviews under the IIAF. INSW also provided monthly progress updates to government. These individual projects are, in themselves, significant in scale and complexity. Addressing them as discrete components for the purposes of the assurance review process is justified and there is no requirement under the IIAF to holistically review projects which together deliver final benefits of the WestConnex program. However, whole‑of‑program review would improve transparency over total costs and benefits.

In 2016, TfNSW revised the design of the M4‑M5 Link and Rozelle to address traffic and integration issues.

TfNSW identified that the concept designs used for the M4‑M5 Link and Rozelle Interchange in the 2015 WestConnex Business Case would not integrate well with surface roads, including the proposed Bays Precinct, and would result in increased traffic on Victoria Road and the ANZAC Bridge. Following a comprehensive review conducted in mid‑2016, TfNSW refined the design of the M4‑M5 Link and Rozelle Interchange to address these limitations without increasing the cost of delivery. TfNSW documented the rationale for the design changes, including how the changes improved on the original design to increase capacity, improve traffic conditions and create more open space.

1. Key findings

Government decisions to fund WestConnex related projects outside of WestConnex's $16.812 billion reported budget have reduced transparency over costs and understate the full cost of WestConnex

In 2015, the work required to integrate WestConnex with existing roads ('network integration') was funded as a separate project with an estimated cost of $1.534 billion outside the 2015 WestConnex budget of $16.812 billion. TfNSW then created the Network Integration Program to respond to the conditions of planning approval for WestConnex. The current estimated cost to deliver all network integration works is $2.3 billion.

Since the 2015 WestConnex Business Case, the NSW Government has removed several elements from the scope of WestConnex and funded them as separate projects, while keeping the published WestConnex budget at an estimated $16.812 billion. Projects removed include:

  • Sydney Gateway, currently costed at $2.56 billion (with an $800 million contribution from WestConnex)
  • Parramatta Road Urban Amenity Improvement Program, costed at $198 million in late 2018 and funded though new funding to the Greater Sydney Commission.

Together, these projects represent costs of $4.26 billion that are not included in the WestConnex budget, but are required for WestConnex to achieve the objectives of the 2013 and 2015 WestConnex Business Cases. The costs of these elements in supporting the objectives of WestConnex is not tracked centrally, and there is no single point of oversight over them. Exhibit 1 compares total WestConnex forecast costs (including related projects) between November 2015 and April 2021.

 

November 2015
($ million)

April 2021
($ million)
WestConnex
Stage 1
Stage 1A (M4 Widening) 497 517
Stage 1B (M4 East) 3,802 3,782
Total 4,299 4,299
Stage 2
King Georges Road Interchange 131 131
New M5 4,335 4,335
Sydney Gateway Contribution 800 800
Total 5,266 5,266
Stage 3
M4‑M5 Link and Rozelle Interchange 7,049 7,049
Urban renewal (Parramatta Road) 198 ‑‑
Urban renewal (Rozelle) ‑‑ 198
Total 7,247 7,247
Total reportable WestConnex 16,812 16,812

Exhibit 1: WestConnex and related projects forecast costs
  November 2015
($ million)
April 2021
($ million)
Related projects
Network integration 1,534 2,300
Urban renewal (Parramatta Road) ‑‑ 198
Sydney Gateway Road Component ‑‑ 1,760
Total 1,534 4,258

Source: AO research.

Many network integration costs are directly attributable to WestConnex and ought to be included in the reported budget for WestConnex

Prior to 2015, the scope of WestConnex included enabling works needed before or during construction, as well as funding for future works to address any adverse traffic outcomes created by WestConnex which become apparent after its opening. These works are also known as network integration works.

When government approved the 2015 WestConnex Business Case, it noted that the project would require $1.534 billion for network integration works to address the impacts of WestConnex on the road network. However, the WestConnex project budget of $16.812 billion did not include funding for network integration works. Instead, Roads and Maritime Services (RMS, now TfNSW) was to fund network integration through its normal budget allocation.

It is important to recognise these costs as part of the total WestConnex project cost because:

  • TfNSW created the Network Integration Program to respond to network traffic and transport elements of the planning conditions of approval for WestConnex granted by the then NSW Department of Planning and Environment under the Environment, Planning and Assessment Act 1979.
  • NSW Treasury guidelines for business cases note that accurate cost estimates include assessment of the financial impact of meeting the conditions of planning approval.
  • Travel time and vehicle operating cost benefits attributed to the WestConnex project in the 2015 WestConnex Business Case assume that some network integration works, then costed at $373 million, were in place.

Refer to Appendix two for more detail on network integration works.

Some of the projects in the WestConnex Network Integration Program provide community and place benefits, such as parklands and cycleways. These benefits have not been attributed to WestConnex. Additionally, some network integration works are likely to deliver additional traffic related benefits to WestConnex. As the Network Integration Program’s primary purpose is to meet the conditions of planning approval for WestConnex, TfNSW should attribute all the costs and benefits of the program to WestConnex.

To September 2021, the total funded cost of the Network Integration Program is approximately $2.077 billion. TfNSW estimates that it will need a further $222 million to complete all expected network integration works.

The NSW Government's decision to separate Sydney Gateway from WestConnex has reduced transparency and accountability for TfNSW's underestimation of the cost of the road component of Sydney Gateway

Sydney Gateway is a high‑capacity connection between the new St Peters Interchange and the Sydney Airport and Port Botany precinct. It includes a road and rail components. The road component was included in the scope of WestConnex in the 2015 WestConnex Business Case. The November 2015 design, which TfNSW costed at $800 million, involved separate roadways from the St Peters Interchange to the International terminal, and to the domestic terminals and Mascot airport precinct.

