Actions for Albert 'Tibby' Cotter Walkway
Albert 'Tibby' Cotter Walkway
On 17 September 2015, the Acting Auditor-General of New South Wales, Tony Whitfield, released a report on the Albert ‘Tibby’ Cotter Walkway which crosses over Anzac Parade in Moore Park. The Walkway’s primary function is to cater for event patrons in the precinct. Moore Park is listed on the State Heritage Register and is an open space specifically established to cater for public recreation.
Roads and Maritime Services (RMS) delivered the Walkway to an extremely tight timeframe. It was operational for the 2015 Cricket World Cup at the Sydney Cricket Ground as promised by the government. However, the World Cup deadline added substantially to the total cost of the Walkway, which is projected to be $38 million.
Transport for NSW and RMS could not provide evidence of a compelling economic or financial argument to support the construction of the Walkway or for the tight deadline. Also, the processes they adopted to provide assurance of the project’s value for money were not adequate.
Parliamentary reference - Report number #260 - released 17 September 2015
Actions for Sydney metropolitan bus contracts
Sydney metropolitan bus contracts
On 9 September 2015, the Acting Auditor-General of New South Wales, Tony Whitfield, released a report on Sydney Metropolitan Bus Service Contracts.
All scheduled bus services in the Sydney metropolitan area are provided under contracts with the public and private operators. The contracts allow Transport for NSW (TfNSW) to determine what bus services are provided and to whom. This audit assessed the effectiveness of TfNSW’s design and management of these contracts.
Bus services provided under the Sydney Metropolitan Bus Service Contracts have largely been effective and efficient. Operators are mostly meeting their key performance indicators. Customer satisfaction is better than under the previous contracts and improving, patronage is increasing, and the unit costs of providing services are now lower than under the previous contracts.
However, punctuality remains a problem. Private operators are mostly starting their trips on time, but rarely meeting their mid and end-of-trip targets. State Transit Authority’s (STA) punctuality is improving but is worse than private operators, and other areas of performance are generally below private operators.
The current situation is a substantial improvement over what we found in our 2010 audit on the previous contracts.
Parliamentary reference - Report number #258 - released 9 September 2015
Actions for Large construction projects
Large construction projects
The independent assurance given to the NSW Government and sponsor agencies on the viability of large capital projects throughout their lifecycle is inadequate. Government policy is regularly not followed and not properly communicated to those responsible for implementing such policy.
This audit sought to test the effectiveness of the NSW capital project assurance system - which includes gateway reviews and reporting - but significant levels of non-compliance identified in our case studies prevented this. The NSW Commission of Audit also identified this issue in 2012. Gateway reviews are conducted by independent reviewers at key stages of a project’s life cycle and provide an independent assessment on a project’s readiness to proceed to the next stage.
Parliamentary reference - Report number #252 - released 7 May 2015
Actions for Areas of focus from 2014
Areas of focus from 2014
Actions for Implementing Asset Management Reforms
Implementing Asset Management Reforms
Hospitals, schools, public housing, roads, bridges, buses and trains are just some of the assets used by government in providing services to citizens.
The NSW Government’s asset base is impressive in size - with a value of around $167 billion and with government plans to spend around $8 billion acquiring or replacing assets in the current year. Another $2 billion is spent each year on maintenance.
Good asset management is very important to government; even a small efficiency gain in this area can provide significant returns. Good practice by those responsible for managing assets can improve reliability, extend asset life, save on maintenance costs and aid in identifying and disposing of unnecessary or non-performing assets.
Improving the NSW public sector’s approach to asset management has been on the reform agenda for at least a decade. Changes in practice have been accelerated more recently by integrating asset management policy with the budget process.
In this audit we examined NSW Treasury’s efforts to improve asset management practices in the public sector and the progress made by 3 agencies - the Department of Corrective Services, NSW Fire Brigades and the Powerhouse Museum - towards better managing their asset portfolios.
This report informs Parliament and the community on progress to date and what more needs to be done to ensure that agencies manage assets effectively and achieve best value.
Parliamentary reference - Report number #143 - released 12 October 2005
Actions for In-year Monitoring of the State Budget
In-year Monitoring of the State Budget
The annual Budget is one of the most important and visible statements about a government’s financial intentions.
Once a Budget is released, it is important to monitor variations from the projections it contains. This is done for two reasons -
- first, to ensure that individual agencies are properly managing their budget allocations and that any genuine emerging need for additional funding is met.
- second, to ensure that any changes to the State’s overall financial position are understood and corrective action is undertaken.
This audit dealt primarily with the second of these objectives.
Budget monitoring involves both agencies and Treasury working together to quickly identify factors that might impact the budget, to clearly understand the implications for their budget position and to take any remedial action needed.
Poor monitoring may reduce the confidence that stakeholders have in the government’s financial management. It may mean that government decisions made in- year or for the following budget (for example on tax measures or spending increases/savings) are based on an incorrect understanding of the State’s true financial position.
I hope that this Report provides some useful insights that will assist in better monitoring.
Parliamentary reference - Report number #141 - released 28 July 2005
Actions for Follow-up of Performance Audit: Bus Maintenance and Bus Contracts
Follow-up of Performance Audit: Bus Maintenance and Bus Contracts
Periodically we review the extent to which agencies have implemented the recommendations they accepted from our earlier audits.
This gives Parliament and the public an update on the extent of progress made.
In this follow-up audit, we examine changes following our May 2002 report on how well the:
- State Transit Authority maintained its buses
- Ministry of Transport administered contracts for the provision of regular passenger bus services.
Parliamentary reference - Report number #138 - released 14 June 2005
Actions for Review of Walsh Bay
Review of Walsh Bay
The decision to seek development of Walsh Bay without a Master Plan and/or detailed study as to the state of the precinct presented significant problems throughout the life of the project. Now, four years later, negotiations still continue on the details of the final scheme. Based on the latest estimates, it will not provide a financial return as was originally expected. The audit found no evidence to indicate why the former Government wished to expedite Walsh Bay, but it is aware that there was an election due. Many of the problems which have been encountered could have been avoided with more careful and more extensive consideration at the start, particularly in the light of Property Services Group's recommendations.
Parliamentary reference - Report number #58 - released 17 December 1998