Actions for WestConnex: Assurance to the Government
WestConnex: Assurance to the Government
This audit assesses the assurance provided to the NSW Government for the initial stages of the WestConnex project.
The audit examined the WestConnex project from concept development to the pre-tender phase for Stage 1A – M4 (Parramatta to Homebush Bay). It did not examine the merit of the project or whether it represented value-for-money.
This audit found a number of shortcomings with the governance of the WestConnex project during its early stages and makes recommendations on how to better govern the remainder of the project to minimise the risk of failure.
Parliamentary reference - Report number #247 - released 18 December 2014
Actions for Volume Fourteen 2014 Focusing on Trade and Investment
Volume Fourteen 2014 Focusing on Trade and Investment
There are 63 agencies in the DTIRIS cluster. These agencies include nine electricity and eight water agencies that were reported in the NSW Auditor-General’s report to Parliament Volume Five 2014 on 11 November 2014. Commentary in this volume is on the remaining 46 DTIRIS cluster agencies. The findings found the quality of financial statements in the trade and investment cluster needs to improve.
Actions for Volume Ten 2014 Focusing on Treasury and Finance (including Superannuation and Insurance)
Volume Ten 2014 Focusing on Treasury and Finance (including Superannuation and Insurance)
The quality of financial reporting in the Finance and Treasury cluster continues to improve with fewer reported misstatements over the last three years. The financial statements of all cluster agencies received unqualified audit opinions, except for the New South Wales Self Insurance Corporation.
Actions for Volume Seven 2014 Focusing on Transport
Volume Seven 2014 Focusing on Transport
All agencies in transport cluster received unqualified audit opinions for the year ended 30 June 2014. The quality of financial reporting continues to improve with the number of misstatements identified during audits falling for the fifth year in a row.
Actions for Volume Four 2014 focusing on New South Wales State Finances
Volume Four 2014 focusing on New South Wales State Finances
For the second consecutive year, the General Government and Total State Sector Accounts received an unqualified auditor’s opinion following more than a decade of qualifications. The quality and timeliness of financial reporting across the NSW public sector has continued to improve. Compared to previous years, there were fewer errors in agencies’ 2013–14 financial statements submitted for audit and used for whole-of-government financial reporting.
Actions for Volume One 2014 - Areas of focus from 2013
Volume One 2014 - Areas of focus from 2013
Today the Auditor-General of New South Wales, Grant Hehir, released his Volume One Report to Parliament for 2014. The observations included in this report are designed to inform readers of common findings from the 2013 financial and performance audits so agencies and audit committees can use them to identify issues that may be relevant to their organisations.
Actions for Planning for road maintenance
Planning for road maintenance
The Audit Office is of the opinion that the RTA is taking positive steps in planning for road maintenance and in many instances follows better practice. There are, however, some important improvements which need to be implemented in order to enhance the efficiency and effectiveness of that function.
Parliamentary reference - Report number #69 - released 1 December 1999
Actions for Review of Walsh Bay
Review of Walsh Bay
The decision to seek development of Walsh Bay without a Master Plan and/or detailed study as to the state of the precinct presented significant problems throughout the life of the project. Now, four years later, negotiations still continue on the details of the final scheme. Based on the latest estimates, it will not provide a financial return as was originally expected. The audit found no evidence to indicate why the former Government wished to expedite Walsh Bay, but it is aware that there was an election due. Many of the problems which have been encountered could have been avoided with more careful and more extensive consideration at the start, particularly in the light of Property Services Group's recommendations.
Parliamentary reference - Report number #58 - released 17 December 1998