By October 2016, TfNSW was aware that the $800 million budget for Sydney Gateway was insufficient and revised the forecast cost for the road component to $1.8 billion. The original cost estimate did not sufficiently consider the cost of:

  • constructing a complex design adjacent to the airport precinct
  • obtaining access to land required for the project
  • managing environmental contamination.

On 9 August 2017, the then Minister for WestConnex announced that the Sydney Gateway project was not part of WestConnex.

The 2015 WestConnex Business Case notes that material changes to the WestConnex budget, funding, scope, or timeframe are subject to Cabinet approval processes. It states that, when seeking approval for material changes, the portfolio Minister will make a submission to the relevant Cabinet Committee. Changes in project scope required the approval of the then Cabinet Committee on Infrastructure and should have been endorsed by the WestConnex Interdepartmental Steering Committee.

TfNSW and the NSW Department of Premier and Cabinet (DPC) assert that there is no documentation to support the government’s decision to separate Sydney Gateway from the WestConnex Program, or the WestConnex Interdepartmental Steering Committee's endorsement of a submission to Cabinet seeking approval for the separation.

The established governance processes for major scope changes were not followed in this instance. The lack of transparency regarding government's decision to separate Sydney Gateway from WestConnex also reduces visibility of TfNSW's underestimation of the cost of delivering the road component of Sydney Gateway.

The November 2018 Final Business Case for Sydney Gateway, which was approved by the government, included an estimate of $2.45 billion (nominal outturn cost) for the road component. This estimate included an $800 million contribution from WestConnex. A more recent estimate (late 2020) for this project is $2.56 billion (nominal outturn cost).

The Parramatta Road Urban Amenity Improvement Program should be included as part of the WestConnex budget

A specific objective of the 2015 WestConnex Business Case was the creation of opportunities for urban renewal along and around Parramatta Road. The business case included an allocation of $198 million in the $16.812 billion WestConnex budget for the Parramatta Road Urban Amenity Improvement program, designed to implement aspects of the objective. In November 2018, the NSW Government removed the Parramatta Road Urban Amenity Improvement Program from the WestConnex program of works and reallocated the $198 million (inside the $16.812 billion WestConnex budget) for urban renewal works around the Rozelle Interchange. As part of this decision, government approved new funding of $198 million to the Greater Sydney Commission for the urban amenity program, outside the $16.812 billion WestConnex budget. This understates the cost of WestConnex meeting its objectives by $198 million.

There is no requirement for ongoing ‘whole‑of‑program’ assurance of the WestConnex program of works, including related projects

In August 2015, INSW conducted its first Gateway Review of WestConnex as a program consisting of composite projects. Following that review, TfNSW registered each of the components of WestConnex with INSW as individual projects, rather than keeping WestConnex registered as a program or mega‑project. This is not inconsistent with the IIAF and all WestConnex related projects, including Sydney Gateway and the Network Integration Program, have undergone independent assurance reviews as individual projects under the IIAF.

Once a program like WestConnex is broken down into its composite parts, there is no requirement for the sponsor agency (TfNSW) or INSW to provide independent assurance on the program as a whole until it is completed. This is then done as part of the Gateway review for benefits realisation, which examines whether project benefits are being measured and meet expectations. These individual projects are, in themselves, significant in scale and complexity. While addressing them as discrete components for the purposes of the assurance review process can be justified, the absence of strategic, holistic reviews of WestConnex allows for total costs and benefits to become opaque and avoid scrutiny. Programs of this scale require greater ongoing transparency on total costs and benefits in order to ensure confidence they will meet intended objectives within budget.

There is a lack of public transparency on the total costs and benefits of the WestConnex project

Prior to 2018, the Audit Office provided assurance on costs borne and levied by Sydney Motorway Corporation and its controlled entities. Since the NSW Government sold 51 per cent of its stake in WestConnex in August 2018, the Auditor‑General no longer has the mandate to provide this assurance. The Audit Office is also unable to provide any assurance regarding the performance of tolling concessions.

This means that the total costs of WestConnex, including those levied on road users through tolling, are not reported alongside the full cost of delivering the project. This information, and independent assurance over that information, would provide transparency and context to the outcome of government's sale of its interest in WestConnex.

To enhance the transparency of existing infrastructure assurance processes, government could consider requiring large and complex infrastructure programs to undergo periodic review at a whole‑of‑program level. This could take the form of annual reports to Parliament on the total costs and benefits of selected large and complex projects by the responsible agency. The reports could include an assessment of the cost to government and cost to the community of funding and financing. Independent assurance of the agency report would provide Parliament with greater confidence that infrastructure is delivered economically and providing value for money for the people of NSW.

The Australian National Audit Office provides similar assurance on selected Department of Defence acquisition projects as part of its annual Major Projects Report.

Design enhancements included in the 2015 WestConnex Updated Strategic Business Case were supported by robust analysis

The 2015 WestConnex Business Case contained more detail than the 2013 WestConnex business case. Design enhancements were made as a result of modelling analysis conducted over the two years since the 2013 business case. Enhancements included a full underground link between Kingsgrove and St Peters as part of the New M5 and re‑alignment of the M4‑M5 link tunnel (Stage 3) to include the Rozelle Interchange. The Rozelle Interchange will provide a direct connection to the Anzac Bridge and Victoria Road, and will enable a connection to the proposed Western Harbour Tunnel and Beaches Link. A map and description of these elements can be found at Exhibits 2 and 3 of this report.

In 2016, TfNSW revised the design of the M4‑M5 Link and Rozelle to address traffic and integration issues

As part of preparing the 2015 WestConnex Business Case, TfNSW prepared a Project Definition and Delivery Report (PDDR) for the M4‑M5 Link. This report describes the scope of the project, including a high‑level concept design. TfNSW identified limitations with the proposed design of the M4‑M5 in the PDDR, which it would need to address as the project moved to a detailed design stage. In particular, these limitations included:

  • poor integration with the Bays Precinct masterplan
  • traffic capacity constraints on Victoria Road and Anzac Bridge
  • construction complexity.

