Actions for The Sydney 2000 Olympic and Paralympic Games - Review of estimates

The Sydney 2000 Olympic and Paralympic Games - Review of estimates

Treasury
Financial reporting

The Olympic Coordination Authority (OCA) has made a concerted and commendable effort in preparing the Games Budget within the definition of expenditure for the Games approved by the Government. OCA has also effectively used the definition of cost to control claims made by government agencies against the estimates to host the Games.

However, because the Games Budget was prepared in accordance with that definition, the Games Budget arguably does not capture the overall expenditure associated with the Games, as required by the Olympic Co-Ordination Authority Act. Accordingly, the taxpayers of NSW do not have a complete picture of the costs for hosting the Games.

 

Parliamentary reference - Report number #62 - released 14 January 1999

Published

Actions for Review of Walsh Bay

Review of Walsh Bay

Finance
Infrastructure
Management and administration
Procurement
Project management

The decision to seek development of Walsh Bay without a Master Plan and/or detailed study as to the state of the precinct presented significant problems throughout the life of the project. Now, four years later, negotiations still continue on the details of the final scheme. Based on the latest estimates, it will not provide a financial return as was originally expected. The audit found no evidence to indicate why the former Government wished to expedite Walsh Bay, but it is aware that there was an election due. Many of the problems which have been encountered could have been avoided with more careful and more extensive consideration at the start, particularly in the light of Property Services Group's recommendations.

 

Parliamentary reference - Report number #58 - released 17 December 1998