Following a comprehensive review in mid‑2016, TfNSW changed the design of the M4‑M5 Link and Rozelle Interchange to address these limitations. These changes included:

  • deletion of the Camperdown intersection to improve traffic conditions on Parramatta Road
  • a fully underground and larger Rozelle Interchange with 10‑hectare dedicated parklands
  • a toll‑free tunnel link from Iron Cove Bridge to Anzac Bridge
  • increasing the lanes in the dual tunnels from three to four each way.

TfNSW documented, but did not publish, the rationale for the design changes, including how the changes addressed the limitations of the previous design while providing increased community benefit through the creation of open space. TfNSW undertook cost comparison studies which estimated that these changes would have a neutral impact on the estimated project cost while achieving the same or improved benefits.

TfNSW's record‑keeping systems for large infrastructure investments negatively impact accountability and transparency

In response to our formal requests for relevant information, made during the conduct of this audit, TfNSW advised that complete and valid records of key decision‑making processes, analysis and advice were unavailable. Additionally, TfNSW often provided information that was incomplete or unverifiable (for instance, unsigned briefing notes). This is not consistent with accepted governance practices and does not comply with the requirements of the State Records Act 1998.

We also requested that TfNSW provide a list of relevant documents held by the Sydney Motorway Corporation (SMC). While TfNSW acknowledged that SMC may hold material relevant to the audit, TfNSW did not have a list or description of these documents. As SMC is now a majority privately held entity, both the Audit Office and TfNSW have limited power to require SMC to provide documentation.

The delivery timeframe for large and complex infrastructure projects such as WestConnex frequently exceeds five years, and some projects can take over a decade to deliver. These projects represent a significant investment of public resources and government agencies should expect independent review and assurance activities such as performance audits. The establishment of dedicated record keeping facilities for major infrastructure projects, such as data rooms, would improve transparency and accountability. This would ensure that the use of public resources is fully auditable in line with public expectations and the requirements of the Government Sector Finance Act 2018, the State Records Act 1998 and the Public Finance and Audit Act 1983.

2. Recommendations

By December 2021, TfNSW should:

1. review the impact of scope changes on project objectives, costs and benefits for complex infrastructure projects

2. when preparing business cases for complex large infrastructure projects, ensure that the estimated costs and benefits of works which are reasonably expected to meet consent conditions are included in the overall project cost and its benefits (as per Treasury guidelines)

3. establish and maintain centralised and project‑specific record keeping, including through dedicated project data rooms, to ensure major infrastructure projects can readily be subject to external oversight and assurance.

By June 2022, INSW should:

4. provide transparent whole‑of‑program assurance on total costs and benefits throughout the project life‑cycle when complex projects are split into sub‑projects.

By June 2022, NSW Government should:

5. consider enhancing the public transparency of existing infrastructure assurance processes by requiring that large complex infrastructure programs undergo periodic review at a whole‑of‑program level. This could take the form of reports to Parliament on the total costs and benefits on selected large and complex projects by the responsible agency, including cost to government and cost to community of funding and financing, as well as an accompanying independent assessment of the agency report.

Following our 2014 performance audit report 'WestConnex: Assurance to the government', the NSW Government established the Infrastructure Investor Assurance Framework (IIAF). INSW is responsible for the development, implementation and administration of the IIAF. The assurance framework involves gateway reviews, health checks, deep dive reviews, and project monitoring and reporting at various stages in the lifecycle of a project. The main aims of the IIAF are to help ensure major infrastructure projects are delivered on time and on budget, and to ensure that reports are regularly monitored by the Cabinet of the NSW Government. The IIAF gateway review process is compulsory for all significant investments and expenditure under the NSW Treasury Gateway Policy.

In accordance with the IIAF, INSW is responsible for the following:

  • providing a dedicated Assurance Team including Gateway Review Managers to coordinate Reviews
  • determining appropriate expert reviewers, and manages scheduling, commissioning and administration of Assurance Review reports. Infrastructure NSW is independent of the Expert Review Team
  • monitoring Tier 1 – High Profile/High Risk projects, Tier 2 and Tier 3 (if required) project performance through independent Assurance Reviews
  • providing independent analysis and advice on key risks and any corrective actions recommended for Tier 1 – High Profile/High Risk, Tier 2 and Tier 3 projects
  • escalating projects to Infrastructure Investor Assurance Committee (IIAC) and Cabinet where projects present ‘red flag issues’ and where corrective action is needed
  • working with delivery agencies to register all capital projects with an estimated cost greater than $10.0 million and ensures they are risk profiled and assigned a risk‑based project tier with an endorsed IIAF Project Registration report
  • preparing forward looking annual Cluster Assurance Plans
  • maintaining and continuously improves the IIAF process
  • reporting to the IIAC, Cabinet and Infrastructure NSW Board
  • regularly report to NSW Treasury on the performance of the IIAF.

In relation to WestConnex, TfNSW is the sponsor agency responsible for meeting relevant IIAF requirements, including:

  • registering and risk profiling projects
  • IIAF gateway, health check, and deep dive assurance reviews
  • regular reporting.

Under the IIAF, it is mandatory for all capital projects valued over $10.0 million to be registered with INSW. Capital projects can be registered either as a program (comprising of a group of related projects or activities) or as a project (which may or may not be part of a program).

According to the IIAF, programs tend to have a lifespan of several years and aim to deliver outcomes and benefits related to an organisation's strategic objectives. Projects tend to have a shorter lifespan, and deal with outputs. Projects can, however, be grouped under a single program if they are similar in nature or if they are aimed at collectively achieving a strategic objective. Complex projects can be delivered in multiple stages, under different contracts, and across different time periods.

The last assurance review of the entire WestConnex program of works as a whole was in 2015

INSW conducted the first IIAF gateway review of WestConnex in August 2015. TfNSW developed a draft WestConnex Updated Strategic Business Case to consolidate the latest analysis on WestConnex, and to confirm that the project remained fit for purpose, economically viable, and financially deliverable. The review followed a recommendation in our 2014 performance audit report that business cases be thoroughly revisited.

During September 2015, INSW conducted additional informal reviews to identify strategic risks associated with public release of the WestConnex business case. Subsequently, INSW gave the Premier of NSW its views on the draft business case, including the following points:

  • The $398 million budget for Sydney Gateway was insufficient to meet the benefits claimed in the business case for a ‘functional’ connection to Sydney Airport and Port Botany. INSW studies indicate a future‑proof solution would require a minimum spend of $755 million.
  • Enabling works for WestConnex estimated at $1.534 billion were excluded from the cost of WestConnex. Significant work remained for RMS to identify mitigation measures to address planning approvals and network performance issues.
  • Enabling works (a Southern Connector), an access ramp and surface road improvements within St Peters were excluded from the draft 2015 business case despite their inclusion in the WestConnex scope in the 2014–15 State Budget.
  • The overall cost of works not funded within the WestConnex budget ranged from $2.011 billion to $2.196 billion. This included the enabling works, access ramp and surface road improvements and the shortfall for Sydney Gateway.

All WestConnex related projects, including Sydney Gateway have undergone independent assurance reviews under the IIAF

Since INSW submitted the first WestConnex progress update report to Cabinet in June 2015, INSW has been reporting monthly on the different stages of the WestConnex Program, including Sydney Gateway, as the projects were registered with INSW as High‑Profile, High‑Risk projects. Separate reporting enabled INSW to report and review each stage with more detailed scrutiny, compared to the reporting and reviewing at a program level.

WestConnex Stage 2 (New M5) underwent both mandatory and non‑mandatory reviews at key points in the project lifecycle. Three mandatory gateway reviews – at Gate 2 (Final business case), Gate 3 (Readiness for market), and Gate 4 (Tender evaluation) – were conducted by TfNSW before the introduction of IIAF. Four non‑mandatory health check reviews and one non‑mandatory deep dive review were conducted after the introduction of the IIAF managed by INSW.

Similarly, WestConnex Stage 3 projects – M4‑M5 link, M4‑M5 Tunnels, and Rozelle Interchange – also underwent mandatory and non‑mandatory reviews at key points in their lifecycle under IIAF.

The M4‑M5 Link had two mandatory gateway reviews and one non‑mandatory health check review under IIAF. These reviews were conducted before Stage 3 was split into two stages, due to major design changes to the Rozelle Interchange and the M4‑M5 tunnels.

The M4‑M5 tunnels had two mandatory gateway reviews (at Gates 3 and 4), one non‑mandatory health check review, and one non‑mandatory deep dive review under IIAF.

Rozelle Interchange also underwent three mandatory gateway reviews at Gate 3 (part 1), Gate 3 (part 2), and Gate 4, two non‑mandatory health check reviews, and one non‑mandatory deep dive review under IIAF.

Since mid‑2017, the Sydney Gateway project has undergone required independent assurance reviews, as well as a number of optional assurance reviews

In November 2016, INSW conducted a mandatory Gate 1 gateway review on a strategic business case for the Sydney Gateway Project. TfNSW did not proceed with this business case. Following the separation of Sydney Gateway from WestConnex in mid‑2017, TfNSW developed a new business case for Sydney Gateway. It has undergone the required Gate 1, Gate 2, and Gate 3 gateway reviews, as well as two non‑mandatory health check reviews, and three non‑mandatory deep dive reviews under IIAF.

Network integration works have undergone all IIAF required assurance reviews

TfNSW completed a strategic business case for the Network Integration Program in August 2020, and INSW completed a gateway review in November 2020. This is despite network integration projects starting as early as 2015, with $645 million having been spent by June 2020. The strategic business case included a prioritisation process for completing remaining works in the program. Prior to November 2020, TfNSW registered individual network integration projects with INSW, and these projects have undergone gateway reviews where required.

The Network Integration Program strategic business case does not include Rozelle interchange network integration works ($353 million) and additional network integration works to settle a contractor claim adjacent to St Peters Interchange ($190 million). These were excluded from the business case on the basis they had already been approved by government, and as such were not subject to the prioritisation elements of the business case. TfNSW has not developed separate business cases for these works, although the scope of the St Peters Interchange works was developed through a negotiated process.

TfNSW did not prepare business cases for some network integration works which have commenced, including the $323 million Campbell Road/Euston Road works

Prior to its development of the August 2020 strategic business case, TfNSW did not prepare business cases for many network integration works that have commenced, and in some instances were completed, before 2019. Significantly, TfNSW did not prepare a business case for the Campbell Road/Euston Road works, which cost $323 million and have been completed.

In 2016, TfNSW’s Business Case Policy requires the creation of business cases for capital projects costing over $1.0 million. At the time of writing this report, TfNSW’s draft policy requires full business cases for capital projects costing $10.0 million or more.

There is no requirement for ongoing ‘whole‑of‑program’ assurance of the WestConnex program of works, including related projects

INSW conducted its first gateway review of WestConnex (as a program, which consisted of composite projects) in August 2015. Following that review, TfNSW registered each of the components of WestConnex with INSW as individual projects, rather than keeping WestConnex registered as a program or complex project. The IIAF allows this to occur.

Separate registration enabled INSW to report and review each stage with more scrutiny compared to whole‑of‑program level review.

Such an approach has merit, considering the individual stages (and components of these stages) are multi‑million dollar works in their own right. Each project has its own timing for gateway reviews at stages such as 'Readiness for Market' and 'Tender Evaluation'.

Once a program such as WestConnex is broken down into its composite parts, there is no requirement for the sponsor agency (TfNSW) or INSW to conduct independent assurance on the program of works as a whole until the whole program is completed as part of the Benefits Realisation (Gate 6) gateway review. The absence of strategic, holistic reviews of projects of the scale and complexity such as WestConnex during their delivery allows for total costs and benefits to become opaque and avoid scrutiny. Projects of this scale require greater ongoing transparency on total costs and benefits in order to ensure confidence they will meet intended objectives within budget.

INSW has advised us that it has prepared a proposal to expand its assurance function to include whole‑of‑program review of inter‑related infrastructure projects.

Appendix one – Responses from agencies

Appendix two – Network integration works

Appendix three – About the audit

Appendix four – Performance auditing

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #351 - released (17 June 2021).

Published

Actions for Acquisition of 4–6 Grand Avenue, Camellia

Acquisition of 4–6 Grand Avenue, Camellia

Transport
Asset valuation
Compliance
Fraud
Infrastructure
Internal controls and governance
Management and administration
Procurement
Risk

The Auditor-General for New South Wales, Margaret Crawford, has today released a report on Transport for NSW’s (TfNSW) acquisition of 4–6 Grand Avenue in Camellia.

This audit, which was requested on 17 November 2020 by the Hon. Andrew Constance MP, the Minister for Transport and Roads, examined:

  • whether TfNSW conducted an effective process to purchase 4–6 Grand Avenue, Camellia
  • whether TfNSW has effective processes and procedures to identify and acquire property required to deliver the NSW Government’s major infrastructure projects.

The audit found that TfNSW conducted an ineffective process when it purchased 4–6 Grand Avenue, Camellia. The audit also found that TfNSW’s internal policies and procedures to guide the transaction were, and continue to be, insufficient.

The Auditor-General has made seven recommendations to address the issues identified in the report.

On 17 November 2020, the Hon. Andrew Constance MP, the Minister for Transport and Roads, requested this audit under section 27B(3)(c) of the Public Finance and Audit Act 1983.

On 15 June 2016, Transport for New South Wales (TfNSW) acquired 6.3 hectares of land at 4–6 Grand Avenue, Camellia, by agreement from Grand 4 Investments Pty Ltd. Grand 4 Investments was a business entity established by the owners of Billbergia Pty Ltd, a property development and investment company.

TfNSW paid Grand 4 Investments $53.5 million and assumed liability for addressing environmental issues and contamination associated with the site. This took place seven months after the vendor acquired the land as part of a competitive Expression of Interest process, in which TfNSW also participated, for $38.15 million.

TfNSW is the NSW Government agency responsible for most major transport infrastructure projects in New South Wales. TfNSW acquired the Camellia site for use as a stabling and maintenance depot to support the Parramatta Light Rail (PLR) project.

Consistent with the minister’s request, this audit assessed:

  • whether TfNSW conducted an effective process to purchase 4–6 Grand Avenue, Camellia
  • whether TfNSW has effective processes and procedures to identify and acquire property required to deliver the NSW Government’s major infrastructure projects.

In considering the effectiveness of the processes for this purchase, the audit considered:

  • the requirements of the Land Acquisition (Just Terms Compensation) Act 1991 (the Act)
  • the application of sound processes to manage risk to the NSW Government and to achieve value for money
  • the application of disciplines associated with complex procurement, such as probity, in a NSW Government context.
The acquisition of the 4–6 Grand Avenue site in Camellia was consistent with a 2014 feasibility study for the PLR, but occurred before the completion of detailed project planning or an acquisition strategy.

TfNSW made two attempts to acquire the 4–6 Grand Avenue site in Camellia, and was successful on the second attempt. TfNSW recognised the risks associated with early acquisition and had high-level strategies in place should the site not be required.

The specific site had been identified in a feasibility study for the PLR commissioned by TfNSW in 2014 as one of several options in Camellia for a stabling and maintenance depot. However, TfNSW had not done any substantive analysis of the various options to identify a preferred location before the two opportunities to acquire 4–6 Grand Avenue were brought to TfNSW’s attention by the landowners (or their agents). On both occasions, TfNSW chose to actively pursue acquisition in advance of any such analysis.

The acquisition was also not informed by a Property Acquisition Strategy, which TfNSW policy recommends in order to guide the process and manage acquisition specific risks.

In 2015, TfNSW identified that it would require a stabling and maintenance depot in the Camellia area for the Parramatta Light Rail

In 2014, TfNSW commissioned an external engineering consultancy to undertake a feasibility design study for the Parramatta Light Rail - the Parramatta Transport Corridor Strategy Feasibility Design study (herein referred to as ‘the feasibility study’). In early 2015, TfNSW received the feasibility study, which was one of several key sources that informed the development of business cases for the PLR.

The feasibility study recommended that TfNSW should consolidate the maintenance and cleaning operations with overnight stabling facilities on one site. The study noted that the optimal location for any such site would be in close proximity to the proposed network, and noted that the site must have access to road connections to accommodate access for cars and trucks.

The study found that a centrally located stabling and maintenance facility would be required for all routes serving the Parramatta CBD, and that the Camellia industrial area was a preferred location for such a facility. The study noted that the Camellia area was contaminated.

The feasibility study notes that its conclusions were based on assumptions about the light rail system adopted and decisions made by the future operator of the system, who had not yet been selected or appointed.

TfNSW's decision to progress a potential acquisition in 2015 considered the risk that the site may not be required

TfNSW's FIC was responsible for making decisions on funding allocations at a whole of program level within TfNSW. FIC was also responsible for approving ‘high-risk/high-value’ variations to program budgets. Members of the FIC included:

  • Secretary of Transport for NSW
  • Deputy Secretary, Infrastructure and Services
  • Deputy Secretary, Freight, Strategy and Planning
  • Deputy Secretary, Customer Services
  • Deputy Secretary Finance and Investment
  • Deputy Secretary People and Corporate Services.

An April 2015 submission, from the then Deputy Director-General to the agency’s FIC, sought authorisation and funding approval to participate in an Expression of Interest sale process. It noted the risk that the project may not go ahead. The submission advised that:

By acquiring a strategic site now, it reduces the risk of having to pay an improved value or a value that may be subject to rapidly improving land values due to changes in land use and rezoning.

The property can be acquired for the project, held strategically and income generated by leasing the site as hardstand 1 space until the project requires the land for the Parramatta Light Rail project.

If the project does not proceed in the medium to longer term, the property can be sold at a premium to what has been paid today as property fundamentals improve.

This submission acknowledged the risks associated with environmental contamination and proposed that these risks would be managed by negotiating a contract where the remediation and associated expenses would be at the landowner’s cost. 

TfNSW assessed the 4–6 Grand Avenue site as one of several sites in Camellia that was a feasible location for a stabling and maintenance facility

The Departmental feasibility study assessed six potential sites for a stabling and maintenance facility, including 4–6 Grand Avenue, noting strengths and weaknesses of each site. A different site on Grand Avenue was assessed as the ‘base case’ option (1 Grand Avenue). The study’s comments on the 4–6 Grand Avenue site included the following:

With an area of approximately 63,000m2, this site has sufficient space for a depot with the required stabling yard and maintenance facilities. The location allows for good road access and LRT [light rail transit] access would be from Grand Avenue, which may require a road crossing or signalised intersection. The site has been used for general industrial uses; however the land has been cleared and is currently undergoing remediation 2. The site is not affected by flooding based on one in 100-year flood data.

In early 2015, once the opportunity to acquire 4–6 Grand Avenue emerged, TfNSW commissioned a specific feasibility study of the 4–6 Grand Avenue site. The feasibility studies clearly documented the existence of environmental contamination. In April 2015, the report concluded:

Given the limitations of this report and within the parameters that have been set it is concluded that from a spatial and geographic perspective the site at 6 Grand Avenue would be suitable as a stabling and maintenance depot for the Parramatta light rail project. There are few engineering and environmental constraints that would affect the feasibility level analysis of this site and all issues identified, within this desk study, are considered to be resolvable. However this being said there is a significant amount of work necessary to reach the final layout and definition of the stabling and maintenance depot. There are numerous items which require further consideration and conformation; planning approvals could impose restrictions on building heights, noise mitigation measures, light and visual impact requirements all of which can have significant impacts on the spatial requirements of any stabling and maintenance depot. 

The acquisition of 4–6 Grand Avenue was not informed by a Property Acquisition Strategy

For major projects, TfNSW typically requires the project team to complete a Property Acquisition Strategy, which is intended to guide both process as well as specific acquisition issues expected to be faced during the project. The Property Acquisition Strategy is not a mandated document but is a recommended tool to support property acquisition as part of major projects.

TfNSW did not have a Property Acquisition Strategy in place to guide the 2015 Expression of Interest process. On 6 November 2015, the then Project Director for the PLR project emailed the property team, noting a need to develop a Property Acquisition Strategy to close off the scoping design and preliminary business case.

In January 2016, TfNSW developed a draft Property Acquisition Strategy for the Parramatta Light Rail Project, although it was silent on the potential sites for the stabling and maintenance facility.

TfNSW focussed on 4–6 Grand Avenue because it was available and aligned to TfNSW's strategic interests

In early 2015, officials commenced monitoring the market for industrial real estate in the Camellia area and surrounds for possible sites for a stabling and maintenance facility.

In March 2015, then owner of the site, Akzo Nobel Pty Limited released the 4–6 Grand Avenue site through an Expression of Interest process managed by CBRE.

TfNSW’s then Deputy Director-General, Planning, sought approval from FIC to lodge an Expression of Interest up to $30.0 million. Approval was sought on the basis that it would ‘provide certainty for the Parramatta Light Rail project by allowing for a depot site in a suitable location and potentially avoid higher costs or longer timeframes associated with compulsory acquisition following completion of the project’s business case’. FIC approved the request at its meeting on 9 April 2015.

At this time, TfNSW had not conducted any analysis of financial or operational benefits and costs of the potential sites identified in earlier feasibility studies. TfNSW staff advised us that the decision to participate in the Expression of Interest process for 4–6 Grand Avenue was because it was available. There is no documentation substantiating this statement, which TfNSW staff provided verbally as part of this audit.

In November 2015, TfNSW was advised that it was unsuccessful in the Expression of Interest process and that Grand 4 Investments (a related entity of Billbergia) had purchased 4–6 Grand Avenue. TfNSW did not conduct any further analysis of alternative potential sites in Camellia between this date and commencing discussions with Grand 4 Investments in April 2016. In that time there had been some movement on other properties that were included in the feasibility study, including 37–39a Grand Avenue being under offer in September 2015.

In March 2016, TfNSW approached CBRE to organise a meeting with Grand 4 Investments. On 1 April 2016, TfNSW met with Grand 4 Investments.

TfNSW advises that a perceived benefit of the 4–6 Grand Avenue site was that it was not subject to other uses or leaseholds that would increase the cost of compulsory acquisition. Officers involved in the acquisition advised that other nominated sites in the feasibility study were subject to other uses or leaseholds. 


1  A hardstand space is a large, paved area to store cars, heavy vehicles and machinery.
2  Officers familiar with the acquisition could not confirm the nature of remediation being undertaken, but noted that the previous landowner had cleared buildings from the site, which may have been considered part of remediation.
TfNSW's independent valuation, which it commissioned and received after the acquisition, specifically excluded consideration of environmental contamination risk. As a result, TfNSW is exposed to the risk that the acquisition was not fully compliant with the Land Acquisition (Just Terms Compensation) Act 1991 (the Act) because it did not use an accurate estimate of market value during negotiations. That said, the acquisition of 4–6 Grand Avenue by agreement was consistent with preferred processes described in the Act.

TfNSW acquired the site from the landowner by agreement, and this is consistent with provisions in the Act. Obtaining approval for compulsory acquisition should negotiations for agreement break down is also consistent with the Act. That said, TfNSW did not at any time assess whether a compulsory acquisition could have resulted in acquisition at a lower cost than what was negotiated by agreement.

Despite the high risks associated with the acquisition, TfNSW did not commission a formal valuation in time to inform the negotiation and purchase. Instead, TfNSW relied on internal advice to estimate market value, but did not obtain a formal valuation from those advisors. For high-risk transactions, the greater expertise and arm's-length independence of an external specialist valuer should be preferred over an agency's own staff.

On 15 June 2016, the settlement date for the acquisition, TfNSW commissioned a formal independent valuation of the site. On 23 November 2016, TfNSW received the final formal valuation report. By not obtaining a formal independent valuation of the property in advance of acquisition to inform the acquisition value, TfNSW exposed itself to non-compliance with the Act by not establishing the market value as the basis for the acquisition price. TfNSW also breached its own internal policies.

TfNSW instructed the valuer to conduct its valuation within the following parameters:

  • Market valuation on an ‘as is’ basis – market value based on the methodology described in the Act. This approach valued the site at $25.0 million.
  • Market valuation on a speculative development basis – market value based on the financial value of the vendor's intended use of the site which, in this case, involved leasing the site for industrial use. This approach valued the site at $52.0 million, and TfNSW advised us this valuation supported the purchase price.
  • Disregard the impact of environmental contamination – TfNSW specifically instructed the independent valuer to disregard any known (or unknown) site contamination. As TfNSW knew of the significant environmental contamination affecting the site, this parameter resulted in a valuation that overstated the value of the site as it did not consider the cost of environmental remediation. The valuer applied this assumption for both market valuation approaches.

Additionally, as the independent valuer completed the valuation after the purchase was finalised, there is a risk that the valuation may have been influenced by the known purchase price.

TfNSW's failure to acquire a formal valuation and an assessment of the financial impact of environmental remediation before it purchased 4–6 Grand Avenue represents ineffective administration and governance.
TfNSW acquired the site at a time when there was demand and increasing prices for industrial property in the area. However, TfNSW did not effectively assess and manage the risks associated with the acquisition, and gaps in process led to increased risk. Briefings to decision-makers did not contain important information, and we found no evidence that gaps in advice were queried or explored by decision-makers.

TfNSW did not have plans or advice in place to assist in managing risk, such as:

  • a property acquisition plan
  • a comprehensive and up-to-date risk management plan
  • a negotiation strategy, or any authorisation limit or minimal acceptable position
  • an independent professional evaluation
  • external expert advice (with the exception of legal advice relating to the contract of sale).

TfNSW was aware of contamination issues affecting the land and had access to considerable information about the environmental conditions, such as site environmental audit reports and information on the NSW Environment Protection Authority's contaminated land register. However, TfNSW had not analysed specific technical information about the contamination and therefore was not aware of the risk implications and cost for remediation. Despite this, TfNSW changed its position from not accepting the risks and costs of contamination, to acquiring the site unconditionally. The basis for this decision is unclear and undocumented.

Briefing to senior leaders on the acquisition was silent on a number of important matters that would have been important for approvers to consider, including:

  • an explanation of the 40 per cent increase in purchase price between November 2015 and May 2016, and a 165 per cent increase from TfNSW’s offer in April 2015
  • the contamination risks associated with the site and an evidence-based estimate of potential costs to remediate the site
  • advice that an independent valuation had not been obtained, inconsistent with TfNSW policy.

Consideration of the acquisition by FIC was based on a summary business paper and was managed out-of-session, thereby removing the ability for comprehensive consideration of the acquisition proposal and its risks.

The probity management controls and assurances in place for the acquisition of the 4–6 Grand Avenue site were insufficient. These insufficiencies were exacerbated by the probity risk profile of the transaction.

The 4–6 Grand Avenue acquisition was a high-risk/high-value transaction, undertaken in a volatile property market in a short timeframe under pressure from Grand 4 Investments. TfNSW was engaging in a direct negotiation in advance of detailed planning for the acquisition, or the PLR as a whole. These circumstances contribute to heightened probity risk.

TfNSW did not establish a probity plan and sought no probity support throughout the acquisition. Also, with one exception, the staff involved in the acquisition did not complete conflict of interest declarations.

TfNSW was aware of the potential for probity or integrity issues with the transaction when it commissioned an internal audit in connection with the transaction in 2019. Internal discussions considered whether a misconduct investigation may be more appropriate, however no such investigation was undertaken.

TfNSW's insufficient probity practices, in addition to its failure to keep complete or comprehensive records of negotiations or decisions, reduce transparency of the process and its outcome and expose TfNSW to a greater risk of misconduct, corruption and maladministration.

At the time of the transaction, the TfNSW policy framework was not sufficiently risk-focussed and did not provide clarity on when officers ought to apply specific guidance or procedures. TfNSW's policies and procedures are more focussed on acquiring land to meet project needs and timeframes, and less on assuring value for money and managing risks.

At the time of its acquisition of 4–6 Grand Avenue, TfNSW had property acquisitions policies and procedures in place. Each of these were broadly sound in their content and intent. However, they lacked specificity on how or when to apply guidance, and when risk levels should elevate the importance of recommended guidance.

TfNSW's key guidance was principles based and relied on agency staff using their experience and expertise to apply guidance according to the circumstances of an individual transaction. This guidance was not duly applied in the acquisition of 4–6 Grand Avenue, Camellia. In addition, TfNSW does not have quality or control assurance to identify when TfNSW officers did not apply important policies or processes.

The primary focus of the TfNSW’s property acquisition guidance is to achieve vacant possession of land in a timeframe that meets the need of the relevant transport project. There is less specific focus on the need to meet the requirements of the NSW Government financial management framework.

Appendix one – Response from agency 

Appendix two – About the audit 

Appendix three – Performance auditing

 

Copyright Notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #349 - released (18 May 2021).

Published

Actions for One TAFE NSW modernisation program

One TAFE NSW modernisation program

Education
Finance
Management and administration
Project management
Shared services and collaboration

The Auditor-General for New South Wales, Margaret Crawford, released a report today examining the management of the One TAFE NSW modernisation program.

In 2016, the Government released 'A Vision for TAFE NSW' which stated that TAFE NSW needed to become more flexible, efficient and competitive. It set out the need to progressively reduce significant cost inefficiencies, including by moving away from separate institutes to a single institute model. TAFE NSW established the One TAFE NSW modernisation program to deliver on that vision.

The Auditor General found that the One TAFE NSW modernisation program did not deliver against its key objectives within planned timeframes. The modernisation program originally aimed to realise $250 million in annual savings from 2018–19. Because of project delays and higher than expected transition costs, TAFE NSW did not meet the original savings target. TAFE NSW has made progress on key elements of the program and anticipates that savings will be realised in coming years.

The report makes two recommendations to improve governance arrangements for delivering on commercial objectives and increasing transparency of non commercial activities. 

The report also identifies a series of lessons for future government transformation programs.

TAFE NSW is the public provider of Vocational Education and Training (VET) in New South Wales. In 2018, TAFE NSW enrolled 436,000 students in more than 1,200 courses at around 130 locations across the State.

There have been major policy changes impacting TAFE NSW over the past decade. Under the Smart and Skilled reform, TAFE NSW started to compete with other Registered Training Organisations (RTOs) for a share of the student market.

In 2016, the NSW Government released 'A Vision for TAFE NSW'. The Vision stated that a failure to adapt to market circumstances had left TAFE NSW with unsustainable costs and inefficiencies. To address this, TAFE NSW needed to become more flexible, efficient and competitive. It set out that TAFE NSW must progressively reduce significant cost inefficiencies, including by moving away from a model of separate institutes to a One  TAFE NSW model. The NSW Government set TAFE NSW a target to achieve savings through implementing the Vision.

TAFE NSW established the One TAFE NSW modernisation program to deliver on that vision. The program initially aimed to deliver savings of $250 million per year from 2018–19, but this target was reviewed and updated as the program was being delivered.

This audit assessed whether TAFE NSW effectively managed the One TAFE NSW modernisation program to deliver on the NSW Government's vision for TAFE NSW. In making this assessment, the audit examined whether:

  • delivery of the program was well planned
  • the program was driven by sound governance arrangements
  • TAFE NSW is making progress against the intended outcomes of the program.

The audit focused on the effectiveness of planning, governance and reporting arrangements. It examined five projects within the overall modernisation program as case studies.

Conclusion

The One TAFE NSW modernisation program was an ambitious plan to deliver on the NSW Government’s vision for TAFE NSW, while achieving ongoing savings. Several factors contributed to TAFE NSW not effectively managing the program to deliver on planned timeframes and objectives. These factors include unclear expectations of the primary role of TAFE NSW, unrealistic timeframes, undertaking a large number of complex projects concurrently, governance arrangements that were not fit-for-purpose and poor-quality data.

Planning for the modernisation program and its projects was driven by top-down savings targets and pre-determined timeframes. This led to TAFE NSW attempting to deliver a large number of programs concurrently within tight timeframes. Program management capability was underdeveloped at the commencement of the program and this affected the quality of planning for delivery.

There was a lack of clarity around TAFE NSW's primary purpose. Part of the NSW Government's vision for TAFE NSW was for it to be more commercial, competitive and efficient. These objectives were not fully supported by existing legislation. The commercial objectives of the modernisation program conflicted with legislated social objectives for TAFE NSW. TAFE NSW did not have the autonomy to operate like a government-owned business in a market environment. And while TAFE NSW received separate funding to support students facing disadvantage this did not cover the costs of other non-commercial activities undertaken for social purposes, such as delivering uneconomic courses. The role of the TAFE Commission Board was ambiguous during the initial years of the program, which increased reporting requirements and blurred accountabilities for decision-making.

TAFE NSW's Strategic Plan 2016-22 nominated ten key milestones for delivery by January 2019. TAFE NSW has made progress against several important milestones, including that TAFE ‘is a single TAFE NSW brand’ and has 'industry specific TAFE NSW SkillsPoints'. Other key elements have yet to be delivered, including that TAFE NSW achieves 'integrated enterprise-wide business systems'. Because of delays to projects and higher than expected transition costs, TAFE NSW reported that it did not meet the originally targeted $250 million in annual savings for 2018–19 (which was reviewed and updated as the program was being delivered). 

Appendix one – Response from agency

Appendix two – About the audit

Appendix three – Performance auditing

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #346 - released 17 December 2020